Prepared By - Welcome to Environment · NABET Sl. No.- 121 as on 05.09.2017 OCT 11TH, 2017....
Transcript of Prepared By - Welcome to Environment · NABET Sl. No.- 121 as on 05.09.2017 OCT 11TH, 2017....
PRE-FEASIBILITY R E P O R T
FOR
PROPOSED 356KM LONG, 18 INCH MULTI PRODUCT PETROLEUM PIPELINE FROM BINA TO PANKI (KANPUR) & AUGMENTATION OF TANKAGES AT RECEIPT TERMINAL,
KANPUR
FOR
ENVIRONMENTAL CLEARANCE (VIDE MOEF GUIDELINES NO. J-11013/41/2006-IA.II(I) DATED 30TH DECEMBER 2010)
OF
M/S BHARAT PETROLEUM CORPORATION LTD., MUMBAI
Prepared By
PROJECTS & DEVELOPMENT INDIA LIMITED (A Govt. of India Undertaking)
PO: Sindri - 828122, Dist: Dhanbad (Jharkhand) NABET Sl. No.- 121 as on 05.09.2017
OCT 11TH, 2017
CONTENTS
CHAPTER DESCRIPTION PAGE NO. 0.0 Executive Summary 1 - 5 1.0 Introduction 6 - 6 2.0 Project Proposal 6 - 10 3.0 Project Benefits 10 - 10 4.0 Pipeline Route 11 - 13 5.0 Project & Process Description 14 - 21 6.0 Water & Power Requirement 21 - 22 7.0 Environmental Aspects 22 - 23 8.0 Land form, land use and land ownership 23 - 23 9.0 Manpower Requirement 23 - 23 10.0 R & R Plan 23 - 24 11.0 Project Schedule & Cost Estimates 24 - 26 12.0 Conclusion 27 - 27
Projects & Development India Limited, Sindri 1 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
EXECUTIVE SUMMARY INTRODUCTION Bharat Petroleum Corporation Limited (BPCL) with an equity base of Rs.723.08 Crore, is a
leading player in the Petroleum Sector in the country. BPCL has a major stake in BORL (Bharat
Oman Refineries Limited) Refinery at Bina with complete marketing rights. The Bina refinery is
operating at capacity of 6 MMTPA and is undergoing low cost expansion to 7.8 MMTPA.
EIA CONSULTANT BPCL entrusted M/s Projects and Development India Limited (PDIL), Sindri, Dhanbad (a QCI-
NABET accredited EIA consultant) for Environmental Clearance (EC) activities.
PROJECT PROPOSAL BPCL proposes to lay a 356 Km long cross-country multi-product petroleum pipeline of 18” dia.
from its Bina Dispatch Terminal to Panki POL terminal (Kanpur). The proposed Bina -Panki
pipeline (BPPL) will replace Rail wagon transport there-by yield savings in fuel expenditure on
transport as well as reduce traffic on Bina-Kanpur rail sector.
The proposed BPPL will be able to supply HSD, MS, SKO & ATF to this terminal. The total
volume (including 25% common carrier volume)assessed for transportation through Bina-Panki
pipeline is as follows:
Commissioning Year: FY 2020-21: 2.78 MMTPA
Phase-1: FY 2025-26: 3.45 MMTPA
The existing Panki Terminal will be augmented with a pipeline receipt terminal facilities
consisting of receipt manifold, Control room, inter-tank transfer pumping facilities, Tank wagon
loading facilities including pump house and automation, additional product tankage of 1,60,416
KL in Phase- I and 52,900 KL in Phase- 2.
PROJECT BENEFITS Pipelines are by far the most superior mode of transportation for petroleum products,as they
have considerable advantage in being able to move large quantities quickly, economically and
reliably over long distances with fewer associated impacts on the environment. It is for this
reason that pipeline transportation is preferred over road and railway transportation.
PIPELINE ROUTE Four Alternatives A, B, C & D are proposed from Bina Dispatch Terminal, Sagar, Madhya
Pradesh to Panki Receipt Terminal, Kanpur, Uttar Pradesh.
Projects & Development India Limited, Sindri 2 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
In view of Sand mining, more undulation, more steep terrain, Close vicinity of stone quarries and
lesser distance from Wild life sanctuaries boundaries, Alternative A& C is not recommended.
Alternative B & D routes are having same features except in view of road approachability for
construction, Operation & Maintenance. Alternative D is having more accessibility through road
than Alternative B hence, Alternative D is selected as most feasible route.
Forest Crossings Sl. No. Name of Forest Length in Km State 1 Balabahat P.F. 0.98 Uttar Pradesh 2 Balabahat R.F. 5.54 UP 3 RichhaMaholi R.F. 0.80 UP 4 Gauna R.F. 1.20 UP 5 BaidauraP.F. 0.08 Madhya Pradesh Total Forest Length in MP 0.08
Total Forest Length in UP 8.52 Grand Total 8.60
Pipeline Crossings
NH
RAILWAY SH Other Roads
Village Roads
River Canal Nala Foreign Pipeline
3 6 6 143 229 11 65 68 1 PROJECT FACILITIES a) Dispatch station at Bina including booster pumps (1Working + 1 Stand by), mainline pumps
(1Working+ 1Stand by), basket filter, metering, Corrosion Inhibitor dosing and scrapper
launcher along with associated facilities.
b) Intermediate pigging station (IPS) including scrapper Receiver/Launcher, filter, metering,
Corrosion Inhibitor dosing and associated facilities.
c) 355km (approx.) Cross Country pipeline from Bina to Panki.
d) Receipt terminal at Panki including scrapper receiver, filter, metering and associated
facilities.
e) Sectionalizing Valve Stations as per code and profile requirement.
f) Providing SCADA (Supervisory Control & Data Acquisition), LDS (Leak Detection
System),CP (Cathodic Protection) & ESD (Emergency Shut Down), Telecom and
Instrumentation system etc.
PROCESS DETAILS Operation & Control Philosophy a) Instrumentation and Control system shall be provided for safe and efficient control of
petroleum products pipeline.
