Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant...
Transcript of Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant...
![Page 1: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/1.jpg)
Presented by:
VINDIKA AMBAGAHAGEMBA In PM (Wales), MPM (USA), B.Eng (Civil), DIPM(UK), Ad Dip QS(UK),MASCE(USA),MAIPM(AUS),PMP(USA),FAAPM(USA), MIIE(SL)
KNOWLEDGE SHARING SESSION (CPD#5) OF SRI-LANKAN QS $ ENGINEERS SOCIETY IN KUWAIT
1
![Page 2: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/2.jpg)
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
2
![Page 3: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/3.jpg)
NO ORAL PROMISES
You must remember always, for every activity in construction specially instructions needs to have written instructions.
3
![Page 4: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/4.jpg)
RECORD KEEPING
Record keeping is generally required for protecting contractual rights and useful for some form of post-contract review. The importance of establishing a documentation system is that it ensures that both the employer and contractor maintain a complete, contemporaneous, chronological and provable record of what happened on site, the problems and their impact upon progress, schedule and cost.
4
![Page 5: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/5.jpg)
▪ Extend time
▪ Instruct for acceleration of works
Note: Neutral events also cause delays;
Force Majeure
5
![Page 6: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/6.jpg)
EOT RELATED CLAUSES IN
CONDITIONS OF CONTRACTS
Majority of construction projects worldwide are administered by the FIDIC forms of contract.
FIDIC recognises delay and related costs and has provisions related thereto. For example;
Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
Clauses 44 & 53 (FIDIC 1987 Edition)
6
![Page 7: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/7.jpg)
▪ Variations.
▪ Exceptionally adverse weather.
▪ Civil commotion or terrorism.
▪ Failure to provide information.
▪ Delay on the part of a nominated sub-contractor.
▪ Statutory undertaker’s work.
▪ A delay in giving the contractor possession of the site.
▪ Force majeure (such as an epidemic or an 'act of God').
▪ Loss from a specified peril such as flood.
▪ The supply of materials and goods by the client.
▪ Strikes.
▪ Changes in statutory requirements.
▪ Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
7
![Page 8: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/8.jpg)
THE FIDIC PROVISIONS
FOR EOTEVENT
The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are;
▪ Late provision of design or drawings
▪ Unforeseeable Physical Conditions encountered on Site
▪ Inclement Weather
▪ Variations instructed by the Engineer (Additional Works etc.)
8
![Page 9: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/9.jpg)
To retain a defined time for completion
To preserve the employer’s right to liquidated damages against acts of
prevention To give the contractor relief from his
strict duty to complete on time in respect of delays caused by
designated neutral event or by employer.
9
![Page 10: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/10.jpg)
▪ CRITICAL PATH- Longest path in the program. Commonly known as path along which float is.
▪ FLOAT- This is the period by which as activity can be delayed without delaying the subsequent activities (Free Float) or without delaying the Project completion date (Total Float).
▪ EXCUSABLE DELAY EVENT- Contractor eligible for EOT if it’s a delay of client. This is having two segments. i.e Compensable and Non-Compensable.
▪ COMPENSABLE EXCUSABLE DELAY- Means EOT will grant with cost.
▪ NON- COMPENSABLE EXCUSABLE DELAY- Means EOT will grant without cost.
10
![Page 11: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/11.jpg)
10 Tips for EOT
Preparation
11
![Page 12: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/12.jpg)
1. Make sure your application complies with the contract.
Any application for extension of time must relate to, and comply with, the provisions of the contract including any bespoke amendments. Each contract will potentially have slightly different requirements in respect of how any application should be made and some forms of contract even prescribe the methodology that must be used.
12
![Page 13: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/13.jpg)
2. Consider who will be reading the request.
Any submission comply with the requirements of the contract but consideration should also be given to who will be reading the request and making the decision.
13
![Page 14: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/14.jpg)
3. Demonstrate cause and effect.
The term ‘cause and effect’ is often used with little thought about what this really means. In reality, for an extension of time request to succeed you must clearly identify a specific discreet cause and the associated specific effect on the programme.
14
![Page 15: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/15.jpg)
4. Evidence your entitlement.
Any submission should be supported by contemporaneous records and facts to fully substantiate the claim(s) being made. This will not only help improve your submission but will also help to expedite any decision from the Contract Administrator or a third party.
