Production Activity Control

73
Arnold, Chapman, & Clive: Intro Materials Management, 6 th ed. © 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved. Production Activity Control Chapter 6 “The time comes when plans must be put into action”

description

Production Activity Control

Transcript of Production Activity Control

Page 1: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Activity Control

Chapter 6

“The time comes when plans must be put into action”

Page 2: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Activity Control• Responsible for executing the:

– Master Production Schedule (MPS)– Materials Requirements Plan (MRP)

• At the same time:– Make good use of labor, machines and materials– Minimize work-in-process inventory– Maintain customer service

Page 3: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Activity Control

• Release work orders

• Control work orders to complete on time

• Control the flow of work– Through manufacturing– Carrying out the plan– To completion

• Manage day-to-day activity and provide support

Page 4: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Planning

MasterProductionScheduling

MaterialRequirements

Planning

Production ActivityControl

Purchasing

Input/OutputControl

Operation

Sequencing

Planning

Implementand

Control

Figure 6.1 Priority planning and production activity control

Page 5: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Planning

• To meet delivery dates

• Ensure:– The required materials, tooling, personnel and

information

• Schedule:– Start and completion times for each shop order– Develop load profiles for the work centres`

Page 6: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Implementation

• Gather information needed to make the product

• Release orders to the shop floor– MRP authorized

“Dispatching”

Page 7: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Control

• The production order has been released

• Is corrective action necessary?– Rank the orders by priority– Establish a dispatch list– Track performance to planned schedule– Replan, reschedule, adjust capacity– Monitor and control WIP, lead times, cues– Report work center effciency, scrap, times

Page 8: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Feedback

PRODUCTION ACTIVITY CONTROL

PLANScheduleReplan

CONTROLCompareDecide

EXECUTEWork

Authorization

Dispatch

MANUFACTURING OPERATIONS

Figure 6.2 Production control system

Page 9: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Manufacturing Systems

• Flow manufacturing

• Intermittent manufacturing

• Project manufacturing

Page 10: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Flow Manufacturing

• High volume

• Standard products– Repetitive or– Continuous

Page 11: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Flow Manufacturing

• Routings are fixed– Work centers arranged according to the routing

• Dedicated to a limited range of products– specifically designed equipment

• Use of mechanical transfer devices– Low WIP and throughput times

• Capacity is fixed by the line

Page 12: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Flow Manufacturing

• Production Activity Control– Plans the flow of work– Planned schedule of materials to the line– Implementation and control are relatively

simple

Page 13: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Intermittent Manufacturing

• Many variations in:– product design– process requirements– order quantities

Page 14: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Intermittent Manufacturing

• Flow of work is varied - work flow not balanced

• Machinery and workers must be flexible– Usually grouped according to function

• Throughput times are generally long

• Capacity required depends on product mix

Page 15: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Intermittent Manufacturing

• Production Activity Control is complex:– number of products made– variety of routings– scheduling problems– PAC is a major activity

• Controlled through shop orders for each batch

Page 16: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Project Manufacturing

• One or a small number of units

• Usually in one place

• Close coordination between:– Manufacturing, Marketing, Purchasing,

Engineering

• Examples:– Shipbuilding– House construction

Page 17: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Data Requirements

• Need to know:– What and how much to produce– When parts are needed– What operations and times are required– Work center capacities

• Organized into databases:

– Planning or Control

Page 18: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Planning Files

• Item master file

• Product structure file

• Routing file

• Work center master file

Page 19: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Item Master File

• Part number

• Part description

• Manufacturing lead

time

• Lot size quantity

• Quantity on hand

• Quantity available

• Allocated quantity

– already assigned to

other work orders

• On-order quantities

Page 20: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Product Structure File

• Bill of material file– A listing of single-level components to make an

assembly– Forms a basis for a ‘pick list’

Page 21: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Routing File

• Step-by-step instructions on how to make the product– Operations and their sequence– Operation descriptions (brief)– Equipment tools and accessories– Operation setup times– Operation run times– Lead times for each operation

Page 22: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Work Center Master File

• Details on each work center– Work center number– Capacity– Shifts, machine hours and labor hours per week– Efficiency– Utilization– Average queue time– Alternative work centers

Page 23: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Control Files

• Shop order master file– Summarized data on each shop order

• Shop order detail file– Current record of each operation

Page 24: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Shop Order Master File