Projects & Development India Limited, Sindri 3 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
b) PLC (programmable logic control) based control system shall be provided at Dispatch
stations, Receipt stations for the process interlocks / shutdown logic / MOV’s (motor
operated valve) operation and station monitoring whereas panel based monitoring/ control
system (Working on 48V DC) shall be provided at intermediate pigging station. Control
panels are provided for mounting the flow computers & other instruments.
c) SCADA (Supervisory Control and Data Acquisition) system is envisaged to ensure effective
and reliable control, management and supervision of pipeline from centralized location using
Remote Telemetry Units (RTU) along the pipeline route.
d) All essential control parameters of receipt terminals shall be integrated suitably inSCADA
system and PLC control.
e) All supply operations for the pipeline system shall be under the control of dispatch stations
which shall ensure the supply of the product at normal operating conditions. The dispatch
station shall make all necessary arrangements for the petroleum products dispatch and
ensure proper lining up of the system in conjunction with the receipt terminal.
f) The main pumping units will be shutdown automatically in the event of low suction pressure
or high discharge pressure, mechanical seal failure, high vibration, high casing temperature
etc.
g) Unit Control Panels (UCP) is envisaged at pumping stations. Pump start / stop / interlocks /
trip functions will be implemented in the pump UCP and this UCP will be interfaced to the
station PLC system for stop / trip / ESD from station / SMC and for status monitoring.
h) Corrosion Inhibitor dosing facilities shall be provided at dispatch station & IPS for controlling
corrosion in the pipeline. Electric Resistance probe for corrosion monitoring shall also be
provided.
i) The sump pump and / or slop transfer pump will be tripped in case of low liquid level in the
sump tank.
j) Thermal relief / safety valves shall be provided as per the requirement / standards such as
API 521 and shell DEP equivalent.
Fire Fighting Facilities i) Existing fire water network of the plant shall be extended to cover the facilities at DT and RT
under this project.
ii) Existing Fire water system is designed to fight two major fires anywhere within the plant as
per the provisions of OISD-116/OISD-117. Adequacy of existing fire water system has been
done to meet the OISD-116/OISD-117 requirements.
Projects & Development India Limited, Sindri 4 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
iii) Hydrant & Monitors:
Double outlet hydrants and monitors shall be provided at 30M interval around proposed
area. The ring main shall be provided above ground around proposed areas on independent
concrete sleepers.
iv) Fire fighting facilities for Mainline pump house:
The mainline pump houses are provided with fixed water spray system as per requirement
of OISD-116/OISD-117 and NFPA-15.
v) Adequate no. of portable fire extinguishers shall be provided at all strategic locations.
WATER & POWER REQUIREMENT Water requirement for the proposed BPPL project is very minimal to the tune of 20 KLD, mainly
for potable use by workers across the pipeline length, dispatch & receipt terminals and SV & IP
stations en-route. There will be one time requirement of 71,000 KL of water for hydro-testing of
the pipeline and tank augmentation at Panki, Kanpur.
Two nos. of HT plant feeder from existing HV switchboard (HT-223 at Substation No. 7) from
Bina Refinery shall be provided by Owner/BPCL to the battery limit of Dispatch Terminal at Bina
to meet the total power requirement (of new 6.6kV switchboard) at the Dispatch Terminal. At
Panki receiving terminal (RT), the incoming power shall be fed from existing emergency
switchboard so that there shall be no separate new Emergency DG for RT.
ENVIRONMENTAL ASPECTS The design approach built into the FEED to avoid/minimize emissions to the air is as follows:
• Fugitive emissions from valves will be avoided or minimized by selection of suitable valve
packing, seals etc.
• Fugitive emissions from pumps will be minimized by use of dual seals or seal-less pumps
when handling high vapour pressure and hazardous material
• Fugitive emissions from flanged connections will be reduced by minimizing the number of
flanged connections in high pressure service.
• Asbestos will be replaced with safer materials wherever possible.
• Only non-Ozone Depleting Substances will be used.
• The Pipeline is a closed loop system and no hydrocarbon will be released to open
atmosphere.
LAND FORM, LAND USE AND LAND OWNERSHIP The Right of User (ROU) for laying the pipeline will be acquired as per The Petroleum &
Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962 through the Competent
Projects & Development India Limited, Sindri 5 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Authority nominated for the project after notification in the Central Government Gazette and
payment of compensation shall be provided directly to the land owners as stipulated in the act.
MANPOWER REQUIREMENT About 400 people shall be employed directly/indirectly during the construction phase. The
requirement of manpower is expected to be met through internal deployment as well as thru
induction of competent manpower as per company’s rules. The existing manpower at Bina and
Panki (Kanpur) would be adequate to handle the operation phase.
R&R PLAN The ROU shall be acquired by BPCL for laying of pipeline and shall be handed over back to the
land owners for cultivation purpose. Compensation for loss of crop during construction phase shall
be paid as per Govt. Policy hence, the rehabilitation and resettlement is not applicable for this
project.
PROJECT SCHEDULE & COST ESTIMATES The project completion period has been estimated to be about 36 months after the grant of
authorization from PNGRB. The estimated cost of laying proposed 18” multi-product pipeline
and augmentation of tankages at receipt terminal is Rs.1542 Crores.
CONCLUSION The proposed pipeline will ensure cost-effective transportation and uninterrupted supply of
petroleum products from Bina to Panki (Kanpur) to cater to the North Indian market of UP,
Uttarakhand and Bihar. This will reduce Rail traffic between Bina to Kanpur and is envisaged to
yield investment returns more than 12%. There are no hilly terrains en-route the pipeline and the
forest area also is less dense calling for minimum cutting of trees etc. The river crossings are
minimum with sufficient space available on either ends to place machinery for boring/auguring
and mostly with a rocky bed that ensures that the pipeline will not be subjected to scouring and
there-by least damage to the pipeline during its operating life. The acquisition of land for ROU
shall be done by following the latest guidelines with least disturbance to land and compensation
to the project affected people as per Govt. guidelines. The pipeline does not call for any
demolition or re-alignment of any existing structure causing social disturbance.
Considering the above facts, the TOR may be granted for the proposed project for preparation
of EIA report as per the guidelines.
Projects & Development India Limited, Sindri 6 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
1.0 INTRODUCTION 1.1 BACKGROUND Bharat Petroleum Corporation Limited (BPCL) with an equity base of Rs.723.08 Crore,
is a leading player in the Petroleum Sector in the country. BPCL currently has
Refineries at Mumbai and Kochi with capacities of 12 MMTPA and 15.5 MMTPA
respectively. BPCL has a major stake in BORL (Bharat Oman Refineries Limited)
Refinery at Bina with complete marketing rights. The Bina refinery is operating at
capacity of 6 MMTPA and is undergoing low cost expansion to 7.8 MMTPA.
