PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve...

3
PROGRESS REPORT As of September 22, 2011

Transcript of PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve...

Page 1: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule.

PROGRESS REPORTAs of September 22, 2011

Page 2: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule.

PRESENTATION OUTLINE

I. Project StatusII. S-CurveIII. Revised Construction ScheduleIV. Manpower ProfileV. Monthly ReportVI. Progress Photos:– Earthworks– Barge Pier Construction– Seawall Construction

Page 3: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule.

-END- THANK YOU