![Page 1: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/1.jpg)
Large Wood in King County Projects
Mercer Island Community and Event Center
June 9, 2015
Nancy Faegenburg, Meeting Facilitator
Water and Land Resources Division
![Page 2: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/2.jpg)
Meeting Overview
Project presentations
Q & A
Open house
![Page 3: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/3.jpg)
Use of Large Wood in Rivers and Streams
Cedar Rapids 2013
Belmondo 2013
Flow Deflection and Redirection
![Page 4: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/4.jpg)
Use of Large Wood in Rivers and Streams
Belmondo
Habitat Enhancement and Mitigation
![Page 5: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/5.jpg)
Use of Large Wood in Rivers and Streams
Rainbow Bend 2015
Natural Deposition
Tolt River 2011
Tolt River 2011 Tolt River 2011
![Page 6: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/6.jpg)
Key Features of Procedures
King County Ordinance and DNRP Procedures for Placed Wood (2010) Consider public safety in project design Seek input through annual meetings and at 30%
design
Project review by professional engineer and ecologist
Applies to all KC projects that place wood or where natural wood is likely to deposit
Website: www.kingcounty.gov\rivers
![Page 7: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/7.jpg)
Programmatic Elements
Ongoing commitments:
Annual safety awareness campaign
Study recreational use and impacts
Independent 3rd party review of projects:
How well does it meet goals and objectives
Design vs. as-built
How was input used and what are the results
Convene stakeholder group to review policies and procedures
![Page 8: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/8.jpg)
Project Locations
![Page 9: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/9.jpg)
Questions?
General Information: Nancy Faegenburg, (206) 477-4688 [email protected]
Project-Specific Information: Contact Project Manager or Contact listed on agenda
![Page 10: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/10.jpg)
PROJECTS ON SMALL
CREEKS USING LARGE
WOOD
HARRIS CREEK FISH PASSAGE PROJECT
CLOUGH CREEK OFF-CHANNEL SEDIMENT POND
SCOTT PROPERTY, JUDD CREEK HABITAT
ENHANCEMENT PROJECT
KLAPP PROPERTY RESTORATION
![Page 11: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/11.jpg)
![Page 12: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/12.jpg)
HARRIS CREEK FISH PASSAGE PROJECT
Duvall
![Page 13: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/13.jpg)
PROJECT GOAL:
Restore fish passage to about 4 miles of stream with excellent habitat characteristics.
Assessment in the Snoqualmie watershed completed in June 2011 by Wild Fish Conservancy ranked Harris Creek as 2nd highest priority.
![Page 14: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/14.jpg)
OBJECTIVES
• Remove the existing, non-functional fish ladder at the downstream end of the NE Stossel Creek Way culvert at NE 138th Place;
• Construct a 95-
foot long roughened channel consisting of a well graded bed mixture and logs.
![Page 15: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/15.jpg)
PURPOSE OF WOOD
17 pieces of large wood will be used to provide channel roughness and complexity to the tapering reach of channel. Wood and boulders are necessary to break up flows and slow water velocities to improve fish passage.
![Page 16: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/16.jpg)
• Project on private property and King County right-of-way.
• No known recreational use; • Property owners are very supportive.
RECREATIONAL REVIEW
![Page 17: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/17.jpg)
PROJECT STATUS
• Final design; • Summer, 2015 construction • Posted for public review and comment in May, 2015
Project Manager/Contact:
Carolyn Butchart 206-477-4659
![Page 18: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/18.jpg)
CLOUGH CREEK OFF-CHANNEL
SEDIMENT POND
![Page 19: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/19.jpg)
PROJECT PURPOSE,
GOALS AND OBJECTIVES
Purpose: Sediment accumulations in the channel have cause flooding of homes and roadways.
Goal: To reduce the amount of excessive sediment in the stream to reduce overbank flood events which have damaged homes, yards, buildings, roads, and utility infrastructure.
Objective: Construct an off-channel pond to collect sediment.
