Presentation on Investment Opportunities in Indian Power ... · PDF filePresentation on...
Transcript of Presentation on Investment Opportunities in Indian Power ... · PDF filePresentation on...
1
Presentation Presentation on on
Investment Opportunities in Indian Investment Opportunities in Indian Power SectorPower Sector
By Rajeev Sharma
Director (Projects) Power Finance Corporation Ltd., New Delhi
(November 09, 2009)
2
POWER INFRASTRUCTURE IN INDIA
HYDRO 24.2% (36,885
MW)
NUCLEAR 2.7% (4,120 MW)
FUEL WISE
THERMAL64.4% (98,045 MW)
RENEWABLES 8.7% (13,310
MW)
Coal + Lignite –
80,396 MW
Gas
–
16,449 MW
Diesel
–
1,200 MW
TOTAL INSTALLED CAPACITY (end Sept.’09) – 1,52,360 MW
3
POWER INFRASTRUCTURE IN INDIA…Contd
STATE 50% (76,627 MW)
PRIVATE 17% (25,891
MW)CENTRAL
33% (49,842 MW)
SECTOR WISE
TOTAL INSTALLED CAPACITY (end Sept.’09) – 1,52,360 MW
4
Total: 78,700 MWBeginning of Xth Plan End of Xth Plan
Peak shortage 12.60% 13.80%Energy shortage 7.5% 9.60%
Total: 78,700 MWBeginning of Xth Plan End of Xth Plan
Peak shortage 12.60% 13.80%Energy shortage 7.5% 9.60%
POWER INFRASTRUCTURE IN INDIA…Contd
XIXIthth
PLAN CAPACITY ADDITION PLAN CAPACITY ADDITION TARGET : TYPEWISE
COAL64% (50,570 MW)
LIGNITE3% (2,280 MW)
GAS/ LNG9% (6,843 MW)
NUCLEAR4% (3,380 MW)
HYDRO20% (15,627 MW)
5
ANNUAL GENERATION (BUs)
4.073 16.937 47.434104.627
245.438
395.889
517.439
723.556
1947 1961 1969 1980 1990 1997 2002 2009
Note : all figures as of month of March except for 1947, which is of December
6
23,238 157,887886,301
2,351,609
4,407,5015,141,413
6,030,148
7,106,078
1947 1961 1969 1980 1990 1997 2002 2008
TRANSMISSION & DISTRIBUTION NETWORK (ckm)
Note : all figures as of month of March except for 1947, which is of December
7
At time of Independence with generating capacity of 1,362 MW, generation and distribution were carried primarily by private utilities in a few urban centres.
The Electricity (Supply) Act, 1948 enacted to facilitate faster power sector development. Consequently SEBs set up with new generation, transmission and distribution coming under purview of SEBs.
As financial constraints of State Governments precluded the SEBs from adding the desired capacity, the need was felt for Central Government supplementing the effort.
• Central Generating companies set up – NTPC/ NHPC/ NEEPCO/ NPCIL etc.
• POWERGRID created for operating & maintaining the inter state and inter regional transmission systems
AN OVERVIEW OF LEGAL & POLICY FRAMEWORK
THE HISTORICAL BACKGROUND
(
8
Power Sector reforms initiated in 1991 with focus to encourage competition and seek private participation (focus was on generation)
• The losses incurred by the SEBs made it difficult to commercially sustain leading to large outstanding thus discouraging new developers.
The key focus shifted to Distribution reforms; the “Bottoms up” approach was facilitated by the legal framework laid through the Electricity Regulatory Commissions Act, 1998 for creating an independent and transparent regulatory regime.
