Presentation: QNP Green Hydrogen to Ammonia Project · Text •Text Commission 2000 BHP Glencore 90...
Transcript of Presentation: QNP Green Hydrogen to Ammonia Project · Text •Text Commission 2000 BHP Glencore 90...
QNP
Green Hydrogen to
Ammonia ProjectQNP and Project Intro - Feb 2020
Text
•Text
Commission
2000
BHP
Glencore
90
employees
235 ktpa AN
QNP facility near Moura, Queensland
Ammonium nitrate products – “Prill” (left) & “Emulsion”
50/50
ownership
$25-35m local
economy
QNP - Location
• Approximately 160km east of Gladstone
• Southern end of the coal rich Bowen Basin
Mines Serviced by QNP
CURRAGH
QNP Process – opportunity for additional
hydrogen and ammonia production
Ammonia
Nitric Acid
Ammonium
Nitrate
Purchased
ammonia
Gas
QNP Production Process
Customers
QNP Green Ammonia Project Concept
H2O Air
• New plant - hybrid wind,
solar, battery (≈ 200 to
300MW)
• Approximately 30MW at
80% capacity for
electrolysis
• 60GWh/yr for existing QNP
facility
• New plant - electrolysis
producing 3500 t/year of
hydrogen (H2)
• New plant – liquid ammonia
(NH3) 20,000 t/year,
• H2 storage to absorb
renewable variability &
provide continuous feed to
NH3 plant
• Existing QNP ammonium nitrate (AN)
facility, output used for mining
explosives within Queensland
• Currently using NH3 from on site gas
steam reformation, which is at
capacity – additional 20kT/y sourced
from 3rd parties
• Concept is to displace 3rd party supply
using new
renewables/hydrogen/ammonia plant
New plant New plant
Existing
QNP Facility
5
Blue Chip Customers
Expected Final Asset Ownership & RelationshipsA
SS
ET
OW
NE
RS
HIP
PPA
MW
/MW
h
Supply of capacity & energy to both the new
H2 and NH3 components, as well as to the
existing QNP ammonia nitrate facility.
6
H2O Air
Ex
pe
rtis
e
Electricity supply Commercials, operations, plant integrationPM, engineering, delivery
•Blue Chip Australian owners
•Experienced chemicals facility operator
•Providing grid support services
•Renewable energy supply
•20 ktpa Ammonia sensible scale up step
•Established offtake and customers
•20 ktpa Ammonia sensible scale up step
Green Hydrogen to AmmoniaSome knowledge from ARENA supported feasibility underway:
•1
•2
•3
•4
•Interruptible loads
OEM inexperienced with dynamic
operation of large electrolysers
• Significant early step to commercialisation
Scalability and learning to:
• take the next step to decarbonise QNP supply
chain
• Take the next step to scale renewables based
hydrogen export potentially via ammonia
•Balancing risk and scale
Large green hydrogen project, small in
relation to the opportunity - the right size
to demonstrate scalability.
•Learn as enablers emerge
Build capability in projects beyond studies.
Potential enablers include:
•Lower cost Renewables
•Carbon pricing
•Natural gas markets
•Hydrogen markets
Potential Business Case Levers
Initial Business
Case
Feasibility
Engineering
Network Costs Energy Costs Grant Funding Concessional
Finance
Tax Treatment Final Business
Case
NP
V
Business Case Lever
Hydrogen Industry DevelopmentEnd game:
• New Renewables based hydrogen export industry
• Decarbonise existing industries• Viable Business Case
• Funding cost
• Risk – proven commercial
application, established
performance characteristics
• Counterparty risk and
contractual arrangements
•.
• Electricity Cost• Operate plant to electricity
market signals
• Unique operating and
contractual arrangements
required
•TransmissionConnecting the electricity generation
to the market – what to transmit?
•Capital Cost• Capital/operating trade-
offs – renewables
intermittency/storage
• Scale
• R&D – technology,
manufacturing costs,
response times.
Project stages
11
Concept
• Prepare initial ARENA
application
• +-50% accuracy –
Class 1
FEED
• +-10% accuracy –
Class 3
• Finalise
renewables supply
and financing
Feasibility
• +-30 accuracy –
Class 2a
• Financing and
renewables
analysis
Delivery
• Construction and
Installation
• Commissioning
Aug 2019
• ARENA -
Feasibility Study
Funding
approval
• QNP Board
approval to
proceed
Q1 2020
• ARENA -Full
Project Funding
approval sought
• QNP Board
approval
Q4 2020
• ARENA -Full
Project Funding
confirmation
• Board sanctions
– QNP and
Neoen
Q4 2022 –
Q1 2023
• Commence
operations
6 months 8-15 months 24 months
ARENA Hydrogen
Round
Additional
Information
12