Production Activity Control
description
Transcript of Production Activity Control
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Activity Control
Chapter 6
“The time comes when plans must be put into action”
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Activity Control• Responsible for executing the:
– Master Production Schedule (MPS)– Materials Requirements Plan (MRP)
• At the same time:– Make good use of labor, machines and materials– Minimize work-in-process inventory– Maintain customer service
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Activity Control
• Release work orders
• Control work orders to complete on time
• Control the flow of work– Through manufacturing– Carrying out the plan– To completion
• Manage day-to-day activity and provide support
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Planning
MasterProductionScheduling
MaterialRequirements
Planning
Production ActivityControl
Purchasing
Input/OutputControl
Operation
Sequencing
Planning
Implementand
Control
Figure 6.1 Priority planning and production activity control
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Planning
• To meet delivery dates
• Ensure:– The required materials, tooling, personnel and
information
• Schedule:– Start and completion times for each shop order– Develop load profiles for the work centres`
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Implementation
• Gather information needed to make the product
• Release orders to the shop floor– MRP authorized
“Dispatching”
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Control
• The production order has been released
• Is corrective action necessary?– Rank the orders by priority– Establish a dispatch list– Track performance to planned schedule– Replan, reschedule, adjust capacity– Monitor and control WIP, lead times, cues– Report work center effciency, scrap, times
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Feedback
PRODUCTION ACTIVITY CONTROL
PLANScheduleReplan
CONTROLCompareDecide
EXECUTEWork
Authorization
Dispatch
MANUFACTURING OPERATIONS
Figure 6.2 Production control system
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Manufacturing Systems
• Flow manufacturing
• Intermittent manufacturing
• Project manufacturing
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Flow Manufacturing
• High volume
• Standard products– Repetitive or– Continuous
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Flow Manufacturing
• Routings are fixed– Work centers arranged according to the routing
• Dedicated to a limited range of products– specifically designed equipment
• Use of mechanical transfer devices– Low WIP and throughput times
• Capacity is fixed by the line
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Flow Manufacturing
• Production Activity Control– Plans the flow of work– Planned schedule of materials to the line– Implementation and control are relatively
simple
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Intermittent Manufacturing
• Many variations in:– product design– process requirements– order quantities
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Intermittent Manufacturing
• Flow of work is varied - work flow not balanced
• Machinery and workers must be flexible– Usually grouped according to function
• Throughput times are generally long
• Capacity required depends on product mix
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Intermittent Manufacturing
• Production Activity Control is complex:– number of products made– variety of routings– scheduling problems– PAC is a major activity
• Controlled through shop orders for each batch
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Project Manufacturing
• One or a small number of units
• Usually in one place
• Close coordination between:– Manufacturing, Marketing, Purchasing,
Engineering
• Examples:– Shipbuilding– House construction
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Data Requirements
• Need to know:– What and how much to produce– When parts are needed– What operations and times are required– Work center capacities
• Organized into databases:
– Planning or Control
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Planning Files
• Item master file
• Product structure file
• Routing file
• Work center master file
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Item Master File
• Part number
• Part description
• Manufacturing lead
time
• Lot size quantity
• Quantity on hand
• Quantity available
• Allocated quantity
– already assigned to
other work orders
• On-order quantities
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Product Structure File
• Bill of material file– A listing of single-level components to make an
assembly– Forms a basis for a ‘pick list’
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Routing File
