PROJECT APPRAISAL REPORT · Translated Document AFRICAN DEVELOPMENT BANK GROUP ized ized. Table of...
Transcript of PROJECT APPRAISAL REPORT · Translated Document AFRICAN DEVELOPMENT BANK GROUP ized ized. Table of...
PROJECT: TOGO AGRO-FOOD PROCESSING ZONE PROJECT (PTA-
TOGO)
COUNTRY: REPUBLIC OF TOGO
PROJECT APPRAISAL REPORT
RDGW/AHFR
July 2018
Translated Document
AFRICAN DEVELOPMENT BANK GROUP P
ub
lic
Dis
clo
sure
Au
tho
rize
d
P
ub
lic
Dis
clo
sure
Au
tho
rize
d
Table of contents
Currency Equivalents, Fiscal Year, Weights and Measures, Acronyms and Abbreviations, Project Profile,
Executive Summary, Results-Based Logical Framework, Implementation Schedule i-vii
I. STRATEGIC THRUST AND RATIONALE ...................................................................... 1
1.1 Project Linkages with Country Strategy and Objectives .................................................. 1
1.2 Rationale for Bank Involvement ...................................................................................... 2
1.3 Aid Coordination .............................................................................................................. 3
II. PROJECT DESCRIPTION ................................................................................................... 4
2.1 Project Components.......................................................................................................... 4
2.2 Technical Solutions Adopted and Alternatives Explored ............................................... 8
2.3 Project Type..................................................................................................................... 9
2.4 Project Cost and Financing Arrangement........................................................................ 9
2.5 Project Area and Beneficiaries ...................................................................................... 11
2.6 Participatory Approach for Project Identification, Design and Implementation ........... 12
2.7 Bank Group Experience and Lessons Reflected in Project Design ............................... 12
2.8 Key Performance Indicators .......................................................................................... 13
III. PROJECT FEASIBILITY ................................................................................................... 13
3.1 Economic and Financial Performance ........................................................................... 13
3.2 Environmental and Social Impact ................................................................................ 15
IV. PROJECT IMPLEMENTATION ...................................................................................... 18
4.1 Implementation Arrangements ....................................................................................... 18
4.2 Project Monitoring and Evaluation ................................................................................ 20
4.3 Governance ..................................................................................................................... 21
4.4 Sustainability .................................................................................................................. 22
4.5 Risk Management ........................................................................................................... 22
4.6 Knowledge Building ....................................................................................................... 23
V. LEGAL FRAMEWORK ..................................................................................................... 23
5.1 Legal Instrument ............................................................................................................ 23
5.2 Conditions for Bank Involvement ................................................................................. 24
5.3 Compliance with Bank Policies...................................................................................... 26
VI. RECOMMENDATION ........................................................................................................ 26
Appendix I: Togo’s Comparative Socio-economic Indicators ...................................................... I
Appendix II: Current Bank Portfolio in Togo .............................................................................. II
Appendix III: An Analysis of Togo's Fragility ........................................................................... III
Appendix IV: Agro-food Processing Zone (ZTAs) : ................................................................ VII
Appendix V: General Table of ADF and TSF Grant and Loan Resource Allocation ................ IX
Appendix VI: Details of the Economic and Financial Analysis .................................................. X
Appendix VII: Map of PTA Intervention Area in the Kara Region ......................................... XII
i
CURRENCY EQUIVALENTS – May 2018
Currency Unit : CFAF
UA 1 : CFAF 780.9
UA 1 : xx EUR
EUR 1 : CFAF 655.957
FISCAL YEAR
1 January – 31 December
WEIGHTS AND MEASURES
Metric System
ACRONYMS AND ABBREVIATIONS
ADF African Development Fund (of the Bank Group)
AFD French Development Agency
ANGE National Environmental Management Agency
APA Advance Procurement Action
ATC Agricultural Transformation Center (Villages level)
DED Detailed Engineering Design
FEED Front End Engineering Design
FRP Full Resettlement Plan
CSP Country Strategy Paper (of the Bank)
DCE Bidding Documents
DPA Agricultural Policy Document (2016-2030)
DWS Drinking Water Supply
ECOWAS Economic Community of West African States
ERR Economic Rate of Return
ESIA Environmental and Social Impact Assessment
ESMP Environmental and Social Management Plan
GCF Green Climate Fund
GHG Greenhouse Gas
HDI Human Development Index
ICAT Technical Advice and Support Institute
ICT Information and Communication Technologies
INDC Intended Nationally Determined Contribution
INFA National Institute of Agricultural Training
ISS Integrated Safeguards System
ITRA Togo Institute for Agronomic Research
PDA Public Development Assistance
PGPP Pests and Pesticides Management Plan
PMU Project Management Unit
PPF Project Preparation Fund
RAP Resettlement Action Plan
SESA Strategic Environmental and Social Assessment
SME Small and Medium-Sized Enterprise
TFP Technical and Financial Partners
TSF Transition Support Facility (Bank Group)
VRD Roads and Main Networks
WB World Bank
WSC Water and Soil Conservation
ZTA Agro-food Processing Zone (AFPZ)
ii
PROJECT INFORMATION SHEET
Client Information
___________________________________________________________________________
BORROWER: Republic of Togo
EXECUTING AGENCY: Agency for Promotion and Development of Agropoles in Togo
(APRODAT)
Financing Plan
Source Amount
(UA M)
Amount
(CFAF M)
Amount
(USD M) Instrument
ADF (including PPF) 4 635 3 619 700 Grant
ADF 8 040 6.278 830 Loan
TSF (Pillar I) 8 320 6 497 500 Loan
BOAD 12 804.92 10 000 000 Loan
Saemaul Globalization
Foundation (South Korean) 3 524.19 2 752 220 5 000 Grant
Government (including
PPF) 7 741.95 6 046 080 Budget
TOTAL COST 45 066.07 35 194.33
* PPF advance: UA 995 000
Key Financial Information on the Loans and Grants
Maturity (years) 40
Grace Period (years) 10
First Period (years) 10
Amortisation Rate (%) 2.0
Second Period (years) 20
Principal Amount Amortisation Rate (%) 4.0
Service Commission (%) 0.75
Commitment Fee (%) 0.50
Interest Rate (%) 0
Concessionality (%) 61
NPV (baseline scenario) CFAF 56 959 375
ERR (baseline scenario) 23.23%
Timeframe – Key Milestones (expected)
Concept Note Approval March 2018
Project Approval July 2018
Effectiveness October 2018
Last Disbursement December 2023
Completion September 2023
Last reimbursement December 2058
iii
Executive Summary
A. Project Overview
A1. The Togo Agro-Food Processing Zone Project (PTA-Togo) is a pilot project implemented
as part of the Togo Agropoles Strategic Development Plan 2017-2030 and the Feed Africa Initiative
2016-2025. The aim of the project is to create conditions conducive to private investment, notably
in the processing of agricultural products, the supply of inputs and marketing, in the Kara region.
The main outcomes expected from the Project are as follows: (i) increase in the productivity and
agricultural production of import substitutes (rice, maize, soybean, broiler meat) and exports
(cashew nuts and sesame); (ii) increase in the share of agricultural products processed in situ (from
19% to 40%) through private investment in the Agro-park (90,000 tons/year of rice paddy, 15,000
tons/year of maize, 10,000 tons/year of soybean, 20,000 tons/year of feed, 10,000 tons/year of
cashew nuts and 10,000 tons/year of sesame, production of 3 million chicks per year, slaughtering
of 2 million broilers/year); (iii) Strengthening of the people’s food and nutritional security; (iv)
creation of wealth and employment, including for young people and women; (v) Preparatory studies
funded by the Project Preparation Fund (PPF). These studies focused on: (1) analysis of the agri-
business environment and market potential; (2) development of a master plan for the Agro-park; (3)
full studies on the electrical and telecommunication networks of the Agro-park; and (4) preliminary
detail design studies of mini-dams, irrigated schemes, drinking water supply systems and access
roads.
A2. The project will bring direct benefits to about 303,000 people in the Bassar, Doufelgou,
Kéran, Bastar and Dankpen Prefectures, 51% of whom are women, and indirect benefits to the
estimated 769,940 people of the Kara region. The main impacts expected from the project for the
direct beneficiaries are as follows: improved food and nutritional security and incomes thanks
particularly to better access to markets, agricultural inputs, agricultural services and financing. To
that end, it is expected that the project would lead to: (i) an increase in private investments thanks to
a more favourable business environment for the establishment of infrastructure in the Agro-park
(roads and sundry networks, single window, training room, maintenance centre, incubation centre,
etc.); (ii) increase in agricultural production capacities thanks to expected rural infrastructure (dams,
irrigated areas, roads, etc.); (iii) capacity building for operators in the 10 multipurpose agricultural
transformation centres (ATCs) (inputs, farm equipment, technologies, financing, harvest
aggregation, etc.). The project will be implemented following the value chain approach through a
partnership between the State (facilitator and regulator), the private sector (promoter) and
professional farmers’ organisations (FOs). In addition to capacity building for FOs (technical and
organisational management), the project will support the operation of consultation frameworks for
priority chains, to ensure the inclusion of farmers and agreements with the private sector.
A3. This pilot project will be implemented over a five-year period at a total pre-tax cost of
about UA 45,066,070 (about CFAF 35.194 billion), broken down as follows: (i) ADF loan: UA 8.04
million (17.8%); ADF grant: UA 4.046 million (10.3%); TSF loan: UA 8.32 million (18.5%) (ii)
BOAD: UA 12,804,920 (28.4%); (iii) Saemaul Globalization Foundation: UA 3,524,190 (7.8%);
and (iv) State: UA 7,741,950 (17.2%). The project has four components: (a) support policy,
governance and incentive measures; (b) infrastructure for processing and accessing agricultural
inputs and services; (c) capacity building for actors in priority agricultural chains; and (d)
coordination, management, monitoring and evaluation. It will be implemented by the Agency for
the Promotion and Development of Agropoles in Togo (APRODAT), which was established by
Decree No. 2018-036/PR of 27 February 2018 to promote and develop ten agropoles over the next
fifteen years.
iv
B. Needs Assessment
B.1 Despite the strong contribution of agriculture to the country’s GDP, estimated at 40% on
average and bringing together 60% of the population, with 87% of assets often family-owned and
revolving around agriculture, Togo’s level of investment in the agricultural sector remains weak
compared to its needs. Public spending, including that of donors, remains low: it went from CFAF
25 billion in 2010 to CFAF 50 billion in 2013-14 and CFAF 44 billion in 2016. Private investments
are quite insufficient compared to the needs and potential of the agricultural sector, owing to,
among other things, a less-than-enticing environment, lack of infrastructure and poor structuring of
agricultural sectors. Investment and management weaknesses explain to a large degree the low
agricultural productivity and insufficient access to domestic (import substitution) and export
markets. The PTA of the Kara region, which is part of the Agropoles Strategic Development Plan
2017-2030, will have to help mobilise private financing to transform the agro-food sector, including
for the six promising sub-sectors that were identified following preliminary studies and broad
consultations.
C. Bank’s Value Added
C.1 The Bank’s goal, through the 2013-2022 Ten-Year Development Strategy, including the
Feed Africa 2016-2025 Strategy and its Agro-Food Processing Zones (ZTAs) flagship programme,
is to increase private investment in the agricultural sector through facilities and incentives
implemented by the State. In that connection, the Bank and its partners have the relevant expertise
and financial resources to facilitate the preparation and implementation of this type of project. The
experience accumulated by the Bank through its previous interventions in the agricultural and rural,
infrastructure, governance and private sectors not only in Togo but in the rest of Africa argues in
favour of such intervention, which concerns both the public sector (for this project) and the private
sector (the principal investor, the Kalyan Group, has submitted a financing request to the Bank that
is currently under review). The Bank also wishes to support the country in the transformation of its
agriculture by promoting private investment through the incentive measures built into the project,
concerning, in particular (i) the business environment; (ii) establishment of basic infrastructure; and
(iii) improvement of the operation of the sub-sectors.
D. Knowledge Building
D.1 Since the Togo-ZTA planned for the Kara region is a pilot operation for the country, a
comprehensive mechanism will be set up to monitor and evaluate the outcomes and impacts of the
project and the Agropoles Strategic Development Plan 2017-2030. In addition to building the
technical, financial, managerial and other capacities of actors, the project will put in place an
adapted mechanism for monitoring the performances of the pilot project, but also of the Agropoles
Strategic Development Plan 2017-2030 for the Agency for the Promotion and Development of
Agropoles in Togo (APRODAT) and institutional actors. The external evaluation of the project,
which will be supervised by the Board of Directors of APRODAT, will should help to provide
baseline as well as end-of-project data. In addition, studies and support specific to APRODAT will
be set up for an in-depth examination of the major issues (including legal, institutional and financial
issues, public-private partnerships and community involvement). Lastly, it is expected that
information-sharing platforms would be set up, analytical reports would be produced, and
consultation meetings would be organised to share experiences and learn useful lessons from this
innovative project to be used by national authorities and those of the Bank.
v
Results-based Logical Framework of Togo-ZTA
NAME: Togo Agro-food Processing Zone Project (PTA-Togo)
GOAL: Contribute to inclusive agricultural growth, which will create wealth and jobs, and to the reduction of food imports through increased private investment in priority value chains, including
agricultural processing and the supply of inputs and agricultural service.
RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF
VERIFICATION
RISKS AND MITIGATION
MEASURES Indicators
(including SCI)
Baseline situation Target
IMP
AC
T
1. Contribute to reducing the volume of food imports per
capita
2. Contribute to reducing the poverty rate (especially in
rural areas)
1. Value of food imports in USD / per capita
2. % of population living below the poverty line (less than
USD 1.90/Day)
2.1 Increase in household food security levels
2.2 Decrease in % of children affected by chronic
malnutrition (including girls)
21.3 (2014)
49.1% (2015)
32.1% (Kara region)
16 (2030)
25% (2030)
28.9% (2025)
National Statistics,
Statistics of the
United Nations
System
Demographic and
Health Survey 2013-
2014 (Baseline
situation)
OU
TC
OM
ES
1. The share of locally processed agricultural products has
increased
2. The living conditions of rural inhabitants of the project
area have improved
1.1 Share of agricultural production of the project region
processed in situ
1.2 Private investments catalysed in agribusiness in the
Kara region (USD million)
2.1 Rate of household access to basic social services in the
project-affected villages has improved: (i) Electricity; (ii)
all-weather roads (within 5 km)
2.2 Number of direct and indirect jobs created / enhanced (of
which 50% are held by women)
2.3 Crop yields of crops t/ha: (i) Irrigated rice (double-
cropping); (ii) lowland rice; (iii) rain-fed rice; (iv) Corn;
(v) soybeans; (vi) sesame; (vi) cashew nuts;
2.4 % of children aged 6-23 months with a minimum
acceptable diet
19%
0
(i) 16%; (ii) 11%
0
(i) 2; (ii) 1.5; (iii) 1;
(iv) 1.2; (v) 0.5 ; (vi)
1; (vii) 0.5
10.5% (Kara region)
36%
>100
(i) 43%; (ii) 22%
39,000
(i) 10 ; (ii) 4; (iii) 2;
(iv) 3; (v) 1; (vi) 1;
(vii) 1
20%
Baseline Survey
and End-of-Project
Reports
National statistics
Demographic and
Health Survey in
Togo 2013-2014
Risk 1: Land security is not
enough to attract the private
sector and protect farmers
Mitigation 1: SESA has
identified mitigation
measures, including decrees
to implement the Land Code
and establishment of the
Kara one-stop-shop
Risk 2: Inadequate attention
to the needs of women and
youth
Mitigation 2: The
Foundation's SESA
(including RAP, ESIMP and
PDC), and gender and
nutrition-sensitive
participatory approach will
have positive effects on the
population
Risk 3: Climate change and
harmful population practices
could degrade natural
resources (NR)
Mitigation 3: Integrated NR
management and the
development of alternative
livelihoods should scale up
the project impacts.
vi
OU
TP
UT
S
A / Support Policies, Governance and Incentives
1. Support to improve the institutional framework of
the ZTA
2. Establishment of the ZTA Governance System
3. Support to non-financial and financial institutions
B / Support infrast. for processing, production and
access to agricultural inputs and services
4. Implementation of Agro-Park development
infrastructure
5. Infrastructure for production aggregation and access
to agricultural inputs & services
6. Establishment of agricultural production support
infrastructure
C / Capacity building of sector actors
7. Capacity building of priority value chain POs
8. Capacity building for communities
9. Strengthening access to state services
D / Coordination, management and monitoring and
evaluation
Steering and Coordination, Procurement, Financial
Management
Audit, Monitoring and Evaluation
1.1 Land Code implementing regulations are enacted
1.2 SSEA-related implementing legislation is enacted
1.2 The national directorates of the Ministry of Industry in
charge of food quality are equipped and trained
2.1 APRODAT's capacities are built
2.2 The Agro-park management company is operational
3.1 The capacity of training, advisory support and
certification structures is built
3.2 Percentage of partner FI portfolios invested in
agriculture: (i) Banks; (ii) MFIs
4.1 Area of the Agro-park and developed (VRD+BC)
4.2 Annual capacity of Agro-park industrial units (x1000):
(i) Rice; (ii) Corn; (iii) Soybean; (iv) Sesame; (v) Cashew
nuts; (vi) Feed; (vii) Broiler chicken; (viii) Chicks
5.1 No. of ATCs built and equipped
5.2 Total length of rehabilitated roads
6.1 Number of small dams built (capacity in m3)
6.2 Area covered by studies (i) Irrigation schemes; (ii)
Lowlands developed (ha)
7.1 No. of ATCs with capacity built
7.2 No. of key OPAs trained and supported
7.3 Number of farmers with access to services provided by
ATCs (inputs, harvest management, e-farming, etc.)
