Preliminary EA Scoping Comment and Response...
Transcript of Preliminary EA Scoping Comment and Response...
Resolution Copper Mining Baseline Hydrological and Geotechnical Data Gathering Activities
Preliminary EA Scoping Comment and Response Report
Tonto National Forest Globe and Mesa Ranger Districts Pinal County
March 2015
United States Department of Agriculture Forest Service Southwestern Region
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color,
national origin, gender, religion, age, disability, political beliefs, sexual orientation, or marital or family status. (Not all
prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program
information (Braille, large print, audiotape, etc.) should contact USDA’s TARGET Center at (202) 720-2600 (voice and TDD).
To file a complaint of discrimination, write USDA, Office of the Assistant Secretary for Civil Rights, 1400 Independence
Avenue, SW, Mail Stop 0115, Washington, DC 20250 or call (202) 720-3808 (voice and TDD). USDA is an equal opportunity
provider and employer.
Printed on recycled paper.
Digital copies are available for download from the Tonto National Forest website.
If printing a copy, please consider the environment and use recycled paper.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
1
INTRODUCTION
Public scoping for the project started with the publication of the Legal Notice in the Arizona Silver Belt
on May 21, 2014 and the Arizona Capitol Times, the newspaper of record on May 23, 2014. The notice
informed the public of Resolution’s Baseline Plan and requested public comments from May 24 to
June 23, 2014. The scoping letter with attachments was mailed to approximately 358 people, including
representatives from approximately 38 Tribal and governmental agencies. Written comments were
submitted via U.S. mail, e-mail, fax, and during the public open house held on June 10, 2014 at the
Superior Junior/Senior High School where a court reporter was available to receive verbal comments. In
total, 226 submissions were received of which 73 were unique, 152 were form letters (some with unique
comments), and 1 was a petition from Queen Valley residents.
This report is organized into three tables. Table 1 is an index that lists, in alphabetical order by last name
or organization name, all commenters, the organizations they represent, letter number, and corresponding
page in the report for the response. Table 2 contains all public scoping comments received during the
scoping period and the Forest’s responses. Table 3 contains all public comments received outside the
scoping period and the Forest’s responses. Some comment letters did not include comments, or indicated
they have no comment at this time, and are identified in the report as “No comments”. All comments
received were reviewed and evaluated for issues, which resulted in modifications to the Proposed Action
and/or development of alternatives.
The proposed Plan is subject to the Project-Level Pre-decisional Administrative Review Process under
36 CFR Part 218, Subparts A and B. Those entities who provided specific written comments during
scoping, or who provide specific comments during any other instance where the responsible official is
seeking written comments, such as the comment period on the preliminary EA, may file an objection.
Consistent with 36 CFR Part 218.2, specific written comments should be within the scope of the proposed
action, have a direct relationship to the proposed action, and must include supporting reasons for the
responsible official to consider. Submission of timely, specific written comments is a prerequisite for
eligibility to file an objection under 36 CFR Part 218.
The Preliminary Environmental Assessment (EA) and this Preliminary EA Scoping Comment and
Response Report are available on the project website (http://www.fs.fed.us/sopa/forest-
level.php?110312).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-1
Table 1: Alphabetical List of Commenters, Organizations They Represent, Letter
Numbers, and Starting Page
Name/Organization Letter Number Starting Page
Adams, Micah Letter 235 3-4
Albright, Dale Letter 235 3-4
Algen, Dale Letter 235 3-4
Alger, Sherry Letter 235 3-4
Amendt, Herb Letter 235 3-4
Anderson, Donna Letter 235 3-4
Anderson, Wayne Letter 235 3-4
Andresen, Lori Letter 37 2-17
Arandelovic, Janice Letter 101 2-22
Armstrong, Cheryl Letter 235 3-4
Armstrong, Gary Letter 235 3-4
Arneson, Carla Letter 112 2-23
Arnst, Diane Letter 157 2-97
Arvago, Raymond Letter 235 3-4
Avanti, Annemarie Letter 80 2-20
Averett, Terry Letter 235 3-4
Bach, Mel Letter 235 3-4
Bach, Pat Letter 235 3-4
Bainbridge, Dennis Letter 235 3-4
Balderas, Ruben Letter 156, 187 2-97, 3-2
Baqinski, Jenny Letter 235 3-4
Barchas, Sarah Letter 166 3-1
Barin, Jr., Eugene Letter 235 3-4
Barrett, Sylvia Letter 135 2-28
Barstap, Vernon D. Letter 235 3-4
Bastek, Christopher Letter 103 2-22
Bealler, Betty Letter 235 3-4
Bealler, Steve Letter 235 3-4
Becker, Mike Letter 235 3-4
Begalke, Donald Letter 151, 206 2-45, 2-146
Beltrane, Edward Letter 208 2-146
Benallie, Jr., Larry Letter 18 2-9
Benedetto, Walter Letter 235 3-4
Bensten, Russ Letter 235 3-4
Bethka, Lorraine Letter 217 2-146
Betty, Jacobson Letter 235 3-4
Bever, Victoria Letter 19 2-10
Bfowl, Phil Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-2
Name/Organization Letter Number Starting Page
Bickel, Bettina Letter 49 2-18
Binder, Fred Letter 66 2-19
Bingham, Brent Letter 86 2-21
Bittick, Cynthia Letter 79 2-20
Blake, Bonnie Letter 235 3-4
Blake, R Gene Letter 235 3-4
Blakeman, C.A. Letter 235 3-4
Blakeman, David Letter 235 3-4
Blakeram, Charles A Letter 235 3-4
Blei, Scott Letter 235 3-4
Bogard, James Letter 235 3-4
Bogard, Robert Letter 235 3-4
Bouneson, Robert Letter 235 3-4
Bourke, Jessie Letter 162 2-105
Brooks, Michael Letter 235 3-4
Brown, Mike Letter 235 3-4
Brown, Phil Letter 235 3-4
Bryant, Leslie Letter 130 2-25
Budenholzer, Alfred V Letter 235 3-4
Byrum, Dale Letter 235 3-4
Cah, Rall Letter 235 3-4
Cairnes, George Letter 235 3-4
Campbell, Matthew Letter 235 3-4
Campbell, Ryan Letter 235 3-4
Campos, Javier Letter 143 2-34
Capps, Jimmy Letter 235 3-4
Carpenter, Eric Letter 235 3-4
Carpenter, Karen Letter 235 3-4
Carpenter, Scott L. Letter 235 3-4
Carrothers, Barbara Letter 235 3-4
Casillas, Rudy Letter 93 2-21
Chadwick, Karen Letter 161 2-104
Champagne, Carla Letter 165 2-105
Champagne, Gene Letter 209 2-146
Chapman, Jeff Letter 235 3-4
Christian, Karen Letter 74 2-20
Clark, James Letter 235 3-4
Coleman, Edwin Letter 59 2-19
Conner, Charles Letter 201 2-145
Contwell, Al Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-3
Name/Organization Letter Number Starting Page
Cook, Chadd Letter 235 3-4
Coppinger, Gene Letter 235 3-4
Coryell, Mark Letter 46 2-18
Cottens, Jerry Letter 235 3-4
Cotton, Josephine Letter 235 3-4
Croak, James Letter 235 3-4
Crosby, G Letter 235 3-4
Crouchlits, Jennie Letter 235 3-4
Crowley, Kenneth Letter 44 2-18
Cruz, Richard Letter 104 2-22
D, Cathy Letter 38 2-17
Dalton-Rabago, Pamela Letter 6 2-2
Dannds, Jerry L. Letter 235 3-4
Davis, Robert B Letter 235 3-4
Dearstyne, William Letter 226 2-147
Dengak, Marie Letter 235 3-4
Denman, Nancy Letter 235 3-4
Denman, Peter Letter 235 3-4
Desrosiers, Donna Letter 75, 120 2-20, 2-24
Devon, Zona Letter 235 3-4
Dilley, Jean (WA) Letter 116 2-23
Dilley, Jean (AZ) Letter 235 3-4
Dillinger, Dolly A Letter 235 3-4
Dyer, Dawn Letter 204 2-145
Eckart, Kathryn Letter 235 3-4
Eckart, Red Letter 235 3-4
Egner, Bill Letter 235 3-4
Elden, Wanda L. Letter 235 3-4
Ellis, James Letter 100 2-22
Elton, Wallace Letter 115 2-23
Enger, William Letter 235 3-4
Erb, Glenn Letter 235 3-4
Erick, Charles Letter 235 3-4
Evans, L&L Letter 235 3-4
Exe, Richard Letter 235 3-4
Fagerquist, Larry Letter 235 3-4
Featherstone, Roger Letter 15, 155, 180, 181, 163 2-5, 2-47, 2-105, 3-2
Finley, Pat Letter 235 3-4
Finstrom, Matt, Holly & Ariel Letter 149 2-38
Fitschen, Carole Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-4
Name/Organization Letter Number Starting Page
Fitschen, Robert Letter 235 3-4
Fitzner, Lisa E. Letter 215 2-146
Flowers, Christopher Letter 202 2-145
Flowers, Taira Letter 87 2-21
Flynn, Letter 235 3-4
Frahm, Larry Letter 235 3-4
Frederiksen, Curt Letter 235 3-4
Freeman, Nancy Letter 150 2-38
Freeman, Nancy (AZ) Letter 235 3-4
Frye, Bob Letter 147 2-36
Frye, Bob (AZ) Letter 235 3-4
Frye, Shelley Letter 235 3-4
Fugate, Peggy Letter 220 2-147
Fura, David Letter 47 2-18
Gaede, Marnie Letter 48 2-18
Gavelek, Joe Letter 231 3-3
Geisenhoff, Earl J. Letter 235 3-4
Gennarelli, Diane Letter 128 2-25
George, James Letter 235 3-4
Gilbert, Mark Letter 235 3-4
Gillis, Carl Letter 235 3-4
Girard, Jackie Letter 235 3-4
Glover, Nanette Letter 219 2-146
Gonsalves, Gail Letter 126 2-24
Goodale, Donna Letter 31 2-17
Goodrich, Gary Letter 235 3-4
Gordon, Janine Letter 142, 213 2-32, 2-146
Gorton, Charles Letter 235 3-4
Graffagnino, Mary Ann and Frank Letter 29 2-16
Graham, Keith Letter 235 3-4
Grantham, Shawna Letter 235 3-4
Gray, Carolyn Letter 136 2-28
Gray, James Letter 133 2-26
Greene, Jeanine Letter 132 2-26
Grueninger, Tim Letter 235 3-4
Guerrero, Barbara Letter 53 2-19
Guidi, Rita Letter 33, 88, 125 2-17, 2-21, 2-24
Gurnow, Mark Letter 10 2-2
Guzman, Albo Letter 7 2-2
Haley, John Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-5
Name/Organization Letter Number Starting Page
Halling, Allen L. Letter 235 3-4
Hammer, Michael Letter 235 3-4
Hampton, Kevin Letter 235 3-4
Hanna, Neal Letter 45 2-18
Hansen, Chris Letter 235 3-4
Harper, Gordon Letter 235 3-4
Harris, Kirk Letter 235 3-4
Harris, Robert & Debra Letter 56 2-19
Hartigan, Zay Letter 144 2-34
Heidbrink, Leslie Letter 235 3-4
Heidinger, Richard Letter 140 2-31
Heiselt, Gabby Letter 235 3-4
Heiselt, James Letter 235 3-4
Henry, John Letter 235 3-4
Henry, Joyce Letter 235 3-4
Hernandez, Tiffany Letter 235 3-4
Heron, Veronica Letter 35 2-17
Hester, Vicki Letter 198 2-144
Hickman, Vanessa Letter 190 2-140
Higley, Tammy Letter 235 3-4
Hill, Ginger Letter 210 2-146
Hill, Sandra Letter 235 3-4
Hillman, David Letter 235 3-4
Hillner, J.C. Letter 235 3-4
Hing, Michael Letter 11 2-3
Hoboat, David L. Letter 235 3-4
Hodiak, Diane Letter 42 2-18