The Electricity Act, 2003 provided the required tool kit and recipe
AN OVERVIEW OF(LEGAL & POLICY FRAMEWORKHISTORICAL BACKGROUND ….Contd
9
1910
1948
1998
2001
2003
Indian Electricity Act, 1910
Indian Electricity (Supply) Act, 1948
Amendments to Indian Electricity (Supply) Act, 1948
Energy Conservation Act, 2001
Electricity Regulatory Commissions Act, 1998
Electricity Act, 2003
AN OVERVIEW OF(LEGAL & POLICY FRAMEWORKHISTORICAL BACKGROUND ….Contd
14
ELECTRICITY ACT, 2003 - NOTIFIED ON 10TH JUNE ‘03
Creates liberal framework for development
Creates competitive environment
Facilitates private investment
Delicenses generation except for hydro : Captive free from controls
Rural Areas : Stand alone Generation and Distribution delicenced
Multiple licensing in Distribution
Stringent provisions for controlling theft of electricity
Focus on revenue recovery in cases of unauthorized use of electricity
• Objective : Competition, Protection of Consumers interests & Power for all areas
11
Obliges States to restructure Electricity Boards
Mandates creation of Regulatory Commissions
• Retail tariff to be determined by regulatory commissions
Open access in Transmission from outset
Open access in Distribution to be allowed by SERCs in phases
Gradual phasing out of cross subsidies
Trading distinct activity permitted with licensing
ELECTRICITY ACT, 2003 - NOTIFIED ON 10TH JUNE ‘03….Contd
12
NATIONAL ELECTRICITY POLICY
NATIONAL ELECTRICITY POLICY (NEP) notified on 12th Feb.’05, with objectives :
Availability of Power – Demand to be met by year 2012 / Energy and Peak shortages to be overcome and adequate spinning reserves available.
- Fresh capacity of 78,000 MW targeted for addition during
XIth Plan.
Supply of Reliable and Quality Power
- ERCs have notified Standards of Performance
Financial Turnaround and Commercial viability of Electricity sector
- AT&C loss reduction strategy provided by ERCs.
- R-APDRP launched by the Government.
Protection of Consumers’ interests
- Consumers Grievance Redressal forums constituted.
Access to Electricity
- Government of India has launched two Schemes to
improve the distribution sector: RGGVY & APDRP
Effective utilization of all available resources for generation, transmission and distribution
- National Electricity Plan notified covering Generation &
Transmission.
13
NATIONAL ELECTRICITY PLAN
National Electricity Plan notified on 3rd Aug.’07- Plan based on 17th EPS and GDP growth rates of Integrated Energy Policy- Serves as Road map towards optimum growth of the power sector Focus areas and the present status :
• Adoption of Super critical technology to improve efficiency and reduce coal consumption
• Introducing Ultra Super critical technology (Plant using Steam parameters above 275 kg/ cm2 and Steam temp. over 565oC)• Encouragement for imported Coal based plants • Harness the Lignite reserves • Use of non conventional energy resources • Strengthening of Transmission system-HVDC , AC
14
TARIFF POLICY
Tariff Policy notified on 6th June ’06, with objectives :• Ensure availability of electricity to consumers at reasonable and competitive rates
- Competitive Bidding guidelines and Standard Bidding Documents for procurement of electricity and for developing Transmission projects through tariff based bidding issued.
- UMPPs have achieved competitive tariffs.• Ensure financial viability of the Sector and attract investments
- CERC notifying rates for Return on Equity and depreciation. - Satisfactory situation of payment to Generators and Transmission
Service Providers• Promote transparency, consistency and predictability in regulatory approaches across jurisdictions and minimize perceptions of regulatory risks.
- The Forum of Regulators is working to facilitate consistency in approach specially in the area of distribution.
- Multi Year Tariff (MYT) implemented by CERC in Generation and Transmission.
- All future requirements of power to be procured competitively by
15
Notified on 23rd August, 2006
Objectives:• Provision of access to electricity to all households by 2009.• Quality and reliable power supply at reasonable rates.• Min. lifeline consumption of 1 unit per household per day by 2012.
Grid connectivity to be normal way of village electrification
“RGGVY” mandated for completion of rural electrification
Off grid solutions based on stand alone system may be taken up in areas where grid connectivity is not feasible or not cost effectiveFranchisees for management of rural distribution for revenue sustainability
States to constitute District Committees to review & coordinate rural Electrification, quality of power supply, consumer satisfaction and promote energy efficiency & conservation
States to notify rural areas Rural Electrification Plans
RURAL ELECTRIFICATION POLICY
16
NEW HYDRO POLICY
Exemption to private sector from tariff based competitive bidding up to
Jan’ 2011 which was available only to public sector.
Merchant sale of up to 40% of the saleable energy.
An additional 1% free power over and above 12% for a Local Area
Development Fund - A regular stream of revenue for income generation,
infrastructure creation and welfare schemes in the affected areas.
Construction of houses at resettled sites. Each Project Affected Family
(PAF) to get 100 units/ month free for 10 years.
An industrial training institute (ITI) at each project site, set up six months
before the beginning of the project work. PAPs will be provided jobs in the
project after training.
17
OPEN ACCESS
Open Access is one of key features of the Electricity Act 2003.
Open Access defined as the “Non-Discriminatory provision for the use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by the Appropriate Commission.”
