Presentation 111 (3)

download Presentation 111 (3)

of 12

Transcript of Presentation 111 (3)

  • 8/12/2019 Presentation 111 (3)

    1/12

    Managing Projects and Operations

    Case Study: Gym Equipment Reconfiguration

    Team Name: NGLRS

  • 8/12/2019 Presentation 111 (3)

    2/12

    Student Name and Number - Report Title Overview of Energise Gym Project Management Assignment

    Research aim or Project aimWhat is the background?Assigned to undertake project management in project teams,What is the reason/rationale/motivation for this project? Internalidentification of potential area efficiency gains to be found in thegym in order to enhance capacity and increase customersatisfaction.

    Key TheoryWhat is the theory that underpins this project?Managing Successful Project with PRINCE 2Operation Management (slack et al,2013)Belbin Team RolesWhat literature has informed the research?The Essentials of Project Management ( Lock,2007)The Project Manager (Newton,2005)Project management ( Field et al,1998 )

    GANTT Chart

    Outcomes

    Did the project achieve its aims.This project had achieved our aims as we came with a proposal that hasthe new equipment locating, which could help the owner either toincrease the capacity of membership or to use the space for moreequipment.What unexpected benefits were there?The methodology made an impact on our performance by forming ourproject stages and efficiency.

    ReflectionWhat went well?Project members were cooperative. Sharing knowledge and experience.What went badly?Misunderstanding of communication. Meetings sometimes wereconflicting with team members other tasks. Also response to emails wasnot as expected.What would you do different next time?

    It is important to get closer to team members to understand them better.Find appropriate time for meetings so all members can attend.

    DeliverablesWhat does this project intend to do?

    Use organisational planning to execute Energise Health & FitnessCentre reconfiguration of gym equipment to meet their current andfuture needs.What questions will it answer?Are there potential area efficiency gains to be found? Are thereoverused and idle machines?What problems will it solve?Areas of inefficiency in the gym, customer satisfaction

  • 8/12/2019 Presentation 111 (3)

    3/12

    Research aim or Project aim

    AIM: Use organisational planning to execute Energise Health & Fitness Centrereconfiguration of gym equipment to meet their current and future needs.

    SCOPE: Internal identification of potential area efficiency gains to be found in thegym assuming that layout / walls have remained the same as of when we visitedthe gym.

    OBJECTIVES:Establish team roles and responsibilities by 04/11/13Identify dependencies and milestones by 04/11/13.

    Identify overused and idle machines to determine future equipment investment by25/11/2013.Develop a layout that will maximise area gains 25/11/2013.

    SUCCSESS: Deliver the outcomes and benefits required Energise Gym throughimplementing deliverables that meet agreed requirement/s.

  • 8/12/2019 Presentation 111 (3)

    4/12

    Deliverables

    What does this project intend to do? Use organisational planning to execute Energise Health &

    Fitness Centre reconfiguration of gym equipment to meettheir current and future needs.

    What questions will it answer? Are there potential area efficiency gains to be found? Are

    there overused and idle machines? What problems will it solve? Areas of inefficiency in the gym, customer satisfaction.

  • 8/12/2019 Presentation 111 (3)

    5/12

  • 8/12/2019 Presentation 111 (3)

    6/12

    GANTT Chart

  • 8/12/2019 Presentation 111 (3)

    7/12

  • 8/12/2019 Presentation 111 (3)

    8/12

    Reflection - Positives

    Members were very cooperative Experiences and opinions were shared

    Everyone contributed there ideas Everyone lived reasonably close to one

    another

    Good mixture of strengths within the group

  • 8/12/2019 Presentation 111 (3)

    9/12

    Negatives

    Focused heavily on time. Conflicting tasks; modules, different courses

    etc... Communication was another negative; lack of

    contact at times, one main way ofcommunicating.

    More difficult to arrange meetings anddeadlines

  • 8/12/2019 Presentation 111 (3)

    10/12

    Potential Improvements

    Initial group member selection needed to bemore thorough.

    We could use the Belbin analysis beforeselecting a group.

    Look at starting the project earlier again. More frequent meetings.

  • 8/12/2019 Presentation 111 (3)

    11/12

    References

    Managing Successful Project with PRINCE 2 Operation Management (slack et al,2013)

    Belbin Team Roles The Essentials of Project Management (

    Lock,2007)

    The Project Manager (Newton,2005) Project management ( Field et al,1998 )

  • 8/12/2019 Presentation 111 (3)

    12/12

    Thanks for paying attention