Presentation to YGG
-
Upload
hugojameswood -
Category
Documents
-
view
231 -
download
9
description
Transcript of Presentation to YGG
![Page 1: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/1.jpg)
YORKSHIRE GEOTECHNICAL GROUP
Evening Meeting
The Geotechnics of the Selby Bypass
Hugo Wood (High-Point Rendel)
Dr Martin Pedley (Cementation)
Keith Sleightholme (Skanska)
![Page 2: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/2.jpg)
Outline of Presentation
Hugo Wood
• History and background to scheme
• Description of scheme and ground conditions
• Summary of geotechnical challenges and solutions adopted
for design of embankments, cutting and bridge foundations
Martin Pedley
• Discussion of design approach for piles to supported embankments
Keith Sleightholme
• Construction and Environmental Issues
![Page 3: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/3.jpg)
Scheme History
1929 Bypass first proposed for Selby
1938 Scheme entered roads programme of Ministry
of Transport
1950-70’s Numerous routes considered and scheme
entered and removed from various roads
programmes
1980’s Scheme resurrected and NYCC appointed
design agent for the Highways Agency
1991-95 Public Enquiries into line orders and CPO
1997-98 Roads review announced that the A63 Selby
Bypass would be part of targeted programme
of investment
![Page 4: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/4.jpg)
Scheme Benefits
The A63, A19 and A1041 all converge on the centre of
the market town and the existing single carriageway
through Selby carries 20,000 vehicles per day
After Construction of the bypass:
• 40% reduction in traffic flows through town
• Estimated 250 fewer accidents over next 30 years
• Release sites for development currently constrained
by existing congestion
![Page 5: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/5.jpg)
Background to current scheme
• Tenders invited Autumn 2000
• Design and Build contract
• Quality submission covering technical issues, safety,
public liaison and traffic management
• Financial submission opened only after consideration
of quality submission
• Contract awarded Summer 2001
• Contractor: Skanska Construction UK
• Designer: High-Point Rendel
• Construction cost approximately £44M
![Page 6: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/6.jpg)
Details of Scheme
• 10km single carriageway highway, from Thorpe
Willoughby in the west to Barlby in the east
• Road passes over Selby Canal, Selby-Doncaster and
Selby-Hull railway lines and the River Ouse
• Roundabouts at each end of the scheme and at
junctions with the A19 and A1041
• Main construction started in January 2002
• Road due to open Spring 2004.
![Page 7: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/7.jpg)
Plan of Alignment
![Page 8: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/8.jpg)
Vertical Alignment
![Page 9: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/9.jpg)
Ground Conditions
![Page 10: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/10.jpg)
Main Geotechnical Challenges
• Poor ground conditions
• High embankments (>9m)
• Rigid settlement criteria
• Existing services
• Integral bridge design for high skew bridges
• Integral bridge foundations
• Swing bridge foundations
![Page 11: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/11.jpg)
Embankment Stability
• Stability of embankments:
–Side slopes 1V:2H fixed by land take constraints
–High embankments
–Low undrained shear strength of foundations
(Su as low as 20kN/m2)
–Development of excess pore water pressures,
including potential for pore pressure spread in
laminated clays
![Page 12: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/12.jpg)
Geotechnical Solutions (Stability)
• Lightweight PFA fill used for high embankments
(g = 15kN/m3)
• Limits imposed in Specification on rate of
construction of high embankments
• Basal reinforcement
• Monitoring
![Page 13: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/13.jpg)
Basal Reinforcement
![Page 14: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/14.jpg)
Monitoring
![Page 15: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/15.jpg)
Monitoring Results
Excess PWP vs Time Ch 5460
0
10
20
30
40
50
60
70
80
90
100
21-09-02 28-09-02 05-10-02 12-10-02 19-10-02 26-10-02 02-11-02 09-11-02 16-11-02 23-11-02 30-11-02
Date
Excess P
WP
(kP
a)
0
3
6
9
12
15
Em
ban
km
en
t C
on
str
ucti
on
(m
OD
)
PNP2
PNP3
PNP4
Embankment Construction
![Page 16: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/16.jpg)
Monitoring Results
PWP Ratio (excess PWP:s'v) Ch 5460
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
21-09-02 28-09-02 05-10-02 12-10-02 19-10-02 26-10-02 02-11-02 09-11-02 16-11-02 23-11-02 30-11-02
Date
PW
P R
ati
o
0.0
3.0
6.0
9.0
12.0
15.0
Em
ban
km
en
t C
on
str
ucti
on
(m
OD
)
PNP2
PNP3
PNP4
Embankment Construction
![Page 17: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/17.jpg)
Embankment Settlement
• Settlement Criteria (measured at the end of the 5
year maintenance period relative to design levels):
–Maximum allowable settlement 75mm
–Maximum differential settlement gradient 1 in 500
(along the carriageway)
–Maximum differential settlement 25mm (across the
carriageway)
• Settlement:
–Greater than 1m for embankments on alluvium
–Up to 250mm for embankments on laminated clay
–Time for 95% consolidation up to 100 weeks
![Page 18: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/18.jpg)
Temporary Surcharge
![Page 19: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/19.jpg)
A19 Barlby Roundabout
• Low height embankment (1-3m)
• 2m of peat and organic clay in foundation soils
• up to 400mm of settlement anticipated
• Surcharge and drainage solution adopted
• Band drains at 2.7m c/c installed on a triangular grid
![Page 20: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/20.jpg)
Band Drain Locations
![Page 21: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/21.jpg)
Typical Section through Band Drains
![Page 22: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/22.jpg)
Design Options for Ouse Flood PlainCOMPARISON OF PILE SUPPORTED AND UNSUPPORTED EMBANKMENTS ACROSS OUSE FLOOD PLAIN
Issue Pile Supported Embankment Unsupported Embankment
PRO CON PRO CON
Overall settlement (post construction)+
Negligible-
Significant (up to 2m). Impacts on structures adjacent toembankment (including existing drainage network etc.) as well asstructures associated with the embankment (culverts, toe drainageetc.). Settlement (absolute and differential) cannot be accuratelypredicted at this stage and even as a result of monitoring duringconstruction long term behaviour may not be defined sufficientlywell.
