PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015

Transcript of PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING...

Page 1: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

PROJECT 123(14) LOR-57-19.42 PID 82645INTERCHANGE IMPROVEMENT

PARTNERING RE-CONNECT MEETING

NOVEMBER 19, 2015

Page 2: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

AGENDA

I. Welcome

II. Review of Charter, Project Successes, and 4/16/15 Action Items

III. 2015 Construction Season Status Report

IV. Issues Pending Resolution

V. 2016 January – March Winter Work

VI. Open Discussion and Action Item Review

VII. Adjourn

Page 3: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

CHARTER REVIEW GOAL ASSESSMENT

PROJECT SUCCESSES

Page 4: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

GOAL ASSESSMENT• How are we meeting our goals?• What action needs to be taken to address goals that are not being

met?

Page 5: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

PROJECT GOALSGoal Performance to Date

Maintain a safe project site

Maximize public value and Contractor profitability

Build the project on time

Build the project within budget • Change orders written to date: $737,551.43.• Major change orders include erosion control, asphalt for

maintaining traffic, partial-depth pavement repairs, variable depth milling.

Minimize inconvenience to the traveling public • Signal timing has been modified with each phase of construction to keep traffic flowing as efficiently as possible.

• Project has worked to have SR 57 lane closures at night or removed by 3:00 PM each work day.

• Recent work to repair storm sewers across SR 57 near Midway Blvd. has impacted traffic and caused backups on SR 57.

Develop a work environment that promotes mutual respect

Collaborate among ODOT, the Contractor, and the utilities to improve construction phasing

.

Page 6: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

COMMUNICATION GOALSGoal Performance to Date

Identify and follow the chain of command for all communication

Establish and maintain honest and open communication

Respond in a timely manner to all project issues

Complete, clear, and concise correspondence

Electronic file of the project

Provide adequate notice for maintenance of traffic and utility impacts

Identify the point of contact for appropriate stakeholders’ communication

Page 7: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

PROBLEM SOLVING GOALSGoal Performance to Date

Identify and address all problems as soon as possible

Resolve problems at the lowest level when possible

Communicate, implement, and document solutions

Seek solutions, not blame

Involve tradesmen in the solutions whenever possible

Follow the designated chain of command

Follow the Dispute Resolution Process

Maintain a “Best for the Project” approach

Page 8: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

PROJECT SUCCESSES

• SR 57 widening and I-90 ramp construction completed.–The surface course is to be placed on SR 57.

• Midway Blvd. and Griswold Rd. intersections are open to full movement, with a plan in place to add protected left-turns.• 49th St. bridge demolition is completed.

Page 9: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

4/16/15 PARTNERING MEETING ACTION ITEMS UPDATE

Page 10: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

ACTION ITEMS

There were seven action items from the 4/16/15 partnering meeting:

1. Emergency Service Provider Jurisdiction Map

2. Snow & Ice Jurisdiction Meeting

3. Winter Traffic Control Issues

4. Construction Traffic Control Issues

5. Consultant Communication

6. Timely Notice to Ohio State Highway Patrol

7. Funding Discussion

Page 11: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

EMERGENCY SERVICE PROVIDER JURISDICTION MAP

• The City of Elyria finalized the map and distributed it to all appropriate parties by April 29, 2015.

Page 12: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

SNOW & ICE JURISDICTION MEETING

• According to the ODOT Lorain County management team, there is no jurisdiction agreement between the District and the City, because there is just a slight overlap of approximately 200’ between the two entities. ODOT plows this portion.

• If the City needs to address this matter further, it will contact the ODOT Lorain County management team.

Page 13: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

WINTER TRAFFIC CONTROL ISSUES

• Plans are in place to install 5-section signal heads, which will add protected left-turn phases for Midway Blvd. EB/WB and Griswold Rd. EB.• Tentative completion date for this work is

November 21, 2015.

Page 14: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

CONSTRUCTION TRAFFIC CONTROL ISSUES

• Based upon the discussion at the April 16, 2015, partnering meeting, the City was going to schedule a meeting by November 1, 2015, if they thought one was needed.

• No meeting was scheduled.

Page 15: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

CONSULTANT COMMUNICATION

• KS Associates has been attending every progress meeting since the April 29, 2015, meeting.

• A list of RFIs, deadlines, and responses has been kept. There have been no problems getting timely information.

Page 16: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

TIMELY NOTICE TO OHIO STATE HIGHWAY PATROL

• The OHSP and the City of Elyria were notified in advance of new signal activation at the Midway Blvd. and Griswold Rd intersections.

Page 17: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

FUNDING DISCUSSION

• Payment for pavement repairs that were needed but not addressed in the plans has been discussed and resolved.

• The Change Order to pay for these repairs is being processed.

Page 18: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

2015 CONSTRUCTION SEASON STATUS REPORT

Page 19: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

PROJECT OVERVIEW

SR 57I-90

Grisw

old Rd

Midw

ay Blvd

Leona St

52nd St

Tillotson St

Beechwood D

r.Schaden Rd.

