Procurement and Construction Management and Oversight What Board Members Need to Know

14
Procurement and Construction Management and Oversight What Board Members Need to Know Jerry Smiley, AICP 24 July 2013

description

Procurement and Construction Management and Oversight What Board Members Need to Know Jerry Smiley, AICP 24 July 2013. Major Capital Projects Alternative Contracting Approaches. Pre-Planning and Acquisition. Finance. Design. - PowerPoint PPT Presentation

Transcript of Procurement and Construction Management and Oversight What Board Members Need to Know

Page 1: Procurement and Construction Management and Oversight What Board Members Need to Know

Procurement and Construction Management and Oversight

What Board Members Need to Know

Jerry Smiley, AICP 24 July 2013

Page 2: Procurement and Construction Management and Oversight What Board Members Need to Know

2

Major Capital Projects

Alternative Contracting Approaches

Operations MaintenancePre-Planning

and Acquisition

Finance Design Construction

RTD Union Station DART Orange Line

Page 3: Procurement and Construction Management and Oversight What Board Members Need to Know

3

Major Capital Projects

Alternative Contracting Approaches – Risk Allocation

Contractor’s Risk / Contractor’s Control

Owner’s Risk / Owner’s Control

Design-Bid-Build/CMGC

(DBB/CMGC)

Design-Build

(DB)

Design-Build-Operate-Maintain (DBOM)

Public Private Partnerships

(DBOM+F/BOT/BOO)

Page 4: Procurement and Construction Management and Oversight What Board Members Need to Know

4

$

Design-Bid-Build

Project Structure and Approach

Architect/EngineerArchitect/Engineer

General Contractor

General Contractor

PD&EPD&E PEPE Final DesignFinal Design ProcurementProcurement ConstructionConstruction$ $ $BU

DG

ET

BID

ES

TIM

ATE

BU

DG

ET

OwnerOwner

Subcontractors and Suppliers

Contractor Selected

Page 5: Procurement and Construction Management and Oversight What Board Members Need to Know

5

Design-Bid-Build

OverviewPros•Standard contracting approach•Transparent procurement process•Public acceptance•Fairest to bidders, level playing field

Cons•Slowest method•Cost not established until bids received•Design change impacts•In some cases, fosters adversarial relationships and increases probability of disputes

Owner retains greatest control, but assumes greatest risk

Page 6: Procurement and Construction Management and Oversight What Board Members Need to Know

6

$

Design-Build

Project Structure and Approach

Design-BuilderDesign-Builder

PD&EPD&E PEPE ProcurementProcurement Final DesignFinal Design

ConstructionConstruction

$ $BU

DG

ET

BID

ES

TIM

ATE

OwnerOwner

Contractor Selected

Subcontractors and Suppliers

Architect/EngineerArchitect/Engineer

Page 7: Procurement and Construction Management and Oversight What Board Members Need to Know

7

Design-Build

SummaryPros•Project costs are determined earlier•Constructability and value engineering benefits accrue to Owner •Single point responsibility •Reduced claims exposure•Tends to be the fastest method

Cons•More complex contracting approach•Competition may be limited•Requires earlier project definition•Reduces design input by Owner•Changes are more costly

Substantial risk is shifted to the contractor,contractor assumes more control

Page 8: Procurement and Construction Management and Oversight What Board Members Need to Know

Construction Manager/General Contractor

Project Structure and Approach

ConsultantsConsultants General Contractor

General Contractor

PD&EPD&E Final Design Final Design$$

OwnerOwner

Subcontractors and Suppliers

Contractor Selected ConstructionConstruction

PEPE$8

Procurement Procurement

BU

DG

ET

BU

DG

ET

GM

P

8

Page 9: Procurement and Construction Management and Oversight What Board Members Need to Know

CMGC

OverviewProsPros•CMGC participates in developing design, budget and schedule•Design assistance reduces E&O•Allows for fast-track (non-linear) construction•Reduces uncertainties (change orders)•Owner knows costs upfront

ConsCons•No significant input by Owner in design•Complex process requiring qualified staff•CMGC’s role changes from CM to GC once construction starts•Owner does not transfer E&O risk•In some areas, relatively few true construction managers

Owner retains significant control,owner retains significant risk

99

Page 10: Procurement and Construction Management and Oversight What Board Members Need to Know

Public Private Partnerships

Project Structure and Approach

PD&EPD&E $

OwnerOwner

Subcontractors and Suppliers

Partner Selected

Construction and Testing

Construction and TestingDesignDesign$

10

Procurement Procurement

ConcessionaireConcessionaire

O&M Contractors

O&M Contractors

RevenueOperationsRevenue

Operations

MaintenanceMaintenance

Design-BuilderDesign-Builder

Architect/EngineerArchitect/Engineer

BU

DG

ET

BU

DG

ET

10

Page 11: Procurement and Construction Management and Oversight What Board Members Need to Know

PPP

OverviewPros•Advance infrastructure projects years in advanceAdvance infrastructure projects years in advance•Value for money through optimal risk transfer and risk management•Accountability through performance incentives•Operational and project execution risk is transferred to the private sector

Cons•Contracts are much more complicated•Difficult to anticipate all possible contingencies that could arise in long-term contract•Re-negotiation of contracts can be high•Performance enforcement

Owner only controls what is negotiated, risk depends on skill of negotiators

1111

Page 12: Procurement and Construction Management and Oversight What Board Members Need to Know

12

What Questions Should You Be Asking?

Page 13: Procurement and Construction Management and Oversight What Board Members Need to Know

13

Risk Allocation Principles

• Risks are unavoidable

• Risk should be allocated to maximize probability of success

• Assessing who is best able to manage risk

• Optimum risk shifting should be the goal – not maximum risk shifting

• Shifting unreasonable risk to the contractor

o Reduces competition

o Increases contingencies

o Increases project disputes

Page 14: Procurement and Construction Management and Oversight What Board Members Need to Know

• Why are we choosing the selected procurement model?

• Would the project be able to move forward using another model?

• Is this model in the agency’s best long-term financial interest?

• Do we have the staff to properly execute this model?

14

What Questions Should You Be Asking?