15
![Page 16: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/16.jpg)
5. Support your application with common sense.
No matter what form of analysis is used, or what planning software is used, the submission must be underpinned by fundamentally sound, robust and sensible logic.
16
![Page 17: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/17.jpg)
6. Analyse all the relevant records available.
Too often only a sample of the records available are analysed and used for the preparation of any extension of time submission. If you claim a delay has occurred in a certain period of time but upon a subsequent review of the labourtimesheets it is found that operatives were in fact working on the task in alleged delay, you might end up having some explaining to do!
17
![Page 18: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/18.jpg)
7. Start from a strong baseline
If you perform an analysis on a programmeyou should ensure that the programmebeing used is robust and reliable. The programme should be stress tested prior to any analysis being performed to ensure that the logic is sound and complete.
18
![Page 19: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/19.jpg)
8. Consider any culpable delay (Faults entirely in
Contract’s side) periods and weak points carefully
It is rare for any contractor not to suffer some form of culpable delay during the course of the works. Rather than try to ‘brush it under the carpet’ it is often better to deal with it at that time of any submission. What was the effect of it, if any, on the completion date? What was done to overcome it? It is often found that if the proper attention is given to culpable delay periods the effects are often relatively small.
19
![Page 20: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/20.jpg)
9. Perform a suitable delay analysis
With extension of time claims being scrutinized more than ever it is vital to the success of any claim that a recognized form of analysis is used and executed correctly. The form of analysis chosen is often driven by the records available but the pros and cons of each of these should be weighed-up carefully before embarking on any analysis.
20
![Page 21: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/21.jpg)
10. Consider the likely submission response
Thinking about how the recipient or a third party might respond to any submission is a good way to strengthen your case. Do all the facts stack up? Are there facts missing? Are there any weaknesses in your baseline programme? What areas of criticism have there been / are likely?
21
![Page 22: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/22.jpg)
As-planned vs. As-built
01Impacted as- planned method
02As-Planned but for Method
03Collapsed as Built Method
04Time Impact Analysis
05
22
![Page 23: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/23.jpg)
This methodology simply compares the activities of the original CPM baseline
schedule with those of the as-built schedule for detailed assessment of the delays that
occurred. Under this method, all delaying encountered on the project (Excusable–
compensable delays (EC), Excusable–Non compensable delays (EN) and Non
excusable–Non-compensable delays (NN)) are depicted on the as-built schedule.
The difference between the as-planned and as-built completion dates is the amount of
time for which the claimant will request for compensation. The critical path is
determined once in the as-planned and again in the as-built schedule.
This technique and the net impact technique utilizing bar chart are similar in that they
all show the net effect of all claimed delays.
P.T.O
23
![Page 24: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/24.jpg)
In this method, first calculate the Sum of Non-excusable–Non-compensable delays
(NN). Then calculate the Sum of Excusable Compensable delays (EC).
Then Assume concurrent delay due to both parties (lower of NN & EC delays). Then
take the Owner responsible delays/Contractor responsible delays as the rest after
removing the concurrent delay.
Net Total Project delay is the difference between as planned project time and as built
project time.
Contractor responsible delays/Owner responsible delays are calculated by
subtracting the Owner responsible delays/Contractor responsible delays calculated
above.
24
![Page 25: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/25.jpg)
ADVANTAGES
▪ Simple to use
▪ In-expensive
DISADVANTAGES
▪ Suitable for only simple programs
25
![Page 26: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/26.jpg)
▪ The technique can be used for analysis of delay during and after project completion.
▪ It measures the effect for as-planned schedule from each delay event.
▪ Therefore the critical path is important for this method.
▪ Amount of delay = Completion dates after the impacts – Completion date before the impacts
26
![Page 27: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/27.jpg)
▪ As built information is not required.
▪ There is no hassle of arguments over correctness of program or update
▪ The extension of time is determined as per original intent of parties
▪ Any float in the activity comes in to effect as planned only.
27
![Page 28: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/28.jpg)
▪ This method is very theoretical since it does not take in to accounts the actual program is vary a lot compared to as planned program
▪ Any errors in the program creeps in to delay analysis
▪ Extension of time assessed may not be rational in the actual sequence or progress is substantially different to as-planned program
28
![Page 29: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/29.jpg)
▪ This method is performed quickly because it is not required to consider about actual progress of the work.
