Presentation to American Council of Engineering Companies
description
Transcript of Presentation to American Council of Engineering Companies
Massachusetts Water Resources Authority
Presentation to
American Council of Engineering Companies
April 11, 2013
Michael J. HornbrookChief Operating Officer
RECENTLY COMPLETED ANDONGOING PROJECTS
Progress On Water System Redundancy
3
Hultman Aqueduct Rehab/MetroWest Interconnections
Southern Spine
Section 18, 50 & 51 Rehab
Spot Pond StorageTank & Pump Station (under construction)
Stoneham/Reading Interconnection
Section 89 Globe Valve Replacement
Hultman Aqueduct Rehab/MetroWest Interconnections
Southern Spine
Section 18, 50 & 51 Rehab
Spot Pond StorageTank & Pump Station (under construction)
Stoneham/Reading Interconnection
Section 89 Globe Valve Replacement
Lynnfield/Saugus Pipelines: Fay, Spofford & Thorndike, LLC
• 12,000 feet of new water mains under Route 1; including new 12-inch main for Saugus
• Completed December 2012
4
Northern Intermediate High – Stoneham Interconnections: Dewberry Engineers, Inc.
• 2,200-foot-long, 36-inch-diameter emergency pipeline connection between Stoneham and Reading
• Completed January 2012
5
Lower Hultman Aqueduct Rehab:Jacobs Engineering Group, Inc.
• 13.2 miles of joint and leak repair• Interconnections to MetroWest
Tunnel• 94% complete
6
Upper Hultman Aqueduct Rehab: Jacobs Engineering Group, Inc.
• Inspection and rehab of 9,600 feet of Upper Hultman
• 75% complete
7
Spot Pond Storage Tank and Emergency Pump Station: Hazen & Sawyer PC, Design – CDM Smith, Owner’s Rep
• 20-million gallon buried, concrete storage tank and emergency pump station
• 21% complete
Gillis Pump Station Improvements (VFDs)Dewberry Engineering, Inc.
Construction Notice to Proceed: June 2013Estimated Cost: $3.9 million
Wachusett Aqueduct Pump Station:Fay, Spofford & Thorndike, LLC
10
Construction Notice to Proceed: April 2014Estimated Cost: $45.6 million
Northern Intermediate High Redundancy:Fay, Spofford & Thorndike, LLC
11
Section 89 & 29 - Phase 1
Construction Notice to Proceed: January 2015Estimated Cost : $21.3 million
Section 89 & 29 - Phase 2
Construction Notice to Proceed: May 2015Estimated Cost : $21.7 million
Southern Extra High Redundancy - Study:Kleinfelder Northeast, Inc.
12
Design Award: January 2014Construction Notice to Proceed: July 2016Estimated Cost: $28.3 million
Carroll Treatment Plant UV: AECOM Technical Services, Inc.
• Addition of ultraviolet disinfection facilities to meet new SDWA regulations
• 87% complete
13
Quabbin Water Treatment Plant UV:AECOM Technical Services, Inc.
• Addition of ultraviolet disinfection facilities to meet new SDWA regulations
• 3% complete
14
Brookline Sewer Separation – Microtunneling: Beta Group, Inc.
• Installation of 4,500 feet of new storm drain by microtunneling
• Plus 5,080 feet of storm drain and sewer by open trench
• 97% complete
15
Brookline Outfall Cleaning: Dewberry Engineers, Inc.
• To ensure that the outfall has adequate hydraulic capacity to convey Brookline’s separated stormwater to the Charles River Basin
• Completed August 2012
16
Cambridge CSO Stormwater Wetland:Kleinfelder Northeast, Inc.
• Construction of 4 x 8 box culvert storm drain and and wetland basin
• 90% complete
17
Alewife Brook CSO Control Plan:Kleinfelder Northeast, Inc.
Sewer Separation - Huron Ave
Construction Notice to Proceed: July 2013Estimated Cost: $17.5 million
Sewer Separation – Concord Ave
Construction Notice to Proceed: January 2014Estimated Cost: $7.3 million
Deer Island – North Main Pump Station VFDs:Malcolm Pirnie, Inc., Design – Fay, Spofford & Thorndike, LLC, EDCS
• Replacing obsolete variable frequency drives
• 18% complete
19
Deer Island: Scum Skimmer ReplacementFay, Spofford & Thorndike, LLC
20
Construction Notice to Proceed: June 2013Estimated Cost: $20.0 million
Deer Island Butterfly Valve Replacement – North Main Pump Station And Winthrop Terminal Facility: AECOM
Construction Notice to Proceed: June 2013Estimated Cost: $10 million
Chelsea Headworks Rehabilitation:Malcolm Pirnie/ARCADIUS US, Inc.