Midway Mall Frontage Rd

Ohio Tu

rnpik

e

Ohio Turnpike Ramps

Midway Mall Dr.

Page 20: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

2015 HIGHLIGHTS AND REMAINING WORK SR 57 SB & Ramp 8A Phase 2B-1 Midway Boulevard Phase 3A 49th Street West Phase 5 Left 49th Street East Phase 5 Right & SR 57 SR 57 NB/SB Phase 6 SR 57 Phase 7 Other Contract Work Items

Page 21: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

SR 57 SB & RAMP 8APHASE 2B-1

• 9” concrete pavement has been completed.

• Ohio Edison pole in conflict with ditch excavation:– Pole was not set at the correct

station and offset per the utility note.

– Did not affect pavement construction.

• Remaining work: – 19mm intermediate course asphalt.– Seed and mulch.

Page 22: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

MIDWAY BOULEVARD PHASE 3A

• 200’length of pavement to be completed near the Leona St. intersection.

• Work to include undercut excavation, 8” concrete pavement, and new drive aprons to Red Roof Inn and Cirillas.

• Storm sewer work was completed during Phase 1B-1.

• Work was delayed due to storm sewer testing and repairs from Phase 1B-1 work along Midway Blvd.

Page 23: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

49TH STREET WESTPHASE 5 LEFT

• Structure and embankment removal work in progress.

• Area to be placed at final grade per plan and seeded.

• Other work: drainage, curb and gutter, and sidewalk along the east side of Leona St.

Page 24: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

49TH STREET EASTPHASE 5 RIGHT & SR 57

• Structure removal work in progress.

• Pier #1 and #2 to be removed in order to complete pavement work on SR 57.

• Proposed 49th St. east of SR 57 revised by the City of Elyria.

Page 25: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

SR 57 NB/SBPHASE 6

• Widening of SR 57 to the outside from Griswold Rd. to Beechwood Dr.

• 9” concrete pavement completed from I-90 EB ramps to the north.

• Remaining work includes 19mm intermediate course asphalt, Type D barrier wall at I-90 structure piers, grading/seeding, guardrail, and permanent sign structures.

Page 26: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

SR 57PHASE 7

• 12.5mm asphalt surface course to be placed on existing and new SR 57 pavement, as well as Ramps D, 8A, and 8B.

• Variable depth milling to be completed on existing SR 57 pavement.

• Partial depth pavement repairs have been completed.

• Milling and surface course will begin in May 2016.

Page 27: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

OTHER REMAINING CONTRACT WORK ITEMS

• Permanent Epoxy Striping– I-90 EB; Ramps C, D, F; Leona St.; 52nd St.; Tillotson St.

• Lighting Work–High mast tower installation I-90 median and ramps.–Foundations for light poles along SR 57.

• Signing Work–Flat sheet and extrusheet signs to be installed at various locations on

SR 57, I-90 EB/WB, Ramp C, Midway Blvd., and Griswold Rd.

• Concrete Barrier Wall–Type D wall to be installed along SR 57 SB in front of Lowe’s.

Page 28: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

ISSUES PENDING RESOLUTION

Page 29: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

OUTSTANDING ISSUES

• Adding 5-section signal heads for protected left turns at Midway Blvd. and Griswold Rd.• Elevation issues at the intersection of SR 57/Ramps A

and C, including the attenuator pad and median barrier wall.• Storm sewers under pavement that require repairs, per

C&MS 611.

Page 30: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

CPM SCHEDULE

• September 2015 update submitted by Karvo on 10/22/15 has been approved.

• Contract completion date remains as July 15, 2016.• Potential time extension for partial depth repairs added to

the Project.• Recent discussions between ODOT and Karvo regarding

2015 work that may carry over to the 2016 season.

Page 31: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

2016 JANUARY – MARCH WINTER WORK

Page 32: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

WINTER WORK• Finish by Christmas:– Embankment removal for 49th Street, east of SR 57.– Final grading of the R/W. – Temporary seeding & mulching.– Installation of the concrete barrier wall:• Under the I-90 bridge (outside lanes)• In front of Sunbelt Rentals (southbound)• In front of Lowe’s (southbound)

• Traffic signs • Guardrail• Ongoing through the winter:– Light pole installation on SR 57 and the I-90 ramps.

Page 33: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

WINTER WORK

• All work is weather dependent.• These work items will not impact traffic with lane

closures or pattern shifts.

Page 34: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

OPEN DISCUSSION & ACTION ITEM REVIEW

Page 35: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

Partnering re-connect session to be scheduled early spring 2016, just before construction resumes, to provide a detailed overview of work to be done during the 2016 season.

Review of Action Items

Page 36: PROJECT 123(14) LOR-57-19.42 PID 82645 INTERCHANGE IMPROVEMENT PARTNERING RE-CONNECT MEETING NOVEMBER 19, 2015.

ADJOURN