    PROCUREMENT WING

    OF

    BESCOM

    BANGALORE

  • 8/3/2019 Procurement Presentation 04.8

    3/40

    3

    Requirement of Major Materials for Planned & Non-

    Planned Works in C O&M Circles, BESCOM for the FY

    2011-12

    &Allotment of Materials C O&M Circles wise

    for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    4/40

    4

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in SOUTH CIRCLE, BESCOM for the FY 2011-12

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 87 10 77 0 0 0 10 10

    2 D.Trs 63 KVA Nos. 19 10 9 0 0 0 10 0

    3 D.Trs 100 KVA Nos. 185 8 177 0 0 5 3 10

    4 D.Trs 250 KVA Nos. 317 9 308 0 0 7 2 105 D.Trs 500 KVA Nos. 25 3 22 0 0 1 2 0

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 10 10 10 10 10 10 7

    2 D.Trs 63 KVA Nos. 3 3 3 0 0 0 0

    3 D.Trs 100 KVA Nos. 25 25 25 25 27 20 20

    4 D.Trs 250 KVA Nos. 43 45 50 40 40 50 30

    5 D.Trs 500 KVA Nos. 2 4 4 4 3 3 2

  • 8/3/2019 Procurement Presentation 04.8

    5/40

    5

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 10 0 10 0 0 0 0 10

    4 PSC Poles 9 mts Nos. 3566 1165 2401 350 740 75 0 0

    5 RCC Pole 9 mts Nos. 3336 150 3186 150 0 0 0 0

    6 Spun Pole Nos. 437 0 437 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    4 PSC Poles 9 mts Nos. 350 400 400 400 350 350 151

    5 RCC Pole 9 mts Nos. 460 500 500 450 450 450 376

    6 Spun Pole Nos. 70 70 75 75 80 35 32

    Requirement/Allotment ofPOLESfor Planned & Non-Planned

    Works in SOUTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    6/40

    6

    SL No Name of the Material Unit

    Already Allotted

    TotalRequirement

    Allottedtill

    July-11

    Balance Apr-11 May-11 June-11

    July-

    1

    1

    Aug-11

    1 Rabbit ACSR Conductor Kms 483.62 150.00 333.62 0.00 0.00 100.00 50.00 50.00

    2 Coyote ACSR Conductor Kms 91.97 0.00 91.97 0.00 0.00 0.00 0.00 0.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 40.00 50.00 40.00 40.00 40.00 50.00 23.62

    2 Coyote ACSR Conductor Kms 10.00 15.00 15.00 10.00 15.00 14.00 12.97

    Requirement/Allotment ofCONDUCTORfor Planned & Non-Planned

    Works in SOUTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    7/40

    7

    SL No Name of the Material UnitAlready Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11July-

    11Aug-11

    1 45 KN Disc Insulator Nos. 5448 0 5448 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 20265 0 20265 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 14023 1500 12523 0 0 1500 0 0

    4 G.I. Pin 1.1 KV Nos. 16105 0 16105 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 8589 0 8589 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set 0 0 0 0 0 0 0 0

    8 SPMT for 250 KVA Set 216 0 216 0 0 0 0 0

    9 L.T.Protection Kit Set 1351 0 1351 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 57.00 27.85 29.15 0 0 11 16.85 4.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 0 0 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 0 0 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 0 0 0 0 0 0 0

    4 G.I. Pin 1.1 KV Nos. 0 0 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 0 0 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set 0 0 0 0 0 0 0

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 0 0 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 3.5 3.5 3.5 3.5 3.5 3.5 3.5

    Requirement/Allotment ofMAJOR LINEMATERIALSfor Planned &

    Non-Planned Works in SOUTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    8/40

    8

    SL

    NoName of the Material Unit

    Already Allotted

    TotalRequirement

    Allottedtill

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 0 0 0 0 0 0 0 0

    2 D.Trs 63 KVA Nos. 0 10 -10 0 0 0 10 0

    3 D.Trs 100 KVA Nos. 168 6 162 0 0 1 5 10

    4 D.Trs 250 KVA Nos. 283 12 271 0 0 2 10 155 D.Trs 500 KVA Nos. 5 0 5 0 0 0 0 0

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 0 0 0 0 0 0 0

    2 D.Trs 63 KVA Nos. 0 0 0 0 0 0 0

    3 D.Trs 100 KVA Nos. 20 25 25 30 25 15 12

    4 D.Trs 250 KVA Nos. 30 38 45 40 40 43 35

    5 D.Trs 500 KVA Nos. 2 1 1 0 1 0 0

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in NORTH CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    9/40