Open access in distribution to be introduced by SERCs in phases. In first phase, open access to consumers with load exceeding 1 MW, latest by January 2009 (Section 42)
Mechanism of cross-subsidy charge to compensate the distribution licensee.
Inter State Open Access in Transmission – Accomplished
PGCIL is the nodal agency for grant of open access in inter state transmission system
18
Focus of the programme on AT&C loss reduction on sustainable basis through systematic measures :• Establishment of base line data• Fixing of accountability• Strengthening and up-gradation of sub transmission and distribution network• Adoption of Information Technology
GOVT. SPONSORED PROGRAMES:‐
RESTRUCTURED ACCELERATED POWER DEVELOPMENT & REFORMS PROGRAMME
(R‐APDRP)
CONTINUATION OF APDRP (R-APDRP) SCHEME DURING THE XITH PLAN APPROVED ON 31.07.08 AS A CENTRAL SECTOR SCHEME.
19
# Project implementation under the scheme primarily to be taken up in two parts :• Part-A includes the projects for establishment of baseline data and IT applications for energy accounting/auditing & IT based consumer service centers. • Part-B includes regular distribution strengthening projects including segregation of feeders.
IUSD=INR 48# Programme size of re-structured APDRP during XIth Plan :-
10.75.BUSD- Part-A (Baseline System projects) :- 2.083 BUSD- Part-B (Strengthening & Up-gradation projects):- 8.33BUSD- Part-C (Enabling activities) :– 0.245 BUSD- Part-D (Incentives to Utility staff):- 0.083 BUSD
GOVT. SPONSORED PROGRAMS:‐
RESTRUCTURED ACCELERATED POWER DEVELOPMENT & REFORMS PROGRAMME (R‐APDRP)
….contd
20
Initially 100% loan for Part A and up-to 25% (90% for special category States) loan for Part B from the Govt. of India.
The entire loan for Part-A to be converted into grant after establishment of Base-line data system.
Up-to 50% (90% for special category States) loan of Part-B to be converted into grant on achieving the 15% AT&C loss in the project area.
(…
GOVT. SPONSORED PROGRAMS:‐
RESTRUCTURED ACCELERATED POWER DEVELOPMENT & REFORMS PROGRAMME (R‐APDRP) ….contd
21
RAJIV GANDHI GRAMEEN VIDYUTIKARAN YOJANA (RGGVY)
Launched in March, 2005
Initial sanction was for last two years of Xth Plan with capital subsidy of 1.041 BUSD (IUSD=INR 48)
Under the scheme 90% Capital Subsidy provided
REC the nodal agency for implementation of RGGVY
Continuation of Scheme in XIth Plan sanctioned in January ‘08 with a subsidy provision of 5.833 BUSD (I USD=INR 48) for Phase I of the Scheme
# PRESENT STATUS :
TARGET ACHIEVED
No. of villages to be Electrified 1,18,146 61,209
No. of free BPL connections (in Lakh)
245.08 59.19
Designated by the Govt of India as the Nodal Agency for the development of UMPPs
Each UMPP to have a generation capacity of 4000 MW
Incorporated wholly owned subsidiary companies to act as SPVs for the projects
Subsidiaries to carry out pre-feasibility studies & facilitate tie-up of inputs, linkages and clearances
SPVs to be transferred to bidders through ‘Tariff Based International Competitive Bidding Guidelines’ issued by Govt. of India.
Tariff-based ICB completed 7 projects transferred to successful bidder as below:
Mundra UMPP (Gujarat) to Tata Power in Apr. 2007: USD 0.047/unit (Rs. 2.26/ unit)
Sasan UMPP (MP) to Reliance Power Ltd in Aug. 2007: USD 0.0247/unit (Rs. 1.19/ unit)
Krishnapatnam UMPP (AP) to Reliance Power in Jan. 2008: USD 0.0485/unit (Rs. 2.33/ unit)
Tilaiya UMPP (Jharkhand) to Reliance Power in Aug. 2009 (Rs. 1.77/ unit)
Designated by the Govt of India as the Nodal Agency for the development of UMPPs
Each UMPP to have a generation capacity of 4000 MW
Incorporated wholly owned subsidiary companies to act as SPVs for the projects
Subsidiaries to carry out pre-feasibility studies & facilitate tie-up of inputs, linkages and clearances
SPVs to be transferred to bidders through ‘Tariff Based International Competitive Bidding Guidelines’ issued by Govt. of India.
