Project B1.- Practical Intervention Techniques to Reduce ... Documents...Contract N 2013/313-757 For...
Transcript of Project B1.- Practical Intervention Techniques to Reduce ... Documents...Contract N 2013/313-757 For...
IAEA International Atomic Energy Agency
Project B1.- Practical Intervention
Techniques to Reduce Public Doses at
Uranium Mining and Milling Legacy Sites
Project B2.- Review of Remediation
Plans and Activities for Uranium Mining
and Milling Sites
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Project rationale/objective:
Project B1
• Significant legacy issues have arisen
from past operating practices that
resulted in poorly sited and designed
tailings facilities which, in some cases,
were not remediated and closed, or not
remediated and closed in accordance
with current international standards.
• Many of these legacy sites are located
in countries eligible to receive technical
support which have poorly developed or
limited regulatory capacity.
2
Mocambique, Mozambique
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Project rationale/objective:
Project B2
• Uranium mining and processing operations produce
significant quantities of radioactive mill tailings which
remain after the decommissioning and closure of the
operation.
• Many countries have both legacy uranium mining
sites that were created at a time when regulatory
supervision of operations was weak or absent and are
also struggling to regulate new uranium mining
operations.
• The legacy issues arose from past operating
practices which were not remediated and closed in
accordance with current international standards.
• In addition, many of these countries share common
issues such as the abandonment of the sites by the
original operators, and ineffective, or an absence of,
institutional controls over the fate of the mill tailings.
3
Tajikistan, Village Beside Mine
Tajikistan, Abandoned Mine
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Expected Outcomes:
Project B1
• The project will provide regulators with
enhanced knowledge of legacy issues,
potential risks to the public, mitigation options
and the management of legacy uranium
tailings.
• Enhanced transfer of knowledge of potential
risks to the public, low-cost/quick-fix mitigation
options for the management of legacy sites to
reduce public exposure now and in the future;
• Improved safety of legacy sites, which will
contribute to increased protection of the public
and a reduction in future legacy issues in the
longer term.
4
Algeria, Abandoned Mine
Algeria, Grazing Animals
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Expected Outcomes:
Project B2 • A transfer of knowledge regarding the regulatory oversight of the remediation of
operating and legacy uranium producing operations;
• The improved regulatory oversight of remediation of operating and legacy uranium
mines over the next 10-15 years, and a reduction of potential exposure to workers
and the public, as well as prevention of future legacies.
5
Canada, Abandoned Mine
IAEA
Expected project impact:
Project B1
• The regulators in African countries and other affected Member States with
uranium legacy sites having the knowledge to develop and implement site
specific, low-cost mitigation techniques to protect the public.
• The measures to be considered will comprise simple administrative,
physical and engineering controls that can be used to reduce doses to
members of the public living close to these uranium legacy sites;
6
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
IAEA
Expected project impact:
Project B2
• The regulators in African countries and other affected Member States
provided with the knowledge and tools to review remediation plans and to
regulate remediation activities.
• The project enhances the regulatory framework for countries that have
operating and legacy uranium production sites in: regulatory review and
planning for remediation; waste management; and the radiation protection
of populations living close to these sites.
7
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
IAEA
Beneficiary Member States:
Both Project B1 and Project B2
First priority - African countries with uranium legacy
sites, but the developed materials could be used for
countries with similar situation in other Regions.
8
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
IAEA
Illustrative Milestones
Projects B1 and B2
• Draft technical documents addressing:
• Project B1 International experience in practical intervention
techniques to reduce public doses at uranium mining and milling
legacy sites.
• Project B2 Knowledge and tools to review remediation plans and to
regulate remediation activities in countries with operating and
uranium legacy sites.
• Draft agenda for the training workshops to be organized in the frame of
both projects were developed.
• Draft training materials including Power Point presentations and lecture
notes were developed for both projects.
