Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning:...

36
Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools David Mulcahy North Carolina State University FREEDM Systems Center 1

Transcript of Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning:...

Page 1: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Transmission Planning:

Framework, Sample Analysis, & Tools

David MulcahyNorth Carolina State UniversityFREEDM Systems Center

1

Page 2: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Planning Motivation

Goal: Apply current tools to perform probabilistic transmission on Texas electricity system

- Evaluate modeling tools- Compare sample projects- Determine gaps and needs to be used

Focused on practical considerations of modeling and analysis

2

Page 3: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Outline

• Probabilistic Planning Introduction• Sample Case on ERCOT system

– Scenario Creation– Contingency Simulation– Risk-based indices

• Outstanding Modeling Issues

3

Page 4: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

PROBABILISTIC PLANNING INTRODUCTION

4

Page 5: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Deterministic Planning

5

NERC TPL-001-4 outlines requirements for scenarios, contingencies, and allowable remedial actions

SensitivitiesLoad Cases

Peak

Off-Peak

New Gen

Trans Upgrade

Retire Gen

New Trans

G1 G2 Gn

….

T1 T2 Tn….

Contingencies

Simulate Scenarios

Any violation requires projects to mitigate issues

Scenario 1

Scenario 2 … Scenario

N

Compare Alternatives

Investment A > Investment

B

Compare cost, mitigation extent, and other benefits

5

Page 6: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Planning

6

G1 G2 Gn

0.10

….

T1 T2 Tn

….

Outage Statistics

Compare AlternativesSimulate Scenarios

Determine reliability impact such as loss of load

Scenario 1

Scenario 2 … Scenario

N

2.5Investment

A > Investment B

Include risk-based reliability indices

0.05 0.07

0.05 0.01 0.02

0 30

• Quantify risk of low probability but high impact scenarios• Additional decision criteria to compare transmission investments

Objectives:

Operating Point Distribution

6

Page 7: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Planning Framework

7

7

Page 8: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

ERCOT CASE STUDY

8

Page 9: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

ERCOT Case Study

• Electric Reliability Council of Texas (ERCOT) system model– Texas, USA– Independent System Operator

• Transmission > 100 kV

• Research performed at ERCOT in summer 2016

9

Page 10: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Statistical Input DataTransmission and Generation Outage Statistics

• Include samples of deep contingency events

(N-3, N-4, N-5, …)

• Future work should include probability common mode outages

Forecasted System Operating States

• Include wind outputs, distributed energy resources, electric vehicles, and other uncertain futures

• Not limited to bivariate distributions

10

10

Page 11: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Load Scenarios

• 2002-2013 historical data – Forecast for 2017

• Include load growth uncertainty• 481,800 hourly scenarios

11

7.9%

24.0%

36.0%

24.0%

7.9%

0.0%

10.0%

20.0%

30.0%

40.0%

-4% -2% 0% 2% 4%

Prob

abilit

y

Load Forecast Error

Page 12: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

2017 Wind and Load Forecasts

12

Coincident ERCOT Wind Output and Load based on

2002-2013 weather

Load probability includes

uncertainty of forecasts

12

Page 13: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Stratified Sampling

13

Stratified Sample Space

Ensures analysis of

high impact but low

probability events

13

Page 14: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Strata Definitions

• From historical wind and load data including load growth forecast

14

Load Bounds (MW) Wind Bounds (MW)

Scenario Name Probability Number of

Hours Upper Lower Upper Lower

Load1\W1 2.97E-05 24 81,511 78,668 16,114 4,025

Load2\W1 2.69E-04 168 78,668 75,825 16,114 4,025

Load3\W1 1.25E-03 589 75,825 72,982 16,114 4,025

Load1\W2 3.13E-05 28 81,511 78,668 4,025 0

Load2\W2 3.67E-04 252 78,668 75,825 4,025 0

Load3\W2 1.84E-03 944 75,825 72,982 4,025 0

Total 3.78E-03 2,005 81,511 72,982 16,114 0

Page 15: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Contingency Statistics

• Generator outage data from Generator Availability Database System (GADS)

• Transmission outage data based on NERC Transmission Availability Database System (TADS) based on voltage class

15

Page 16: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Contingency Scenarios

• Enumerated ~8,000 N-2 (generator and transmission) contingencies in coastal region of ERCOT

• Analysis would ideally include higher level contingencies

• Statistics include frequency and mean time to repair to measure severity

16

Page 17: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Simulating Contingency Events

17

/Power Floww/ Remedial Actions

1. Re-dispatch generators

2. Adjust switched components

3. Adjust taps

N. Load Shedding

ContingencyList

/Contingency Impacts

FrequencyDurationSeverity

Power Flow Scenario

…Remedial actions solve

system violations resulting from contingency through

control actions

Load shedding give severity of events instead of binary

failures

17

Page 18: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Planning Tools

18

RBPSB(EPRI Research

Level Tool)

TransCARE(EPRI Research

Level Tool)

PSS/E(Siemens

Commercial Tool)

Self Developed code

(Post Processing)

18

Page 19: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Probabilistic Planning Tools

19

RBPSB(EPRI Research

Level Tool)

TransCARE(EPRI Research

Level Tool)

PSS/E(Siemens

Commercial Tool)

Self Developed code

(Post Processing)

19

Page 20: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Calculation of Probabilistic Indices

Quantifying risk indices

• Includes likelihood and severity of events

• Currently, no established criteria for acceptable risk or indices– System wide (e.g. expected unserved energy (EUE), frequency of loss of load,

etc.)

