Progress Report - rutag.iitd.ac.in
Transcript of Progress Report - rutag.iitd.ac.in
1
Progress Report
RuTAG Centre at IIT Delhi Developing Demand
Driven Technology for Rural Areas
(April 01, 2019 – March 31, 2020)
By
Prof. Subir Kumar Saha (P.I.), ME
Prof. M. R. Ravi (Co. P.I.), ME
Prof. S. Kohli (Co. P.I.), ME
Department of Mechanical Engineering
IIT Delhi, Hauz Khas
New Delhi 110 016
Tel: (011) 2659 1135; 1385 Fax: (011) 2659 7359
Email: [email protected]
May 17, 2020
2
Abstract
This report discusses the projects approved by PSA under project titled “RuTAG Centre IIT
Delhi Developing Demand Driven Technology for Rural Areas” (Phase-II). Some ongoing
work of Phase-I have been carried forwarded in Phase-II. Ongoing, and new projects have been
briefly described. Details of the workshops conducted and proposed have also been given in
this report. RuTAG IIT Delhi published 9th edition of newsletter which has covered most of the
on-going activities at all RuTAG centers in seven IIT’s during 2019-20. To encourage the
participation of IIT Delhi student and faculty, orientation and felicitation programme will be
organized. RuTAG Club IIT Delhi participated in ‘Tour of Stalls’ orientation program on July
27-28, 2019. The aim was to sensitise the new students joining IIT Delhi about the activities
of RuTAG Club, IIT Delhi.
Acknowledgements
The authors sincerely acknowledge the support from the Office of the Principal Scientific
Advisor to the Government of India and especially to Prof. K. Vijay Raghavan, Principal
Scientific Advisor (PSA) to the Govt. of India and Dr. Ketaki Bapat, Scientist ‘F’ with whom
we interacted on a regular basis. The encouragements from the Chairman Core group of
RuTAG IIT Delhi Prof. R. R. Gaur are highly appreciable. Other significant contributors
include Mr. Raj Kumar Gupta (Sr. Project Assistant), Mr. Davinder Pal Singh (Project
Associate), Mr. Suraj Bhat (Research Scholar), Mr. Yashwant Prasad (Research Scholar), Mr.
Ashish (Jr. Project Assistant), Mr. Mangal Sharma (Jr. Project Attendant), and many more B.
Tech. and M. Tech. students of RuTAG Club, IIT Delhi by their contributions in the project.
3
Contents
Abstract 2
Acknowledgement 2
1. Projects of RuTAG IIT Delhi during April 01, 2019 – March 31, 2020 5
1.1 Projects in the Financial Year 2018 – 2019 and 2019 – 2020 5
1.2 New Projects likely to be taken up 7
2. Summary of Projects in the Financial Year 2018 – 19 and 2019 – 20 9
2.1 On-going Projects 9
2.1.1 Improvement in Furnace Design and Working Conditions of Artisan for Making
Bangles (Phase-II) 9
2.1.2 Design of an LPG fired Pottery Kiln for the Pottery Cluster at Khurrampur,
Haryana 12
2.1.3 Adaptation of Sheep Hair Shearing Machine Developed by IIT Delhi (Phase-III) 18
2.1.4 Fabrication of Tree Climbing Device for Safe and Convenient climbing of
Coconut Trees, Palakad, Kerala 22
2.1.5 Development of More Ergonomic and Efficient Street Sizing System for
Chirala Handloom Cluster 26
2.1.6 Proposal for Designing of Vertical Vermicomposting Unit for Mata Vaishno
Devi, Katra Jammu and Kashmir 30
2.1.7 Dissemination of Improved Metallic Carpet Looms Developed by IIT Delhi for
Carpet Weavers at Jaipur, Rajasthan 35
2.1.8 Design Improvement of Tulsi Mala Making Device for Bigger Beads 40
2.1.9 Design Improvement and Fabrication of New Model Charkha (NMC) 43
2.1.10 Prevention of Stone Dust Inhalation for Stone Carvers at Bharatpur, Rajasthan 46
2.1.11 Truncated Unglazed Percolative Clay Ceramic Ware as a Modified Pitcher
Irrigation System 48
2.1.12 Proposal for Improvement in the Batasha Making Process Phase-II 53
2.1.13 Improvement in Bhilawa Seed Decortication Process 57
3. Follow-up Projects after Completion 62
3.1 A Device for Making Tulsi Mala Beads 62
3.1.1 Status after Completion 62
3.1.2 Increased in Sales of Device after Modifications 62
3.1.3 Buy RuTAG IIT Delhi products through FITT 64
4
4. Reporting 65
4.1 Workshop Organised during April 01, 2019 – March 31, 2019 65
4.1.1 RuTAG IIT Delhi Regional workshop conducted on June 03, 2019 at Khamir,
Gujarat. 65
4.1.2 RuTAG IIT Delhi Regional workshop conducted on December 16, 2019 at Mathura
Uttar Pradesh 67
4.1.3 RuTAG Management Development Programme at IIT Delhi during October 2-4,
2019 (In association with IIT Kharagpur) 69
4.1.4 RuTAG Workshop held on August 11, 2019 as a part of Tech4Seva 2019 70
5. Field visits during Financial Year 2019 – 2020 (April 01, 2019 – March 31, 2020) 72
6. Other Salient Activities during Financial Year 2019 – 2020 (April 01, 2019 –
March 31, 2020) 75
6.1 Logo of Rural Technology Action Group (RuTAG) IIT Delhi 75
6.2 A Compendium on Rural Technology Action Group (RuTAG) of 52 Technologies
from 7 IITs 76
6.3 Rural Technology Development and Delivery Conference Proceedings
published by Springer 76
6.4 Rural Innovative Techno-hunt: A Technical Challenge to Identify Rural Problems
and Suggest Solutions - Organized by RuTAG IIT Delhi 77
6.5 RuTAG IIT Delhi published Newsletter by annually 77
6.6 RuTAG Technologies Displayed in Open House at IIT Delhi on April 20, 2019 77
6.7 RuTAG Club IIT Delhi participated in ‘Tour of Stalls’ on July 27-28, 2019 78
6.8 RuTAG IIT Delhi demonstrated of its technologies in Tech4Seva at LHC, IIT Delhi
campus during August 10 – 12, 2019 78
6.9 RuTAG Club Orientation and Felicitation programme was held at LHC, IIT Delhi
on August 30, 2019 78
6.10 RuTAG IIT Delhi presented posters of its technologies in Industry Day at IIT Delhi
campus on September 21, 2019 78
6.11 RuTAG IIT Delhi team attended 2nd International Conference on "Rural
Technology Development and Delivery" (RTDD-2020) was held on March 12-14,
2020 at IIT Madras. 79
7. RuTAG IIT Delhi’s Collaboration with Purdue’s EPICS Programme 79
8. Internship at RuTAG IIT Delhi 80
5
1. Projects of RuTAG IIT Delhi during April 01, 2019 – March 31, 2020
1.1 Projects in the Financial Year 2018 – 2019 and 2019 – 2020
Sl.
No.
Project Title Year of
Approval
(Duration)
Status Remarks
1. Improvement in
Furnace Design
and Working
Conditions of
Artisan for
Making Bangles
(Phase-II)
01/10/18
(One Year)
Ongoing The modifications are in progress as per the
design-decisions taken after trials of two
improved furnace for six months at Unch
village. The most reliable cluster have
extended help by providing space and
completed civil work as suggested by
RuTAG team for the installation of the
furnace. Lupin foundation have been
managing logistics, materials etc., for
construction at site at Unch village and also
convincing artisans at another village to
install new furnace through Gram
Panchayat.
1. Design of an
LPG-fired Pottery
Kiln for the
Pottery Cluster at
Khurrampur,
Haryana
01/10/2018
(One Year)
Closed The furnace has been vandalized to such an
extent that it cannot be repaired.
3. Adaptation of
Sheep hair
shearing machine
developed by IIT
Delhi [Phase-III]
01/10/2018
(6 months)
Ongoing The modified device has been tested at two
locations. Identified vendor have
successfully developed the device and
samples are ready for testing in the field.
4. Fabrication of
Tree Climbing
Device for Safe
and Convenient
climbing of
Coconut Trees,
Palakad, Kerala
01/03/2019
(One Year)
Ongoing The problems associated with the developed
device at IIT Delhi during the trial at Kerala
were observed and analysis of the said device is
under process. Soon it will be modified
fabricated and retested with the help of the NGO
at location.
5. Development of
More Ergonomic
and Efficient
Street Sizing
System for
Chirala
Handloom
Cluster
01/01/2019
(One Year)
Ongoing Several iterations have been made to initial
design as per sizers’ feedback and the process of
product. The final model contains improved
brushing action. CAD model of new drive
mechanism/ Street sizing machine has been
completed with engineering drawing, and
fabrication is under progress. Manufacturing of
following parts of the street sizing machine have
been completed i.e. base structure frame, yarn
6
wrapping octagonal frame, rubber roller,
solution tank, guide roller etc.
6. Proposal for
Designing of
Vertical
Vermicomposting
Unit for Mata
Vaishno Devi
Katra
01/06/2019
(One Year)
Ongoing A CAD model of Vertical Vermicomposting
and assembly drawing of Vertical
Vermicomposting Setup is under progress after
narrowing down the design requirements as per
the feedback and will be finalised for
manufactured soon.
7. Dissemination of
Improved
Metallic Carpet
Looms
Developed by IIT
Delhi for Carpet
Weavers at
Jaipur, Rajasthan
01/10/2018
(06 Months)
Ongoing Three looms have been manufactured and sent
three different locations such as one at
RCWPDS, Jaipur, Rajasthan, another one is at
Mpr. Jitendra Bonal, Pithoragarh, Uttarakhand
and one at Chirala, Andhra Pradesh.
8. Design
Improvement of
Tulsi Mala
Making Device
for bigger beads
01/03/2019 ( 06 Months)
Ongoing New model to produce bigger size beads has
been designed, fabricated. Prototypes
distributed in various villages in Rajasthan and
UP for feedback. Modifications have been
incorporated as per the feedback received.
9. Design
Improvement and
Fabrication of
New Model
Charkha (NMC)
01/03/2019 ( 06 Months)
Ongoing To avoid the brakeage of threads an RPM meter
has been attached to the new model charkha so
that user can operate the machine at optimum
speed. A CAD model of Table with Sitting
Arrangement for New Model Charkha and
assembly drawing of Table with Sitting
Arrangement for New Model Charkha is under
progress and will be fabricated soon after the
finalization of the design.
10. Prevention of
stone dust
inhalation for
stone carvers at
Bharatpur,
Rajasthan
01/01/2019 ( One Year)
Ongoing Two designs were thought of to address the
problem of stone dust inhalation after visiting
the cluster and observing the problems faced by
labourers working in stone quarry and marble
carving units. A portable glove hood, and a
suction system. The advantages of this system
are many: the system is versatile, cheap, and
portable. The system has been developed and
tested successfully at IIT Delhi. The use of
ventilation hood has been found to be effective
in reducing the particulate concentration at the
stone carver’s inhalation level considerably.
However, the field-testing of the setup is still
pending. The prototype of the suction system
was developed and tested at IIT Delhi.
11. Truncated
Unglazed
01/07/2019
(9 Months)
Ongoing The objectives of the project have been
achieved by re-introduce the Pitcher irrigation
7
Percolative Clay
Ceramic Ware as
a Modified
Pitcher Irrigation
System
or Matka Irrigation in arid Western Rajasthan,
and along with modified sub-surface irrigation
by changing shape of the pitcher and
introducing mechanization to produce it. A
considerable reduction in water usage have been
observed. The system is currently under testing
at Gelabaas Village, Rudiya Village, Banad
Village, IIT Jodhpur Experimental campus, and
Salawas village in Jodhpur.
12. Improvement in
the Batasha
Making Process
Phase-II
01/12/2019 ( One Year)
Ongoing Units of improved hygienic Batasha making
process developed during phase-I were installed
and tested at various place near Greater Noida
and Ghaziabad, Uttar Pradesh. Suggestions and
observations were noted and changes have been
implemented. Recently one unit of improved
adjustable table has been sent to Kolkata for
testing and feedback.
13. Improvement in
Bhilawa Seed
Decortication
Process
01/12/2019 ( One Year)
Ongoing Two design ideas have been shortlisted after
visiting the village in M.P. The existing
decortication machines are under review
considering the hazardous nature of the fruit.
Therefore safe operation of the device without
any exposure and human contact will be the
objective of the project.
14. Follow-up
Projects after
Completion:
a. Tulsi Mala
making Device
b.Treadle Pump
c. Bullock Driven
Tractor
d.Animal Driven
Prime Mover
01/10/2018
Follow-up
after
Completion
The products were sell through FITT as follows:
a. Tulsi mala making device – 10
b. Treadle Pump – 02
c. Bullock Driven Tractor – 01
d. Animal Driven Prime Mover - 01
1.2 New Projects likely to be taken up
1. Carding Machine ● Carding machine manufacturers have been
identified across the country who can support
us in fabricating suggested design.
● A questionnaire to understand the requirements
of carding machine in Kutch have been
prepared and shared with Khamir (field
partner).
8
● A field visit has been planned to collect
relevant data related to carding machine design
and development.
2. Tawa Making Process
● The samples of tawa received from tawa cluster
were baked in a controlled muffle furnace from
room temperature to 800° C as per defined
temperature profile.
● Field visit has been planned to collect
temperature history of existing tawa making
furnace and process.
● Customised K-type thermocouples as per the
span of the existing furnace have been
fabricated for measuring temperature at
different positions of the open furnace during
firing.
3. Sheep Wool Applications
● It has been decided that RuTAG IIT Delhi will
support in testing the properties of sheep wool
as and when required by Hunnarshala
Foundation
● Hunnarshala will provide funding for the
testing
4. Yamunotri Palki
● After the field visit, a report was shared with
the CDO of Uttarkashi. It was decided that IIT
Bombay will help in designing the new Palki
because of their prior experience with the Katra
Palki project. RuTAG IIT Delhi was to analyse
the structural design aspects of the concept.
● The same was conveyed to CDO via email and
telephonic conversations. However despite
repeated reminders, there was no response and
the project had to be closed.
5. Improving the furnace used in coating
copper bell for coating multiple bells at
a time.
Project under consideration.
6. Design improvement of potters kiln at
Bhuj
Project under consideration.
7. Developing Wax Removing
Technology
Project under consideration.
8. Block making Technology for Printing
on Clothes.
Project under consideration.
9. Improving efficiency/technology for
the glass furnace.
Project under consideration.
10. Validation of properties of recycled
and reused wood, bamboo, etc. which
are used for construction purposes.
Project under consideration.