    9

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    4 PSC Poles 9 mts Nos. 80 80 90 90 90 85 62

    5 RCC Pole 9 mts Nos. 600 600 800 800 500 400 389

    6 Spun Pole Nos. 35 35 40 40 40 30 31

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 5 0 5 0 0 0 0 5

    4 PSC Poles 9 mts Nos. 2112 1535 577 350 1110 75 0 0

    5 RCC Pole 9 mts Nos. 4239 150 4089 75 0 75 0 0

    6 Spun Pole Nos. 251 0 251 0 0 0 0 0

    Requirement/Allotment ofPOLES for Planned & Non-Planned

    Works in NORTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    10/40

    10

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 415.34 100.00 315.34 0.00 0.00 50.00 50.00 50.00

    2 Coyote ACSR Conductor Kms 70.49 0.00 70.49 0.00 0.00 0.00 0.00 0.00

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 40.00 45.00 40.00 30.00 40.00 40.00 30.00

    2 Coyote ACSR Conductor Kms 10.00 10.00 0.00 10.00 15.00 15.00 10.00

    Requirement/Allotment ofCONDUCTORfor Planned & Non-Planned

    Works in NORTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    11/40

    11

    SLNo

    Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 2827 0 2827 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 10838 0 10838 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 6829 0 6829 0 0 0 0 0

    4 G.I. Pin 1.1 KV Nos. 10306 0 10306 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 5520 0 5520 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set 0 0 0 0 0 0 0 08 SPMT for 250 KVA Set 202 0 202 0 0 0 0 0

    9 L.T.Protection Kit Set 0 0 0 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 16.20 26.00 -10 0 0 11 16.05 0

    SL

    NoName of the Material Unit Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 350 400 450 500 450 450 227

    2 Pin Insulator Shells 1.1 KV Nos. 1500 1800 1800 1500 1400 1400 1438

    3 Pin Insulator Shells 11 KV Nos. 1000 1000 1200 1200 800 800 829

    4 G.I. Pin 1.1 KV Nos. 1500 1500 1800 1800 1500 1200 1006

    5 G.I. Pin 11 KV Nos. 800 800 1000 1000 700 600 620

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set 0 0 0 0 0 0 0

    8 SPMT for 250 KVA Set 25 25 40 40 25 25 22

    9 L.T.Protection Kit Set 0 0 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 0 0 0 0 0 0 0

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in NORTH CIRCLE, BESCOM for the FY 2011-12

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    12/40

    12

    SL No Name of the Material Unit

    Already Allotted

    TotalRequirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 87 10 77 0 0 0 10 10

    2 D.Trs 63 KVA Nos. 19 20 -1 0 0 0 20 0

    3 D.Trs 100 KVA Nos. 353 14 339 0 0 6 8 10

    4 D.Trs 250 KVA Nos. 600 21 579 0 0 9 12 10

    5 D.Trs 500 KVA Nos. 30 3 27 0 0 1 2 0

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 10 10 10 10 10 10 7

    2 D.Trs 63 KVA Nos. 3 3 3 0 0 0 0

    3 D.Trs 100 KVA Nos. 25 25 25 25 27 20 20

    4 D.Trs 250 KVA Nos. 43 45 50 40 40 50 30

    5 D.Trs 500 KVA Nos. 2 4 4 4 3 3 2

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in BMAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    13/40

    13

    Requirement/Allotment ofPOLES for Planned & Non-Planned

    Works in BMAZ, BESCOM for the FY 2011-12

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 15 0 15 0 0 0 0 15

    4 PSC Poles 9 mts Nos. 5678 2700 2978 700 1850 150 0 05 RCC Pole 9 mts Nos. 7575 300 7275 225 0 75 0 0

    6 Spun Pole Nos. 688 0 688 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 0 0 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    4 PSC Poles 9 mts Nos. 430 480 490 490 440 435 213

    5 RCC Pole 9 mts Nos. 1060 1100 1300 1250 950 850 765

    6 Spun Pole Nos. 105 105 115 115 120 65 63

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    14/40

    14

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in BMAZ , BESCOM for the FY 2011-12