• Step-by-step instructions on how to make the product– Operations and their sequence– Operation descriptions (brief)– Equipment tools and accessories– Operation setup times– Operation run times– Lead times for each operation
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Work Center Master File
• Details on each work center– Work center number– Capacity– Shifts, machine hours and labor hours per week– Efficiency– Utilization– Average queue time– Alternative work centers
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Control Files
• Shop order master file– Summarized data on each shop order
• Shop order detail file– Current record of each operation
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Shop Order Master File
• Shop order number• Order quantity• Quantity completed• Quantity scrapped• Quantity of material
issued to the order• Due date• Priority• Balance due• Cost information
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Shop Order Detail File
• Operation number
• Setup hours planned and actual
• Run hours planned and actual
• Quantity complete (at this operation)
• Quantity scrapped (at this operation)
• Lead time remaining
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Order Preparation
• A check for available:– Tooling– Materials– Capacity - when it is needed
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Scheduling
• To meet delivery dates
• Make the best use of resources
• Need information on:– Routing– Capacity– Competing jobs– manufacturing lead times
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Manufacturing Lead Time
• Queue - time spent waiting before operation
• Setup - time to prepare the work center
• Run - time to make the product
• Wait - time spent after the operation
• Move - transit time between work centers
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Manufacturing Lead Time
Queue Setup Run Wait
Move
Queue Setup Run WaitMove
Need a lift truck here
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Cycle Time
• “The length of time from when material enters a production facility until it exits”
– APICS Dictionary 11th Edition
• Synonym - throughput time
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem
Work Center A operation time = 30 + (100 x 10) = 1030 minutesWait time = 240 minutesMove time from A to B = 10 minutesWork Center B operation time = 50 + (100 x 5) = 550 minutesWait time = 240 minutesMove time from B to stores = 15 minutesTotal manufacturing lead time = 2085minutes
= 34 hours, 45 minutes
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Scheduling Techniques
• Forward Scheduling– Start when the order is
received
– May finish early
– Used to determine the earliest completion date
– Determine promise dates
– Builds inventory
• Backward Scheduling– Uses MRP logic
– Schedule last operation to be complete on the due date
– Schedule previous operations back from the last operation
– Reduces inventory
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Order Recieved Due Date
Forward Scheduling
Backward Scheduling
1 2 3 4 5 6 7 8 9
Figire 6.4 Infinite load profile
Forward and Backward Scheduling:Infinite Load
MaterialOrdered
3rdOperation
1st Operation
2ndOperation
MaterialOrdered
3rdOperation
1st Operation
2ndOperation
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Capacity
Capacity Underload
Capacity Overload
Figure 6.5 Infinite load profile
Infinite Load Profile
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Order Recieved Due Date
Forward Scheduling
Backward Scheduling
1 2 3 4 5 6 7 8 9
Figure 6.6 Forward and Backward scheduling: finite load
Forward and Backward Scheduling:Finite Load
MaterialOrdered
3rdOperation
1st Operation
2ndOperation
MaterialOrdered
3rdOperation
1st Operation
2ndOperation
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Capacity
Figure 6.7 Finite load profile
Smoothed Load
Finite Load Profile
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem Backward Scheduling
• A company has an order for 50 brand X to be delivered on day 100
• Only one machine is available for each operation
• The factory works one 8 hour shift 5 days a week
• The parts move in one lot of 50
Part Operation TimeA 10 5
20 3B 10 10X Assembly 5
X
A B
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
85 90 95 100
X
AssemblyPart B
Part A
Working Days
Example Problem Answer
OP 10 OP 20
OP 10
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Operation Overlapping• The next operation is allowed to begin
before the entire lot is completed
• Reduces the manufacturing lead time
• Order is divided into at least two transfer lots
SU Lot 1 Lot 2
Operartion A
SU Lot 1 Lot 2
Operation B
T T Transfer Time
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Operation Overlapping
• Costs involved:
• Handling costs between work centers