– Component or contingency level (e.g. probability and frequency of violations)

• Better for ranking alternatives than as absolute metric

20

20

Page 21: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Calculation of Probabilistic Indices

Potential uses of probabilistic criteria and indices

• Evaluate cost/benefit of investment alternatives

• Used to identify weak areas of system

• Benchmark reliability over time and define acceptable risk

21

21

Page 22: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Contingency Probability

• Individual element probabilities used calculate probability of scenario

• Assumes that deeper contingencies has at least the impact of similar higher contingency

• Deeper contingencies are dependent on shallower contingencies – i.e. Probability Gen A and Gen B out together is

subset of both probabilities of Gen A and Gen B

22

Page 23: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Expected Unserved Energy (EUE)

• Expected value of load shedding unmitigated by remedial actions

• PSSE was used to calculated EUE for each operational scenario (strata samples)

• Common list of contingencies for all scenarios

23

Page 24: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Indices Calculations

• EUE – Expected Unserved Energy

𝐸𝐸𝐸𝐸𝐸𝐸 = �𝑠𝑠∈𝑆𝑆

𝑃𝑃 𝑠𝑠 × 𝑎𝑎𝑎𝑎𝑎𝑎𝑖𝑖(𝐸𝐸𝐸𝐸𝐸𝐸𝑖𝑖,𝑠𝑠)

EUEi,s is unserved energy for operational scenario, i, in stratum, s

• IRI – Incremental Reliability Index

𝐼𝐼𝐼𝐼𝐼𝐼 =𝐸𝐸𝐸𝐸𝐸𝐸

𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝐶𝐶𝑃𝑃𝑠𝑠𝑃𝑃

24

Page 25: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Modeling Assumptions

25

• Sampling from 4/6 high load strata

• 5 wind\load samples per strata

• ~8,000 enumerated N-2 contingencies for coast region

• Use ERCOT system in PSSE

• Base case without improvement is not N-1 secure

• Simulating 3 N-1 secure transmission options

• EUE assumes independence of failures and probability of wind\load strata

conditions

• Determining project rank based on comparison of EUE

25

Page 26: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Expected Unserved Energy

26

15.02

8.26

11.00 10.97

0

5

10

15

20

Base Project A Project B Project C

Expe

cted U

nser

ved E

nerg

y (M

Wh/y

r.)

EUE allows ranking by risk of losing load in terms of severity and frequency

Project A1 Project C2 Project B3

26

4 Strata Case

Page 27: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

N/A

0.011

0.007

0.005

0.000

0.005

0.010

0.015

Base Project A Project B Project C

Incre

menta

l Reli

abilit

y Ind

ex

(MW

h/yr./$

Millio

n)

Incremental Reliability Index (IRI)

Capital Cost ($ Millions) - $ 590 $ 554 $ 806

27

IRI shows reliability improvement from

base case per investment cost

Project A1 Project B2 Project C3

4 Strata Case

Page 28: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

174

95 86 109

-

40

80

120

160

200

Base Project A Project B Project C

EUE

(MW

h/yea

r)

Load3\W1 Load3\W2 Load2\W1 Load2\W2 Load1\W1 Load1\W2

EUE by Strata with 6 Strata28

Capital Cost ($ Millions) - $ 590 $ 554 $ 806

Page 29: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Contributions to Project EUE29

-

50

100

150

Avg.

EUE

by S

trata

(MW

h\yea

r)

Base Project A Project B Project C

-

50

100

Load1\W1 Load1\W2 Load2\W1 Load2\W2 Load3\W1 Load3\W2EUE

Contr

ibutio

n (M

Wh\y

ear)

Base Project A Project B Project C

Page 30: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

OUTSTANDING MODELING ISSUES

30

Page 31: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Input Data Needs

• Improved element outage statistics

• Incorporate statistics of common mode outages– Common tower or substations– Cascading failures– Low probability but high impact

31

Page 32: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Sampling Needs

• Strata definitions?– Probability cutoffs– Operational conditions of interest

• Number of samples from strata?– What are the sufficient number of samples to

characterized the region?

• Sampling techniques and contingency depth?

32

Page 33: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Remedial Actions Needs

• Handling failed power flow solutions?– Can you ignore failures?– Are they indications of high impact events or

problem with numerical method?– Automate rerunning the cases?

• What are the appropriate remedial actions?

• Transparency of remedial action results?

33

Page 34: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Risk-Based Indices Needs

• Incorporating probability dependent deeper and shallower contingencies

• Comparison of different indices for decision support

• Determine how to be used for ranking alternatives or absolute metrics

34

Page 35: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

Conclusions

• Barriers to application are primarily practical based on large, real systems

• Need improvements to modeling tools for remedial actions

• Useful as criteria to incorporate risk into current planning practices

35

Page 36: Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning: Framework, Sample Analysis, & Tools ... Load Cases Sensitivities ... • Handling

David [email protected]

North Carolina State University

FREEDM Systems Center

Thank you!

36