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requiremen

    t

    Allotted

    till

    July-11Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 898.96 250.00 648.96 0.00 0.00 150.00 100.00 100.00

    2 Coyote ACSR Conductor Kms 162.46 0.00 162.46 0.00 0.00 0.00 0.00 0.00

    SL

    NoName of the Material Unit Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 80.00 95.00 80.00 70.00 80.00 90.00 54.00

    2 Coyote ACSR Conductor Kms 20.00 25.00 15.00 20.00 30.00 29.00 23.00

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    15/40

    15

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in BMAZ, BESCOM for the FY 2011-12

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 8275 0 8275 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 31103 0 31103 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 20852 1500 19352 0 0 1500 0 0

    4 G.I. Pin 1.1 KV Nos. 26411 0 26411 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 14109 0 14109 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set0 0 0 0 0 0 0 0

    8 SPMT for 250 KVA Set 418 0 418 0 0 0 0 0

    9 L.T.Protection Kit Set 1351 0 1351 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 73 53.85 19.35 0 0 22 32.9 4.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 1150 1150 1300 1400 1200 1200 875

    2 Pin Insulator Shells 1.1 KV Nos. 4500 4300 4800 4500 4400 4900 3703

    3 Pin Insulator Shells 11 KV Nos. 2800 2800 2700 3200 2800 2800 2252

    4 G.I. Pin 1.1 KV Nos. 3800 4000 4300 4100 3800 3700 2711

    5 G.I. Pin 11 KV Nos. 2000 2100 2300 2500 1900 1600 1709

    6 SPMT for 25/63 KVA Set 0 0 0 0 0 0 0

    7 SPMT for 100 KVA Set 0 0 0 0 0 0 0

    8 SPMT for 250 KVA Set 60 60 75 70 55 55 43

    9 L.T.Protection Kit Set 200 200 200 210 200 200 141

    10 Fresh Transformer Oil Good KL 4.00 4.00 4.00 4.00 4.00 4.00 4.00

    NOTE: Action Plan works Approved, LOI issued on 02.08.2011 to execute the works

  • 8/3/2019 Procurement Presentation 04.8

    16/40

    16

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Require

    ment

    Allotted

    till

    July-11

    Balance Apr-11 May-1 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 1999 182 1817 0 12 98 72 80

    2 D.Trs 63 KVA Nos. 863 60 803 12 25 23 0 70

    3 D.Trs 100 KVA Nos. 391 24 367 4 0 20 0 30

    4 D.Trs 250 KVA Nos. 2 0 2 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL

    NoName of the Material Unit

    Future Allotment.

    Sep-11 Oct-11 Nov-11 Dec-1 Jan-12 Feb-12Mar-

    12

    1 D.Trs. 25 KVA Nos. 120 250 250 270 270 289 280

    2 D.Trs 63 KVA Nos. 90 90 100 110 123 110 110

    3 D.Trs 100 KVA Nos. 35 45 50 50 68 45 44

    4 D.Trs 250 KVA Nos. 2 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non Planned

    Works in BRC, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    17/40

    17

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in BRC, BESCOM for the FY 2011-12

