Presentation to American Council of Engineering Companies

34
Massachusetts Water Resources Authority Presentation to American Council of Engineering Companies April 11, 2013 Michael J. Hornbrook Chief Operating Officer

description

Presentation to American Council of Engineering Companies. Michael J. Hornbrook Chief Operating Officer. April 11, 2013. RECENTLY COMPLETED AND ONGOING PROJECTS. Progress On Water System Redundancy. Section 89 Globe Valve Replacement. Stoneham/Reading Interconnection. - PowerPoint PPT Presentation

Transcript of Presentation to American Council of Engineering Companies

Page 1: Presentation to American Council of  Engineering Companies

Massachusetts Water Resources Authority

Presentation to

American Council of Engineering Companies

April 11, 2013

Michael J. HornbrookChief Operating Officer

Page 2: Presentation to American Council of  Engineering Companies

RECENTLY COMPLETED ANDONGOING PROJECTS

Page 3: Presentation to American Council of  Engineering Companies

Progress On Water System Redundancy

3

Hultman Aqueduct Rehab/MetroWest Interconnections

Southern Spine

Section 18, 50 & 51 Rehab

Spot Pond StorageTank & Pump Station (under construction)

Stoneham/Reading Interconnection

Section 89 Globe Valve Replacement

Hultman Aqueduct Rehab/MetroWest Interconnections

Southern Spine

Section 18, 50 & 51 Rehab

Spot Pond StorageTank & Pump Station (under construction)

Stoneham/Reading Interconnection

Section 89 Globe Valve Replacement

Page 4: Presentation to American Council of  Engineering Companies

Lynnfield/Saugus Pipelines: Fay, Spofford & Thorndike, LLC

• 12,000 feet of new water mains under Route 1; including new 12-inch main for Saugus

• Completed December 2012

4

Page 5: Presentation to American Council of  Engineering Companies

Northern Intermediate High – Stoneham Interconnections: Dewberry Engineers, Inc.

• 2,200-foot-long, 36-inch-diameter emergency pipeline connection between Stoneham and Reading

• Completed January 2012

5

Page 6: Presentation to American Council of  Engineering Companies

Lower Hultman Aqueduct Rehab:Jacobs Engineering Group, Inc.

• 13.2 miles of joint and leak repair• Interconnections to MetroWest

Tunnel• 94% complete

6

Page 7: Presentation to American Council of  Engineering Companies

Upper Hultman Aqueduct Rehab: Jacobs Engineering Group, Inc.

• Inspection and rehab of 9,600 feet of Upper Hultman

• 75% complete

7

Page 8: Presentation to American Council of  Engineering Companies

Spot Pond Storage Tank and Emergency Pump Station: Hazen & Sawyer PC, Design – CDM Smith, Owner’s Rep

• 20-million gallon buried, concrete storage tank and emergency pump station

• 21% complete

Page 9: Presentation to American Council of  Engineering Companies

Gillis Pump Station Improvements (VFDs)Dewberry Engineering, Inc.

Construction Notice to Proceed: June 2013Estimated Cost: $3.9 million

Page 10: Presentation to American Council of  Engineering Companies

Wachusett Aqueduct Pump Station:Fay, Spofford & Thorndike, LLC

10

Construction Notice to Proceed: April 2014Estimated Cost: $45.6 million

Page 11: Presentation to American Council of  Engineering Companies

Northern Intermediate High Redundancy:Fay, Spofford & Thorndike, LLC

11

Section 89 & 29 - Phase 1

Construction Notice to Proceed: January 2015Estimated Cost : $21.3 million

Section 89 & 29 - Phase 2

Construction Notice to Proceed: May 2015Estimated Cost : $21.7 million

Page 12: Presentation to American Council of  Engineering Companies

Southern Extra High Redundancy - Study:Kleinfelder Northeast, Inc.

12

Design Award: January 2014Construction Notice to Proceed: July 2016Estimated Cost: $28.3 million

Page 13: Presentation to American Council of  Engineering Companies

Carroll Treatment Plant UV: AECOM Technical Services, Inc.

• Addition of ultraviolet disinfection facilities to meet new SDWA regulations

• 87% complete

13

Page 14: Presentation to American Council of  Engineering Companies

Quabbin Water Treatment Plant UV:AECOM Technical Services, Inc.

• Addition of ultraviolet disinfection facilities to meet new SDWA regulations

• 3% complete

14

Page 15: Presentation to American Council of  Engineering Companies

Brookline Sewer Separation – Microtunneling: Beta Group, Inc.

• Installation of 4,500 feet of new storm drain by microtunneling

• Plus 5,080 feet of storm drain and sewer by open trench

• 97% complete

15

Page 16: Presentation to American Council of  Engineering Companies

Brookline Outfall Cleaning: Dewberry Engineers, Inc.

• To ensure that the outfall has adequate hydraulic capacity to convey Brookline’s separated stormwater to the Charles River Basin

• Completed August 2012

16

Page 17: Presentation to American Council of  Engineering Companies

Cambridge CSO Stormwater Wetland:Kleinfelder Northeast, Inc.

• Construction of 4 x 8 box culvert storm drain and and wetland basin

• 90% complete

17

Page 18: Presentation to American Council of  Engineering Companies

Alewife Brook CSO Control Plan:Kleinfelder Northeast, Inc.