![Page 20: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/20.jpg)
![Page 21: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/21.jpg)
PURPOSE OF WOOD
Several logs without rootwads will be installed at the inlet to the off-channel pond to divert flow and sediment into the pond. More wood, with rootwads, will be installed in the reach of Clough Creek adjacent to the new pond to improve habitat and provide bank stability.
![Page 22: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/22.jpg)
RECREATIONAL REVIEW
No known recreational use; Summer flows between 1 - 2 cubic feet per second.
![Page 23: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/23.jpg)
PROJECT STATUS
Preliminary design; Project plans and instream design checklist will be posted for review and comment soon; Summer, 2016 construction.
Project Manager/Contact: Wendy Kara 206-477-4723
![Page 24: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/24.jpg)
SCOTT
PROPERTY,
JUDD CREEK
HABITAT
ENHANCEMENT
PROJECT
![Page 25: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/25.jpg)
Vashon Island
![Page 26: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/26.jpg)
PROJECT PURPOSE
AND GOAL
The purpose of the project is to restore natural habitat in Judd Creek and the Judd Creek Estuary.
Goal:
To conserve and restore natural processes by placing woody debris that was naturally and historically more common on Puget Sound shores and streams.
![Page 27: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/27.jpg)
PROJECT OBJECTIVE:
Restore natural habitat forming processes by placing 30 logs with root balls in 550 feet of Judd Creek and 30 logs with root balls along 400 feet of shoreline in the Judd Creek Estuary.
![Page 28: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/28.jpg)
TYPICAL WOOD PLACEMENTS IN THE STREAM REACH
![Page 29: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/29.jpg)
TYPICAL WOOD PLACEMENTS IN THE ESTUARY REACH
![Page 30: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/30.jpg)
RECREATIONAL REVIEW- STREAM
Judd Creek is a wadable creek that averages 15’ wide and has summer stream flows of < 10 CFS.
Property is owned and managed by the Vashon Maury Island Land Trust, but privately leased. Access is currently limited
![Page 31: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/31.jpg)
Judd Creek estuary near low tide
Recreational Review- Estuary
Tide lands are privately owned by the Vashon Maury Island Land Trust and other private property owners. At low tide, the shallow Judd creek low flow channel averages 20’ wide and 18” deep. At high tide the estuary is accessible from Quartermaster Harbor by small boats with minimal draft. An existing log blocks the deeper water access to the estuary. Kayaks and small boats with trawling motors are known to explore the estuary. The proposed wood placement will not block existing low flow channel and will not exclude recreational use of the estuary.
Large log at stream mouth limits boat access to upper estuary.
![Page 32: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/32.jpg)
Project Manager/Contact: Paul Adler , Project Manager
206.477-4606 [email protected]
Project Status
Final Design; Construction scheduled Summer, 2015
![Page 33: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/33.jpg)
KLAPP PROPERTY
RESTORATION
![Page 34: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/34.jpg)
PROJECT GOALS AND OBJECTIVES
Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel habitats.
Objectives: Remove bank armor and debris from Mackey Creek; Improve instream habitat by replacing missing structure in the form of large woody debris; Provide off-channel rearing habitat for juvenile salmonids by enlarging the channel of Mackey Creek at the confluence and connecting the adjacent pond to Mackey Creek; Establish riparian plant communities throughout the property;
![Page 35: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/35.jpg)
![Page 36: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/36.jpg)
![Page 37: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/37.jpg)
PURPOSE OF WOOD
To push the channel of Mackey Creek into the newly-connected wetland pond; To provide cover and hydraulic complexity to the otherwise simple channel; To provide shade to open areas of the channel
![Page 38: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/38.jpg)
RECREATIONAL USE
Both Mackey Creek and Bear Creek are too small for recreational floating;
Some passive recreation (fish viewing).
![Page 39: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/39.jpg)
PROJECT STATUS
• Final Design; • Summer, 2015 Construction; • Posted for public comment in April, 2015
Project Manager/Contact:
Laird O’Rollins 206-477-4790
![Page 40: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/40.jpg)
Large Wood Public Meeting June 9, 2015
Winkelman Revetment Reconstruction Project
Chase Barton, PE, LG, Project Manager River and Floodplain Management Section
King County Water and Land Resources Division
![Page 41: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/41.jpg)
Project Site Location
![Page 42: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/42.jpg)
Project Site Details
![Page 43: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/43.jpg)
Project Goals
• Reconstruct the revetment to protect the City of Seattle’s Tolt River Water Supply Pipeline.