9
2. Summary of Projects in the Financial Year 2018 – 19 and 2019 – 20
2.1 On-going Projects
2.1.1 Improvement in Furnace Design and Working Conditions of Artisan for Making
Bangles (Phase-II).
a) Principal Investigator: Prof. Sangeeta Kohli
b) Co-Principal Investigator (Furnace Design): Prof. M. R. Ravi
c) Co-Principal Investigator (Tools and Seating Design): Prof. S. K. Saha
d) Duration of Project: One Year
e) Project Commenced: 01/10/2018
f) Status: On-going
g) NGO partner: Lupin Foundation,
Bharatpur, Rajasthan
Summary:
During the Phase-I of the project entitled “Improvement in Furnace Design and Working
Conditions for Making Bangles”. Lupin Foundation, an NGO, expressed the need to improve
a traditional bangle-making furnace which is highly polluting and inefficient. RuTAG IIT Delhi
did various interventions for developing, fabricating and installing furnaces with improved
design, a better seating arrangement along with some modification in molding tools which
helped in providing better working conditions for the artisans. Two improved furnaces with
different designs were installed at two sites in Unch village in Bharatpur district of Rajasthan.
Lupin Foundation contributed in the logistics as well as civil work required in erecting a shed
and the ergonomically designed working platform/space.
Considering deliverable for the phase-I of the said project, three sets of problems faced by the
artisans in Bharatpur were addressed and solutions were proposed. Two modified furnaces have
been developed, installed in the village. 74% saving of fuel was recorded in both the furnaces.
Substantial reduction in emissions in the workspace due to the flue gases leaving through the
chimney and reduction in workspace temperature due to the insulated furnace were also
recorded. Thus, the improved furnace has resulted in substantial improvement in their working
environment.
Subsequently, while testing the prototypes in the field, artisans of both the groups were happy
with the usage of the furnaces. Eventually after the period of four months, one of the group
stopped using the furnace. After discussion, field agency and RuTAG team agreed to their
demand for the provision of the free raw material (glass) to sustain their testing for few months.
Nevertheless, the group started the work. However, the work continued till the stock of the free
raw material lasted and the furnace was left abandoned afterwards. However, the second group
used the furnace seamlessly without conducting regular maintenance and repairing in such a
manner that despite warnings raised by the RuTAG team to stop the work until the replacement
of the damaged parts, their continuous usage caused the furnace to collapse.
10
In the backdrop of the village politics along with the resistance of the artisans in accepting the
developed technology and during the testing of the technology following are the observation:
1. Industrial insulation of a brand/supplier could not sustain the inside temperature of the
furnace (as claimed and specified by the said supplier) during the field trials, which
eventually got damaged within few months of the trial
2. The clay core in one of the furnace developed cracks due to cyclic thermal stress much
earlier than expected.
3. Base of the furnace which comprises two layers of the alumina board underperformed
and got damaged much earlier than expected as per the specification provided by the
refractory manufacturer.
4. The M S attachment used to hold the baffle failed number of time and it was later
replaced with the refractory grade stainless steel.
5. Though no loss of the productivity was observed.
After observing the trail data of the furnace, the objectives of the phase-II
are listed as follows:
1. Core of the furnace will be constructed using refractory castable instead of clay.
2. Mild Steel (MS) molds will be fabricated to cast the core of the furnace.
3. Industrial insulation having higher temperature bearing capacity will be used.
4. Ceramic board used in the base of the furnace will be replaced the refractory bricks
5. Refractory grade stainless steel will be used to fabricate baffle for the furnace
Fabrication methods for the said molds have been laid after thoroughly observing the viability
of manufacturing. Vendor are selected according to their capacity and ability to manufacture.
A dish-end fabrication process have been followed to achieve the dimensional tolerance and
cost effectiveness of the said molds. The CAD model of molds is shown in Fig. 1.
Fig. 1 CAD models of Molds
11
The fabrication of the mold was divided into three parts neck (Fig. 2), dish-end and base ring
(Fig. 3)
Fig. 2 Mold parts neck Fig. 3 Dish-end and Base ring
Similarly, the castable and the required thickness of the shell (Fig. 4) have been calculated
and optimised as per the existing clay structure and the trial data available. Mold is casted
(Fig. 5) and industrial insulation will be fixed on inner and outer surface soon.
Fig. 4 Castable and the required thickness of the shell
Present Status:
The modifications are in progress as per the design-decisions taken after trials of two improved
furnace for six months at Unch village. The most reliable cluster at the village have extended
help by providing space for civil work as suggested by RuTAG team for the installation of the
new furnace. Lupin foundation have been managing logistics, materials etc., for construction
site at Unch village and also sensetising artisans at another village to install new furnace with
the help from gram panchayat. The necesscary construction at site has been completed. Other
12
parts of furnace such as customised boom for lifting casted frunace due to its weight and
fragility have been fabricated. The other components required have been identifed and will be
procured after the lockdown period is over and once life gets back to normal. Furnace will be
assembled at IIT Delhi and transported to village for installation.
Fig. 5 Actual Casted Mold ready installation
2.1.2 Design of an LPG fired Pottery Kiln for the Pottery Cluster at Khurrampur,
Haryana
a) Principal Investigator: Prof. M. R. Ravi
b) Co-Principal Investigator: Prof. Sangeeta Kohli
c) Duration of Project: One Year
d) Project Commenced: October 01, 2018
e) Status: Closed
g) NGO partner: Khurrampur Village
Panchyat and District
Administration, Gurgaon,
Haryana
Project Summary:
Village Khurrampur is a highly backward village with bulk of its population constituted by
Backward and Scheduled castes. It has about 20-25 families of potters, who belong to OBC
communities of Haryana. IIT Delhi has adopted this village for development under the Unnat
Bharat Abhiyan of the Ministry of Human Resource Development. In the process of
preparation of the Village Development Plan, during the survey of the demographics and
occupations of the village, the requirements of the Prajapat (Potters) community came to the
fore.
13
The primary difficulty they have is availability of clay for their work. Since most of them are
landless, to obtain clay for their work, they need to go far and wide, or purchase cartloads from
landowners on whose land clay fit for pottery use is available. The second major difficulty is
that the process of firing is extremely polluting with thick black smoke emanating from their
kilns, owing to which other villagers object to the kilns being fired. Since the income from the
profession has also dwindled, the younger generation of the community has preferred not to
continue this profession and are looking for other sources of livelihood.
Therefore it was proposed to develop an LPG fired furnace for use by these potters so that the
furnace is more efficient and less polluting. It would also aim at training the local potters in
craft that would fetch them better income, by diversifying into more value-added products in
addition to the traditional pottery and diyas they normally make.
6. Preliminary Investigation and Problem Identification:
Two options were available for RuTAG to technologically intervene in this situation. One is
to design a furnace which can be fired using a clean fuel such as LPG or Piped natural gas,
depending on availability of these fuels to the potters in the colony. A second is to design a
gas furnace, but fire is using producer gas, made from the same powdery biomass fuel presently
being used by the potters. The latter has a limitation, since there are no mature technologies of
gasification of powdery biomass available, and it also involves addition of extra hardware in
the form of a gasifier in addition to a new kiln. Thus, both in terms of cost and in terms of
technological complexity, the second option suffers from a disadvantage, though the fuel for
this option would be cheaper. Thus, in the first phase of intervention, it is proposed to opt for
the design of an LPG / PNG fired kiln.
From the preliminary interactions, it transpired that the cost of a single firing at present is close
to Rs. 1600-1800, for wares that sell for Rs. 5000-6000. An inspection of the updraught kilns
in use in the area reveals that based on experience of the IIT Delhi team, if a well-insulated,
light-weight kiln is designed, the energy consumption of the kiln could easily be reduced by a
factor of 3-4. As of now, the cost comparison between the powdery biomass and commercial
LPG per unit energy is 1:6. If PNG is used, this ratio decreases to 1:4. This would make the
firing with the new kiln about 50% more expensive with LPG, and comparable to the present
cost with PNG. But given the fact that the new kiln would be capable of firing wares at much
higher temperatures, they could easily diversify into products which can fetch them much
higher returns per firing, such as decorative wares, glazed wares etc.
Thus, it was proposed that in the first phase of the project, a new kiln is designed, tested and a
prototype be installed in the field for use by artisans and their feedback. It should then be
monitored over about 6 months and the teething problems removed. Once the kiln is designed
and a prototype is installed and successfully tested in the field, RuTAG could identify and train
entrepreneurs who could construct the kilns in the field in the second phase of the project.
14
Design of New Improved Model:
After the analysis of the energy audit, it was found that the major heat loss was occurring
through the ground and due to the high thermal mass of the kiln. To reduce the thermal mass
of the structure while also ensuring considerable insulation at low cost, the walls of the kiln
were decided to be made using rat trap bond structure. To ensure proper air-fuel ratio for
complete combustion of fuel, a provision for an air channel was also proposed near the fire
mouth.
Keeping in mind the above discussed design considerations, detailed CAD models were made
using SOLIDWORKS software. All the CAD models and parts (Fig. 6 and 7) were made
according to the standards to ensure the feasibility of the designs for construction.
A cuboidal cross-draught arrangement kiln with composite walls consisting of both thin layer
of insulation boards and bricks arranged in rat trap structure. Provision of two burners provided
on one side of the kiln and a separation wall of 0.07 m with multiple openings made with
special firebricks for effective and controlled flow of heat towards the payload ware.
Fig 6 CAD model of Kiln Design
Fig. 7 Cross-sectional view of kiln design
The base layer has been designed with two insulation layers of 0.1099 m thickness each with
uniform air gaps. The grate consists of mild steel rods placed equally apart for the passage of
flue gases towards the chimney.
15
Construction:
The site available for the construction was situated at a distance from the main village area.
Before any kind of construction, proper levelling (Fig. 8) and back filling of the land was
required to be done to ensure rigid base for foundation and construction of shed.
Fig. 8 The process of levelling and settling down of soil during the beginning of construction
process of shed and kilns
This was followed by demarcation and construction of foundation boundaries and base shown
in Fig. 9.
Fig. 9 Laying of foundation of the cross-draught pottery kiln
During time, the refractory bricks, seamless MS pipes for chimney, T-joints, U-bend, MS
flanges, draft control valve and its parts were fabricated (Fig. 10). To ensure the cost
effectiveness and fulfil the specific dimensional requirements, the entire valve including the
bushes and revolving plate were designed, fabricated and assembled beforehand and were later
transported to the site because at the construction site there was no means of making weldments
and drills due to absence of electricity. Apart from this, in case of the cross-draught kiln special
16
fire bricks and cement was also used for the construction of critical areas like that of the
dividing perforated wall to ensure high energy utilization.
Fig. 10 Fabrication of chimney parts at Khyala, Delhi
The construction work (Fig. 11) continued for about two to three weeks due to hinderances
caused by unfavourable weather conditions and rain. All possible measures were taken to
protect the sensitive insulation boards and other materials to avoid any loss due to rainy
conditions.
Fig. 11 The above pictures depict the construction of air-flow channel below the grate and
fixing of the chimney structure using grouting operation in order to ensure the rigidity of the
assembly.
(a) (b)
Fig. 12 (a) Shows the construction of separation wall made by introducing gaps between
specialized refractory bricks for controlled exposure of ware to the heat from the flame.
Fig. 12 (b) Shows the assembly for the kiln top gate.
17
The top gate of the kiln (Fig. 12 a & b) was made using a rigid steel frame with two layers
insulation boards of thickness 0.15 m, with the insulation exposed towards the inner portion of
kiln since the top inner surface of the kiln would be exposed to large amount of heat throughout
the entire course of firing operation. Moreover, special care was taken to ensure the
dimensional accuracy of the top gate assembly because even a small gap in the final structure
could lead to leakage from the kiln chamber, consequently leading to drastic decrease in the
level of efficiency. LPG gas bank was also fabricated to ensure proper and safe regulation of
the gas to fire stoves (Fig. 13).
Fig. 13 LPG gas bank was fabricated and safe regulation of the gas to fire stoves
The new designs of the enhanced kilns were made keeping in mind the above-mentioned
considerations:
1. Low thermal mass of the structure was achieved by reducing the thickness of the walls
of the kiln and by introducing rat-trap bond structure in the walls. The rat-trap structure
provides sound and economical insulation as the air gap after the innermost row of bricks
insulates the rest of the brick structure from the hot inner layer, consequently preventing
a large part of the wall from absorbing energy.
2. The kiln was significantly isolated from the ground by raising the base platform of the
kiln above the ground and creating airgaps and channels to act as insulation layers. This
helped us reduce the notable 13% losses that were earlier happening exclusively due to
heat lost to the ground.
3. To ensure a less open flame and better control on primary and secondary air inlet areas,
a method using cross-draught arrangement in the cuboidal kiln, in which the flame does
not remain exposed to the atmosphere thereby reducing the losses to atmosphere, which
constituted about 45% of the total heat released by the fuel in the firing operation.
Note: before the final testing could be done, furnace was vandalised by some mischievous
elements of the society. The extent of the damage done to furnace is beyond the limits of repair.
Hence it needs to be constructed again. Therefore this project is closed.
18
2.1.3 Adaptation of Sheep Hair Shearing Machine Developed by IIT Delhi (Phase-III)
a) Principal Investigator: Prof. S. K. Saha
b) Co- Principal Investigators: Prof. D. Ravi Kumar, Prof. Deepak
Kumar
c) Duration of Project: 06 Months
d) Project Commenced: 01/10/2018
e) Status: On-going
f) NGO partner: Jansamarth, Tehri, Uttarakhand
Summary:
Sheep-hair shearing machine is used to cut the woollen fleece of the sheep. The machine along
with comb and cutter was indigenously developed by IIT Delhi during 2006-2008. The
performance of the device matches the performance of the imported devices. Requirement of
a mechanised device to remove sheep hair was raised by an NGO Jansamarth during a meeting
at RuTAG IIT Roorkee. He mentioned the following problems with the current sheep shearing
practices in the region of Uttarakhand:
• Currently, in most of the places in Uttarakhand region, shepherds use scissor-type
blades.
• The blades of the scissors need to be sharpened on a regular basis, and thus one can use
them for a limited period of time.
• Needs to apply larger muscle power, which is tedious for a longer duration to shear
sheep hair. In Phata, Rampur, Uttarkashi, Devprayag and Kedarnath shepherds are not
aware of the mechanized device to remove sheep hair.
Therefore, RuTAG IIT Delhi took the initiative of the said problem under three phases. In the
first phase, two workshops were conducted to give hands-on experience of the mechanized way
of shearing to the shepherds of Rampur and Pipalkothi of Uttarakhand region. Thus, after
completing two training programs at various locations at Uttarakhand, phase-I was considered
completed.
In the second phase of the project, RuTAG IIT Delhi has taken the initiative to indigenously
develop and manufacture all the components of the device such as motor with flexible shaft
(Fig. 14), Handpiece with comb and cutter (Fig. 15). Also, suitable manufacturing processes
for mass production of components have been identified. The device set was manufactured and
tested at the several locations such as Barot, Bharmour, Bikaner, Rampur, and Hisar. The
device performed very well during the testing. Taking into consideration the Phase-II of the
project was considered completed. In the third phase of the project, the objective is vendor
development for mass production of the device and conducting training and awareness
programme for the shepherds and Shearers. Meanwhile the device will be optimized for the
smoother user experience. The device will also be tested at some specific locations after the
final modifications.
