Production System Analysis & Italian Freight
Transport Companies
![Page 2: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/2.jpg)
Is it possible to use the method we use to analyze the production system for analyzing a transport company?
![Page 3: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/3.jpg)
Is it possible to assume a delivery good as a final Product (PF) of
Problem Tree?
![Page 4: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/4.jpg)
In addition, how about the Elementary Operations (EO),
Resources, Production Functions,
Agents, Information patterns
and Organizational Chart!
![Page 5: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/5.jpg)
I INVITE YOU TO VISIT: TRANSPORT AND LOGISTICS - BREAKING DOWN THE BARRIERS
![Page 6: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/6.jpg)
Assume that FP as satisfaction of client
by delivering good Pi to Ij
![Page 7: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/7.jpg)
OV
IVECO
dp
![Page 8: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/8.jpg)
The Problem Tree as a fundamental imagination
of what is happening in the production line
in our casefrom
NV = Non prepared vehicle
☟
FP = Satisfaction of the client by delivering her goods Pi in Ij
![Page 9: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/9.jpg)
��
�
��
PF2 = Final unloading of goods
�
PF3 = Enter to the plant
��
�� � Doc. = Transport’s Documents has taken
� L = Goods has Loaded
FP = Satisfactory of client by delivering his goods Pi to Ij
GE = Goods has entered to Delivery Point
GA = Goods (vehicle) has arrived to the plant
PF5 = Driving
GA = Goods (vehicle) has exited from the plant
PF4 = Exit from the plant
PF6 = Documents has taken
PF1 = Loading operation
�� VA = Vehicle has arrived to the plant
�� VE = Vehicle has entered to client’s plant
PF3 = Enter to the plant
�� VX = Vehicle has exited from the plant
PF5 = Driving
��
VR = Vehicle is ready to start working
PF4 = Exit from the plant
NV = Non prepared vehicle for work
PF7 = Vehicle preparing
Sometime depends to
various situation,
here we will see a kind of
LOOP. Means that
vehicle have to exit of the
plant and enter in it
again. Maybe
because of different Point of
Loading or waiting for
receive Final Product that is not ready
yet etc.
![Page 10: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/10.jpg)
��
PF2 = Final unloading of goods
PF3 = Enter to the plant
��
�� � Doc. = Transport’s Documents has taken
� L = Goods has Loaded
FP = Satisfactory of client by delivering his goods Pi to Ij
GE = Goods has entered to Delivery Point
GA = Goods (vehicle) has arrived to the plant
PF5 = Driving
GA = Goods (vehicle) has exited from the plant
PF4 = Exit from the plant
PF6 = Documents has taken
PF1 = Loading operation
�� VA = Vehicle has arrived to the plant
�� VE = Vehicle has entered to client’s plant
PF3 = Enter to the plant
�� VX = Vehicle has exited from the plant
PF5 = Driving
VR = Vehicle is ready to start working
PF4 = Exit from the plant
NV = Non prepared vehicle for work
PF7 = Vehicle preparing
Sometime depends to
various situation,
here we will see a kind of
LOOP. Means that
vehicle have to exit of the
plant and enter in it
again. Maybe
because of different Point of
Loading or waiting for
receive Final Product that is not ready
yet etc.
![Page 11: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/11.jpg)
The table of Production functions
N Production Functions
1 Loading
2 Unloading
3 Entering to the plant
4 Exiting from the plant
5 Driving
6 Tack/release Documents
7 Preparing Vehicle
8 Control
9 PAC
![Page 12: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/12.jpg)
++PF7 PF4
PF4
PF5
PF5
PF3
PF3
PF1
PF6
PF2
Note that these functions are an
external resources.