• Shop order number• Order quantity• Quantity completed• Quantity scrapped• Quantity of material

issued to the order• Due date• Priority• Balance due• Cost information

Page 25: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Shop Order Detail File

• Operation number

• Setup hours planned and actual

• Run hours planned and actual

• Quantity complete (at this operation)

• Quantity scrapped (at this operation)

• Lead time remaining

Page 26: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Order Preparation

• A check for available:– Tooling– Materials– Capacity - when it is needed

Page 27: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Scheduling

• To meet delivery dates

• Make the best use of resources

• Need information on:– Routing– Capacity– Competing jobs– manufacturing lead times

Page 28: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Manufacturing Lead Time

• Queue - time spent waiting before operation

• Setup - time to prepare the work center

• Run - time to make the product

• Wait - time spent after the operation

• Move - transit time between work centers

Page 29: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Manufacturing Lead Time

Queue Setup Run Wait

Move

Queue Setup Run WaitMove

Need a lift truck here

Page 30: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Cycle Time

• “The length of time from when material enters a production facility until it exits”

– APICS Dictionary 11th Edition

• Synonym - throughput time

Page 31: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem

Work Center A operation time = 30 + (100 x 10) = 1030 minutesWait time = 240 minutesMove time from A to B = 10 minutesWork Center B operation time = 50 + (100 x 5) = 550 minutesWait time = 240 minutesMove time from B to stores = 15 minutesTotal manufacturing lead time = 2085minutes

= 34 hours, 45 minutes

Page 32: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Scheduling Techniques

• Forward Scheduling– Start when the order is

received

– May finish early

– Used to determine the earliest completion date

– Determine promise dates

– Builds inventory

• Backward Scheduling– Uses MRP logic

– Schedule last operation to be complete on the due date

– Schedule previous operations back from the last operation

– Reduces inventory

Page 33: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Order Recieved Due Date

Forward Scheduling

Backward Scheduling

1 2 3 4 5 6 7 8 9

Figire 6.4 Infinite load profile

Forward and Backward Scheduling:Infinite Load

MaterialOrdered

3rdOperation

1st Operation

2ndOperation

MaterialOrdered

3rdOperation

1st Operation

2ndOperation

Page 34: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Capacity

Capacity Underload

Capacity Overload

Figure 6.5 Infinite load profile

Infinite Load Profile

Page 35: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Order Recieved Due Date

Forward Scheduling

Backward Scheduling

1 2 3 4 5 6 7 8 9

Figure 6.6 Forward and Backward scheduling: finite load

Forward and Backward Scheduling:Finite Load

MaterialOrdered

3rdOperation

1st Operation

2ndOperation

MaterialOrdered

3rdOperation

1st Operation

2ndOperation

Page 36: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Capacity

Figure 6.7 Finite load profile

Smoothed Load

Finite Load Profile

Page 37: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem Backward Scheduling

• A company has an order for 50 brand X to be delivered on day 100

• Only one machine is available for each operation

• The factory works one 8 hour shift 5 days a week

• The parts move in one lot of 50

Part Operation TimeA 10 5

20 3B 10 10X Assembly 5

X

A B

Page 38: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

85 90 95 100

X

AssemblyPart B

Part A

Working Days

Example Problem Answer

OP 10 OP 20

OP 10

Page 39: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Operation Overlapping• The next operation is allowed to begin

before the entire lot is completed

• Reduces the manufacturing lead time

• Order is divided into at least two transfer lots

SU Lot 1 Lot 2

Operartion A

SU Lot 1 Lot 2

Operation B

T T Transfer Time

Page 40: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Operation Overlapping

• Costs involved:

• Handling costs between work centers

• May increase queue and wait for other orders

• Idle time if the second batch doesn’t arrive in time

Page 41: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Size of the Transfer BatchSUA = Set up time operation A

SUB = Set up time operation B

RTA = Run time per piece operation A

RTB = Run time per piece operation B

QT = Total order size

T1 = size of the first transfer batch

T1 = QT x RTA - SUB T2 = QT - T1

RTA + RTB

Page 42: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Size of the Transfer Batch

• If the second operation is slower than the first make the first transfer batch small– i.e. get the slower machine started early