Tariff-based ICB completed 7 projects transferred to successful bidder as below:
Mundra UMPP (Gujarat) to Tata Power in Apr. 2007: USD 0.047/unit (Rs. 2.26/ unit)
Sasan UMPP (MP) to Reliance Power Ltd in Aug. 2007: USD 0.0247/unit (Rs. 1.19/ unit)
Krishnapatnam UMPP (AP) to Reliance Power in Jan. 2008: USD 0.0485/unit (Rs. 2.33/ unit)
Tilaiya UMPP (Jharkhand) to Reliance Power in Aug. 2009 (Rs. 1.77/ unit)
ULTRA MEGA POWER PROJECTS
Coastal
Tamil Nadu
Power Ltd.
SasanPower Ltd.
Coastal
Maharashtra
Mega Power
Ltd.
CoastalKarnatakaPower Ltd
JharkhandIntegratedPower Ltd
Awarded ProjectsAwarded Projects Under ProcessUnder Process
Akaltara
Power Ltd.
Orissa
Integrated
Power Ltd.
Coastal
Gujarat
Power Ltd.
Coastal
Andhra
Power Ltd
.
Sakhi
GopalIntegrated
Power Co. Ltd, Orissa
GhogarpalliIntegrated
Power Co. Ltd, Orissa
Tatiya
Andhra Mega
Power Limited, Andhra
Pradesh
22
ULTRA MEGA POWER PROJECTS UNDER PROGRESS
Coastal Tamil Nadu Power Ltd., Cheyyur UMPP, Tamil Nadu: RfQ to be issued after finalisation of port site.
Orissa Integrated Power Ltd., Sundergarh UMPP, Orissa: Gram Sabha for 8 villages held in Sept’ 09. Outstanding issues to be resolved by Chief Secretary, GoO. RfQ to be issued after issuance of section 4 notification.
Akaltara Power Ltd., Chhattisgarh UMPP: Application filed for section 4 notification for 5 villages. Work for Section-4 application for five remaining villages in progress. RfQ to be issued after issuance of section 4 notification
Andhra Pradesh 2nd UMPP: Site near Kothapeta finalised. Alternate locations of Ash Dyke and Colony Area sent by CEA to APGENCO. Consent of State Govt awaited.
23
ULTRA MEGA POWER PROJECTS UNDER PROGRESS….CONTD
Coastal Maharashtra Mega Power Ltd., Maharashtra UMPP : Site yet to be finalised.
Sakhigopal Integrated Power Ltd., Orissa Additional UMPP 1: Site yet to be finalised.
Ghogarpalli Integrated Power Ltd., Orissa Additional UMPP 2: Site yet to be finalised.
Coastal Karnataka Power Ltd., Karnataka UMPP: Sites to be proposed by States
Gujarat 2nd UMPP: Site yet to be finalised
Tamil Nadu 2nd UMPP: Sites to be proposed by States
24
POTENTIAL FOR AUGMENTATION OF POWER PLANT EQUIPMENT MANUFACTURING BASE
• Currently, BHEL is the only manufacturer in India for the main plant equipments (Boiler, Turbine and Generator)with current capacity is about 10000 MW, and another 5000 MW expansion is under execution
• The rest of the supply for main plant equipments from the imports thru OEMs-Alstom, Siemens, GE. Chinese companies
• Many Indian private players are setting up joint ventures with OEMs to manufacture the power plant equipments in India.
• According to IMaCS’ estimates, during 12th Five Year plan, about 28000 MW to 31000 MW of capacity addition would be required per year assuming that India will maintain a GDP growth rate of 9% in the period
• With reference to the Mckinsey Report “Powering India: The Road to 2017”, India will require a generation capacity of 415 to 440 GW by FY 17, which in turn means an annual capacity addition of about 40,000 MW,
• According to the computations mentioned above, India will reach to an annual capacity of 39000 MW (15000 MW by BHEL and 24000 MW by JVs) by the end of FY 17, which is in line with foregoing projections.