BPCL proposes to lay a 356 Km long cross-country multi-product petroleum pipeline of
18” dia. from its Bina Despatch Terminal to Panki POL terminal (Kanpur). BPCL has
already submitted its bid to PNGRB for the proposed pipeline and is the sole bidder
(after opening of the technical bid by PNGRB). The proposed Bina - Panki pipeline
(BPPL) will replace Rail wagon transport there-by yield savings in fuel expenditure on
transport as well as reduce traffic on Bina-Kanpur rail sector.
1.2 DFR & EIA CONSULTANT BPCL envisaged the Detailed Engineering Survey, Cadastral Survey and
miscellaneous works for Bina - Panki (Kanpur) Multiproduct Petroleum Pipeline
Project. In view of this, BPCL entrusted M/s. N. K.Buildcon Pvt. Ltd., Jaipur to carry out
survey works, M/s Engineers India Limited (EIL) to prepare Detailed Feasibility Report
(DFR)and M/s Projects and Development India Limited, Sindri, Dhanbad (a QCI-
NABET accredited EIA consultant) for environmental clearance activities.
2.0 PROJECT PROPOSAL BPCL proposes to lay 18" dia. Bina-Panki pipeline (BPPL) for transfer of petroleum
products viz. Motor Spirit (MS), High Speed Diesel (HSD), Superior Kerosene Oil
(SKO) and Aviation Turbine Fuel (ATF) from Bina Despatch Terminal to PankiPOL
Terminal (Kanpur) for distribution in the region of Kanpur, Mughalsarai, Aonla,
Shahjahanpur, Baitalpur, Gonda in Uttar Pradesh, Kathgodam in Uttarakhand and
Muzaffarpur in Bihar. The pipeline is proposed to pass through Sagar&Tikamgarh
districts of Madhya Pradesh (MP) and Lalitpur, Jhansi, Jalaun, Kanpur Dehat and
Kanpur Nagar districts of Uttar Pradesh (UP). The Right of Use (ROU) for laying the
pipeline will be acquired as per the Petroleum & Mineral Pipeline (Acquisition of Right
of User in Land) Act, 1962 through the Competent Authority nominated for the project
Projects & Development India Limited, Sindri 7 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
after notification in the Central Government Gazette and necessary compensation
shall be paid directly to the land owners as stipulated in the act. The pipeline will be
provided with 10 nos. of Sectionalizing Valve (SV) Stations and 1 no. of Intermediate
Pigging (IP) station along with dispatch and pumping station at Bina and receipt
terminals at Panki (Kanpur).
The proposed BPPL will be able to supply HSD, MS, SKO & ATF to this terminal. The
total volume (including 25% common carrier volume) assessed for transportation
through Bina-Panki pipeline is as follows:
Commissioning Year: FY 2020-21: 2.78 MMTPA
Phase-1: FY 2025-26: 3.45 MMTPA
The mainline / booster pumps with VFD shall be designed in such a way so as to meet
the Phase-1 throughput.
The existing Panki Terminal will be augmented with a pipeline receipt terminal facilities
consisting of receipt manifold, Control room, inter-tank transfer pumping facilities, Tank
wagon loading facilities including pump house and automation, additional product
tankage of 1,60,416 KL in Phase- I and 52,900 KL in Phase- 2. The Panki POL
terminal already has 30,400 KL of tankage for product storage. Total tankage will be
1,90,816 KL at the end of Phase-1 and2,43,716 KL at the end of Phase-2. The existing
Panki Terminal handles HSD, MS, SKO, ATF, Ethanol and Hexane. The proposed
BPPL will be able to supply HSD, MS, SKO & ATF to this terminal.Necessary EC for
the existing facilities have been accorded by State Environment Authority vide letter
ref. 69/Parya/SEAC/3287/2015/DD(Sh.) dt.13.04.2016.
The receipt terminal at Panki (Kanpur) is proposed to undergo tankage augmentation
(total 10 nos. tanks) with storage capacity of 2,13,316 KL. The details of storage
capacity shall be as below:
i. MS : 4 x 32,500 KL (FRT, 38m dia., 18m height)
ii. HSD : 4 x 20,400 KL (FRT, 48m dia., 18m height)
iii. Slop : 2 x 858 KL (CRT, 9m dia., 13.50m height)
Table- 1.1 Proposed Facilities at Panki Terminal
S. No. Facility Description 1 Pipeline Receipt Manifold 60m x 60m 2 Admin / Control Room Building 45m x 25m 3 Engineering Store 30m x 8m
Projects & Development India Limited, Sindri 8 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Figure-1.1 Schematic Arrangement for Bina-Panki Pipeline
Projects & Development India Limited, Sindri 9 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Table- 1.2 Pipeline Facilities
Sl. No.
Pipeline Parameters Bina Dispatch Terminal
Intermediate Pigging Station
Panki Receipt Terminal
1 Service Petroleum Products
Petroleum Products
Petroleum Products
2 Max Flow Rate, m3/hr 520x1.1 520x1.1 520x1.1
3 Design Pressure, Kg/cm2g
19 99 99
4 Allowable pressure drop, Kg/cm2g
1 (max for dirty condition)
1 (max for dirty condition)
1 (max for dirty condition)
5 Design Temp., 0C 65 65 65 6 MOC CS CS CS 7 Corrosion Allowance,
mm 3.0 3.0 3.0
8 Booster Pumps, m3/hr 520x1.1, (1+1) - - 9 Mainline Pumps, m3/hr 520x1.1, (1+1) - - 10 Flow meters, m3/hr 520x1.1, (1+1) 520x1.1, (1+1) 520x1.1, (1+1) 11 Control valves, m3/hr 520x1.1 520x1.1 12 Sump tank, m3 20 20 20 13 Pig Launcher For launching
intelligent pig Receiving intelligent pig
14 Basket filters 520x1.1, (1+1) 520x1.1 (1+1) 520x1.1 (1+1) 15 Service water 5 m3/hr
(intermittent), Service water at Bina will be fed from existing source of Bina Terminal
- 5m3/hr (intermittent)
16 Power Main incomer 2nos. feeders will be fed from Bina Refinery.
- From the existing Panki substation after enhancement of connected load / existing transformer
17 Sectionalizing valves
Provided as per ASME B 31.4. & OISD-141 and PNGRB regulations.
