PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independent - Mumin Hacimusalar
Click here to load reader
-
Upload
mumin-hacimusalar -
Category
Documents
-
view
1.182 -
download
6
Transcript of PRESENTATION-Commissioning Experiences on Ammonia and Urea projects- Independent - Mumin Hacimusalar
PRE-COMMISSIONING & COMMISSIONING EXPERIENCES
ON AMMONIA AND UREA PLANTS Mümin HACIMUSALAR
(Independent) Professional Commissioning
Manager / Consultant [email protected]
[email protected] Mobile: +905337746920
Ankara - Turkey
Presentation Update for Nitrogen + Syngas 2016
29 February - 03 March 2016 – Estrel Berlin, Germany
1
Projects
1. Turkmendokunhimiya Tecen Ammonia and Urea Project, 2005, Turkmenistan
2. AlexFert Ammonia and Urea Project, 2006, Alexandria, Egypt
3. MOPCO-I Ammonia and Urea Project, 2008, Damietta, Egypt
4. Engro Ammonia and Urea Project, 2010, Daharki, Pakistan
5. Sorfert Ammonia and Urea Project, 2013, Arzew, Algeria
6. Turkmenhimiya Mary Ammonia and Urea Project, 2014, Turkmenistan
2
1. Tecen Ammonia and Urea Complex Precommissioning And Commissioning Diary
600MT/day Ammonia–Uhde, 1050 MT/day Urea–Stamicarbon; Granulation-HFT
Tecen / Turkmenistan: 2002-2005
3
2003 Plant Site - Turkmenistan
July 2004 Started Pre-commissioning and Commissioning
Activities
Raw Water Available (Water Intake 25 km from Plant B.L.)
Fire Water System In Operation
Temporary Cooling Tower In Operation
August 2004 Waste Water System In Operation
Instrument & Service Air Available
Nitrogen Generation Unit In Operation
Drinking Water Available
4
September 2004
Water Treatment Unit In Operation
Demin Water Unit In Operation
Deaerator and Motor Driven BFW Pump In Operation
Mechanical Cleaning of Cooling Water System Before First Water Filling / Flushing
Steam Boiler Fuel Gas System Ready to Service (Awaiting Natural Gas)
Started Precommissioning of Steam Boiler
Started Air Blowing of Ammonia Plant Front-End Utilizing Desulphurization Unit As Buffer Vessel
Started Oil Flushing for Turbines/Compressor
5
OCTOBER 2004
Natural Gas Available at the Metering Station (5 Km from Plant Battery Limit)
Blowing of Natural Gas Supply Line to Plant B.L. Using Natural Gas; Installed a Blow-Off Pipe to Safe Location at Plant B.L. and then Blown-Out the NG Supply Line Utilizing Natural Gas from the Metering Station
Fuel Gas System to Steam Boiler In Service Steam Boiler In Operation (45 Bar; MP Steam) Started Steam Blowing of MP Steam System Test Operation of Natural Gas/Start-up Compressor Reactors are ready to Catalyst Filling
6
7
Blowing of Natural Gas Supply Line Using Natural Gas
8
Blowing of Natural Gas Supply Line Using Natural Gas
November 2004
Steam Blowing of Ammonia Plant Going on (HP-115 barg; MP-45 barg; LP-3,5 barg)
Natural Gas/Start-up Compressor Ready to Operation
Completed Oil Flushing of Steam Turbines/Compressors
Preparation of Steam Turbines for Over-speed Tests
Ammonia Storage Tank Ready to Service
9
December 2004
Reformer Combustion Air (FD) Fan and Flue Gas (ID) Fan Test Operation
Started Urea Steam System Blowing Carried out Steam Drum & WHB Chemical Cleaning
and Boiling Out Air Blowing of Ammonia Refrigeration System Reformer Fuel Gas System Tightness Test Over-speed Test of BFW Pump Turbine Cooling Water System In Operation Completed Over-speed Tests for Turbines
10
January 2005
First Feed In Reformer Ammonia Plant Front-End In Operation LTS Converter Catalyst Reduction Done (But Not
Put Into Service) CO2 Removal System In Operation Blowing of CO2 Line to CO2 Compressor by Means
of CO2 from CO2 Removal System Test operation of CO2 Compressor Draw-back Process Gas to CO2 Removal System
11
February 2005
Introduced Process Air to Secondary Reformer LTS Converter Catalyst Dedusting, LTS Online CO2 Removal System Online / Stabilization Methanation Online Ammonia Refrigeration System In Operation Synthesis Compressor In Operation 15 Feb. 2005: FIRST AMMONIA PRODUCTION CO2 Compressor Surge Mapping 21 Feb.2005: Completed Ammonia Converter
