Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110...

14
Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552 www.utroninc.com Progress Update April 8, 2008

Transcript of Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110...

Page 1: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Corporate Office 9441 Innovation Dr.

Manassas, VA, 20110 (703) 369-5552

www.utroninc.com

Progress Update April 8, 2008

Page 2: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

The lighter propellant gases keep the pressure behind the projectile higher

CLGG Physics

Hydrogen/Oxygen

Light Combustion Products

Page 3: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

CLGG Chronology

1 9 9 3 1 9 9 5 2 0 0 7 Time

16 mm 45 mm 155 mm Bore Size

Kinetic Energy Levels

kJ’s Few MJ’s Tens of MJ’s

Page 4: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

CLGG Benefits

• Higher velocity

• Lower operating pressures

• Lower acceleration on projectile

• Infinite zoning

• Ability to produce propellant onsite

Page 5: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Combustion Control and Zoning

5 10 15 20

Time (ms)

40

10

20

60

50

30

Pres

sure

(kps

i)

Shot B

Shot A

Same Chemical Energy, Same Projectile Mass, Different Chemistry

0

Page 6: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Modeling

Page 7: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

155 mm CLGG 14 shots with up to 28 MJ muzzle energy to date, A fraction of its capability, tests are ongoing

Page 8: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

155mm Test Data

Shot number

Projectile mass (kg)

Peak Chamber Pressure

(psi)

Peak Acceleration

(g’s)

Velocity (m/s)

Kinetic Energy

(MJ)

Barrage Range (miles)

14 20.3 25,000 17,000 1667 28 111

Page 9: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Current Propellant Supply System

Page 10: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Future Propellant Production – Pilot Plant

 Steam Natural Gas Reforming  Diesel Reforming  Electrolysis

Hydrogen Production  Electrolysis  Cryogenic Air Separation  Pressure Swing Absorption  Membrane Separation

Oxygen Production

Possible pilot plant using off the shelf hardware

Page 11: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Future – Instrumented Projectiles

3 axis accelerometer Onboard recorder Battery

Pressure Gage

Page 12: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Future – Instrumented Projectiles

Page 13: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008

Future – Transportable Extreme Range System

•  R&D - Support Long Range Guided Projectile Development •  Field - Provide Extreme Range Artillery Support

Page 14: Progress Update April 8, 2008€¦ · Corporate Office 9441 Innovation Dr. Manassas, VA, 20110 (703) 369-5552  Progress Update April 8, 2008