18 Pipeline roughness 45 microns
19 Pipeline Corrosion protection
Pipeline Internal Protection Suitable corrosion inhibitor injection system shall be provided for pipeline with suitable automated system for controlling dosing rate as per requirement. Pipeline External Protection Ø 3LPE external coating shall be provided. Ø Cathodic protection by impressed current for buried portion of pipeline shall be provided for PL.
Projects & Development India Limited, Sindri 10 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
20 Operating Hours 8000 Hrs./Annum 21 Basis for hydraulic
Calculation Pipeline hydraulics shall be carried out based on HSD with Sp. Gravity 0.820, dispatch temperature of 350C and Kinematics viscosity 2.1 at 40 0C at subsoil temperature of 25ºC and 8000 hrs per annum operation.
3.0 PROJECT BENEFITS Pipelines are by far the most superior mode of transportation for petroleum products,
as they have considerable advantage in being able to move large quantities quickly,
economically and reliably over long distances with fewer associated impacts on the
environment. It is for this reason that pipeline transportation is preferred over road and
railway transportation. The general advantages of pipelines with special reference to
the proposed pipeline are described below:
a. Pipeline, being underground, will involve lesser direct contact with the populace
thereby reducing its hazardous impact as well as provide better overall security.
b. Pipeline mode is mechanized and automatic with in-built safety features and
therefore less liable to human errors.
c. Due to easier and accurate monitoring of transfer rate & volume with on-line
instruments, the operator sitting in the control room can immediately detect any
leakage.
d. Pipeline transportation minimizes the detrimental environmental emissions
associated with other modes of transport. It completely eliminates noise pollution.
e. There is no loss of gas in transport resulting in conservation of energy source.
f. Pipeline transportation results in lower consumption of energy as compared to
other modes of transport.
g. Installation of pipeline will contribute to socio-economic growth and development of
the region.
h. Highest safety, most economical, energy efficient, environment friendly &minimum
handling loss amongst all modes of transportation of gas.
i. Continuous, uninterrupted, silent and smooth transfer of custody.
j. Reduction/mitigation of hazards & risks by performing HAZID & HAZOP during
detail design stage.
Projects & Development India Limited, Sindri 11 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
4.0 PIPELINE ROUTE Four Alternatives are proposed from Bina Dispatch Terminal, Sagar, Madhya Pradesh
to Panki Receipt Terminal, Kanpur, Uttar Pradesh. The alternative routes are
described briefly below:
Alternative –A
The proposed route will start from Bina and runs near via Semarkhedi, Bildho,
Dhudwani, Dhaura, Lalitpur, Mirchwara, Bar, Mohangarh, Sakrar, Pirona, Ait, Orai,
Chamari, Kamalpur, Sangasiyapur, Pur, SinghpurDewani, and Panki.
Alternative - B:
The Proposed route will Stat from Bina and will run near Balabahat, Banpur,
Kelgawan, Digaura, Ladhaura, Kharon, Ranipur, Gurusarai, Saidnagar, Orai, Kalpi,
Bhognipur, Pukhryan, Akbarpur and Terminates at Panki.
Alternative –C:
The Proposed Pipeline will run near Dhaura, Pali, Bar, Mohangarh, BiroraKhet,
Teharka, Tehrauli, Gurusarai, Saidnagar, Orai, Kalpi, Bhognipur, Pukhryan, Akbarpur
and Panki. The proposed alt. C follows the same route as of alternative A up to
khiriyabant. Thereafter, the pipeline route crosses NCR Jhansi-Manikpur branch Line.
Alternative C matches the Alternative B at Malehta before Betwa River.
Alternative – D:
The Proposed route will Stat from Bina and will run near Balabahat, Banpur,
Kelgawan, Digaura, Ladhaura, Kharon, Ranipur, Gurusarai, Saidnagar, Orai, Kalpi,
Bhognipur, Pukhryan, Akbarpur and Terminates at Panki. The proposed alt. D follows
the same route as of alternative B up to Lidhorakhas Village.
After analyzing four alternatives, it is observed that alternative A is much closer than
other alternative routes from Rajghat Reservoir & Mahavir Swami Wild life sanctuaries
which is environment sensitive areas and crossing forest stretch at downstream of
Betwa river crossing .forest boundary is starting immediately at downstream bank of
Betwa river at crossing location hence from execution point of view of River crossing
by HDD method may require extra efforts inside forest boundary or may increase the
length of HDD considering limit of crossing beyond forest boundary. Width of Yamuna
River at crossing location in Alternative A is more than other alternatives routes.
Alternative A passes through ravines near Yamuna River crossing which require extra
effort from construction point of view.
Projects & Development India Limited, Sindri 12 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Alternative B route is passing more farther distance from the Rajghat Reservoir &
Mahavir Swami Wild life sanctuaries than alternative A& C and having Lesser width of
major river i.e. Betwa& Yamuna at crossing locations.
Alternative C is having common route up to KM 190 with Alternative A and after that up
to KM 222 having route joining Alternatives A & B after that having common route up
to receipt terminal with Alternative B. Alternative C is Shortest length from BINA DT to
Panki RT.
Alternative D is having common route with Alternative B except deviated from
Alternative Bat Lidhora Khas and again matching the alternative B after crossing NH-
76.
In view of Sand mining, more undulation, more steep terrain, Close vicinity of stone
quarries and lesser distance from Wild life sanctuaries boundaries, Alternative A& C is
not recommended.
Alternative B & D routes are having same features except in view of road
approachability for construction, Operation & Maintenance. Alternative D is having
more accessibility through road than Alternative B hence, Alternative D (Ann.-I) is
selected as most feasible route.
4.1 Forest Details
Table- 1.3 Forest Crossings
Sl. No. Name of Forest Length in Km State 1 Balabahat P.F. 0.98 Uttar Pradesh 2 Balabahat R.F. 5.54 UP 3 RichhaMaholi R.F. 0.80 UP 4 Gauna R.F. 1.20 UP 5 BaidauraP.F. 0.08 Madhya Pradesh Total Forest Length in MP 0.08
Total Forest Length in UP 8.52 Grand Total 8.60
4.2 Pipeline Crossings
Table- 1.4 NH
RAILWAY SH Other Roads
VillageRoads
River Canal Nala Foreign Pipeline
3 6 6 143 229 11 65 68 1
Projects & Development India Limited, Sindri 13 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Figure-1.2
Fig.-1.3
Project location & Pipeline routes
Projects & Development India Limited, Sindri 14 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
5.0 PROJECT& PROCESS DESCRIPTION 5.1 TYPE OF PROJECT A cost-effective and uninterrupted supply of petroleum products to the end users is the
prime aim of the proposed project. This will reduce Rail traffic between Bina to Kanpur
and is envisaged to yield investment returns more than 12%. The pipeline is not
passing through any eco-sensitive areas.