Hoeffling, Eugene Letter 235 3-4
Hoey, Don Letter 235 3-4
Hood, Chris Letter 167 2-105
Hood, Gary Letter 235 3-4
Huckfolda, Dick Letter 235 3-4
Huffs, W. Larry Letter 235 3-4
Huggenvik, Jodi Letter 92 2-21
Hughes, Hannah Letter 235 3-4
Hughes, Kevin Letter 235 3-4
Hunt, Paul T. Letter 235 3-4
Ingram, Gary Letter 235 3-4
Jacobs, Sky Letter 188 3-2
Jacobson, Allen L. Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-6
Name/Organization Letter Number Starting Page
Jarrell, Joseph Letter 159 2-104
Jeffrey, Anna Letter 139 2-30
Jenkins, Annette Letter 235 3-4
Johnson, Joc Letter 235 3-4
Jones, Johanna Letter 106 2-22
Jordan, Gary Letter 235 3-4
Karr, Mary Letter 235 3-4
Kay, Greg Letter 211 2-146
Keck, Aubrey Letter 26 2-16
Keeime, Desirey Letter 235 3-4
Keimis, Jeff Letter 235 3-4
Kelley, Lawrence Letter 24, 196 2-16, 2-144
Kellogg, Quinn Letter 129 2-25
Kelly, Daniel E. Letter 235 3-4
Kelmis, Jeff Letter 235 3-4
Kendall, Sandra Letter 235 3-4
Kimby, Steven E. Letter 235 3-4
Kittredge, David Letter 235 3-4
Kittredge, Karen Letter 235 3-4
Klopatek, Carole Letter 168, 169, 170 2-105, 2-124
Koepike, Jay Letter 235 3-4
Koetter, Tim Letter 235 3-4
Kozma, John Letter 214 2-146
Kravcov Malcolm, Karen Letter 25, 114 2-16, 2-23
Krieg, Jim and Kathy Letter 137 2-29
Krieg, John (AZ) Letter 20 2-10
Krieg, John (AK) Letter 235 3-4
Krieg, Karen Letter 235 3-4
Krieg, Kathy Letter 235 3-4
Krumm, Jim Letter 235 3-4
Kurtz, Andy Letter 8 2-2
Kuwanwisiwma, Leigh Letter 195 2-143
Lambertus, Sharon Letter 222 2-147
Lance, Jerry Letter 235 3-4
Lape, Terry Letter 235 3-4
Law, Goeff Letter 235 3-4
Lee, Michael C. Letter 235 3-4
Leisestad, Jerry Letter 235 3-4
Leslie, Darlene Letter 227 2-147
LeStarge, Wendy Letter 145 2-35
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-7
Name/Organization Letter Number Starting Page
Levendowski, Merrilee Kinney and Dan Letter 134 2-27
Lewis, Barnaby V. Letter 18, 194 2-9, 20142
Lintecum, Kelly Letter 228 2-148
Livingston, Ron Letter 81 2-20
Longfield, Sherrill Letter 235 3-4
Lopez, Sam Letter 235 3-4
Losey, Kevin E. Letter 131 2-26
Luptak, Roger Letter 235 3-4
Lytle, Heidi Letter 108 2-22
Macias, Tom Letter 172 2-124
Magill, Sue Letter 107, 223 2-22, 2-147
Marks, Darrell Letter 203 2-145
Marks, Makaius Letter 94, 95 2-21
Marrow, Michael J. Letter 235 3-4
Matty, Chris Letter 235 3-4
Matty, George Letter 235 3-4
McCauley, Joshua Letter 123 2-24
McCollister, Michael Letter 160 2-104
McDonald, Thomas Letter 21, 70 2-11, 2-20
McDonald, Tom Letter 178 2-133
McFarland, Dennis A Letter 235 3-4
Mckee, Derek Letter 98 2-21
McMillan, Don Letter 235 3-4
McMullen, Patrick Letter 176, 185 2-125, 2-139
McQuillan, Barbara Letter 235 3-4
Messenger, Red Letter 235 3-4
Metivier, Pam Letter 91 2-21
Michaud, Rene Letter 235 3-4
Micksch, Carol Letter 235 3-4
Micksch, Greg Letter 235 3-4
Miller, Georgia A. Letter 235 3-4
Miller, Linda Letter 36 2-17
Miller, Russ Letter 179 2-133
Miller, Tom Letter 235 3-4
Millman, Eric Letter 235 3-4
Miniuk, Jacqueline Letter 28, 89 2-16, 2-21
Miniuk-Sperry, Colleen Letter 55 2-19
Mischell, Robert Letter 235 3-4
Mischell, Trudy Letter 235 3-4
Montgomery, Esq., Susan B. Letter 154, 186 2-47, 2-139
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-8
Name/Organization Letter Number Starting Page
Monti, Frank Letter 235 3-4
Montijo, Frank Letter 235 3-4
Morgan, Jerold G. Letter 235 3-4
Morrow, Kristen Letter 235 3-4
Moser, Paul Letter 54 2-19
Most, Terry Letter 235 3-4
Muñoz., Henry C. Letter 141 2-31
Murphy, Carolyn Letter 235 3-4
Nash, Bill Letter 235 3-4
Nelson, Geraldine Letter 235 3-4
Nelson, Gordon Letter 235 3-4
Nelson, Ken Letter 235 3-4
Neuesley, John M. Letter 235 3-4
Neumann, Renee Letter 58 2-19
Noncutt, Grant Letter 235 3-4
Norcutt, Richard Letter 235 3-4
Nordan, Laura Letter 171 2-124
Norman, Bob Letter 235 3-4
Norman, Clayton Letter 110 2-22
North, Chad Letter 235 3-4
Nosie, Vanessa Letter 224 2-147
Novak, Vic Letter 235 3-4
O’Connor, Cornelia Letter 84, 118 2-24
O’Neill, Vicki Letter 99 2-22
O’Rourke, Terry Letter 235 3-4
Ogo, Linda Letter 234 3-3
Olson, C.R. Letter 235 3-4
Orsofield, Charles N Letter 235 3-4
Oxford, Rex Letter 57 2-19
Pastor, Mike Letter 174 3-1
Pavelek, Joan Letter 235 3-4
Pavelek, Ken Letter 235 3-4
Paxton, Harold Letter 78 2-20
Payne, Guy Letter 235 3-4
Peat, Evelyn Letter 43 2-18
Peddle, J Letter 235 3-4
Pedersen, Annette Letter 63, 82 2-19, 2-20
Peltier, Drew Letter 60 2-19
Pemberton, Celeste Letter 189 2-140
Pepin, Cheryl Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-9
Name/Organization Letter Number Starting Page
Pepin, Larry Letter 235 3-4
Perea, Orlando Letter 182 2-136
Perkins, Bonnie Letter 235 3-4
Perry, Kenny Letter 235 3-4
Petersburg, David K. Letter 235 3-4
Peterson, Claire Letter 235 3-4
Phillips, Sally Letter 235 3-4
Phillips, Sean Letter 65 2-19
Pike, Naelyn Letter 83 2-21
Pilgrim, Barry Letter 235 3-4
Pina, Loren Letter 216 2-146
Plath, Greg Letter 235 3-4
Plath, Jim Letter 235 3-4
Porter, John Letter 235 3-4
Potter, Leonard A Letter 235 3-4
Pottyjohn, Larry Letter 235 3-4
Prchal, Steven Letter 30 2-16
Puddefoot, Jean Letter 235 3-4
Quillen, Robert Letter 235 3-4
Quinlan, Jim Letter 76 2-20
Rachel, Bernard Letter 235 3-4
Rafoth, Richard Letter 111 2-22
Rambler, Terry Letter 158, 175, 177 2-97, 2-124, 2-133
Rangel, Manuel Letter 27 2-16
Reeves, Joe Letter 235 3-4
Reinhard, Matthew Letter 90 2-21
Reynolds, Lyle Letter 235 3-4
Reynolds, Troy Letter 5, 14 2-1, 2-5
Richards, Christopher Letter 64 2-19
Richards, Pat Letter 230 2-148
Richter, John L Letter 235 3-4
Ringler, Jim Letter 235 3-4
Rings, Sally Letter 68 2-20
Robb, Natalie Letter 72 2-20
Robinson, C Dennis Letter 235 3-4
Rodriquez, Carlos Letter 235 3-4
Romero, Greg Letter 9 2-2
Romero, Richard Letter 235 3-4
Roth, Roger Letter 235 3-4
Royer, Michael Letter 119 2-24
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-10
Name/Organization Letter Number Starting Page
Rozanki, Tyler Letter 235 3-4
Rubach, Will Letter 34, 77 2-17, 2-20
Russell, Wendy Letter 225 2-147
Russell, William Letter 235 3-4
S, Fred Letter 235 3-4
S, J Letter 212 2-146
Sanchez, Manuel G. Letter 235 3-4
Santori, Nancy Letter 113 2-23
Sarish, Allan Letter 235 3-4
Sauer, A Letter 39, 40, 96 2-17, 2-21
Scanlon, Peter Letter 221 2-147
Schanz, Dan Letter 235 3-4
Schepers, Stan Letter 13 2-3
Schmidt, Barbara Letter 235 3-4
Schmidt, Barbara M Letter 235 3-4
Schmidt, Frederick E Letter 235 3-4
Schmidt, Joyce E. Letter 235 3-4
Schroeter, Rogil Letter 62 2-19
Senman, Gary J Letter 235 3-4
Sherry, Constance Letter 122 2-24
Shicks, Troy Letter 235 3-4
Shields, David and Kathleen M Letter 235 3-4
Shiley, Brandon Letter 235 3-4
Shores, Michael Letter 218 2-146
Sinclair, Marion Letter 235 3-4
Sinclair, Merle Letter 235 3-4
Sinclair, Patti Letter 235 3-4
Sloan, Dylan Letter 207 2-146
Small, Marsha Letter 121 2-24
Smith, Daniel Letter 235 3-4
Smith, Myron Letter 12 2-3
Smith, Rich Letter 23 2-15
Snodgrass, Rick Letter 235 3-4
Sohocki, D. Letter 235 3-4
Sohocki, Dennis Letter 235 3-33-4
Sohocki, Dennis and Dena Letter 200, 232 2-144, 3-3
Soldan, Ted Letter 148 2-38
Sorenson, Nancy Letter 235 3-4
Sorenson, Robert Letter 235 3-4
Sorenson, Robert and Nancy Letter 146 2-35
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-11
Name/Organization Letter Number Starting Page
Spellman, Don Letter 235 3-4
Spellman, Kathy Letter 235 3-4
Spragett, Cedra & Eric Letter 32 2-17
Steckline, Robert T Letter 235 3-4
Stegman, Bart Letter 50 2-18
Steinmetz, Frank Letter 199 2-144
Sternquist, Dennis A Letter 235 3-4
Steuter, Don Letter 205 2-146
Stevens, Dorothea Letter 153 2-47
Stokes, Ken Letter 235 3-4
Stone, Tim (WA) Letter 117 2-24
Stone, Tim (AZ) Letter 235 3-4
Strayer, Becky Letter 235 3-4
Strong, Daryl Letter 235 3-4
Sullivan, Tim Letter 235 3-4
Summers, Shannon Letter 152 2-46
Swanson, Lesly Letter 164 2-105
Taegen, TC Letter 235 3-4
Taunt, Linda Letter 145 2-35
Taylor, David Letter 235 3-4
Terrill, Michael Letter 235 3-4
Thiel, Dianne Letter 233 3-3
Thomas, Albert Letter 235 3-4
Titmus, Andrew Letter 235 3-4
Torrez, Juan Letter 235 3-4
Tucker, Kathleen Letter 17, 71 2-8, 2-20
Tuttle, Carol Letter 235 3-4
Tuttle, Kenn Letter 235 3-4
Urman, Michael R Letter 191, 192 2-141
Valder, Carolina Letter 61 2-19
Valencia, Ruth Letter 173 3-1
Vannulli, Dominique Letter 235 3-4
Vaunvelli, Dominic Letter 235 3-4
Verhoef, Darrell Letter 235 3-4
Vernon, Alton Letter 235 3-4
Vernon, Bonnie Letter 235 3-4
Verty, Tom Letter 235 3-4
Vickery, Gary Letter 235 3-4
Waddell, Sonny Letter 235 3-4
Waddell, Tristen Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 1-12
Name/Organization Letter Number Starting Page
Warren, Barbara Letter 52 2-18
Warren, John W. Letter 235 3-4
Warrington, Malcolm Letter 235 3-4
Waters, Kathy Letter 235 3-4
Waters, Paul Letter 235 3-4
Watkins, Jackie Letter 109 2-22
Watson, Jason Letter 235 3-4
Weaver, Reece Letter 235 3-4
Webster, Darryl Letter 235 3-4
Weil, Charles Letter 41 2-17
Weise, Karen Letter 235 3-4
Weise, Ken Letter 235 3-4
West, Joanne Letter 102 2-22
Whitman, Frances Letter 85, 127 2-21, 2-24
Wilkey, James Letter 105 2-22
Wilkinson, Cliff Letter 51 2-18
Williams, James Letter 235 3-4
Williams, Margaret Letter 235 3-4
Wilson, Chris Letter 235 3-4
Wilson, Laura Letter 235 3-4
Wilson, Melissa Letter 229 2-148
Wilson, Russell Letter 235 3-4
Wise, John Letter 124 2-24
Witzeman, Bob Letter 183, 184 2-136, 2-138
Wolff-Krauter, Kelly Letter 22, 72 2-12, 2-20
WongCarter, Austin Letter 73 2-20
Wright, David Letter 235 3-4
Wright, David Thomas Letter 193 2-142
Wright, Jennifer Letter 235 3-4
Yeargain-Williams, Peggy Letter 67, 97 2-20, 2-21
Years, Thelma Letter 235 3-4
York, Jared Letter 235 3-4
York, Jesse Letter 235 3-4
Yowes, Howard Letter 235 3-4
Zongker, Jane C. Letter 235 3-4
Zongker, Layle K. Letter 235 3-4
Zuke, Lee Letter 235 3-4
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-1
Table 2: Responses to Public Scoping Comments Submitted During the Public Scoping Period,
May 24, 2014 through June 23, 2014
Comment
Number Comment Response
Letter 5 - Reynolds, Troy
1 my son and I own a small 40 acer placer claim,
Superstition #3 AMC 406084 1S 12E sec31 . Will this
project take away any of our placer rights?
