Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning:...
Transcript of Probabilistic Transmission Planning: Framework, Sample ... · Probabilistic Transmission Planning:...
Probabilistic Transmission Planning:
Framework, Sample Analysis, & Tools
David MulcahyNorth Carolina State UniversityFREEDM Systems Center
1
Probabilistic Planning Motivation
Goal: Apply current tools to perform probabilistic transmission on Texas electricity system
- Evaluate modeling tools- Compare sample projects- Determine gaps and needs to be used
Focused on practical considerations of modeling and analysis
2
Outline
• Probabilistic Planning Introduction• Sample Case on ERCOT system
– Scenario Creation– Contingency Simulation– Risk-based indices
• Outstanding Modeling Issues
3
PROBABILISTIC PLANNING INTRODUCTION
4
Deterministic Planning
5
NERC TPL-001-4 outlines requirements for scenarios, contingencies, and allowable remedial actions
SensitivitiesLoad Cases
…
Peak
Off-Peak
New Gen
Trans Upgrade
Retire Gen
New Trans
…
G1 G2 Gn
….
T1 T2 Tn….
Contingencies
Simulate Scenarios
Any violation requires projects to mitigate issues
Scenario 1
Scenario 2 … Scenario
N
Compare Alternatives
Investment A > Investment
B
Compare cost, mitigation extent, and other benefits
5
Probabilistic Planning
6
G1 G2 Gn
0.10
….
T1 T2 Tn
….
Outage Statistics
Compare AlternativesSimulate Scenarios
Determine reliability impact such as loss of load
Scenario 1
Scenario 2 … Scenario
N
2.5Investment
A > Investment B
Include risk-based reliability indices
0.05 0.07
0.05 0.01 0.02
0 30
• Quantify risk of low probability but high impact scenarios• Additional decision criteria to compare transmission investments
Objectives:
Operating Point Distribution
6
Probabilistic Planning Framework
7
7
ERCOT CASE STUDY
8
ERCOT Case Study
• Electric Reliability Council of Texas (ERCOT) system model– Texas, USA– Independent System Operator
• Transmission > 100 kV
• Research performed at ERCOT in summer 2016
9
Statistical Input DataTransmission and Generation Outage Statistics
• Include samples of deep contingency events
(N-3, N-4, N-5, …)
• Future work should include probability common mode outages
Forecasted System Operating States
• Include wind outputs, distributed energy resources, electric vehicles, and other uncertain futures
• Not limited to bivariate distributions
10
10
Load Scenarios
• 2002-2013 historical data – Forecast for 2017
• Include load growth uncertainty• 481,800 hourly scenarios
11
7.9%
24.0%
36.0%
24.0%
7.9%
0.0%
10.0%
20.0%
30.0%
40.0%
-4% -2% 0% 2% 4%
Prob
abilit
y
Load Forecast Error
2017 Wind and Load Forecasts
12
Coincident ERCOT Wind Output and Load based on
2002-2013 weather
Load probability includes
uncertainty of forecasts
12
Stratified Sampling
13
Stratified Sample Space
Ensures analysis of
high impact but low
probability events
13
Strata Definitions
• From historical wind and load data including load growth forecast
14
Load Bounds (MW) Wind Bounds (MW)
Scenario Name Probability Number of
Hours Upper Lower Upper Lower
Load1\W1 2.97E-05 24 81,511 78,668 16,114 4,025
Load2\W1 2.69E-04 168 78,668 75,825 16,114 4,025
Load3\W1 1.25E-03 589 75,825 72,982 16,114 4,025
Load1\W2 3.13E-05 28 81,511 78,668 4,025 0
Load2\W2 3.67E-04 252 78,668 75,825 4,025 0
Load3\W2 1.84E-03 944 75,825 72,982 4,025 0
Total 3.78E-03 2,005 81,511 72,982 16,114 0
Contingency Statistics
• Generator outage data from Generator Availability Database System (GADS)
• Transmission outage data based on NERC Transmission Availability Database System (TADS) based on voltage class
15
Contingency Scenarios
• Enumerated ~8,000 N-2 (generator and transmission) contingencies in coastal region of ERCOT
• Analysis would ideally include higher level contingencies
• Statistics include frequency and mean time to repair to measure severity
16
Simulating Contingency Events
17
/Power Floww/ Remedial Actions
1. Re-dispatch generators
2. Adjust switched components
3. Adjust taps
N. Load Shedding
ContingencyList
/Contingency Impacts
FrequencyDurationSeverity
Power Flow Scenario
…Remedial actions solve
system violations resulting from contingency through
control actions
Load shedding give severity of events instead of binary
failures
17
Probabilistic Planning Tools
18
RBPSB(EPRI Research
Level Tool)
TransCARE(EPRI Research
Level Tool)
PSS/E(Siemens
Commercial Tool)
Self Developed code
(Post Processing)
18
Probabilistic Planning Tools
19
RBPSB(EPRI Research
Level Tool)
TransCARE(EPRI Research
Level Tool)
PSS/E(Siemens
Commercial Tool)
Self Developed code
(Post Processing)
19
Calculation of Probabilistic Indices
Quantifying risk indices
• Includes likelihood and severity of events
• Currently, no established criteria for acceptable risk or indices– System wide (e.g. expected unserved energy (EUE), frequency of loss of load,
etc.)