8.1 No of OPA support sub-projects completed (2 ATCs)
8.2 Number of improved stoves installed
8.3 Number of civil status documents established through
the project
9.1 Capacity building of state services in participatory
approach, gender, health and nutrition, etc.
9.2 Capacity building for SESA implementation
9.3 Monitoring of ESIA, ESMP, RAP and PGPP (ANGE)
Financial management /accounting/procurement procedures
and systems prepared and implemented
Number of PM Plans submitted on time and approved
Annual audit report submitted on time
Number of semi-annual progress reports submitted on time
Project baseline and completion surveys conducted
0
0
0
0
0
0
(i) 0.3%; (ii) 10%)
0
(i) 0 ; (ii) 0 ; (iii) 0 ;
(iv) 0 ; (v) 0 ; (vi) 0 ;
(vii) 0 ; (viii) 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
1
1
1
1
1
(i) 3% ; (ii) 15%
46 ha
(i) 90T; (ii) 15T; (iii)10T;
(iv) 10T; (v)10T; (vi)20T;
(vii) 2000; (viii) 3000
10
100 Km
2 (Vol. >15 M.m3)
(i) 1500 ha; (ii) 1500
ha
10
50
10 000 (incl. 30% wom.)
10 000 (incl. 30% wom.)
6
5000
50 000
1
1
1
1
5
5
10
2
Baseline and
Project
Completion
Surveys Reports
Baseline data: year
2017
Project semi-
annual activity
reports
Bank Supervision
Reports
Risk4: Lack of private
sector interest could limit
investment in the Agro-park
Mitigation4: (i) Meetings
have been held with the
private sector (including the
Kalyan Group, a key
investor), and their needs
taken into account;
(ii) The Project will finance
infrastructure for the
development of the Agro-
park site and production
areas; (ii) support for the
implementation of PI
reforms is planned (land,
standards and quality
control, PPPs, etc.); and (iii)
Technical assistance (legal,
technical, management,
PPPs, etc.) will be made
available to APRODAT.
Risk 5: Project delays due to
APRODAT's lack of control
over the Bank's procedures)
Mitigation 5: Substantial
institutional support (see
action plans) is planned for
APRODAT within the
framework of the project.
KE
Y
AC
TIV
ITIE
S Components: (1) Support Policies, Governance and Incentives; (2)
Support Infrastructure for Processing, Production and Access to
Agricultural Inputs and Services (3) Capacity Building for Agro-industrial
Sector Actors; (4) Coordination, Management and Monitoring and
Evaluation
Resources by component: (1) Component A: UA 4.983 million (11%); (2)
Component B: UA 30.339 million (67%); (3) Component C: UA 4.440
million (10%); (4) Component D: UA 5.304 million (12%)
Sources of funding: (i) ADF loan: UA 8.04 million, ADF Grant (with
PPF): UA 4.635 million; (ii) TSF: UA 8.32 million; (iii) BOAD: UA
12.80 million; (iv) Saemaul Foundation: UA 3.52 million; (v) State: UA
7.74 million
vii
Project Implementation Schedule Year 2018 2019 2020 2021 2022 2023
Quarter 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Preparatory activities
Project appraisal
Loan, grant negotiations and approval
Signing of loan/grant agreements and compliance with conditions precedent to first disbursement
Publication of General Procurement Notice
Finalisation of selection of key staff and project launch
I / Support policies, governance and incentives
Recruitment of the technical assistance firm at APRODAT and delivery of services: preparation of procedures
manual, legal instruments, specifications of the management company, Technical Assistant to the Contracting Authority (ACA), training, etc.
Procurement of equipment and capacity building for: APRODAT, Quality Directorates in charge of quality
(Min.industry), Agricultural Technical Services, Agro-Park Management Company, etc.
Recruitment of firms and feasibility study for two new ZTAs (OTI and Haut Mono) Selection of and capacity building for non-financial and financial institutions (equipment and training): guarantee
funds, IT equipment and agribusiness-oriented training
II/ Support infrastructure for processing, production and facilitating access to agricultural inputs and services (i) Architectural Studies and preliminary project design and bidding documents (APD/DCE) for the Agro-park;
(ii) APD/DCE for small dams and irrigated areas; (iii) complete studies on dam B9; (iv) Access roads and
Agricultural transformation Centres-ATC (10)
Development of the Agro-park including roads and sundry networks (drinking water, electricity, sanitation, roads, etc.), DWSS, WTP and BC: selection of service providers &works implementation
Rehabilitation of access roads (national budget)and construction of 10 ATCs (ADF/TSF) selection of service
providers and works implementation
III/ Capacity building for actors in agricultural sectors Capacity building for 10 ATC (sector structuring, technical and management training, support for input
procurement/management, agricultural services including e-farmers platform, etc.)
Support for the implementation of priority sub-projects in the key sectors of 2 pilot ATCs (Saemaul Globalization Foundation)
Capacity building for rural communities: local planning, environmental management, nutrition manufacture of
improved stoves, civil status documents, etc.)
Capacity building for central and decentralise services (local development approach, action plans for protected
areas and pesticides, ESMP/RAP, missions and training, etc.)
IV/ Project coordination and management
Implementation of the financial, administrative and accounting management system
Establishment of the baseline situation and implementation of the monitoring and evaluation system
Coordination and management, monitoring and evaluation and communication
Technical assistance to APRODAT (procedures manual, engineering, legal matters, etc.)
Annual audit reports
Mid-term review
Completion report
1
REPORT AND RECOMMENDATION OF BANK GROUP MANAGEMENT TO THE
BOARD OF DIRECTORS CONCERNING THE AWARD OF LOANS AND GRANTS
TO THE REPUBLIC OF TOGO TO FINANCE THE TOGO AGRO-FOOD
PROCESSING PROJECT (PTA-TOGO)
Management hereby submits this report and its recommendation concerning a proposed loan of
UA 8.04 million from the African Development Fund (ADF) country allocation and UA 8.32
million from the Transition Support Facility (TSF), as well as a grant of 4.635 million from the
ADF allocation, to the Government of Togo to finance the activities of the Togo-ZTA.
I. STRATEGIC THRUST AND RATIONALE
Project Linkages with Country Strategy and Objectives
1.1.1 Following the end of the implementation period of its Accelerated Growth and
Employment Promotion Strategy (SCAPE) 2013-2017, the Togolese Government has started
preparing its National Development Programme 2018-2022 (NDP 2018-2022), which is expected
to be adopted in 2018. The NDP 2018-2022,
which will be the sole reference for the
Government’s activities over the medium term
(including for this project), builds on three
activities (i) establishing an excellence
logistical hub for international trade; (ii)
creating jobs through the development of agro-
processing centres (case of this project),
manufacturing and extractive industries; and
(iii) consolidating social development and
strengthening inclusion mechanisms. At a
recent Cabinet meeting held on 7 March 2018,
the Government also approved draft legislation
on the Land Code that would be more
favourable for investment, particularly in the
agricultural sector. The Government has also
set its Intended Nationally Determined
Contribution (INDC), to limit the effect of
climate change; in that connection, this project
will help in achieving the INDC goals
concerning adaptation to climate change
(considered a risk) and strengthening the
resilience of the production systems and
sustainable livelihoods.
1.1.2 The country has also formulated and
adopted the Agricultural Policy Paper (DPA)
for the period 2016-2030. The overall objective
of the DPA 2016-2030 is to help speed up economic growth, poverty reduction and improvement
in living conditions, while ensuring social inclusion and environmental protection. The project
should, therefore, help to achieve the specific objectives of the DPA, namely to ensure, in a
sustainable manner: (i) food security; (ii) readjustment of the agricultural trade balance; (iii)
improvement of agricultural income levels; (iv) creation of decent jobs in the agricultural sector
AGROPOLES DEVELOPMENT PROGRAMME IN
TOGO (PRODAT)
The Agropoles Development Programme in Togo-PRODAT (2017-2030), approved by Decree No. 2017-110/PR of 29/09/2017 is the strategic development plan for Togo's agropoles. The main objective of the programme managed by the Agence de promotion des Agropoles (APRODAT) is to accelerate economic growth and reduce poverty through better performance of the primary, secondary and tertiary sectors. The specific objectives are to: (i) develop irrigation schemes, rural infrastructure and agricultural mechanisation; (ii) promote the value chain approach for priority sectors with a market (national and export); (iii) develop agro-industry and the supply of agricultural services; (iv) develop the ICT sector; (v) promote research, innovation and training; (vi) build the capacities of sector actors. Thus, in the long term, the Government targets structural transformation of the agricultural sector through the promotion of 10 ZTAs or 'agropoles' over the next 15 years. The ZTA or "Agropole" is defined as a "given geographical area in which professional organisations (companies, farmers’ organisations, etc.) which maintain functional relations in the activities of production, processing, services and marketing of products of plant, animal, fisheries or forestry origin". The Kara Region CTA is, therefore, the first to be implemented, with in particular the Bank's support.
2
and reduction of labour instability; (v) and maintenance of a high growth rate. In that regard, the
Agropoles Strategic Development Plan 2017-2030 (PRODAT 2017-2030) established by Decree
No. 2017-110/PR of 29 September 2017, designed to establish ten (10) agropoles over the next
fifteen (15) years, underpins Togo’s PTA. The project will ultimately facilitate private
investment in the agro-industrial sector for the development of value chains of interest in terms
of import and export substitution.
1.1.3 Lastly, this project is also part of the Bank’s Country Strategy Paper (CSP) 2016-2022,
Pillar 1 of which concerns the “development of inclusive growth and agribusiness
competitiveness poles”, through the development of agro-industrial processing zones known as
“agropoles”.
1.2 Rationale for Bank Involvement
1.2.1 Togo’s average GDP growth over the 2011-2015 period was 5.3%, compared with
2.7% for the 2006-2010 period. However, in the Human Development Index (HDI) rankings for
2015, Togo was ranked 162nd out of 188 countries with a score of 0.484. The incidence of
poverty fell from 61.7% in 2006 to 58.7% in 2011 and 55.1% in 2015, but the level of poverty
remains high. The rate of extreme poverty did not improve tangibly, going from 28.6% in 2006
to 30.4% in 2011 and then to 28.7% in 2015. In 2015, the incidence of poverty in rural areas
stood at 68.9%, compared with 34.3% in Lomé and 37.8% in other urban areas. The rate of
under-employment rose from 22.1% in 2011 to 24.9% in 2015, according to data from the 2011
and 2015 QUIBB1 surveys. The breakdown of that rate by social category indicates a level of
unemployment, and even under-employment, of about 53.2% for women and about 59% for
young people. In 2014, the prevalence of chronic malnutrition among children under 5 was 28%
at the national level and 32% for the Kara Region.
1.2.2 Despite the political and economic progress made, Togo remains a fragile country,
because its average score following the Country Policy and Institutional Assessment (CPIA) of
the Bank and the World Bank is 3.2 out of 6. Despite structural reforms undertaken by the
Government between 2006 and 2015, the country’s environment remains tense, with political
protests since 2017, notwithstanding the intensification of dialogue between the Government and
the opposition. Another source of fragility concerns the economy’s high level of dependence on
the phosphate sub-sector (+40% of export revenue) and income from seaport and airport traffic,
on the one hand, and socio-economic spatial disparities, on the other.
1.2.3 The country’s economy remains largely dominated by agriculture which, in 2015,
employed 72.6% of the population and accounted for 47.6% of GDP, while services accounted
for 36.2%, and industry 16.2%. There are barely 22 large agro-industrial enterprises in the
country and they supply less than 5% of the products processed and sold on the domestic market.
According to customs statistics for 2014, Togo imported the equivalent of USD 160 million
dollars of food products (including 100,000 tonnes of rice), but only exported the equivalent of
USD 50 million. Over the period 2011-2014, the agricultural trade balance recorded a deficit of
about CFAF 60 billion, owing primarily to growing imports of food products.
1.2.4 The constraints analysis shows that agriculture remains unproductive and not
integrated into the markets, owing to limited access to agricultural equipment, inputs, financing
and land, especially for women and young people. These challenges are compounded by low
level of support infrastructure for agricultural production, storage, processing, packaging and
marketing. This is true for the products targeted by the project in terms of import substitution
3
(rice, maize, soybean, broiler meat) or export (cashew nuts, sesame). The project is located in the
Kara region, deemed a priority area in the implementation of the PRODAT 2017-2030, based on
the following criteria: (i) geographic position; (ii) socio-economic infrastructure; (iii) natural
potential (water, arable land, etc.); and (iv) possibility of growing high-value-added crops.
1.2.5 The Bank has a comparative advantage in the implementation of this project financed
through the public sector window and designed to create favourable conditions for private
investors (the main one being the Kalyan Group, which is interested in cashew nuts and sesame,
and has submitted a financing request to the private sector window that is currently being
reviewed). Moreover, the Bank’s
intervention, which is aimed at helping in the
implementation of the Agropoles Strategic
Development Plan 2017-2030, is perfectly in
line with the Feed Africa Strategy 2016-25,
whose goals are to: (i) help eliminate extreme
poverty; (ii) end hunger and malnutrition; (iii)
make Africa a net food exporter; and (iv)
move Africa to the top of export-oriented
global value chains where it has a
comparative advantage. The project will also
help to achieve the objectives of the Bank’s
Ten-Year Strategy (2013-2022), especially its
operational priorities concerning the
development of infrastructure, the private
sector and inclusive growth.
1.3 Aid Coordination
1.3.1 Within the Government, external aid
is coordinated by the Ministry of Planning,
Development and Economy and Finance.
Since 2010, the Government has put in place
an official development assistance framework
known as Official Development Assistance
(ODA), which is the reference structure for
technical and financial partner (TFP) support.
The framework, which is divided into 11
sectoral committees, including one on
agriculture, is a platform where TFPs
exchange information and align their
interventions with the country’s policies and
strategies. The Bank’s collaboration with the
TFPs, therefore, revolves around the sectoral committees, joint review activities and co-
financing. The Bank, which is very active, co-chairs with Germany the TFP committee on the
agricultural sector. It also plays a leadership role in the dialogue on economic infrastructure,
Agro-Food Processing Zones or ‘agropoles’, fiscal reform and inclusive finance.
PARTNERSHIP WITH THE PRIVATE SECTOR
Project preparation was facilitated by studies
conducted on key agricultural value chains,
potential markets and the business environment.