19
Fig. 14 Indigenous Motor with Flexible Shaft and Handpice
Fig. 15 Sheep-hair Shearing Handpiece with Comb and Cutter
Testing of Sheep Shearing Device at Palampur, H. P. during Nov. 15-21, 2018:
In 2014, IIT Delhi has taken a project titled “Dissemination of Low-cost Sheep Hair Shearing
Device developed by IIT Delhi” from Central Wool Development Board, Jodhpur, Rajasthan
under the supervision of Prof. S. K. Saha. The main objective of the project was to develop a
low-cost mechanised device for the removal of woollen fleece of the sheep to get the maximum
staple length of the extracted wool which will result in good quality yarn. Prof. S. K. Saha and
his team studied the device and worked in this project diligently. An indigenous device set was
finally developed and tested at several locations such as Barot, Bharmour, Palampur in H.P.,
Hisar in Haryana, and Bikaner in Rajasthan. The device was recently tested at Palampur, H. P.
Two project staff (Mr. Davinder Pal Singh and Mr. Ashish) from RuTAG IIT Delhi visited
Palampur (Fig. 16) for the testing during November 15-21, 2018. The indigenous set tested
included Handpiece, Combs, Cutters, Motor, and Flexible Drive. There, 18 sets of comb and
cutter, along with one motor, one flexible shaft and 7 Handpieces, were tested. The testing was
done with collaboration of Himachal Pradesh Wool Federation (HPWF) under the guidance of
Mr. Deepak Saini (Office In-charge, HPWF at Palampur).
20
Fig. 16 Testing of Sheep Hair Shearing Device developed by IIT Delhi at Bir, Palampur, H.P.
He assigned Mr. Hans Raj (Wool Grader, HPWF Palampur) for the supervision of the shearing.
Mr. Hans Raj managed everything for RuTAG IIT Delhi team such as identifying shearing
locations, shearers, sheep flocks, place of stay, etc. Over 125 sheep were sheared by indigenous
set at 5 different locations in Palampur region, named, Bodha, Sihol, Molichak, Bir, and Patti
during 8 days as the per the availability of the flocks. The indigenously developed Comb,
Cutter, Flexible Drive, Motor, and Handpiece performed at par with the imported device. The
comparative data was recorded by the team. Four different shearers, named, Malbar, Ashok,
DeshRaj, and Nitesh worked with the indigenous device and acknowledged the good
performance of the device during the testing. The shearers were happy to use the device
developed by IIT Delhi, and Mr. Saini has commented that this low cost device will certainly
boost the livelihood of the shepherds due to its nature of affordability.
Demonstration of Sheep Hair Shearing Device developed by IIT Delhi at Bhuj, Gujarat:
Mr. Davinder Pal Singh and Mr. Ashish Dahiya visited Bhuj, Gujarat on March 15, 2019 for
demonstration cum training programme in collaboration with KHAMIR and Gujarat Sheep and
Wool Development Corporation (GUSHEEL). RuTAG Team, KHAMIR Team, GUSHEEL
Team, some local sheep herders along with traditional shearers were present there. A total of
20 sheep were sheared by the device in front of all. A trained shearer (Fig. 17) was arranged
by GUSHEEL for the training and demonstration. The device performed very well throughout
the day. Traditional shearer who use scissors for shearing also got exposure to the device.
Traditional shearers tried the mechanized device for the first time and handled it very well. The
shearers were very happy and keen to use the mechanized device.
Fig. 17 Demonstration of Sheep Hair Shearing Device developed by IIT Delhi at Bhuj,
Gujarat
21
Present Status:
The long-awaited quest to convince someone to manufacture and sell the device in India has
come to an end as one of the identified vendor have successfully developed the device which
is ready for testing in the field. In the backdrop the existing modified device has been tested at
two locations which is as follows:
Demonstration of Sheep Hair Shearing Device developed by IIT Delhi at CSWRI,
Avikanagar, Rajasthan:
RuTAG IIT Delhi team comprising, Mr. Ashish (Jr. Project Assistant tech.), Mr. Srijan
Prabhakar (Research Scholar), Mr. Sumit Kumar (Project Assistant), and Mr. Mangal Sharma
(Project Attendant) visited Central Sheep and Wool Research Institute (CSWRI), Avikanagar,
Rajasthan (Fig. 18) on September 23-24, 2019 to test and demonstrate the components of sheep
shearing device along with ten teeth comb and three teeth cutter manufactured by different
Fig. 18 Mr. Balraj (shearer) showing sheared sheep by IIT Delhi device at CSWRI shearing
section, Avikanagar, Rajasthan
vendors in field which are under development at RuTAG IIT Delhi. Newly developed three
teeth cutters manufactured by forging process (developed under the project funded by Moody’s
Corporation) worked at par with the machined cutter. The machined combs and cutters have
been modified as per the feedback and experience gained from trails at various places during
this project. These combs and cutters have great severance, minimal entering, and driving
forces. Their performance is better and equivalent to the imported comb and cutters available.
2 Handpieces were demonstrated/tested at the CSWWRI shearing section, both performed very
well. Sunner motor with new switch performed excellently, but on/off angle of improved pull
cord switch needs reduction. The flexible drive worked flawlessly.
Field trial of Sheep Hair Shearing Device developed by IIT Delhi at USWDB, Rishikesh,
Uttarakhand
RuTAG IIT Delhi team comprising, Mr. Ashish (Jr. Project Assistant tech.), and Mr. Davinder
Pal Singh (Project Associate) visited Uttarakhand Sheep and Wool Development Board
(USWDB), Rishikesh, Uttarakhand (Fig. 19) during January 10-14, 2020 to test and
22
demonstrate the components of sheep shearing device along with ten teeth comb and three teeth
cutter manufactured by different vendors in field which are under development at RuTAG IIT
Delhi.
Fig. 19 RuTAG IIT Delhi device in work at shearing camp in Bhanivala forest range,
Bhogpur, Rishikesh, Uttarakhand
Newly developed three teeth cutters manufactured by forging process (developed under the
project funded by Moody’s Corporation) worked at par with the machined cutter. The imported
combs and cutters need to be changed every 3 sheep (as per the observance at the shearing
camp and according to USWDB Officials), however, IITD combs and cutters sheared a
maximum of 13 sheep without changing. 3 Handpieces were tested at the camp. The power
output of the generators was not linear, it was fluctuating constantly, and therefore, the team
was not able to take the data as expected. The motor and flexible shaft worked very well
throughout the shearing. From testing data, we can easily conclude that our Handpiece, comb,
cutter, flexible shaft, and motor are working well, and the performance is at par with the
imported device.
2.1.4 Fabrication of Tree Climbing Device for Safe and Convenient climbing of Coconut
Trees, Palakad, Kerala
a) Principal Investigator: Prof. S. P. Singh
b) Co-Principal Investigator: Prof. S. K. Saha
c) Duration of Project: One Year
d) Project Commenced: March 01, 2019
e) Status: On-going
f) NGO partners: Maithri, Palakad, Kerala
Summary:
The project has its background in an old letter from the ministry that coconut tree climbing is
a relevant problem in India and there should be put forward some solutions for efficient and
safe climbing of these trees and working up to harvest the coconuts. In this relation, a project
was proposed to two students as part of summer undergraduate research project. They did good
work and proposed an initial design of the tree climber.
23
There are a few climbers already in use, but they require the use of a coordinated hand and foot
movements and have safety concerns. Thus, apart from a development of the climber such that
one can climb the tree with the ease of climbing a staircase with primary function of the foot
and legs, the hand and arms are used only for additional safety concerns which comes to fore
whenever there is scope of accident or failure of the equipment.
Working Principle:
The gripping mechanism consists of steel strip attached via leaf spring to hinge which is free
to rotate about an axis attached to right (left) leg part head. This strip is wound across the tree
trunk. When the climber pushes the system down with his/her weight through the foot holder,
the strip clings on to the tree creating a couple which holds the weight of the person. To climb
up, the person lifts (Fig. 20) the right (left) leg (Fig. 21) part. The part moves up but the hinge
joint (Fig. 22) which was free to rotate, remains at the same position. This causes the strip to
lose its coupling effect and become slack. The hinge is supported by a stiff spring to control its
rotation. The slacked strip along with leg part can now be easily moved up and fixed again by
pushing it down from the foot holder (Fig. 23). Similar method is applied for climbing down.
Making the CAD Model:
We designed the CAD model using AutoCAD and Solidworks environment. Our basic
variables were manufacture and production cost and sustainability of the model under various
loads. Following are the major components:
Fig. 20 Right Leg Fig. 21 Left Leg
Fig. 22 Hinge Joint Fig. 23 Foot Holder
24
Material Selection and Manufacturing Process:
After considering the weight as well as the cost of various materials available, we finalised
Mild Steel as the basic material for production of first prototype. Mild Steel (MS) is cheap and
most easily available, thus making it appropriate for prototype production. Our second-best
contender was Aluminium because of its light weight, but its machining is difficult and is
expensive.
The material chosen for the steel strip was Spring Steel because the gripper was required to be,
tough, flexible and elastic. It should be able to take load of approximately 100kgs person
without getting permanently deformed. It should be tough enough not to crack under such load.
In addition to these Leaf Springs was used with the strip to add to its toughness.
Spring of high stiffness was also used which joined the hinge and the leg part. It is a very
important part of the system as it restricts and controls the free rotatory motion of the hinge
about its axis thus assuring safety in the gripping mechanism of the tree climber.
Manufacturing processes involved:
i. Milling- Most of cutting of steel was done by this process. Manufacture of Hinge joint
(Fig. 22) was solely based on this process.
ii. Laser Cutting- For cutting out templates of all the parts which were to be made by
sheet metal cutting. Templates were made of plywood or acrylic glass from CNC Lab.
iii. Sheet Metal Cutting- Every other part was made of sheets of MS of thickness 1mm or
2mm. This was done to reduce the weight of the overall product and ease in mobility.
The templates were used by the worker to cut the sheet metal.
iv. Welding- To join the parts made by sheet metal. Arc Welding was majorly used. TIG
Welding was also used.
v. Drilling- To drill holes into components wherever necessary.
vi. Powder coating- To protect the components from getting rusted with time. Colour-
White
Testing:
Our one of the aims was to climb a general tree. So, we testes the final prototype on a random
tree in front of the cricket field of IIT Delhi (Fig. 24 and 25). We used safety harness belt along
with carabiners to protect the climber in case of failure. It was initially difficult to climb but as
we got hang of it we climbed approximately 10 feet above the ground. And climbed down
successfully. No injuries were reported.
Preliminary Investigation and Problem Identification:
After the preliminary product was developed, a visit was made to Kerala (Maithri) NGO who
looks after the welfare of coconut planters as well as the workers. The presentation was made,
and the device was also tested. The preliminary prototype being a crude version has several
limitations in proper functioning.
25
Fig. 24 Final product ready for use Fig. 25 Reached max. Height
But the concept was very much liked by the concerned persons and that encouragement has
motivated us to enhance the product further and make a prototype fully usable with all the
envisaged advantages.
● The current tree climbers in the market are not safe and some accidents have happened.
● The arrangement using a closed loop of rope is also very risky. Due to this risk there is
a social taboo amongst the tree climbers’ community. People do not marry their girls in
tree climber’s family because of the large amount of risk involved in the job.
● People would also prefer an arrangement where they can use mechanized way a
climbing. They are ready to shell out money for a product so long as they realize that it
is productive and safe.
● The income of tree climber is related to the number of trees he can climb in one day.
Per tree the charges are around Rs 30. One of their interests is also to increase the
productivity of the person.
Preliminary Objectives:
Based on the observations, following objectives are formulated.
a) Development of improved prototype of Tree Climber: Fabrication of the new prototype
will be aimed to remove the limitation of right foot movement. Currently the design of
the right leg (upper leg) of the attachment is such that the mechanism movement is not
synchronous with the natural lifting movement of the leg. This results in mechanism
getting locked at times.
b) Safety Measure: Another important aspect of the climber is to design/provide a safe and
low-cost harness which can be used as guard against any unprecedented loss of grip.
The purpose is to make the climbing process safer. Such harness solutions are already
available for mountaineering but whether they will be suitable for coconut tree
climbing.
Present Status:
Design analysis of the prototype is presently being done to understand the significance of the
various parameters which are vital in manoeuvring the device vertically over the tree. The
26
results will be incorporated to improve the device and will be tested with the help of the NGO
partner (Maithri), Palakad, Kerala (Fig. 26).
Fig. 26 Existing arrangement and a prototype of the proposed mechanism
2.1.5 Development of More Ergonomic and Efficient Street Sizing System for Chirala
Handloom Cluster
a) Principal Investigator: Prof. Samrat Mukhopadhyay, Textile
Technology, IIT Delhi
b) Duration of Project: 06 Months
c) Project Commenced: January 01, 2019
d) Status: On-going
e) NGO partners: Rastra Chenetha Jana Samakhya (RCJS)
Jandrapet, Chirala, Prakasam, Andhra Pradesh
Summary:
The process of sizing (Fig. 27) is a very crucial step in weaving. Sizing is done to give
temporary strength to single count cotton yarn to withstand the rigor of weaving while keeping
the characteristics and properties of cotton yarn intact. It directly affects the production rate
and number of breakages and faults in fabric. Street sizing is one of the two most common
ways to do it, other being Hank sizing. The process of street sizing is very tedious and
repetitive. The weavers in Chirala, spray the sizing liquid on around 10-15 m of yarn sheet,
subsequently carry a heavy brush/comb to evenly spread the sprayed liquid onto yarn surface
and leave it to dry. This process is repeated for 3- 4 hours on both side of fabric. This is a
painful as well as heavily time consuming. Also spraying is not very efficient method of
applying the solution.
27
Fig. 27 Traditional Sizing of Warp Sheet
Preliminary Investigations and Problem Formulation:
The need of improvement in one of the handloom process, Street sizing was identified. The
problem was brought to us by the trade union itself and we visited Chirala to better understand
the problem and validate it. The operation mainly consists of coating long warp sheet from
starch paste by using hand held spray and heavy brush. It strengthens the yarn so that it can
endure the various forces exerted in weaving loom. Sizing is crucial as it directly affects
production rate & number of breakages. Sizers are leaving the operation due to drudgery of
sizing operation and low income.
We proposed four different mechanical designs to aid in the street sizing process, namely
helical, circular, hexagonal and hexagonal with off brush mechanisms (Fig. 28).
Fig. 28 Hexagonal with off Brush Mechanisms
28
Action Plan and Deliverables:
The sizers of Chirala need to work on the device conduct regular testing sessions at each
Sunday for one hour and get them to prepare a note of every discussion. Make the testing
more organized by working on specific problems each time to fine tune the design which
would include refinements of
● Brushing action
● Accommodation of lease rods
● Reversal mechanism
● Loading and unloading of warp sheet
● Any other issue they come up with tests will be performed of the raw yarn, Chirala
traditional method sized yarn and the new device sized yarn. After testing, optimized
conditions and finalized model will be ready to operate by the sizers.
