Production Planning SAP
Transcript of Production Planning SAP
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 1/17
TABLE OF CONTENTS
1. MASTER DATA ......................... ......................... .......................... ......................... .......................... ..........2
1.1 PRODUCT STRUCTURE – TWIN SIZE BED..................................................... ...2
1.2 DETAILS OF PRODUCT STRUCTURE – TWIN SIZE BED.................................3
2. STOCK LEVELS .......................... ......................... .......................... ......................... ................ ....... ....... ...3
2.1 STOCK LEVELS – TWIN SIZE BED......................................................................4
2.2 TRANSACTION CODE AND MENU PATH...................................................... ....5
3. BILL OF MATERIALS ........................ .......................... ......................... .......................... ................... .....5
3.1 GRAPHICAL HARDCOPY......................................................................................6
3.2 BOM - EXPLODED VIEW – LEVEL BY LEVEL........................................... .......6
3.3 BOM – FUNCTION APPLIED TO TWIN SIZE BED..................................... ........7
4. MATERIAL REQUIREMENT PLANNING ......................... ......................... ........................ ........ .......84.1 DEFINITION OF FIELDS IN MRP VIEWS................................................. ...........8
4.2 FINAL MRP RUN – Twin Size Bed.........................................................................9
5. WORK CENTRE ......................... ......................... .......................... ......................... .............. ........ ....... ..10
5.1 WORK CENTRE GRAPHICAL VIEW..................................................................10
5.2 WORK CENTRE INFORMATION SYSTEM AND TRANSACTION CODE......11
5.3 FUNCTION OF WORK CENTER IN SAP PP.................................................. .....12
6. ROUTING ........................ ......................... ......................... .......................... ......................... ............ .......13
6.1 ROUTING REPORT...............................................................................................14
6.2 ROUTING FUNCTION.................................................................................... ......14
6.3 PRODUCTION ORDER DISPLAY.......................................................................15
7. REFERENCES .......................... ......................... .......................... ......................... .................. ........ ....... .16
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 2/17
1. MASTER DATA
1.1 PRODUCT STRUCTURE – TWIN SIZE BED
Twin Size Bed(FinishedProduct)
FootboardAssembly
(Semi-FinishedProduct)
HeadboardAssembly
(Semi-FinishedProduct)
Side RailAssembly
(Semi-FinishedProduct)
MiddleSupport
Slats(SemiFinishedProduct)
Wheel Set(Semi-FinishedProduct)
MetalScrews(RawMaterial)
WheelSet(Semi-Finished
Product)
MetalScrews(RawMaterial)
WheelSet(Semi-Finished
Product)
MetalScrews(RawMaterial)
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 3/17
1.2 DETAILS OF PRODUCT STRUCTURE – TWIN SIZE BED
Table 1: Details of Twin Size Bed
ItemCode
Description Type Unit of Measure
GrossWeight
Unit of Weight
Size
M-639-S Metal Head FrameAssembly
Semi FinishedPC 10.0
Kg 25inchesx 28inches
M-639-IMetal Screws (1/2"x 1/16")
Raw Material PC 1.0 G 5mm
M-639-NWheel Set for Head Frame, FootFrame, and MiddleFoot
Semi FinishedPC 1.0 Kg
M-639-R Metal Foot Frame
Assembly
Semi FinishedPC 9 Kg 20
inches
x 28inches
M-639-TSide Frames withmiddle leg Semi Finished
PC 10 Kg 79inches
M-639-U Middle Support(Slats)
Semi FinishedProduct
PC 10 Kg 38 x27inches
M-639-Z Twin Size BedFinishedProduct
PC 50 Kg
2. STOCK LEVELS
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 4/17
2.1 STOCK LEVELS – TWIN SIZE BED
Item Code StorageLocation
UNe Plant Stock onHand
MW-639-A 0001 PC
3000
500
MW-639-B 0001 P 30 6,000
MW-639-C 0001 P 30 3,000
MW-639-D 0001 P 30 500
MW-639-E 0001 P 30 1000
MW-639-F 0001 P 30 1000
MW-639-Z 0001 P 30 500
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 5/17
2.2 TRANSACTION CODE AND MENU PATH
TRANSACTION CODE: MB52MENU PATH: Logistics > Material Management > Inventory Management > Environment > Stock > Warehouse Stock
3. BILL OF MATERIALS
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 6/17
3.1 GRAPHICAL HARDCOPY
3.2 BOM - EXPLODED VIEW – LEVEL BY LEVEL
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 7/17
3.3 BOM – FUNCTION APPLIED TO TWIN SIZE BED
Bill of Materials function defines multilevel bill of materials - one level at a time. The structure of BOM has an hierarchical arrangement of
components. All the sub-assemblies and raw materials that are required to assemble and produce the finished product are shown under theBOM.