The mission conducted extensive consultations
with the private sector, including:
The focus group held with the Private Sector to identify their expectations, particularly in terms of the business environment;
Focus group with commercial banks and financial institutions, to assess the risks they face;
Targeted interviews with private groups that expressed interest in financing the agro-park, including (i) the Kalyan Group, a key investor that requested financing from the Bank; (ii) SOMDIAA (malting), (iii) NIOTO (oil mill); etc.
Consultations made during the investment promotion days in the Kara Agropole organized on 05 and 06 April 2018 by Togo’s Chamber of Commerce and Industry (CCIT) and the National Employers Council (CNP)
Exchanges made in the field with agricultural cooperatives and SMEs having invested in several value chains (fish farming, market gardening, poultry farming, etc.), which made it possible to identify their constraints
Interviews with the government services
(including Togo Invest) in charge of the
promotion of private investment
4
1.3.2 Togo’s main TFPs in 2016 were the following: West African Development Bank
(BOAD) with 11.43% of total PDA; Compassion International (10.54%); World Bank (9.69%);
European Union (8.75%); Global Agriculture and Food Security Programme - GAFSP (7.05%);
United Nations system (6.73%); International Fund for Agricultural Development (6.60%);
China (5.48%); Arab Fund (5.44%); Global Fund (4.56%). The AfDB disbursed USD 17.40
million in 2016, representing 3.94% of PDA; the sectoral breakdown of the PDA was as follows:
infrastructure (29%); social protection and employment (25%); governance (13%); agriculture
(13%); health (10%); water, sanitation and environment (6%); education (3%).
Sector or sub-
sector*
Importance
GDP Exports Labour
Agriculture 31% 14% 66% of the workforce
Stakeholders-Annual public spending (average) 2011-2015
Years
Government (internal
public resources) (in
CFAF)
Total agricultural
expenditure of technical and
financial partners-TFPs (in
CFAF)
Total public expenditure of the
agricultural sector (in CFAF)
2010 12 962 743 316.30 13 036 336 918.00 25 999 080 234.30
2011 18 969 601 917.75 8 945 649 877.19 27 915 251 794.94
2012 24 334 975 318.35 13 346 112 440.15 37 681 087 758.50
2013 14 453 025 773.66 31 579 754 732.06 46 032 780 505.72
2014 14 981 443 966.86 35 636 939 006.25 50 618 382 973.11
2015 14 229 608 562.00 37 196 105 916.22 51 425 714 478.22
2016 14 566 951 868.00 30 152 960 156.22 44 719 912 024.22
Aid Coordination Level
Existence of thematic work groups [Yes]
Existence of a comprehensive sectoral programme [Yes]
Role of AfDB in aid coordination*** [M]****
Source: DPD being finalised
II. PROJECT DESCRIPTION
2.0.1 The overall objective of the project is to promote inclusive agricultural growth that
creates jobs and reduces imports thanks to incentive measures for private investment in key areas
(rice, maize, soybean, sesame, broiler meat and cashew nuts).
2.0.2 The specific objectives of the project are to: (i) facilitate private investments in key
areas thanks to policy support, governance and incentive measures; (ii) promote the development
of priority value chains through the establishment of infrastructure to support production, storage
and processing; and (iii) build the capacities of stakeholders in priority agro-industrial areas.
Project Components
2.1.0 Project preparation was largely informed by the conduct of several PPF-funded studies,
including the following: (i) Studies on priority agricultural sectors, potential markets, and the
business environment; (ii) Study on the development of the agro-industrial park master plan; (ii)
preliminary design study of dams, irrigation schemes, DWS and electrification of 6 villages; (iv)
Detail design study of Agro-park electrification and access to the ICT network. Thus, these
studies underpinned the design of this pilot project, which is developed as the first Agro-food
Processing Zone (ZTA) in the Kara region and in the country. It includes measures to support
political, regulatory and institutional reforms with a view to attracting private investment, as well
5
as measures to improve rural infrastructure in the project area and build the capacities of
stakeholders in priority areas in terms of import substitution (rice, maize, soybean, broiler meat)
and exports (cashew nuts and sesame). Specifically, the project has a multidimensional
approach:
2.1.1 At the institutional level, several measures in favour of private investment are planned
under the project, including:
Capacity building of the Agropoles Promotion and Development Agency of Togo
(APRODAT), established by Decree No. 2018-036/PR of 27 February 2018 to achieve the
objective of implementing ten agropoles in the next 15 years (see paragraph 4)
Support for the future semi-public company for the promotion and management of the
Kara Agro-Park, to promote private investment in agro-processing and input supply. and
agricultural services
Improvement of the regulatory and institutional framework for private investment in
agribusiness, in particular through:
The operationalisation of land reform through technical assistance for the drafting of
implementing decrees relating to agricultural and rural land law voted by the
National Assembly on 5 June 2018, including the establishment of a single land
tenure office;
Support to the Directorates and Agencies of the Ministry of Industry in charge of the
implementation of ongoing reforms in standardization and metrology, through
provision of equipment (including laboratory equipment) and training;
Improvement of access to financing, particularly for SMEs and cooperatives, by
setting up a guarantee fund with financial institutions and by providing ad hoc
support (IT equipment and training);
The study to be carried out by the TA firm for the development of the Agro-park
business plan taking into account the targeted markets (national, regional and
international), the business environment, and possible desirable incentives;
Measures to build the capacities of universities and other research, training and
advisory support institutes operating in the agro-industrial sector (IT and laboratory
equipment, training, etc.)
2.1.2 At the physical level, the infrastructure development works planned under the project
to improve the private sector intervention environment will concern three major entities, namely:
A central portion or Agro industrial-park composed of developed land with roads and
sundry networks (drinking water supply, sanitation, electricity, ICT, etc.), logistical
support and specialized facilities and services (cold chain, laboratory and certification,
business services, waste treatment, single window, etc.); a joint savings company will be
responsible for promoting and managing the Agro-park, where private companies invest in
the processing of agricultural products and the provision of services and inputs.
Agro-transformation centres (ATCs), located in 10 village centres, are multipurpose
platforms for use by agricultural operators comprising: (i) an aggregation, sorting and
primary storage centre; (ii) an input distribution centre; (iii) a service centre (agricultural
credit, business centre, farm equipment rental and maintenance, zoo-sanitary clinic, etc.);
(iv) a food quality control and seed certification service; (v) an education and training
centre for producers.
6
Agricultural production zones: They cover zones targeted to provide agricultural products
to the Agro-park through the ATCs. They will benefit from public investments (dams,
irrigated areas, roads, etc.) that will help to boost agricultural productivity for the selected
areas.
2.1.3 Concerning the strengthening of value chain actors to favour greater inclusion, the
project will support implementation of the following measures:
Support the establishment and capacity building of consultation frameworks of the main
targeted sectors, to facilitate business relations with the private sector;
Enhance the capacities of the Agricultural Production Organisations (OPA) of the ten (10)
Agricultural Transformation Centres identified in the three agricultural zones (irrigated,
lowland and rain-fed) with the Saemaul Foundation for Globalization;
Improve the capacity of village communities in participatory diagnosis, participatory local
planning, and the formulation and implementation of community projects (Saemaul
Foundation for Globalization);
Support capacity building of government services and other partners involved in the
implementation of project activities;
Support the implementation of priority sub-projects in support of agricultural sectors
identified by two ATCs (Saemaul Foundation for Globalization);
Support for the implementation of risk mitigation measures as identified in the
Environmental and Social Strategic Assessment (SESA): compensation of
displaced/affected persons, compensation, protection of sensitive sites, etc.
2.1.4 The components, sub-components and activities of the project are presented in the
following table.
Components Cost CFAF M) Description of the Components
A/ Support
policy,
governance and
incentive
measures
4.98
A1/ Improvement of the policy, regulatory and operational framework
Technical assistance for the preparation of instruments for
implementation of the Land Code (voted by the National Assembly on 5
June 2018), the specifications of the Agro-park management company
and operationalisation of the single window
Support for the development of a legal, regulatory and operational
framework for the Strategic Environmental and Social Assessment
(SESA)
Support for the national departments responsible for quality, standards
and metrology (facilities, training) at the Ministry of Industry
Technical assistance for the implementation of private investment
promotion measures in the Agro-park (including instruments and
incentives), financial and management procedures and support for project
management (APRODAT)
Convening of an investment promotion forum for the ZTA (2)
A2/ Establishment of the ZTA governance system
Institutional support for APRODAT’s capacity building (staff, legal,
technical and management assistance, training, etc.)
Support for the preparation of the specifications of the Agro-park
management company, its recruitment (CAT) and monitoring of
performance quality
Feasibility study for two new ZTAs (OTI and Haut Mono regions)
7
Components Cost CFAF M) Description of the Components
A3/ Strengthening State and non-State public institutions
Support for non-financial institutions (computer and laboratory equipment
and training): research institutes (Togo Institute for Agronomic Research
(ITRA)), consulting (Technical Advice and Support Institute (ICAT)),
training (CIDAP, INFA-Tové), Technical Advice and Support Institute
(ICAT), universities, etc.) and seed control/certification
Support for financial institutions: Establishment of a risk insurance fund,
procurement of equipment (computer hardware and software), and
capacity building for banks and financial institutions (including in
agribusiness)
B/ /
Infrastructure
for processing
and accessing
agricultural
inputs and
services
30.91
B1/ Agro-park development infrastructure (Broukou)
Architectural, detailed engineering design/bidding documents studies and
supervision of construction work
Site development works & roads and sundry networks (roads, drinking
water supply, sanitation, electricity, telecommunication, fencing, etc.);
drinking water supply station, water treatment, etc.
Construction of buildings: (i) administrative and residential block; (ii)
services block (training centre, conference centre, laboratories, etc.); (iii)
socio-collective infrastructure block (school, health centre, hotel, etc.);
(iv) etc.
Agro-park electricity supply (CEET) and fibre optic telecommunication
works
Assistance for the establishment of a business incubator (provider)
B2/ Infrastructure for aggregation and access to agricultural inputs and
services
Establishment of basic infrastructure for 10 ATCs located in 10 village
centres covering the three agricultural production areas (irrigated,
lowlands, rain-fed), under the ADF:
- Technical studies and supervision of the construction of ATCs
- Construction works on 10 ATCAs (harvest storage stores, input storage
hangars, cooperative offices)
- Procurement of agricultural, cleaning and logistical equipment
Detailed preliminary design study of the main road (100 km) and
secondary roads (50 km):
Work on the rehabilitation of roads (100 km) including ancillary
structures
Control and supervision of rehabilitation works on the main road
B3/ Support infrastructure for agricultural production
Detailed engineering design/bidding documents studies for three mini-
dams and irrigated areas (1 500 hectares)
Supervision of the construction of two mini-dams (Vol>15 Mm3)
Full technical and economic studies on the B9 dam with irrigated areas
Construction of two mini-dams for agricultural use (potential of 1,500
hectares) and industrial use (4,000 - 5,000 m3/day for the Agro-park)
C/ Capacity
building for
actors in priority
agricultural
sectors
4.44
C1/ Capacity building for agricultural producers (with the Foundation)
Networking of sub-sectors (rice, maize, soybean, sesame, cashew nuts
and broiler meat) and development of consultation frameworks
(Foundation)
Building of the technical and management capacity of 10 ATCs of
villages situated in the three agricultural zones (irrigated, lowlands, rain-
fed) – Saemaul Foundation
Establishment of an information system for use by FOs (e-farmers, e-
aggregation, e-inputs, e-services, etc., ADF)
Increased access to financing by FOs (guarantee fund)
Training and TA of state workers on the Saemaul Foundation approach
8
Components Cost CFAF M) Description of the Components
C2/ Strengthening central and decentralised services
Training and technical assistance from State services (with ICAT) in the
participatory, gender, nutrition and local development approach
Implementation of the safeguards included in the SESA: (i) Preparation of
a resettlement policy framework; (ii) Preparation of a wastewater and
solid waste management blueprint; (iii) Preparation of an environmental
best practices manual; (iv) Implementation of the Environmental and
Social Impact Assessment Plan (ESMP) and pesticide management plan;
(v) Environmental and social baseline situation
Monitoring implementation of the Environmental and Social
Management Plan ESMP (ANGE), RAP (ANGE) and PGPP (ANGE)
Procurement of motorcycles and computer equipment (agricultural
regional administration)
D/Coordination,
management,
monitoring and
evaluation
5.30 Steering and coordination
Procurement
Administrative, financial and accounting management
Monitoring and evaluation (M&E)
2.2 Technical Solutions Adopted and Alternatives Explored
2.2.1 The aim of the Togo PTA is to contribute to the transformation of Togolese agriculture
to achieve inclusive agricultural growth that would reduce poverty and food imports and also
create jobs. Expected investments would come from both public funds (to attract private
investments) and private funds (including in the processing of agricultural products, supply of
inputs and agricultural services), to ensure better integration of import substitutes (rice, maize,
soybean, broiler meat) and exports (cashew nuts and sesame). The measures envisaged under this
innovative project include: (i) establishment of a conducive political, regulatory and institutional
framework that would attract direct private financing and also facilitate access to financing for
small and medium-sized enterprises (SMEs) and cooperatives (insurance funds and technical
support for banks); (ii) development of an Agro-park, including roads and main networks (clean
water, electricity, sanitation and ICTs) in order to facilitate the establishment by private parties
of processing units, agricultural services and access to inputs; (iii) rehabilitation of access roads
to production areas and markets, fully connected to regional and national road networks; (iv)
establishment of Agricultural Transformation Centres in 10 village centres (aggregation of
harvests, supply of inputs and services, capacity building, financing, etc.); and (v) construction
of mini-dams (2) and conduct of detailed studies for other infrastructure (irrigated areas,
developed lowlands, partial control of water in rain-fed areas), while waiting for the mobilisation
of additional financing (including green climate funds). The project will also cover the costs of
detailed studies on the construction/equipping of basic social infrastructure needed to develop
economic activities and improve the living conditions of the local population (drinking water and
electricity). The capacity building segment for actors (beneficiaries, State services, training and
research centres) will be implemented through a participatory approach, with the support of the
Saemaul Foundation. The costs related to the implementation of the Environmental and Social
Impact Assessment Plan (ESMP) will be fully supported by the project.
9
Table 2.2: Alternatives Explored and Reasons for Rejection
Alternatives Short Description
Reason for Rejection
Implement a
traditional project
to support the
improvement of
agricultural
production
Finance the
development of
agricultural
production
infrastructure and
equipment
The State has neither the intention nor the resources to
invest sustainably in tools to increase agricultural
production
The sustainable increase in agricultural production is
only possible if sufficient private investments are
mobilised for processing and marketing
Finance only
partial water
control in the
project
Exclude from the
project the
construction of dams
and irrigated areas
The sharp drop and even stoppage of river water flow
represents a major risk, especially for rice
Drilling capacities are too low; only one dam may be
able to permanently supply water to the Agro-park
2.3 Project Type
2.3.1 The Togo-PTA is a public investment project which aims to create the requisite
conditions for boosting private investments in six priority areas, in particular in the processing of
agricultural products, supply of inputs and provision of agricultural services and marketing.
2.4 Project Cost and Financing Arrangement
2.4.1 Project cost: The total project cost is estimated at UA 45.07 million (CFAF 35.19
billion), net of taxes and custom duties. The cost is broken down as follows: UA 25.53 million
(CFAF 19.94 billion) in foreign exchange and UA 19.53 million (CFAF 15.26 billion) in local
currency. It comprises provisions for physical contingencies and price escalation estimated at 2%
each, on average. The provision for price escalation was estimated based on the current and
projected levels of inflation of the cost of the local currency and the foreign exchange at 2% and
1.5% per year, respectively, on average. The provision for physical contingencies is estimated at
between 0% and 3%. A summary of the estimated project cost by component and by expenditure
account is presented in Tables 2.3, 2.4 and 2.5 below, while the details are provided in the
Technical Annex to the project appraisal report.
10
Table 2.3: Summary of estimated costs by component
PROJECT COMPONENTS
(CFAF million) (UA '000)
%
Dev.