Present Status:
The final model contains improved brushing action. Instead of moving the brush, the warp was
lifted off the polygon and stretched between two rotating rollers. Brush is located in the middle
of these two rollers, so that warp always remains in contact with it. Several prototypes were
made and a scaled model was installed at Chirala (Fig. 29), where the local sizers only are
doing trials. Several iterations have been made to our initial design as per sizers’ feedback and
the process of product development is still going on.
Fig. 29 A Octagonal with off Brush Mechanisms
A CAD model of new drive mechanism/ Street sizing machine (Fig. 30) has been completed
with engineering drawing, and fabrication is under progress (Fig. 31). Manufacturing of
following parts of the street sizing machine have been completed i.e. base structure frame, yarn
wrapping octagonal frame, rubber roller, solution tank, guide roller etc. (Fig. 31) and rest parts
under process.
29
Fig. 30 CAD Model of New Drive Mechanism/ Street sizing machine
Fig. 31 Actual Model of New Drive Mechanism/ Street sizing machine
30
2.1.6 Proposal for Designing of Vertical Vermicomposting Unit for Mata Vaishno Devi
Katra
a) Principal Investigator: Prof S. K. Saha (Mech. Engg. Dept.);
b) Co-Principal Investigators: Prof. Satyawati Sharma, CRDT, IIT
Delhi;
Prof. Balbir Singh, Dept. of Mech. Engg.
SMVDU, Kakryal, Katra, J&K;
Dr. Kalpana Arora, SESS, New Delhi
c) Duration of Project: One Year
d) Project Commenced: June 01, 2019
e) Status: On-going
f) NGO partners: Centre for Technology and Development
(CTD), A unit of Society for Economic
and Social Studies (SESS), New Delhi
Summary:
Mata Vaishno Devi Shrine is visited on an average every day by about 40 thousand pilgrims
and the numbers are growing every year. As the Shrine is located in quite steep hilly region,
about 15 km walking distance from Katra Town, about 5 to 10% of the pilgrims use local horses
and mules for visiting the Shrine. For transporting all the material to the lodges existing near
Shrine a caravan of Mules are used. It is a rough estimate that about 1000 horses and mules are
in service in this area. Mules not only provide the ease of access to pilgrims but also a livelihood
activity for the people involved in this service.
During the field visit to the Shrine Area in November 2007 for an Environmental, Ecological
and Hydrological basin Study it was found that the dung of these animals is causing a problem
also in November 2018, Honourable Supreme Court had asked to treat the following with
immediate effect:
1. Pollution of the Banganga stream and other water sources in the area by mule dung.
2. The dumping of the dung along the path to the Shrine is spreading bad odour in the
area, causing inconvenience to the pilgrims.
3. The path has become slippery at several places along the path due to dung and urine of
these animals.
4. The dry dung dumps are openly burnt at several places, which release smoke.
As the flat land area is limited in the hilly areas and the ecology of the area is also very fragile,
maintaining the garbage dump yard sites is limited. The disposal of tonnes of garbage is a
difficult task for the shrine board and also the Katra Municipality. Also the rate of
decomposition is limited due to altitude and existing low temperatures for several months in a
year. To tackle this ecological challenge of solid waste management, there is a need for a
comprehensive solution.
The action plan as suggested by the Supreme Court proposed the following activities:
● A detailed study of the dung and garbage disposal problem in the areas.
31
● Interaction with the stakeholders and finding solutions for segregation and
management of the solid waste.
● Designing or adopting appropriate technologies such as biomass stoves for cooking
and heating purposes with dung/garbage pellets.
● Vermicompost preparation using the dung for which, identification of the suitable
earthworms and designing the technique of vermicomposting. Developing a scientific
method for Composting wet garbage, dung, and local biomass.
● Training to the local people, farmers and others on the above technologies.
Objectives and Work Plan:
a) Primary objective: To develop and disseminate the vertical vermicomposting unit for
horse/mule dung composting at Mata Vaishno Devi Katra.
b) Secondary objectives:
Phase I
1. Designing of vertical system for vermicomposting of mule/horse dung.
Experiments will be conducted at waste management site, IIT Delhi, in various
designed structures for vermicomposting. Various materials will also be tested for
the strength and suitability. Aerobic vermicomposting process will be carried out
by using various E. fetida species and their efficacy will be tested. Work will be
carried out in a known quantity of substrate mix. Compost samples will be collected
at a specific interval of time for its analytic work.
2. Quality analysis (physical, biochemical and microbial) of the compost produced
Mule dungs taken from experimental site will be analysed for its physico-chemical
properties namely bulk density, ash content, EC, pH, organic carbon, and
macronutrients (N,P,K). Standard methods will be followed for different analysis.
Phase II
1. Testing of the vertical vermicomposting system on site i.e. Sri Vaishno Devi Katra
(with some polyhouse kind arrangement for colder months)
2. Training and engagement of local people for the development of the units.
The Work Plan will have following steps:
i. Review of literature
ii. Designing of Vertical Vermicomposting unit
iii. Testing of design proposed at IITD campus
iv. Analysis (chemical, biochemical and microbial) of compost sample taken in a
specific interval of time.
v. Design Improvement and trials at IITD campus
vi. Data analysis (statistical) and report writing.
32
Expected Deliverables:
1. Two – three finished prototypes vertical vermicomposting units.
2. Fully working vertical vermicomposting unit
3. A detailed report
Present Status:
A visit has been organized to Mata Vaishno Devi Shrine Board on July 30 – 31, 2019 by
team members (Prof. Balbir Singh and Dr. Kalpana Arora) with following objectives to
analyze the feasibility of the proposed activities:
● To seek the administrative support of shrine board during project activities
● To identify the present collection and dumping mechanism for mule dung
● To have information about the treatment methods being followed
The Mule dung is collected and transported to the dedicated composting site at Village
Natali, and the composting process is being carried out there with the help of staff deputed
by Shrine Board. The project was initiated under Solid Liquid Waste Management
(SLWM) with the help of Indian Green Service, Vellore, Tamil Nadu. Additionally,
Department of Agriculture, Horticulture, Floriculture and Krishi Vigyan Kendra are
assisting the Shrine Board in procurement and distribution of the manure to the farmers.
The distribution is being done free of cost. However the following issues are being faced
by the Shrine board:
● The current duration of the composting process is 120-180 days.
● The compost is not suitable for seedlings and transplantation process (probably due to
high Electrical Conductivity (EC).
● The vermicomposting of mule dung has also been tried in the past but could not get
materialized.
The consent regarding the development and field trials for vertical vermicomposting unit
has been given by the Shrine Board and it has been assured by the Shrine Board that it will
provide the assistance of space, water and other basic facilities there.
Mule Dung Composting site, Village Natali (Fig. 32):
The visit was done by RuTAG Project team members Prof. Balbir Singh (SMVDU) and Dr.
Kalpana Arora (CTD) on July 30, 2019. As per the brief given by the staff, the details are as
follows:
Fig. 32 Mule Dung Composting at Village Natali
33
Soon after the Shrine Board vehicle brings the mule dung at composting site, it is taken
for sieving, which is done manually by standing sieve of 10 mm size, to separate the
polythene, and other non-biodegradable material from the dung (Fig. 33 & Fig. 34).
Fig. 33 Dumping of Mule Dung Fig. 34 Sieve for screening of dung
● After segregation, the dung is subjected to composting by filling it into the circular pits
having diameter and depth of 12ft each respectively. Thus making total volume 1357
cu.ft. (approx 50 m3).
● The daily waste input is around 6TPD and total number of pits is 13. It will take
approx10-11 days to fill the pit completely.
● Bio-inoculant manufactured by M/s. Organica Biotech has been used to treat the waste
(Fig. 35).
● The waste is filled in the pits gradually by adding bio-inoculant after every 1.5ft layer
of dung. When completely filled the pit is covered and kept undisturbed till the
composting is done (Fig. 36).
● Approx. 3,00,000 (3 Lakhs) kg of manure has been distributed among farmers till date
free of cost.
Fig. 35 Bio-inoculant used for composting Fig. 36 Filled and Covered Pits
Forest Nursery, Kunia, Village Panthal:
The forest nursery has 900 CFT capacity vermicomposting unit. The unit utilized Farm
Yard Manure (FYM), procured from nearby villages. The duration of composting is
approx 150 days and earthworm variety Eisenia fetida is used for making
vermicompost (Fig. 37).
34
Fig. 37 Vermicomposting unit at Kunia, Village Panthal
A CAD model of Vertical Vermicomposting (Fig. 38) and assembly drawing of Vertical
Vermicomposting Setup (Fig. 39) is under progress after narrowing down the design
requirements as per the feedback and will be send manufactured soon.
Fig. 38 CAD model of Vertical Vermicomposting Setup
35
Following are the key features and design requirements for Vertical Vermicomposting Setup:
1. The design is for vertical vermicomposting
2. Sprinklers on the top of each box for water supply
3. Drawers can be pulled out fully for loading and un-loading
4. Water pump for supplying water in sprinklers.
5. Handles for easy pulling of boxes
6. Sliding mechanism (rollers) for boxes.
7. Good ground clearance for keeping some trolley during un-loading.
8. Space above the boxes for sprinklers and air circulation.
9. Holes on four sides of drawers for air circulation.
10. Holes at bottom of boxes for removal of excess water into drain.
11. Wheels for mobile setup.
Fig. 39 Assembly Drawing of Vertical Vermicomposting Setup
2.1.7 Dissemination of Improved Metallic Carpet Looms Developed by IIT Delhi for
Carpet Weavers at Jaipur, Rajasthan
a) Principal Investigator: Prof. S. K. Saha
b) Duration of Project: 06 Months
e) Project Commenced: 01/10/2018
f) Status: On-going
g) NGO partners: Rajasthan Carpet and Woollen Products
Development Society (RCWPDS)
Basement, Chamber Bhawan, MI Road, Jaipur,
Rajasthan
36
Summary:
India produces a large variety of carpets in terms of quality, size, and raw material. At present,
carpets are woven on wooden (Fig. 40a) and metallic (Fig. 40b) looms, which have several
drawbacks, like susceptibility to termites, low life (2-5 years), loss of environment friendly
trees, etc. Moreover, it is very difficult to provide tension to the warp, as it requires 4 to 5
persons and about 30-40 minutes. The tension is given by pulling a rope tied with a metal rod
on the upper and lower beams. To overcome the drawbacks of a wooden loom, IIT Delhi had
developed metallic carpet loom (Fig. 41) during 2007-08. Field trials indicated that the
designed metallic looms in which one person can easily give tension in about 10 min. are very
much acceptable to the users. Moreover, beam bending is also very small, providing uniform
tension that improves the quality of carpets.
Carpet looms are used for weaving woollen and silk carpets. During weaving different
operations are carried out, such as tensioning of warp, shading, knotting, cutting, and beating.
For these operations, some arrangements should be provided. While designing the loom
structure, its strength, ease of operation, high productivity, ergonomics (seating arrangement)
and cost should be considered so that they add maximum value for money. Carpet weaving is
the process of interlacement of warp and weft in a fabric. Here warp means longitudinal threads
that run parallel to vertical channel whereas, and weft means transverse thread that run across
the fabric (Fig. 42).
Some of the hand-knotted carpet making areas of India are:
● Uttar Pradesh: Mirzapur and Bhadohi (where 90 per cent of all carpets of country are
produced).
● Rajasthan: Jaipur, Jaisalmer, Ajmer and Barmer
● Madhya Pradesh: Gwalior
● Delhi (carpets as well as durries)
● Jammu and Kashmir (Persian designs), Ladakh (Tibetan designs)
● North-eastern states: Arunachal Pradesh, Sikkim and Manipur (Tibetan designs)
● Andhra Pradesh: Warangal and Elluru
● Tamil Nadu
● Karnataka
Regions specially known for hand tufting in India are:
● Haryana and Punjab Particularly Panipat in Haryana is famous for panja durries
● Tamil Nadu: Salem durries in Bhavani
● Karnataka: Jamkhan durries in Navalgund
● Andhra Pradesh: Bandha or ikat durries in Warangal
● Rajasthan: Jaisalmer and Barmer for woollen durries
37
(a) Wooden Loom (b) Metallic Loom
Fig. 40 Existing Wooden and Metallic Loom
Fig. 41 Hand tools (Knife and Beater)
Preliminary Investigations and Problem Formulation:
For further improvement of the developed metallic loom, it is required to be disseminated to
the users to gather feedback. During the previous workshop, it was identified that wooden
looms and older model of the metallic looms were being used in Jaipur, Rajasthan (Fig. 40b).
Hence, there is a need to create awareness about the new standardized metallic loom among
the weavers. It was decided that the looms could be provided to Rajasthan Carpet and Woolen
Products Development Society (RCWPDS) so that a wider user base can be made aware of the
new metallic loom.
Problems in the existing Wooden/Metallic Carpet Looms:
● Wooden/existing metal loom structure is susceptible to termites.
● Life is less (2-5 years).
● Due to high tension, bending occurs in the beams.
● Difficult to provide tension to the warp. (4 to 5 persons and about 30 to 40 minutes).
● Sometimes upper beam falls during weaving.
38
Fig. 42 Metallic Carpet loom designed and developed of by IIT Delhi during 2008-09
Objectives and Action Plan:
The objective of this project would be to manufacture and deliver two looms to Rajasthan
Carpet and Woollen Products Development Society (RCWPDS) for testing and feedback.
A vendor has been identified to manufacture and deliver the metallic carpet loom. The
identified vendor will be kept in the feedback loop so that necessary modifications may be
incorporated.
Present Status:
Three looms have been manufactured and sent three different locations such as one at
RCWPDS, Jaipur, Rajasthan, another one is at Mr. Jitendra Bonal, Pithoragarh, Uttarakhand
(Fig. 43), and one at Chirala, Andhra Pradesh.
First loom has been installed at Pithoragarh, Uttarakhand and five weavers were imparted loom
operation training. The express happiness during the usage of the loom which as reduced
drudgery. They said, modified loom has solve three problems such as non-uniformity tension
in the WARP thread, easy tension developed in the TANA, and ease in handling bigger length
carpets Second loom has been installed at Jain Arts, Village–Banskho, Tehsil–Bassi, Jaipur,
Rajasthan (Fig. 44) under the supervision of RCWPDS, Jaipur, Rajasthan.
39
Fig. 43 Loom installed at Pithoragarh, Uttarakhand
RuTAG team trained one weaver/ technician, for the operation of loom. The weaver/users
expressed happiness in using improved loom which eliminated their four problems have been
such as non-uniformity tension in the WARP Thread, easy tension developed in the TANA,
easy move one place to other place, and bigger size in length of darri will be weave on this
loom.