In Nov-2014 the draft technical documents and the lectures of
both projects were reviewed for coherence and consistency
9
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
IAEA
Figure 33: The mine shaft in the summer prior to PUF installation. The PUF material is covered with the blue tarp (Canadian case study).
1. INTRODUCTION
2. BASIC INFORMATION ON THE REMEDIATION OF LEGACY SITES
2.1. EXPLOITATION OF URANIUM ORE
2.2. RISKS TO MEMBERS OF THE PUBLIC
2.3. APPLICATION OF THE IAEA SAFETY STANDARDS
2.4. REMEDIATION PROGRAMME
2.5. NATIONAL APPROACH
3. GENERAL APPROACH TO SHORT TERM DOSE REDUCTION MEASURES
4. SITE ASSESSMENT
4.1. INITIAL SITE VISIT
4.2. INITIAL SITE SURVEY
4.3. DETAILED ASSESSMENT
4.4. SURVEY EQUIPMENT
4.5. SAMPLING TECHNIQUES
4.6. SIMPLE TECHNIQUES FOR THE ANALYSIS OF SAMPLES
4.7. DATA MANAGEMENT
5. DOSE ASSESSMENT
6. PRIORITIZATION OF LEGACY SITES
7. SIMPLE DOSE REDUCTION MEASURES
8. EXAMPLE OF SHORT TERM MEASURES APPLIED TO A LEGACY SITE
10
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757 Results Achieved to Date
Project B1 Draft document has the following content:
IAEA
Results Achieved to Date
Project B1 Elaborated 20 PP presentations and lectures notes:
11
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
1. Workshop overview and introduction
2. Historical overview of legacy sites
3. Introduction to radiation and radiation protection
4. Existing exposure situations (GSR Part 3)
5. Risks to the public arising from legacy uranium sites
6. Development of a national inventory of legacy sites
7. Issues to be considered in the initial site visits
8. Overview of the Site Characterization. (including non-radiological aspects)
9. Simple Radiological Survey, Dose Assessments and Data Reduction
10. Simple Sampling and Analysis Techniques
11. Prioritisation of sites and public risks
12. Radiation protection programmes for workers
13. Remediation objectives and criteria
14. Regulatory aspects: authorization and inspection of remediation
15. An overview of simple intervention techniques to reduce public doses. (Part 1)
16. An overview of simple intervention techniques to reduce public doses. (Part 2)
17. Case study presentation (South Africa studies and Mozambique)
18. Case study presentation. (US, Canada, Germany)
19. Case study presentation. (Australia)
20. Prevention of future legacy sites
IAEA
1. INTRODUCTION
2. LEGACY SITES AND THEIR REMEDIATION
3. INTERIM MEASURES TO REDUCE RISKS AT LEGACY SITES
4. ELEMENTS OF A REMEDIATION PLAN
4.1. GENERAL CONSIDERATIONS
4.2. SITE CHARACTERIZATION
4.3. COMMUNICATION WITH STAKEHOLDERS
4.4. SAFETY ASSESSMENT
4.5. ENVIRONMENTAL IMPACT ASSESSMENT FOR REMEDIATION
4.6. RADIATION PROTECTION PROGRAMME
4.7. NON-RADIOLOGICAL HAZARDS
4.8. PROTECTION AND RESTORATION OF WATER RESOURCES
4.9. REMEDIATION OF LAND
4.10. MANAGEMENT OF RESIDUES GENERATED BY REMEDIATION
4.11. RECORD KEEPING
4.12. ACTIVITIES ON COMPLETION OF REMEDIATION
5. FUNDING OF REMEDIATION
6. REGULATORY OVERSIGHT OF REMEDIATION
6.1. ROLES AND RESPONSIBILITIES
6.2. REGULATORY SUPERVISION
6.3. APPROVAL AND AUTHORIZATION PROCESS
7. CHECKLIST FOR REGULATORY REVIEW OF REMEDIATION PLANS
12
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757 Results Achieved to Date
Project B2 The draft document has the following content:
COSM I C
NORM FROMEXTRACTIVE INDUSTRIES
TERRESTRIAL
INDOOR RADON
ACCIDENTS
CURRENT PRACTICES
COMMODITIES
PAST ACTIVITIESAND EVENTS
IAEA
Results Achieved to Date
Project B2 Elaborated 26 PP presentations and lectures notes:
13
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
1. Workshop overview and introduction
2. Types of mining and milling sites
3. Radiation and radiation protection
4. Exposure situations from the mining and
milling lifecycle.