The proposed 18” multi-product pipeline will carry petroleum products viz. Motor Spirit
(MS), High Speed Diesel (HSD), Superior Kerosene Oil (SKO) and Aviation Turbine
Fuel (ATF) from Bina to Panki (Kanpur). The proposed pipeline is designed for a
capacity of 6.0 MMTPA.
5.2 PROJECT FACILITIES Project (pipeline) battery limits:
g) Dispatch station at Bina including booster pumps (1Working + 1 Stand by),
mainline pumps (1Working+ 1Stand by), basket filter, metering, Corrosion Inhibitor
dosing and scrapper launcher along with associated facilities.
h) Intermediate pigging station (IPS) including scrapper Receiver/Launcher, filter,
metering, Corrosion Inhibitor dosing and associated facilities.
i) 355km (approx.) Cross Country pipeline from Bina to Panki.
j) Receipt terminal at Panki including scrapper receiver, filter, metering and
associated facilities.
k) Sectionalizing Valve Stations as per code and profile requirement.
l) Providing SCADA (Supervisory Control & Data Acquisition), LDS (Leak Detection
System), CP (Cathodic Protection) & ESD (Emergency Shut Down), Telecom and
Instrumentation system etc.
5.2.1 Bina Despatch Terminal The Petroleum products namely MS, HSD, SKO & ATF will be pumped from storage
tanks. To ensure adequate NPSH to mainline pumps, booster pumps are provided.
Basket filters are provided to remove the suspended particles. Flow is measured using
ultrasonic / mass flow meters which are provided along with flow computer. Density
meter is provided downstream of flow meters to measure the density of petroleum
product and to signal the batch. Signal from density meter is fed to the dual-stream
common flow computer. The Flow computer indicates the corrected volumetric flow
Projects & Development India Limited, Sindri 15 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
rate as well as the mass flow rate of the products to be transported. Corrosion Inhibitor
will be injected in the pipeline to prevent internal corrosion of the Pipeline. Corrosion
Inhibitor dosing tank and corrosion inhibitor dosing pumps have been provided for this
purpose.
One no. of sump tank have been provided for collection of drains from various points
such as header drains, scraper drain, line flushing, TSV discharge etc. and to cater the
requirement of separate storage of MS & HSD slops. The slops from these tanks can
be transferred back into the pipeline with the help of sump pump. The product will also
be routed to the upstream header of booster pumps. Pig launcher is provided at Bina
dispatch station for pigging operation. The entire Pipeline system is a close loop
system and no hydrocarbon will be discharged to open atmosphere.
5.2.2 Intermediate Pigging Station One Intermediate pigging station has been provided between Bina and Panki for
receiving and launching of pigs. Basket filters are provided for removing the solid
particles from the products. Flow is measured using ultrasonic / mass flow meters
which are provided along with flow computer. Density meter is provided downstream of
flow meters to measure the density of petroleum product and to signal the batch.
Signal from density meter is fed to the dual-stream common flow computer. The Flow
computer indicates the corrected volumetric flow rate as well as the mass flow rate of
the products to be transported. Scraper Receiver and Scraper Launcher are provided
for pigging operation. A sump tank is provided for collection of slops from various
points such as header drains, scraper drain, line flushing, TSV relief etc. The collected
slop is pumped back into HSD product passing through mainline with the help of the
sump pump and one slop transfer pump.
5.2.3 Panki Receipt Terminal Scraper Receiver is provided for pigging operation at Panki Receipt terminal. A sump
tank is provided for collection of slops from various points such as header drains,
scraper drain, line flushing, TSV relief etc. The collected slop is pumped into the slop
tanks with the help of the sump pump. The petroleum products will be transported to
the respective tanks at Panki receipt terminal. Further, necessary hook-up will be
taken at the Panki terminal for transporting of ATF also. Pipeline will be hooked-up to
product manifold for transferring MS/HSD/SKO/ATF to the storage tank. A provision for
Projects & Development India Limited, Sindri 16 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
filter coalesce is provided in the ATF line to remove any water droplets at the receipt
terminal.
5.2.4 PIPELINE COVER & BACKFILLING The pipeline shall be buried to ensure a minimum cover of 1.2 meter below natural
ground level except at Rocky Stretch/ river/ rail/ road/ canal/ waterways crossing
where minimum cover shall be as given below or as per the requirements of statutory/
local authorities, whichever is more stringent. The minimum pipeline cover for various
locations and crossings shall be as follows:
Table- 1.5
Details of Pipeline Cover Sl.No. Location Minimum Cover (m)
1 Industrial, Commercial, residential, Cultivated, agricultural and barren areas
1.2 (for Normal soil)
2 Rocky Terrain 1.0 3 Unlined Canals / Drains / Nalas (Open cut) 2.0 (for Normal soil)
1.5 (for Rocky strata) 4 River Crossings (Open cut method) River Crossings (Below Scour) 2.5 (for Normal soil)
1.5 (for Rocky strata) River Crossings (When scour level is not
known) 3.5 (for Normal soil)
1.5 (for Rocky strata) 5 Drain / ditches at road & railway 1.5 6 Horizontal Directional Drilling Rivers 2.5 (Below Scour depth)
or 5.0 (below bed)
whichever is lower National Highway 5.0 State Highway 5.0 Railway 5.0 Lined Canal 5.0
7 Lined Drains or or Lined Nalas 1.5 8 Uncased road crossings/station approach 1.2
Piping at stations shall be installed above ground at grade level with adequate
supporting. Piping shall be provided with sufficient flexibility for minimizing the
stresses.
Projects & Development India Limited, Sindri 17 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
5.3 PROCESS DETAILS The specification of petroleum products to be transported thru proposed pipeline shall
be as follows:
Table- 1.6 Product Specification
Sl.No.