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 8/17
The product chosen here is Twin-Size Bed. The sub-assemblies in this can be divided into two levels – first and second. First levelassemblies are the head board assembly, footboard assembly and side rail assembly. These semi-finished products further moves down tosecond level where in wheel sets (Semi-finished Product) are fixed to it using the metal screws (Raw Material).
4. MATERIAL REQUIREMENT PLANNING
4.1 DEFINITION OF FIELDS IN MRP VIEWS
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 9/17
Safety Stock and service level: Safety Stock and Service Level: Safety stock as the name suggests is the stock level till whichthe dead stock or stock out situation will not arise (probable figure based on past data maintained in master). As such this figure is notstock, it is cut-off figure maintained in master which is used for Planning and once the stock level dips below this value, we canconfigure system to generate PR, orders automatically. It has its relevance in MRP. Safety Stock is the quantity of stock held tosatisfy unexpectedly high requirements in the stocking-up period. The purpose of the safety stock is to prevent a material shortagefrom occurring. In order to determine the safety stock level, we must first specify the risk of a material shortage and also the desiredservice level.
The purpose of the safety stock is to prevent a material shortage from occurring.
In order to determine the safety stock level, we must first specify the risk of a material shortage and also the desired service level .
The safety stock depends on the service level that we specify in the MRP 2 view of the material master record and on the accuracy of the forecast. The more accurate the forecast, the smaller our safety stock can be.
Lead Time: A lead time is the period of time between the initiation of any process of production and the completion of that process.For example, the lead time for ordering a new car from a manufacturer may be anywhere from 2 weeks to 6 months depending on the
internal processes involved in processing the end product. It needs calculate all the upstream product movement and upstream anddownstream information movement and the time consumption in each step.
Minimum Lot Size: We define the minimum lot size on the Lot Size tab page in location product master data in conjunction with theFixed Lot Size or Lot-for-Lot lot-sizing procedure. The SNP optimizer takes these settings into account for integration purposes (withPP/DS, for example). The minimum lot size defined in the product master applies to all the PPMs that use this product as the header material. If the minimum lot size in the product master is larger than the minimum lot size in the PPM, the optimizer takes into accountthe value from the product master. The maximum lot size defined in the product master has no relevance for the SNP optimizer.
Planned Delivery Time: A finished component is made of several sub components. Once the order is received by the system, ithas several process to be followed. Once we create our material by giving the subcomponents- each component and subcomponenthas a procurement cycle which includes the planned delivery time. The material requirements are calculated using the following
formula:
Forecast value for the interval (cycle + purchasing department processing time + planned delivery time + goods receipt processingtime) + safety stock. The planned delivery time is included in the calculation in the calendar days and the purchasing departmentprocessing time and goods receipt processing time in workdays.
4.2 FINAL MRP RUN – Twin Size Bed
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 10/17
5. WORK CENTRE
5.1 WORK CENTRE GRAPHICAL VIEW
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 11/17
5.2 WORK CENTRE INFORMATION SYSTEM AND TRANSACTION CODE
Transaction Code : CR60
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 12/17
5.3 FUNCTION OF WORK CENTER IN SAP PP
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 13/17
The work center includes the details on capacity requirement planning, costing (resources), scheduling, and execution times.
6. ROUTING
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 14/17
6.1 ROUTING REPORT
Transaction Code – CA51
6.2 ROUTING FUNCTION
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 15/17
As the diagram above shows, routings show the flow of the production process. It is a template which we use in the production process.The above diagram shows the structure of routing which gives a detailed description of the products used, the capacity, time etc.
6.3 PRODUCTION ORDER DISPLAY
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 16/17
7. References
1. SAP 2010,SAP,Viewed 5th September 2010,
< http://www.sap.com>
8/8/2019 Production Planning SAP
http://slidepdf.com/reader/full/production-planning-sap 17/17
2. Vollmann TE et.al 2005, Manufacturing Planning and Control Systems for Supply Chain Management, NewYork.