Catalyst Reduction 28 Feb.2005: FIRST UREA PRODUCTION
12
Tecen Project PRECOMMISSIONING/COMMISSIONING PERIOD TO
FIRST UREA PRODUCTION July 2004 – Feb. 2005: 8 MONTHS
*TURN-KEY PROJECT*
(By GAP INSAAT, ISTANBUL-TURKEY)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA PRODUCTION
March 2002 – February 2005: 36 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION
31 MONTHS PROJECT DELAY: 5 MONTHS
13
14
First Urea Granules / Turkmenistan
15
Ammonia And Urea Complex - Turkmenistan
16
2. AlexFert Ammonia And Urea Complex
1200 MT/day Ammonia–Uhde Technology 1925 MT/day Urea–Stamicarbon Technology
Granulation–Stamicarbon Technology
2005 – 2006 Alexandria / Egypt
17
AlexFert Ammonia And Urea Complex / Egypt
AlexFert Ammonia And Urea Complex / Egypt Commissioning Milestones
01 Nov. 2005: Started Precommissioning And Commissioning Activities
24 Jan.–10 Mar. 2006: Precommissioning And Commissioning of Steam Boiler
04–28 Mar 2006: Steam Blowing of Ammonia Plant 02 May 2006: FIRST FEED IN REFORMER 18 June 2006: FIRST AMMONIA PRODUCTION 25 June 2006: Completed Catalyst Reduction 28 June 2006: Shutdown Ammonia Back-End Due to Heavy
Leakage on Ammonia Separator Level Transmitter 09 July 2006: Urea Synthesis Water Run with CO2 (~140 bar) 12 July 2006: FIRST UREA PRODUCTION
18
AlexFert Project PRECOMMISSIONING/COMMISSIONING PERIOD TO
FIRST UREA PRODUCTION: 01 Nov 2005 – 12 July 2006: 8.5 MONTHS
*TURN-KEY PROJECT*
(By Krupp Uhde GmbH, Germany)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA PRODUCTION:
December 2003 – July 2006): 32 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION 34 MONTHS
PROJECT EARLY COMPLETION: 2 MONTHS
19
20
3. Mopco-I Ammonia And Urea
Complex
1200 MT/day Ammonia–Uhde Technology 1925 MT/day Urea–Stamicarbon Technology
Granulation–Uhde Fertilizer Technology (UFT)
2007 – 2008 Damietta / Egypt
21
Mopco-I Ammonia And Urea Complex
MOPCO-I Ammonia And Urea Complex Commissioning Milestones (1)
September 2007 To April 2008:
Carried out Precommissioning And Commissioning of Off-Sites & Utilities
Flushing / Air Blowing of Ammonia Units
*** 3 Months Delay In Providing Natural Gas ***
03 April 2008: Pigging of Natural Gas Line to Metering Station
05 April: Natural Gas Available At the Plant B.L.
07 April: Ignition of Steam Boiler Burners And Commissioning
22
23
Mopco-I Ammonia And Urea Complex 03 April 2008: Metering Station; Pigging of Natural Gas Supply Line
24
Mopco-I Ammonia And Urea Complex 05 April 2008: Natural Gas Available At Metering Station
MOPCO-I Ammonia And Urea Complex Commissioning Milestones (2)
21 April–05 May 2008: Steam Blowing (HP/MP/LP) 24 May: FIRST FEED IN REFORMER, Catalyst Reduction 21 June: P. Air Compressor Test Operation, Blowing and
Surge Mapping 24 June: Power Generator Test Operation 09 July: Ammonia Refrigeration Compressor Test Operation 28 July: Synthesis Gas Compressor Test Operation 29 July: CO2 Compressor Test Operation 04 Aug: Started Ammonia Catalyst Reduction 06 Aug: FIRST AMMONIA PRODUCTION 10 Aug: CO2 Compressor Surge Mapping 11 Aug: Urea Synthesis Water Run With CO2 (~140 Bar) 13 Aug: Completed Ammonia Converter Catalyst Reduction 14 Aug 2008: FIRST GRANULE UREA PRODUCTION
25
Mopco-I Project PRECOMMISSIONING/COMMISSIONING PERIOD TO FIRST UREA
PRODUCTION: SEP 2007 – AUG 2008: 11 MONTHS
FROM NATURAL GAS PROVISION TO FIRST UREA GRANULE
(03 APR–16 AUG 2008) : 4 MONTHS
*TURN-KEY PROJECT* (By Krupp Uhde GmbH, Germany)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA PRODUCTION:
SEP 2005 – AUG 2008: 35 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION 33 MONTHS
PROJECT DELAY: 2 MONTHS (Due To 3 Months Delay On N.G. Provision)
26
4. Engro Fertilizer Project 2200 MTPD Ammonia Plant/Haldor Topsoe, 3835 MTPD Urea Prilled/Snamprogetti
Daharki – Pakistan: 2009-2011
27
Engro Project – Pakistan Precommissioning / Commissioning Milestones
No MAJOR PROJECT EVENTS Completion
Date Duration
(Day)
