Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager...

27
Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising SAG mill throughput: A case study in tuning

Transcript of Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager...

Page 1: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Presentation to The Mill Optimisation Summit 2011

Presented by:Paul WilsonTechnology Manager Calibre Automation, Communications & Technology Group

Optimising SAG mill throughput:A case study in tuning

Page 2: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Two SAG mills

1

Page 3: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

• Porgera Mine, PNG

• 4.5 Megawatt, variable speed drive

• About 500 tonnes per hour per mill

• Highly variable lithology with grinding factors from 6 to 18 kilowatt hours per tonne

The mills

2

Page 4: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The mills

3

Page 5: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The mills were often unstable, seen as oscillations in the feedrate trend graphs

Unstable behaviour

4

Page 6: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Loss of production

7

As much as 15% on bad days

Up to 380 ounces of gold per day on bad days

At $425 US per ounce = $160,000 per day

You could hire a very good plant operator for that kind of money

Page 7: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Natural instability

8

Poor tuning causes natural instability

Page 8: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Operator-caused instability

8

Poor operator skills also forces instability

Page 9: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The control system

9

Highest levelMinnovex expert system control

Optional top level controlConstraint control

Mid-levelClosed loop control

Bottom levelDelta-V distributed control system

Page 10: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The Minnovex expert system

9

A fuzzy rules based artificial intelligence system

Running on a G2 expert system shell

Running on a Windows NT PC platform

Takes data from, & feeds setpoints to, the loop controllers on the Delta-V

Page 11: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Performance comparison

9

Expert system control is far better than poor operator control

Page 12: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Why mills go unstable (#1)

9

Mills stall (bog or centrifuge). The behaviour at maximum throughput is highly non-linear

Page 13: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Why mills go unstable (#2)

9

Dynamic behaviour of a mill is type 1

Control engineers recognise that type 1 systems are more likely to be unstable than type 0 systems

Caused by the inherent integration in the mill transfer function

Page 14: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Mill load (level) is the integral of the nett feedrate

level = ∫ (Qin – Qout).dt

This induces a -90o phase shift in the transfer function which leads to reduced stability

Why mills go unstable (#2)

10

Page 15: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Why mills go unstable (#2)

9

The integration causes a phase shift

Page 16: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Simulated integral response

11

Page 17: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

1. When a mill stalls it stops working. 2. The mill fills with unground material.3. It takes time to grind out the rock and get the

outflow going again

So: the control system / plant operator must be:

PATIENT

Why mills go unstable (#3)

10

Page 18: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The result of operator impatience

13

Page 19: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Mill under tuned expert system control

13

Page 20: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Section A to B is the maximum speed of recovery to prevent stalling the mill again

Expert system recovers from a motor overheat event

13

Page 21: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

The result

30

• In 2004 / 2005 mill production rose from850,000 ounces to 1,000,000 ounces

• At $425 US per ounce that was $63.75 million US increase per year

Not possible without increasing SAG mill throughput

Page 22: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Extra energy used

7

The difference in energy usage between the unstable zone and the stable zone is:

the unstable zone averages

25% more motor energy per tonne of product

than the stable zone and produces

15% less product

Which adds 10% to the energy costs for the remainder of the processing plant

Page 23: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

How was it done?

30

• Develop a mathematical model• Use trend plots and tests to characterise

the mill (find the characteristics of mill behaviour)

• Estimate fastest possible recovery times on the worst-case ores

• Retune the expert system rules for robust, always-stable behaviour

Page 24: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

How was it done?

30

Block diagram model of mill behaviour

Page 25: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

How was it done?

30

Transfer function of mill load to ore feedrate

Page 26: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Additional development

30

The decision to secondary crush the harder ores.

A secondary crusher was installed. With a bit of clever mathematics we were able to estimate SAG mill grinding factor at the primary crusher. We used this to feed some of the hard ore (GF > 10 kWhr per tonne) through the secondary crusher thus increasing SAG mill throughput on the harder ore.

Page 27: Presentation to The Mill Optimisation Summit 2011 Presented by: Paul Wilson Technology Manager Calibre Automation, Communications & Technology Group Optimising.

Questions

31

Your questions are welcome

Plant characterisation & transfer function development is a complex process. I am happy to discuss some of the methods afterwards with anyone interested.