– Component or contingency level (e.g. probability and frequency of violations)
• Better for ranking alternatives than as absolute metric
20
20
Calculation of Probabilistic Indices
Potential uses of probabilistic criteria and indices
• Evaluate cost/benefit of investment alternatives
• Used to identify weak areas of system
• Benchmark reliability over time and define acceptable risk
21
21
Contingency Probability
• Individual element probabilities used calculate probability of scenario
• Assumes that deeper contingencies has at least the impact of similar higher contingency
• Deeper contingencies are dependent on shallower contingencies – i.e. Probability Gen A and Gen B out together is
subset of both probabilities of Gen A and Gen B
22
Expected Unserved Energy (EUE)
• Expected value of load shedding unmitigated by remedial actions
• PSSE was used to calculated EUE for each operational scenario (strata samples)
• Common list of contingencies for all scenarios
23
Indices Calculations
• EUE – Expected Unserved Energy
𝐸𝐸𝐸𝐸𝐸𝐸 = �𝑠𝑠∈𝑆𝑆
𝑃𝑃 𝑠𝑠 × 𝑎𝑎𝑎𝑎𝑎𝑎𝑖𝑖(𝐸𝐸𝐸𝐸𝐸𝐸𝑖𝑖,𝑠𝑠)
EUEi,s is unserved energy for operational scenario, i, in stratum, s
• IRI – Incremental Reliability Index
𝐼𝐼𝐼𝐼𝐼𝐼 =𝐸𝐸𝐸𝐸𝐸𝐸
𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝐶𝐶𝑃𝑃𝑠𝑠𝑃𝑃
24
Modeling Assumptions
25
• Sampling from 4/6 high load strata
• 5 wind\load samples per strata
• ~8,000 enumerated N-2 contingencies for coast region
• Use ERCOT system in PSSE
• Base case without improvement is not N-1 secure
• Simulating 3 N-1 secure transmission options
• EUE assumes independence of failures and probability of wind\load strata
conditions
• Determining project rank based on comparison of EUE
25
Expected Unserved Energy
26
15.02
8.26
11.00 10.97
0
5
10
15
20
Base Project A Project B Project C
Expe
cted U
nser
ved E
nerg
y (M
Wh/y
r.)
EUE allows ranking by risk of losing load in terms of severity and frequency
Project A1 Project C2 Project B3
26
4 Strata Case
N/A
0.011
0.007
0.005
0.000
0.005
0.010
0.015
Base Project A Project B Project C
Incre
menta
l Reli
abilit
y Ind
ex
(MW
h/yr./$
Millio
n)
Incremental Reliability Index (IRI)
Capital Cost ($ Millions) - $ 590 $ 554 $ 806
27
IRI shows reliability improvement from
base case per investment cost
Project A1 Project B2 Project C3
4 Strata Case
174
95 86 109
-
40
80
120
160
200
Base Project A Project B Project C
EUE
(MW
h/yea
r)
Load3\W1 Load3\W2 Load2\W1 Load2\W2 Load1\W1 Load1\W2
EUE by Strata with 6 Strata28
Capital Cost ($ Millions) - $ 590 $ 554 $ 806
Contributions to Project EUE29
-
50
100
150
Avg.
EUE
by S
trata
(MW
h\yea
r)
Base Project A Project B Project C
-
50
100
Load1\W1 Load1\W2 Load2\W1 Load2\W2 Load3\W1 Load3\W2EUE
Contr
ibutio
n (M
Wh\y
ear)
Base Project A Project B Project C
OUTSTANDING MODELING ISSUES
30
Input Data Needs
• Improved element outage statistics
• Incorporate statistics of common mode outages– Common tower or substations– Cascading failures– Low probability but high impact
31
Sampling Needs
• Strata definitions?– Probability cutoffs– Operational conditions of interest
• Number of samples from strata?– What are the sufficient number of samples to
characterized the region?
• Sampling techniques and contingency depth?
32
Remedial Actions Needs
• Handling failed power flow solutions?– Can you ignore failures?– Are they indications of high impact events or
problem with numerical method?– Automate rerunning the cases?
• What are the appropriate remedial actions?
• Transparency of remedial action results?
33
Risk-Based Indices Needs
• Incorporating probability dependent deeper and shallower contingencies
• Comparison of different indices for decision support
• Determine how to be used for ranking alternatives or absolute metrics
34
Conclusions
• Barriers to application are primarily practical based on large, real systems
• Need improvements to modeling tools for remedial actions
• Useful as criteria to incorporate risk into current planning practices
35