• May increase queue and wait for other orders
• Idle time if the second batch doesn’t arrive in time
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Size of the Transfer BatchSUA = Set up time operation A
SUB = Set up time operation B
RTA = Run time per piece operation A
RTB = Run time per piece operation B
QT = Total order size
T1 = size of the first transfer batch
T1 = QT x RTA - SUB T2 = QT - T1
RTA + RTB
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Size of the Transfer Batch
• If the second operation is slower than the first make the first transfer batch small– i.e. get the slower machine started early
• If the second machine is faster than the first make the first transfer batch large– i.e. the second machine will be able to catch up
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem
30 70 x 10 = 700 30 x 10 = 300
Operartion A
50 70 x 5 = 350 30x5 = 150
Operation B
T T Transfer Time
0 30 730 1,000 (Minutes)
740 790 1140 1290
1,010
Stores 1305
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Operation Splitting
• Reduces manufacturing lead time
• The order is split into at least two lots
• Similar machines are run simultaneously
• Setup time is low compared to run time
• Operators can run more than one machine
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Operation Splitting
SU Run
SU Run
SU Run
One Machine
Two Machine Operation Splitting
Reduction in Lead Time
Figure 6.9 Operation splitting
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Load Leveling
• Load Report
• Tells PAC the current and upcoming load on a work center
• Based on standard hours of operation for each order
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Load ReportWork Center: 10 Available Time: 120 Hours per weekDescription: Lathes Efficiency: 115%Number of Machines: 3 Utilization 80%Rated Capacity: 110 standard hours / wk
Week 18 19 20 21 22 23 Total
ReleasedLoadPlanned Load
105 1008060
3080
0130
080
315350
Total Load 105 100 140 110 130 80 665
RatedCapacity
110 110 110 110 110 110 660
(Over) /UnderCapacity
5 10 (30) 0 (20) 30 (5)
Figure 6.10 Work centre load report
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Scheduling Bottlenecks
• Some workstations are overloaded and some are underloaded
• Bottlenecks– “a facility, function, department, or resource
whose capacityis equal to or less than the demand put upon it.”
APICs Dictionary 11th Edition
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Throughput
• The total volume of product passing through a facility
• Bottlenecks control the throughput– Work centers feeding bottlenecks will build
inventory – Work Centers fed by bottlenecks have their
throughput controlled by the bottleneck
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem - Bottlenecks
• Wagon Wheel Assembly - 1200 sets (2) per week• Handle Assembly - 450 per week• Final Assembly - 550 wagons per week
a. What is the capacity of the factory?
b. What limits the throughput of the factory?
c. How many wheel assemblies should be made?
d. What is the utilization of the wheel assembly?
e. What happens if utilization is 100%
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem - Bottlenecks
a. 450 units per week
b. Throughput is limited by the handle assembly operation
c. 900 wheel assemblies per week
d. Utilization of the wheel assemblies =
900 ÷ 1200 = 75%
e. Excess inventory of wheel assemblies
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Bottleneck Principles (7)1. Utilization of a non-bottleneck resource is not determined
by its potential, but by another constraint in the system.
2. Utilization of a non-bottleneck 100% of the time does not produce 100% utilization.
3. The capacity of the system depends on the capacity of the bottleneck.
4. Time saved at a non-bottleneck saves the system nothing.
5. Capacity and priority must be considered together.
6. Loads can and should be split.
7. Focus should be on balancing the flow in the shop.
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Managing Bottlenecks
1. Establish a time buffer before each bottleneck.
2. Control the rate of material feeding the bottleneck.
3. Do everything to provide the bottleneck with capacity.
4. Adjust loads.
5. Change the schedule.
Back schedule before the bottleneck; forward schedule after the bottleneck.
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Theory of Constraints
• 1. Identify the constraint
Process 15 per hour
Process 27 per hour
Process 34 per hour
Process 49 per hour
Marketing sells5 per hour?
Figure 6.11
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Theory of Constraints continued
2. Exploit the constraint. (idle time?)
3. Subordinate everything to the constraint.
4. Elevate the constraint.
5. Once the constraint is a constraint no-
longer, find the new one and repeat the
steps.