PF
![Page 13: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/13.jpg)
The table of Resources
Resources Tasks
R1 Forklift
R2 Van
R3 Truck
R4 Trailer
R5 Trailer Trainer
R6 Drive
![Page 14: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/14.jpg)
The Graphical Table of Resources
R1 R2 R3 R4 R5 R6
![Page 15: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/15.jpg)
![Page 16: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/16.jpg)
The table of Agents
Agents Assigned production Functions Type Responsibility
onSubordinated
to
DM1 Loading&Unloading LO Storehouse STAFF
DM2 Driver LO Transport STAFF
DM3 Logistics Sub-Control LO Logistic Activities STAFF
DM4 Logistics Control STAFF P. Activity of System PAC
DM5 Company (Transport) Activity Control PAC System ——
![Page 17: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/17.jpg)
“CHI COMANDA QUI” ?!!!
![Page 18: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/18.jpg)
CHI COMANDA QUI ?!!!
LA MAMMA !!!
![Page 19: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/19.jpg)
List of the steps to resolve 1st Exercise!
1. Read the Problem Tree carefully!2. Graph of Components (that represent the Elementary Operations)!3. The Table of Paths to find the number of PHASES!4. Represent the diagram of EO’s!5. Identify the Production Functions!6. Represent the Work Sequence!7. Graph of Production Functions!8. Table and Graph of Resources!9. Scheme of Layout, evaluation of DM’s and Critical Points!!10. Information Pattern and Organizational Chart
- Study the table of Agents- Represent the type of connections according to the table of Agents
��
�
��
PF2 = Final unloading of goods
�
PF3 = Enter to the plant
��
�� � Doc. = Transport’s Documents has taken
� L = Goods has Loaded
FP = Satisfactory of client by delivering his goods Pi to Ij
GE = Goods has entered to Delivery Point
GA = Goods (vehicle) has arrived to the plant
PF5 = Driving
GA = Goods (vehicle) has exited from the plant
PF4 = Exit from the plant
PF6 = Documents has taken
PF1 = Loading operation
�� VA = Vehicle has arrived to the plant
�� VE = Vehicle has entered to client’s plant
PF3 = Enter to the plant
�� VX = Vehicle has exited from the plant
PF5 = Driving
��
VR = Vehicle is ready to start working
PF4 = Exit from the plant
NV = Non prepared vehicle for work
PF7 = Vehicle preparing
Sometime depends to
various situation,
here we will see a kind of
LOOP. Means that
vehicle have to exit of the
plant and enter in it
again. Maybe
because of different Point of
Loading or waiting for
receive Final Product that is not ready
yet etc.
![Page 20: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/20.jpg)
Graph of Components
NV VR VX VA VE L DO EX GA GE PF12345678910
![Page 21: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/21.jpg)
Table of Paths
NV VR VX VA VE L DOC. EX GA GE PF
10 PHASES
![Page 22: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/22.jpg)
Elementary Operations (EO’s) & Phases
10987654321
1° 2° 3° 4° 5° 6° 7° 8° 9° 10°
![Page 23: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/23.jpg)
PF’s & EO’s
PF’s \ EO’s 1 2 3 4 5 6 7 8 9 10
1 1
2 1
3 1 1
4 1 1
5 1 1
6 1
7 1
8
9
![Page 24: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/24.jpg)
Functions & Phases
7
6
5
4
3
2
1
F’s/P’s 1° 2° 3° 4° 5° 6° 7° 8° 9° 10°
![Page 25: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/25.jpg)
Graph of Production Functions
PF7 PF4 PF5 PF3 PF1 PF6 PF4 PF5 PF3 PF2 PFGEGAEXDOCLVEVAVXVRNV
![Page 26: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/26.jpg)
Graph of Resources
R’s \ PF’s 1 2 3 4 5 6 7 8 9
1 1 1
2
3
4 1
5 1
6 1 1 1 1 1
You see the mass traffic of production functions behind the Resource 6
![Page 27: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/27.jpg)
Do you remember who was responsible of 6th resource?
This means that the qualification of this resource is very important. So the manager or the controller should collaborate with the driver,
because efficiency and performance of this resource could seriously effect on the production line of transport & logistic system.
![Page 28: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/28.jpg)
Finally
we arrived to the destination!