▪ This method is analysed according to contractor’s point of view and owner’s point of view.
▪ Contractor’s Point of View.
▪ The as-planned schedule is adjusted by adding the contractor-caused delays (non-excusable). Then the results are compared with the actual completion date and the amount of delay which the owner is responsible is calculated.
29
▪ Owner’s Point of View.
▪ The as-planned schedule is adjusted by adding the owner-caused delays (non-excusable). Then the results are compared with the actual completion date then amount of delay which the contractor is responsible is calculated.
![Page 30: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/30.jpg)
ADVANTAGES
▪ It can be performed quickly because there is no need to consider actual progress of the work.
▪ Consider the impact of delays on the critical path.
DISADVANTAGES
▪ Owner’s point of view and contractor’s point of view may yield different results resulting in disputes.
▪ It assumes that the planned construction sequence remains valid during the project duration.
▪ Does not consider the changes in the critical path schedule during the course of the project.
30
![Page 31: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/31.jpg)
In this method as-planned schedule is used as a baseline schedule. It involves removing the delays of each party from the as-built schedule so that the resulting schedule will give the completion date of the project but for the delays of the other party.
The results from contractor’s point of view and owner’s point of view are same in this method.
31
![Page 32: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/32.jpg)
COLLAPSED AS BUILT METHOD
ADVANTAGES AND
DISADVANTAGES
ADVANTAGES
▪ It takes in to account actual program, hence certainty of that delay analysis is based on the actual sequence of the work adopted in the project.
DISADVANTAGES
▪ The removal of the delays from the schedule could result in an unrealistic as-built but-for schedule.
▪ It ignores the circumstance at the time of the delay.
▪ The use of as-built information to prepare the as-built schedule is subjective and highly amenable to manipulation.
▪ Does not consider the changes in the critical path schedule during the course of the project.
32
![Page 33: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/33.jpg)
▪ Time Impact Analysis can be done either following two ways;
1. Snapshot Analysis
2. Window Analysis
33
![Page 34: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/34.jpg)
5.1 SNAPSHOT ANALYSIS
▪ This method recognized in Delay disruption Protocol-The Society of Construction Law in UK (https://www.scl.org.uk/resources/delay-disruption-protocol).
▪ This analysis normally used in contemporaneous delay analysis.
▪ i.e, taking the progress update on instance of occurrence of delay incorporating the effect of excusable delay in the progress update.
34
![Page 35: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/35.jpg)
5.2 WINDOW ANALYSIS
▪ In Window Analysis, the entire project is divided in to multiple time windows.
▪ Generally we can say 1 month time each portion.
▪ Each progress update is updated with or any change of sequence of work etc…
▪ This shall also include the effect of delay due to any excusable events.
▪ Each window is then compared with previous window to analyze the effect of valid delay events.
35
![Page 36: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/36.jpg)
▪ This method is most favored delay analysis recognized internationally.
▪ In each window, there are few activities with negative float, that needs to be analyzed to evolve the delay and therefore process and it’s more clearer than a global approach.
▪ It gives more realistic events, since it takes in to accounts the project status at the time of occurrence.
▪ Calculation of concurrent delay is more practical.
36
![Page 37: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/37.jpg)
▪ Accurate progress information to relate to each progress update needs to be maintained.
▪ This method is more time consuming than the other methods and required planning skills.
37
![Page 38: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/38.jpg)
▪ Prolongation Cost
▪ Disruption Cost
▪ Compensation for Concurrent Delays
▪ Compensation for Lost Float
▪ Acceleration Costs
▪ Claim Preparation Costs
38
![Page 39: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/39.jpg)
This is based on the actual cost incurred by the contractor: work actually done, time actually taken
up, or loss and expense actually suffered. Even if one agrees the rates of compensation which
reflected the anticipated activity on site at the time the contract is signed, these would have to be
recalculated every time a delay occurred, whether or not an extension of time was granted,
because delay inevitably affects the level of activity which the contractor undertakes.
Heads of Prolongation Costs:
▪ Salaries or wages of Indirect staff
▪ Site office costs
▪ Extended safety costs
▪ Bond and Insurance Costs
▪ Scaffolding costs
▪ Handling and material storage works
▪ Head office costs
▪ Subcontractor claims
▪ Delayed release retention/ Financing/delaying payments 39
![Page 40: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/40.jpg)
What is Concurrent delay?