• Minimize long-term maintenance needs and costs of flood hazard management associated with repeated repairs and the likelihood of emergency actions.
• Provide riparian and aquatic habitat benefits to the extent practicable and required for mitigation.
![Page 44: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/44.jpg)
Project Site Conditions
Looking Upstream from floodplain surface
![Page 45: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/45.jpg)
Project Site Conditions
Looking downstream from toe of bank during low flow conditions
![Page 46: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/46.jpg)
Proposed Design – Bank & Scour Protection
Revetment Elements: • Large Wood:
– ~840 Logs
• Toe:
–Fill scour hole with riprap and wood
• Lower Bank:
–Pile supported bank roughening jam
–Bank resloping
• Upper Bank:
–Live stakes
–Coir encapsulated soil lifts
–Bank resloping
![Page 47: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/47.jpg)
Proposed Design – Bank Protection
Revetment Elements: • Large Wood:
– ~840 Logs
• Toe:
–Riprap and wood
• Lower Bank:
–Pile supported bank roughening jam
–Bank resloping
• Upper Bank:
–Live stakes
–Coir encapsulated soil lifts
–Bank resloping
![Page 48: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/48.jpg)
Proposed Design – Floodplain Alcove Reconnection
Alcove Elements: • Large Wood:
– ~210 Logs
• Stream Channel:
– Culvert replacement
– Channel resloping
• Access Road:
– Reconfigured access road across new culvert
– Invasive plant removal
![Page 49: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/49.jpg)
Recreational Use
• Access to project reach is limited.
– Upstream access from Carnation
– Downstream access from Duvall
• Slow velocities in project reach.
• Long sight lines to wood placement locations.
• Infrequent to moderate use by fisherman and motorized boats
– MacIlroy, June 2009
– Herrera, October 2014
• Wildlife cameras at site form May – Sept 2014.
![Page 50: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/50.jpg)
Recreational Use
![Page 51: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/51.jpg)
Recreational Use
![Page 52: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/52.jpg)
Recreational Use
![Page 53: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/53.jpg)
Recreational Use
![Page 54: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/54.jpg)
Project Schedule
• April 2015 - Alternatives Analysis [COMPLETED]
• July/August 2015 - 30% plans available
• August/September 2015 - Permit applications to be submitted
• January 2016 - 100% design complete
• July 2016 – October 2016 - Construction
![Page 56: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/56.jpg)
Elliott Bridge Reach
Elliott Bridge Reach Off-Channel Habitat and Floodplain Reconnection Project
![Page 57: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/57.jpg)
N
![Page 58: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/58.jpg)
Objectives • Satisfy Mitigation Reserve Program Obligations
Wetland
Off-channel habitat
Mainstem Scour structure
• Maintain Flood hazard protection
• Address Recreational safety issues
• Compatibility with future plans
![Page 59: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/59.jpg)
![Page 60: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/60.jpg)
Purpose of Wood
Wood is designed to: Create a scour pool with natural cover in the Cedar
Provide cover and complexity along inside bend
Limit sediment deposition at mouth of outlet channel
Provide cover and structure within backwater and wetland
Provide variety of flow velocity, induce scour, and create eddies of slow water
AND is required part of Mitigation obligations
![Page 61: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/61.jpg)
![Page 62: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/62.jpg)
Right Bank Overview
![Page 63: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/63.jpg)
Right bank Scour Structure
![Page 64: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/64.jpg)
Right bank Scour Structure
![Page 65: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/65.jpg)
Left Bank Overview
![Page 66: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/66.jpg)
Left Bank inlet constricted and stable
![Page 67: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/67.jpg)
Left Bank inlet constricted and stable
![Page 68: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/68.jpg)
RECREATIONAL REVIEW • 2010 & 2013
Recreational Studies • Heavy recreational use • Tube & Raft use HIGH
On-site meetings with River Safety Council and Resource Agencies
Iterative Design Process
Open dialog Incorporating ideas Minimizing conflicts
![Page 69: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/69.jpg)
PROJECT STATUS • Construction Summer 2015
Scour Structure as 2nd Phase in 2016
• Posted for public review and comment in Jan & May, 2015