Sewer Separation - Huron Ave

Construction Notice to Proceed: July 2013Estimated Cost: $17.5 million

Sewer Separation – Concord Ave

Construction Notice to Proceed: January 2014Estimated Cost: $7.3 million

Page 19: Presentation to American Council of  Engineering Companies

Deer Island – North Main Pump Station VFDs:Malcolm Pirnie, Inc., Design – Fay, Spofford & Thorndike, LLC, EDCS

• Replacing obsolete variable frequency drives

• 18% complete

19

Page 20: Presentation to American Council of  Engineering Companies

Deer Island: Scum Skimmer ReplacementFay, Spofford & Thorndike, LLC

20

Construction Notice to Proceed: June 2013Estimated Cost: $20.0 million

Page 21: Presentation to American Council of  Engineering Companies

Deer Island Butterfly Valve Replacement – North Main Pump Station And Winthrop Terminal Facility: AECOM

Construction Notice to Proceed: June 2013Estimated Cost: $10 million

Page 22: Presentation to American Council of  Engineering Companies

Chelsea Headworks Rehabilitation:Malcolm Pirnie/ARCADIUS US, Inc.

22

Construction Notice to Proceed: February 2015Estimated Cost: $52.1 million

Page 23: Presentation to American Council of  Engineering Companies

Clinton Wastewater Treatment Plant Aeration:Fay, Spofford & Thorndike, LLC

• Installing fine bubble diffusers in aeration tanks obtain a better oxygen transfer rate and reduce electricity consumption

• 99% complete

23

Page 24: Presentation to American Council of  Engineering Companies

Clinton Wastewater Treatment Plant Digester Rehab:Fay, Spofford & Thorndike, LLC

• Clean and rehab digesters and rehab the tanks (replace covers, piping, valves, gas lancers and mixers) to operate under new NPDES permit

• Construction Notice to Proceed: June 2013• Estimated Construction Cost: $3.2 million

24

Page 25: Presentation to American Council of  Engineering Companies

Clinton Treatment Plant Phosphorous Removal

25

Phosphorous Reduction

Facility

Chlorine Contact Tank Design Award: June 2013

Construction Notice to Proceed: August 2016Estimated Cost: $5.8 million

Page 26: Presentation to American Council of  Engineering Companies

MWRA’s Capital Improvement Program

• Over 80% of MWRA’s capital spending has been for projects mandated by federal or state regulators

$0

$100

$200

$300

$400

$500

$600

$700

FY86 FY88 FY90 FY92 FY94 FY96 FY98 FY00 FY02 FY04 FY06 FY08 FY10 FY12

Mill

ion

s

Mandated v. Non-Mandated Project Spending

Mandated(Court Orders,

Consent Orders)

Non-Mandated(Pipeline Rehabilitation and Infrastructure Replacement)

Page 27: Presentation to American Council of  Engineering Companies

Future Capital Spending

27

$1,134.5 $1,143.9

$793.5

$0.0

$200.0

$400.0

$600.0

$800.0

$1,000.0

$1,200.0

$1,400.0

FY04-08 Cap FY09-13 Cap Proposed FY14-18 Cap

5-Year Spending Caps

$320 million less than projected in the Final FY2013 CIP

• FY2014 will mark the beginning of a new five-year cap for MWRA’s CIP - $350 million lower than the current cap

• The lowest projected spending since the Boston Harbor Clean-up began in 1990

Page 28: Presentation to American Council of  Engineering Companies

• As of December 31th, 2012, the total Indebtedness is $5.8 billion

• For the first time, MWRA will be paying off more principal on debt than annual capital spending

Paying Down Debt

28

$4,000,000,000

$4,500,000,000

$5,000,000,000

$5,500,000,000

$6,000,000,000

$6,500,000,000

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018

MWRA's Outstanding Debt

TotalOutstandingDebt will decrease

by $351 million

Page 29: Presentation to American Council of  Engineering Companies

UPCOMING CONTRACT AWARDS

Page 30: Presentation to American Council of  Engineering Companies

Upcoming Design Contracts

30

Project Phase Notice to ProceedEstimatedContract

Amount ($000s)

FY13 Anticipated Awards

Weston Aqueduct Supply Mains Weston Aqueduct Supply Mains 3 – MEPA/Design May-13 $32,979

Clinton Wastewater Treat Plant Phosphorous Removal Design/ESDC Jun-13 $900

Carroll Water Treatment Plant Technical Assistance 7 Jun-13 $750

Carroll Water Treatment Plant Technical Assistance 8 Jun-13 $750

Page 31: Presentation to American Council of  Engineering Companies

Upcoming Design Contracts

31

Project Phase Notice to ProceedEstimatedContract

Amount ($000s)

FY14 Anticipated Awards

Capital Maintenance Planning & Development As-Needed Design Contract 11 Aug-13 $1,600

Capital Maintenance Planning & Development As-Needed Design Contract 12 Aug-13 $1,600

Capital Maintenance Planning & Development As-Needed Design Contract 13 Aug-13 $1,600

DI Treatment Plant Asset Protection

Heating Ventilation Air Conditioning Equipment Replacement - Design/ESDC Aug-13 $3,500

DI Treatment Plant Asset Protection Fire Alarm System Replacement-Design Sep-13 $2,100

Wastewater Meter System-Equipment Repl. Planning / Study Sep-13 $100

DI Treatment Plant Asset Protection

Thermal Power Plant Fuel System Modifications Resident Engineer Inspection Sep-13 $800

Spot Pond Supply Mains Rehabilitation

Section 4 Webster Ave Bridge Pipe Rehabitation Design Sep-13 $500

DI Treatment Plant Asset Protection Digester & Storage Tank Rehab Design/ESDC Oct-13 $3,000

DI Treatment Plant Asset Protection Clarifier Ph 2 Design Nov-13 $3,000

Page 32: Presentation to American Council of  Engineering Companies

IN OTHER NEWS

Page 33: Presentation to American Council of  Engineering Companies

E-Procurement: Phased Approach

• MWRA has been working to get procurements on-line• Contracts Portal expected to go live this summer

33

Page 34: Presentation to American Council of  Engineering Companies

E-Procurement: Supplier Portal Went Live Last Week

34