Department of Education Caraga Administrative Region Division of Surigao del Norte District of Alegria SAN PEDRO ELEMENTARY SCHOOL San Pedro, Alegria, Surigao del Norte PROGRAM OF WORK Name of Project : Repair of Classrooms Source of Funds : MOOE Estimated Cost of the Project: Materials : Php 10,610.00 Labor : Php 3,900.00 Total : Php 14,510.00 A. Materials: Unit Item Description Quanti ty Unit Cost Total Cost pcs Marine plywood 1/4 18 341.70 6,150.60 bund le Sticks 2x2x8 6 260.00 1,560.00 Kl. Common nails # 1, 1 ½ , # 2 3 110.00 330.00 Kl. Nails #3 2 50.00 100.00 Kl. Nails # 2 1/2 1 70.00 70.00 pc Corrugated Zinc 12 360.00 4,320.00 TOTAL PHP 12,530.00 B.Labor Number of Workers Work Description Rate per Day Number of Working Days Total Salary 1 Carpenter/Mason 400.00 5 2,000.00 1 Helper 300.00 5 1,500.00 Total 3,500.00 Over-All Total Php 16,030.00 Prepared by:

Transcript of Program of Work -March 2015.docx

Department of EducationCaraga Administrative Region Division of Surigao del NorteDistrict of AlegriaSAN PEDRO ELEMENTARY SCHOOLSan Pedro, Alegria, Surigao del Norte

PROGRAM OF WORK

Name of Project: Repair of ClassroomsSource of Funds: MOOEEstimated Cost of the Project:Materials : Php 10,610.00 Labor: Php 3,900.00Total : Php 14,510.00

A. Materials:

UnitItem DescriptionQuantityUnit CostTotal Cost

pcsMarine plywood 1/418 341.70 6,150.60

bundleSticks 2x2x8 6 260.00 1,560.00

Kl.Common nails # 1, 1 , # 23 110.00 330.00

Kl.Nails #32 50.00 100.00

Kl.Nails # 2 1/21 70.00 70.00

pcCorrugated Zinc 12 360.00 4,320.00

TOTAL PHP 12,530.00

B. LaborNumber of WorkersWork DescriptionRate per DayNumber of Working DaysTotal Salary

1Carpenter/Mason400.0052,000.00

1Helper300.005 1,500.00

Total 3,500.00

Over-All Total Php 16,030.00

Prepared by:

LINA D. UGAY Principal-INoted:

ROSARIO P. BENITEZ District Supervisor

Checked and Verified: GREGORIO B. CANEDAEPS-I Sec.Makabayan/Physical Facilities

Noted:

DR. FIDELA M. ROSAS , CESO VSchools Division Superintendent

Division of Surigao del NorteDistrict of AlegriaSAN PEDRO ELEMENTARY SCHOOLSan Pedro, Alegria, Surigao del Norte

PROGRAM OF WORK

Name of Project: Construction of Computers Room Window Grillsand Computers TableSource of Funds:MOOEEstimated Cost of the Project:Materials :Php 17,650.00Labor : Php 4,400.00Total : Php 22,050.00A. Materials:

UnitItem DescriptionQuantityUnit CostTotal Cost

pcSquare Bar 10 mm48205.009,840.00

Kl.Welding Rod5198.00990.00

LitersPaint Metal prime295.00190.00

Bots.Paint Thinner235.0070.00

Pc.Plyboard6985.005,910.00

Plastic botStick well 1650.00650.00

Total PHP 17,650.00

B. Labor

Number of WorkersWork DescriptionRate per DayNumber of Working DaysTotal Salary

1 Welder400.0083,200.00

1Carpenter 400.0031,200.00

TotalPhp 4,400.00

Over-All Total Php 22,050.00

Prepared by:

LINA D. UGAY Principal-INoted: ROSARIO P. BENITEZ District Supervisor

Checked and Verified:

GREGORIO B. CANEDAEPS-I Sec. Makabayan/Physical FacilitiesNoted:

DR. EVELYN R. FETALVERO, CESO VI.Schools Division Superintendent

Department of EducationCaraga Administrative Region Division of Surigaodel NorteDistrict of AlegriaSAN PEDRO ELEMENTARY SCHOOLSan Pedro, Alegria, Surigaodel Norte

PROGRAM OF WORK

Name of Project: Renovation of Covered PathwaySource of Funds: MOOEEstimated Cost of the Project:Materials : Php 7,770.00Labor : Php 4,400.00Total : Php 22,050.00C. Materials:

UnitItem DescriptionQuantityUnit CostTotal Cost

pcCorrugated Zinc15360.00Php 5,400.00

Kl.Tie Wire 3 150.00Php 450.00

pcSteel bar12160.00Php 1,920.00

Total PHP 7,770.00

D. Labor

Number of WorkersWork DescriptionRate per DayNumber of Working DaysTotal Salary

1welder400.0031,200.00

1carpenter400.001 400.00

TotalPhp 1,600.00

Over-All Total Php 9,370.00

Prepared by:

LINA D. UGAY Principal-INoted: ROSARIO P. BENITEZ District Supervisor

Checked and Verified:

GREGORIO B. CANEDAEPS-I Sec. Makabayan/Physical FacilitiesNoted:

DR. FIDELA M. ROSAS, CESO VSchools Division Superintendent