If the Client caused delay and contractor caused delay, affect the same activity or different activities on parallel activity paths which are equally critical, and as such the client caused delay and contractor caused delay would each have delayed the completion of the project, the delays are said to be concurrent.
The term ‘concurrent delay’ is usually understood to describe circumstances when different causes of delay overlap during a period of time.
Only entitlement would be EOT but no prolongation cost. Employer to bear LD & Contractor to bear Prolongation Cost.
The contractor should only be entitled to recover the proven cost of the delay caused to him by the employer. He must be able to separate the costs caused by the employer delay from those caused by his own delay. The effect of this approach is that, concurrent delay will give the contractor an extension of time but no compensation, even though the delay caused by the employer would have given rise to compensation, had it occurred on its own. 40
![Page 41: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/41.jpg)
This happens when the employer delay has deprived the contractor of the benefit of his float. If the contractor had intended to complete any portions of the work before the scheduled completion dates but the employer delay means he only completes by the programmed completion date thus consuming the available float, then he should receive compensation for the extended period that he has been on site, being the length of the consumed float.
This can be applicable when the contractor is entitled to an extension of time may be agreed, and is paid such agreed sum, or a reasonable sum to compensate the contractor for the additional cost of the agreed measures to accelerate the work and the effect of those measures on other aspects of the work together with an allowance for profit. The net effect of the agreed acceleration order will be a variation to the contract.
41
![Page 42: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/42.jpg)
This is also usually the inherent discretion of the arbitrators or the courts to award
such costs. But where it can be shown that the contractor, or employer, has been put
to additional cost as a result of „unreasonable actions or inactions‟ in preparing or
defending claims, then these costs should be recoverable.
Disruption is defined as „disturbance, hindrance or interruption to a contractor‟s
normal working methods‟, resulting in lower working efficiency and productivity,
hindering and interrupting regular progress. When caused by the employer, it
should be compensated either under the contract or as damages for breach of
contract.42
![Page 43: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/43.jpg)
43
![Page 44: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/44.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Path 1 Float = 3.5 Weeks
Path 2 Float = 5.5 Weeks
Path 2
Figure A - Accepted Contract Programme
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
44
![Page 45: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/45.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Path 1 Float = 1.0 Week
Path 2 Float = 5.5 Weeks
<=Date of Excusable Delay
Figure B - Delay Impact 1
Weeks
Path 1
Contract Start
Date
Contract
Completion
Date
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Contract
Completion
Date
Impact on Path
1 = 2.0 Weeks
Path 2
Path 1
45
![Page 46: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/46.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Float = -0.5 Week
Contract
Completion
Date
Impact on Path
1 = 3.5 Weeks
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
<=Date of Excusable Delay
Figure C - Delay Impact 2
Weeks
Path 1
Contract Start
Date
Contract
Completion
46
![Page 47: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/47.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Float = -0.5 Week
Excusable DelayImpact on Path 2 = 6.0 Weeks
<=Date of Excusable Delay
Figure D - Delay Impact 3
Weeks
Path 1
Contract Start
Date
Contract
Completion
Path 2
Path 1
Contract
Completion
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation 47
![Page 48: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/48.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Excusable DelayImpact on Path 1 = 2.0 Weeks
Float = -3.5 Weeks
Figure E - Delay Impact 4
Weeks
Path 1
Contract Start
Date
<=Date of Excusable Delay
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation 48
![Page 49: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/49.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Impact on Path 1 = 2.0 Weeks
Excusable Delay
Float = -3.5 Weeks
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Figure F - Delay Impact 5
Weeks
Path 1
Contract Start
Date
Path 2
49
![Page 50: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/50.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
Path 2 Float = 2.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Float = -1.5 Weeks
Excusable Delay = 3.5 Weeks
Figure G - Delay Impact 6
Weeks
Path 1
Contract Start
Date
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation 50
![Page 51: Presented by: 1 VINDIKA AMBAGAHAGE€¦ · Exceptionally adverse weather. ... EOT will grant without cost. 10. 10 Tips for EOT Preparation 11. 1. Make sure your application complies](https://reader033.fdocuments.in/reader033/viewer/2022060609/60604c7194d0d03316453a3f/html5/thumbnails/51.jpg)
51