    SL

    No

    Name of the

    MaterialUnit

    Already Allotted

    Total

    Requirement

    Allotted

    till July-

    11

    BalanceApr

    11

    May-

    11

    June-

    11

    July-

    11

    Aug-

    11

    1 PCC Pole 8 mts Nos. 600 40 560 0 0 0 40 50

    2 PSC Poles 8 mts Nos. 6398 70 6328 0 0 0 70 50

    3 RCC Pole 8 mts Nos. 3247 0 3247 0 0 0 0 40

    4 PSC Poles 9 mts Nos. 16963 400 16563 0 150 150 100 80

    5 RCC Pole 9 mts Nos. 5666 225 5441 150 0 75 0 20

    6 Spun Pole Nos. 35 0 35 0 0 0 0 0

    SL

    No

    Name of the

    MaterialUnit

    Future Allotment

    Sep-11 Oct-11Nov-

    11

    Dec-

    11

    Jan-

    12

    Feb-

    12

    Mar-

    12

    1 PCC Pole 8 mts Nos. 75 75 75 75 75 75 60

    2 PSC Poles 8 mts Nos. 900 900 900 900 900 900 878

    3 RCC Pole 8 mts Nos. 460 460 460 460 460 460 447

    4 PSC Poles 9 mts Nos. 2000 2420 2420 2420 2420 2420 2383

    5 RCC Pole 9 mts Nos. 700 790 790 790 790 790 771

    6 Spun Pole Nos. 0 5 5 10 10 5 0

  • 8/3/2019 Procurement Presentation 04.8

    18/40

    18

    SL NoName of the

    MaterialUnit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1Rabbit ACSR

    ConductorKms 5663.75 300.00 5363.7 0.00 0.00 100.00 200.00 100.00

    2Coyote ACSR

    Conductor

    Kms 140.41 0.00 140.41 0.00 0.00 0.00 0.00 0.00

    SL NoName of the

    MaterialUnit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1Rabbit ACSR

    ConductorKms 750.00 800.00 800.00 700.75 750.00 732.00 731.00

    2 Coyote ACSRConductor Kms 0.00 25.00 25.00 25.00 25.00 25.00 15.41

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in BRC , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    19/40

    19

    SLNo

    Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 28074 0 28074 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 48792 0 48792 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 71770 0 68410 0 0 0 0 0

    4 G.I. Pin 1.1 KV Nos. 47774 0 48792 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 68410 0 68410 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 2367 0 2367 0 0 0 0 0

    7 SPMT for 100 KVA Set 246 0 246 0 0 0 0 0

    8 SPMT for 250 KVA Set 15 0 15 0 0 0 0 0

    9 L.T.Protection Kit Set 5605 0 5605 0 0 0 0 0

    10 Fresh Transformer Oil Good KL58.00 76.25 -18.25 0.00 9.45 32.90 33.90 0.00

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 4100 4100 4100 4100 4100 4100 3474

    2 Pin Insulator Shells 1.1 KV Nos. 7000 7000 7000 7000 7000 7000 6792

    3 Pin Insulator Shells 11 KV Nos. 10000 10000 10000 10000 10000 10000 8410

    4 G.I. Pin 1.1 KV Nos. 7000 7000 7000 7000 7000 7000 6792

    5 G.I. Pin 11 KV Nos. 10000 10000 10000 10000 10000 10000 8410

    6 SPMT for 25/63 KVA Set 340 340 340 340 340 340 327

    7 SPMT for 100 KVA Set 0 241 241 241 241 241 241

    8 SPMT for 250 KVA Set 0 5 0 10 0 0 0

    9 L.T.Protection Kit Set 800 800 800 800 800 800 805

    10 Fresh Transformer Oil Good KL 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in BRC, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    20/40

    20

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till July-

    11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 1643 316 1327 64 99 119 34 120

    2 D.Trs 63 KVA Nos. 606 222 384 25 57 106 34 60

    3 D.Trs 100 KVA Nos. 121 97 24 7 20 54 16 2

    4 D.Trs 250 KVA Nos. 0 0 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material Unit

    Future Allotment.

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 155 172 185 195 180 175 145

    2 D.Trs 63 KVA Nos. 30 46 50 50 50 50 48

    3 D.Trs 100 KVA Nos. 2 2 2 5 5 3 3

    4 D.Trs 250 KVA Nos. 0 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in KOLAR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    21/40

    21

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    tillJuly-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 12758 0 12758 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 3522 0 3522 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 5093 0 5093 0 0 0 0 0

    4 PSC Poles 9 mts Nos. 7283 0 7283 0 0 0 0 0

    5 RCC Pole 9 mts Nos. 3686 75 3611 0 0 75 0 0

    6 Spun Pole Nos. 701 0 701 0 0 0 0 0

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 1914 1900 2000 2000 1330 1914 1700

    2 PSC Poles 8 mts Nos. 500 510 497 515 500 503 497

    3 RCC Pole 8 mts Nos. 728 680 755 720 800 680 730

    4 PSC Poles 9 mts Nos. 1040 1100 897 1150 1200 1000 896

    5 RCC Pole 9 mts Nos. 516 550 492 500 510 550 493

    6 Spun Pole Nos. 90 110 110 110 110 110 61

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in KOLAR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    22/40

    22

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 6398.12 200.00 6198.12 0.00 0.00 0.00 200.00 100.00

    2 Coyote ACSR Conductor Kms 1764.00 0.00 1764.00 0.00 0.00 0.00 0.00 0.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 800.00 870.00 910.00 910.00 850.00 879.00 879.12

