Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
Transcript of Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
1/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 4 of 11Revision : 0
1.0. Purpose.
This procedure describes the system of receipt, storage, handling and treatment of welding
consumable in all fabrication area of the workshop and the yard (Open Area).
2.0. Reference.
2.1. ASME Section II Part C.
2.2. EEMUA Publication No. 158 paragraph 5.3.2.
2.3. AWS D1.12004
2.4. ESAB Six Edition - Consumables for Manual and Automatic Welding.
2.5. GS 118-4
3.0. Responsibility.
3.1. Contractor welding engineer is responsible to issue procurement requirement,
warehousing requirement, reviewing the manufacturing test certificate, specifying
additional handling and reconditioning requirements.
3.2. The warehouse supervisor is responsible for withdrawal, handling and storage of
consumables. He is also responsible to monitor who check the temperature of oven.
3.3. The store keeper is responsible to issue welding rod, electrode and flux to the welder
or the welding operator. He is also responsible for scrapping damaged consumables.
3.4. The welding inspector is responsible for the periodic inspection or audit of stored
materials.
4.0. Warehousing.
4.1. All welding consumable will be received at the warehouse.
4.2. Then, the warehouse supervisor will issue the Consumables Receiving Inspection
Report (CRIR) which indicate batch / lot number, brand name, manufacturer, delivery
date, dimension and quantity ( See appendix-1 )
The welding engineer will check the batch certificate against specification and the
CRIR. The welding engineer will sign the certificate and CRIR for approval. A copy of
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
2/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 5 of 11Revision : 0
approved CRIR will be sent to warehouse for releasing the consignment, the original
certificate and CRIR will be kept by the welding engineer.
4.3. All additional and issuance of welding consumable from storage will be carried out on
a rotation basic to ensure to correct stock rotation.
4.4. All welding consumable shall be stored in their original sealed container packing.
Each packet of welding consumable shall be stored on the pallets or shelves. The
welding consumable shall not be stacked excessively high (do not stack more than
eleven layers of electrodes ) so as will damage the packaging of the lower layers.
4.5. Unopened packets of electrode shall be stored under warm and dry conditions.
These conditions shall be maintained, 24 hours a day 7 days a week, to avoid
promoting pick up of the moisture which permeates through the packaging and be
absorbed into the flux coating. Upon receipt the main stock of consumables shall kept
and maintained in a close and dry environment with a minimum of temperature 20 oC
and a relative humidity equal to or less than 60%.
5.0. Baking, Oven and Drying for Low Hydrogen Electrode.
5.1. Low Hydrogen Electrode AWS A5.1 (E 7016-1, E 7018, E 7018-G)
The electrode shall be kept clean, dry, and properly stored. The electrode that is
damaged, damp, greasy or oxidized shall be scrapped.
After unpacking, welding electrode shall be drying to the baking oven at temperature
260oC - 350oC for minimum 2 hours and the holding oven at temperature 120oC -
150oC before distribution to production area. ( Appendix-2)
Method of drying, baking and oven in accordance with electrode manufacturers
recommendation.
5.2. Electrode For Stainless Steel (E 316L-15) and Duplex Stainless Steel (E 2209-17)
The electrodes for Stainless Steel welding shall not be in contact with metal iron, iron
oxide and paints containing zinc
Drying temperature is 260oC350oC for minimum 2 hours before use and the holding
oven at temperature 120oC150oC before distribution to production are ( appendix-3 )
Method of drying, baking and oven in accordance with electrode manufacturers
recommendation.
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
3/8
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
4/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 7 of 11Revision : 0
For Stainless Steel and Duplex Stainless Steel, the remaining of unused electrodes in the
quivers shall be returned for re-drying and immediately marked silver paint to indicate
Cycle 1 finished after 12 hours (see appendix-3)
7.5. For distribution of Cycle2 shall use same method as appendix-2 & 3
8. Solid Wire (ER 2209)
8.1. The wire shall be identified with brand name and lot number.
8.2. The wire shall be kept clean, dry and free from damage, damp, and grease.
8.3. Wire to be cleaned or degreased prior to being used.
8.4. All wire shall be protected from weather and stored in accordance with manufacturers
recommendation.
8.5. Unidentified wire, showing signs of contamination and rust damage shall not be used and
shall be discarded.
8.6. All unused wire shall be identified, covered and returned to the warehouse, unless it to be
used by continuing shift.
