This table shows a record of significant changes to the document.
Version Date Who Description of ChangeV1.0 2010-04-13 OUDDANI MustaphaV1.2 2010-06-23 DEVOS Marc LSR ID declaration
Contact Ericsson: Marc Devos Contact Mobistar : Mohamed Amraoui
2 CONFIGURATION CSG
2.1 Connection CSG
Step 1: Connect SHDSL links on the SHDSL Board of the CSG. Same for ADSL.
Step 2: Connect your PC on the ETH/OAM port of the CXPA Board with RJ45 cable
The following indicators are present on the front panel of the CXPA: STAT indicator, red or green, which indicates the board working status PROG indicator, red or green, which indicates the running status of the program SYNC indicator, red or green, which indicates the clock synchronization status SRV indicator, red, yellow or green, which indicates the service status CRIT indicator, red, which indicates critical alarms MAJ indicator, orange, which indicates major alarms MIN indicator, yellow, which indicates minor alarms LINK indicator, green, which indicates the port connection status ACT indicator, yellow, which indicates the data transceiving status of the port
Step 3: Start U 2000 server and after all the processes are started, start U2000 Web LCT
The default IP of NE PTN910 is 129.9.X.X/255.255.0.0Your laptop must have an IP on this range.In case that the PTN910 was already configured, be sure that you have an IP Address in its range.For U2000 Web LCT starts use the following:
User: adminPassword: admin123
Step 4: Click Auto Discovery NextThe system will start to search the NE
Step 5: When the NE is found Click stopCreate
The NE will be created on U2000LCT
Use the following:
User: lctPassword: password
Step 6: Click right on the NEConfigurationupload
The configuration of the NE will be uploaded on U2000LCT
Step 7: Click right NEOpen Slot Diagram
Click right on the SHDSL board and ADSL boardAdd physical board
Step 8: Click right NE NE explorer
Step 9: ConfigurationNE Attribute Modify NE IDEnter the values given by engineer
Step 10: Communication Communication ParametersConfigure the Management IP address
IP Address: Management IP of the CSGSubnet Mask: 255.255.224.0Gateway IP address: Management IP of the MASG (Primary GNE IP Address: 10.35.63.254)
You will loose the connectivity after configuring the management IP.You need to configure your laptop with an IP on the same range of the management IP.Then you can start to configure interface and management tunnel.
Step 11: Change the LSR ID
Function Tree -> Configuration -> MPLS Management -> Basic Configuration
Note: If the LSR ID is not blank, after you modify the LSRID the softwar of PTN910 will reboot. Wait until the PTN910 software startup completely, and then do the other configuration.
2.2 Configuration Interface
2.1.1 G.SHDSL Link
Step 1:Set G.shdsl bound mode is EFM
Interface Management—》DSL Interface—》G.shdsl Interfaces—Bound Mode
Step 2:Check G.shdsl link statusPort state = Data OKPort state = IDLE NOK
Interface Management—》DSL Interface—》G.shdsl InterfacesGenernal AttributesClick on “Query” button
Step 3:Set G.shdsl link port mode is Layer Mix
Interface Management—》Ethernet Virtual Interface—》Genernal Attributes
Step 4:Create sub-Interface on G.shdsl link
Interface Management—》Ethernet Virtual Interface—》Genernal Attributes—》NEW
Port : 50Name : Sub-1050Port Type : VLAN Sub interface
Board : Virtual PortPort : choose the port where the 4-SDH4 board is connected VLAN : 1050Specify IP Address: ManuallyIP address: set IP primary addressIP Mask : 255.255.254.0Enable tunnel : Enabled
Step 5:Check subInterface
Interface Management—》Ethernet Virtual Interface—》Layer 3 Attributes
2.2.2 ADSL Link
Step 1:Set ADSL link VPC list that include DSLAM VPC configuration
Interface Management—》DSL Interface—》ADSL Interfaces—》VPI/VPC Configuration—》Configure VPI/VCI
8/35 should be there
Step 2:Set ADSL link port mode is Layer MixInterface Management—》Ethernet Virtual Interface—》Genernal Attributes
Step 3:Creat subInterface on ADSL linkInterface Management—》Ethernet Virtual Interface—》Genernal Attributes—》NEW
Port : 51Name : Sub-1051Port Type : VLAN Sub interfaceBoard : Virtual PortPort : choose the port where the 3-ADS2A-1 is connected VLAN : 1051Specify IP Address: ManuallyIP address: set IP offload addressIP Mask : 255.255.254.0Enable tunnel : Enabled
Step 4:Check subInterface Interface Management—》Ethernet Virtual Interface—》Layer 3 Attributes