1 Started Pre-commissioning 1-Jun-2009 1
2 Raw Water Available & Plant Effluent System Ready (Owner Scope)
1-Oct-2009 122
3 Natural Gas Available at Site (Owner Scope) 6-Nov-2009 158
4 Commissioning of Gas Turbine and & Power Generation (Owner Scope)
25-Nov-2009 177
5 Commissioning of HRSG (Heat Recovery Steam System; Owner Scope)
2-Jan-2010 215
6 P. Air Comp. Commissioning and Surge Mapping & Ready For Air blowing
29-Jun-2010 393
7 Commissioning of KS/HS Steam Systems and Boiler Blow Down System
4-Nov-2010 521
8 FEED IN REFORMER 11-Nov-2010 528
9 UREA SYNTHESIS LEAK TEST 21-Nov-2010 538
10 Ammonia Synthesis Loop & ARU Pneumatic Test 22-Nov-2010 539
11 FIRST AMMONIA PRODUCTION 26-Dec-2010 573
12 FIRST UREA PRODUCTION 29-Dec-2010 576
ENGRO FERTILIZER PROJECT DAHARKI/PAKISTAN
PRECOMMISSIONING/COMMISSIONING PERIOD TO FIRST UREA PRODUCTION:
Jun 2009 – Dec 2010: 19 MONTHS
*EP+LIMITED SUPERVISION CONTRACT* (By SAIPEM S.p.A., Italy)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA
PRODUCTION: April 2007 – December 2010: 45 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION
37 MONTHS PROJECT DELAY: 8 MONTHS
29
5. Sorfert Fertilizer Project 2x2200 MT/day Ammonia–Uhde, 3450 MT/day Urea–Stamicarbon; Granulation-UFT
Arzew – Algeria: Dec 2011 – June 2013
30
SORFERT FERTILIZER PROJECT / Arzew–ALGERIA
TRAIN-1: AMMONIA 1 / UREA AND GRANULATION
PRECOMMISSIONING AND COMMISSIONING PERIOD TO FIRST UREA PRODUCTION: Nov 2010-May 2012; 19 MONTHS
*EP+SUPERVISION CONTRACT* (By Krupp Uhde GmbH, Germany)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA PRODUCTION: (June 2007 – May 2012) 59 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION: 42 MONTHS
PROJECT DELAY FOR TRAIN 1: 17 MONTHS
AMMONIA TRAIN-2
PRECOMMISSIONING PERIOD: (April 2012–December 2012) 9 MONTHS (*)
(*) READY FOR GAS FEED IN / INITIAL START UP as of Dec. 2012 WAITING FOR ALGERIAN AUTHORITY–ARH–OPERATION PERMIT
Ammonia Production: September 2013 Project Realization Time to First Ammonia Production : September 2013 ; 75
months from project start date with 27 months delay
6. Mary Fertilizer Project 1200 MT/day Ammonia–M.W. Kellog Limited, 1925 MT/day Urea–Stamicarbon; Granulation–UFT
Mary – Turkmenistan: 2013 - 2014
32
Turkmenistan Mary Fertilizer Project
PRECOMMISSIONING/COMMISSIONING PERIOD TO FIRST UREA PRODUCTION:
(15 July 2013 – 20 September 2014) 14 MONTHS
*EP+SUPERVISION CONTRACT* (By Kawasaki Heavy Industries, Kobe-Japan)
FROM PROJECT EFFECTIVE DATE TO FIRST UREA
PRODUCTION: (January 2011 – September 2014) 45 MONTHS
PROJECT TARGET SCHEDULE TO FIRTS UREA PRODUCTION:
42 MONTHS PROJECT DELAY: 3 MONTHS
33
Turkmenistan Mary Fertilizer Project Commissioning Progress
34
Projects Summary / Overviews
Project Name, Location, Plant Size and Year
Contract Type
Pre / Commissioning
Time (M)
Time to First Urea Granule
(M)
Project Target Urea (M)
Time Deviation
(M)
Tecen, Turkmenistan 600 MTPD Ammonia;1050 MTPD Urea (2002 – 2005)
Turn-key 8 M 36 M 31 M 5 M delay
AlexFert, Egypt 1200 MTPD Ammonia; 1925 MTPD Urea (2003 – 2006)
Turn-key 8,5 M 32 M 34 M 2 M early
Mopco, Egypt 1200 MTPD Ammonia; 1925 MTPD Urea (2005 – 2008)
Turn-key 11 M (*) 35 M 33 M 2 M delay
Engro, Pakistan 2200 MTPD Ammonia; 3835
MTPD Urea (2007 – 2011)
EP + Limited Supervision
19 M 45 M 37 M 8 M delay
Sorfert, Algeria 2x2200 MTPD Ammonia; 3450
MTPD Urea (2007 – 2013)
EP+ Supervision
Train-1: 19M Train-2: 27M
(**)
Train-1: 59M Train-2: 75M
Train 1: 42M Train 2: 48M
17 M delay 27 M delay
Mary, Turkmenistan 1200 MTPD Ammonia; 1925
MTPD Urea (2011 – 2014)
EP+ Supervision
14 M 45 M 42 M 3 M delay
(* ) 3 months delay in providing natural gas supply (**)Train 2: Precommissioning was conducted within 9 months. However due to environmental and export permits issue from local authorities the commissioning of the plant was suspended for 16 months. M: Month
35
Conclusions / Observations (1) • Only 1 out of 6 projects, a turn-key project; AlexFert, Egypt, was completed
earlier than expected.