8.7. The wire for Stainless Steel, Duplex Stainless Steel and Carbon Steel shall be separated
storage.
9. Flux for Submerged Arc Welding (OK Flux 10.71, OK Flux 10.62)
9.1. The flux shall be kept clean, dry and free from damage, damp, and grease before use
9.2. Unopened flux bag must be stored under warm, clean from foreign materials and dry
conditions and maintained 24 hrs a day 7 days a week. The relative humidity of the
storage is not exceeding 70 %.
9.3. During and after welding, flux may be recovered. The un-melted flux will be sieved to
remove all coarse particle, fuse flux, mill scale, dirt or other foreign matter.
9.4. The flux will be reused as necessary during each welding period or added with new flux
as required.
9.5. The remaining of flux in the opened bags or flux hopper should be stored at a
temperature at 150 25C. ( Appendix-4 )
9.6. If the fluxes have for some reason become wet, it shall be scrapped.
10. Appendixes.
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
5/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 8 of 11Revision : 0
Appendix-1
CONSUMABLE RECEIVING INSPECTION REPORT
Purchase Order : Item No. :
Supplier :
Specification / Class : Class :
Description : Quantity :
Initiated By : Data :
* Condition
Material
MFG Brand Size Manufacture Lot/Batch/Marking Quantity
Reported by
Sent to Welding Date :
* Engineer
Material Agree with ManufacturerYes No
Documentation
Manufacturer Doc. Agree with OrderingYes No
Requirement
Non-Conformances :
Disposition of Non-conformance :
Material release for fabrication :
By : Date :
Copy to Store Room :
* If not acceptable : Quarantine and Contract Welding Engineer
PT. GUNANUSA UTAMA FABRICATORS
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
6/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 9 of 11Revision : 0
Appendix-2
FLOW CHART FOR ELECTRODES DISTRIBUTION
CARBON STEEL LOW HYDROGEN TYPE (E 7016-1, E 7018, E 7018-G)
RECEIVINGCHECK
ELECTRODE STORAGEAREA CHECK
START
CYCLE-1
START
CYCLE-1
HEATEDQUIVER70
oC-100
oC
WELDING OPERATIONCONSUMED
EXPOSEDATMOSPHERE
T > 6 HOURS
SURPLUSRETURN
BACKING OVEN
260OC-350oC HOURS MINIMUM
HOLDING OVEN120
oC-150
oC
HEATEDQUIVER (s)
WELDING OPERATIONCONSUMED
EXPOSEDATMOSPHERE
T > 4 HOURS
MARK BY SILVERPAINT
START
CYCLE-1
START
CYCLE-1
MARK BY SILVERPAINT
START
CYCLE-1
DISCARDED /SCRAPPED
MARK BY REDPAINT
(**)
(***)
(****)
(*) GS 118-4(**) Essab Recommendation(***) Essab Recommendation & AWS D1.1(****) Essab Recommendation
(*)
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
7/8
BP BERAU LTD
Document : 9501-PRC-QC-5932 Page 10 of 11Revision : 0
Appendix-3
FLOW CHART FOR ELECTRODES DISTRIBUTION
STAINLESS STEEL (E 316L-15) AND DUPLEX STAINLESS STEEL (E 2209-17)
RECEIVINGCHECK
ELECTRODE STORAGEAREA CHECK
START
CYCLE-1
START
CYCLE-1
HEATED QUIVER70
oC-100
oC
WELDING OPERATIONCONSUMED
EXPOSEDATMOSPHERE
T > 12 HOURS
SURPLUSRETURN
BACKING OVEN260OC-350
oC HOURS MINIMUM
HOLDING OVEN120
oC-150
oC
HEATEDQUIVER (s)
WELDING OPERATION
CONSUMED
EXPOSEDATMOSPHERE
T > 4 HOURS
MARK BY SILVERPAINT
START
CYCLE-1
START
CYCLE-1
MARK BY SILVERPAINT
START
CYCLE-1
DISCARDED /SCRAPPED
MARK BY REDPAINT
(**)
(***)
(****)
(*) Essab Recommendation(**) Essab Recommendation & AWS D1.1(***) Essab Recommendation
(*)
-
8/10/2019 Procedure for Receipt, Storage and Handling of Welding Consumable (Rev 1) Doc
8/8