Fig. 44 Loom installed at Jain Art, Banskho, Tehsil-Bassi, Jaipur, Rajasthan
Third loom will be installed soon at Warangal under the supervision of Mr. Mohan Rao, Rastra
Chenetha Jana Samakhya (RCJS) Jandrapet, Chirala, Prakasam, Andhra Pradesh.
40
2.1.8 Design Improvement of Tulsi Mala Making Device for Bigger Beads.
a) Principal Investigator: Prof. S. K. Saha, ME, IIT Delhi
b) Duration of Project: 06 Months
d) Project Commenced: March 01, 2019
e) Status: On-going
f) NGO partners: Human social Welfare Society, Mathura,
Uttar Pradesh
Summary:
RuTAG IIT Delhi in collaboration with NGO – Human Social Welfare, Mathura conducted
a workshop and training at Jait village in Mathura to demonstrate Tulsi Mala Making device
(Fig. 45). Dhanendra Kumar , President of Human social Welfare Society, Mathura told
that around 2000 families in the villages near Mathura make Tulsi Mala beads to earn their
livelihood. Around 80% of the beads produced have size less than 15mm and remaining
20% of the beads produced have size ranging between 15 to 25 mm (Fig. 46). The current
design of Tulsi Mala making device developed by RuTAG IIT Delhi is capable of making
beads around 10-12 mm. The device uses a 12V DC motor which can draw current up to
5A. The NGO- Human Social Welfare Society, Mathura had expressed the need for
updating Tulsi Mala device so that it can be used to make beads of size 25mm. It was also
mentioned that the tulsi stem comes out of the stem holder (Chuck) while operation and
adjusting the tail stock pin is a cumbersome process. During the training users also pointed
out that the transmitted vibration from the motor was large and the machine produces lot
of sound.
Fig. 45 CAD Model of Tulsi Mala making Device
41
Fig. 46 Tulsi mala beads of different sizes made in Jait, Mathura
Objective and action plan:
Design improvement required in the device:
● To select motor which can meet the load requirement for the bead size of 25 mm.
● Redesign the structure as per the new load conditions.
● Redesign the concept of holding tulsi stem.
● Feasibility of replacing the existing switch with contact less switch.
● Including design concept to reduce the amplitude of transmitted vibration and
sound.
● Include hand rest to support hand that holds cutting tool.
Present Status:
Team from RuTAG IIT Delhi visited Jait Village to gather input required in the design
modification of Tulsi beads making machine. Load and power requirement calculation has
been done to turn tulsi stem of 25mm. A 100-watt AC motor with clutch to control the
speed of motor has been selected for turning operation. A prototype was made to test the
motor. Testing of motor was done in RuTAG Lab and beads of size 10 to 25mm were made.
To slide the motor during operation linear bearing and guide rail attachment has been
incorporated in the design. The attachment has the capability to absorb vibration
transmitted from the motor and thus the sound level produced by the machine has been
controlled. Sockets of closed spanner has been selected to hold tulsi stem. Design
modification of tool post has been done to handle tulsi beads. CAD model of new tulsi
beads making machine has been generated (Fig. 47). Next step is to fabricate modified
device (Fig. 48) and distribute it to the artisans for feedback.
Fig. 47 CAD Model of Modified Tulsi Beads making Device
42
Fig. 48 Actual Model of Modified Tulsi Beads making Device for bigger Beads
● The regional workshop conducted by RuTAG at Mathura on December 16, 2019
focused on training and demonstration of new tulsi mala bead making machine.
● NGO Human Social Welfare Society organised two weeks training for women at Jait
village, Mathura, Uttar Pradesh to operate new machine.
● New machine was demonstrated during the inauguration of Gandhi Haat at Rajghat.
● Two artisans from Jait received half-day training to operate the machine at IIT Delhi in
February 2020 (Fig. 49)
● From the recent feedback from artisans the speed of operation needs to be reduced as
higher speed is restricting the complete removal of the outer layer of stem. Also the
portion of the bead coming in contact with the tool post surface burns due to friction
and due to this dark spots are formed.
● There is requirement of design improvement of the tool post and chuck
● There is random power cut in the village and sometime artisans have to wait for a long
time to restart working. This also beaks the continuity of work. So, a solution has to be
thought to solve this issue.
Fig. 49 Artisan working on Modified Tulsi Beads making Device
43
2.1.9 Design Improvement and Fabrication of New Model Charkha (NMC)
a) Principal Investigator: Prof. R. Chattopadhyay, Textile
Technology, IIT Delhi
b) Co-Principal Investigator: Prof. S. K. Saha
c) Duration of Project: 06 Months
d) Project Commenced: March 01, 2019
e) Status: On-going
f) NGO partners: Khadi and Village Industries
Commission (KVIC), Mumbai,
Maharastra
Summary:
The New Model Charkha (NMC) is used to spin cotton yarn. The existing charkha is a
miniaturized version of ring spinning machine with drafting system and spindles. The
equipment is run by turning a handle. Under KVIC funded project design modification was
initiated and the driving system was changed. Instead of driving by hand, pedal operated drive
was introduced to make it hand free operation and using leg power.
The modified NMC (Fig. 50) was fabricated by a KVIC approved fabricator in Gondal, Gujrat
and sent for field trial in four different locations across the country. The feed has been found
to be encouraging.
Fig. 50 New Model Charkha
Preliminary Investigations and Problem Formulation:
Features of newly developed charkha
1. Dual drive i.e. Pedal or hand.
2. Free rotation of chain in case of accidental reverse turning of pedal.
3. Number of spindles increased from 8 to 10.
44
4. Ring rail movement smoothened.
5. Delivery increased by 10% (From 7.1 inches per single rotation of handle in
traditional NMC charkha to 7.83 inches per single rotation of pedal).
6. Hands free operation; support handle for balancing.
7. Twin spindle drive (single pulley drives two spindles).
8. Central seating arrangement of operator (ergonomically suitable).
There is still scope for improvement as stated below:
● Seat redesign (wider and back support) for ergonomic comfort.
● Height adjustability of seat for accommodating legs of different sizes.
● Speed monitor to help the operator to run it at optimum speed.
● Slightly large spindle to reduce spindle jumping and increase bobbin content.
Present Status:
To avoid the brakeage of threads an RPM meter (Fig. 51) was attached to the new model
charkha so that user can operate the machine at optimum speed. Seat re-designing for better
ergonomics and comfort is being done.
Fig. 51 Improved New Model Charkha
A ten Spindle New Model Charkha (Fig. 52) was purchased from Amber Utpadan & Research
Centre, Gondal, Distt.-Rajkot, Gujarat. The New design of table with seating arrangement will
be attached for better ergonomics and comfort for the users.
Fig. 52 Improved Ten Spindle New Model Charkha
45
A CAD model of Table with Sitting Arrangement for New Model Charkha (Fig. 53) and
assembly drawing of Table with Sitting Arrangement for New Model Charkha (Fig. 54) is
under progress and will be manufactured soon.
Fig. 53 CAD Model of Table with Sitting Arrangement for New Model Charkha
Fig. 54 Assembly Drawing of Table with Sitting Arrangement for New Model Charkha
46
2.1.10 Prevention of Stone Dust Inhalation for Stone Carvers at Bharatpur, Rajasthan
a) Principal Investigator: Prof. Debabrata Dasgupta
b) Co-Principal Investigator: Prof. Bahni Ray
c) Duration of Project: One Year
d) Project Commenced: January 01, 2019
e) Status: On-going
f) NGO partners: Lupin Foundation, Bharatpur, Rajasthan
Summary:
Inhalation of stone dust is a common and severe problem faced by labourers working in stone
quarry and stone crushing units. The silica traces present in the stones, if inhaled, can cause a
respiratory ailment known as ‘Silicosis’. The disease in its severe form can be fatal and there
is no known cure for silicosis till date.
Type of stones involved include sandstone and white marble. Stone quarry workers deal with
sandstone and the stone carvers work on white marbles. The workers in the unorganized sectors
are most affected since they do not have the proper economic and social support to create a
safe working environment for themselves. The images (Fig. 55) below show the stone carving
techniques (manual and mechanised) used in a mine near Bharatpur, Rajasthan.
Fig. 55 Stone carving Techniques (manual and mechanised) near Bharatpur, Rajasthan
Preliminary Investigation and Problem Identification:
A visit was made to a mine near Bharatpur, Rajasthan, to observe and study the working
environment and working process of the stone carvers. The following observations were made
in that regard.
● Artisans use both manual and mechanised way to carve the stones based on the
applications.
● Particulate measurement devices reported abnormally high amount of particulate matter
concentration in the working environment.
47
● Use of water to supress the dust is not feasible due to severe water shortage.
● P1 Masks are provided by the contractor. Proper maintenance and utilization of the mask
is not done.
● Labourers prefer thinner mask since the current mask is bulky and restrictive.
● It was noted that the local government body compensates the artisans who are contracted
with silicosis with a sum amount of Rs. 2.00 Lakhs. This may be one of the causes of
observed lack of interest to prevent silicosis among the artisans.
Preliminary Objectives:
Based on the observations, following objectives are formulated.
a) A socio-economic study to completely assess the situation: A study will be required to
completely understand the ground level situation of the artisans. To fulfil this, a socio-
economic study will be planned and conducted. The study will be aimed to understand
the main reasons that hinder the labourers from using the masks provided, the impact
of silicosis on the artisans and the precautions taken up by them to prevent the same.
b) Technical solutions to prevent the inhalation: Based on the socio-economic study,
technical solutions will be developed that can prevent the inhalation of stone dust by
the artisans. This may include dust suppression at source, low cost masks, controlled
environments, etc., based on the technical and economic feasibility.
Present Status:
Prof. Debabrata Dasgupta, along with RuTAG staff visited the cluster to observe the
problems faced by labourers working in stone quarry and marble carving units. Two
groups of students under Prof. Debabrata Dasgupta and Prof. Bahni Ray are working
on two alternative prospective solution models. One on a portable and affordable glove
box setup (Fig. 56), and the second group on vacuum attachments for the tool. The
proposed solutions are currently being assessed and tested in the prototype stage.
Fig. 56 Portable and affordable Glove Box Setup
48
Two designs were thought of to address the problem of stone dust inhalation – A
portable glove hood, and a suction system. The portable glove-hood is made by using
PVC sheets over a steel frame (Fig. 56). Two access holes are provided, using which,
a person’s hands could be comfortably inserted inside the dome, and the cutting
operation could be done. Anti-static spray is applied to prevent the sticking of dust
particles on the dome surface in order to maintain proper visibility inside the dome. The
advantages of this system are many: the system is versatile, cheap, and portable. The
system has been developed and tested successfully at IIT Delhi, where the stone
particulate concentrations have been measured (PM 1, PM 2.5, PM 4 and PM 10) with
and without the use of the ventilation hood. The use of ventilation hood has been found
to be effective in reducing the particulate concentration at the stone carver’s inhalation
level considerably. However, the field-testing of the setup is still pending. The
prototype of the suction system was developed and tested at IIT Delhi.
2.1.11 Truncated Unglazed Percolative Clay Ceramic Ware as a Modified Pitcher
Irrigation System
a) Principal Investigator: Prof. Anand Plappally, IIT Jodhpur
b) Co-Principal Investigators: NA
c) Duration of Project: 09 Months
d) Project Commenced: July 01, 2019
e) Status: On-going
f) NGO partners: Sehgal Foundation, Gelabaas village in
Luni block, Jodhpur, Rajasthan
Summary:
Truncated unglazed porous clay ceramics are recently used in several parts of India for
household drinking water filtering purposes. Flow rate through these porous filters named G-
filters in fully filled conditions was found to be 950ml/h. This technology is presently available
in some areas neighboring the Thar Desert. These areas have poorly drained soil therefore a
ditch or tile (porous clay pipe) is a potential drainage solution. Porous vessels such as pitchers
and tiles are used for sub-surface irrigation (Fig. 57). From history, it is also known that
societies residing in the arid regions in India used to practice this sub surface irrigation
technology. This technology was said to be invented by prehistoric north African farming
communities provides exemplary yields from crops. For example, the pitcher irrigated farm in
India fetched melons amounting to 0.1x 105 kg/acre with very low water requirement. Pitcher
irrigation is also good to conserve water with high effectiveness. Water from the pitchers wash
away the salts in the soils to the far edges of the wetted boundaries of the soil defined by porous
transport of water about the pitcher surroundings. The unglazed truncated porous clay ceramics
“the G Filters” are having porosity in the range 36-42% will be good enough to wash away
salts in the loamy saline soils of Jodhpur thus helping to desalt. With the availability of
truncated porous clay ceramics with controlled percolation rates in the areas near Thar, it may
be a boon to re-introduce this irrigation technology in these desert lands. According to UN,
49
there is need to install such technologies especially in area with precipitation lower than 500
mm/year.
Fig. 57 Model Arrangement of the Truncated Unglazed Porous Clay Ceramics for Sub-
surface Irrigation
Preliminary Investigation and Problem Identification:
Salt affected soils of Rajasthan are spread over an area of 374942ha. Large amounts of soluble
salts or exchangeable sodium in the soils affect the growth of crops in Rajasthan. Further the
ground water in the Jodhpur district region is also salty. Table 1 showing the recent water
analysis performed for waters from Arna Jharna Museum, Jodhpur, Rajasthan.
Table1: The ground water salinity in one of the locations in Jodhpur.
Plants showcase stunted growth in soils with high salinity. It is said that irrigation using porous
clay tiles and pitcher have been proven to be successful to leach salt out from the neighboring
soils by the water carrying tile or pitcher. Unglazed truncated porous ceramic structures placed
50
inside the soils can desalinate the soils. The soils of most of the location are having negligible
carbon content as well as nitrogen which is needed for plant growth. Animal waste and plant
fiber geo-textiles can be used to improve the carbon and nitrogen content in these soils.
Objectives and Action Plan:
● Carry out soil analysis in farm sites in salt affected 5 villages: It is proposed that the
farmland affected with soils will be selected and soil test will be conducted using the
commercial soil analysis test kit. The nutrients in the soils will be noted.
● Installation of truncated unglazed clay ceramics ware below the ground surface as
shown in Fig 44. An array of 50 porous vessels in an area of 5000 ft2 in each farmland
will be installed. These vessels will be surrounded by animal dung to improve nitrogen
content in the surrounding soils and local geotextile mats made of Crotolaria Burhia
(Siniya in local Marwari dialect) will be laid surrounding each porous vessel to suppress
wind erosion.
● Plants for the trails: Brinjal and Okra are the vegetables that will be grown during the
seasons and will be studied for understanding the influence of the technology on their
physical and structural attributes while they grow on saline soils.
With these interventions, it is expected that the salinity of the surrounding soils near to the
porous vessel will diminish. Plants will show better growth. Carbon, Phosphorus and
Nitrogen content are supposed to improve in the soils in the Kharif and Rabi seasons. Water
saving per plant is supposed to increase when compared with control trials. Here the control
trails are proposed on two separate 5000 ft2 lands without any treatment and the other with
geotextile or any local soil stabilization treatment.