%
C.B
Local
currency
Foreign
exchange Total
Local
exchange
Foreign
currency Total
A. SUPPORT POLICY, GOVERNANCE
& CAPACITY BUILDING 2 379.97 1 457.20 3 837.17 3 047.53 1 865.94 4 913.47 38 11
Support policies & improvement of ZTA
operational framework 633.97 583.20 1 217.17 811.79 746.79 1 558.58 48 4
Establishment of ZTA governance system 488.00 672.00 1 160.00 624.88 860.49 1 485.37 58 3
Strengthening of State and non-State
public institutions 1 258.00 202.00 1 460.00 1 610.86 258.66 1 869.52 14 4
B. DEVELOPMENT OF PROCESSING
AND ACCESS INFRASTRUCTURE 7 214.96 15 457.40 22 672.35 9 238.69 19 793.08 29 031.77 68 67
Kara (Broukou) Agro-park infrastructure 2 150.81 4 896.06 7 046.87 2 754.10 6 269.37 9 023.46 69 21
Access to input infrastructure and
agricultural services 1 279.64 2 975.84 4 255.48 1 638.57 3 810.54 5 449.11 70 13
Production support infrastructure /b 3 784.50 7 585.50 11 370.00 4 846.02 9 713.17 14 559.20 67 33
C. STAKEHOLDER CAPACITY
BUILDING 2 425.82 1 019.40 3 445.22 3 106.24 1 305.33 4 411.57 30 10
Producers of key sectors 2 150.81 4 896.06 7 046.87 2 754.10 6 269.37 9 023.46 69 21
Rural communities 1 279.64 2 975.84 4 255.48 1 638.57 3 810.54 5 449.11 70 13
Central and decentralised services 3 784.50 7 585.50 11 370.00 4 846.02 9 713.17 14 559.20 67 33
D. PROJECT MANAGEMENT &
COORDINATION 2 797.70 1 244.84 4 042.55 3 582.44 1 594.01 5 176.45 31 12
TOTAL BASE COST 14 818.45 19 178.84 33 997.28 18 974.91 24 558.35 43 533.26 56 100
Physical contingencies 169.83 338.20 508.03 217.46 433.06 650.53 67 1
Financial contingencies 267.15 421.86 689.02 342.09 540.19 882.28 61 2
TOTAL PROJECT COST 15 255.43 19 938.90 35 194.33 19 534.46 25 531.61 45 066.07 57 104
Table 2.4: Summary of project costs and expenditure categories
EXPENDITURE CATEGORIES
(CFAF million) (UA '000)
%
Dev.
%
C.B
Local
currency
Foreign
exchange Total
Local
currency
Foreign
exchange Total
I. Investment costs 12 371.80 18 667.24 31 039.04 15 841.99 23 903.26 39 745.25 60 91
A. WORKS 6 170.21 14 397.15 20 567.35 7 900.90 18 435.43 26 336.33 70 60
Dams and development schemes 3 000.00 7 000.00 10 000.00 3 841.48 8 963.45 12 804.92 70 29
Infrastructure 2 960.21 6 907.15 9 867.35 3 790.52 8 844.55 12 635.07 70 29
Construction and rehabilitation 210.00 490.00 700.00 268.90 627.44 896.34 70 2
B. GOODS\a 431.97 867.38 1 299.35 553.14 1 110.67 1 663.81 67 4
Vehicles 57.00 171.00 228.00 72.99 218.96 291.95 75 1
Equipment, materials and inputs 374.97 696.38 1 071.35 480.15 891.71 1 371.86 65 3
C. SERVICES\b 3 442.27 3 402.72 6 844.99 4 407.80 4 357.15 8 764.96 50 20
Training 1 149.52 766.35 1 915.87 1 471.95 981.30 2 453.25 40 6
Technical assistance 213.75 1 211.25 1 425.00 273.71 1 551.00 1 824.70 85 4
Studies 1 160.25 1 088.87 2 249.12 1 485.69 1 394.29 2 879.98 48 7
Various studies 641.70 784.30 1 426.00 821.69 1 004.29 1 825.98 55 4
Preparation advance 518.55 304.57 823.12 664.00 390.00 1 054.00 37 2
Contractual services 885.00 295.00 1 180.00 1 133.24 377.75 1 510.98 25 3
Audits 33.75 41.25 75.00 43.22 52.82 96.04 55 -
D. MISCELLANEOUS 2 327.35 - 2 327.35 2 980.15 - 2 980.15 - 7
II. Recurring costs 2 446.65 511.60 2 958.25 3 132.92 655.10 3 788.01 17 9
A. PERSONNEL 1 572.00 - 1 572.00 2 012.93 - 2 012.93 - 5
B. TRAVEL EXPENSES 407.43 - 407.43 521.70 - 521.70 - 1
C. MAINTENANCE, OPERATIONS &
REPAIRS 295.10 454.22 749.32 377.87 581.63 959.50 61 2
D. OVERHEAD EXPENSES 172.13 57.38 229.50 220.40 73.47 293.87 25 1
TOTAL BASE COST 14 818.45 19 178.84 33 997.28 18 974.91 24 558.35 43 533.26 56 100
Physical contingencies 169.83 338.20 508.03 217.46 433.06 650.53 67 1
Financial contingencies 267.15 421.86 689.02 342.09 540.19 882.28 61 2
TOTAL COST OF THE PROJECT 15 255.43 19 938.90 35 194.33 19 534.46 25 531.61 45 066.07 57 104
11
Table 2.5: Schedule of expenditures by component (in UA thousand)
COMPONENTS PROJECT YEARS
Total 2017 2018 2019 2020 2021
A. SUPPORT POLICIES, GOVERNANCE &
INSTITUTIONAL CAPACITY BUILDING 2 646.68 1 611.11 710.68 7.12 7.21 4 982.79
Support policies & improvement of ZTA operational
framework/a 1 392.21 125.88 39.13 7.12 7.21 1 571.55
Establishment of ZTA governance system 714.67 643.71 171.23 - - 1 529.61
Strengthening of State and non-State public institutions 539.80 841.51 500.31 - - 1 881.62
B. DEVELOPMENT OF PROCESSING AND ACCESS
INFRASTRUCTURE 3 418.78 11 660.38 14 583.38 677.02 - 30 339.56
Kara (Broukou) Agro-park infrastructure 475.53 3 472.24 4 830.56 677.02 - 9 455.35
Access to input infrastructure and agricultural services 2 443.54 2 072.12 1 127.76 - - 5 643.42
Production support infrastructure/b 499.70 6 116.02 8 625.07 - - 15 240.79
C. STAKEHOLDER CAPACITY BUILDING 1 382.98 1 312.24 1 070.38 336.94 337.45 4 439.97
Producers in key sectors 926.07 1 134.61 926.61 301.52 301.52 3 590.32
Rural communities 60.33 74.47 61.98 21.80 22.11 240.68
Central and decentralised services 396.58 103.16 81.79 13.62 13.82 608.97
D. PROJECT MANAGEMENT 2 110.66 873.57 828.69 743.00 747.83 5 303.74
TOTAL COST OF PROJECT 9 559.08 15 740.07 17 479.64 1 764.07 1 092.49 45 635.35
2.4.2 Financing Mechanism: The project will be financed by an ADF loan and grant, a TSF
loan, BOAD and the Korean Fund, to the tune of UA 8.04 million (17.8%), UA 4.635 million
(10.3%), including the PPF refund of UA 995,000; UA 8.32 million (18.5%), CFAF 10 billion
(UA 12.8 million), USD 5.068 million (UA 3.52 million), respectively, and the Togolese
Government to the tune of CFAF 6.046 billion, (including the PPF counterpart of CFAF 46.08
million). The breakdown of expenditure by source of financing and according to the list of goods
and services is presented in Table 2.6.
Table 2.6: Project financing plan
SOURCE OF
FINANCING
(CFAF Million) (UA '000)
% Local
Currency
Foreign
Exchange Total
Local
Currency
Foreign
Exchange Total
ADF loan 1 887.43 4 391.41 6 278.83 2 416.84 5 623.16 8 040.00 17.8
TSF loan 2 250.64 4 246.86 6 497.50 2 881.93 5 438.07 8 320.00 18.5
ADF grant 2 374.41 1 245.30 3 619.70 3 040.41 1 594.59 4 635.00 10.3
BOAD 3 331.70 6 668.30 10 000.00 4 266.21 8 538.71 12 804.92 28.4
Korean Fund 2 122.27 629.95 2 752.22 2 717.55 806.64 3 524.19 7.8
State of Togo 3 288.99 2 757.09 6 046.08 4 211.52 3 530.43 7 741.95 17.2
Total 15 255.43 19 938.90 35 194.33 19 534.46 25 531.61 45 066.07 100.0
2.5 Project Area and Beneficiaries
2.5.1 In the 2016-2020 Agricultural Development Programme, 10 ZTAs or ‘agropoles’ were
identified among the priorities to be financed over the next 15 years. Ongoing studies on the
Project Preparation Fund (PPF) are concentrated in the Kara region, which is deemed a priority
by the Government, considering the current level of poverty, the high agricultural potential (rice
in particular), the opportunities in terms of synergy offered by ongoing projects (PARTAM,
PBVM, PDRI-Mô and PDRD) and the presence of a dynamic private sector (including the
Kalyan Group). The project covers the Bassar, Doufelgou, Dankpen and Kéran prefectures in the
Kara region, located between latitudes 9° 00’ and 10° 00’ North and between longitudes 0°15’
and 1°45’ East.
2.5.2 The population of the Kara region comprises 769,940 inhabitants distributed as follows:
184,693 inhabitants in urban areas and 585,247 inhabitants in rural areas. The activities
envisaged for the project will affect about 303,419 people directly, of whom 151,710 will be
12
women. The population that would be indirectly affected is estimated at around 769,000 people
(51% women).
2.6 Participatory Approach for Project Identification, Design and
Implementation
2.6.1 The project formulation was facilitated by the establishment of an Inter-Ministerial
Steering Committee involving all stakeholders. Discussions between the key players (private
sector, OPAs, banks, etc.) and the Bank’s mission continued during private investment
promotion days in the Kara region, held on 5 and 6 April 2018 by the Chamber of Commerce
and Industry of Togo (CCIT) and the National Council of Employers (CNP). Targeted meetings
were held with the private sector, including with the Kalyan Group, which has applied for a loan
from the Bank’s private sector window to finance its planned investments in the Agro-park for
sesame and cashew nuts. Several meetings were also held with TFPs including the World Bank,
the French Development Agency, GIZ, UNIDO and FAO. At the local level, the people and local
chiefs were involved and their expectations on major issues have been addressed including the
issue of compensation for impacted persons. Awareness and information campaigns for various
social groups (men, women and young people) were conducted throughout the project
formulation process.
2.6.2 The consultation momentum that emerged during the project preparation phase will be
maintained during the implementation phase through: (i) an APRODAT steering entity comprising
representatives of major stakeholders (including the private sector and civil society); (ii)
technical assistance to strengthen the APRODAT; (iii) participatory approach selected for the
implementation of activities to be funded by, among others, the Saemaul Foundation; (iv) the
results-based and project impact monitoring and evaluation mechanism; and (v) joint supervision
missions. Special efforts will be made during project implementation to ensure that women
participate in all forms of consultation undertaken under the project.
2.7 Bank Group Experience and Lessons Reflected in Project Design
2.7.1 The current portfolio consists of 13 operations for a total commitment of UA 212.71
million spread across ten national operations of UA 102.81 million (48.33%) and three
multinational operations of UA 109.90 million (67.88%). The main sectors are transport
(75.55%), economic and financial governance (13.88%), and the social sector (8.77%). The
portfolio’s performance is deemed satisfactory, with an average age of two years (more than
50% of the projects approved between 2015 and 2017). The conditions precedent to the first
disbursement under the loan and grant agreements were fulfilled in time for all the
portfolio’s projects.
2.7.2 The CSP 2011-2015 completion report shows that implementation of the Bank’s
assistance strategy is positive overall. The two regional road projects helped to create 5,000
temporary jobs and 750 permanent jobs and improve traffic flow through a fivefold reduction in
travel times in some large cities. The Bank’s support in governance enabled the Government to:
(i) operationalise the Court of Auditors; (ii) produce management accounts by the Public
Treasury; (iii) improve the public procurement process; (iv) adopt trade and transport facilitation
measures: and (v) establish the Togolese Revenue Board.
2.7.3 Lessons learned from the implementation of the previous CSP, the IDEV long-term
evaluation report (sixth selectivity criterion) and periodic reviews of the CSP brought to light
recurring difficulties relating to counterpart resource mobilisation, slow pace of the procurement
13
process, disbursement red tape, and weaknesses in quality-at-entry of operations. Several project
design measures were therefore taken, including: (i) mobilisation of PPF resources to finance the
feasibility studies; (ii) allocation of an amount of CFAF 206 million in the State budget for 2018;
(iii) signing of a decree establishing the APRODAT and appointing the Board of Directors; (iv)
use of advance procurement action; (v) inclusion of poor people (including women) and
protection of the environment; and (vi) synergy of inter-sector interventions (energy, transport,
water, telecommunication).
2.7.4 The measures that have been taken into account in the project’s design, with a view to
accelerating its implementation, are as follows: (i) mobilisation of PPF resources to finance
feasibility studies (development of the Agro-park, dams and irrigation schemes, rural roads,
DWS) and the preparation study; (ii) the establishment, since December, of a Preparation
Monitoring Committee co-chaired by the Bank's Office and the Office of the Prime Minister,
which meets weekly; (iii) inclusion of an amount of CFAF 206 million in the 2018 State budget;
(iv) signing of the Decree establishing APRODAT and the appointment of members of the Board
of Directors and the acting Director General of the Agency; and (v) use of advance procurement
(including for the recruitment of project staff); (vi) ongoing appraisal of a financing request
submitted by the main private investor (Kalyan Group) (vii) inclusion of destitute populations
(including women) and environmental protection through SESA and (viii) synergy of inter-sector
interventions (energy, transport, water, telecom).
2.8 Key Performance Indicators
2.8.1 The key performance indicators such as those presented in the project’s logical
framework are the following: Impact indicators (i) level of household food security; (ii) value of
food imports per capita; (iii) percentage of the population living below the poverty line (less than
USD 1.90/day) (iv) percentage of children suffering from chronic malnutrition (including girls);
Output indicators: (i) share of agricultural production from the region processed in situ; (ii)
number of direct and indirect jobs created/strengthened (including 50% women); (iii) trend of
yields of priority sub-sectors (rice, maize, soybean, sesame, cashew nuts); (iv) rate of household
access to basic social services (electricity, roads); (v) Volume of private investment catalysed in
agribusiness in the Kara region; Output indicators: (i) % of partner FI portfolios invested in
agriculture by Banks and MFIs; (ii) Number of dams constructed (capacity in m3); (iii) Number
of ATCs built and strengthened; (iv) Number of km of rehabilitated roads; (v) Financing volume
mobilised by the private sector; (vi) level of people’s access to a civil status document (including
70% women).
III. PROJECT FEASIBILITY
3.1 Economic and Financial Performance
3.1.1 The project is designed to generate a minimum of eight (8) types of benefits:
(i) increased value added of cashew nuts by boosting their productivity from about 36.8 kg/tree
to about 73.5 kg/tree, representing a yield improvement from 368 kg/hectare to 735 kg/hectare;
for an area of 3,027 hectares (including new trees covering 1,500 hectares), production is likely
to reach 2,229 tonnes/year; (ii) processing of cashew nuts into higher value-added products such
as almonds, cashew nut juice and biogas; (iii) additional farm products from sesame and
soybean; (iv) enhancement of most of the agricultural production benefitting from the facilities
and climate regulation function of forest cover created by cashew trees, particularly for rice and
maize; (v) improvement of the people’s welfare by preventing drought and hunger, boosting
food security, reducing labour insecurity for families and in particular for women and vulnerable
14
groups, improving the people’s life expectancy, increasing their income to allow them to have
access to health care and education, etc.; (vi) improvement of animal production and livestock
breeding owing to the quality and abundance of pasture and water; (vii) effects of carbon
sequestration (carbon credit); and (viii) creation of temporary and permanent jobs resulting from
the benefits generated by the project.