2.2 Configuration Management
Step 1:Create Static Route for IP TunnelConfiguration—》Control Plan Configuration—》Static Route Management —》Create
Two routes are needed:
Route List ID: 1 Board: Virtual EthernetPort: 50Next Hop IP Address: IP Primary of MASGDestination Node IP Address : IP Primary of MASGDestination Node Subnet Mask: 255.255.255.255
Route List ID: 2Board: Virtual EthernetPort: 50Next Hop IP Address: IP Primary of MASGDestination Node IP Address: LSR IP of MASGDestination Node Subnet Mask: 255.255.255.255
Step 2:Create LDP PeerConfiguration—》Control Plan Configuration—》MPLS-LDP Configuration —》Create
Opposite IP Address: LSR IP of MASG
Step 3:Create IP TunnelIP/GRE Tunnel Management—》IP Tunnel Management —》New
Tunnel ID : automaticSource Board: Virtual EthernetSource Port: 50Destination IP Address: IP Primary of MASG
Step 4:Enable IP Tunnel for DCN
Communication --》DCN Management —》Tunnel Settings—》IP Tunnel—》Enabled
3 CONFIGURATION MASG
3.1 Basic configuration
This part should be done during the commissioning
3.1.1 MASG NNI Side
Step 1:Set GE port mode is Layer MixInterface Management—》Ethernet Interface—》Port Mode
Step 2:Creat VLAN subinterface with IP MASG primary and offloadInterface Management—》Ethernet Virtual Interface—》General AttributesNew
Step 3:Check VLAN subinterfaceInterface Management—》Ethernet Virtual Interface—》Layer3 Attributes
3.1.2 UNI Side
Step 1:Change MASG GE port Attribute:Encapsulation Type :QinQ;MAX Frame Length:9000Function Tree—》Configuration—》Interface ManagementEthernet Interface—》General Attributes
Step 2:Change MASG GE port Layer 2 Attribute:Tag:81 00
Function Tree—》Configuration—》Interface ManagementEthernet Interface—》Layer 2 Attributes
Step 3:Create QinQ Link that means create S_VLAN we need:Function Tree—》Configuration—》Ethernet Service ManagementQinQ Link—》New
Step 4:Create E_Lan service that means add S_VLAN to service:Function TreeConfigurationEthernet Service ManagementE_Lan serviceNew
3.2 Configuration Management
Step 1:Create Static Route for IP TunnelConfiguration—》Control Plan Configuration—》Static Route Management —》Create
Two routes are needed:
Route List ID: follow the orderBoard: Virtual EthernetPort: 50Next Hop IP Address: IP Primary of CSGDestination Node IP Address : IP Primary of CSGDestination Node Subnet Mask: 255.255.255.255
Route List ID: follow the orderBoard: Virtual EthernetPort: 50Next Hop IP Address: IP Primary of CSGDestination Node IP Address: LSR IP of CSGDestination Node Subnet Mask: 255.255.255.255
Step 2:Create LDP Peer
Configuration—》Control Plane Configuration—》MPLS-LDP Configuration —》Create
Opposite IP Address: LSR IP of CSG
Step 3:Create IP TunnelIP/GRE Tunnel Management—》IP Tunnel Management —》New
Tunnel ID : AutomaticSource Board: Virtual EthernetSource Port: 50Destination IP Address: IP Primary of CSG
Step 4:Enable IP Tunnel for DCN (search by tunnel ID)Communication --》DCN Management —》Tunnel Settings—》IP Tunnel—》Enabled
4 CHECKING
4.1 ADD NE ON U2000
When the CSG and MASG is configured, you can ADD the CSG on NMS
Step 1: FileDiscoveryNE
Step 2: FileTransport NE search Add Select IP Address of GNEEnter IP Mngt of MASGClick OKStart search
Step 3: Click Stop when he found the NE ID of the CSGSelect the GNE ID (ID of MASG) and then create
When the NE is created: double-click on NEuploadThe configuration of CSG will be uploaded on the NMS. Then change the name of the CSG: ConfigurationAttribute
4.2 CHECK THE MANAGEMENT
Step 1 : Click right on the CSG and then login to check the management
Step 2 : Click right on the CSG on then do a ping to test the connectivity between the CSG and MASG
5 Backup/Recover Configuration
5.1 Backup Configuration
Step 1: Administration NE Software Management NE Data Backup/Restoration
Step 2: choose the NE to backup and click “backup”
You have all the backup history on “backup information”
5.2 Recover configuration
Step 1: Administration NE Software Management NE Data Backup/Restoration
Step2: choose NE to recover and click “Recover”
Step 3: Click Start and click Yes in the displayed Operation Confirmation dialog box. The processing information is displayed in the Device View area.NOTEWhen the restoration is complete, the following information will be displayed in the Device View area.
Step 4: Right-click the device icon and click Activation Database to activate the database file whichis just restored.