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Drum-Buffer-Rope
• Drum - pace of production set by the
constraint
• Buffer - inventory established before the
constraint
• Rope - coordinated release of material
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem
Work Center 20: Capacity = 40 hours per week
Y: Setup = 1 hour, Run Time = .3 hours per piece
Z: Setup = 2 hours, Run Time = .2 hours per piece
Let x = the number of Y’s and Z’s to produce
1 + 0.3x + 2 + .2x = 40 hours
0.5x = 37 hours
x = 74 (you can produce 74 Y’s and 74 Z’s)
X
Y Z
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Implementation
• Issuing shop orders to manufacturing
• Which have a good chance of being completed on time
• Orders which have the:– tooling– material– capacity
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Shop Order Information
• Order number,
description
• Engineering Drawings
• Bills of Material
• Route Sheets
• Material Issue Tickets
• Tool Requisitions
• Job Tickets
• Move Tickets
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Review Order
Check Toolingand MaterialAvailability
Check CapacityRequirementsand Availability
Release Order
Okay?
Okay?
ResolveNo
Yes
Resolveor
Reschedule
No
Yes
Figure 6.12Order ReleaseProcess
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Control
• Control the work going into and out of a work center: Input/output control
• Set the priority of orders to run at each work center
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Input / Output ControlInput Rate
Control
Output RateControl
Queue(Load, WIP)
Figure 6.13Input/output control
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Work Center: 201Capacity per period: 40 standard hours
Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10
Planned Output 40 40 40 40 40 200
Actual Output 32 36 44 44 36 192
Cumulative Variance -8 -12 -8 -4 -8 -8
Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20
Figure 6.14 Input/output report
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Cumulative Variance
• The difference between the total planned for a given period and the actual total for that period
• Cumulative variance
= previous cumulative variance + actual
- planned
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Work Center: 201Capacity per period: 40 standard hours
Period 1 2 3 4 5 Total
Planned Input 38 32 36 40 44 190
Actual Input 34 32 32 42 40 180
Cumulative Variance -4 -4 -8 -6 -10 -10
Planned Output 40 40 40 40 40 200
Actual Output 32 36 44 44 36 192
Cumulative Variance -8 -12 -8 -4 -8 -8
Planned Backlog 32 30 22 18 18 22
Actual Backlog 32 34 30 18 16 20
Figure 6.14 Input/output report
Cumulative variance week 2 = -4 + 32 -32 = -4
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Example Problem: Input/OutputWeek 1 2
Planned Input 45 40
Actual Input 42 46
Cumulative Variance
Planned Output 40 40
Actual Output 42 44
Cumulative Variance
Planned Backlog 30
Actual Backlog 30
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Operations Sequencing
• “a technique for short term planning of actual jobs to be run in each work center based on capacities and priorities.”
APICS Dictionary 11th Edition
• Priority: The sequence in which jobs should run at a work center
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Dispatching
• Selecting and sequencing jobs to be run at a work center
• Dispatch list• Plant, department, work center
• Part number, shop order number, operation number and description
• Standard hours
• Priority information
• Jobs coming to the work center
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Dispatching Rules
• FCFS - First come, first served
• EDD - Earliest job due date
• ODD - Earliest operation due date
• SPT - Shortest processing time
• CR - Critical ratio
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Critical Ratio
CR= due date - present date
lead time remaining
= actual time remaining
lead time remaining
CR<1 Behind Schedule
CR=1 On Schedule
CR>1 Ahead of Schedule
CR<0 Already late
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Sequencing RuleJob
ProcessTime(days)
ArrivalDate
DueDate
OperationDue Date FCFS EDD ODD SPT
A 4 223 245 233 2 4 1 3
B 1 224 242 239 3 2 2 1
C 5 231 240 240 4 1 3 4
D 2 219 243 243 1 3 4 2
Figure 6.16 Application of sequencing rules
Sequencing Rules
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Reporting
• Feedback of what is actually happening on the shop floor
• Needed for management decisions
on-hand on-order
job status shortages
scrap material shortages
Arnold, Chapman, & Clive: Intro Materials Management, 6th ed.
© 2008 Pearson Education, Upper Saddle River, NJ 07458. All Rights Reserved.
Production Activity Control Summary
• Converting MRP plans into action– Reporting results– Revising plans
• Need:– detailed and current schedules and priorities
• Results:– on-time deliveries, well utilized labor, and
equipment, minimum inventory levels