3.1.2 Financial Analysis: A significant part of the impacts listed above are not subject to
commercial transactions, or are not even tangible and, therefore, do not lend themselves to
financial performance analysis, based on existing markets. Under these conditions, it was not
deemed relevant to include them in a quantitative analysis, based on the production model or
income-generating-activity approach. Nonetheless, it was possible to carry out a FARMOD
analysis based on the following five (5) models: (i) cashew nut production; (ii) rice production
resulting from the development of the Agro-park; (iii) maize production; and (iv) soybean
production.
3.1.3 In light of the above, the financial analysis related to the dividends from agricultural
production was conducted for the cashew nut production and processing models, as well as for
the crops mentioned above. The operation cycle is 25 years.
3.1.4 The financial analysis led to the following results: (i) a financial impact of about CFAF
4.45 billion per year as of the fourth year of operation projected over 25 years, in line with
similar operations, depending on the lifespan of the investments; this means that the financial
dividends from the project over the operating period exceed the cost of investment needed for its
financing; (ii) a cost/benefit ratio of 1.48, meaning that the benefits are higher than the cost of
investments; (iii) an internal rate of return of 23.84%, which is higher than the capital
opportunity cost (capital cost of financial resources for investments under the project) estimated
at 12%. Based on these results, it can be concluded that Togo’s PTAT has a rate-of-return
profile that offers a financial justification for the cost of the project’s investments.
3.1.5 Economic Analysis: The economic analysis was conducted using the reference price
method, namely prices under economic efficiency conditions, in accordance with the “Pareto”
optimum criterion. It was also conducted based on a comparison between the “without project”
and the “with project” scenarios of the production models discussed in the financial analysis. In
this model, cashew nuts were considered a tradeable commodity, meaning that they could be
traded outside the country (FOB delivery at the port and CIF delivery at the Hamburg Port).
Under these conditions, the reference price of cashew kernels (economic price) is evaluated
based on the ex-ante balance of this crop to obtain the export-parity farm gate price. Labour was
estimated at 65% of its financial value of CFAF 1,000/day, considering the inelasticity of
demand for labour in the country as a whole and in the project area in particular.
3.1.6 Based on realistically defined assumptions, the project’s economic rate of return is
estimated at 23.91%, with a cost/benefit ratio of 2.14. Consequently, the overall rate of return of the
project may be deemed satisfactory in light of these results.
3.1.7 Sensitivity Analysis: The sensitivity tests conducted based on a reduction in production
prices helped to measure the stability of the financial and economic performance indicators. The
tests show that prices will have to be reduced to 27.20% (profitability threshold) to offset the
additional financial and economic benefits generated at the financial and economic levels
respectively, with the IRR and ERR equivalent to the opportunity cost of capital, or 12%. This
test shows that the project’s rate of return is robust, although it was not performed on all
endogenous values of the model. Nonetheless, the price variable is more significant, being the only
15
variable that is not subject to the management, and hence operation, of the project. A summary of
the sensitivity analysis is presented in the annex to the report.
3.2 Environmental and Social Impact
3.2.1 Environment
3.2.1.1 In accordance with the requirements of the Integrated Safeguards System (ISS), the
project was classified in Category 1, considering the scope of its environmental and social
impacts. A strategic environmental and social assessment (SESA) was conducted to ensure that
the incidence of the future activities carried out in the project area are already taken into account
and possible mitigation measures have been identified. The SESA was approved by the Togo
National Environmental Management Agency (ANGE) on 23 February 2018. A summary of the
study was published on the AfDB website on 27 February 2018.
3.2.1.2 The SESA will be implemented taking into account the AfDB and BOAD safeguards
policies and will be in conformity with the environmental laws of the Republic of Togo for each
activity to be developed on the site. In that regard, environmental and social impact assessments
(ESIAs), resettlement action plans (RAPs) and pest and pesticide management plans (PPMPs)
are being prepared to study in more detail the impact of the Agro-park infrastructure, the
infrastructure of the production area (dams, rural roads, irrigated areas, developed lowlands and
social infrastructure), and the electricity and telecommunication line.
Positive Environmental Impacts
3.2.1.3 From an environmental standpoint, the project will contribute to: (i) improved control
of water resources in the three agricultural zones (water-fed, lowlands and irrigated) and of their
availability throughout the year (thanks to mini-dams, among other things); (ii) flood risk
management (effects on flooding); (iii) creation of wet zones conducive to the development of
biodiversity; (iv) restoration of the plant cover of the hills located near the facilities and
protection of the natural habitats and banks of the water courses on which dams are built; and
(v) development of the biomass through the production of steam or any other type of energy
from agricultural by-products (cashew nut shells, etc.).
Negative Environmental Impacts
3.2.1.4 The SESA revealed the most significant negative impacts that might be generated
during construction and operation of the project, namely: (i) loss of biodiversity; (ii) ecological
fragmentation; (iii) disruption of fish habitats; (iv) degradation of air quality; (v) greenhouse gas
emissions; (vi) water pollution; (vii) soil pollution through the contamination of chemical inputs;
and (viii) production of solid waste and waste water. Several mitigation measures have been
proposed to contain the negative impacts, including standard measures to be implemented during
construction of infrastructure (watering, compensatory reforestation, awareness-raising, waste
management plan, etc.) and specific measures to be taken during the operation phase. The SESA
has established appropriate lists of mitigation measures as well as occupational health and safety
measures for each product line. For each specific impact assessment to come, a detailed
Environmental and Social Management Plan (ESMP) will be prepared based on these
indications. A social and environmental management plan (ESMP) will also be developed to
promote the provision of resources and the establishment of a framework conducive to the
identification, management and monitoring of the project’s impacts, while observing the Bank’s
safeguards measures.
16
3.2.2 Social
Positive Social Impacts and Enhancement Measures
3.2.2.1 At the local level, the beneficial effects of the PTA relate to: (i) development of
intensive agricultural activities in the project area; (ii) creation of direct and indirect jobs,
especially for young people; (iii) technical education for farmers through training and
internships; (iv) development of the primary sector (livestock farming, agriculture, fishery, etc.);
(v) opening-up of the main production centres; (vi) strengthening of means of transport
(production roads) and means of storage (stores); (vii) increase in gross income per farmer; and
(viii) increase in the people’s purchasing power as a result of improved nutritional intake and
living conditions of households. At the national level, the project will help to boost food
production, especially rice production, and reduce rice imports.
3.2.2.2 Enhancement measures have been built into the PTA. The project will support the
construction of social infrastructure to improve the people’s living conditions through: (i) the
conduct of comprehensive studies on the establishment and rehabilitation of mini-drinking water
supply (DWS) systems; (ii) long-term electrification of village centres; (iii) implementation of
various activities to build the capacities and facilities of the 10 village centres; and (v)
installation of 5,000 improved fireplaces, and reforestation.
Negative Social Impacts
3.2.2.3 The major social, economic, security and health impacts are as follows: (i) physical or
economic displacements; (ii) loss of tangible and intangible cultural heritage, (iii) nuisances such
as noise and dust during construction work; (iv) increase in the incidence of endemic, parasitic,
water-borne and sexually transmitted diseases; (v) increased risks of accident during construction
works: (vi) social disturbances and conflicts due to a population influx and deepening of social
disparities; and (vii) increased competition for the use of resources. Just like for the
environmental impacts, mitigation measures have been proposed to manage the negative social
impacts. These measures involve compensation for the affected population, education on health,
security and work schedules, supply of individual protective equipment (IPE), arrangement of
work schedules and detour routes, etc. These measures will be included and explained in detail in
the Environmental and Social Management Plan (ESMP) of upcoming impact assessments. The
Environmental and Social Management Master Plan (ESMMP) includes strategic measures for
the management of social and environmental impacts.
3.2.3 Environmental and Social Management Master Plan
3.2.3.1 SESA provides for strategic environmental and social measures to create a framework
for identifying, managing and monitoring project impacts. These measures concern: (i)
strengthening the political, institutional, environmental and social framework (implementing
texts dealing with the SESA); (ii) sound knowledge of the area (baseline situation); (iii)
management of natural resources; (iv) surveillance, monitoring and evaluation; and (v) training
of actors involved in environmental and social management and education of the people. The
implementation of these measures will be supported by the APRODAT and the relevant State
entities. Implementation of the ESMMP will be under the responsibility of the APRODAT,
which will recruit an Environmental Expert and a Social Development Expert. The
implementation of the ESMMP will be monitored by various technical services under the
coordination of the ANGE. The total cost of the environmental and social strategic measures is
CFAF 486,000,000, which has already been taken into account.
17
3.2.4 Involuntary Resettlement
3.2.4.1 Resettlement action plans are being prepared for the Agro-park and rural infrastructure.
Based on the estimate of land area that will be affected and the value of the land in the area, a
provision of CFAF 800 million has been set aside to compensate affected persons. A
resettlement master plan will also be prepared as part of the project. Although it is not a tool
proposed by the Bank’s ISS, the resettlement policy framework (RPF) is required as a
precaution, to specify the procedure by which land that is not currently affected by the project
will be developed subsequently.
3.2.5 Climate Change
3.2.5.1 Togo and the Kara region are facing severe deforestation related to tree-cutting for
farming and alternative income-generation needs. The rate of deforestation is about 15,000
hectares/year, compared with a reforestation rate barely exceeding 3,000 hectares/year. This
situation exacerbates the problem of climate change by depleting carbon stock. The PTA also has
the potential to contribute to greenhouse gas emissions, owing to tree-cutting for the farmland
development, rice production and building of dams.
The PTA economic model will help to strengthen climate resilience through less-carbon-emitting
activities throughout the agricultural production chains. These activities will involve: promotion
of diversified agro-ecological systems and application of green technologies for waste
management, as well as production of renewable energy that helps to reduce greenhouse gas
emissions. The potential impacts are the following: (i) reduction of deforestation; (ii) increase in
farmers’ incomes; (iii) enhanced food and nutrition security in the communities; (iv) soil
productivity; (v) waste management through organic composting; (vi) employment of women
and young people; (vii) use of improved, drought-resistant grains and seeds; and (viii) improved
management of water resources.
3.2.6 Gender
3.2.6.1 According to the 2010 general population census, the Togolese population comprised
48.6% men and 51.4% women, while the rural population, which lives essentially on agriculture,
comprises 48.8% men and 51.2% women. The project area is one of the poorest, with a fairly
visible impact on women and children. Women are involved in most of the product lines: rice,
soybean, sesame, maize. Land insecurity, access to improved seeds, equipment and markets to
sell their crops are major problems for women in the area.
3.2.6.2 The following measures and actions will be taken to boost the role of women and
maximize their contribution to the project: (i) grouping of women farmers by food product line
(rice, maize, soybean and sesame); (ii) allocation of at least 30% of developed land to groups of
women farmers; (iii) allocation of a 30% quota, at least, for women industrial promoters in the
CTA; (iv) facilitation of women’s access to modern agricultural production and processing
equipment: inputs (seeds, fertilizers and phytosanitary products), processing materials and
equipment (rice parboiling, maize husking); (v) building of the entrepreneurial capacities of
women’s groups in the production, storage, processing, packaging and marketing of agricultural
products; (vi) building of women’s capacities in business plan preparation, marketing and
networking for the market and access to financing; (vii) facilitation of access to basic services,
such as water and electricity; and (viii) facilitation of the process of obtaining civil status
documents, such as identification and nationality cards. The budget to be allocated for specific
gender promotion and women’s empowerment activities is UA 7.2 million. The project is
18
classified under category 2, according Gender Marker System. For a detailed gender analysis of
the entire value chain and the budget for implementation of the gender component, see Annex
B.7.
IV. PROJECT IMPLEMENTATION
4.1 Implementation Arrangements
4.1.0 The PTA-Togo will be implemented by the Agency for the Promotion and
Development Agropoles in Togo (APRODAT) which was established by Decree No. 2018-
036/PR of 27 February 2018 to steer the implementation of the Togo Agropoles Strategic
Development Plan. The Ministers responsible for Agriculture and Industry respectively will
provide joint supervision of APRODAT which has two organs: (i) a Board of Directors, chaired
by the Prime Minister, and comprised of seven active members (public and private) and observer
members, and (ii) a Directorate General (DG). The Board of Directors will meet quarterly to
review and approve the work programme and activity reports. The Directorate General to be set
up with project support will eventually comprise five Directorates: the Directorate of Legal,
Administrative and Financial Affairs, the Directorate of Forecasting, Planning, Monitoring and
Evaluation, the Directorate of the Promotion of Financing and Investments, the Directorate of
Facilities and Works Control and the Directorate of Training, Research and Development. A
team of experts will be recruited to build APRODAT's capacity, particularly in the
implementation of the PTA. This team, under the responsibility of the Director General, PTA
Coordinator, will include: an Administrative and Financial Officer, an Accountant, an Agro-
Industry Specialist, an Investment Specialist, a Monitoring and Evaluation Specialist, a
Procurement Specialist, a Rural Infrastructure Specialist, an Agronomist (Development), an
Environment and Social Specialist, a Social Development Specialist, a Legal Officer, an Internal
Auditor and Specialist in Organisation Management, Gender and Capacity Building. The PTA
implementation team will be supported by a Project Assistant and Drivers. Similarly, the Project
will support APRODAT in partially covering equipment and personnel costs and in setting up
the administrative, financial and accounting management system required for the project
financed by the Bank. In accordance with the provisions of the Presidential Decree establishing
APRODAT, the entity in charge of promoting and managing the Kara Agro-park will be
managed as a semi-public company involving the State and the private sector and will therefore
have administrative, financial and accounting management autonomy.
4.1.1 Procurement Arrangements
4.1.1.1 The procurement of goods (including non-consultancy services), works and
consultancy services, financed by the Bank as part of the project, will be carried out in
accordance with the Procurement Framework for Bank Group-Funded Operations, October
2015 edition and the provisions set out in the Financing Agreement. More specifically, the
procurements will be carried out as follows:
Borrower’s Procurement System (BPS): Procurement methods and procedures (PMP)
based on Togo's procurement system including its laws and implementing decrees (Law
No. 2009-013 of 30 June 2009 and implementing Decree No. 2009-277/PR of 11
November 2009 relating to the Public Procurement Code as well as its subsequent
implementing decrees and texts), based on standard national competitive bidding
documents (SNCBDs) or other bidding documents as approved during project
negotiations for works and low-complexity goods contracts provided for in the project
and generally available in Togo.
19
Bank Procurement Methods and Procedures (BPM): The Bank's standard BPM,
based on the relevant standard competitive bidding documents (SCBDs) for major and
more complex works and goods contracts, as well as consultancy services, deemed to be
the most appropriate. Given the delays in procurement and in order to limit their impact
on project implementation, the Government submitted to the Bank a request to use
advanced procurement action (APA) to make procurements for: (i) the recruitment of
APRODAT's key project implementation staff (Director General, Administrative and
Financial Officer, Accountant, Agribusiness Specialist, Investment Officer, Procurement
Specialist, Legal Officer And Internal Auditor, Specialist in Environmental and Social
Issues, Rural Infrastructure ,Specialist, Specialist in Organisation Management, Gender
and Capacity Building); (ii) procurement of APRODAT furniture and office equipment
provided for under the project; (iii) the recruitment of a consulting firm for the
development of a summary preliminary design and a detailed preliminary design of Agro-
Park facilities; and (iii) the recruitment of a consulting firm for the development of the
detailed preliminary designs for studies on small dams/irrigated areas and roads ; and (iv)
procurement of office furniture for APRODAT and the Kara Agro-Park Management
Company.
