Long-Baseline Neutrino Facility LBNF Print Package Review & Major Electrical Requirements 131.01.03.03.02.04.02 Primary Water LCW System 131.01.03.03.02.04.03 Electrical Bus Noah Curfman October 31, 2019 Primary Beamline Low Conductivity Water (LCW) Preliminary Design Review

Transcript of Primary Beamline Low Conductivity Water (LCW) Preliminary ...

Page 1: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

Long-Baseline Neutrino FacilityLBNF

Print Package Review & Major Electrical Requirements

131.01.03.03.02.04.02 Primary Water LCW System

131.01.03.03.02.04.03 Electrical Bus

Noah Curfman

October 31, 2019

Primary Beamline

Low Conductivity Water (LCW)

Preliminary Design Review

Page 2: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF10.31.19 Noah Curfman | Primary Beamline LCW Preliminary Design Review2

LBNF-05 Magnet LCW Overall Flow Schematic

Page 3: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF-05 Magnet LCW Overall Flow Schematic

Noah Curfman | Primary Beamline LCW Preliminary Design Review3

Remotely operated 3-way valve Primary LCW pumps

Heat Exchanger Bypass Pump Diagram

10.31.19

Page 4: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF-05 Magnet LCW Overall Flow Schematic

10.31.19 Noah Curfman | Primary Beamline LCW Preliminary Design Review4

Standard DI/Filtration loop

Remotely operated electric valve

Page 5: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF – 5 Service Building LCW Piping Arrangement

Noah Curfman | Primary Beamline LCW Preliminary Design Review5 10.31.19

Page 6: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

• Bus will run directly

above power supplies

• Indicated crossover will

not occur in practice

LBNF – 5 Service Building LCW Piping Arrangement

Noah Curfman | Primary Beamline LCW Preliminary Design Review6 10.31.19

Page 7: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF – 5 Service Building LCW Piping Arrangement

Noah Curfman | Primary Beamline LCW Preliminary Design Review7

• Previously specified aluminum

monocoque shielding for bus

no longer suitableMore complex bus

routing incompatible with monocoque shielding

10.31.19

Page 8: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNFNoah Curfman | Primary Beamline LCW Preliminary Design Review8 10.31.19

Reverse return reduces dP variances between magnets

LBNF Primary Beamline LCW & Bus Flow Schematic

Page 9: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF Primary Beamline LCW & Bus Flow Schematic

10.31.19 Noah Curfman | Primary Beamline LCW Preliminary Design Review9

Standard dipole/quad/dipole cell

2”x2” to 1”x4” bus connector without LCW pass-thru

Recirculation jumper

Page 10: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF Primary Beamline LCW & Bus Flow Schematic

Noah Curfman | Primary Beamline LCW Preliminary Design Review10

Air separators at tunnel crestRemotely operated electric valves

LBNF LCW Fill System Beamline Tunnel Crest

10.31.19

Page 11: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF – 5 Service Building Power Supply P&ID

Noah Curfman | Primary Beamline LCW Preliminary Design Review11 10.31.19

Page 12: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF – 5 Service Building Power Supply P&ID

Noah Curfman | Primary Beamline LCW Preliminary Design Review12

• One flow control valve per

power supply

• Bus jumpers between A/B

power supplies are external

Griswold Flow Control Valves

10.31.19

Page 13: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF – 20 Target Hall Power Supply P&ID

Noah Curfman | Primary Beamline LCW Preliminary Design Review13 10.31.19

Page 14: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

Instrumentation

• Designed based on MI and similar LCW Systems

• Detailed estimates and info found in DUNE DocDB Doc #9955

• Specific component selection delayed to take advantage of

emerging technologies

Noah Curfman | Primary Beamline LCW Preliminary Design Review14 10.31.19

Page 15: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

System Redundancy

• Two 150HP Pumps, one running, one hot spare

• Both pumps VFD controlled

• All major components may be valved out for replacement

• Filters

• DI bottles

• Power supplies

• Instrumentation

• Magnet cells

• Recirculation jumpers on all supply/returns

10.31.19 Noah Curfman | Primary Beamline LCW Preliminary Design Review15

Page 16: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

Electrical Requirements

• 2 primary circulation pumps with VFDs

• 3 electrically actuated valves

- 1 valve in pump room

- 2 valves in beam enclosure

• 1 three-way valve to control HX flow

Noah Curfman | Primary Beamline LCW Preliminary Design Review16

Power RequirementsQuantity Rated Power Voltage Input Phase I @ Full Load I @ Stall

Primary Pumps 2 150 HP 480 V Three 177 A 969.4 A

Recirculation Pump 1 1/2 HP 480 V Three 2.2 A Not Listed

Primary Pump VFDs 2 150 HP 480 V Three 180A N/A

3 Way Valve Actuator 1 1/12 HP 480 V Three 0.32 A 1.16 A

Electrically Operated Valves 3 0.5 HP 120 V Single Not Listed 3A (est.)

Control Panel 1 N/A 110V Single 15A N/A

10.31.19

Page 17: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF Vehicle Access Tunnel LCW Piping & Bus Layout

Noah Curfman | Primary Beamline LCW Preliminary Design Review17 10.31.19

Page 18: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

LBNF Beamline LCW Pipe & Bus Routing

Noah Curfman | Primary Beamline LCW Preliminary Design Review18

• Provides maximum room for cable trays in alcove

• 2” LCW Downstream return continues into alcove for Q211

10.31.19

Page 19: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

Full Layout Envelope Showing Bus LCW Cable Trays and Headers

Noah Curfman | Primary Beamline LCW Preliminary Design Review19

Full envelope layout showing all possible components along

beamline wall

10.31.19

Page 20: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

Full Layout Envelope Showing Bus LCW Cable Trays and Headers

Noah Curfman | Primary Beamline LCW Preliminary Design Review20

Full envelope layout showing all possible components along

beamline wall

10.31.19

Page 21: Primary Beamline Low Conductivity Water (LCW) Preliminary ...

LBNF

System Design Requirements

• Meet previously described operational goals

• Require minimal unscheduled interventions

• Meet established lab standards for flow and capacity

• Operate over a range of elevations determined by CF

• Use pond water for cooling and MI LCW for fill

• Conform to ASME B31.3 and FESHM 5031.1

Noah Curfman | Primary Beamline LCW Preliminary Design Review21

Fluid Low Conductivity Water

Resistivity 9MΩ·cm or better

Nominal Temperature 95°F

Radioactivity < 1900 pCi/ml

MAWP 200 psig