    2 Coyote ACSR Conductor Kms 252.00 260.00 260.00 260.00 250.00 241.00 241.00

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in KOLAR CIRCLE , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    23/40

    23

    SL No Name of the Material Unit

    Already Allotted

    Total

    Require

    ment

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 24525 0 24525 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 23218 0 23218 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 55951 5500 50451 500 4000 1000 0 0

    4 G.I. Pin 1.1 KV Nos. 23874 500 23374 0 500 0 0 0

    5 G.I. Pin 11 KV Nos. 52343 1400 50943 0 1000 400 0 0

    6 SPMT for 25/63 KVA Set 2162 0 2162 0 0 0 0 0

    7 SPMT for 100 KVA Set 64 0 64 0 0 0 0 0

    8 SPMT for 250 KVA Set 200 0 200 0 0 0 0 0

    9 L.T.Protection Kit Set 3374 0 3374 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 120.00 78.11 41.89 3.00 28.35 33.81 12.95 5.00

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 3500 3500 4000 4000 4000 2763 2763

    2 Pin Insulator Shells 1.1 KV Nos. 3300 3300 3500 3500 3300 3159 3159

    3 Pin Insulator Shells 11 KV Nos. 7200 7200 7200 7200 7500 7500 6651

    4 G.I. Pin 1.1 KV Nos. 3300 3300 3800 3300 3800 2937 2937

    5 G.I. Pin 11 KV Nos. 7200 7300 7300 7500 7000 7322 7322

    6 SPMT for 25/63 KVA Set 300 350 350 300 310 276 276

    7 SPMT for 100 KVA Set 0 10 14 10 20 10 0

    8 SPMT for 250 KVA Set 10 30 30 30 30 50 20

    9 L.T.Protection Kit Set 500 450 450 500 500 487 487

    10 Fresh Transformer Oil Good KL 5.27 5.27 5.27 5.27 5.27 5.27 5.27

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in KOLAR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    24/40

    24

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 3642 498 3144 64 111 217 106 200

    2 D.Trs 63 KVA Nos. 1469 282 1187 37 82 129 34 130

    3 D.Trs 100 KVA Nos. 512 121 391 11 20 74 16 324 D.Trs 250 KVA Nos. 2 0 2 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 275 422 435 465 450 464 425

    2 D.Trs 63 KVA Nos. 120 136 150 160 173 160 158

    3 D.Trs 100 KVA Nos. 37 47 52 55 73 48 47

    4 D.Trs 250 KVA Nos. 2 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in BRAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    25/40

    25

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 13358 40 13318 0 0 0 40 50

    2 PSC Poles 8 mts Nos. 9920 70 9850 0 0 0 70 50

    3 RCC Pole 8 mts Nos. 8340 0 8340 0 0 0 0 40

    4 PSC Poles 9 mts Nos. 24246 400 23846 0 150 150 100 80

    5 RCC Pole 9 mts Nos. 9352 300 9052 150 0 150 0 206 Spun Pole Nos. 736 0 736 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 1989 1975 2075 2075 1405 1989 1760

    2 PSC Poles 8 mts Nos. 1400 1410 1397 1415 1400 1403 1375

    3 RCC Pole 8 mts Nos. 1188 1140 1215 1180 1260 1140 1177

    4 PSC Poles 9 mts Nos. 3040 3520 3317 3570 3620 3420 32795 RCC Pole 9 mts Nos. 1216 1340 1282 1290 1300 1340 1264

    6 Spun Pole Nos. 90 115 115 120 120 115 61

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in BRAZ CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    26/40

    26

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till July-

    11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 12062 500 11562 0 0 100 400 200

    2 Coyote ACSR Conductor Kms 1904 0 1904 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 1550 1670 1710 1611 1600 1611 1610

    2 Coyote ACSR Conductor Kms 252 285 285 285 275 266 256

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in BRAZ , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    27/40

    27

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 52599 0 52599 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 72010 0 72010 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 127721 5500 118861 500 4000 1000 0 0