Consistent with Forest Service Manual 2800, Chapter 2810,
Section 2813.11, the locator of a mining claim acquires rights against
other possible (peaceable) locators when the locator has complied with
the applicable Federal and State laws. Where more than one locator is
involved on the same land, Forest Service actions should be impartial
to all known locators of that land, as the controversy is the
responsibility of the locators, not the Forest Service, to settle.
2 concerns about road access? during and after project. All Baseline activities would be accessed using existing forest roads,
previously disturbed areas, and short term temporary access roads
(Section 2.3 preliminary EA). Improvements would be necessary along
portions of existing forest roads and previously disturbed areas. Road
improvements include widening the roadway and widening turns to
allow access for all equipment. Short term temporary access roads
would not require construction activities because a tracked drill rig and
light duty truck would access the site only once. Reclamation would be
implemented immediately after use for short term temporary access
roads and previously disturbed areas would be reclaimed when
monitoring activities have concluded.
3 this area is nice, how will it be left? Disturbance associated with Baseline activities would be reclaimed
when data gathering activities are complete. Drill pads and test trenches
would be restored to pre-disturbance conditions. Short term temporary
access roads would be reclaimed immediately after use. Improvements
to existing roads would include smoothing out rough areas and
widening of turns. Previously disturbed areas would also be used as
temporary access roads to minimize new disturbance.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-2
Comment
Number Comment Response
Letter 6 - Dalton-Rabago, Pamela
1 I would like to look for another area for the Tailings
rather than the selected area. This is a forest service
property used by much of the public where as there is
more that enough land that is owned by the State Land
Trust and zoned industrial at the base of the mountains
and South of US 60 just West of Gonzales Pass.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 7 - Guzman, Albo
1 We need to open this mine. Resolution Copper Co. We
needs jobs here in Superior
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 8 - Kurtz, Andy
1 I feel the mine is being responsible. I think this session
is not.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
Letter 9 - Romero, Greg
1 Science based decisions are the pillars of fundamentally
sound decisions regarding the copper mine project
The affected environment and environmental consequences evaluated
in the preliminary EA for Baseline activities, include: Water Resources,
Soil Resources, Vegetation Communities and Fire Regimes, Invasive
Species, Wildlife and Special Status Species, Range, Cultural
Resources, Travel Management and Public Safety, Recreation, Visual
Resources, Air Quality, Climate Change, and Noise. Please refer to
Chapter 3 to review this analysis.
Letter 10 - Gurnow, Mark
1 I believe the project is important and proceed without
delay. The long term potential economic impact is
difficult to ignore.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-3
Comment
Number Comment Response
2 There are recreational and ..... concerns with disruption
to native land. However, the positives for outway any
issues, or potential issues caused by the data gathering.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
3 There are ..... and visual concerns with disruption to
native land.
A visual analysis was conducted for Baseline activities and impact
results documented in a Visual Resource Technical Report were used to
develop the analysis in Section 3.12 of the preliminary EA.
Letter 11 - Hing, Michael
1 I “do not” support the tailings to be dump anywhere in
the Tonto National Forest area. I was sold on the project
with the intent it was going to the Pinto Valley open pit.
This is not happening.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 Contamination is my big concern. Effects to Water Resources, including potential contamination, are
discussed in Section 3.3 of the preliminary EA.
Letter 12 - Smith, Myron
1 The more quality data the better and easier the final
decision will be.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 13 - Schepers, Stan
1 My concern is the effects on the area with the drilling
activity with regards to dust in the air
Effects on the area from the Baseline activities in regards to air quality
are discussed in the preliminary EA in Section 3.13.
2 My concern is...the road conditions and maintaining the
road,
All Baseline activities would be accessed using existing forest roads,
previously disturbed areas, and short term temporary access roads
(Section 2.3 preliminary EA). Improvements would be necessary along
portions of existing forest roads and previously disturbed areas. Road
improvements include widening the roadway and widening turns to
allow access for all equipment. Short term temporary access roads
would not require construction activities because a tracked drill rig and
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-4
Comment
Number Comment Response
light duty truck would access the site only once. Reclamation would be
implemented immediately after use for short term temporary access
roads and previously disturbed areas would be reclaimed when
monitoring activities have concluded.
3 We live near the road, so we’re worried about the light
and the noise from that as well.
Light emitted by the Project will be shielded and directed straight down
toward the work area. Based on design specifications provided by the
lighting manufacturer, it is unlikely that light emitted by the Project
will extend beyond a radius of greater than 90 feet around each Project
light source during typical operations. Please refer to Sections 3.12
(Visual Resources) and 3.15 (Noise) of the preliminary EA for
additional analysis of project impacts.
4 We have a concern as to whether that (drilling these test
wells) is going to have an impact on our well. Will they
be taking a lot of water that might impact our
well?...they are drilling holes and they say there is a
plate there where they would be able to put the tailings
there, and once you drill holes down and go through that
plate, isn’t that going to let the tailing seep down into
the aquifer or whatever at later dates?
Potential effects to groundwater are presented and discussed in the
preliminary EA (Section 3.3.3.3). The purpose of Resolution’s Plan is
to collect hydrological, geochemical, and geotechnical data in order to
provide baseline information on these aspects of the environment over
an area being considered for a potential tailings storage site. The pre-
decisional EA prepared by the Tonto National Forest complies with
CEQ NEPA regulations (40 CFR 1500) and Forest Service NEPA
Regulations (36 CFR part 220) for the proposed Baseline activities.
Chapter 3 of the EA considers direct, indirect, and cumulative impacts
of the Proposed Action on resources within and adjacent to the project
area, including surface water and ground water (see preliminary EA,
Section 3.3.3.4). As a part of their Plan, Resolution is proposing to
construct 16 drill sites to accommodate 16 groundwater testing and
monitoring wells, and complete 41 geotechnical drill holes and
piezometer installations. Any future construction and/or development
of a tailings facility is considered outside the scope of analysis of the
preliminary EA (Section 1.5).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-5
Comment
Number Comment Response
5 Why do they need to monitor the water when there is no
mining plan approved or anything yet? So it’s just
something doesn’t fit here. You know, are they drilling
for core samples to see if there is anything else out
there, due to the fact that they’ve staked the claims on
all the -- all the land out there has been staked
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Monitoring of
groundwater is one part of Resolution’s proposed Plan currently under
review by the Forest Service, and will provide Resolution with baseline
hydrological data on an area that may be considered for a future tailings
site.
6 My concern is...the...., hours of operation. Section 3.15 of the preliminary EA describes the noise in the affected
environment and potential effects on resources, recreation, and adjacent
landowners.
Letter 14 - Reynolds, Troy
1 Will we still have access to our 40-acre mining claim? Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
2 During the drilling process will they allow us to check
the assay, what they find when they drill the hole? Will
we be allowed those assays of the material? Unfeathered
access when looking at the analysis? No restrictions?
What they find, we want to know.
The Tonto National Forest has provided Resolution with a copy of all
comments received during scoping. Consistent with Forest Service
Manual 2800, Chapter 2810, Section 2813.11, the locator of a mining
claim acquires rights against other possible (peaceable) locators when
the locator has complied with the applicable Federal and State laws.
Where more than one locator is involved on the same land, Forest
Service actions should be impartial to all known locators of that land,
as the controversy is the responsibility of the locators, not the Forest
Service, to settle.
Letter 15 - Featherstone, Roger
1 it is clear to the Coalition that we do not have enough
information to provide the Forest Service with the best
and most complete comments with the information that
is available on the project website....We respectfully
request an extension of at least two weeks (preferably
30) for us and other members of the public to provide
complete comments
The Tonto National Forest welcomes your comments throughout the
NEPA process. During the NEPA process comments are considered as
they are received consistent with Forest Service NEPA regulations and
36 CFR 218. Public notification regarding the initial preparation of the
EA was conducted in accordance with CEQ and Forest Service NEPA
regulations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-6
Comment
Number Comment Response
Letter 16 - various
1 The US Forest Service’s (“USFS’s”) review outlined in
the scoping letter contains numerous legal and factual
errors and as such should be revised in order to comply
with federal law.
The May 13, 2014 scoping letter was based on the information
available at that time regarding Resolution’s proposed Baseline
activities. Since that time, the proposed action has been revised based
on internal and external scoping comments. Section 2.3 of the
preliminary EA describes the revisions made by Resolution to the
Proposed Action.
2 The proposal involves drilling and test trenches using
new, illegal “user created” roads, and existing Forest
Service roads.
Please refer to Section 2.3 of the preliminary EA for a description of
the Proposed Action including the access roads proposed for use during
the Baseline activities.
3 There is no reason this project to be undertaken except
for its connection to the Main Mine Plan. Therefore, the
proposed main mine is a connected action that must be
reviewed in one environmental review.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-7
Comment
Number Comment Response
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
4 because of the connection of this proposed project to the
Main Mine Plan, and the controversial and complicated
nature of this project and because of the potential for
impact to cultural and sacred sites, and full
Environmental Impact Statement (EIS) should be
prepared.
As discussed in the Preliminary EA, Section 1.5.1.4, the development
of the deep underground copper ore body is not a connected action to
the proposed Baseline Hydrological and Geotechnical Data Gathering
Activities, and therefore is not evaluated in the preliminary EA.
Based on the analysis presented in the preliminary EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice. If Resolution were to proceed
with development of the deep underground copper ore body or other
actions not addressed in this preliminary EA, the potential effects on
resources would be considered in a separate review under NEPA and
36 CFR part 228A.
5 The proposed project would heavily impact the Queen
Creek watershed.... The project needs to study closely,
carefully, and completely, the Queen Creek watershed
and the impacts of the project on the towns of Queen
Valley and Superior.
Effects to Water Resources from Baseline activities, including
watersheds, are discussed in Section 3.3 in the preliminary EA.
6 If the Forest Service does not consider the project and
the proposed main mine as part of the same project, then
the proper permitting authority is not the mining law or
the Forest Service 36 part 228 regulations, but the Forest
Service’s special use permitting regulations. In addition,
Rio Tinto is not “entitled” to have the project approved
under the 1872 Mining Law.
Connected actions are defined by CEQ as those actions that are closely
related and should therefore be analyzed together (40 CFR 1508.25).
Please see Section 1.5 in the Preliminary EA for an explanation of
independent utility and connected actions relative to Resolution’s
proposed Baseline activities.
Because the activities proposed by Resolution in their Baseline Plan are
considered a use that is reasonably incident to mineral exploration, they
are explicitly exempted from special use authorization. Consistent with
36 CFR part 251.50(a), special uses are designated as all uses of
National Forest System lands, improvements, and resource, except
those authorized by the regulations governing…minerals (part 228).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-8
Comment
Number Comment Response
Therefore, Forest Service special use authorization does not apply to
Resolution’s Baseline plan.
7 The Forest Service must fully comply with the National
Historic Preservation Act (NHPA) and all other cultural
and religious freedom protection laws.
Section 1.6 of the preliminary EA discusses compliance with NHPA
and other relevant regulations. Section 3.9 of the preliminary EA
discloses effects to cultural resources and SHPOs concurrence with the
findings based on current information. It is anticipated that the
“Ethnographic/Ethnohistoric Study of the Superior Area, Arizona”
(Study) will be completed prior to a final decision being reached on the
Baseline Plan. The Forest Service will consider the findings of the
Study, in conjunction with Tribal comments which come out of
government to government consultation in the final decision on the
Baseline Plan.
Letter 17 - Tucker, Kathleen
1 Resolution’s (and a couple of elected officials) “want” is
not more important than saving the water supply, the
geo‐stability of the area, preventing air, ground, and
water pollution from tailings and tunnels, the destruction
of ancient sites, the privatization of public lands for the
sake of greed.. ..to enrich a foreign corporation.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not considered a connected
action to the proposed Baseline activities, and therefore is not evaluated
in the EA. That separate action would be subject to a separate review
under NEPA and 36 CFR part 228A.