5. Lifecycle and graded approach to
regulation and safety
6. Roles and Responsibilities
7. Prevention of future legacy sites
8. Interim Measures for Legacy Sites
9. Decommissioning and Soil Remediation
10. Overview of the environmental
remediation process. Regulatory
requirements.
11. Site Characterization (including non-
radiological)
12. CSM Exercise
13. Management and disposal of Waste
14. Geotechnical Engineering
15. Financial assurance for remediation
activities
16. Surface water and erosion protection. Water
treatment, sludge, disposal of other waste
17. Radiation Protection. Remediation and
abatement of radiation hazards
18. Monitoring during remediation and post-
remediation monitoring and control
19. Protection of water resources
20. Unique considerations for ISL facilities,
exploratory drilling, heap leach
21. Environmental Impact Assessment. Dose and
Risk Assessment
22. Stakeholder engagement and risk
communication
23. Long term care and surveillance
24. Regulatory oversight of remediation.
Authorization and, inspection
25. Regulatory checklist for review of
remediation plans
26. Exercise on Regulatory checklist for review
of remediation plans
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
For both Project B1 and Project B2
In the next six months it is planned to have in place training packages, which
will consist of
14
Training Manual
(TECDOC)
Syllabus
Power Point
Presentations
E-Learning
material
The technical basis for the
training workshops
Methodological
recommendations
to the lecturer
English, French and
Portuguese
Online training e-learning material to be used
as precondition for admission for training.
Workshop
content
Objectives
and content of
each lecture
Lecture’s
notes
Workshop
Agenda
Notes for the
lecturers in each
slide
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Next Steps in the Project
Both Project B1 and Project B2
In the next six month the key activities planned are:
• Technical meeting to review for coherence and consistency the training materials
developed in the framework of project B1 (Vienna, 23-27 February 2015).
• Technical meeting to review for coherence and consistency the training materials
developed in the framework of project B2 (Vienna, 9-13 March 2015).
• HBA for the translation of the materials into French and Portuguese.
• Consultancy for the preparation of the CDs with the technical document and related
training materials.
• First workshop on Project B.1. “Practical Intervention Techniques to Reduce Public
Doses at Uranium Mining and Milling Legacy Sites” (South Africa, 15-19 June
2015).
15
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Difficulties Encountered or Envisaged
• No major difficulties encountered till now in
the implementation of the working plan.
• There is a challenge to organize and
implement the four planned training
workshops in the African region because of
the EBOLA epidemic. Not only with the
selection of the host country but also with the
willingness of experts to participate as
lecturers.
Measures to Address Them
• An alternative measure may be to organize
the training workshops in Vienna.
16
IAEA
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Conclusions
• Both projects B1 and B2 will be completed on time in the frame of the
approved budget.
• The outcomes of both projects will be achieved. Note: within the
approved budget, two technical documents will be elaborated and
issued as part of the training package (were not included in the initial
project plan).
• The project could be extended to:
• Expand the training to other interested parties in other regions (operators
and regulators).
• Consider developing model regulations for remediation of uranium
legacy sites.
17
IAEA 18
Uranium Mining and Milling Legacy Sites
Contract N° 2013/313-757
Luis Jova Sed ([email protected])
Zhiwen Fan ([email protected])
Ron Stenson ([email protected])
John Rowat ([email protected])