YAKIMA T.O.C. LOAD ASSIST
Presenters:Michael DixonBen Gheliuc
Group Members:Haidar Al GharashDaniel GheliucFue HerZach McCurter
Capstone Advisors:Faryar Etesami
Evan Thomas
Yakima Sponsors:Mark Elliot
Chris Sautter
OVERVIEW
Introduction / Background Internal/External Customers PDS Criteria House of Quality Technical Risk Management Project Timeline Summary
TARGET PERSONA
Average 45 year old 5’ 2” womanPaddles a sea kayakRides a bikeDrives a Subaru Outback
EXTERNAL CUSTOMERS
Chris Sautter Mark Elliot Yakima Legal Department Yakima Financial Department End-User
Target Persona
PDS CRITERIA Ergonomics
Ease of use for target personaMax load assist
CostTarget retail - $500
SafetyPinch points
Clear existing IP/Patents Testing
Yakima internal standards – ISO #
PROJECT TIMELINETask Assign Date Finish Date Tasks due
Discussion of ideas and scope of project Dec-13-11 Jan-11-12
Internal and External Research Jan-9-12 Feb-3-12
Draft Design Jan-23-12 Feb-29-12
PDS Report Jan-16-12 Jan-30-12 Jan-30-12
PDS Report Presentation Jan-30-12 Feb-13-12 Feb-13-12
Evaluation Of Drafted Design Feb-13-12 March-5-12
Design/make Product Feb-20-12 March-15-12
End of the Term Progress Report Feb-27-12 March-12-12
Progress Report Presentation Feb-27-12 Feb-27-12 Feb-27-12
Presentation design to Sponsor March-12-12 March-14-12
Testing and Prototyping March-14-12 April-4-12
Redesigning Concept And Prototype March-21-12 April-18-12
Repeat Testing April-11-12 April-25-12
Manufacture Final Product April-25-12 May-23-12