    4 G.I. Pin 1.1 KV Nos. 71648 500 72166 0 500 0 0 0

    5 G.I. Pin 11 KV Nos. 120753 1400 119353 0 1000 400 0 0

    6 SPMT for 25/63 KVA Set 4529 0 4529 0 0 0 0 0

    7 SPMT for 100 KVA Set 310 0 310 0 0 0 0 0

    8 SPMT for 250 KVA Set 215 0 215 0 0 0 0 0

    9 L.T.Protection Kit Set 8979 0 8979 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 178.00 154.36 23.64 3.00 37.80 66.71 46.85 5.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 7600 7600 8100 8100 8100 6863 6237

    2 Pin Insulator Shells 1.1 KV Nos. 10300 10300 10500 10500 10300 10159 9951

    3 Pin Insulator Shells 11 KV Nos. 17200 17200 17200 17200 17500 17500 15061

    4 G.I. Pin 1.1 KV Nos. 10300 10300 10800 10300 10800 9937 9729

    5 G.I. Pin 11 KV Nos. 17200 17300 17300 17500 17000 17322 15732

    6 SPMT for 25/63 KVA Set 640 690 690 640 650 616 603

    7 SPMT for 100 KVA Set 0 251 255 251 261 251 241

    8 SPMT for 250 KVA Set 10 35 30 40 30 50 20

    9 L.T.Protection Kit Set 1300 1250 1250 1300 1300 1287 1292

    10 Fresh Transformer Oil Good KL 5.27 5.27 5.27 5.27 5.27 5.27 5.27

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in BRAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    28/40

    28

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 1356 382 974 72 79 158 73 50

    2 D.Trs 63 KVA Nos. 188 171 17 0 41 93 37 5

    3 D.Trs 100 KVA Nos. 42 67 -25 0 2 43 22 0

    4 D.Trs 250 KVA Nos. 0 2 -2 0 0 0 2 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material Unit

    Future Allotment.

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 130 144 130 130 125 145 120

    2 D.Trs 63 KVA Nos. 0 5 5 2 0 0 0

    3 D.Trs 100 KVA Nos. 0 0 0 0 0 0 0

    4 D.Trs 250 KVA Nos. 0 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non Planned

    Works in TUMKUR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    29/40

    29

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 260 290 -30 0 0 0 290 0

    2 PSC Poles 8 mts Nos. 14243 150 14093 0 0 0 150 1000

    3 RCC Pole 8 mts Nos. 2956 250 2706 0 0 0 250 250

    4 PSC Poles 9 mts Nos. 15506 200 15306 0 0 0 200 1000

    5 RCC Pole 9 mts Nos. 3338 0 3338 0 0 0 0 500

    6 Spun Pole Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 0 0 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 2000 2000 2500 2500 2300 1396 397

    3 RCC Pole 8 mts Nos. 350 400 400 556 350 350 50

    4 PSC Poles 9 mts Nos. 2200 2100 2100 2200 2200 2506 1000

    5 RCC Pole 9 mts Nos. 400 380 380 410 448 410 410

    6 Spun Pole Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in TUMKUR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    30/40

    30

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 10031.36 300.00 9731.36 0.00 0.00 100.00 200.00 100.00

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 1266 1400 1400 1500 1500 1300 1266

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in TUMKUR CIRCLE , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    31/40

    31

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 21294 0 21294 0 0 0 0 0

    2 Pin Insulator Shells 1.1 KV Nos. 29299 0 29299 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 64663 2500 62163 0 2500 0 0 0

    4 G.I. Pin 1.1 KV Nos. 29299 0 29299 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 64663 0 64663 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 1306 0 1306 0 0 0 0 0

    7 SPMT for 100 KVA Set 230 0 230 0 0 0 0 0

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 1576 0 1576 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 105.00 76.15 28.85 10.00 28.35 28.35 9.45 5.00

    SL No Name of the Material Unit Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 3000 3042 3000 3300 3300 3000 2652

    2 Pin Insulator Shells 1.1 KV Nos. 4200 4200 4500 4500 4200 4200 3499

    3 Pin Insulator Shells 11 KV Nos. 8880 9000 9000 10000 10000 8500 6783

    4 G.I. Pin 1.1 KV Nos. 4200 4200 4300 4300 4100 4100 4099

    5 G.I. Pin 11 KV Nos. 10000 10000 10000 9500 9500 9500 6163

    6 SPMT for 25/63 KVA Set 200 200 200 180 180 200 146

    7 SPMT for 100 KVA Set 35 35 35 35 30 30 30

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 225 250 250 250 250 250 101

    10 Fresh Transformer Oil Good KL 3.50 3.50 3.50 3.50 3.50 3.50 2.85

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned &

    Non-Planned Works in TUMKUR CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    32/40

    32

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 3046 462 2584 84 66 196 116 84

    2 D.Trs 63 KVA Nos. 162 37 125 8 15 9 5 10

    3 D.Trs 100 KVA Nos. 77 17 60 0 0 16 1 5

    4 D.Trs 250 KVA Nos. 0 1 -1 1 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL

    NoName of the Material Unit

    Future Allotment.