• If the second machine is faster than the first make the first transfer batch large– i.e. the second machine will be able to catch up

Page 43: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem

30 70 x 10 = 700 30 x 10 = 300

Operartion A

50 70 x 5 = 350 30x5 = 150

Operation B

T T Transfer Time

0 30 730 1,000 (Minutes)

740 790 1140 1290

1,010

Stores 1305

Page 44: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Operation Splitting

• Reduces manufacturing lead time

• The order is split into at least two lots

• Similar machines are run simultaneously

• Setup time is low compared to run time

• Operators can run more than one machine

Page 45: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Operation Splitting

SU Run

SU Run

SU Run

One Machine

Two Machine Operation Splitting

Reduction in Lead Time

Figure 6.9 Operation splitting

Page 46: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Load Leveling

• Load Report

• Tells PAC the current and upcoming load on a work center

• Based on standard hours of operation for each order

Page 47: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Load ReportWork Center: 10 Available Time: 120 Hours per weekDescription: Lathes Efficiency: 115%Number of Machines: 3 Utilization 80%Rated Capacity: 110 standard hours / wk

Week 18 19 20 21 22 23 Total

ReleasedLoadPlanned Load

105 1008060

3080

0130

080

315350

Total Load 105 100 140 110 130 80 665

RatedCapacity

110 110 110 110 110 110 660

(Over) /UnderCapacity

5 10 (30) 0 (20) 30 (5)

Figure 6.10 Work centre load report

Page 48: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Scheduling Bottlenecks

• Some workstations are overloaded and some are underloaded

• Bottlenecks– “a facility, function, department, or resource

whose capacityis equal to or less than the demand put upon it.”

APICs Dictionary 11th Edition

Page 49: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Throughput

• The total volume of product passing through a facility

• Bottlenecks control the throughput– Work centers feeding bottlenecks will build

inventory – Work Centers fed by bottlenecks have their

throughput controlled by the bottleneck

Page 50: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem - Bottlenecks

• Wagon Wheel Assembly - 1200 sets (2) per week• Handle Assembly - 450 per week• Final Assembly - 550 wagons per week

a. What is the capacity of the factory?

b. What limits the throughput of the factory?

c. How many wheel assemblies should be made?

d. What is the utilization of the wheel assembly?

e. What happens if utilization is 100%

Page 51: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem - Bottlenecks

a. 450 units per week

b. Throughput is limited by the handle assembly operation

c. 900 wheel assemblies per week

d. Utilization of the wheel assemblies =

900 ÷ 1200 = 75%

e. Excess inventory of wheel assemblies

Page 52: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Bottleneck Principles (7)1. Utilization of a non-bottleneck resource is not determined

by its potential, but by another constraint in the system.

2. Utilization of a non-bottleneck 100% of the time does not produce 100% utilization.

3. The capacity of the system depends on the capacity of the bottleneck.

4. Time saved at a non-bottleneck saves the system nothing.

5. Capacity and priority must be considered together.

6. Loads can and should be split.

7. Focus should be on balancing the flow in the shop.

Page 53: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Managing Bottlenecks

1. Establish a time buffer before each bottleneck.

2. Control the rate of material feeding the bottleneck.

3. Do everything to provide the bottleneck with capacity.

4. Adjust loads.

5. Change the schedule.

Back schedule before the bottleneck; forward schedule after the bottleneck.

Page 54: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Theory of Constraints

• 1. Identify the constraint

Process 15 per hour

Process 27 per hour

Process 34 per hour

Process 49 per hour

Marketing sells5 per hour?

Figure 6.11

Page 55: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Theory of Constraints continued

2. Exploit the constraint. (idle time?)

3. Subordinate everything to the constraint.

4. Elevate the constraint.

5. Once the constraint is a constraint no-

longer, find the new one and repeat the

steps.