2 That copper isn’t going anywhere. One day, technology
may allow mining that doesn’t destroy any area, and I
hope the Forest Service waits for that day.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
3 President Eisenhower was well aware that Oak Flat was
within the copper corridor when he specifically
prohibited mining in the area.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-9
Comment
Number Comment Response
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
4 I want future generations to enjoy this beautiful area.
Please don’t allow any further intrusion by mining, or
testing, of this Federally Protected Land.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 18 - Benallie, Jr., Larry; Lewis, Barnaby V.
0 we. would like to reiterate that the GRlC-THPO opposes
and does not approve of mining activities of any type.
The proposed project area is within the ancestral lands
of the Four Southern · Tribes (Gila River Indian
Community; Salt River Pima-Maricopa Indian
Community; Ak-Chin Indian Community and the
Tohono O’Odham Nation).
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-10
Comment
Number Comment Response
2 If Resolution’s geotechnical data gathering activities are
unable to avoid these archaeological properties,
Resolution Copper Mining, LLC in conjunction with
their archaeological consultants, will be required to
develop an historic property treatment plan (HPTP) and
submit the HPTP for Section 106 compliance review.
Section 3.9 of the preliminary EA discloses effects to cultural resources
and SHPOs concurrence with the findings based on current
information. The Proposed Action is not expected to affect any known
cultural resources listed in or eligible for the NRHP. It is anticipated
that the “Ethnographic/Ethnohistoric Study of the Superior Area,
Arizona” (Study) will be completed prior to a final decision being
reached on the Baseline Plan. The Forest Service will consider the
findings of the Study, in conjunction with Tribal comments which
come out of government to government consultation in the final
decision on the Baseline Plan.
Letter 19 - Bever, Victoria
1 ADOT is planning a construction project (US 60, Silver
King – Town of Superior) that will impact one of the
proposed access routes shown in your map. I believe
you can access all of the shown boring locations using
an alternate route from your map (Hewitt Station Rd).
I’ve attached your map with the conflict area marked.
Resolution made modifications to their Proposed Action based on
internal and external scoping comments received during the Scoping
Period (Section 2.3 of the preliminary EA). Resolution agreed not to
use FR 2395 to access the Baseline activities from US 60.
Letter 20 - Krieg, John
1 We respect the areas that are off limits to motorized
vehicles and can’t imagine the area closed to ATVs, but
open to large drilling rigs, bulldozers, road graders and
the necessary equipment to support this type of activity.
Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
Short term temporary access and previously disturbed areas to be used
for access would be reclaimed immediately following Baseline
activities.
2 If we lost FSR 252, we would be basically be cut off
form the TNF and our wonderful trails.
FR 252 is an existing forest road that would remain open during
construction and implementation of Baseline activities. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
3 The proposed drilling would forever ruin the nature of
the area, as it has done in the area behind Oak Flats.
Effects to Visual Resources and Recreation are evaluated in
Sections 3.11 and 3.12 in the preliminary EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-11
Comment
Number Comment Response
Letter 21 - McDonald, Thomas
1 Expand the submitted RC tailings site geological
sampling plan to include some regions within the
tailings footprint where the Mescal Limestone (Ym on
the geologic map), the Escabrosa Limestone (Me on the
map), and the Martin Formation (Dm on the map) have
surface expression to investigate if solution channels are
present and, if so, whether the channels extend to the
depth of the current water table.
Resolution developed the proposed locations by evaluating the need for
hydrological and geotechnical data while minimizing potential impacts
to National Forest System lands. Section 2.3 of the preliminary EA
describes the location of each geotechnical drill site. Resolution
currently has four proposed hydrological test wells DS-I, DS-J, DS-K,
and DS-L to investigate the limestone sequences in the Apache Group
(Mescal) and Paleozoic (Escabrosa, Naco and Martin) units near
surface and outcrops located in the northwestern portion of the
investigation area. The boreholes will allow Resolution to determine
(through geophysical logging and analysis of cuttings) the degree of the
fracturing within the subsurface units including the limestone should
they be present at depth as anticipated. Aquifer testing in the
hydrologic test wells will provide information regarding water
production and the hydrogeologic properties including transmissivity of
the unit. Based on current understanding of the hydrology in the basin,
groundwater flows are likely to be in a west / southwesterly direction
towards Whitlow Dam. The limestone units appear to be bounded on
all sides by geologic units that have historically been less transmissive
to flow including the Pinal Schist, Gila Conglomerate, and Proterozoic
diabase.
2 Keep public access to all current roads within the
tailings footprint during the data collection period.
Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
3 Within the tailings footprint, any significant vegetation
(such as saguaros, ocotillos, and hedgehog cacti) that
will be adversely affected by the data collection
activities and/or the infrastructural changes to support
those activities should be carefully removed and either
replanted or offered at no cost to local governments
and/or local non‐profit organizations.
Applicant-proposed Environmental Protection BR-4 states the Project
activities would comply with the Biological Resources Monitoring Plan
for Resolution Copper Mining, LLC Plan of Operations; Baseline
Hydrologic and Geotechnical Data Gathering Activities on Tonto
National Forest, dated June 2013. Mitigation Measure MM-3 specifies
that Saguaro, barrel, pincushion, hedgehog cacti, ocotillo, and agave
species would be avoided.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-12
Comment
Number Comment Response
4 All waste products (fuel, lubricants, solvents, waste
water, etc.) developed as a result of the data collection
process should be disposed of in an EPA certified
landfill.
Public safety, including the use of hazardous materials, will be
managed in accordance with FSMs 770 and 7730 as well as through the
use of Applicant-proposed EPMs identified in section 2.3.6, of the
preliminary EA and also discussed in Section 3.10 (Travel
Management and Public Safety).
Letter 22 - Wolff-Krauter, Kelly
1 In Arizona, Arizona Revised Statute (ARS) § 17-1 02
codifies state ownership of wildlife. The Department has
public trust responsibility and primary authority to
manage and regulate take of wildlife within the state of
Arizona irrespective of landownership, excepting those
wildlife existing on tribal trust-status lands.
Section 3.7 of the preliminary EA evaluates potential effects on
wildlife and wildlife habitat.
2 The extent of the trenches, road improvement, and the
footprints of the drilling and hydrological sites are
quantified as 96.04 acres within the Plan of Operation.
This creates a loss of important Sonoran desert habitat.
Impacts to wildlife and wildlife habitat should be
evaluated and a mitigation plan should be developed to
offset the loss to wildlife resources. Arizona Game and
Fish Commission Policy (attached) require the
Department to develop mitigation plans for impacts to
wildlife and habitat for land and water projects.
Based on internal and external comments received during Scoping,
Resolution has made modifications to their Proposed Action
(Section 2.3 preliminary EA), and updated disturbance acreage
estimates are provided in Table 2-1 of Chapter 2. Effects to Wildlife
and Special Status Species are evaluated in Section 3.7, including any
mitigation measures proposed by the applicant and/or the Forest
Service.
3 More specific information is needed to determine the
impacts to wildlife, due to increased vehicle traffic and
noise in the project area. The equipment at each drill site
would likely disrupt behavior and cause wildlife to leave
the area. The potential for noise disturbance associated
with drilling, roadway improvement and construction,
grading and brush removal should be evaluated.
Measures should be identified that avoid or minimize
the potential for noise disturbance.
Effects to Wildlife and Special Status Species, including effects from
noise, are evaluated in Section 3.7 of the preliminary EA. And Noise,
in general, is evaluated in Section 3.15.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-13
Comment
Number Comment Response
4 This area is heavily used by OHV recreationists and
hunters. We support your plan that current access
continue to be open unless significant public safety
concerns mandate temporary closure.
Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
5 We also recommend that the 3.39 miles of short term
temporary roads be reclaimed immediately and rendered
impassable after mine activity is completed and to
prevent further disturbance to wildlife.
Short term temporary access roads will be reclaimed immediately after
use (Sections 2.3.5 of the preliminary EA).
6 Executive Order 13443 requires the Forest to “ensure
that agency plans and actions consider programs and
recommendations of comprehensive planning efforts
such as State Wildlife Action Plans, the North American
Waterfowl Management Plan, and other range-wide
management plans for big game and upland game
birds”.
Section 1.3 of the preliminary EA discloses applicable regulations and
Section 3.7 describes the affected environment and discloses effects to
wildlife including big game and upland game bird species.
7 We recommend avoiding potential impacts to important
game species such as mule deer, whitetail deer, javelina,
cottontail rabbits and quail. Potential impacts to all
wildlife in the area should be identified and evaluated.
Effects to Wildlife and Special Status Species are evaluated in
Section 3.7 in the preliminary EA.
8 Impacts to vegetation should be minimized and any
protected native plant be protected and relocated
adjacent to the site in adherence to Arizona’s native
plant laws. We support Resolution’s plan for
reclamation ofthese sites and the use of weed free native
Sonoran desert vegetation in these efforts as well as the
cleaning of equipment to prevent the spread of invasive
plants. In addition, we recommend providing further
information on strategies to address plant survival post
planting, as well as measures to prevent degradation of
rehabilitated areas by foot traffic and/or vehicles after
completion.
Applicant-proposed Environmental Protection BR-4 states the Project
activities would comply with the Biological Resources Monitoring Plan
for Resolution Copper Mining, LLC Plan of Operations; Baseline
Hydrologic and Geotechnical Data Gathering Activities on Tonto
National Forest, dated June 2013. Mitigation Measure MM-3 specifies
that Saguaro, barrel, pincushion, hedgehog cacti, ocotillo, and agave
species would be avoided. Reclamation would involve reseeding using
weed-free native species seed (MM-4). Salvage and transplanting is
anticipated to result in increased rates of revegetation success.
Effects to Vegetation Communities and Invasive Species are evaluated
in Sections 3.5 and 3.6 of the preliminary EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-14
Comment
Number Comment Response
9 The Forest should determine if there is any potential for
the introduction of noxious weeds, pathogenic fungi
(chytridiomycota), and other organisms which may
cause disease or alteration to ecological functions.
Forest Service follows policy on addressing noxious weeds
(Section 3.6); see also the Tonto National Forest’s website on seed
testing policy:
http://www.fs.usda.gov/detail/tonto/landmanagement/resourcemanage
ment/?cid=fsbdev3_018789. Noxious weed mitigation is addressed in
the preliminary EA (Section 3.6.3.3). Noxious weeds currently exist
throughout the project area. The weed specific mitigation is meant to
reduce introductions and the spread of these species. Effects to Noxious
Weeds are evaluated in Section 3.6 of the preliminary EA. Aquatic
habitat that is thought to support pathogenic fungi is not known to exist
within the proposed project area.
10 We recommend surveys for Sonoran desert tortoise and
burrows be conducted prior to disturbance of the sites
and we support your Biological Monitoring Plan with
particular protocols established for the monitoring and
avoidance of desert tortoise (Gopherus morajkai) and
Reticulate Gila Monster (Heloderma Suspectum)
individuals and shelter sites. Please utilize the following
guidelines found on our Department website for project
planning and implementation
Effects to Wildlife and Special Status Species are discussed in
Section 3.7 of the preliminary EA.
11 The Department is concerned with the cumulative
impacts of this project; including impacts from mining
should minerals be located. The effect of mineral
exploration can reasonably be foreseen to be actual
mining activity at the site should minerals be located.
This project, therefore, could result in significant effects
on the human environment depending on the amount
and type of minerals located. The Department is
interested in the potential mining activity which could
result from the exploration.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site related to
Resolution’s proposed General Plan of Operations. The General Plan of
Operations is a separate proposal and will be subject to a separate
review under NEPA and 36 CFR part 228A.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-15
Comment
Number Comment Response
Letter 23 - Smith, Rich
1 The area described in the released documents is located
in the heart of a highly used and much valued
Off_highway Vehicle (OHV) area in the Mesa and
Globe districts
Section 3.11 of the preliminary EA evaluates potential effects on off
highway vehicles use and recreation.
2 The activities described in the Data Gathering Plan,
while limited in scope have substantial impact to OHV
recreation in the area.... the proposed improvements
completely remove the element of interest and challenge
from these modified road sections.
Several existing forest roads are currently maintained as a high-
clearance vehicle road (Forest Service maintenance Level 2), and
Resolution has determined that some road segments are in sufficient
condition to allow construction equipment access without
improvement. Existing forest roads requiring improvement may include
widening the road bed and/or widening turns to permit construction
equipment access. The Proposed Action improvements along forest
roads would still meet maintenance Level 2 standards.
3 Following the Data Gathering Plan to its next step
described in the Mine Plan of Operations, these same
routes will be completely closed over time assuming
that the plan moves forward with this site as a tailings
storage area. The loss of the closed routes will be
substantial to the OHV community and we have
additional concern that another iconic route popularly
called the Montana Mountain loop (routes 172, 172A
and 650) may be impacted and possibly in jeopardy due
to their proximity to the mining operations.