● Post- Treatment Soil Analysis: All the five trials and two controls are supposed to
influence soil fertility and quality. Therefore a weekly assessment of the soil fertility
parameters and salinity levels will be performed.
The first trials are proposed in Rudiya Village, (Bhopalgarh block), Banad Village,
Jodhpur, Salawas Village, Jheepasni village (IIT Jodhpur, Campus C) and a village in Luni
block (along with M.S. Sehgal Foundation). Five student teams will work over the next one
year on this project. The plan of work is extending to two seasons Rabi and Kharif. The
elaboration of the same is given in the Gantt Chart below.
Main Objectives:
1. To re-introduce the Pitcher irrigation or Matka Irrigation in arid Western Rajasthan.
2. To propose a modified sub-surface irrigation by changing shape, and introducing
mechanization.
3. To provide distinct materials specific to the location, required micro-structure and could
be locally manufacturable.
4. To overcome disadvantages of drip technology/micro irrigation (regarding energy,
many parts, water efficiency and also plastic use).
5. To bring in a technology which can provides assimilative nutrient to the roots
effectively.
51
6. To re-establish the multi-level perspective network between potter and farmer which
existed within the village.
Present Status:
Dr. Anand Plappally elaborated about the Picher irrigation system and its significance like, it
is good for preparing transplants or direct seeding, it enhance seed germination and
establishment in very hot, dry conditions, and it is more reliable than drip irrigation systems,
which are more likely to be clogged up by soil, salt, insects or damaged by animals, require flat
fields. He told that the main objectives of the project are to re-introduce the Pitcher irrigation
or Matka Irrigation in arid Western Rajasthan, and to propose a modified sub-surface irrigation
by changing shape and introducing mechanization. The system is currently under testing at
Gelabaas Village, Rudiya Village, Banad Village, IIT Jodhpur Experimental campus, and
Salawas village in Jodhpur.
We have to reduce water use energy, use improve root nutrition, improve irrigation efficiency
for a specific volume, decontaminate the soil and yet best yield (Compete with best in the
market).
Manufacturing process of G-filter - see the machine manual for steps (Fig. 57 - a to d). Drying
in shade for two days, then for 7-10 days under sun may vary with location (Fig. 57 - e). After
burning in a furnace (Fig. 58 -f). Porosity can be varied according to location and need for
water table management (Fig. 59).
Fig. 58 Photograph of Stages of Manufacturing
52
Fig. 59 Porosity can be varied according to location and need for water table
Even Neem oil medication being directly applied using the G-filter to get rid of root fungal
problems for the lemon crop (Fig. 60) at Esau Village, Sirohi district, Rajasthan, India.
Soil properties changes before and after the Porous Vessels were embedded. Test were
undertaken at Krishi Vigyan Kendra, Paota, Jodhpur as shown in Table-2.
Fig. 60 Using the G-filter to get rid of root fungal problems for the lemon crop
Table-2: Test were undertaken at Krishi Vigyan Kendra, Paota, Jodhpur
Standard Unit Normal Values Initial
Test
28/6/19
Initial
Analysis Near the
Porous Vessel,
11/09/2019
Centre of
the field,
11/09/2019
At boundary,
11/09/2019
pH 7.0 to 8.5, normal alkalinity
8.5-9.5(high alkalinity)
8.6 Moderately
alkaline
8.7
8.6
8.5 Electrical
Conductivity
( EC, dS/m)
Less than 1.5 (low), good
(1.5-3.0), more than 3 (more
salts)
1.36 Moderately
alkaline
0.33
0.19
0.18
Organic Carbon
(%) 0.5 (low), 0.5-0.75-
Medium, more than 0.75
(maximum)
0.1 less
0.13
0.13
0.11
Phosphorous
(P2O5kg/ha) 23.0 (low), 23-56- Medium,
more than 56 (maximum)
46 medium
26
49
36 Potash (K2O
kg/ha) 144 (Low), 144-336
Medium, more than 336
(maximum)
414 more
355
404
452
53
Zinc (ppm) More than 0.6 0.32
less
0.26 0.28 0.32
Iron (ppm) More than 4.5 1.82
less
1.94 1.7 1.86
Copper
(ppm) More than 0.2 0.48
normal
0.56 0.52 0.5
Manganese
(ppm) Less than 2 (normal soil)
More than 2 (More) 4.68 normal 4.42 4.54 4.96
2.1.12 Proposal for Improvement in the Batasha Making Process Phase-II
a) Principal Investigator: Dr. Vinay Gupta, IEC Greater Noida
b) Co-Principal Investigators: Mr. Nurul Hassan Laskar
c) Duration of Project: One Year
d) Project Commenced: December 01, 2019
e) Status: On-going
f) NGO partners: Lupin Human Welfare & Research
Foundation, 160-Krishna Nagar,
Bharatpur, Rajasthan
Summary:
Batasha is a very commonly known name in the households of Indian families. It is a traditional
sweet dish used in offerings to God and also used in Indian marriages. Sugar is used as its main
ingredient and is available at cheap rates hence is easily affordable by all categories of the
Indian society.
Batasha is prepared by making a mixture of water, sugar, milk, citric acid, retha and
hydrosulphite in appropriate amount. This mixture is heated in a pan called dhaura up to the
temperature 100-110 centigrade. After this, dhaura is taken form furnace and in the process
of continuous stirring and rubbing the drop of this mixture is dropped on plastic sheet through
a tool call Chidiya. The drop of mixture distends and after few seconds get solidify and batasha
is ready as shown in Fig. 61.
The batasha making process is tiring and unhygienic, to eradicate the same a set-up was
designed and build shown in Fig. 45 in the first phase of this project. The set-up is a three rack
setup which is slidable over the channels and one can adjust the height of the set-up as per the
users’ requirement. Also, it is modular in nature. Person can sit comfortably on the chair and
make batasha. The set-up takes care of both the issue of drudgery and hygiene (Fig. 62).
However, to make the set-up more user friendly and as per the feedback of the artisans the
furnace used to heat batasha solution is also to be lifted to the level of sitting person along with
some changes to improve stability and life of the setup.
54
Fig. 61: Batasha making process Fig. 62: Existing setup developed in Phase-I
Preliminary Investigation and Problem Identification:
On the basis of feedback of the batasha artisans, following modifications are proposed:
1. Furnace which is on the ground level it is to be redesigned to lift up so that artisan siting
on chair can work easily and conveniently.
2. In the existing setup plywood has been used as a material of the rack. It is observed that
plywood gets bend itself with time. It reduces the space between the racks which was
as per the height of batasha.
3. During the batasha making the setup has little sway movement.
4. Rigorous testing to study production rate is to be done.
Preliminary Objectives for the Improvement:
As per the problems in Section 2, following improvements are envisioned to be carried out as
a project:
1. Design of furnace so that the efficiency better than underground furnace can be
achieved.
2. Selection of suitable material for rack plate.
3. Rigorous testing to study production.
4. Some design modification related to assembly and stability.
Present Status:
To overcome the problems of traditional batasha making process a three rack setup was
developed under the project ‘Improvement in traditional batasha making process’. This project
further needs rigorous testing, modification in design and synchronisation of furnace with the
setup. In contrast of which we have done few testing, some modifications, etc. which are
mentioned below:
Visit to Ghantaghar, Naya Ganj, Ghaziabad on October 15, 2019 (Fig. 63):
Our motto to test the developed set-up and get the feedback.
55
Fig. 63 Testing of previous Setup
Feedback by batasha artisan and our observation:
● New plates should be fabricated. As the old ply has bend with time. Hence, material is
to be found out to make the plate of the rack.
● Plates covering with suitable material.
● Stability of setup is needed to be improved.
● Design and fabrication of chair for back support.
● Synchronisation of furnace for proper analysis of production.
Fabrication of new plates with covering material:
The plates with aluminium composite were fabricated to overcome the bending as well as
problem occurs with change in environment conditions (Fig. 64). The plates are covered with
thick cotton cloth (called as bashana).
Fig. 64 New Fabricated Plates
56
Second visit to Ghantaghar, Naya ganj, Ghaziabad on October 27, 2019 (Fig. 65):
After changing the plates and addressing stability issues the visit was organised to test the
same.
Fig. 65 Testing on the New Fabricated Plates
Design and fabrication of C-clamp shown in Figure 66 (a, b, and c):
C-clamp is designed and for the easy installation of nut and bolts which joins the base stand
and channel.
Fig. 66 (a) CAD model C-clamp Fig. 66 (b) Modified C-camp
Fig. 66 (c) CAD Model of New Modified Setup
57
Modified setup sent to Kolaghat, West Bengal:
During visit of Prof. S. K. Saha, PI, RuTAG, IIT Delhi to College of Engg. & Management,
Kolaghat, West Bengal, Prof. Dipak Kumar Mandal, Associate Professor, at the college shown
interest in Batasha set-up and requested for one set. Therefore, Prof. Saha asked us to send a
set-up to Prof. Mandal. One set-up was sent and reached safely (Fig. 67). The feedback on the
set-up is awaited from Prof. Mandal.
Fig. 67 Packed Setup Reached Safely at Kolaghat, West Bengal
2.1.13 Improvement in Bhilawa Seed Decortication Process
a) Principal Investigator: Dr. Vinay Gupta, IEC Greater Noida
b) Co-Principal Investigators: Dr. Mukesh Kumar, IEC Greater Noida
c) Duration of Project: One Year
d) Project Commenced: December 01, 2019
e) Status: On-going
f) NGO partners: KARuNaH Society for Development,
Bodkhi, Amla, Dist.- Betul, Madhya
Pradesh Summary:
Semecarpus anacardium (also known as Bhilawa in Hindi) is a plant whose seeds are
mainly used as medicines. It is also known as bibba in Marathi & Agnimukh in Sanskrit. It
is used cure many disease. Sanjivani Vati and Sanivani Gutika are few market products
made using bhilawa. Without purification it is poisonous along with its medicinal
properties. And the oil from its seeds can give blisters and painful wounds. Fig. 68 and 69
shows Bhilawa fruit and seed.
Fig. 68 Bhilawa Fruit Fig. 69 Bhilawa Seed
58
Preliminary Investigation and Problem Identification:
Traditionally in decortication process the shell is break with the help of a small metal rod
or stone while holding the seed with other hand (Fig. 70). During this process the hands
and some of the body parts come in contact with the oil which splashes due to hitting the
seed. Since the oil of the seed is toxic in nature it burns the skin wherever it splashes on the
body.
Fig. 70 Traditional Method of Bhilawa Decortication
Few years back TATA Centre of Technology and Design, IIT Bombay designed and
developed a machine (Fig. 71) for de-shelling the seeds of Bhilawa.
Fig. 71 Fully functional bhilawa de-shelling machine by TATA Centre of Technology
and Design, IIT Bombay
After study, following points revealed:
a) Decortication is done with the help of traditional method (by hands) or with the de-
shelling machine developed by TATA Centre of Technology and Design, IIT
Bombay. Both the process involves other hand to hold the seed, knowing the fact
that the oil of fruit is toxic in nature and while breaking its shell, oil can damage
fingers shoddily.
b) While performing the decortication process, oil splashes to exposed body parts.
This is another problem that also not taken care in the de-shelling machine
developed by TATA Centre of Technology and Design, IIT Bombay. There is no
protective shield (transparent plastic film or glass) installed in the front part of the
machine.
c) Time taken in decortication process of the fruit is quite a lot. Hence, it affects the
production of the seed.
59
Preliminary Objectives for the Improvement:
As per the problems in Section 2, following improvements are intended to be carried out
as a project:
a) Primary objective to develop machine tool to have absolute hand free experience
while breaking the shells of the fruit keeping other required safety measures.
Present Status:
A. Literature Review - The literature is as follows:
a. Some of the Available Techniques:
The two basic actions can be used to open the shell of a seed (nut). One is caused by an
impact on the seed against a hard object, or applying direct mechanical pressure to crush,
cut or shear through the shell. The stated actions can performed manually using knives,
hammers, simple presses, etc. Some the techniques used given below. Also, the action can
be used to make a machine (Fig. 72). A hand press machine for Bhilawa seed decortication
was developed by IIT Bombay (Fig. 73).
Centrifugal impact
decorticator
Peg and drum
decorticator
Bar and drum
decorticator
Parallel gap disc
decorticator Tapered gap disc
decorticator
Reciprocating
action decorticator
Parallel cylinder decorticator
Fig. 72 Action can be Used to Make a Machine
60
Fig. 73 Hand press deeloped by IIT Bombay
b. Study of Physical and Mechanical Properties:
Physical properties of Bhilawa fruit and seed (Table-3):
Sl.
No.
Properties Fruit Seed
1 Shape Obliquely ovoid nut Ovate, oblong to conical,
irregularly flattened
2 Size
Length= 2.5-3cm
Width= 2-2.5cm
Thickness= 0.4-4-0.5 cm
Length= 1.2-1.8 cm
Width= 0.8-1.4 cm
Thickness= 0.5-0.8 cm
3 Colour Brownish black Reddish-brown
4 Taste Acrid and highly irritating Slightly sweet and oily
5 Ridges Longitudinally wrinkled NA
6 Surface Smooth, shining Rough
Mechanical properties of Bhilawa fruit and seed (Table-4):
Sl. No. Mechanical properties Bhilawa fruit Seed (Kernel)
1 Rupture force (kg) 37.17 17.20
2 Deformation (mm) 3.61 2.65
3 Hardness (kg/mm) 10.82 6.49
4 Energy used for rupture (kg-mm) 134.80 45.58
5 Deformation at rupture point 0.20 0.11
61
B. Site Visit to Pattan Village in District of Betul, Madhya Pradesh on Nov. 16-19, 2019
(Fig. 74):
Two of our students Mr. Shekahar Chauhan and Mr. Sarthak Machkoria visited the Pattan
village, Betul, Madhya Pradesh with Mr. Suraj (Research Scholar, RuTAG, IIT Delhi) to gain
the experience how people their decorticating Bhilawa and to know their challenges.
Fig. 74 Womens Decoticating Bhilawa Seed
Following are the observations:
a. In this village, people generally purchase Bhilawa fruit bag weigh around 56 kg.
b. Cost of one bag is approimately Rs1000/-.
c. Out of that 56kgs of Bhilawa fruit, after decortication they got around 7 kg of seed and
6 litre of oil which is extracted from the waste shells of the fruit.
d. In the market, they sell seeds and oil. Selling price of seed is around Rs.400–500 per
kg and of oil is around Rs.10-20 per litre.
e. They get profit of around Rs. 600-1000 on each bag they purchase.
f. They use the method of breaking the Bhilawa seed with rod or stone.
g. For safety, they wrap their hands with cloth and wear the cloth apron also. The proper
safety measures were not available.