Page 56: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Drum-Buffer-Rope

• Drum - pace of production set by the

constraint

• Buffer - inventory established before the

constraint

• Rope - coordinated release of material

Page 57: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem

Work Center 20: Capacity = 40 hours per week

Y: Setup = 1 hour, Run Time = .3 hours per piece

Z: Setup = 2 hours, Run Time = .2 hours per piece

Let x = the number of Y’s and Z’s to produce

1 + 0.3x + 2 + .2x = 40 hours

0.5x = 37 hours

x = 74 (you can produce 74 Y’s and 74 Z’s)

X

Y Z

Page 58: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Implementation

• Issuing shop orders to manufacturing

• Which have a good chance of being completed on time

• Orders which have the:– tooling– material– capacity

Page 59: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Shop Order Information

• Order number,

description

• Engineering Drawings

• Bills of Material

• Route Sheets

• Material Issue Tickets

• Tool Requisitions

• Job Tickets

• Move Tickets

Page 60: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Review Order

Check Toolingand MaterialAvailability

Check CapacityRequirementsand Availability

Release Order

Okay?

Okay?

ResolveNo

Yes

Resolveor

Reschedule

No

Yes

Figure 6.12Order ReleaseProcess

Page 61: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Control

• Control the work going into and out of a work center: Input/output control

• Set the priority of orders to run at each work center

Page 62: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Input / Output ControlInput Rate

Control

Output RateControl

Queue(Load, WIP)

Figure 6.13Input/output control

Page 63: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Work Center: 201Capacity per period: 40 standard hours

Period 1 2 3 4 5 Total

Planned Input 38 32 36 40 44 190

Actual Input 34 32 32 42 40 180

Cumulative Variance -4 -4 -8 -6 -10 -10

Planned Output 40 40 40 40 40 200

Actual Output 32 36 44 44 36 192

Cumulative Variance -8 -12 -8 -4 -8 -8

Planned Backlog 32 30 22 18 18 22

Actual Backlog 32 34 30 18 16 20

Figure 6.14 Input/output report

Page 64: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Cumulative Variance

• The difference between the total planned for a given period and the actual total for that period

• Cumulative variance

= previous cumulative variance + actual

- planned

Page 65: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Work Center: 201Capacity per period: 40 standard hours

Period 1 2 3 4 5 Total

Planned Input 38 32 36 40 44 190

Actual Input 34 32 32 42 40 180

Cumulative Variance -4 -4 -8 -6 -10 -10

Planned Output 40 40 40 40 40 200

Actual Output 32 36 44 44 36 192

Cumulative Variance -8 -12 -8 -4 -8 -8

Planned Backlog 32 30 22 18 18 22

Actual Backlog 32 34 30 18 16 20

Figure 6.14 Input/output report

Cumulative variance week 2 = -4 + 32 -32 = -4

Page 66: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Example Problem: Input/OutputWeek 1 2

Planned Input 45 40

Actual Input 42 46

Cumulative Variance

Planned Output 40 40

Actual Output 42 44

Cumulative Variance

Planned Backlog 30

Actual Backlog 30

Page 67: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Operations Sequencing

• “a technique for short term planning of actual jobs to be run in each work center based on capacities and priorities.”

APICS Dictionary 11th Edition

• Priority: The sequence in which jobs should run at a work center

Page 68: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Dispatching

• Selecting and sequencing jobs to be run at a work center

• Dispatch list• Plant, department, work center

• Part number, shop order number, operation number and description

• Standard hours

• Priority information

• Jobs coming to the work center

Page 69: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Dispatching Rules

• FCFS - First come, first served

• EDD - Earliest job due date

• ODD - Earliest operation due date

• SPT - Shortest processing time

• CR - Critical ratio

Page 70: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Critical Ratio

CR= due date - present date

lead time remaining

= actual time remaining

lead time remaining

CR<1 Behind Schedule

CR=1 On Schedule

CR>1 Ahead of Schedule

CR<0 Already late

Page 71: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Sequencing RuleJob

ProcessTime(days)

ArrivalDate

DueDate

OperationDue Date FCFS EDD ODD SPT

A 4 223 245 233 2 4 1 3

B 1 224 242 239 3 2 2 1

C 5 231 240 240 4 1 3 4

D 2 219 243 243 1 3 4 2

Figure 6.16 Application of sequencing rules

Sequencing Rules

Page 72: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Reporting

• Feedback of what is actually happening on the shop floor

• Needed for management decisions

on-hand on-order

job status shortages

scrap material shortages

Page 73: Production Activity Control

Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.

© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.

Production Activity Control Summary

• Converting MRP plans into action– Reporting results– Revising plans

• Need:– detailed and current schedules and priorities

• Results:– on-time deliveries, well utilized labor, and

equipment, minimum inventory levels