Procedure for Setting Deletion Flag:
List of material to be flagged for deletion to be generated by Design department
along with correct material code.
Redundant Material codes to be blocked for task list/BOM ( Cross Plant material
Status -02)
Bill of material to be revised by removing redundant material code with correct
codes. (Design to finalise issue of revised Bill of material to Manufacturing/
Projects)
For all redundant material list following need to be checked
Open PR
Open P.O
Inventory
Open Production Orders in which redundant material will be consumed.
Proposed Action for Redundant Material without open transactions:
Redundant material where no open transaction exist (as mentioned above)
should be immediately flagged for deletion.
Proposed Action for Redundant Material with open Purchase Requisition:
Open Purchase Requisition - Unreleased
Open unreleased Purchase requisition will be deleted automatically after
weekly Plan run in Planvisage system subject to Bill of Material is revised
with correct material code.
Open Purchase Requisition -Released
Open released Purchase requisitions need to be deleted manually by each
indenter and new Purchase requisition with correct material code will be
generated in next Plan run in Planvisage System.
Proposed Action for Redundant Material with open Purchase Order:
Redundant material to be deleted from purchase order and new PR with correct
material code to be adopted.
Proposed Action for Redundant Material in Inventory:
Material to Material transfer carried out (Movement Type -309) after taking
approval from MD.
Proposed Action for Redundant Material without open Production orders:
Open Production Order -Released
Redundant material to be immediately issued against open order.
Open Production Order -Unreleased
Function Read PP mater data to be used to copy latest (revised)BOM in
Production order.