Project Type: Restaurant Application: Polishable concrete overlay with integral color Location: Los Angeles, CA Project Dates: May 15-20, 2015 Project Size: 4,500 sq. ft. Project Owner: Bromberg Bros. Blue Ribbon Restaurants Contractor: Sanders & Wohrman Products: Rapid Set ® Cement All ® , SET Control ® , TRU ® Self-Leveling, TXP Fast Epoxy Primer Blue Ribbon Sushi Bar & Grill at the Grove Shopping Center in Los Angeles is the restaurant chain’s first California location. Build-out for the restaurant called for integrally colored concrete flooring. The contractor first patched the substrate with Cement All ® before performing surface prep. To prevent pinholes and create a strong adhesive grip for the topping, the crew applied TXP Fast Epoxy Primer by squeegee and back-rolled to achieve a uniform thickness of 12 mils. Next, the crew mixed TRU ® Self-Leveling via Hippo mixers and added a custom integral color. Although work was performed indoors, the average temperature throughout the project hovered around 80 degrees Fahrenheit. To ensure the material would not set too fast in the heat, the contractor also added SET Control ® to the mix. The additive slows down the hardening of cement, giving crews more time to place and finish the mortar. They placed the TRU topping at 3/8-inch thick and finished with a spiked roller to release any trapped air and provide a smooth, level surface. Polishing began the next day, with the crew using a proprietary concrete floor polishing system and a 27-inch high-speed burnisher. PROJECT BRIEF BLUE RIBBON SUSHI BAR & GRILL AT THE GROVE © 2020 CTS Cement Manufacturing Corp. AR_144_EN_043020E CTS Cement Manufacturing Corp. | 12442 Knott St. Garden Grove, CA 92841 | 800-929-3030 | Fax: 714-379-8270 | www.CTScement.com | [email protected]

Transcript of PROJECT BRIEF · 2020-06-16 · Project Type: Restaurant Application: Polishable concrete overlay...

Page 1: PROJECT BRIEF · 2020-06-16 · Project Type: Restaurant Application: Polishable concrete overlay with integral color Location: Los Angeles, CA Project Dates: May 15-20, 2015 Project

Project Type: Restaurant

Application: Polishable concrete overlay with integral color

Location: Los Angeles, CA

Project Dates: May 15-20, 2015

Project Size: 4,500 sq. ft.

Project Owner: Bromberg Bros. Blue Ribbon Restaurants

Contractor: Sanders & Wohrman

Products: Rapid Set® Cement All®, SET Control®, TRU® Self-Leveling, TXP™ Fast Epoxy Primer

Blue Ribbon Sushi Bar & Grill at the Grove Shopping Center in Los Angeles is the restaurant chain’s first California location. Build-out for the restaurant called for integrally colored concrete flooring.

The contractor first patched the substrate with Cement All® before performing surface prep. To prevent pinholes and create a strong adhesive grip for the topping, the crew applied TXP™ Fast Epoxy Primer by squeegee and back-rolled to achieve a uniform thickness of 12 mils. Next, the crew mixed TRU® Self-Leveling via Hippo mixers and added a custom integral color.

Although work was performed indoors, the average temperature throughout the project hovered around 80 degrees Fahrenheit. To ensure the material would not set too fast in the heat, the contractor also added SET Control® to the mix. The additive slows down the hardening of cement, giving crews more time to place and finish the mortar.

They placed the TRU topping at 3/8-inch thick and finished with a spiked roller to release any trapped air and provide a smooth, level surface. Polishing began the next day, with the crew using a proprietary concrete floor polishing system and a 27-inch high-speed burnisher.

PRO

JECT

BRI

EF

BLUE RIBBON SUSHI BAR & GRILL AT THE GROVE

© 2

020

CTS

Cem

ent M

anuf

actu

ring

Corp

. AR_

144_

EN_0

4302

0E

CTS Cement Manufacturing Corp. | 12442 Knott St. Garden Grove, CA 92841 | 800-929-3030 | Fax: 714-379-8270 | www.CTScement.com | [email protected]