• It is stated that turnkey contract projects were completed faster than EP contracts.
The most common causes of delay observed on the projects can be identified as follows depending on the project location and countries:
1. Visa provision for expatriates
2. Language, lack of English speaker
3. Lack of Experienced manpower of owner, contractor or consultant
4. Frequent change of labor or staff; Contractor, Subcontractor, Owner
5. Poor HSE (Health, Safety and Environment) management
6. Provision of operation spare parts
7. Poor Communication / coordination in the workplace and among the project team members and parties
36
Conclusions / Observations (2)
8. Insufficient task priority assignment, project tracking to determine the Critical Path & Expected Completion Time
9. Unqualified subcontractor(s)
10.Poor site management, supervision of EP Contractors
11. Shipping and supply delays; material procurement / delivery, import or export formalities
12.Extreme climatic conditions; weather disruptions or natural disasters, unexpected rains & floods
13.Design errors, design change
14.Change orders or deviation order; by EP Contractor or Owner
15.Unforeseen ground conditions for implementation of projects, faulty soil investigation report, de-watering
37
Conclusions / Observations (3)
16.Conflicts between owner and other Stakeholders of Project
17.Bureaucracy in owner’s organization
18.Improper Factory Acceptance Test (FAT)
19.Local industrial peace and labor issues, public demonstrations
20.Poor inspection and testing techniques methods
21.Delay in obtaining permissions & approvals from Local Authorities
22.Financial Constraints of contractor / owner
23.Improper storage / preservation conditions of materials leading to damaged material when necessary
24.Unnecessary restrictions to access at site
38
Recommendations (1)
1. The most common causes of delay observed on the projects were listed in the previous section; need to be improved
2. Project on Turnkey Basis (EPC Contract; minimize project schedule)
3. Availability of Mechanical Completion and Project Progress Monitoring and Control Systems (ICAPS, WinPCS, …)
4. Work on non-destructive testing (NDT) methods from the initial phase of construction
5. Availability of Detailed –STEPWISE-Pre-Commissioning Procedure to guide Construction / Erection / Pre-commissioning / Commissioning
6. CONTRACTOR’S and OWNER’s Organization Chart corresponding to each other in terms of Pre-commissioning / Commissioning and Normal Operation Responsibilities
39
Recommendations (2) 7. Assignment of expert Operators / Engineers for all disciplines
(Operation, Electric, Instrumentation, Machinery, Mechanic and Administrative) as well as new trainees.
8. A Dedicated Operation Team should be assigned for each system or Unit (Continuity is important; do not change team members).
9. Sometimes, extended or unusual work shifts are required during pre-commissioning / commissioning and start-up
10. Pre-commissioning / Commissioning period is the right time for training of Owner’s Operation team who will operate the plant: They can learn a lot only during pre-commissioning and commissioning phases.
11. Task Force Teams can be formed for the systems / subsystems or units which has high priorities
40
Recommendations (3)
12. Owner's close follow up is necessary for any activities at plant site. Project Manager / Unit Managers / Engineers / Operators should study their lessons (procedures, operating manual, P&ID etc.)
13. Close communication and coordination between all project parties are always essential.
14. Availability of Temporary Cooling Tower for Initial Start Up (to be used for Nitrogen generation, Instrument- Service Air, Steam Boiler / BFW)
15. Commissioning Spares / Operation Spares Availability
16. Respect people; no matter who they are. Treat them properly!
41
THANK YOU!