No roads will be closed during the course of this proposed project. As
discussed in the preliminary EA, Section 1.5.1, the development of the
deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore was not evaluated in the EA.
An appropriate analysis and environmental document will be prepared
to address the General Mining Plan.
4 find another location to be used as a tailings storage area
and in doing so leave the much valued OHV routes in
this area undisturbed. We have no specific expertise in
mine operations and planning but like much of the
public would rather see tailings stored in an area already
disturbed by previous mining
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-16
Comment
Number Comment Response
5 we estimate the loss of high quality OHV routes to be in
the 30+ mile range.
Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
Please refer to Section 3.11 of the preliminary EA for additional
information on recreation resources.
6 In the recently released Draft EIS published by the
Tonto National Forest, we observe that there are
additional routes proposed to be closed to motorized
traffic in this area in addition to the 30+ miles that will
eventually be lost to the Resolution Mine project.
Section 2.3 of the EA describes the Proposed Action including access
roads, and Table 3-1 in Section 3.2 describes the projects where there is
potential for cumulative impacts, to include the draft Travel
Management Plan Environmental Impact Statement, when considered
with the proposed Baseline activities.
Letter 24 - Kelley, Lawrence
No Comments
Letter 25 - Kravcov Malcolm, Karen
No Comments
Letter 26 - Keck, Aubrey
1 Having lived in that area and knowing so many of those
people and their families I know how their health has
suffered from the mines. Small children (pre‐school)
suffering from asthma and cancers. The older people
with all their lung related issues. Isn’t it past time that
we took the human cost into account?
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 27 - Rangel, Manuel
No Comments
Letter 28 - Miniuk, Jacqueline
No Comments
Letter 29 - Graffagnino, Mary Ann and Frank
No Comments
Letter 30 - Prchal, Steven
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-17
Comment
Number Comment Response
Letter 31 - Goodale, Donna
No Comments
Letter 32 - Spragett, Cedra & Eric
No Comments
Letter 33 - Guidi, Rita
No Comments
Letter 34 - Rubach, Will
No Comments
Letter 35 - Heron, Veronica
No Comments
Letter 36 - Miller, Linda
1 It sickens me to have to drive through the incredible
destruction that mining has caused in the Superstition
Mountains. NO MORE. There should be NO MORE
mining anywhere in or around the Superstition
Mountains. It is a blight that will last forever.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 37 - Andresen, Lori
No Comments
Letter 38 - D, Cathy
No Comments
Letter 39 - Sauer, A
No Comments
Letter 40 - Sauer, A
No Comments
Letter 41 - Weil, Charles
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-18
Comment
Number Comment Response
Letter 42 - Hodiak, Diane
1 Oak Flat campground ia prime birding territory and
includes at least 4 species on the threatened list
according to Natiional Audobon Society. Bird habitat is
iin extreme decline, particularly in ARizona. This is
particularly true in Arizona where mining projects strip
away precious resources and deposit toxic waster for
wildlife. Birdlng is a billion dollar industry and Az is
known to be a birding hotspot. Continuing mining
operations in critical habitat will imperil both species
the associated economic benefits from birding tourism.
The purpose and need for Baseline activities is to gather additional
baseline hydrological and geotechnical data (Section 1.4 of the
preliminary EA) to determine the area’s suitability as a tailings storage
location. Section 1.5.1 describes the consideration of connected actions.
Potential effects of mining the deep underground copper ore body will
be described based on Resolution’s general mine plan, and they would
be addresses in a separate and appropriate NEPA document.
Letter 43 - Peat, Evelyn
No Comments
Letter 44 - Crowley, Kenneth
No Comments
Letter 45 - Hanna, Neal
No Comments
Letter 46 - Coryell, Mark
No Comments
Letter 47 - Fura, David
No Comments
Letter 48 - Gaede, Marnie
No Comments
Letter 49 - Bickel, Bettina
No Comments
Letter 50 - Stegman, Bart
No Comments
Letter 51 - Wilkinson, Cliff
No Comments
Letter 52 - Warren, Barbara
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-19
Comment
Number Comment Response
Letter 53 - Guerrero, Barbara
No Comments
Letter 54 - Moser, Paul
No Comments
Letter 55 - Miniuk-Sperry, Colleen
No Comments
Letter 56 - Harris, Robert & Debra
No Comments
Letter 57 - Oxford, Rex
No Comments
Letter 58 - Neumann, Renee
No Comments
Letter 59 - Coleman, Edwin
1 The damage the mining companies leave behind ‐‐ to the
land, to the watersheds and to the ground water ‐‐ is
irreversible and reprehensible.
Effects to Water Resources are evaluated in Section 3.3 of the EA.
Letter 60 - Peltier, Drew
No Comments
Letter 61 - Valder, Carolina
No Comments
Letter 62 - Schroeter, Rogil
No Comments
Letter 63 - Pedersen, Annette
No Comments
Letter 64 - Richards, Christopher
No Comments
Letter 65 - Phillips, Sean
No Comments
Letter 66 - Binder, Fred
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-20
Comment
Number Comment Response
Letter 67 - Yeargain-Williams, Peggy
No Comments
Letter 68 - Rings, Sally
No Comments
Letter 70 - McDonald, Thomas
No Comments
Letter 71 - Tucker, Kathleen
No Comments
Letter 72 - Wolff-Krauter, Kelly; Robb, Natalie
No Comments
Letter 73 - WongCarter, Austin
No Comments
Letter 74 - Christian, Karen
No Comments
Letter 75 - Desrosiers, Donna
No Comments
Letter 76 - Quinlan, Jim
No Comments
Letter 77 - Rubach, Will
No Comments
Letter 78 - Paxton, Harold
No Comments
Letter 79 - Bittick, Cynthia
No Comments
Letter 80 - Avanti, Annemarie
No Comments
Letter 81 - Livingston, Ron
No Comments
Letter 82 - Pedersen, Annette
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-21
Comment
Number Comment Response
Letter 83 - Pike, Naelyn
No Comments
Letter 85 - Whitman, Frances
No Comments
Letter 86 - Bingham, Brent
No Comments
Letter 87 - Flowers, Taira
No Comments
Letter 88 - Guidi, Rita
No Comments
Letter 89 - Miniuk, Jacqueline
No Comments
Letter 90 - Reinhard, Matthew
No Comments
Letter 91 - Metivier, Pam
No Comments
Letter 92 - Huggenvik, Jodi
No Comments
Letter 93 - Casillas, Rudy
No Comments
Letter 94 - Marks, Makaius
No Comments
Letter 95 - Marks, Makaius
No Comments
Letter 96 - Sauer, A
No Comments
Letter 97 - Yeargain-Williams, Peggy
No Comments
Letter 98 - Mckee, Derek
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-22
Comment
Number Comment Response
Letter 99 - O’Neill, Vicki
No Comments
Letter 100 - Ellis, James
No Comments
Letter 101 - Arandelovic, Janice
No Comments
Letter 102 - West, Joanne
No Comments
Letter 103 - Bastek, Christopher
No Comments
Letter 104 - Cruz, Richard
No Comments
Letter 105 - Wilkey, James
1 The riparian Queen Canyon is home to many unique AZ
animals. Once mining removes the last of the water, all
those animals will perish. Please do not let a huge,
insensitive mining company kill these rare, and unique
animals.
The purpose of the proposed Baseline activities is to collect baseline
hydrological, geochemical, and geotechnical data (Section 1.4 of the
preliminary EA) over an area being considered for a potential tailings
site. Section 1.5.1 describes the consideration of connected actions.
Letter 106 - Jones, Johanna
No Comments
Letter 107 - Magill, Sue
No Comments
Letter 108 - Lytle, Heidi
No Comments
Letter 109 - Watkins, Jackie
No Comments
Letter 110 - Norman, Clayton
No Comments
Letter 111 - Rafoth, Richard
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-23
Comment
Number Comment Response
Letter 112 - Arneson, Carla
1 Without environmentally safe and secure waste disposal,
there is no mine. Without knowing how waste will be
treated and transported, how much waste there will be,
and what toxins it will contain there is no way to judge
the suitability of a site
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 the EIS must fully analyze all direct, indirect, and
cumulative impacts – including from Rio Tinto’s main
mine proposal.
Based on an initial review, it has been determined that an
Environmental Assessment (EA) would be the appropriate level of
analysis for the proposed Plan. The preliminary EA complies with CEQ
NEPA regulations (40 CFR 1500) and Forest Service NEPA
Regulations (36 CFR part 220) for the proposed Baseline activities.
Chapter 3 considers direct, indirect, and cumulative impacts of the
Proposed Action on resources within and adjacent to the project area,
regardless of land status.
As described in the preliminary EA, the Baseline Plan has independent
utility from Resolution’s General Plan of Operations and that separate
action would be subject to a separate review under NEPA and 36 CFR
part 228A (Sections 1.4, 1.5).
Letter 113 - Santori, Nancy
No Comments
Letter 114 - Kravcov Malcolm, Karen
No Comments
Letter 115 - Elton, Wallace
No Comments
Letter 116 - Dilley, Jean
1 air quality issues are of significant concern Effects on the area from the Baseline activities in regards to air quality
are discussed in the preliminary EA in Section 3.13.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-24
Comment
Number Comment Response
Letter 117 - Stone, Tim
1 In every country and every state where Rio Tinto
operates, there are past and pending law suits seeking
damages from the decimated country, ruined lives and
deaths of it’s inhabitants. Is this the company that you
want to give a foothold in one of the most pristine areas
of the Sonoran Desert?
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 118 - O’Connor, Cornelia
No Comments
Letter 119 - Royer, Michael
1 The toxic tailings location would heavily affect Boyce
Thompson Arboretum, a world‐class botanical preserve.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in the EA.
Letter 120 - Desrosiers, Donna
No Comments
Letter 121 - Small, Marsha
No Comments
Letter 122 - Sherry, Constance
No Comments
Letter 123 - McCauley, Joshua
No Comments
Letter 124 - Wise, John
No Comments
Letter 125 - Guidi, Rita
No Comments
Letter 126 - Gonsalves, Gail
No Comments
Letter 127 - Whitman, Frances
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-25
Comment
Number Comment Response
Letter 128 - Gennarelli, Diane
No Comments
Letter 129 - Kellogg, Quinn
1 Oak flats has a long history in the climbing world, it
became a mecca in the early 90’s because of
competitions that were held there, attracting hundreds of
professional and average climbers alike. Since then it
has been a winter destination for people all over the
country, and world. I personally travel all the way from
Ohio almost every year to live in Oak Flats for months
at a time.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
2 And this is saying nothing of the terrible environmental
impacts on the fragile mountaintop ecosystem
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
3 And this is saying nothing of the ... desecration of sacred
Native lands
Please refer to Section 3.9 of the preliminary EA for a description and
discussion of Native lands.
4 And this is saying nothing of the ... false promise of
jobs.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 130 - Bryant, Leslie
1 This area of interest is a very important recreational area
which brings in a large amount of money to our state’s
economy yearly.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-26
Comment
Number Comment Response
2 But as a resident of a near by town, I disagree with this
plan to put Rio Tinto’s tailing so near the Queen Creek
watershed. I believe this will have a future impact on
our water in Queen Valley, which will have a future
impact on our existence.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of the preliminary EA.
Letter 131 - Losey, Kevin E.
1 this project, in whole, is detrimental to our environment.
This project will affect communities surrounding, as
well as “downstream”.
Effects to Water Resources are evaluated in Section 3.3 of the EA.
Letter 132 - Greene, Jeanine
No Comments
Letter 133 - Gray, James
1 This area is one of the most pristine and scenic desert
areas within the Southwest and the TNF. It is hard to
imagine anyone would allow the destructive actions
being proposed by Resolution Copper.
A visual analysis was conducted for Baseline activities and impact
results documented in a Visual Resource Technical Report were used to
develop the analysis in Section 3.12 of the preliminary EA.
2 I’m very concerned about the natural habitat destruction
that will take place if heavy construction and drilling
rigs are allowed within this area. There is a possibility
that the fragile balance between the land and wildlife
will suffer under these proposed actions.
Effects to Vegetation Communities are evaluated in Section 3.5 and
effects to Wildlife and Special Status Species are evaluated in
Section 3.7 of the preliminary EA.