Differential settlement (long.)+
Negligible-
Potentially unacceptable within unsupported embankment if groundconditions vary locally (e.g. buried channels), Will require treatmentbetween piled sections adjacent to bridge structures and mainunsupported embankment.
Differential settlement (lat.)+
Negligible-
Difficult to accurately calculate, potentially unacceptable,
Stability+ -
Basal reinforcement required to preventlateral spreading (loading on piles) toBS8006, but conservative design and failureis very unlikely. Reinforcement required tospan between piles.
-Significant reinforcement required to prevent lateral spreading, andfoundation extrusion, particularly given the requirement to steepenthe sideslopes to allow placement of surcharge. Difficult toefficiently design without the results of a trial embankment. Stagedconstruction may still be required to prevent excessive movementof foundation soils.
Instrumentation+
Minimal required-
Significant instrumentation required, to be regularly monitored andresults interpreted to determine progress of construction/contingentmeasures etc.
Programme+
Little uncertainty, shorter programme-
Longer programme, unknown at start of construction, greateruncertainty in meeting overall deadline
Cost-
Greater cost (but little uncertainty)+
Probably lesser estimated cost (but greater uncertainty andpotentially greater long term costs)
![Page 23: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/23.jpg)
Pile Supported Embankments
![Page 24: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/24.jpg)
Typical Plan of Pile Locations
![Page 25: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/25.jpg)
Reinforcement Layout
![Page 26: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/26.jpg)
Protection of Existing Services
![Page 27: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/27.jpg)
Earthworks
• Use of waste products from other industries (PFA and
minestone)
• Testing of materials prior to construction to confirm
appropriate design parameters
• Detailed testing regime during construction to confirm
properties of materials
![Page 28: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/28.jpg)
Cutting
• Overall 700m long, up to 13m maximum depth
• Sherwood Sandstone
• Variable weathering profile
• Landscaping of cutting important consideration
• Horseshoe Bridge taking bridleway across cutting
![Page 29: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/29.jpg)
Plan of Cutting
![Page 30: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/30.jpg)
Typical Section through Cutting
![Page 31: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/31.jpg)
General Arrangement - Horseshoe Bridge
![Page 32: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/32.jpg)
General Arrangement - Oakney Bridge
![Page 33: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/33.jpg)
Integral Bridges
• All Highway Bridges <60m and <30° skew to be
integral with their abutments
• Thermal cycling of bridge decks leads to the
development of high earth pressures on abutment
• BA 42/96 provides derivation of design earth
pressure coefficient k*
![Page 34: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/34.jpg)
Earth Pressures on Integral Abutments
Fig 3.1 from BA 42/96
![Page 35: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/35.jpg)
Design Approach for Integral Bridges
• Full 3 dimensional frame analysis model of bridge
and foundations
• Piles modelled with springs defined as secant p-y
curves for lateral load resistance of soil
• p-y mutipliers applied to spring stiffnesses to model
interaction of pile rows
![Page 36: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/36.jpg)
Frame Model for Integral Bridges
![Page 37: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/37.jpg)
Foundations to Integral Bridges
![Page 38: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/38.jpg)
General Arrangement - William Jessop Bridge
![Page 39: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/39.jpg)
Supported Bankseat Abutment
![Page 40: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/40.jpg)
Reinforced Soil Wingwalls
• Designed to BS 8006 (as implemented by BD 70/97
for Highway Structures) on coherent gravity method
• 1.8mx2m pre-cast concrete panels with galvanised
steel reinforcing strips
• Standardisation of panel types to minimise variety of
panels to be constructed
![Page 41: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/41.jpg)
Reinforced Soil Wingwalls
![Page 42: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/42.jpg)
Panel Layout
![Page 43: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/43.jpg)
River Ouse Swing Bridge
![Page 44: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/44.jpg)
Ouse Bridge Foundations
![Page 45: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/45.jpg)
Summary of Geotechnical Challenges
• Poor ground conditions on eastern half of alignment
• High embankment construction leading to concerns
over settlement and stability of embankments
• Integral bridge form adopted for high skew bridges
• Differential settlement between bridge structures and
embankments
• Complex loading on swing bridge foundations
![Page 46: Presentation to YGG](https://reader031.fdocuments.in/reader031/viewer/2022020319/563db7cc550346aa9a8e07cc/html5/thumbnails/46.jpg)
Summary of Geotechnical Solutions
• Different forms of embankment construction including
surcharging, pile supported embankments, basal
reinforcement and drainage
• Monitoring of embankment stability and settlement
• Supported foundations to integral bridges
• Arrangement of vertical and raked tubular steel piles
to swing bridge foundation.