Products Sp. Gravity Viscosity cSt Reid Vapour Pressure (RVP), Kg/cm2, max at38oC
Flash Point, (C) Abel, min
1 HSD 820-845 kg/m3 at 150C
2.1 at 400C 5.0 at 25 0C
0.1 37-66
2 MS 720-775 kg/m3 at 150C
0.51 at 37.80C 0.7 at 200C
0.61 < 10
3 SKO 780-830 kg/m3 at 150C
1.18 at 37.80C 1.53 at 20 0C
0.3 35
4 PCK 780-830 kg/m3 at 150C
1.18 at 37.80C 1.53 at 20 0C
0.3 35
PCK specification is similar to SKO the only difference is the percentage sulfur in pipeline compatible kerosene (PCK) which is 35ppm in PCK.
Table- 1.7
Permissible contamination level (% vol) Sl. No.
Main Product Contaminant (% Vol) MS SKO PCK** HSD
1 MS -- NIL 1* NIL 2 SKO NIL -- -- NIL 3 PCK NIL -- -- NIL 4 HSD NIL NIL 2 – * 2% if MS RON is 91.8 and more ** Normally all Euro 4 products are pumped with PCK (pipeline compatible kerosene) and not SKO. SKO is plugged between 2PCK batch.
5.3.1 Operation & Control Philosphy
k) Instrumentation and Control system shall be provided for safe and efficient control
of petroleum products pipeline.
l) PLC (programmable logic control) based control system shall be provided at
Dispatch stations, Receipt stations for the process interlocks / shutdown logic /
MOV’s (motor operated valve) operation and station monitoring whereas panel
based monitoring/ control system (Working on 48V DC) shall be provided at
intermediate pigging station. Control panels are provided for mounting the flow
computers & other instruments. All controls, recording and link to remote indicating
devices shall be through PLC located in the control rooms at dispatch station.
Projects & Development India Limited, Sindri 18 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
m) SCADA (Supervisory Control and Data Acquisition) system is envisaged to ensure
effective and reliable control, management and supervision of pipeline from
centralized location using Remote Telemetry Units (RTU) along the pipeline route.
The SMCS (SCADA monitoring and control station) for this pipeline shall be
provided. Real time leak detection system & Batch tracking integrated with SCADA
network will be provided. Intrusion detection and negative pressure wave based
leak detection system shall be explored.
n) All essential control parameters of receipt terminals shall be integrated suitably in
SCADA system and PLC control.
o) All supply operations for the pipeline system shall be under the control of dispatch
stations which shall ensure the supply of the product at normal operating
conditions. The dispatch station shall make all necessary arrangements for the
petroleum products dispatch and ensure proper lining up of the system in
conjunction with the receipt terminal.
p) The main pumping units will be shutdown automatically in the event of low suction
pressure or high discharge pressure, mechanical seal failure, high vibration, high
casing temperature etc. Very high station discharge pressures will also shutdown
the pumps. At the pump discharge, a pressure control valve shall be provided to
control the pipeline inlet pressure within MAOP of the existing pipeline. Low signal
selector is provided for selecting the low signal either from pump discharge or from
suction side pressure controllers. This pressure control valve normally controls the
pipeline inlet pressure and the pump suction pressure controller over rides the
discharge pressure controller if the suction pressure falls below the set value and
pipeline inlet pressure is maintained at pre-set value.
q) Unit Control Panels (UCP) is envisaged at pumping stations. Pump start / stop /
interlocks / trip functions will be implemented in the pump UCP and this UCP will
be interfaced to the station PLC system for stop / trip / ESD from station / SMC and
for status monitoring. Metering facilities shall be provided (1W+1S, at each station)
with bypass line at the dispatch station, IPS and receipt terminals with flow
computers to compute corrected volumetric flow rate as well as mass flow rate.
Flow meter shall be ultrasonic flow meter. Density and viscosity meter (1 no. at
each station) shall be provided at the dispatch terminal, IPS and at Panki receipt
terminal density meters at SBV and in terminal.
Projects & Development India Limited, Sindri 19 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
r) Corrosion Inhibitor dosing facilities shall be provided at dispatch station & IPS for
controlling corrosion in the pipeline. Operation of CI dosing pumps shall be local.
Corrosion monitoring system with corrosion probe and coupons located at 6 o’clock
position in the station piping shall be provided at two suitable locations for
monitoring corrosion in the pipeline. Electric Resistance probe for corrosion
monitoring shall also be provided.
s) The sump pump and / or slop transfer pump will be tripped in case of low liquid
level in the sump tank.
t) Thermal relief / safety valves shall be provided as per the requirement / standards
such as API 521 and shell DEP equivalent.
5.3.2 Shutdown of Pipeline Shutdown of any station along the pipeline may cause shutting down of the entire
pipeline operation. Shutdown of the pipeline, if required, can be done either manually
or through SMCS. However, Shutdown will be done manually only when the SMCS is
not working due to any reason. Any station willing to have shutdown will request
SMCS for the shutdown of the pipeline.
A. Shutdown of Pipeline through SMCS Shutdown of the pipeline, if required, will be done manually and through the SMCS.
Through SMCS shutdown can be done using prompts and without prompts.
B. Shutdown of Pipeline through SMCS without Prompts Pipeline can be taken into shutdown by actuation of a single command in the SMCS.
Here the operator is not required to follow the shut down steps. SMCS will follow all
the steps to take smooth shut down of pipeline.
C. Shutdown of Pipeline through SMCS with Prompts Pipeline can be taken into shutdown by actuation of sequence of prompts in the
SMCS. Here the operator is required to follow the shutdown steps to take smooth shut
down of pipeline. Pipeline can be taken into shutdown manually only when SMCS is
not working due to any reason. Here the operator is required to follow the shutdown
steps to take smooth shut down of pipeline.
E. Shutdown of Receipt Terminal In case of fire, a big leak or other such emergencies, it is important to shutdown the
receipt terminal at Panki. Pipeline can be isolated completely by closing the station
isolation valves by pressing ESD push buttons, which can be closed from SMCS. For
Projects & Development India Limited, Sindri 20 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
the shutdown of pipeline operator at receipt terminal will inform to the pipeline control
room. The fire alarm should be raised and appropriate steps should be taken.