3 Access to this area will be denied to those who regularly
seek the beauty and solitude this unique desert
environment brings
Public access of proposed activity areas would be managed by crew
members during roadway improvements and maintenance. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
4 This is a highly regarded recreational area used by
hikers, horseback riders, hunters, birdwatcher’s, and
naturalist from Arizona and throughout the United
States.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-27
Comment
Number Comment Response
5 This area provides a vital economic boost for the small
rural communities that border this area of the TNF. The
future economic and recreational impact on these
communities must not be upset due to destruction of this
pristine and fragile environment.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
6 Any contamination or altering of the water supply in this
desert region should be a grave concern to us all. Since
we are already in a drought condition, this would further
alter the balance in nature.
Effects to Water Resources, including potential contamination, are
discussed in Section 3.3 of the preliminary EA.
7 The agency cannot assume that Rio Tinto/Resolution
Copper has “rights” to proceed with the project yet at
the same time argue that the project is not part of the
proposed main mine proposal.
Section 1.4 and 1.5.1 of the preliminary ES describe that this project is
a “stand alone” project and has separate utility; the development of the
deep underground copper ore body is not a connected action to the
Proposed Action, and therefore was not evaluated in the preliminary
EA. If Resolution were to proceed with development of the deep
underground copper ore body or other actions not addressed in this
preliminary EA, the potential effects on resources would be considered
in a separate review under NEPA and 36 CFR part 228A.
8 I believe this proposed project violates the “forest-wide
goals, objectives, and management area standards for
protecting the air, cultural resources, recreation
opportunities, soils, visual resources, water and
wildlife”.
Chapter 3 of the preliminary EA considered the forest wide goals,
objectives, and management area standards for all of the resources
analyzed in the EA including air, cultural resources, recreation
opportunities, visual resources, soils, water and wildlife.
Letter 134 - Levendowski, Merrilee Kinney and Dan
1 Please reconsider the location of the mine tailings. We
are not against the mining operation, only the site of the
tailings deposit.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 We are also members of the Boyce Thompson
Arboretum which, we understand, would be adversely
affected by the tainted water shed.
Effects to Water Resources, including potential contamination, are
discussed in Section 3.3 of the preliminary EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-28
Comment
Number Comment Response
3 We moved to Superior to enjoy its ... accessibility. No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public.
4 We use this area often for hiking and jeep riding plus
javelina, white tail, and quail hunting.... We moved to
Superior to enjoy its quiet beauty, spectacular views
Section 3.11 of the preliminary EA evaluates potential effects on
recreation. And Section 3.12 evaluations potential effects to visual
resources.
Letter 135 - Barrett, Sylvia
1 My husband and I along with our friends (sometime as
many as 24 or more) quad ride in that area. As we ride
in the area we encounter many other kids and adults
doing the same thing.... This area is extremely important
for recreation.
Section 3.11 of the preliminary EA evaluates potential effects on off
highway vehicles use and recreation.
2 I urge you to reconsider allowing a tailings site to go in
that area.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 136 - Gray, Carolyn
1 This area is one of the few remaining pristine and
natural environments in Southern Arizona. Devastation
from mining is evident from Miami to Pinto Valley
from San Manuel to Hayden from Kearney to Superior.
All of this is due to disregard of the land, the
environment, the water, and the wild life.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-29
Comment
Number Comment Response
2 I also, believe the “tailings” will cover a very large area
of land in terms of miles in length by thousands of feet
high. A person can see these consequences in Miami,
Arizona where nothing will ever grow or be sustained
again.
A visual analysis was conducted for Baseline activities and impact
results documented in a Visual Resource Technical Report were used to
develop the analysis in Section 3.12 of the preliminary EA. The
purpose and need for Baseline activities is to gather additional baseline
hydrological and geotechnical data (Section 1.4) to determine the area’s
suitability as a tailings storage location. Section 1.5.1 describes the
consideration of connected actions. Potential effects of mining the deep
underground copper ore body will be described based on Resolution’s
general mine plan, and they would be addresses in a separate and
appropriate NEPA document.
3 And then there is another consequence of these
chemicals leaching into the water table flowing west
towards Gold Canyon and Apache Junction, involving
Queen Valley and Boyce Thompson Arboretum, a
famous botanical preserve.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of the preliminary EA.
Letter 137 - Krieg, Jim and Kathy
1 The United States Forest Service (USFS) should include
the analysis of this proposed drilling and exploration as
an integrated part of the impacts associated with the full
mining plans.
Section 1.4 and 1.5.1 of the preliminary ES describe that this project is
a “stand alone” project and has separate utility; the development of the
deep underground copper ore body is not a connected action to the
Proposed Action, and therefore was not evaluated in the preliminary
EA. If Resolution were to proceed with development of the deep
underground copper ore body or other actions not addressed in this
preliminary EA, the potential effects on resources would be considered
in a separate review under NEPA and 36 CFR part 228A.
2 The United States Forest Service (USFS) should include
... the impacts associated with the full mining plans.
Otherwise, the Forest Service will be in violation of
both NEPA and the CEQ regulations, which do not
allow segmentation of impact analysis on projects.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-30
Comment
Number Comment Response
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
3 If the use of recreational areas, the Boyce Thompson
Arboretum, and the Superstition Wilderness areas were
to be compromised with drilling, many residents and
visitors to Arizona would be missing the natural beauty
this state offers.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation. And Section 3.12 evaluations potential effects to visual
resources.
4 It is apparent that the environmental and economic
impacts to the area would be negative
Please refer to Chapter 3 of the preliminary EA for a description of the
environment in the Project Area and discussion of potential impacts to
several resources. Economic impacts from the Proposed Action are
discussed in Chapter 3.
Letter 139 - Jeffrey, Anna
1 I was told and have seen many Native American
artifacts and burial grounds in the very vicinity RCC is
planning to use.... it more valuable for its ... vivid
historical and archaeological significance and study.
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known/identified
cultural resource sites that would be affected by the Baseline activities.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-31
Comment
Number Comment Response
2 if the drilling is allowed it would be an open door for
more non reversible destruction on the land, water and
air.
Effects to Water Resources and Air Quality from the Baseline activities
are evaluated in Sections 3.3 and 3.13 of the preliminary EA.
3 Not only is it more valuable for its recreational uses ... Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
Letter 140 - Heidinger, Richard
1 we found that nothing compares to Queen Valley. It is a
real jewel in Arizona’s crown of ideal settings. The wild
life is abundant, from foxes and eagles, to deer and even
a rare appearance of a black bear.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
2 The possibility of a toxic tailings dump in the vicinity of
the water shed of our water supply is unthinkable! Even
the possibility, no matter how remote, is unthinkable!
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of the preliminary EA.
3 The destruction of Queen Valley’s prosperity and land
values and the associated luscious golf course, would
result in untold millions of dollars.... the gain to
Superior, Queen Valley, and Boyce Thompson
Arboretum is almost non-existent. Queen Valley is
made up of a large percentage of seasonal residents as
well as many full-time residential homeowners. Some
have already mentioned the possibility of selling their
homes, afraid of collapsing land values.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
Letter 141 - Muñoz., Henry C.
1 The area is a pristine hunting area with an abundance of
wildlife deer, javelinas, quail that is enjoyed by myself
and many hunters.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation, including hunting.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-32
Comment
Number Comment Response
2 The area is a pristine hunting area.... It is also a prime
hiking-mountain bike and horseback riding area.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
Letter 142 - Gordon, Janine
1 where is all of our water going? All of these years and
always having springs and running water to explore in
the desert....disappearing and gone. Per Resolution,
water will be piped to Maricopa County to replenish the
groundwater there. What happened to replenishing the
Superior/Queen Valley watersheds that be drawn down?
What is the quality of any remaining water going to be?
Tailing/Slag Mountains full of chemicals and poisons,
leaching into the groundwater. Wells running dry
already. Why would anyone be able to quantify that as
okay to happen?
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of the preliminary EA.
2 the tailing mountains will distribute the chemicals and
poisons into the atmosphere, blowing thru this precious
wilderness habitat and impairing both wildlife and
mankind with health issues.
The purpose and need for this project is to gather additional baseline
hydrological and geotechnical data (see Section 1.4 of the preliminary
EA) to determine the areas suitability as a tailings storage location.
Section 1.5.1 describes the consideration of connected actions.
Potential air quality effects of tailings facility locations would be
evaluated along with the development of the deep underground copper
ore body under Resolution’s general mine plan in a separate and
appropriate NEPA document.
3 subcontracted jobs to contractors who are not offering
above market wages, benefits, etc. We don’t need those
jobs to improve the local economy....only the Resolution
Trust direct hires will have those quality compensated
jobs and they don’t choose to live in [the local area]
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
4 Homes in Queen Valley will lose value.........if large
poison tailings are leaching in the groundwater, and
polluting the air with chemicals....if the water tables
continue to drop and wells dry up....who will want to
buy those homes or live in Queen Valley.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-33
Comment
Number Comment Response
5 why destroy the habitats of so many animals and people,
for a block mined copper project
The purpose and need for Baseline activities is to gather additional
baseline hydrological and geotechnical data (Section 1.4 of the
preliminary EA) to determine the area’s suitability as a tailings storage
location. Section 1.5.1 describes the consideration of connected actions.
Potential effects of mining the deep underground copper ore body will
be described based on Resolution’s general mine plan, and they would
be addresses in a separate and appropriate NEPA document.
6 why destroy the habitats of so many animals and people,
for a block mined copper project that is illegal to
consider in the first place due to grandfathered
protections put in place to protect the area due to its’
sacred importance to the Indian people.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-34
Comment
Number Comment Response
7 Review putting the tailing/slag heap outside of Gold
Canyon, next to the Superstition Mtn Golf Course. Use
some State Trust or Tonto National Forest Land near
there
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
8 Queen Valley is unique, priceless and cannot be
duplicated anywhere else. The Tonto National Forest,
State Trust Lands, the Arboretum, Queen Creek,
Whitlow Dam, Picket Post Mountain..............just
scratch the surface of the many wonderful and
irreplaceable environments surrounding Queen Valley.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 143 - Campos, Javier
No Comments
Letter 144 - Hartigan, Zay
1 I feel it is necessary to conduct a full EIS on the full
project as there are many reasons a mine of the type
suggested in the Poo is a bad choice for this area.
Section 1.4 and 1.5.1 of the preliminary ES describe that this project is
a “stand alone” project and has separate utility; the development of the
deep underground copper ore body is not a connected action to the
Proposed Action, and therefore was not evaluated in the preliminary
EA. If Resolution were to proceed with development of the deep
underground copper ore body or other actions not addressed in this
preliminary EA, the potential effects on resources would be considered
in a separate review under NEPA and 36 CFR part 228A.
2 The biggest concerns I have are water for residents in
the area, the destruction of the scenic highway through
the area, and the destruction of some outstanding
recreational assets. In particular as regards just the
tailings study, I think the amount of tailings and the
toxicity of it will be too great for this sensitive area.
The preliminary EA addresses effects to Water Resources (Section 3.3),
Visual Resources (Section 3.12), and Recreation (Section 3.11) relative
to the proposed Baseline activities. Public access of proposed activity
areas would be managed by crew members during roadway
improvements and maintenance. No road closures are expected to take
place and road improvements would be conducted in a manner that
would allow continued use by the public including recreational use.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-35
Comment
Number Comment Response
Letter 145 - LeStarge, Wendy; Taunt, Linda
1 Under Section 303(d) of the Clean Water Act, Queen
Creek is identified as an “impaired water” due to
exceedances of the surface water quality standard for
copper. Generally, listing as an impaired water may
impact Clean Water Act permits
Effects to Water Resources from Baseline activities, including water
quality, are discussed in Section 3.3 of the preliminary EA.
0 ADEQ would agree with the PoO as to the need of
obtaining permit coverage under: · The Arizona
Pollutant Discharge Elimination System (AZPDES)
Program’s Construction General Permit, · The AZPDES
De Minimis General Permit, and Discharges of water,
drilling fluids, or drill cuttings from a well, such as for
water quality sampling, hydrologic parameter testing,
well development, redevelopment, or potable water
system maintenance and repair purposes, are authorized
under a 1.04 General Aquifer Protection Permit (APP)
as long as the drilling and testing operations for each
drilling location meet the rule requirements.
Chapter 3 of the preliminary EA evaluates the potential direct, indirect,
and cumulative effects of the proposed Baseline activities. The
Baseline Activities, which can reasonably be expected to result in any
discharges into waters of the United States, would be subject to
compliance with CWA Sections 401, 402, and/or 404 as applicable.
Letter 146 - Sorenson, Robert and Nancy
1 There are many folks, like us, who winter in the area
whose property would be detrimentally effected by this
proposal.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
2 Water pollution, air pollution, curtailing of recreational
activities, loss of wildlife habitat, and damage to
valuable historically and prehistorically significant sites
are just a few of the reasons that this location would be
unsuitable.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). The preliminary EA addresses effects
to Water Resources (Section 3.3), Air Quality (Section 3.13), Wildlife
and Special Status Species (Section 3.7), and Cultural Resources
(Section 3.9) for the proposed Baseline activities
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-36
Comment
Number Comment Response
3 Please reconsider the location of the tailings. It could be
placed in one of the abandoned pits from past mining
activities.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 147 - Frye, Bob
1 I have concerns with water quality and quantity. Any
action has to have an overall Watershed Analysis to
protect the public. Historically most of copper mining
operations in Arizona have created water quality issues.