C. Design Ideas:
To ease the decortication process and increase the production level of bhilawa, two
design ideas are presented. One is manual (requires man power to operate) and the other
is motorized (it operates with the help of motor and toggle mechanism). This can also
be modified for manual operation.
a. Manual Machine (Fig. 75):
The manual machine uses the manually operated press principal where the person will
apply force with the help of a handle. Below is the image of the same for better
understanding.
62
Fig. 75 CAD Model of the Manual Machine
b. The automatic machine adds up a piston-cylinder arrangement and powered with a motor
with the help of toggle mechanism. Below is the image of the automatic machine design
for better understanding (Fig. 76).
Fig. 76 CAD Model of Motorized Design
3. Follow-up Projects after Completion
3.1 A Device for Making Tulsi Mala Beads
3.1.1 Status after Completion
● One hundred thirty five devices were manufactured by Ms. Omwati Devi at Bharatpur.
● All sold.
● A new version of non-contact switch (Fig. 77 and 78) is under development.
63
3.1.2 Increased in Sales of Device after Modifications (Fig. 79)
The devices are being manufactured by a Carpenter in the Nadbai village, Bharatpur district,
Rajasthan. They have sold 135 devices, some locations in the area as mentioned below:
1. Chainpora, Bharatpur – 01
2. Khanwan, Bharatpur – 01
3. Raja Khera, Bharatpur – 03
4. Belara, Bharatpur – 01
5. Bharatpur district – 06
6. Deeg district – 01
7. Mahila Bal Vikas Gramudhyog
Shikshia Samiti, Bharatpur – 09
8. Dholpur district – 07
9. Alwar district – 10
10. Lupin Foundation, Bharatpur – 23
11. Ahmedabad, Gujarat – 02
12. Kolkata, West Bangal – 01
13. Nadiad, Gujarat - 01
14. Karnataka - 01
Fig. 78 Position of the fingers to start
the motor with Contactless Switch Fig. 77 Position of the fingers before
starting the motor with Contactless Switch
Fig. 79 Latest Developed of Tulsi Mala making Device
64
3.1.3 Buy RuTAG IIT Delhi products through FITT
A facility has been created by RuTAG IIT Delhi in collaboration with Foundation for
Innovation and Technology Transfer (FITT) at IIT Delhi under the scheme of
“Innovative Product Delivery” to sell the following field tested products directly to the
hands of the users on payment basis:
3. Animal Driven Prime Mover
4. Batasha making Process
5. Bullock Driven Tractor
6. Carpet Loom
7. Ground Water Level Measuring Device
8. Marble Artefacts
9. Potters Kiln for Pottery Items
10. Sheep Hair Shearing Machine
11. Treadle Pump
12. Tulsi Mala Making Device
13. Tulsi Mala Making Device for Bigger Beads
We intend the users to make payment to FITT, IIT Delhi based on the fabrication cost and
delivery charge quoted by the respective vendor of the above devices. The deposited fund will
be utilized by RuTAG IIT Delhi to manufacture and deliver the products to the users. The
following products were sold through FITT (Table-5).
The products were sold through FITT (Table-5):
Sl. No. RuTAG IIT Delhi Technologies Name of
Purchasers
Name & Address of Organization
Name of Technologies Qty.
1.
Tulsi Mala Making Device 01 Mr. Amit Jain
Shantidhara Dugdh Yojna
Sagar, Madhya Pradesh
Treadle Pump 01
Bullock Driven Tractor 01
Animal Driven Prime Mover 01
2. Tulsi Mala Making Device 02 Mr. Amar Pal Singh Nabha Power Limited (L&T Power
Development Limited). Rajpura, Punjab.
3. Tulsi Mala Making Device 02 Mr. Saumendra Das SAMPARK, 4th Lane, Nilachakra
Navarro, Athr Nala, Puri – 752002,
Odisha
4. Treadle Pump 01 Ms. Vinny R. Peter Centre for Urban Biodiversity
Conservation and Education (CUBE),
Coimbatore, Tamil Nadu
5. Tulsi Mala Making Device 01 International Society for Krishna
Consciousness (ISKCON), Mathura, U.P.
6. Tulsi Mala Making Device 01 Dr. Jainendra
Shukla
Indraprastha Institute of Information
Technology, Delhi
7. Tulsi Mala Making Device 01 Ms. Madhumita House No. A/2, Mahanadi Bihar, Near
police outpost, And bakers Delite,
Cuttack, Odisha
8. Tulsi Mala Making Device 01 Mr. Rathore Korba, Bilashpur, Chhatisgarh
9. Tulsi Mala Making Device for
Bigger Beads
01 Mr. Sanjeev Kumar
Sharma
Kamda Mahila Agarbatti Udyog, Kasim
Bazar, Munger, Bihar
65
4. Reporting
4.1 Workshop Organised during April 01, 2019 – March 31, 2020
4.1.1 RuTAG IIT Delhi Regional workshop conducted on June 03, 2019 at Khamir,
Gujarat.
RuTAG IIT Delhi organised a Regional Workshop at Bhuj, Gujarat in collaboration with
KHAMIR, Bhuj, Gujarat during June 3-4, 2019. Three faculty from RuTAG IIT Delhi, Prof.
R. R. Gaur, Prof. S. K. Saha, and Prof. M. R. Ravi (Fig. 80), three project staff, Mr. Davinder
Pal Singh, Mr. Ashish Dahiya, Mr. Yashwant Prasad, one RuTAG Club Member, Mr. Rutvik
Solanki, and Mr. Raviveer Chaudhary, Assistant District Commissioner, DHC, Mr. Lal
Rambhia, Kutch Nav Nirman Sansthan, three persons from KHAMIR, Mr. Ghatit Laheru, Mr.
Shouryamoy, and Mr. Harish Hurmade along with 25 other delegates from various NGOs,
institutions, and other organizations have attended the workshop. Prof S. K. Saha welcomed
all the participants with his warmth gratitude and explained the RuTAG concepts and work,
followed by the introduction of the participants. Prof. Saha presented the RuTAG technologies
and interventions such as Bullock Driven Tractor, Treadle Pump, Ground Water Measurement
Device, Sheep Shearing Device, Tulsi Mala Making Device, etc. Prof. Ravi presented the
furnace related technologies such as Improvement of Bangle making furnace at Bharatpur,
Rajasthan, updraft potter’s kiln with the use of rat-trap technology, and bell metal furnace. Mr.
Ghatit Laheru, Mr. Jigar Vaidya, and Mr. Shouryamoy Das presented about the technologies
on which Khamir is working on such as Wool Development programmes in collaboration with
Gujarat Sheep and Wool Development Board, Bhuj, supporting Copper bell making artisans,
and other textile related technologies. They also presented some technical interventions
required for the artisans near Bhuj. Prof. Gaur, along with session chairs, had conducted the
Conclusion session in which he stated the steps to be taken for resolving the technical problems
that were proposed by the participants. At the end, Prof. Saha and Prof. Gaur thanked the
participants and invited them to join the field visit to nearby villages to look into the technical
interventions required for them on the next day.
Fig. 80 Prof. M. R. Ravi, Mr. Raviveer Chaudhary, Prof. S. K. Saha, Prof. R. R.
Gaur, Mr. Lal Rambhia, and Mr. Ghatit Laheru during the RuTAG Regional
Workshop at Bhuj, Gujarat
66
Next day (June 4, 2019), RuTAG IITD team along with Khamir team and some other
Workshop participants visited Nana Reha Village where the work for making swords and
knives was going on (Fig. 81). The artisan showed his work and the furnace to the team for
better understanding. They were using mechanical hammer machine for sharpening of the
swords and a furnace for heating of the material upto the moulding temperature. The team
noticed the living conditions and the techniques of the villagers to suggest some possible
interventions.
After that Mr. Ghatit Laheru took RuTAG IITD team and other participants to Zura village
where about 35 families are working on making traditional copper bells (Fig. 82). The main
issue with the existing process is that the artisans could bake only one or two bells at a time
and the way the furnace is being used is also not efficient and it consumes a lot of raw material.
These technological inputs that were required to boost the livelihood of the community were
noted down and Prof. Ravi from RuTAG IIT Delhi will be working on the same. Khamir had
initially done some improvisations regarding the furnace in which the villagers bake the bells
for uniform coating of copper. But still some significant improvisations are required which can
help the artisans to improve their productivity and to reduce the time and raw material
consumption. After that the delegates visited a pottery cluster in Bhuj, where team noted some
of the problems such as requirement of improvement in pottery kiln (Fig. 83), sieving of clay
through screen, etc. After that team visited Hunnershala where Mr. Mahavir Acharya showed
the campus made up of several organic building materials. Ms. Barkha invited RuTAG team
to visit Shrujan LLDC campus, where they showed some museum preservation techniques that
have been implemented for long lasting age of craft displayed. Then Mr. Raviveer Chaudhary
invited RuTAG team to attend the on-going “Shilpotsav” event at Bhuj Haat. Prof. Saha, Mr.
Davinder Pal Singh, and Mr. Ashish Dahiya attended the programme from RuTAG Team and
Fig. 81 Sword and Knife Manufacturing Facility at Nana Reha
67
Fig. 82 Artisans Demonstrating the Copper Bell Manufacturing Process at Zura village
Mr. Ghatit Laheru attended the programme from Khamir. There Mr. Raviveer welcomed the
event participants and artisans, He invited Prof. Saha and Mr. Singh to dais. Prof. Saha
addressed the participants and distributed the participation certificates to the artisans. At the
end, Prof. Saha and Mr. Davinder Pal Singh thanked Mr. Raviveer and the participants and
returned back to Khamir.
Fig. 83 Visiting Potters Community in Bhuj
4.1.2 RuTAG IIT Delhi Regional workshop conducted on December 16, 2019 In Collaboration
with Human Social Welfare Society, Hathras held at Hotel Wingston, Masani, Mathura,
Uttar Pradesh.
RuTAG IIT Delhi, in association with Human Social Welfare Society, Hathras, organized a
one-day regional workshop in Hotel Wingston, Mathura on December 16, 2019 [Fig. 84 (a)
and (b)]. This workshop primarily focused on Tulsi Mala Bead Making Device. Around 20
artisans who make Tulsi beads for their livelihood attended the workshop. Artisans hailed from
a nearby village Jait, and some came from Bharatpur, Rajasthan. Apart from the artisans, there
were representatives from various government and voluntary organizations such as DC
68
Handicrafts, NABARD, RSETI, Ministry of Textiles, Ministry for MSME, Lupin Foundation,
Jan Vikas Sansthan, and Adarsh Yuva Samiti.
Fig. 84 (a): Core committee on Dias during Regional Workshop of RuTAG IIT
Delhi at Hotel Wingston, Mathura, U.P.
Mr. Davinder Pal Singh (Project Associate, RuTAG IIT Delhi) initiated the workshop by
greeting the participants. Prof. S. K. Saha, Coordinator – RuTAG IITD, welcomed the audience
and mentioned that this workshop would be primarily focussing on the Tulsi Mala device. He
then requested the participants to introduce themselves so that the participants get acquainted
with each other. Prof. R. R. Gaur, Chairman, Core Group, RuTAG IITD delivered the welcome
address wherein he stressed the importance of premier institutes like IITs channelling their
research toward the improvement of rural livelihoods. He also mentioned how field-based need
identification is a crucial part of problem-solving. He also thanked the govt. organizations for
attending the workshop and apprised the audience about the role of govt. organizations and
ministries in the development and dissemination of technologies. Prof. Saha and Prof. M. R.
Ravi later explained in brief about various technologies developed and disseminated by
RuTAG IIT Delhi. In the next session, organizations presented their work, schemes available
for the artisans, and they put forward some of the technical difficulties faced by the artisans.
Post lunch, Mr. Yashwant Prasad conducted a game where the artisans formed groups of five
and tried to assemble the Tulsi Mala Device, whose parts were kept in a disassembled state on
the table [Figure 84 (c)]. Later, Prof. Saha, Mr. Raj Kumar Gupta, and Mr. Yashwant Prasad,
took the audience through the journey of Tulsi Mala Bead Making Device with the help of
presentations. After that, Ms. Omwati and Mr. Laxman demonstrated the use of the new Tulsi
Mala Bead Making Device to other artisans. Later each of the artisans was trained by them to
use the device and make beads. Artisans liked the new device and were eager to try it out more
so that they could use the device on a regular basis.
Prof. Saha and Prof. Gaur concluded the session by taking feedback and comments from the
audience. Mr. Dharmender from HSWS proposed the vote of thanks.
69
Figure 84 (b): Group photo of RuTAG IITD Team and Participants of the Workshop
Figure 84 (c): Demonstration and Training of Tulsi Mala Bead making device during the
workshop
4.1.3 RuTAG Management Development Programme at IIT Delhi during October 2-4,
2019 (In association with IIT Kharagpur).
Rural Technology Action Group (RuTAG) is continuously working on the transformational
practice of technology development incorporating Government agencies, NGOs, Researchers
and Academicians with in intent to deliver innovative interventions in rural sectors. The prime
70
mission of RuTAG is to ameliorate the rural systems to the most efficient level for upgrading
the rural economy.
A three-day program entitled “Management Development Program (MDP) on Rural
Entrepreneurship” was organized from October 2-4, 2019, at IIT Delhi [Fig. 84 (a) and (b)]
that took the participants through an engaging discussion that would help in facilitating people
interested in becoming a competent rural entrepreneur and setting up a rural enterprise.
The inauguration session was graced by Dr. Ketaki Bapat, Scientist ‘F’, Principal Scientific
Adviser to the Government of India; Prof. S. K. Saha, Coordinator and Principal Investigator,
RuTAG IIT Delhi; Mr. Varun Vidyarthi, Director, Manovodaya, Lucknow, U.P. The MDP was
coordinated by Prof. Varun Ramamohan of IIT Delhi and Prof. Bhaskar Bhowmik from
Rajendra Mishra School of Engineering Entrepreneurship, IIT Kharagpur. Prof. Bhowmik gave
a brief insight about the orientation and theme behind this program. Prof. Bhowmick mentioned
the theme of this program centered around the question as to how one goes form a technological
solution developed to solve a local rural problem to a full-fledged enterprise that manufactures,
markets, and distributes a product to make a sustainable outcome.
The participants were made aware of the basics; what is a product, difference between product
and service, what is a rural enterprise and its importance, what are the various business models,
critical success factors for setting up rural enterprise, assessing marketability. The program also
offered the participants an excellent idea to various theories of Techno-Management practices
such as Finance, Marketing, Human Resources, Information Technology, Skill-Development,
Supply Chain Management, Quality Improvement. The participants also got an exposure to
various complexities, uncertainties, challenges associated with rural enterprises.
