PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II...

31
PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin

Transcript of PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II...

Page 1: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

PRM 702Project Risk Management

Lecture #28

PMI’s Project Risk Management Processes

II of II

Ghazala Amin

Page 2: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

2

• Risk management planning is the process of deciding how to approach and plan the risk management activities for a project.

• The process of developing and documenting an organized, comprehensive and interactive strategy and methods – for identifying and analyzing risks, – developing risk response plans, – and monitoring and controlling how risks have changed.

Plan Risk Management

Page 3: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

3

Plan Risk Management

• Inputs– Project scope statement– Cost management plan– Schedule management plan– Communications management plan– Enterprise environmental factors– Organizational process assets

Page 4: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

4

Plan Risk Management• Tools & techniques

– Planning meetings and analysis

Page 5: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

5

Plan Risk Management• Outputs

– Risk management plan

Page 6: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

6

Risk Identification• Involves determining which risks might affect the

project and documenting their characteristics.

• The process of examining – the program areas and each critical technical process – to identify and – document the associated risk.

Page 7: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

7

Risk Identification• Inputs

– Risk management plan– Activity cost estimates– Activity duration estimates– Scope baselines– Stake holder baseline– Cost management plan– Schedule management plan– Quality management plan– Project planning documents– Enterprise environmental factors– Organizational process assets

Page 8: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

8

Risk Identification• Tools & techniques

– Documentation reviews– Information gathering techniques– Checklists analysis– Assumption analysis– Diagramming techniques– Expert judgment– SWOT Analysis

Page 9: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

9

Risk Identification• Outputs

– Risks register

Page 10: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

10

Plan Risk Analysis• The process of examining each identified risk

to– Estimate the probability– And predict the impact on the project.

• It includes:– Qualitative Risk Analysis– Quantitative Risk Analysis

Page 11: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

11

Qualitative Risk Analysis• The process of assessing the impact and

likelihood of identified risks• Risk analysis includes

– Evaluating• Probability that a risk would occur• Impact of the risk if it occurs• Time frame in which it might occur• Frequency of risk occurrence

– Prioritizing• Prioritize to ensure right amount of

management attention

Page 12: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

12

Qualitative Risk Analysis• Inputs

– Risk register– Risk management plan– Project scope statement– Organizational process assets

Page 13: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

13

Qualitative Risk Analysis• Tools & Techniques

– Risk probability and impact– Probability and impact matrix– Risk data quality assessment– Risk categorization– Risk urgency assessment– Expert judgment

Page 14: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

14

Qualitative Risk Analysis• Outputs

– Risk register updates

Page 15: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

15

Risk Rating System• High

– Likely to cause significant disruption to schedule, increase in cost or degradation of performance

• Moderate– Has potential to cause some disruption as above, will probably overcome

difficulties

• Low– Has little potential to cause disruption to schedule, cost or degradation of

performance

Page 16: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

16

Quantitative Risk Analysis• Aims to analyze numerically the probability of

each risk and its consequence on project objectives

Page 17: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

17

Quantitative Risk Analysis

• Inputs– Risk management plan– Risk register– Cost management plan– Schedule management plan– Organizational process assets

Page 18: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

18

Quantitative Risk Analysis• Tools and Techniques

– Data gathering and representation techniques– Quantitative risk analysis and modeling techniques– Expert judgment

Page 19: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

19

Quantitative Risk Analysis• Outputs

– Risk register updates

Page 20: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

20

Risk Response Planning• Process of developing options and determining actions to

enhance opportunities and reduce threats to the project’s objectives

• The process that:– identifies, evaluates, selects and implements – one or more strategies,– in order to set risk at acceptable levels given program

constraints and objectives.

• This includes the specifics on – What should be done– When it should be accomplished– Who is responsible – And associated cost and schedule.

Page 21: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

21

Risk Response Planning• Risk response options include:

– Acceptance– Avoidance– Mitigation– Transfer

Page 22: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

22

Risk Response Planning• Opportunity response options include:

– Acceptance– Enhance– Exploit– Share

Page 23: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

23

Risk Response Planning• Inputs

– Risk management plan– Risk register

Page 24: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

24

Risk Response Planning

• Tools & Techniques– Strategies for negative risks or threats– Strategies for positive risks or opportunities– Contingent response strategies– Expert judgment

Page 25: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

25

Risk Response Planning• Outputs

– Risk register updates– Risk related contract decisions– Project management plan updates– Project document updates

Page 26: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

26

Reserves

• Contingency Reserve– A separately planned quantity used to allow for

future situations which may be planned for only in part

– Also known as “known unknowns”– May involve cost, schedule or both

Page 27: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

27

Reserves

• Management Reserve– A separately planned quantity used to allow for

future situations which are impossible to predict– Also known as “unknown unknowns”– May involve cost, schedule or both

Page 28: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

28

Insurance Strategies

• Direct Property Damage

• Indirect Consequential Loss

• Legal Liability

• Personnel

Page 29: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

29

Risk Monitoring and Control• Inputs

– Risk register– Project management plan– Work performance information– Performance reports

Page 30: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

30

Risk Monitoring and Control• Tools & Techniques

– Risk reassessment– Risk audits– Variance and trend analysis– Reserve analysis– Technical performance measurement– Status meetings

Page 31: PRM 702 Project Risk Management Lecture #28 PMI’s Project Risk Management Processes II of II Ghazala Amin.

31

Risk Monitoring and Control• Outputs

– Risk register updates– Organizational process assets updates– Change requests– Project management plan updates– Project document updates