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 350 400 410 410 350 380 204

    2 D.Trs 63 KVA Nos. 15 20 20 20 15 15 10

    3 D.Trs 100 KVA Nos. 7 7 10 10 10 6 5

    4 D.Trs 250 KVA Nos. 0 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in DAVANAGERE CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    33/40

    33

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 20397 0 20397 0 0 0 0 0

    2 PSC Poles 8 mts Nos. 10962 0 10962 0 0 0 0 0

    3 RCC Pole 8 mts Nos. 3912 0 3912 0 0 0 0 0

    4 PSC Poles 9 mts Nos. 4099 0 4099 0 0 0 0 0

    5 RCC Pole 9 mts Nos. 6670 0 6670 0 0 0 0 0

    6 Spun Pole Nos. 0 0 0 0 0 0 0 0

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 3000 3000 3200 3200 3000 2499 2498

    2 PSC Poles 8 mts Nos. 1500 1600 1700 1700 1500 1500 1462

    3 RCC Pole 8 mts Nos. 550 600 600 600 550 550 462

    4 PSC Poles 9 mts Nos. 600 600 599 550 600 600 550

    5 RCC Pole 9 mts Nos. 900 1000 1000 1000 950 950 870

    6 Spun Pole Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in DAVANAGERE CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    34/40

    34

    SL

    NoName of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 9650.25 300.00 9350.25 0.00 0.00 100.00 200.00 100.00

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 1350.00 1350.00 1200.00 1300.00 1300.00 925.00 925.25

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in DAVANAGERE CIRCLE , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    35/40

    35

    SL

    NoName of the Material Unit

    Already AllottedTotal

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 23593 5000 18593 0 0 0 5000 0

    2 Pin Insulator Shells 1.1 KV Nos. 57321 0 57321 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 100270 1000 99270 1000 0 0 0 0

    4 G.I. Pin 1.1 KV Nos. 57321 0 57321 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 100270 0 100270 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 3208 0 3208 0 0 0 0 0

    7 SPMT for 100 KVA Set 77 0 77 0 0 0 0 0

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 3362 0 3362 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 200.00 66.15 133.85 0.00 28.35 18.90 18.90 10.00

    SL

    NoName of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 2600 2600 2800 2800 2500 2600 2693

    2 Pin Insulator Shells 1.1 KV Nos. 8200 8200 8321 8100 8200 8200 8100

    3 Pin Insulator Shells 11 KV Nos. 14200 14300 14300 14200 14200 14300 13770

    4 G.I. Pin 1.1 KV Nos. 8200 8200 8321 8100 8200 8200 8100

    5 G.I. Pin 11 KV Nos. 14300 14500 14500 14300 14300 14185 14185

    6 SPMT for 25/63 KVA Set 500 400 550 450 450 500 358

    7 SPMT for 100 KVA Set 10 10 17 10 10 10 10

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 500 500 500 550 500 450 362

    10 Fresh Transformer Oil Good KL 20.00 20.00 20.00 20.00 18.00 15.00 10.85

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned & Non-

    Planned Works in DAVANAGERE CIRCLE, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    36/40

    36

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allottedtill

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 D.Trs. 25 KVA Nos. 4402 844 3558 156 145 354 189 134

    2 D.Trs 63 KVA Nos. 350 208 142 8 56 102 42 15

    3 D.Trs 100 KVA Nos. 119 84 35 0 2 59 23 5

    4 D.Trs 250 KVA Nos. 0 3 -3 1 0 0 2 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment.

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 D.Trs. 25 KVA Nos. 480 544 540 540 475 525 324

    2 D.Trs 63 KVA Nos. 15 25 25 22 15 15 10

    3 D.Trs 100 KVA Nos. 7 7 10 10 10 6 5

    4 D.Trs 250 KVA Nos. 0 0 0 0 0 0 0

    5 D.Trs 500 KVA Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofTransformers for Planned & Non-Planned

    Works in CTAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    37/40

    37

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 PCC Pole 8 mts Nos. 20657 290 20367 0 0 0 290 0