It is critical that all future projects address and prevent
these problems.... What will be the environmental
effects of trenching? This action need to be addressed
along with the soil and watershed issues.
Effects to Water Resources from Baseline activities, including water
quality, are discussed in Section 3.3 of the preliminary EA.
2 This project as proposed will add to the loss of Sonoran
Desert bajada habitats.... The Sonoran Desert is home to
60 species of mammals, more than 350 kinds of birds, at
least l00 reptiles and 20 amphibians. How will this
project affect them? This issue needs to be addressed in
detail.
Effects to Wildlife and Special Status Species are evaluated in
Section 3.7 of the preliminary EA.
3 Recreation is a major use of the proposed area. Large
numbers of people from the surrounding Phoenix area
use it for a variety outdoor recreation including
camping, off road vehicles, hunting, sight-seeing, etc. A
baseline of recreational use needs to be developed.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
4 Well over 2000 native species of plants occur within the
Sonoran Desert. How many of these species are present
in the project area and how will they be affected? This is
issue that needs to be qualified and quantified. The
world famous Boyce Thompson Arboretum is adjacent
to the proposed site. Is this project a compatible use with
such important asset?
Baseline activities would not preclude activities at the arboretum.
Effects to Vegetation Communities are evaluated in Section 3.5 and
Visual effects are evaluated in Section 3.12 of the preliminary EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-37
Comment
Number Comment Response
5 Improvements to current secondary roads should be
minimized.
Resolution made modifications to their Proposed Action based on
internal and external scoping comments received during the Scoping
Period (Section 2.3 preliminary EA). Resolution made modifications
that would result in fewer disturbances to roads. Reclamation would be
implemented for previously disturbed areas and short-term temporary
access roads once Baseline activities have concluded
6 The visuals of this action need to be addressed A visual analysis was conducted for Baseline activities and impact
results documented in a Visual Resource Technical Report were used to
develop the analysis in Section 3.12 of the preliminary EA.
7 Why is this proposal is being presented as a minor
action when it is really a major environmental action
with long term affects?
From the analysis presented in the preliminary EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice.
8 Resolution was committed to sending all residents of
Queen Valley a notice of this proposed action along
with the opportunity to comment. Since this may not
have occurred I request an extension of the comment
period if there was indeed no such mailing.
The Legal Notice announcing the opportunity to comment on
Resolution’s proposed Baseline Plan was published in the Arizona
Capitol Times, the newspaper of record, on May 23, 2014, and on
May 21, 2014 in the Arizona Silver Belt. Consistent with CEQ
Regulations found at 40 CFR part 1501.7, affected and interested
persons were notified of the proposal with the mailing of a scoping
letter dated May 13, 2014. In addition, the proposal was uploaded to
the Forest’s Schedule of Proposed Actions (SOPA) on May 22, 2014.
Please notify the ID Team Leader at comments-southwestern-
[email protected] of any other residents in Queen Valley or neighboring
communities who wish to be included in the project mailing list.
9 The proposed action is connected to the proposed main
mine and should be treated as one environmental
review. This action should not be separated from the
overall proposed action.
Section 1.4 and 1.5.1 of the preliminary ES describe that this project is
a “stand alone” project and has separate utility; the development of the
deep underground copper ore body is not a connected action to the
Proposed Action, and therefore was not evaluated in the preliminary
EA. If Resolution were to proceed with development of the deep
underground copper ore body or other actions not addressed in this
preliminary EA, the potential effects on resources would be considered
in a separate review under NEPA and 36 CFR part 228A.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-38
Comment
Number Comment Response
10 Since this proposal is in support of a speculative and an
uncertain mine should new road construction be
allowed. I would think not.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Section 1.5.1 describes and discusses
potential connected actions to the Baseline activities.
11 What will be the environmental effects of trenching? Test trenches require a 60’x30’ area where vegetation and soils will be
disturbed to allow safe access of personnel to inspect and perform soil
infiltration tests. The test trenches would be reclaimed immediately
after all tests are complete.
Letter 148 - Soldan, Ted
1 I have to admit I’m astonished that such a toxic project
is even being taken seriously enough to warrant a study.
Particularly since this one so severely impacts an
important Native American site.
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known/identified
cultural resource sites that would be affected by the Baseline activities.
Letter 149 - Finstrom, Matt, Holly & Ariel
No Comments
Letter 150 - Freeman, Nancy
1 Trees of our forests are the Earth’s sentinels protecting
and ensuring the continuation of life. Trees provide
clean water, clean air, clean soil, shade and habitat. We
must protect them; they must flourish for life on the
Earth to continue.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 Personally, I want to continue enjoying the National
Forest and the benefits they bring to my health and the
health of the planet.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-39
Comment
Number Comment Response
3 the present Congress would be bypassing the laws
created by past Congresses if they were to pass the Land
Swap Bill HR-6B
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
4 Forests in the southwest were to be protected to preserve
rivers, streams and ponds to gather and conserve rain to
provide water for the growing western cities.
The Tonto National Forest management plan describes the multiple use
management goals, objectives and standards as described in Section 1.3
of the preliminary EA. Section 3.3 includes a discussion of the
applicable management goals, objectives, and standards for water
resources from the Tonto National Forest Land and Resource
Management Plan.
5 For the past four years, Resolution Copper has
continuously been pumping water from Shaft 9 and the
new Shaft 10.
Section 1.5.1 of the preliminary EA evaluates potential connected
actions to the Baseline activities, including the dewatering of Shaft No.
9 and Shaft No. 10. Chapter 3 of the preliminary EA evaluates the
potential direct, indirect and cumulative impacts from the proposed
Baseline activities, and several current and future projects, including
Shaft 9 and 10 are included in the cumulative effects analysis
(Section 3.2 and Table 3-1).
6 AIG assessed that the underground blasting would make
the nearby climbing areas unpredictably unstable and
therefore unsafe for recreational climbers. The entire
southwest is an earthquake zone
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). As part of the Baseline activities
blasting would not be required.
7 A company spokesperson said that 2,000 of the jobs
would be construction jobs to get the mine in operation.
There are already buildings at the site, so the principal
construction will be the struts and conveyance system at
7,000 feet (they start mining at the lowest depth). There
will be no Arizonan company capable of accomplishing
this kind of work. How long will these 2,000 jobs last?
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-40
Comment
Number Comment Response
8 When Resolution has a rally in Superior to gather
support, there are a number of miners present. I have
questioned them. They are all working miners at the
nearby Pinto Creek, Miami or Hayden mines. They have
no intention of working at Resolution’s operation.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
9 The current operations manager and almost half of the
management team are from Australia, South Africa and
Canada. [See http://resolutioncopper.com/about-us/].
And what taxes will the foreign managers be paying
here? David Salisbury, a former operations supervisor
told me, “Like all corporations, Rio Tinto will not pay
any Federal taxes. Senator John McCain said there
would be a billion dollars in the Federal coffers, but that
money will come from the federal income tax the
employees pay.” But what about the taxes the managers
will pay?
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
10 Resolution has already shown that they use out-of-state
contractors, as they used Boart Longyear out of Salt
Lake City (home of Rio Tinto’s Kennecott operation) to
do the explorative drilling project on National Forest
Lands between the Old Magma operations and Oak Flat
Campground. So how many of the jobs will go to
Arizonans?
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and therefore is not evaluated in this EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-41
Comment
Number Comment Response
11 I always say if you want to know how mining creates
prosperous communities, drive through Globe, Miami,
Hayden and Ray where mining has been going on
continuously for 100 years. There is not a single
indication, monument or decent building that there was
every any prosperity for the miners. Anyone who is
pretending that mining brings prosperity to a community
is perpetuating a myth. The money went to New York
City investors in the past, and now goes to foreign
investors.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
12 Resolution Copper admitted there would be subsidence
the size of Arizona’s “Meteor Crater,” which is nearly
one mile across, 2.4 miles in circumference and more
than 570 feet deep. No reclamation plan deals with this
huge crater and no reclamation plan can deal with this
huge crater.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-42
Comment
Number Comment Response
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
13 but mountain will be a great burden on the surrounding
landscape and watershed of the Tonto National Forest,
not” only for its size, but also for its contents of milled
heavy metals that can be released to the environment.
Will the heavy metals include radioactive components
that are so prevalent in Arizona’s bedrock that when the
EPA published a study on technologically enhanced
radioactive materials (TENORM), the analysis had been
conducted in Arizona mine sites.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
14 One must take into account the critical situation of water
levels in Arizona, which have been lowering
continuously for the past 100 years. When President
Roosevelt created National Forests in order for the
population of the Southwest to have sufficient water, he
had no idea of the impact that modern pit mining and
subsidized cotton farming would take on Arizona’s
water supply.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of the preliminary EA.
15 To alleviate the problem, the Federal Government
subsidized Central Arizona Project (CAP)-the largest
and most expensive aqueduct system ever constructed in
the United States at a cost of $3 billion to taxpayers. The
project was envisioned to provide water to nearly one
million acres of irrigated subsidized cotton land in
Maricopa, Pinal and Pima counties, as well as municipal
water for metropolitan areas of Phoenix and Tucson.
However, the problems of lowering water tables
continues, especially east of Phoenix:
http://www.azwater.gov/AzDWR/Hydrology/Geophysic
s/documents/LandSubsidencelnArizonaFactSheet_003.p
df
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-43
Comment
Number Comment Response
16 Resolution Cooper will be using major amounts of
water. The Freeport-McMoran Sierrita mine’s water use
for processing the ore is at 27,000 acre feet per year.
Section 1.5.1 of the preliminary EA evaluates potential connected
actions to the Baseline activities, including the dewatering of Shaft No.
9 and Shaft No. 10. Chapter 3 of the preliminary EA evaluates the
potential direct, indirect and cumulative impacts from the proposed
Baseline activities, and several current and future projects, including
Shaft 9 and 10 are included in the cumulative effects analysis
(Section 3.2 and Table 3-1).
17 Will the tailings contaminate Superior water? This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
18 One delay was the tailings location-the Pinto Valley
mine site idea was finally abandoned. (It’s still a useful
mine.)
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
19 Resolution has over 150 wells listed on the ADWR well
inventory. However, there is sparse information on the
pumping from most of wells. Further, the “Other”
category of 48 wells remains undefined. However, many
of the “Other” category were drilled to 7,000 feet, so it
is not likely that the wells are used to pump water.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of Resolution’s Plan is to collect hydrologic,
geochemical, and geotechnical data in order to provide baseline
information on these aspects of the environment over an area being
considered for a potential tailings storage site.
20 During the reclamation efforts by Resolution at the old
Magma smelter and mill site, they purchased water from
Arizona Water Company, reported at a public meeting
with the Superior Town Council to be some 200,000
gallons a month during their reclamation project at the
old mill, smelter and tailings site. This source of water
from the Florence Junction well field serves
communities. What effect will it have on current users?
Section 1.5.1 of the preliminary EA evaluates potential connected
actions to the Baseline activities, including the dewatering of Shaft No.
9 and Shaft No. 10. Chapter 3 of the preliminary EA evaluates the
potential direct, indirect and cumulative impacts from the proposed
Baseline activities, and several current and future projects, including
Shaft 9 and 10 are included in the cumulative effects analysis
(Section 3.2 and Table 3-1).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-44
Comment
Number Comment Response
21 That is to way when it comes to water, Resolution
Copper officials do not seem to have a clear concept of
Federal or Arizona water statutes.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
22 There needs to be a complete modeling of the hydrology
of the region and the impact on private wells in Supeior
region, Including • up to and Including wells up to and
including the town of Top of the World and private
ranchers In the region. Resolut;on Copper needs to be
proactive in analyzing the regional hydrology.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects from the Baseline activities to
Water Resources are discussed in Section 3.3 of preliminary EA.
23 When the United States reserves public land for uses
such as Indian reservations, military reservations,
national parks, forest, or monuments, it also implicitly
reserves sufficient water to satisfy the purposes for
which the reservation was created.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
24 Ramifications of having a mile wide and deep crater in
the area with corresponding waste piles from the
diggings, the sump caused by subsidence will dewater
the surrounding forests and private ranchers’ wells in
the region and will serve as a catchment basin for the
rainwater that would have been delivered to Devil’s
Creek.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
25 In the January, 2000, U. S. Forest Service report: Water
and the Forest Service,
[http://www.stream.fs.fed.us/publications/PDFs/Watera
ndFS.pdf] created by the FS National Headquarters
(with taxpayers money) emphasizes the importance of
forests for maintaining a viable, clean water supply.