25
RECENTLY ANNOUNCED JV’S FOR MAIN PLANT EQUIPMENT MANUFACTURING
26
S.No. Joint Venture
Equity Mix Capacity Addition (in
MW)
Product
1 JSW- Toshiba
JSW: 25%; Toshiba : 75%
3000 TG
2 NTPC- BHEL IL&FS 50%; NTPC 25% ; BHEL 25%
5000 TG, Boiler, BoP, EPC
3 NTPC- Bharat Forge
Bharat Forge : 51%; NTPC : 49%
Forging, casting of rotors etc
4 Reliance Infra- SEC
NA 10000
5 L&T- Mitsubishi
L&T : 51%; Mitsubishi: 49%
1000 TG
1000 Boiler6 Bharat
Forge- Alstom
Alstom : 51% - Bharat Forge- 49%
5000 TG for Coal, Gas & Nuclear
Total 24000
GENERATION CAPACITY ADDITION DURING XITH FYP
Particulars State Centre Private Total (BUSD)Projects under Construction (including Projects Commissioned and under best efforts )
13.72 26.78 14.97 55.48
Advance action for XII Plan 10.93 15.85 14.88 41.66Total Generation 24.64 42.64 29.85 97.13Decentralized Distribution Generation - 2.08 - 2.08New & Renewable Energy Sources 4.69 - 9.38 14.06Captive Power Plants - - 10.00 10.00Integrated Generation 29.33 44.72 49.23 123.28Renovation & Modernization (R & M) 3.31 0.00 0.00 3.31Renovation & Modernization (R & M) 3.31 0.00 0.00 3.31Transmission 13.54 15.63 - 29.17Total Transmission 13.54 15.63 - 29.17Sub-Transmission & Distribution 41.04 - - 41.04RGGVY 10.63 - - 10.63APDRP 10.75 - - 10.75Others 2.08 - - 2.08Total Distribution & Rural Electrification 64.50 - - 64.50
Human Resource Development (HRD) - 0.10 - 0.10Research & Development - 0.25 - 0.25Demand Side Management (DSM) - 0.14 - 0.14Total Others - 0.49 - 0.49Grand Total 110.68 60.83 49.23 220.73 27
INVESTMENT REQUIRED IN GENERATION SECTOR IN XI TH FYP
Particulars State(BUSD)
IUSD‐INR 48
Centre(BUSD)
Private(BUSD)
Total(BUSD)
Projects under Construction (including Projects Commissioned
and under best efforts )
13.72 26.78 14.97 55.48
Advance action for XII Plan10.93 15.85 14.88 41.66
Total Generation 24.64 42.64 29.85 97.13
Decentralized Distribution Generation - 2.08 - 2.08
New & Renewable Energy Sources 4.69 - 9.38 14.06
Captive Power Plants - - 10.00 10.00
Integrated Generation 140.79 214.66 236.29 123.28
28
TRANSMISSION SYSTEM DEVELOPMENT DURING XITH PLAN
Items UnitsProjected addition in
XI Plan
Target at the end of XI Plan i.e.
March 2012TRANSMISSION LINES
765 KV ckm 5,428 7,132HVDC +/- 500 KV ckm 5,206 11,078
HVDC 200KV Monopole ckm - 162400 KV ckm 49,278 125,000
230/220 KV ckm 35,371 150,000Total Transmission Line ckm 95,283 293,372
SUBSTATIONSHVDC BTB MW - 3,000
HVDC Bipole+Monopole MW 6,000 11,200Total- HVDC Terminal Capacity MW 6,000 14,200
765 KV MVA 51,000 53,000400 KV MVA 52,058 145,000
230/220 KV MVA 73,503 230,000Total- AC Substation Capacity MVA 176,561 428,000
Source: National Electricity Plan – Transmission – Apr.'2007 – CEA.29
INVESTMENT REQUIRED IN XITH PLAN FOR TRANSMISSION DEVELOPMENT PROGRAM
IN BUSD
Central Sector 15.63
State Sector 13.54
Total 29.17
30
31
32
TOTAL INVESTMENT REQUIREMENT FOR XIth
PLAN
In BUSD
CAPACITY ADDITION DURING XII th
AND XIIIth
PLAN
Items 12 th
plan (2012‐17) 13 th
plan (2017‐22)
Coal Based (MW) 74000 64000Gas Based (MW) 0 6000
Lignite Based (MW) 2500 0Hydro (MW) 20000 24500
Nuclear (MW) 3400 8000Total (MW) 100000 100000
Source: CEA (Booklet on equipment on key input requirements for power sector 12 th plan and beyond
33
TOTAL INVESTMENT REQUIREMENT FOR XIIth
PLAN
Area Fund Requirement (BUSD)
Generation 103.14
Transmission 50.00Distribution 83.40
Total 236.54Source: CEA (Booklet on equipment on key input requirements for power sector 12 th plan and
beyond1 USD = INR 48
34
35
THANK YOU