Project Manager/Contact: Jon Hansen
206-477-4706 [email protected]
Project webpage:
www.kingcounty.gov/rivers
![Page 70: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/70.jpg)
Green River 2015 Log Placement Projects
![Page 71: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/71.jpg)
Green River Log Placement Projects Mitigate for 2009 Levee Clearing
![Page 72: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/72.jpg)
Four Green River Sites Designated for Tree Cutting Mitigation
• Foster Golf Course (2015) 22 Logs
• Teufel Nursery (2016) 89 Logs
• Fenster Park (2015) 27 Logs
• Green R. Natural Area (2015) 79 Logs ________________________________
• Total Mitigation (2015-2016) 217 Logs • 2015 Mitigation 128
Logs
![Page 73: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/73.jpg)
Fenster Park Location Auburn, Left Bank, River Mile 32.0
![Page 74: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/74.jpg)
Lower Green River Recreational Use at Fenster Park
![Page 75: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/75.jpg)
Lower Green River Recreational Users at Fenster Park
![Page 76: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/76.jpg)
Fenster Park 2014 King County Sheriff’s Findings
“Removal is a good idea.”
![Page 77: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/77.jpg)
Fenster Park 2014 Log Removal Action
![Page 78: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/78.jpg)
Fenster Park 2014 Log Removal Action
![Page 79: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/79.jpg)
Fenster Park 2014 Log Removal Action
![Page 80: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/80.jpg)
Fenster Park 2014 Log Removal Action
![Page 81: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/81.jpg)
Fenster Park 2015 River Condition
![Page 82: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/82.jpg)
Fenster Park Log Placement (2015) 27 Logs
![Page 83: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/83.jpg)
Fenster Park Log Placement (2015) 27 Logs
![Page 84: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/84.jpg)
Green River Natural Area Location King County, Right Bank, RM 38.0
![Page 85: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/85.jpg)
Recreational Use at Green River Natural Area
![Page 86: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/86.jpg)
Recreational Use at Green River Natural Area
![Page 87: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/87.jpg)
Recreational Use at Green River Natural Area
![Page 88: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/88.jpg)
Recreational Use at Green River Natural Area
![Page 89: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/89.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2002 River Channel Alignment
![Page 90: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/90.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2007 River Channel Alignment
![Page 91: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/91.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2009 River Channel Alignment
![Page 92: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/92.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2012 River Channel Alignment
![Page 93: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/93.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2013 River Channel Alignment
![Page 94: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/94.jpg)
Green River Natural Area Log Placement Project (2015) 79 Logs
2013 River Channel Alignment
![Page 95: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/95.jpg)
Green River Natural Area 2015 Log Placement Project
![Page 96: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/96.jpg)
Green River Natural Area 2015 Log Placement Project
![Page 97: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/97.jpg)
Green River Natural Area 2015 Log Placement Project
![Page 98: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/98.jpg)
Green River Natural Area 2015 Log Placement Project
![Page 99: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/99.jpg)
Reagan Dunn
Board of Supervisors, King County Flood Control District
On the Web:
www.kingcountyfloodcontrol.org
Project Manager:
(206) 477-4753
![Page 100: Presentation Slides: Large Wood in King County Projects...Goal: To enhance the ecological values of the Klapp property and the confluence of Mackey and Bear Creeks, including off-channel](https://reader031.fdocuments.in/reader031/viewer/2022040814/5e5abe7a8b3e4009d074a62f/html5/thumbnails/100.jpg)
OPEN HOUSE
• Small Projects: Laird O’Rollins
• Winkleman Revetment Reconstruction Project: Chase Barton
• Elliott Bridge Reach Off-Channel Habitat and Floodplain Reconnection Project: Jon Hansen
• Green River 2015 Log Placement Projects: Andy Levesque
• Project Effectiveness Monitoring: Laura Hartema