4.1.1.2 Procurement Risk and Capacity Assessment (PRCA): The assessment of country,
sector and project risks as well as of the capacity of the executing agency (EA) for procurement
purposes was conducted1 for the project and the outcomes served to guide the decision on the
choice of procurement system (Borrower or Bank) used for specific activities or for all similar
project activities. The Project Executing Agency is the Agency for the Promotion and
Development Agropoles in Togo (APRODAT) which is a public institution with legal
personality and management autonomy. It is under the joint supervision of the Ministries
responsible for Agriculture and Industry. APRODAT is not fully operational because only the
Board of Directors and the acting Director General have been appointed and therefore the
procurement risk is deemed "high". In fact, APRODAT does not yet have procurement bodies
(Procurement Officer, Public Procurement Board and Procurement Control Board), while staff
members have not yet been appointed or recruited, particularly the Procurement Specialist,
dedicated to the Project and having the required qualifications and experience. In order to reduce
the risk to "low", APRODAT will have to recruit a Procurement Specialist and set up
procurement bodies. Moreover, the Bank will finance technical assistance in which procurement
will be taken into consideration. The Borrower and the Bank will agree on a procurement plan
for the first 18 months of the Project, which will be updated annually or as needed, in order to
reflect the actual project implementation needs. Any revision of the plan will be subject to prior
approval by the Bank. Appropriate risk mitigation measures have been included in the PRCA
action plan outlined in paragraph B.5.9 of Annex B5.
4.1.2 Financial Management and Disbursement Arrangements
4.1.2.1 Established on 27 February 2018, APRODAT is in the process of being set up.
Whereas the Board of Directors which will act as the PTA Steering Committee has been
appointed pursuant to Decree No. 2018/036/PR of 27 February 2018, and its Chairman appointed
Acting Director General, it will be necessary to wait for the recruitment of financial management
staff and the establishment within APRODAT of an operational financial management system to
ensure full transparency, traceability and accountability in the use of PTA funds. To this end, the
Togolese Government will have to take the following actions:
1 See the Technical Annexes for more details
20
(i) Completion of the organisation chart in accordance with the principles of internal
oversight, particularly the separation of incompatible functions, and the appointment of
the heads of services making up the directorates mentioned in the Decree, especially
those of the directorates involved in the implementation of the SCPP (Administrative
and Financial Officer, Accountant, Procurement Officer, etc.);
(ii) Development of the administrative, financial and accounting procedures manual, on
which its internal oversight system will be based, covering all management cycles:
expenditure management cycle (procurement procedures for goods and services), asset
management cycle (fixed assets, inventories, etc.), cash management cycle (scheduling,
disbursement, cash monitoring and control, etc.), resource mobilisation cycle
(fundraising, direct payments, etc.), accounting, financial and budgetary information
cycle, personnel management cycle, control and internal audit cycle;
(iii) Development, where appropriate, of an operations manual for facilitation and financial
intermediation activities (access of processing units to financing);
(iv) Establishment of an integrated multi-project and multi-user management system to
ensure the keeping of budgetary, analytical and general budget accounts. General
accounting has to be a private accrual accounting system, applying the SYSCOHADA
standards and taking into account the specific features of development projects;
(v) Establishment of internal audit mechanisms, with the recruitment of an Internal Auditor
who will ensure that the SCPP control system is operational and effective; and
(vi) Establishment of external audit mechanisms through the hiring of independent external
auditors on a competitive basis and in accordance with the terms of reference agreed
with the Bank, in line with the Bank's requirement that audit reports be submitted no
later than 30 June of the year following the year audited.
4.1.2.2 Pending the establishment and operationalisation of APRODAT, the overall fiduciary
risk, incorporating the inherent risk and the risk of non-control resulting from the evaluation of
the agency’s financial management capacity, will remain high. Details are provided in the
Technical Annexes of the Appraisal Report.
4.1.2.3 Disbursements: Bank financing will be mobilised in accordance with the rules and
procedures of the Bank Disbursement Manual through the three disbursement methods: (i) direct
payment (for the procurement of works, goods and services and other relatively high-cost
expenditure...); (ii) the special account (mainly for operating expenditure); and (iii)
reimbursement, where appropriate.
4.2 Project Monitoring and Evaluation
4.2.1 Technical and Financial Monitoring. The Project Monitoring and Evaluation Officer
appointed from within the project management unit will be responsible for collecting, analysing
and compiling information on physical achievements and financial execution. For this purpose,
he/she will have a roadmap with quantitative indicators on Project progress, relating to
implementation of the sub-components. Such monitoring will make it possible to obtain, every
six months, the following information for each activity: physical objective, achievement level,
expected costs, actual costs, differences and explanations for possible deviations. This
information will be used to prepare the half-yearly project progress reports. Moreover, in
21
addition to the Steering Committee’s review work, the Bank will carry out two supervision
missions per year, to which should be added a mid-term review mission.
4.2.2 Impact Assessment. The Project impact assessment will be conducted through
participatory studies. The first step in this assessment will be the study of the baseline situation
which will aim at determining the level of the following indicators at Project year zero: (i)
current average household income; (ii) major crop yields (t/ha); (iii) current production levels;
(iv) industrial processing rates; (v) level of organisation of supply of inputs and delivery of
agricultural services (including mechanization and electronic payments); (vi) level of
organisation of marketing; and (vii) volume of funding mobilised. The same study will be
conducted at project completion based on the same sample.
4.3 Governance
4.3.1 According to the 2017 Mo Ibrahim Report on the Assessment of Global Governance in
Africa, Togo is ranked 26th out of 54 countries assessed (compared with 33rd in 2016) with a
score of 51.7 over 100. This relatively average ranking notwithstanding, Togo with an average
improvement of +10 points, is ranked 2nd best reforming country in governance over the period
2007-2016, behind Côte d'Ivoire (12.6), and ahead of Zimbabwe (+9.5) ), Rwanda (+8.7) and
Liberia (+6.5). In 2016, it was the only country whose global governance had steadily improved
with progress in each of the 14 sub-categories of the IIAG. With regard to corruption perception,
the 2017 Transparency International Report ranks Togo 117th out of 180 with a Corruption
Perception Index (CPI) of 32 compared with 29 in 2014, on a scale of 0 (high corruption) to 100
(very low corruption).
4.3.2 In order to support the ongoing reform momentum in the country and foster good
governance, the Bank, in close collaboration with the IMF and other partners, has regularly
maintained sustained policy dialogue with the Togolese authorities through reform and
institutional support operations. In 2017, the Bank approved budget support totalling UA 9.53
million for the Governance and Agribusiness Promotion Support Programme (PAGPA), which
focuses on reforms aimed not only at creating an enabling environment for private and public
investments for the promotion of agribusiness but also at improving revenue mobilisation to
enhance investment expenditure. The government has undertaken significant strategic and
structuring reforms as part of this reform support operation. These include (i) the revision and
adoption of the Land Code; (ii) preparation of the national agropoles development strategy; and
(iii) preparation and adoption of the private sector development strategy. Other major reform
measures planned for 2018 are underway, namely, the preparation and adoption of the country's
national industrialisation policy and strategy, as well as the issue of decrees on the organisation
and functioning of national entities responsible for quality, standards and metrology.
4.3.3 The SCPP, which is a continuation of PAGPA, will contribute to the improvement of
governance in the agricultural sector through the operationalisation of the major reforms
mentioned above as well as amendments to the institutional, legislative and regulatory
arrangements required for the development of Agro-Food Processing Zones (ZTAs). The Project
also includes a component to provide technical, methodological and material capacity building
for APRODAT, the agropoles governance and steering structure, the devolved administrative
services involved in staple crop promotion, private sector development as well as training
institutes.
4.3.4 Lastly, the activities planned, particularly through the Korean Saemaul Foundation, will
enhance project inclusiveness by involving the beneficiaries (including women and young
22
people) in the decision-making process. Specific actions are planned to build the people’s
capacity so that they can organise themselves in cooperatives, improve their agricultural
performance and interact with other actors (especially the private sector).
4.4 Sustainability
4.4.1 The project is in line with a sustainable development approach and its sustainability is
based on the fact that most of the activities to be financed were identified with the collaboration
of stakeholders. The participatory approach implemented during the project preparation phase,
with the State as "facilitator", the private sector as "investor", and the professional agricultural
organisations (PAOs) as "direct actors", should create the conditions for good sustainability of
project outputs and impacts. The key actors (producers, private sector, financial institutions, etc.)
of the six priority value chains (rice, maize, sesame, soybean, broiler chicken and cashew nuts)
were therefore consulted, particularly during the studies (Agro-park, water supply, irrigation,
roads, electricity, ICT, etc.) and their concerns were taken into account in the context of this
project.
4.4.2 The Project will help not only to improve the political, regulatory and institutional
framework for the establishment of planned Agro-Food Processing Zones (ZTAs), but also to
mobilise significant resources for the construction of basic infrastructure (roads, clean water,
sanitation, electricity, ICT, etc.) needed to encourage private investment, particularly within the
Agro-park. Such private sector (leader) involvement is the guarantee of easier access to markets
(national, regional and international), technology and financing (especially for PAOs and SMEs).
This public-private partnership is a key to the sustainability of the approach advocated by the
Project.
4.4.3 The various actions targeted by the project, such as capacity building for
entrepreneurial culture, business management and the organisational spirit of beneficiary groups,
are likely to foster inclusive growth. These effects will provide an additional guarantee for
sustainable achievements, while allowing continuation of the momentum ushered in beyond the
end of the project. Secondly, the technical assistance provided for under the project will have a
positive direct impact on the capacity of national institutions and PAOs to make optimum and
sustainable utilisation of the infrastructure put at their disposal. This initial activity will thus
enable each professional organisation to regularly generate resources capable of supporting the
identified activities and facilitate the implementation of other sub-projects that are likely to make
investments more profitable. This component is, therefore, essential to ensure the sustainability
of the actions.
4.4.4 Furthermore, with the complete modernisation of infrastructure, works and irrigation
equipment projected in the study reports, including the introduction of equipment and more
efficient varieties in water use, abstractions on already heavily reduced water resources will be
minimized. Lastly, for road maintenance, project will utilise the mechanisms already defined
under the current National Transport Strategy.
4.5 Risk Management
4.5.1 The main risks associated with the project implementation were identified their
potential impacts analysed and the mitigation measures specified (see table).
23
Risks Risk level Mitigation measures/actions
Risk 1: Land security measures are
insufficient to attract the private sector and
protect small farmers
Moderate
Mitigation 1: The SESA has identified mitigation
measures in the project, including the
implementing decrees of the new Land Code and
the establishment of single window for land tenure
in Kara
Risk 2: The significant benefits expected
from the project could be monopolised by a
minority
High
Mitigation 2: SESA (including RAP, and ESIMP,
PDC), and Saemaul Foundation participatory and
gender sensitive approach and nutrition of the will
have positive effects for the people
Risk 3: Climate change and harmful practices
of the people could degrade natural resources
(NR)
Moderate
Mitigation 3: IWRM and the development of
alternative livelihoods should sustainably enhance
the project effects
Risk 4: Lack of interest by the private sector
could limit investments planned in the Agro-
park
Moderate
Mitigation 4: (i) (i) Meetings were held with the
private sector (including Kalyan Group, key
investor) and their needs taken into account; (ii) the
Project will finance infrastructure for the
development of agro-parks and production areas;
(iii) support for the implementation of NP reforms
is planned (land security, standardization and
quality control, PPP, etc.); and (ii) technical
assistance (including legal, technical, management,
PPP etc.) will be made available to APRODAT
Risk 5: Delays in project implementation due
to poor knowledge of Bank procedures by
APRODAT
High
Mitigation 5: Substantial institutional support (see
action plans) for APRODAT is envisaged under the
project
Risk 6: The significant benefits expected
from the project could be monopolised by a
minority
Moderate
Mitigation 6: The SESA provides for the
implementation of actions (Population
Resettlement Action Plan, ESIMP and PDC) that
will have positive impacts on the people
4.6 Knowledge Building
4.6.1 This Project differs from those conventionally financed in Togo by the Bank, mainly
because of the following innovations: the development of public-private partnership in the agro-
industrial sector to finance all the needs of competitive sectors. Through documented monitoring
and evaluation of the innovations, lessons learned by the State, the private sector (agribusiness,
banks, etc.) and consultation frameworks from priority sectors will be drawn. These lessons
learned will not only be taken into consideration by APRODAT but will also be used by the
Bank in experience sharing between the regional member countries. At the end of the project, the
lessons learned will be consolidated in the completion report.
V. LEGAL FRAMEWORK
5.1 Legal Instrument
5.1.1 The project will be financed through an ADF grant of UA 4.635 million (including the
PPF refund of UA 995,000), an ADF loan of UA 8.04 million from the country allocation, and a
TSF loan (pillar 1) of UA 8.32 million.
24
5.2 Conditions for Bank Involvement
5.2.1 The ADF and TSF loans and the ADF grant will be subject to the following conditions:
Conditions precedent to effectiveness:
a) The effectiveness of the ADF and TSF Loan and Grant Agreements will be subject to
the fulfilment by the Borrower, to the satisfaction of the Fund, of the conditions set
forth in Section 12.01 of the General Conditions applicable to Loan, Guarantee and
Grant Agreements of the African Development Fund as may be amended periodically.
b) ADF Grant: The effectiveness of the ADF Grant shall be subject to its signature by the
Donee and the Fund and in according accordance with the provisions of the General
Conditions Applicable to the Grant Agreement of the Fund as may be amended
periodically.
Conditions precedent to first disbursement
a) Loan and Grant: In addition to effectiveness of the ADF and TSF Loan Agreements and
the ADF Grant Agreement, the disbursement of the loan and grant resources shall be
subject to fulfilment, by the Borrower, and to the satisfaction of the Fund, of the
following conditions:
b) Provide the Fund with evidence of the completion of the Executing Agency's
organisational chart and the filling of positions of responsibility, including the positions of
Directors and Service Heads, Procurement, Financial Management, Accounting, Internal
Audit and Monitoring and Evaluation Officers.
Special Conditions Precedent to the Disbursement of Loan and Grant Resources for Works
Involving Expropriation
a) Loan and Grant: In addition to effectiveness of the ADF and TSF Loan Agreements and
the ADF Grant Agreement and fulfilment of the conditions precedent to first disbursement,
the disbursement of the loan and grant resources for works involving expropriation shall be
subject to fulfilment, by the Borrower, and to the satisfaction of the Fund, of the following
conditions
b) Submit to the Fund the reports of environmental and social studies (Environmental and
Social Impact Assessment, Environmental and Social Management Plan, Populations
Resettlement Action Plan and Pests and Pesticides Management Plans) of the Agro-park
and rural infrastructure approved by the National Agency for Environmental
Management (ANGE); and
c) Provide, as work progresses, and before any work begins on an area concerned,
evidence of compensation and/or resettlement of project persons affected in that area, in
accordance with the ESMP and the Resettlement Framework Plan (RFP) and the
relevant African Development Bank Group rules and procedures, in particular the
Involuntary Resettlement Policy and its Integrated Safeguards System. It is specified
that when this compensation or resettlement is not possible, either totally or partially,
due to the impossibility of identifying the beneficiaries or in the event of litigation or
other impossibility beyond the Borrower’s control duly justified and acceptable to the
Fund (hereinafter referred to as "Contentious Cases"), the condition may be deemed to
25
be fulfilled if the Borrower provides evidence that the resources allocated to the
compensation and/or the resettlement of the Contentious Cases are deposited in a bank
account acceptable to the Fund specifically earmarked for such compensation and/or
resettlement, or remitted to and deposited with a trustworthy third party acceptable to
the Fund.
Other Conditions
a) ADF and TSF Loans: The Borrower undertakes, to the satisfaction of the Fund, to:
i). Provide, prior to the request for disbursement of ADF and TSF loan resources in
special accounts, evidence of the opening by the Executing Agency of a special
ADF account and a special TSF account, in the name of the Project, with a bank
acceptable to the Fund, intended to receive the resources of each loan.
b) ADF Grant: The Donee undertakes, to the satisfaction of the Fund, to:
i). Provide, prior to the request for disbursement of Grant resources in the special
account, evidence of the opening by the Executing Agency of a special account, in
the name of the Project, with a bank acceptable to the Fund, intended to receive
the resources of the Grant.