The Work sequence
and
the layout of the system
![Page 29: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/29.jpg)
PF 1 PF 2
DM5
DM4
DM3
DM2 DM1
PF 7 PF 4
PF 5PF 3 PF 6
PF 4 PF 5
PF 3
R6R6
THEOF THERESOURCES (PRODUCT FUNCTIONS (AND DECISION MAKERS (
![Page 30: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/30.jpg)
DM4
DM3 DM2
DM1
DM5
Information Pattern
![Page 31: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/31.jpg)
PAC
STAFF LO
LO LO LO LO
Organization ChartLA MAMMA !!!
![Page 32: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/32.jpg)
KPI ?!!
MSWhat can not be measured CAN NOT be represent!
![Page 33: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/33.jpg)
SOME CONSTRAINTS ABOUT HOURS OF WORKS AND DRIVE
• Total Daily hour of driving ⥴ 9 hours (2 times 10 h)
• Total Daily hour of all kind of work ⥴ 15 hours
• Total Weekly hour of working ⥴ 56 hours
• Total hour of work in two weeks ⥴ 90 hours
![Page 34: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/34.jpg)
• Obligated daily hours of rest ⥲ 11 hours - max 3 times per week ( 9 + 3)
• Obligated daily break time ⥲ 45 min - after 4.5 hours of driving
• Obligated weekly hours of rest ⥲ 45 hours - once minimum 24 hours
SOME CONSTRAINTS ABOUT HOURS OF RESTING
![Page 35: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/35.jpg)
HOW HOURS OF DRIVING AND WORKING COULD BE MEASURED ?!
![Page 36: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/36.jpg)
• Analog
• Digital
CRONOTACHIGRAFO
![Page 37: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/37.jpg)
• Analog • Setup time
++
• S ij ≠ S ji
PF7
![Page 38: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/38.jpg)
• Digital • Setup time •S ij = S ji
![Page 39: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/39.jpg)
SOME CONSTRAINTS ABOUT TRAFFIC
• Max speed in city center 50 km/h BUT most of the time maximum 30 km/h
• Max speed in regional ways 70 km/h
• Max speed in highways 80 km/h
![Page 40: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/40.jpg)
• In addition, many specific traffic signs such as:
![Page 41: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/41.jpg)
CONSTRAINTS ABOUT WEIGHT AND DIMENSION
MAXIMUM TOTAL WEIGHT
40 TONS
40 = +14 26
“FQ” BATCH
![Page 42: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/42.jpg)
CONSTRAINTS ABOUT TRAFFIC POLICY AND CONTROL
![Page 43: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/43.jpg)
SOME OTHER CONSTRAINTS ABOUT GENRE AND KIND OF GOODS OR MATERIAL
![Page 45: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/45.jpg)
ADR
•S ij ≠ S ji
![Page 46: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/46.jpg)
KPI
MS
SO AFTER THAT SHORT INTRODUCTION ABOUT THE VARIES KIND OF CONSTRAINTS, THAT WE FACE THEM EVERY DAYS IN THE WORLD OF TRANSPORT & LOGISTICS LETS COME BACK AGAIN TO THE KPI CONCEPT:
7 th Scheduling problem,
Series Res.
![Page 47: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/47.jpg)
Statistic analysis based on calculating time to reach the customers, time to loading, necessary time to drive the distance between the customer and delivery point etc.
![Page 48: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/48.jpg)
MS & Standard Transport Time
![Page 49: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/49.jpg)
KPI = MS
4%10%
22%
23%
11%
24%
6%
Reach Customer Driving Wait for LoadingWait for Unloading L + tack doc. UL + tack doc.etc.
![Page 50: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/50.jpg)
KPI = Compare your system with Competitor
![Page 51: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/51.jpg)
Organized transport companies, those are familiar to benefit form modern navigating systems (Real-time Optimization System),
have a Core Transport Network and an efficient work sequence cycles.
![Page 52: Production System Analysis & Italian Transport Companies](https://reader034.fdocuments.in/reader034/viewer/2022042618/58a8583f1a28ab210b8b70db/html5/thumbnails/52.jpg)
Sajjad Khaksari, Politecnico di Torino http://italiancoaddress.blogspot.it
Thank you very much for listening!