    2 PSC Poles 8 mts Nos. 25205 150 25055 0 0 0 150 1000

    3 RCC Pole 8 mts Nos. 6867 250 6617 0 0 0 250 250

    4 PSC Poles 9 mts Nos. 19605 200 19405 0 0 0 200 1000

    5 RCC Pole 9 mts Nos. 10008 0 10008 0 0 0 0 500

    6 Spun Pole Nos. 0 0 0 0 0 0 0 0

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 PCC Pole 8 mts Nos. 3000 3000 3200 3200 3000 2499 2498

    2 PSC Poles 8 mts Nos. 3500 3600 4200 4200 3800 2896 1859

    3 RCC Pole 8 mts Nos. 900 1000 1000 1156 900 900 512

    4 PSC Poles 9 mts Nos. 2800 2700 2699 2750 2800 3106 1550

    5 RCC Pole 9 mts Nos. 1300 1380 1380 1410 1398 1360 1280

    6 Spun Pole Nos. 0 0 0 0 0 0 0

    Requirement/Allotment ofPOLES for Planned & Non-PlannedWorks in CTAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    38/40

    38

    SL No Name of the Material Unit

    Already Allotted

    Total

    Requirement

    Allotted

    till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 Rabbit ACSR Conductor Kms 19682 600.00 19081.61 0.00 0.00 200.00 400.00 200.00

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    SL No Name of the Material UnitFuture Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 Rabbit ACSR Conductor Kms 2616.00 2750.00 2600.00 2800.0 2800.00 2225.00 2191.00

    2 Coyote ACSR Conductor Kms 0.00 0.00 0.00 0.00 0.00 0.00 0.00

    Requirement/Allotment ofCONDUCTOR for Planned & Non-Planned

    Works in CTAZ , BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    39/40

    39

    SL No Name of the Material Unit

    Already Alloted

    Total

    Requirement

    Allotted

    Till

    July-11

    Balance Apr-11 May-11 June-11 July-11 Aug-11

    1 45 KN Disc Insulator Nos. 44887 5000 39887 0 0 0 5000 0

    2 Pin Insulator Shells 1.1 KV Nos. 86619 0 86619 0 0 0 0 0

    3 Pin Insulator Shells 11 KV Nos. 164933 3500 161433 1000 2500 0 0 0

    4 G.I. Pin 1.1 KV Nos. 86619 0 86619 0 0 0 0 0

    5 G.I. Pin 11 KV Nos. 164933 0 164933 0 0 0 0 0

    6 SPMT for 25/63 KVA Set 4514 0 4514 0 0 0 0 0

    7 SPMT for 100 KVA Set 307 0 307 0 0 0 0 08 SPMT for 250 KVA Set 0 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 4938 0 4938 0 0 0 0 0

    10 Fresh Transformer Oil Good KL 305.00 142.30 162.70 10.00 56.70 47.25 28.35 15.00

    SL No Name of the Material Unit

    Future Allotment

    Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12

    1 45 KN Disc Insulator Nos. 5600 5642 5800 6100 5800 5600 5345

    2 Pin Insulator Shells 1.1 KV Nos. 12400 12400 12821 12600 12400 12400 11599

    3 Pin Insulator Shells 11 KV Nos. 23080 23300 23300 24200 24200 22800 20553

    4 G.I. Pin 1.1 KV Nos. 12400 12400 12621 12400 12300 12300 12199

    5 G.I. Pin 11 KV Nos. 24300 24500 24500 23800 23800 23685 20348

    6 SPMT for 25/63 KVA Set 700 600 750 630 630 700 504

    7 SPMT for 100 KVA Set 45 45 52 45 40 40 40

    8 SPMT for 250 KVA Set 0 0 0 0 0 0 0

    9 L.T.Protection Kit Set 725 750 750 800 750 700 463

    10 Fresh Transformer Oil Good KL 24.00 24.00 24.00 24.00 22.00 19.00 14.00

    Requirement/Allotment ofMAJOR LINE MATERIALS for Planned & Non-

    Planned Works in CTAZ, BESCOM for the FY 2011-12

  • 8/3/2019 Procurement Presentation 04.8

    40/40

    40