Project 1.4
description
Transcript of Project 1.4
www.smart-microgrid.ca
Project 1.4Operational Strategies and Storage Technologies to Address Barriers for a Very High Penetration of DG Units in Intelligent MicrogridsMichael Ross (McGill University)Dr. Chad Abbey (Hydro-Québec)Prof. Géza Joós (McGill University)
Presentation Outline
• Problem Identification.• Existing Solutions (Status Quo) and gaps in the
solutions.• Proposed solution and methodology.• Results and Conclusions.• Future work and potential collaborations.
Problem Identification1. A high penetration of highly volatile renewable
energy generation introduces many adverse effects:– High power fluctuations seen by the Electric Power
System,– Peak power flow through the Point of Common Coupling
(PCC) might not be reduced, and – Power production is not guaranteed during an islanding
event.2. Microgrids can be implemented for a variety of
reasons:– Boston Bar, BC: Microgrid controls have been
implemented to maintain reliability and optimize dispatch.
– Hartley Bay, BC: Microgrid controls have been implemented for energy conservation and reduced diesel consumption.
How to utilize available Distributed Energy Resources to optimize the desired benefits of the Microgrid with a high penetration of renewable resources?
Status Quo• In collaboration with Hydro-Québec, a call for
offers for a commercial Microgrid controller was made to be implemented on the IREQ Distribution Test Line.
25 kV / 120 kVΔ-Ү
28 MVA
PC1
S3
F1
RC3 RC1
Microgrid Control Centre
B1
Neutral Conductor
25 kV/ 600 V3-167 kVA
3-200 kVA14 A
X1
X2
VR
RC2
Line 1Line 2Line 3
Underground Network
PC2
Xda
Xdb
Xdc
S1S2
S4S5
Line 4
Zg
25 kV/ 600 V3-167 kVA
25 kV/ 600 V3-167 kVA
R XL
MXC
Loads
If,dc
VDCSupply
DC Motor
Induction Generator
Vs+AC DC
If,sg
VACDrive
Induction motor
Synchronous Generator
ACAC
Spinning Generators
+VdcLiFEPO4
ESSAC/DC
Converter
VDCSupplyVs
+
AC/DC Inverter
Inverter Generators & ESS
Diesel GeneratorDiesel
ICESynchronous
Generator
AC
If,sg
25 kV/ 600 V3-167 kVA
Status Quo – Problems• Although many companies advertise a Microgrid
controller, only one company submitted a proposal.– The controller is still in the development phase.– Only the cost of energy is minimized.
There is an upcoming need for such controllers, however they currently are not commercially available or flexible for general implementation.
If this gap is addressed, it can put Canada at the forefront on Microgrid controller and EMS technologies.
Proposed Solution• The energy management in the Microgrid is
formulated as a mixed-integer, multi-objective optimization problem.– The multiple objectives aim to maximize the benefits,
while minimizing the adverse effects of a high penetration of renewables.
• The objectives are identified through a collaboration with Project 2.1.
• The quantification of the objectives are established so that they can be directly compared, and evaluated through common metrics.
Optimization Objectives• The identified objectives include:
• The optimization formulation (subject to power balance and DER constraints):
Objective Valuation Function Quantification Method
Reduce the cost of energy Market cost of electricity & fuel costsImprove Reliability Cost of non-delivered energyMinimize Peak Power through the Electric Power System
Infrastructure investment deferral
Reduce Power Fluctuations The difference in firm generation price versus fluctuation generation
Reduce Greenhouse Gas Emissions Carbon trading market
Test System
• The test system and dispatch algorithm were implemented in Matlab and GAMS.
• Profiles were obtained through discussions with CanmetENERGY on real profiles and prices of energy.
Energy Storage System Non-Critical
Loads (500 kW peak)
Diesel Generator(1.25 MW)
Critical Loads (500 kW
peak)
Electric Power System
WTG(s)N x 330 kW
turbines
PVsM x 10 kW modulesLi-Ion,
300 kW, 900 kWh η= 92.8%
• The MOO minimizes peak power and power fluctuations at the PCC while also minimizing cost.
Results
Results
• The MOO maintains reliability for critical loads through demand response and storage utilization during islanded operation.
Conclusions• By quantifying the benefits with standard
evaluation metrics, the Multi-Objective Optimization can be solved as a single valuation objective function.
• Even with a high penetration of renewable generation:– The mean ramping rates were reduced by 33%– Peak power was reduced by 10%– The cost of energy was reduced by 11%– GHG emissions were reduced by 18%– SAIFI was 0 for critical loads and SAIDI was reduced by
29% for all loads
Future work• Address intra-dispatch operation.
– Potential collaboration with Projects 1.2, 2.3.• Address stochastic nature of renewables.
– Potential collaboration with Projects 1.1, 2.2.• Implement ICT with proposed controller.
– Potential collaboration with Projects 3.3, 3.4.