Commitments: The Borrower undertakes, to the satisfaction of the Fund, to:
(i) prepare and forward to the Fund for opinion, no later than four (4) months after
effectiveness of the ADF and TSF Loan Agreements and the Grant Agreement,
for opinion, the Administrative, Financial and Accounting Procedures Manual, the
basis of its internal control system, covering all management cycles: expenditure
management (procedures for the procurement of goods and services), asset
management (fixed assets, inventories, etc.), cash flow management
(authorisation, disbursement, monitoring and control of cash flow, etc.), resource
mobilisation (requests for transfer of funds, direct payments, etc.), accounting,
financial and budgetary information, personnel management, control and internal
audit cycle;
(ii) prepare [no later than twelve (12) months after effectiveness of the ADF and TSF
Loan Agreement] an operations manual for financial facilitation and
intermediation activities in view of access to financing by processing units;
(iii) set up an integrated multi-project and multi-post management system to ensure
that the budgetary, cost and general accounting modules of the Project are kept in
accordance with the financial management rules for Fund-financed projects;
(iv) set up internal audit mechanisms, with the recruitment of an internal auditor who
will ensure that the Project's control system is operational and effective;
(v) implement the Project and have it implemented by the Executing Agency and its
contractors in accordance with : (a) the relevant rules and procedures of the Fund;
(b) national law; and (c) the recommendations, requirements and procedures
contained in the ESMP;
26
(vi) not to commence work in a given area without the project-affected persons in
that area having been fully compensated in accordance with Section 4.03
paragraph ii) above; and
(vii) provide the Fund with half-yearly reports on ESMP implementation, including
any shortcomings and corrective actions initiated or to be initiated, and any
documents reasonably necessary for monitoring the Project’s implementation.
5.3 Compliance with Bank Policies
5.3.1 The Project will contribute to three of the Bank's High-Fives, namely: (i) "Feed
Africa"; (ii) "Industrialise Africa"; and (iii) "Improve the quality of life for the people of Africa".
It is also consistent with the Bank's environmental and social management policies, guidelines
and procedures.
VI. RECOMMENDATION
6.1 Bank Management recommends that the Board of Directors should approve an ADF
grant of UA 4.635 million (including the PPF refund of UA 995,000), an ADF loan of UA
8.04 million under the country allocation and a TSF loan (pillar 1) of UA 8.32 million to the
Togolese Republic for the purpose and under the conditions set out in this report.
I
Appendix I: Togo’s Comparative Socio-economic Indicators
Year Togo Africa
Develo-
ping
Countries
Develo-
ped
Countries
Basic Indicators
Area ( '000 Km²) 2017 57 30,067 80,386 53,939Total Population (millions) 2017 7.7 1,184.5 5,945.0 1,401.5Urban Population (% of Total) 2017 40.1 39.7 47.0 80.7Population Density (per Km²) 2017 141.4 40.3 78.5 25.4GNI per Capita (US $) 2016 540 2 045 4 226 38 317Labor Force Participation *- Total (%) 2017 81.0 66.3 67.7 72.0Labor Force Participation **- Female (%) 2017 81.0 56.5 53.0 64.5Sex Ratio (per 100 female) 2017 97.9 0.801 0.506 0.792Human Dev elop. Index (Rank among 187 countries) 2015 166 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2015 49.1 39.6 17.0 ...
Demographic Indicators
Population Grow th Rate - Total (%) 2017 2.6 2.6 1.3 0.6Population Grow th Rate - Urban (%) 2017 3.7 3.6 2.6 0.8Population < 15 y ears (%) 2017 41.8 41.0 28.3 17.3Population 15-24 y ears (%) 2017 19.4 3.5 6.2 16.0Population >= 65 y ears (%) 2017 2.8 80.1 54.6 50.5Dependency Ratio (%) 2017 80.6 100.1 102.8 97.4Female Population 15-49 y ears (% of total population) 2017 24.5 24.0 25.8 23.0Life Ex pectancy at Birth - Total (y ears) 2017 61.0 61.2 68.9 79.1Life Ex pectancy at Birth - Female (y ears) 2017 61.7 62.6 70.8 82.1Crude Birth Rate (per 1,000) 2017 34.1 34.8 21.0 11.6Crude Death Rate (per 1,000) 2017 8.3 9.3 7.7 8.8Infant Mortality Rate (per 1,000) 2016 50.7 52.2 35.2 5.8Child Mortality Rate (per 1,000) 2016 75.7 75.5 47.3 6.8Total Fertility Rate (per w oman) 2017 4.4 4.6 2.6 1.7Maternal Mortality Rate (per 100,000) 2015 368.0 411.3 230.0 22.0Women Using Contraception (%) 2017 22.2 35.3 62.1 ...
Health & Nutrition Indicators
Phy sicians (per 100,000 people) 2008 5.8 46.9 118.1 308.0Nurses and midw iv es (per 100,000 people) 2008 30.0 133.4 202.9 857.4Births attended by Trained Health Personnel (%) 2014 44.6 50.6 67.7 ...Access to Safe Water (% of Population) 2015 63.1 71.6 89.1 99.0Access to Sanitation (% of Population) 2015 11.6 51.3 57 69Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2016 2.1 39.4 60.8 96.3Incidence of Tuberculosis (per 100,000) 2016 46.0 3.8 1.2 ...Child Immunization Against Tuberculosis (%) 2016 79.0 245.9 149.0 22.0Child Immunization Against Measles (%) 2016 87.0 84.1 90.0 ...Underw eight Children (% of children under 5 y ears) 2014 16.2 76.0 82.7 93.9Prev alence of stunding 2014 27.5 20.8 17.0 0.9Prev alence of undernourishment (% of pop.) 2015 11.5 2 621 2 335 3 416Public Ex penditure on Health (as % of GDP) 2014 2.0 2.7 3.1 7.3
Education Indicators
Gross Enrolment Ratio (%)
Primary School - Total 2016 123.9 106.4 109.4 101.3 Primary School - Female 2016 120.8 102.6 107.6 101.1 Secondary School - Total 2011 55.1 54.6 69.0 100.2 Secondary School - Female 2007 30.7 51.4 67.7 99.9Primary School Female Teaching Staff (% of Total) 2016 16.2 45.1 58.1 81.6Adult literacy Rate - Total (%) 2015 63.7 61.8 80.4 99.2Adult literacy Rate - Male (%) 2015 77.3 70.7 85.9 99.3Adult literacy Rate - Female (%) 2015 51.2 53.4 75.2 99.0Percentage of GDP Spent on Education 2016 5.1 5.3 4.3 5.5
Environmental Indicators
Land Use (Arable Land as % of Total Land Area) 2015 48.7 8.6 11.9 9.4Agricultural Land (as % of land area) 2015 70.2 43.2 43.4 30.0Forest (As % of Land Area) 2015 3.5 23.3 28.0 34.5Per Capita CO2 Emissions (metric tons) 2014 0.4 1.1 3.0 11.6
Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :
UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.
Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)
** Labor force participation rate, female (% of female population ages 15+)
TogoCOMPARATIVE SOCIO-ECONOMIC INDICATORS
May 2018
0
10
20
30
40
50
60
70
80
90
100
20
00
20
05
20
10
20
11
20
12
20
13
20
14
20
15
20
16
Infant Mortality Rate( Per 1000 )
Togo Africa
0
500
1000
1500
2000
2500
20
00
20
05
20
10
20
11
20
12
20
13
20
14
20
15
20
16
GNI Per Capita US $
Togo Africa
2.3
2.4
2.4
2.5
2.5
2.6
2.6
2.7
2.7
2.8
2.8
20
00
20
05
20
10
20
12
20
13
20
14
20
15
20
16
20
17
Population Growth Rate (%)
Togo Africa
01020304050607080
20
00
20
05
20
10
20
12
20
13
20
14
20
15
20
16
20
17
Life Expectancy at Birth (years)
Togo Africa
II
Appendix II: Current Bank Portfolio in Togo
Sect. Project Name
Share
Commit
(%)
Window
Approval
Date
Amount
Disbursed
Amount
Approved
Disburs
Rate
(%)
Wa
ter
&
Sa
nit
at.
Toilets for all in Sokodé through the valorisation
of faecal sludge AWF 19/04/2013 860 540 1 003 905 85 .72
Sub-Total - Water and Sanitation 0.6% 860 540 1 003 905 85.72
Ag
ricu
ltu
re
PPF- Agropoles Development Project
ADF 29/02/2016 762 950 995 000 76.68
Sub-Total - Agriculture 0.6% 762 950 995 000 76.68
Go
ver
na
nce
Resource Mobilisation and Institutional Capacity
Building Support Project (PAMOCI) TSF 09/10/2014 2 970 136 5 000 000 59.40
Tax Governance Support Project (PAGFI) TSF 17/02/2016 580 492 3 080 000 18.85
TSF 17/02/2016 2 309 346 11 920 000 19.37
Governance and Agribusiness Promotion Support
Programme
05/12/2017 2 320 000 2 320 000 100.00
05/12/2017 7 210 000 7 210 000 100.00
Sub-Total - Governance 18.2% 15 389 974 29 530 000 52.12
So
cia
l
Kara and Lomé Markets Reconstruction and
Traders Support Project
ADF 22/01/2014 1 015 852 1 930 000 52.63
ADF 22/01/2014 855 893 1 650 000 51.87
FAPA- Market Reconstruction Support Project FAPA 26/01/2015 539 652 561 771 96.06
Youth Employability and Integration Support
Project
ADF 28/10/2015 593 914 6 670 000 8.90
NTF 28/10/2015 654 655 6 500 000 10.07
TSF 28/10/2015 31 754 1 330 000 2.39
Sub-Total - Social 11.5% 3 691 720 18 641 771 19.80
En
erg
y Pilot Phase of the Rural Electrification
Programme CIZO SEFA 08/08/2017 0 684 629 0.00
Total - Energy 0.4% 0 684 629 0.00
Fin
an
ce Project to Support the Financial Inclusion of
Vulnerable Women (PAIFFV) TSF 22/08/2016 512 357 1 152 173 44.47
Sub-Total - Finance 0.7% 512 357 1 152 173 44.47
Total - National 24.4% 21 217 541 52 007 478 40.80
Tra
nsp
ort
Mu
ltin
ati
on
als
Benin/Togo: Project to Rehabilitate the Lomé -
Cotonou Road and Facilitate Transport on The
Abidjan-Lagos Corridor – Phase 1
ADF 05/10/2011 1 587 374 4 810 000 33.00
Togo/Burkina Faso Road Rehabilitation and
Transport Facilitation on the Lomé-Ouagadougou
CU9 Corridor
ADF 27/06/2012 15 082 941 17 800 000 84.74
ADF 27/06/2012 23 168 917 30 230 000 76.64
TSF 27/06/2012 15 648 435 21 500 000 72.78
EU-AITF 23/02/2015 922 956 991 198 93.12
Benin/Togo: Lomé-Cotonou Road Rehabilitation
(Phase 2) and Coastal Protection Project
ADF 16/12/2016 96 118 9 000 000 1.07
ADF 16/12/2016 0 930 000 0.00
GEF 16/12/2016 0 6 303 265 0.00
TSF 16/12/2016 0 18 350 000 0.00
TSF 16/12/2016 0 30 000 0.00
Sub-Total - Transport 67.9% 56 506 740 109 944 463 51.40
Total - Multinationals 67.9% 56 506 740 109 944 463 51.40
Total - Public Sector 76.1% 77 724 281 161 951 941 47.99
Pri
va
te
Sec
tor
Container Terminal AfDB 15/07/2011 36 005 049 36 005 049 100.00
Container Terminal (Priv. Sect. Credit Enhance
Facility) 75.6% AfDB 04/11/2015 0 14 852 083 0.00
Sub-Total – Non-Sovereign 23.9% 36 005 049 50 857 132 70.80
GRAND TOTAL 100.0% 113 729 331 212 809 073 53.44
III
Appendix III: An Analysis of Togo's Fragility
Fragility factors
identified by the
fragility
assessment
The situation, challenges and resilience measures supported by
General State Policy with assistance from Technical and
Financial Partners (TFPs)
Measures supported by
African Development
Bank intervention under
PTA-Togo (2018-2023)
Political,
institutional and
security-related
factors
1. Legitimate policies and political governance (legitimacy, inclusivity, consolidation of the
State and trust in its institutions)
Legitimacy: Togo has made significant progress which has
undoubtedly set the country on the path to achieving long-lasting resilience. Its achievements to date include increased security and
stability, an economic recovery which has seen average growth rates
of 5% during a ten-year period, the implementation of major institutional and economic reforms, a return to stability, the
strengthening of social cohesion and enhanced regional
cooperation. The TFPs continue to largely commend the Togolese Government for its efforts to rebuild its infrastructure and revive the
country's economy since cooperation resumed in 2006. Yet, despite these improvements, the process of reconstruction following the
political and democratic crisis is far from complete. Beginning in
August 2017, the country once again witnessed a series of political demonstrations calling for a return to the country’s constitution of
1992 that limited the number of presidential terms of office to two. The draft law excluding key provisions on retroactive application
were rejected by the opposition, hence a referendum will be held in
order to separate the two parties, who agreed to take part in negotiations in February 2018 under the supervision of the
President of Ghana, Nana Akufo-Addo. In addition, ethnic and
regional polarisations between the North and South of the country continue to undermine its political stability, and underpin the
entrenched political splits between Togo's political figures. The relative slow pace of democratic transition and the weakness of the
country's institutions are major challenges for political governance
in Togo. This has aggravated the mutual mistrust that exists between the dominant coalitions and led to poor ownership of sustainable
mechanisms for respectful, inclusive and constructive dialogue within the political class and between the elite.
PTA proposes a series of
initiatives designed to improve the legal,
regulatory and institutional
framework for a number of sectoral policies, in order
to in turn improve
economic governance and the transparency of
government action. The introduction of a new Land
Code addresses the issue of
institutional credibility and trust systematically, in
order to improve certain pockets of fragility detected
in political governance.
The consultation
frameworks including
traditional leaders and NGOs strengthen the local
ownership and inclusion process.
Governance: Togo has taken a number of steps to improve its
situation. This process, coordinated by the Permanent Secretariat for Reforms, has enabled several relevant texts to be drafted; these
include a public procurement code, documents on the
operationalisation of the Court of Auditors, the General
Inspectorate of Finance, the creation of a Treasury one-stop service
and the production of reports on the budget review law. Both centrally and locally, the capacity of the Togolese administration
remains weak with regard to contract management and award procedures, as well as the planning, implementation, monitoring and
evaluation of programmes and projects for the development or
assimilation of the principle of accountability.
The implementation of the
proposed system of
governance for agropoles and the operationalisation
of a one-stop land service
are measures designed to
supplement the action
already instigated by the government in order to
improve political, economic and financial
governance. Improvements
to organisations responsible for quality,
standards and metrology
will boost the capacities of control and anti-corruption
bodies to deliver improved quality of services to the
population.
Transparency: Despite remarkable progress, corruption perception
in the country remain high, with Togo ranked 117th out of 179
countries in 2017 on Transparency International's Corruption
Perception Index, compared with 116th out of 176 countries in 2016.
The country's corruption perception rating also places it below the
international average for the 176 most corrupt countries (32
IV
Fragility factors
identified by the
fragility
assessment
The situation, challenges and resilience measures supported by
General State Policy with assistance from Technical and
Financial Partners (TFPs)
Measures supported by
African Development
Bank intervention under
PTA-Togo (2018-2023)
compared with an average of 43). Public-private partnerships
(PPPs) are plagued by the absence of a formal framework for
consultation – a situation that leaves room for the practice of
directly negotiated agreements that can sometimes be misused.
Other challenges include lack of transparency in the management
and allocation of rights to natural resources: the lack of
transparency and good governance in the award of public contracts
and the abuse of private operational permits for mining on large
areas of land are symptomatic of major, unresolved problems and
weaknesses in the governance of natural resources. To remedy this
situation, the Government decided to set up an institution with the
resources needed to fight this type of corruption, and the High
Authority for the Prevention and Fight against Corruption
(HATPLC), an independent administrative body, was established on
28 July 2015. Its members were appointed on 3 January 2017 and
officially sworn in on 7 February of the same year. The purpose of
this anti-corruption body is to promote and strengthen efforts to
prevent and combat corruption and similar violations within
government services, public institutions, private enterprises and
non-governmental organisations. It enjoys financial and
administrative autonomy, and must also ensure the protection any
individual who, acting in good faith, reports the details of
established offences to the relevant public authorities. Since this
organisation is neither a law enforcement body nor a court of law, it
is obliged to forward all substantiated complaints to the Public
Prosecutor so that investigations may be conducted and state action
initiated.