5.3.3 Start - Up a. Initial start up Initially, pre-flush water is pushed by running booster pump by lining up the tank which
is having water. A first batching pig is then launched with water by running one booster
pump and pipeline is filled with water. Once backpressure starts increasing start one
Mainline Pump. After some time, another Booster and another Mainline Pump can be
started. As earlier second batching pig shall then be launched and further filling up of
water is done. Finally, insert third batching pig and operate the pumps on Petroleum
products to propel the pig trains. Thereafter, pig train is propelled by operating booster
and mainline pumps in series.
b. Start up after emergency shutdown Start Booster Pump with minimum flow bypass on auto mode. Start Mainline Pump.
Check suction pressure at the dispatch terminal. Once pressure reaches,
above5kg/cm2, ensure that flow is established up to tank at Panki. Once flow is
established, start corrosion inhibitor dosing subsequently.
5.3.4 Fire Fighting Facilities
vi) Existing fire water network of the plant shall be extended to cover the facilities at
DT and RT under this project.
vii) Existing Fire water system is designed to fight two major fires anywhere within the
plant as per the provisions of OISD-116/OISD-117. Adequacy of existing fire water
system has been done to meet the OISD-116/OISD-117 requirements. Fire water
network is laid in closed loops to ensure multi directional flow in the system. The
same shall be followed for the fire water network for the new area and same shall
be hooked up to the existing network at adequate places. 12” fire water header
size required upto proposed area from hook-up point.
viii) Hydrant & Monitors:
Double outlet hydrants and monitors shall be provided at 30M interval around
proposed area.
The ring main shall be provided above ground around proposed areas on
independent concrete sleepers.
ix) Fire fighting facilities for Mainline pump house:
Projects & Development India Limited, Sindri 21 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
The mainline pump house are provided with fixed water spray system as per
requirement of OISD-116/OISD-117 and NFPA-15.
x) Adequate no. of portable fire extinguishers shall be provided at all strategic
locations.
5.4 CODES & STANDARDS The following industry Codes & Standards shall be applicable for the proposed
pipeline:
Table- 1.8 Codes & Standards
Codes/Standards Title ASME B 31.4 Pipeline Transportation System for liquids & Slurries API 5L Specification for Line Pipe DIN EN ISO 21809 Part 1 External coatings for buries or submerged pipelines
used in pipeline transportation systems, Part 1: Polyolefin coatings (3-ayer PE & 3- layer PP)
ASME B 16.5 Pipe Flanges and Flanged Fittings: NPS ½ through NPS 24 metric/inch standards
ASME B 16.34 Valves Flanged, Threaded and Welding End ASME B 16.20 Metallic Gaskets for Pipe Flanges: Ring-Joint, Spiral
Wound and Jacketed ASME B 16.9 Factory Made Wrought Butt Welding Fittings MSS-SP-75 Specification for High Test Wrought, Butt Welding
Fittings MSS-SP-97 Integrally Reinforced Forged Branch Outlet Fittings-
Socket Welding, Threaded, and Butt-welding Ends ASME B 16.11 Forged Fittings, Socket Welded & Threaded ASME B 16.25 Butt Welding Ends
6.0 WATER& POWER REQUIREMENT Water requirement for the proposed BPPL project is very minimal to the tune of 20
KLD, mainly for potable use by workers across the pipeline length, dispatch & receipt
terminals and SV & IP stations en-route.
Two nos. of HT plant feeder from existing HV switchboard (HT-223 at Substation No.
7) from Bina Refinery shall be provided by Owner / BPCL to the battery limit of
Dispatch Terminal at Bina to meet the total power requirement (of new 6.6kV
switchboard) at the Dispatch Terminal. At Panki receiving terminal (RT), the incoming
power shall be fed from existing emergency switchboard so that there shall be no
separate new Emergency DG for RT. During construction phase, High Speed Diesel
(HSD) of approx. 250 L / day shall be used in DG sets. During operation phase, the
Projects & Development India Limited, Sindri 22 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
power consumption shall be 2.8 MWhr and met thru available State Electricity Supply
Company in the respective area. The system shall operate on constant V/F supply with
required voltage boost capability in low frequency mode of operation. Variable speed
drive shall be arranged so that it can be operated in an open circuit mode,
disconnected from the motor for start-up adjustments and trouble-
shooting/maintenance.
7.0 ENVIRONMENTAL ASPECTS The design of the proposed pipeline will be on minimum pollution basis and include all
the features required to ensure that control of all forms of pollution will comply with
regulatory & governmental requirements.
The design approach built into the FEED to avoid/minimize emissions to the air is as
follows:
• Fugitive emissions from valves will be avoided or minimized by selection of suitable
valve packing, seals etc.
• Fugitive emissions from pumps will be minimized by use of dual seals or seal-less
pumps when handling high vapour pressure and hazardous material
• Fugitive emissions from flanged connections will be reduced by minimizing the
number of flanged connections in high pressure service.
• Asbestos will be replaced with safer materials wherever possible.
• Only non-Ozone Depleting Substances will be used.
• The Pipeline is a closed loop system and no hydrocarbon will be released to open
atmosphere.
7.1 Waste Generation, Management & Disposal There is no continuous source of waste generation. The waste water in the form of
sanitary waste at stations shall be treated anaerobically and disposed off through septic
tanks.
The excavated soil generated while laying of pipeline shall be placed around and on top
of the pipe as soft soil / sand padding so that thickness of padding shall be at least 300
mm on top of pipe corrosion coating. Disposal of debris and surplus material to
designated disposal areas or designated place(s), as the case may, shall be carried out.
The proposed project falls under non-polluting activities. There will be no industrial
wastewater generation, no sludge/solid waste generation and no air pollutant generation
Projects & Development India Limited, Sindri 23 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
except by intermittent operation of the DG sets & Fire water pumps. Hence,
management of industrial waste is not applicable at this point.
Insignificant solid waste generation during operation of the pipeline in the form of oily
sludge during pigging cannot be ruled out. This shall be tested for determining its
characteristics and disposed off thru CPCB approved recyclers as per the current
practices of BPCL. Thus, any significant impact, practically immeasurable, on the nature
of soil and physical features due to spillage or disposal of solid wastes is not foreseen.
8.0 LAND FORM, LAND USE AND LAND OWNERSHIP The Right of User (ROU) for laying the pipeline will be acquired as per The Petroleum
& Minerals Pipelines (Acquisition of Right of User Inland) Act, 1962 through the
Competent Authority nominated for the project after notification in the Central
Government Gazette and payment of compensation shall be provided directly to the
land owners as stipulated in the act.