4.1.4 RuTAG Workshop held on August 11, 2019 as a part of Tech4Seva 2019.
A RuTAG workshop was held on August 11, 2019 as a part of Tech4Seva 2019 organised by
Unnat Bharat Abhiyan and Vigyan Bharti. The workshop was held in LH 408 of the Lecture
Hall Complex at IIT Delhi. The session was chaired by Dr. Ketaki Bapat (Fig. 87, Front Left),
Scientist F, Office of the PSA, Vigyan Bhawan, New Delhi. Following speakers were present
namely Prof. V. K. Vijay, Coordinator UBA; Prof. S. K. Saha (Fig. 87, Front Right),
Fig. 85 (a): Participants during
RuTAG IIT Delhi MDP Programme
Fig. 85 (b): Group photo of the participants of
RuTAG IIT Delhi MDP Programme
71
Coordinator/Principal Investigator, RuTAG IIT Delhi; and Prof. Vivek Kumar, CRDT, IIT
Delhi. Workshop was attended by 38 participants (See the list in Appendix I) which included
representatives from UBA Regional Coordinating Institutes (RCI) and various RuTAGs
centers.
Fig. 86 Audience members from UBA RCIs and various RuTAGs Centres
Prof. Saha introduced the chairperson to the audience and asked the audience members to
introduce themselves shown in Fig. 86.
Dr. Bapat welcomed the gathering and explained to the audience, the concept of RuTAG, how
it came into being, and its objectives. She also said that it is important to build a synergy
between UBA RCIs and RuTAG centres so that it will strengthen the impact of both UBA and
RuTAGs not just nationally but also at the international level. Dr. Bapat mentioned that the
PSA office operates alongside the Prime Ministers Office and that the office is in a position to
coordinate with other ministries such as MSME, DoNER, MHRD etc. togather to pull resources
and facilitate the smooth functioning of RCIs and RuTAGs.
Prof. Saha spoke about the strengths of respective units. The UBA RCIs have strengths on
grassroots reach, a vast network of institutes, and social awareness, whereas RuTAGs have the
technical experience from 7 IITs. He also emphasised that the RuTAGs and the PSA office has
an experience of 15 years of problem solving and making demand-driven interventions in rural
areas. On these lines, the panel proposed a model wherein RCIs can refer the identified
technical problems to their regional RuTAG centre and can join hands with it in solving the
technical problems before the same would be implemented by the UBA RCIs. Prof. Saha also
suggested that RuTAGs could also consider funding some projects (in addition to the Rs. 1.00
lakhs by UBA) if the need arises. Later, he asked for feedback and suggestions from the RCIs
and RuTAGs representatives on the proposal.
72
Fig. 87 Souvenir handover to Dr. Ketaki Bapat by Prof. S. K. Saha
Discussion keypoints:
i. Since the concept of RuTAG was new to most of the RCI representatives, they
requested an orientation session for all the RCIs.
ii. All the RCI representatives were in agreement with the proposal and agreed that it
would build a good synergy between the two units.
iii. Dr. Bapat and Prof. Saha clarified that this was the first meeting and that things are
in the initial stage. The proposal would be discussed with The PSA and the Secretary,
MHRD for their inputs and suggestions before moving forward.
The workshop was ended with a vote of thanks by Prof. Saha.
5. Field visit held during Financial Year 2019 – 2020 (April 01, 2019 – March
31, 2020).
5.1 National Institute of Rural Development and Panchayati Raj (NIRD&PR),
Hyderabad, Telangana.
Mr. Raj Kumar Gupta, Mr. Davinder Pal Singh and Prof. S. K. Saha from RuTAG IIT Delhi
visited Hyderabad during April 20-25, 2019 for the exhibition of RuTAG Technologies in
National Institute of Rural Development and Panchayati Raj (NIRD&PR).
5.2 Installation of Treadle Pumps at Deoria, Uttar Pradesh.
Mr. Mangal Sharma from RuTAG IIT Delhi visited Deoria, U. P. for installation of Treadle
Pump during May 16-20, 2019.
73
5.3 RuTAG IIT Delhi team visit to Yamunotri, Uttarakhand.
Mr. Suraj Bhat, Mr. Davinder Pal Singh and Mr. Yashwant Prasad from RuTAG IIT Delhi
visited Yamunotri for design interventions required in Palki during June 24-28, 2019.
5.4 Installation of Metallic Carpet Loom at Pithoragarh, Uttarakhand.
Mr. Raj Kumar Gupta and Mr. Mangal Sharma from RuTAG IIT Delhi visited Pithoragard,
Uttarakhand during July 5-9, 2019 for installation, demonstration training of weavers/artisan
on metallic carpet loom developed by RuTAG IIT Delhi.
5.5 Visit to Shri Mata Vaishno Devi Shrine Board Central Office and Composting Sites
during July 29-31, 2019.
The meeting was held on July 30, 2019 at Shri Mata Vaishno Devi Shrine Board Central Office
with Mr. Vinay Kumar, Assistant Conservator of Forest (ACF) at SMVDS Board. The RuTAG
Project team members Prof. Balbir Singh, Shri Mata Vaishno Devi University and Dr. Kalpana
Arora from Centre for Technology and Development (CTD) attended the meeting.
Role of RuTAG Team:
Since, the Shrine board had tried the vermicomposting of mule dung in the past also but could
not get materialised. Now, under the RuTAG project “Development of vertical
vermicomposting system for Mule dung at Shri Mata Vaishno Devi Shrine Board, Katra” the
vermicomposting unit after developing at SMVDU, Kakryal, Katra, J&K will be installed for
the field trials at Shrine Board Mule Dung Composting site at village Natali, for field trials.
After successful operationalization of said one unit, same can be scaled up with financial
support and direction from Shrine Board.
5.6 Installation of Metallic Carpet Loom at Jain Art, Banskho, Tehsil-Bassi, Jaipur,
Rajasthan.
Mr. Raj Kumar Gupta and Mr. Mangal Sharma from RuTAG IIT Delhi visited Banskho, Jaipur,
Rajasthan during September 11 – 13, 2019 for installation, demonstration and training of
weavers/artisan on metallic carpet loom developed by RuTAG IIT Delhi.
5.7 Demonstration of Sheep Hair Shearing Machine developed by IIT Delhi at CSWRI,
Avikanagar, Rajasthan.
Mr. Ashish Dahiya, Mr. Mangal Sharma, Mr. Srijan Prabhakar, and Mr. Sumit Kumar visited CSWRI,
Avikanagar, Rajasthan during September 22-24, 2019 for demonstration of Sheep Hair Shearing Device
developed by IIT Delhi.
74
5.8 Mr. Suraj Bhat presented a paper entitled “Design Analysis of Wooden Palanquin
used in Yamunotri Dham” in IEEE Global Humanitarian Technology Conference at
Seattle, USA during October 17-20, 2019.
Mr. Suraj Bhat, Ph. D. student at IIT Delhi, presented a paper entitled “Design Analysis of the Wooden
Palanquin Used in Yamunotri Dham” in the IEEE Global Humanitarian Technology Conference held
in Seattle, WA during October 17- 20, 2019. The conference was focused on humanitarian activities
going across the globe and there were presentations on different technologies developed with a focus
of betterment of the society.
5.9 Mr. Suraj Bhat and Mr. Davinder Pal Singh visited EPICS at Purdue University in
Indianapolis, USA during October 22-25, 2019.
Mr. Suraj Bhat and Mr. Davinder Pal Singh (Project Associate, RuTAG IITD) later visited EPICS (Fig.
88) at Purdue University in Indianapolis, USA during October 22-25, 2019. EPICS Purdue program
solves community problems globally. Since September 2017 EPICS has acquainted students to RuTAG
program and ever since students have taken up three different problems and have tried to provide
solutions with different perspectives. The objective of the visit was to have a personal experience of the
EPICS program by meeting students, staff, faculty and visiting their labs. Also, EPICS and Shah Global
Innovation Labs at Purdue university have expressed their willingness to jointly solve the community
problems along with RuTAG IITD.
Fig. 88 Evan Hultman, Joshua Brody, Vivek Talapeneni, Davinder Pal Singh, Suraj Bhat,
Mrigank Sharma, and Ali Brown
During the same visit, Mr. Singh and Mr. Bhat met Ms. Pallavi Gupta, Assistant director of
Programs at Shah Family Global Innovation Lab at Purdue. The lab funds projects from across
the world that is focused on the humanitarian issues. Since RuTAG IIT Delhi works on similar
projects, she invited RuTAG to participate in the program, wherein, a Faculty-student group
from Purdue will work with a Faculty-student group at IIT Delhi to solve global problems.
5.10 Site Visit to Pattan Village in District of Betul, Madhya Pradesh on Nov. 16-19, 2019:
Two of our students Mr. Shekahar Chauhan and Mr. Sarthak Machkoria visited the Pattan
village, Betul, Madhya Pradesh on November 16-19, 2019 with Mr. Suraj (Research Scholar,
RuTAG, IIT Delhi) to gain the experience how people their decorticating Bhilawa and to know
their challenges.
75
5.11 Mr. Davinder Pal Singh and Ms. Sajja Sai Priyanka (an Intern) visited Bharatpur
for field survey regarding Bangle Making furnace, Potter’s Kiln, and Tulsi Mala Making
Device on November 18, 2019.
5.12 Mr. Yashwant Prasad and Ms. Sajja Sai Priyanka visited Jait village, Mathura,
U. P. for testing of Modified Tulsi Mala Making Device and field survey on November 25,
2019.
5.13 RuTAG Technologies displayed in Desi Oon Exhibition at Bikaner House, Delhi
(Fig. 89) organized by an NGO (Khamir, Bhuj, Gujarat) during Jan. 10-13, 2020 with
Mr. Raj Kumar Gupta, Mr. Mangal Sharma, and Mr. Yashwant Prasad.
Fig. 89 Display of Sheep Shearing Device in Desi Oon Exhibition at Bikaner House
6. Other Salient Activities during Financial Year 2019 – 2020 (April 01, 2019
– March 31, 2020)
6.1 Logo of Rural Technology Action Group (RuTAG) IIT Delhi
76
6.2 A Compendium on Rural Technology Action Group (RuTAG) of 52 Technologies
from 7 IITs
6.3 Rural Technology Development and Delivery Conference Proceedings published by
Springer
77
6.4 Rural Innovative Techno-hunt: A Technical Challenge to Identify Rural Problems
and Suggest Solutions - Organized by RuTAG IIT Delhi
6.5 RuTAG IIT Delhi published Newsletter by annually
a. RuTAG IIT Delhi published its 12th newsletter (Vol. 7, No. 2) about all RuTAG centre
activities in July 2019
b. RuTAG IIT Delhi published its 13th newsletter (Vol. 8, No. 1) about all RuTAG centre
activities in January 2020
6.6 RuTAG Technologies Displayed in Open House at IIT Delhi on April 20, 2019
(Fig. 90).
Fig. 90 Display of Technologies Developed by RuTAG IIT Delhi
78
6.7 RuTAG Club IIT Delhi participated in ‘Tour of Stalls’ on July 27-28, 2019 (Fig. 91).
The aim was to sensitise the new students joining IIT Delhi about the activities of
RuTAG Club IIT Delhi.
Fig. 91 RuTAG Club IIT Delhi participated in Tour of Stalls on July 27-28, 2019
6.8 RuTAG IIT Delhi demonstrated of its technologies in Tech4Seva at LHC, IIT Delhi
campus during August 10 – 12, 2019.
6.9 RuTAG Club Orientation and Felicitation programme was held at LHC, IIT Delhi on
August 30, 2019 (Fig. 92).
Fig. 92 Prof. Sangeeta Kohli giving certificate to winner of RuTAG IIT Delhi Technohunt
6.10 RuTAG IIT Delhi presented posters of its technologies in Industry Day at IIT
Delhi campus on September 21, 2019 (Fig. 93).
79
.
Fig. 93 Prof. V. Ramgopal Rao, Director, IIT Delhi visiting RuTAG IITD stall during
Industry Day 2019
6.11 RuTAG IIT Delhi team attended 2nd International Conference on "Rural
Technology Development and Delivery" (RTDD-2020) was held on March 12-14, 2020 at
IIT Madras.
The 2nd International Conference on "Rural Technology Development and Delivery" (RTDD-
2020) was held on March 12-14, 2020 at IIT Madras. The conference was attended by Mr.
Suraj Bhat, Mr. Yashwant Prasad, Mr. Raj Kumar Gupta and Mr. Davinder Pal Singh from
RuTAG IIT Delhi.
7. RuTAG IIT Delhi’s Collaboration with Purdue’s EPICS Programme.
We are a team of students working as a part of Purdue University’s EPICS program. We are
currently collaborating with RuTAG IIT Delhi to create a design for a bullock driven tractor
which will aid rural farmers in India. We started this project as a way to not only build a strong
relationship between IIT Delhi and Purdue, but also to make a difference in the quality of life
of struggling farmers in India. Through our collaboration with the RuTAG group, we have
discovered that we need to improve the design of an existing bullock driven tractor in three
main ways:
By creating a consistent, and mechanically simple mechanism for lifting farming
attachments which will allow the tractor to make turns without draining the bullock’s
energy.
By designing wheels which will allow the tractor to drive across multiple different
surfaces since currently the tractor struggles to plow through clay or wet soil.
80
By improving the overall ergonomics of the tractor via improvements to sitting
condition over the course of long-term usage.
We are currently coming up with design ideas for creating an efficient lifting mechanism for
farming attachment by pulling inspiration from simple machines such as levers, pulleys, and
gear systems. We are able to make great progress on our project with the assistance of the
RuTAG group, and their invaluable feedback and critique. The whole experience our team has
had working with the RuTAG group thus far has been overwhelmingly positive due to their
responsiveness, expertise, and support. We are excited to continue our relationship with the
RuTAG group and IIT Delhi and provoke real change throughout India.
Mr. Mrigank Sharma, Mr. Evan Hultman, Mr. Joshua Brody,
Mr. Vivek Talapeneni, and Ms. Ali Brown,
B. E. Students, Purdue University, USA
8. Internship at RuTAG IIT Delhi
In my one-month internship at RuTAG, IIT Delhi I gained an understanding of the functioning
of RuTAG and the various technological interventions made to enhance rural livelihood by
promoting rural entrepreneurs.
During the internship, I had the opportunity to visit Bharatpur and Mathura, where I observed
various clusters such as Tulsi mala makers, Furnace for jointless glass bangles and Pottery kiln.
Here, I observed their processes and the technological interventions provided by IIT Delhi.
With regards to Tulsi mala maker, I made observations and tried analyzing as to why the users
behaved in a certain manner eg. social norms, rumors, traditional thinking, resistance to change
etc., and have also made recommendations to enhance the acceptability of the product among
the rural consumers. I definitely had an enriching experience at RuTAG, IIT Delhi.
I had a great privilege working under Prof. S. K. Saha and Prof. Richa Kumar and also the
amazing team of RuTAG IIT Delhi, who have always supported, encouraged and inspired me,
and have been very patient in explaining me everything. Thank you!
Sajja Sai Priyanka, Intern, RuTAG IIT Delhi, M. A., Social Innovation and
Entrepreneurship, Tata Institute of Social Sciences, Tuljapur, Maharashtra
------------------------------------
------------------------------
------------------------