2. Questions of security and violence, and security sector capacity and performance
Security: Despite Togo's largely stable security situation, sporadic
incidents with the potential to destabilise the country continue to occur, justifying continuous efforts towards social sector reform in
order to address the diverse and now recurrent demands for better
conditions for individuals in the education and health sectors. More generally, security problems are reflected in acts of violence against
people and property and the criminalisation of the economy, including the informal sector or even illegal exploitation of natural
resources.
PTA makes no direct
contribution to issues of security. It does, however,
offer solutions to food
insecurity, and it works to mitigate risks that could
worsen the security situation.
3. The justice sector (inclusive access to justice, the rule of law and independence of the
judiciary, as well as checks and balances)
Weakened judicial system: Successive crises arising from the
democratic transition, and sanctions imposed by Togo's main
technical and financial partners for a decade have taken a significant toll on the judicial system. With its ability to operate
diminished by the various causes of fragility, this system has been manipulated for political purposes by the entire political class, and
appears undermined by a lack of independence, problems of
corruption, and inadequate technical and material resources. Therefore, even after the end of the crises, those seeking justice
PTA makes no direct
contribution to the justice
system. However, it addresses the issue of
social and spatial inclusion, a source of
social injustice, by
mainstreaming the concerns of vulnerable
V
Fragility factors
identified by the
fragility
assessment
The situation, challenges and resilience measures supported by
General State Policy with assistance from Technical and
Financial Partners (TFPs)
Measures supported by
African Development
Bank intervention under
PTA-Togo (2018-2023)
continue to feel a deep mistrust of the justice system. Aware of this
situation, regional leaders in every member country have begun the work of judicial reform. Significant progress has been made thus far,
though it remains modest in the eyes of the populations concerned.
In view of this disparity, Togo was requested and has pledged to accelerate the process of modernising the justice system, the
adoption of the Penal Code and Criminal Procedure Code, as well
as reform of the National Human Rights Commission (CNDH).
groups in its activities -
especially women and young people.
Financial and
Economic
Factors
4. Strengthening the economic base and the resilience of communities (equitable access to
infrastructure and the benefits of natural resources)
Togo's macroeconomic performance has been encouraging, and this has undoubtedly enabled its return to growth. However, the situation
remains fragile and extremely sensitive to exogenous shocks and unpredictable climatic events because of the structure of the
country’s economic fabric, which witnessed little change in recent
years. Growth remains at a structural disadvantage because of low overall productivity and high production factor costs. Similarly,
although improvements in education have enabled the workforce to
expand, the accumulation of physical capital has stagnated since the 1990s, contributing to the steady decline in overall factor
productivity since 1980. Togo needs to make the most of its geographical position and turn it into an asset. With the
modernisation of its seaport and airport, and considering that the
country is the hub for ASKY Airline, it has at its disposal the
structuring infrastructure required to recapture its past position.
A range of structures and forms of support offered by
the PTA are likely to help create an environment
conducive to diversifying
the country’s economy, which has an agricultural
sector representing nearly
40% of its GDP. The creation of agropoles and
greater professionalization of agriculture will mitigate
the effect of exogenous
shocks and offer new
opportunities for the
private sector, which is a driver of economic growth.
Social Factors:
Poverty and
Inequality
4. 5. The increased mobilisation of resources to develop opportunities for employment, revenue
and inclusive access to basic social services, with a focus on the crucial role played by the
State; improved financial governance and an appropriate refocusing of the functions of the
State
Inequalities: The pace of progress in human development varies by
region and prefecture, and is insufficient to meet the Agenda 2030 sustainable development objectives. Although slow progress can be
seen in education and healthcare, as well as in living standards of
the Togolese population, several factors are holding back this
improvement: the presence of inequalities, which reduce the impact
of growth on poverty reduction, the absence of any real structural transformation, which restricts economic opportunities, and a lack
of progress towards gender equality, which has a knock-on effect on
the development of businesses and skills. Beyond these observations, the country faces enormous difficulties to deliver human
development for a young and growing population which is
increasingly mobile in the search for work, and these difficulties should be factored into the vast reform programme the Government
embarked upon following the resumption of cooperation with its various donors.
The range of activities
supported by PTA aims to produce an environment
conducive to the
operationalisation of
agropoles as a key plank in
the structural transformation of the rural
social fabric, which is more
affected by inequalities and widespread poverty among
women caused by barriers
to economic opportunities.
Revenue sources: The economy’s reliance on the phosphate sector,
as well as seaport and airport traffic, is a source of fragility. The
greatest share of the country's GDP is produced by two prominent
business sectors, namely the Port of Lomé and the mining of a huge
PTA's proposals include
the active involvement of
the private sector,
particularly agricultural
VI
Fragility factors
identified by the
fragility
assessment
The situation, challenges and resilience measures supported by
General State Policy with assistance from Technical and
Financial Partners (TFPs)
Measures supported by
African Development
Bank intervention under
PTA-Togo (2018-2023)
phosphate deposit, which generates over 40% of the country's export
revenue. Togo is the world's fifth largest phosphate producer. Many studies have revealed that "countries with economies that are
dependent on exporting a limited number of primary products are
more prone to political fragility" and conflict. To change this, the authorities plan to invest heavily in the structural transformation of
the under-productive agricultural sector by developing agropoles, in
order to consolidate the share of GDP represented by agriculture and gradually reduce expenditure on food imports.
and financial research
institutions, to produce in the commodities the value
addition that the country
needs to increase its tax base and support the
sustained mobilisation of
revenue.
Regulatory framework (the State’s role in service provision): Togo enjoys the advantage of having renovated the road network that
connects the country to its neighbours, and developed good quality urban roads in the capital city, even though their condition has
deteriorated as a result of the political and democratic crisis.
Impediments to the development of infrastructure to improve the quality of the State’s service provision vary in magnitude from one
sector of activity to the other. Progress has been observed in the
international transport sector, despite the persistence of significant regional disparities. However, sectors covering public utilities such
as water, waste treatment, electricity and transport are finding it hard to take off due to lack of swift and efficient action), as well as
financing delays. The unbalanced distribution of public services
across regions and sections of the population constitutes another fragility factor which could, in the long run, exacerbate socio-
political tensions if corrective action is not taken to eradicate the
potential for a social divide.
PTA’s geographical location is an initial
response to the imbalance in the provision of services
noted between urban and
rural areas. PTA proposes a number of elements
designed to facilitate the
implementation of agropoles, and in terms of
their operationalisation, agribusiness centres of
excellence with all public
service rights necessary will be constructed to
promote the successful
socio-economic integration
of communities.
VII
Appendix IV: Agro-food Processing Zone (ZTAs) :
A Flagship Programme of the “Feed Africa Strategy”
A/. What is an Agro-food Processing Zone?
An Agro-Processing Hub is a well-defined, centrally managed tract of land developed,
subdivided and dedicated to supporting firms and other stakeholders engaged in agro-processing and
related activities, located throughout the production area surrounding the hub. (FAO, 2017);
Agro-food Processing Zones are agro-based spatial development initiatives designed to
concentrate agro-processing activities within areas of high agricultural potential to boost
productivity and integrate production, processing and marketing activities. These initiatives
may or may not be granted Special Economic Zone status;
They are purposely built shared facilities to enable agricultural producers, processors, aggregators
and distributors to operate in the same vicinity in order to reduce transaction costs and share business
development services for increased productivity and competitiveness.
B/. Main Objectives of Agro-food Processing Zones (ZTAs)
The main objective of an Agro-food Processing Zone is to transform the African rural landscape into
prosperous economic zones through the development of agro-industry in major agricultural production
area. Its specific objectives are to:
Promote private investment, particularly in agro-industry, in order to increase value addition to
agricultural products and facilitate marketing;
Increase productivity and agricultural production of sectors with a market potential at national
(substitution of imported products) and international (exports) levels;
Increase the contribution of the agriculture sector to GDP, and to wealth and employment creation,
especially in rural areas.
C/. Main Geographical Entities of a Agro-food Processing Zone
The Agro-food Processing Zone is a geographically defined area designed to cover one or more
agricultural production areas relevant to the priority value chains identified following the conduct of
studies. It comprises three major entities which should be perfectly connected by proper transport
infrastructure:
A Hub or an Agro-park consisting of a developed area with roads and main networks (clean water,
sanitation, electricity, ICT, etc.), logistics and specialized facilities and services (cold chain,
laboratory and certification, business services, waste treatment, etc.), all of which are required for the
conduct of agro-industrial activities by the private sector. The ownership and management of the
hub are often left in the hands of an independent entity, usually in the context of a public-
private partnership arrangement.
Agricultural Transformation Centres (ATCs): The ATC is a physical complex of facilities centrally
located in the middle of a farming community, where required services are offered to farmers,
including:
Aggregation, sorting and primary storage centres for agricultural products
Agricultural input distribution platforms (seeds, fertilizers, etc.)
Service centres (agricultural credit, business centres, rental and maintenance of agricultural
equipment, zoo-sanitary clinic, etc.)
Food quality control and seed certification
The extension and training centre for producer organisations
Basic social services (schools, health centres, DWS, etc.).
VIII
Centres de transfor-mationagricole
Conglomérats agricoles modernes
SerresExploitations
modernesExploitations
piscicoles
Recherche et développement,
bibliothèqueCentre de formation
Zones de transformation
agricole
MécanisationCentre de réparation
Centre de conférence
Salles de réunion
Services publics et Entretien
du sol
Accueil Centres de santé
Centres de nutrition
Écoles Terrain de
sport
Chambres froidesChambres de maturation
Entreposage
Logistique des marchés
terminaux
Conditionnement Complexe des affaires
/ administratif
Centres de transfor-mationagricole
Centres de transfor-mationagricole
Centres de transfor-mationagricole
Plateforme agro-industrielle
Commercialisation
Agricultural production zones: These correspond to the zones targeted to supply agro-parks
with basic agricultural products via Agricultural Transformation Centres (ATCs). They can
benefit from public investments that can facilitate the increase of agricultural productivity
and the production of the farmers of the sectors selected for the Agro-food Processing Zone.
D/. Key Success Factors:
A ZTA should be based on an Agricultural Transformation Strategy and Plan that targets
areas of high agricultural potential, which are provided the basic infrastructure (water, electricity,
roads / tracks, etc.) by the State (facilitator) in order to promote private investment (promoter),
especially in agro-industrial activities.
The implementation of ZTAs should be facilitated by the State by creating a conducive policy,
regulatory and institutional environment for innovation, skills transfer and private investment,
including through tax and customs incentives.
Agro industrial-parks should provide the private sector with reliable hard and soft
infrastructure required by agro-industries to become competitive (uninterrupted power
supply at a competitive cost, good road infrastructure, clean water, ICT, waste treatment,
proximity to the administrative regulatory offices and the one-stop-shop system).
The structuring and operation of consultation frameworks for priority value chains should
be supported and encouraged by the State. The objective is to improve the functioning of the
value chains in order to improve the performance of the actors.
Inclusion of local communities and capacity building for smallholder farmers are essential
for ensuring the success of ZTA initiatives. Building the capacity of local communities,
smallholder farmers and SMEs is imperative for improving their agricultural performance and
their access to agricultural markets, and for preventing potential conflicts.
Agricultural
Transformation - Centres
Modern Farms Clusters
Green Houses Modern
Livestock Farms Fish Farms
Research and Development,
Library Training Centre
Agro- Processing Zones
Mechanisation Repair
Shop
Conference Centre
Meeting Room
Utilities and Ground Maintenance
Hospitality Health Centres
Nutrition Centres
Schools Sports
Grounds Cold Stores
Ripening Chambers
Warehousing
Terminal Markets
Logistics Packaging
Business/Administrative Complex
Agricultural Transformation -
Centres
Agricultural Transformation -
Centres
Agricultural
Transformation -
Centres
Agro-Industr ial Hub
Marketing
IX
Appendix V: General Table of ADF and TSF Grant and Loan Resource Allocation
LIST OF GOODS AND SERVICES ADF Loan TSF Loan ADF Grant TOTAL
LC FE Total LC FE Total LC FE Total LC FE Total
A. WORKS
Developments - - - 1 037.73 2 421.36 3 459.09 - - - 1 037.73 2 421.36 3 459.09
Infrastructure 1 883.56 5 303.74 7 187.30 274.42 645.99 920.40 - - - 2 157.97 5 949.73 8 107.70
Construction & Rehabilitation - - - 38.86 90.50 129.36 - - - 38.86 90.50 129.36
Sub-total 1 883.56 5 303.74 7 187.30 1 351.00 3 157.85 4 508.85 - - - 3 234.56 8 461.59 11 696.15
B. GOODS
- -
Vehicles - - - 8.00 24.01 32.01 42.54 127.61 170.15 50.54 151.62 202.16
Equipment - - - 169.12 314.40 483.53 53.32 99.24 152.56 222.44 413.65 636.09
Sub-total - - - 177.13 338.41 515.54 95.85 226.85 322.71 272.98 565.26 838.25
C. SERVICES
- - -
1. TRAINING - - - 86.66 57.63 144.29 181.57 120.78 302.35 268.23 178.41 446.64
2. TECHNICAL ASSISTANCE - - - 145.31 823.14 968.45 67.93 385.10 453.04 213.24 1 208.25 1 421.49
3. STUDIES
- - -
Various studies 70.21 85.82 156.03 642.60 785.33 1 427.93 65.13 79.65 144.78 777.94 950.80 1 728.74
Preparation advance - - - - - - 605.00 390.00 995.00 605.00 390.00 995.00
Sub-total 70.21 85.82 156.03 642.60 785.33 1 427.93 670.13 469.65 1 139.78 1 382.94 1 340.80 2 723.74
4. Contracting services - - - 173.11 57.69 230.80 183.09 61.00 244.09 356.20
118.68 474.89
5. Audit - - - - - - 28.81 35.21 64.02 28.81 35.21 64.02 Sub-total 70.21 85.82 156.03 1 047.68 1 723.79 2 771.47 1 131.54 1 071.74 2 203.29 2 249.43 2 881.36 5 130.79
D. MISCELLANEOUS - - - 192.07 - 192.07 - - - 192.07 - 192.07
E. STAFF - - - - - - 1 640.31 - 1 640.31 1 640.31 - 1 640.31
F. OPERATION 349.90 - 349.90 10.82 20.12 30.93 148.09 261.31 409.40 508.81 281.43 790.23
Unallocated 113.17 233.60 346.76 103.23 197.90 301.13 24.62 34.68 59.30 241.01 466.19 707.20
TOTAL 2 416.84 5 623.16 8 040.00 2 881.93 5 438.07 8 320.00 3 040.41 1 594.59 4 635.00 8 339.17 12 655.83 20 995.00
X
Appendix VI: Details of the Economic and Financial Analysis
SENSITIVITY ANALYSIS
Summary of scenarios
Present values: Fall in Price -2.5% Fall in Price -5% Fall in Price -25% Fall in Price -26.36% Fall in Price -30% Fall in Price -32.5% Fall in Price -35%
Variables cells: Profitability threshold
Price drop 0.00% 2.50% 5.00% 25.00% 27.20% 27.50% 30.00% 35.00%
Resulting cells B35:
NPV 56 304 609.37 53 489 949.80 50 689 002.81 28 775 079.70 26 418 125.95 26 097 545.92 23 433 724.71 20 783 616.09
IRR 23.23% 22.24% 21.24% 12.95% 12.00% 11.87% 10.78% 9.67%
Cost/Benefit Ratio 2.03 1.98 1.93 1.55 1.51 1.50 1.45 1.40
XI
XII
Appendix VII: Map of PTA Intervention Area in the Kara Region