Pipeline will be laid in ROU land which has a width of 30m and ownership will remain
with the land owner. Land for Sectionalizing Valve (SV) station and Intermediate
Pigging (IP) station coming along the route of the pipeline will be procured. There
would be 11 such stations along the route (10 SV stations and 1 IP station) and the
land requirement will be approx. 2,500 m2 per SV station and approx. 11,000 m2 for the
IP station. Land for dispatch facility at Bina and receipt facility at Panki is already
available with BPCL.
Provision of Rs.66.28 Crore is kept for ROU acquisition and for crop & tree
compensation.
9.0 MANPOWER REQUIREMENT About 400 people shall be employed directly/indirectly during the construction phase.
The requirement of manpower is expected to be met through internal deployment as
well as thru induction of competent manpower as per company’s rules. The existing
manpower at Bina and Panki (Kanpur) would be adequate to handle the operation
phase.
10.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN The ROU shall be acquired by BPCL for laying of pipeline and shall be handed over
back to the land owners for cultivation purpose. Compensation for loss of crop during
Projects & Development India Limited, Sindri 24 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
construction phase shall be paid as per Govt. Policy hence, the rehabilitation and
resettlement is not applicable for this project.
11.0 PROJECT SCHEDULE & COST ESTIMATES 11.1 Project Schedule The pre-project activities that have to be completed before the physical execution of the
project are briefly enumerated below:
i) Approval of the project by BPCL- Approved ii) Appointment of owner’s project management team- Approved iii) Statutory approvals and licenses from all the concerned external agencies. iv) Financial clearance and commitment from financial institutions v) Preparation of EIA Study and clearance by State and Central Pollution Control
Boards vi) Risk Analysis Study vii) Survey and soil Investigation of the site viii) Appointment of Engineering Consultant (EC) ix) Approvals from the Chief Controller of Explosives and Chief Electrical Inspector x) Authorization from Petroleum and Natural Gas Regulatory Board (PNGRB). xi) All the above activities along with construction of compound wall and land
development activities have to be completed before the physical execution of the project.
The project completion period has been estimated to be about 36 months after grant of
Environmental Clearance.
Fig.: 1.3 Overall Project Schedule
Projects & Development India Limited, Sindri 25 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
The proposed Bina-Panki pipeline project is scheduled to be completed within 36
months from the date of receipt of statutory clearances including MOEFCC.
11.2 Cost Estimates
The basic assumptions made for working out the capital cost estimate are as under:
• Project shall be executed on EPCM Basis.
• Cost estimate is valid as of Apr-2017 price basis.
• No provision has been made for any future escalation
11.2.1 Financial Analysis Financial analysis has been carried out for calculating Transportation Tariff to achieve
internal rate of return (IRR) 12% on equity after tax.
Table- 1.9
Financial Parameters 1 Construction Period 3 years 2 Project life 25 years 3 Debt / Equity Ratio 1:5:1 4 Expenditure Pattern Equity Before Debt (B) 5 Loan Repayment Period 25 years 6 Moratorium Period 2 year 7 Interest on long term Loan 10.0 % 8 Capital Phasing (Total Capital) 8.1 1st Year of construction 15% 8.2 2nd year of construction 40 % 8.3 3rd Year of Construction 45 % 9 Capacity Build-up 9.1 1st Year 87 % 9.2 2nd Year 91 % 9.3 3rd Year 96 % 9.4 4th Year 100 % 10 Corporate Tax Rate 34.61 % 11 MAT 0%
The estimated cost of laying proposed 18” multi-product pipeline and augmentation of
tankages at receipt terminal is Rs.1495 Crores.
Revenue considered for financial analysis is based on client’s input is as follows:
Projects & Development India Limited, Sindri 26 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
Table- 1.9 Pipeline cost
Sl. No. DESCRIPTION Cost (Rs. Crore) 1 Capital Cost (Excluding Financing Charges,
Line Pack Cost, Working Capital Margin, Escalation During Implementation Phase)
1167.97
2 Variable Operating Cost (Annual) 11.84 3 Fixed Operating Cost (Annual) 27.98 4. Total Operating Cost (Annual) 39.82
The estimated cost of laying proposed 18" pipeline and augmentation of tankages at
receipt terminal is Rs.1495 Crores.
Table- 1.10 Revenue
Year of Operation Rs Lakhs 2021 20783 2022 22690 2023 24817 2024 26860 2025 29063 2026 31501 2027 34153 2028 37060 2029 40226 2030 43707 2031 47198 2032 50995 2033 52480 2034 54579 2035 56765 2036 59033 2037 61397 2038 63851 2039 66406 2040 69062 2041 71822 2042 74698 2043 77683 2044 80792 2045 84024
Projects & Development India Limited, Sindri 27 of 27
Pre-Feasibility report for TOR of Proposed 356km long, 18 inch Multi product petroleum pipeline from Bina to Panki (Kanpur) & augmentation of tankages at receipt Terminal, Kanpurof M/S BPCL, Mumbai
12.0 CONCLUSION The proposed pipeline will ensure cost-effective transportation and uninterrupted
supply of petroleum products from Bina to Panki (Kanpur) to cater to the North Indian
market of Kanpur, Mughalsarai, Aonla, Shahjhanpur, Baitalpur, Gonda (UP),
Kathgodam (Uttarakhand) and Muzaffarpur (Bihar). This will reduce Rail traffic
between Bina to Kanpur and is envisaged to yield investment returns more than 12%.
The pipeline is not passing through any eco-sensitive areas. The natural gradient of
the route means a high level at Bina and lower level at Kanpur is a technical
advantage with requirement of low power to transfer the product. There are no hilly
terrains en-route the pipeline and the forest area also is less dense calling for
minimum cutting of trees etc. The river crossings are minimum with sufficient space
available on either ends to place machinery for boring/auguring and mostly with a
rocky bed that ensures that the pipeline will not be subjected to scouring and there-by
least damage to the pipeline during its operating life. The acquisition of land for ROU
shall be done by following the latest guidelines with least disturbance to land and
compensation to the project affected people as per Govt. guidelines. The pipeline does
not call for any demolition or re-alignment of any existing structure causing social
disturbance.
Considering the above facts, the TOR may be granted for the proposed project for
preparation of EIA report as per the guidelines