22
Construction Notice to Proceed: February 2015Estimated Cost: $52.1 million
Clinton Wastewater Treatment Plant Aeration:Fay, Spofford & Thorndike, LLC
• Installing fine bubble diffusers in aeration tanks obtain a better oxygen transfer rate and reduce electricity consumption
• 99% complete
23
Clinton Wastewater Treatment Plant Digester Rehab:Fay, Spofford & Thorndike, LLC
• Clean and rehab digesters and rehab the tanks (replace covers, piping, valves, gas lancers and mixers) to operate under new NPDES permit
• Construction Notice to Proceed: June 2013• Estimated Construction Cost: $3.2 million
24
Clinton Treatment Plant Phosphorous Removal
25
Phosphorous Reduction
Facility
Chlorine Contact Tank Design Award: June 2013
Construction Notice to Proceed: August 2016Estimated Cost: $5.8 million
MWRA’s Capital Improvement Program
• Over 80% of MWRA’s capital spending has been for projects mandated by federal or state regulators
$0
$100
$200
$300
$400
$500
$600
$700
FY86 FY88 FY90 FY92 FY94 FY96 FY98 FY00 FY02 FY04 FY06 FY08 FY10 FY12
Mill
ion
s
Mandated v. Non-Mandated Project Spending
Mandated(Court Orders,
Consent Orders)
Non-Mandated(Pipeline Rehabilitation and Infrastructure Replacement)
Future Capital Spending
27
$1,134.5 $1,143.9
$793.5
$0.0
$200.0
$400.0
$600.0
$800.0
$1,000.0
$1,200.0
$1,400.0
FY04-08 Cap FY09-13 Cap Proposed FY14-18 Cap
5-Year Spending Caps
$320 million less than projected in the Final FY2013 CIP
• FY2014 will mark the beginning of a new five-year cap for MWRA’s CIP - $350 million lower than the current cap
• The lowest projected spending since the Boston Harbor Clean-up began in 1990
• As of December 31th, 2012, the total Indebtedness is $5.8 billion
• For the first time, MWRA will be paying off more principal on debt than annual capital spending
Paying Down Debt
28
$4,000,000,000
$4,500,000,000
$5,000,000,000
$5,500,000,000
$6,000,000,000
$6,500,000,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
MWRA's Outstanding Debt
TotalOutstandingDebt will decrease
by $351 million
UPCOMING CONTRACT AWARDS
Upcoming Design Contracts
30
Project Phase Notice to ProceedEstimatedContract
Amount ($000s)
FY13 Anticipated Awards
Weston Aqueduct Supply Mains Weston Aqueduct Supply Mains 3 – MEPA/Design May-13 $32,979
Clinton Wastewater Treat Plant Phosphorous Removal Design/ESDC Jun-13 $900
Carroll Water Treatment Plant Technical Assistance 7 Jun-13 $750
Carroll Water Treatment Plant Technical Assistance 8 Jun-13 $750
Upcoming Design Contracts
31
Project Phase Notice to ProceedEstimatedContract
Amount ($000s)
FY14 Anticipated Awards
Capital Maintenance Planning & Development As-Needed Design Contract 11 Aug-13 $1,600
Capital Maintenance Planning & Development As-Needed Design Contract 12 Aug-13 $1,600
Capital Maintenance Planning & Development As-Needed Design Contract 13 Aug-13 $1,600
DI Treatment Plant Asset Protection
Heating Ventilation Air Conditioning Equipment Replacement - Design/ESDC Aug-13 $3,500
DI Treatment Plant Asset Protection Fire Alarm System Replacement-Design Sep-13 $2,100
Wastewater Meter System-Equipment Repl. Planning / Study Sep-13 $100
DI Treatment Plant Asset Protection
Thermal Power Plant Fuel System Modifications Resident Engineer Inspection Sep-13 $800
Spot Pond Supply Mains Rehabilitation
Section 4 Webster Ave Bridge Pipe Rehabitation Design Sep-13 $500
DI Treatment Plant Asset Protection Digester & Storage Tank Rehab Design/ESDC Oct-13 $3,000
DI Treatment Plant Asset Protection Clarifier Ph 2 Design Nov-13 $3,000
IN OTHER NEWS
E-Procurement: Phased Approach
• MWRA has been working to get procurements on-line• Contracts Portal expected to go live this summer
33
E-Procurement: Supplier Portal Went Live Last Week
34