Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal...

13
Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri Lanka Dr. Gamani Chandrasena Vice Chancellor Uva Wellassa University, Sri Lanka

Transcript of Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal...

Page 1: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Progress Review On

Ongoing Construction Projectsaimed at

Budget - 2016

Professor Ranjith Premalal De Silva

Vice ChancellorUva Wellassa University, Sri

LankaDr. Gamani Chandrasena

Vice ChancellorUva Wellassa University, Sri Lanka

Page 2: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Construction (Capital) Projects of Uva Wellassa 1. Phase I

2. Phase IIPhase I

i. Administration Building Block ii. Lecture Hall + Lab (Block A)iii. Lecture Hall + Lab (Block B)iv. Lecture Hall + Lab (Block C)

Total Cost Estimated (Amended TCE) => Rs. 350 MillionActual Expenditure incurred to 30.06.2015 => Rs. 348 MillionFuture Commitment (Final Bill to be Settled) => Rs 10 MillionPhysical Process : 100% Financial Progress : 99%

Administration Building Block

• Awarding On : 03rd Aug 2005

• Completed On : 16th Oct 2006

25 August 2015

Page 3: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Lecture Hall + Lab (Block B)

• Awarding On : 03rd Aug 2005

• Completed On : 11th Oct 2006

Lecture Hall + Lab (Block C)

• Awarding On : 03rd Aug 2005

• Completed On : 11th Oct 2006

Lecture Hall + Lab (Block A)

• Awarding On : 03rd Aug 2005

• Completed On : 01st Nov 2006

25 August 2015

Page 4: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Hostel Block No. 2•Awarding On : 01st Sep 2006•Completed On : 26 Jun 2008•Physical Progress : 100%•Financial Progress : 87%

Hostel Block No. 3•Awarding On : 01st Aug 2006•Completed On : 04th Dec 2008•Physical Progress : 100%•Financial Progress : 87%

Hostel Block No. 1•Awarding On : 01st Jul 2006•Completed On : 30th Jul 2007•Physical Progress : 100%•Financial Progress : 87%

25 August 2015

Phase II

Page 5: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Dinning & Study Hall Kitchen for Dinning & Study Hall

•Awarding On : 15th May 2006•Completed On : 30th Jun 2006•Physical Progress : 100%•Financial Progress : 87%

Water Sump & Pump House

•Awarding On : 01st Sep 2006

•Completed On : 16 Jun 2008

•Physical Progress : 100%

•Financial Progress : 73%

Hostel Block No. 4• Awarding On : 01st Nov 2006• Completed On : 25th Jul 2008• Physical Progress : 100%• Financial Progress : 87%

25 August 2015

TCE: 457 Million

Page 6: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Name Board and Developments at entrance

•Awarding On : 01st Jul 2007•Completed On : 19th Jan 2008•Physical Progress : 100%•Financial Progress : 35%

Temporary Sports Court•Awarding On : 15th Jan 2007

•Completed On : 27th Feb 2006

•Physical Progress : 100%

•Financial Progress : 70%

Landscaping - Phase - 1 Area•Awarding On : 01st Jan 2007•Completed On : 19th Jan 2008•Physical Progress : 100%•Financial Progress : 70%

25 August 2015

Page 7: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Fiber Network (IT back-born at Phase 1 buildings)

•Awarding On : 01st Dec 2007•Completed On : 31st Dec 2008•Physical Progress : 100%•Financial Progress : 97%

Vice Chancellor's Bungalow•Awarding On : 08th Sep 2008•Completed On : 09th Mar 2010•Physical Progress : 100%•Financial Progress : 98%

Play Ground (For 200m track)

•Awarding On : 01st Apr 2007

•Completed On : 13th Sep 2009

•Physical Progress : 100%

•Financial Progress: 63%

Page 8: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Internal Road Network (A,B & D)•Awarding On : 01st Mar 2007•Completed On : 30th Mar 2009 •Physical Progress : 100%•Financial Progress: 66%

Lecture Hall + Lab (Block E)

• Awarding On : 05th Sep 2008

• Completed On : 15th Mar 2011

• Physical Progress : 100%

• Financial Progress : 65%

Lecture Hall + Lab (Block F - I)

• Awarding On : 01st Jan 2009

• Completed On : 08th Mar 2010

• Physical Progress : 100%

• Financial Progress: 65%

Page 9: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Lecture Hall + Lab (Block F - II)• Awarding On : 27th Apr 2010• Completed On : 26 Jul 2011• Physical Progress: 100%• Financial Progress: 65%

Lecture Hall + Lab (Block D)• Awarding On : 27th Apr 2010• Completed On : 26th Aug 2011• Physical Progress: 100%• Financial Progress:65%

Storm Water Drainage System

•Awarding On : 30th Dec 2009

•Physical Progress: 65%

•Financial Progress: 17% Ongoing

Page 10: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Quarters for Deans/ Registrar/ Bursar & Course Directors

•Awarding On : 01st Dec 2011

•Completed On : 15th Feb 2013•Physical Progress : 100%

•Financial Progress : 77%

Staff Quarters (Studio Apartments)

•Awarding On : 25th Nov 2012

•Completed On : 05th Mar 2013

•Physical Progress : 100%

•Financial Progress : 50%

Roads and Landscaping at Phase II Area

•Awarding On :17th Dec 2009

•Physical Progress : 50%

•Financial Progress : 41%

Ongoing

Page 11: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Sports Center & Gymnasium

• Awarding On : 30th Dec 2014

• Physical Progress : 25%

• Financial Progress : 25%

Pavilion

•Awarding On :06th Aug 2015

•Physical Progress : 5%

•Financial Progress : 5%

(Mobilization Advance)

Ongoing

Ongoing

Cafeteria and Toilets

•Awarding On : 27th Aug 2012

•Completed On : 26th Aug 2013

•Physical Progress : 100%

•Financial Progress: 100%

Page 12: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

25 August 2015

Maintenance section

• Awarding On : 08th Jan 2014

• Completed On : 08th Oct 2014

• Physical Progress : 100%

• Financial Progress: 66%

Senate Building

• Awarding On : 20th Mar 2013

• Physical Progress : 95%

• Financial Progress: 85% Ongoing

Balance work Roads & Landscaping

•Awarding On : 22nd Mar 2014

•Physical Progress: 65%

•Financial Progress: 44% Ongoing

Page 13: Progress Review On Ongoing Construction Projects aimed at Budget - 2016 Professor Ranjith Premalal De Silva Vice Chancellor Uva Wellassa University, Sri.

Waste water drainage & treatment works (Job 01 & Job 02)

•Awarding On :14th Oct 2010 / 17th May 2013

•Physical Progress : 85%

•Financial Progress: 36%

University Guest House

•Awarding On: 05th Nov 2012

•Completed On: 17th Aug 2013

•Physical Progress: 100%

•Financial Progress: 96%

25 August 2015

Ongoing

University Guest House

•Awarding On: 05th Sep 2011

•Completed On: 20th Oct 2012

•Physical Progress: 100%

•Financial Progress: 64%