Certainly, the situation has not changed, only worsened,
in thirteen years. The Forest Service is not living up to
its own publicly-stated mission and goals-or well
researched reports.
The Tonto National Forest management plan describes the multiple use
management goals, objectives and standards as described in Section 1.3
of the preliminary EA. Section 3.3 includes a discussion of the
applicable management goals, objectives, and standards for water
resources from the Tonto National Forest Land and Resource
Management Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-45
Comment
Number Comment Response
26 Many individuals are seriously concerned about the
possibility of intensive mining in Arizona, where water
is very short and precious, and biodiversity is unusually
high. Take any acre in an Arizona National Forest and I
guarantee, you will find more diversity in flora, fauna,
reptiles and insects than any forest in any other state.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).Impacts to resources from the
proposed Baseline activities are discussed in Chapter 3.
27 The mission of the USDA Forest Service is to sustain
the health, diversity, and productivity of the Nation’s
forests and grasslands to meet the needs of present and
future generations
The Tonto National Forest management plan describes the multiple use
management goals, objectives and standards as described in Section 1.3
of the preliminary EA. Section 3.3 includes a discussion of the
applicable management goals, objectives, and standards for water
resources from the Tonto National Forest Land and Resource
Management Plan.
Letter 151 - Begalke, Donald
1 DUMPING MINING TAILINGS DOES NOT
ENHANCE THE FOREST NOR PROTECT THE
FOREST.... TAILINGS’ DUMPING WOULD BE A
HORRIBLE DESTRUCTION OF TNF
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 MUST BE MAINTAINED FOR U.S. CITIZENS ‐ MANY WHO USE IT FOR HIKING, OTHER
RECREATIONAL REASONS, RESEARCHES, AND
PHOTOGRAPHY ...!!!!!!!
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-46
Comment
Number Comment Response
3 THE TNF IS VERY IMPORTANT FOR THE
WILDLIFE, THE BIRDLIFE, AND OTHER
NATURAL LIVES FOR IT IS THEIR HOME
APPROVED BY U.S. CITIZENS.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
4 THE 5‐SQUARE MILES OF THE TNF REQUEST
WOULD DESTROY THE WATER RESOURCES
REQUIRED BY THE NATURAL INHABITANTS
AND THE TREES, SHRUBS AND OTHER PLANTS,
PLUS THE QUEEN CREEK WATER SHED.
Effects to Water Resources from Baseline activities, including water
quality, are discussed in Section 3.3 in the preliminary EA. Impacts to
vegetation and wildlife are discussed in Sections 3.5 and 3.7,
respectively.
5 PLEASE, TELL THE RIO TONTO COMPANY THAT
THEIR MINING TAILINGS ARE NOT
COMPATIBLE WITH REGULATIONS FOR THE
TONTO NATIONAL FOREST!!!!!!!!!!!!!!!!!!!
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). As described in Section 1.4 of the preliminary EA, the
purpose of the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site.
Letter 152 - Summers, Shannon
1 There are Thousands of acres in the desert ... there has
got to be a better place for the tailings!
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 the place that is considered is in the middle of beautiful
trails close for people to enjoy hiking, 4 wheeling and
for hunters. It is close to people enjoying the beautiful
scenery
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-47
Comment
Number Comment Response
Letter 153 - Stevens, Dorothea
1 Toxic tailings Will destroy the beautiful desert and
animals, not to mention the surrounding communities.
The toxic damage is irreversible
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
2 The water use is too much for our dry land. This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 154 - Montgomery, Esq., Susan B.
1 please accept this email to reiterate the ITCA’s request
(made earlier today) that the Forest Service extend the
comment period on the Tailings plan until such time as
the Forest Service can make the requested documents
available to ITCA (and therefore its 21 member tribes)
for review.... the 30 day limitation is applicable ONLY
once the EA process has been undertaken ... at this point
you have not prepared a draft EA ... This is because you
are only in SCOPING and under NEPA should yet have
decided where to go from here (EA/EIS) — because this
is informed by scoping.
The Tonto National Forest welcomes your comments throughout the
NEPA process. During the NEPA process comments are considered as
they are received consistent with Forest Service NEPA regulations and
36 CFR 218. Public notification regarding the initial preparation of the
EA was conducted in accordance with CEQ and Forest Service NEPA
regulations.
Letter 155 - various
1 Resolution Copper’s Proposed Plan of Operations will
adversely impact the Apaches’ ability to harvest and use
certain plants within the Operations area for ceremonial,
religious, medicinal, and sustenance purposes.
Resolution would not close any areas to use during their Baseline
activities. Effects to Cultural Resources from the Baseline activities are
described in Section 3.9 of the preliminary EA. There are no known or
currently identified cultural resource sites that would be affected by the
Baseline activities.
2 the US Forest Service’s (“USPS’s”) review outlined in
the scoping letter contains numerous legal and factual
errors and as such should be revised in order to comply
with federallaw. ...any USFS plan to continue its review
The scoping letter sent on May 13, 2014 was based on the information
available at that time regarding Resolution’s proposed Baseline
activities. Since that time, there have been modifications to the
Proposed Action based on scoping comments. Section 2.3 of the
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-48
Comment
Number Comment Response
of the PoO must· comply with federal law as detailed
herein. At a minimum, if the agency proceeds with its
review, an Environmental Impact Statement (“EIS’ )
must be prepared due to the potential for _significant
impacts from the Project alone, and especially when
viewed with its cumulative impacts from other and/or
related activities as well as connected actions.
preliminary EA describes the revisions made by Resolution to the
proposed action.
3 THE EIS or EA MUST FULLY ANALYZE ALL
DIRECT, INDIRECT, AND CUMULATIVE
IMPACTS- INCLUDING FROM RESOLUTION’S
MAIN MINE PROPOSAL The scoping letter states that
the agency will unilaterally limit its review of direct,
indirect, and cumulative environmental impacts and
ignore the impacts from Resolution’s proposed large
mine which is directly linked to the Project. Yet under
the National Environmental Policy Act (“NEP A”), the
USFS must fully review the impacts from all “past,
present, and reasonably foreseeable future actions.”
These are the “cumulative effect/impacts” under NEPA.
To comply with NEP A, the USFS must consider all
direct, indirect, and cumulative environmental impacts
of the proposed action. 40 CFR §§ 1502.16, 1508.8,
1508.25(c).
Sections 1.4 and 1.5 of the preliminary EA describe that this project is
a stand alone project and has separate utility from other ongoing or
proposed activities, such as development of Resolution’s deep copper
ore body. Development of the deep underground copper ore body is not
a connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body or other actions
not addressed in this preliminary EA, the potential effects on resources
would be considered in a separate review under NEPA and 36 CFR part
228A.
4 A cumulative impact analysis must provide a “useful
analysis” that includes a detailed and quantified
evaluation of cumulative impacts to allow for informed
decision-making and public disclosure. Kern v. U.S.
Bureau of Land Management, 284 F.3d 1062, 1066 (9th
Cir. 2002); Ocean Advocates v. U.S. Army Corps
ofEngineers, 361 F.3d 1108 1118 (9th Cir. 2004). The
NEPA requirement to analyze cumulative impacts
prevents agencies from undertaking a piecemeal review
of environmental impacts. Earth Island Institute v. U.S.
Forest Service, 351 F.3d 1291, 1306-07 (9th Cir. 2003).
Section 3.2 of the preliminary EA describes the methodology used to
conduct the cumulative effects analysis for Resolution’s proposed
Baseline Plan. Each resource evaluated in Chapter 3 of the preliminary
EA was examined for potential cumulative effects consistent with CEQ
regulations (40 CFR part 1508.7; 40 CFR part 1508.8) and Forest
Service NEPA requirements (36 CFR 220; FSH 1909.15, Section 15.1).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-49
Comment
Number Comment Response
The NEPA obligation to consider cumulative impacts
extends to aU “past,” “present,” and “reasonably
foreseeable” future projects. Blue Mountains, 161 F.3d
at 1214-15; Kern, 284 F.3d at 1076; Hall v. Norton, 266
F.3d 969,978 (9th Cir. 2001) (finding cumulative
analysis on land exchange for one development failed to
consider impacts from other developments potentially
subject to land exchanges); Great Basin Mine Watch v.
Hankins, 456 F.3d 955, 971-974 (9th Cir.
2006)(requiring “mine-specific ... cumulative data,” a
“quantified assessment of their [other projects]
combined environmental impacts,” and “objective
quantification ofthe impacts” from other existing and
proposed mining operations in the region).
5 Oregon Natural Resources Council Fund v. Brong, 492
F.3d 1120, 1133 (91 h Cir. 2007). Note that the
requirement for a full cumulative impacts analysis is
required in an EA, as well as in an EIS. See Te-Moak
Tribe of Western Shoshone, 608 F.3d 592, 603 (9th Cir.
2010) (rejecting EA for mineral exploration that had
failed to include detailed analysis of impacts from
nearby proposed mining operations).
Section 3.2 of the preliminary EA describes the methodology used to
conduct the cumulative effects analysis for Resolution’s proposed
Baseline Plan. Each resource evaluated in Chapter 3 of the preliminary
EA was examined for potential cumulative effects consistent with CEQ
regulations (40 CFR part 1508.7; 40 CFR part 1508.8) and Forest
Service NEPA requirements (36 CFR 220; FSH 1909.15, Section 15.1).
6 NEPA regulations also require that the agency obtain
the missing “quantitative assessment” information:
When an agency is evaluating reasonably foreseeable
significant adverse effects on the human environment in
an environmental impact statement and there is
incomplete or unavailable information, the agency shall
always make clear that such information is lacking. (a)
If the incomplete information relevant to reasonably
foreseeable significant adverse impacts is essential to a
reasoned choice among alternatives and the overall costs
of obtaining it are not exorbitant, the agency shall
include the information in the environmental impact
Reasonably foreseeable actions which may have a cumulative effect on
surface resources have been analyzed in preliminary EA in Chapter 3,
Affected Environment and Environmental Consequences (Table 3-1;
Figure 3-1).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-50
Comment
Number Comment Response
statement. (b) If the information relevant to reasonably
foreseeable significant adverse impacts cannot be
obtained because the overall costs of obtaining it are
exorbitant or the means to obtain it are not known, the
agency shall include within the environmental impact
statement: (1) A statement that such information is
incomplete or unavailable; (2) a statement of the
relevance of the incomplete or unavailable information
to evaluating reasonably foreseeable significant adverse
impacts on the human environment; (3) a summary of
existing credible scientific evidence which is relevant to
evaluating the reasonably foreseeable significant
adverse impacts on the human environment, and (4) the
agency’s evaluation of such impacts based upon
theoretical approaches or research methods generally
accepted in the scientific community. For the purposes
of this section, “reasonably foreseeable” includes
impacts which have catastrophic consequences, even if
their probability of occurrence is low, provided that the
analysis of the impacts is supported by credible
scientific evidence, is not based on pure conjecture, and
is within the rule of reason.
7 CFR § 1502.22. “If there is ‘essential’ information at the
plan- or site-specific development and production stage,
[the agency] will be required to perform the analysis
under§ 1502.22(b).” Native Village of Point Hope v.
Jewell,--- F.3d ----, 2014 WL 223716, *7 (9th Cir.
2014). Here, the adverse impacts from the Project when
added to other past, present or reasonably foreseeable
future actions is clearly essential to the USPS’
determination (and dut-y to ensure) that the Project
complies with all legal requirements and minimizes all
adverse environmental impacts.
Section 3.2 of the preliminary EA describes the methodology used to
conduct the cumulative effects analysis for Resolution’s proposed
Baseline Plan. Each resource evaluated in Chapter 3 of the preliminary
EA was examined for potential cumulative effects consistent with CEQ
regulations (40 CFR part 1508.7; 40 CFR part 1508.8) and Forest
Service NEPA requirements (36 CFR 220; FSH 1909.15, Section 15.1).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-51
Comment
Number Comment Response
8 the USFS must fully consider the cmnulative impacts
from all past, present, and reasonably foreseeable future
projects in the region on, at a minimum, water and air
quality including ground and surface water quantity and
quality, recreation, cultural/religious, wildlife,
transportation/traffic, scenic and visual resources, etc.
At a minimmn, this requires the agency to fully review,
and subject such review to public comment in a draft
EA or EIS, the cumulative ·impacts from all other
mining, grazing, recreation, energy development, roads,
etc., in the region.
Section 3.2 of the preliminary EA describes the cumulative impact
methodology including the reasonably foreseeable future actions
considered. All of the resources considered in Chapter 3 were evaluated
for cumulative impacts.
9 the scoping letter is based on a seriously deficient view
regarding its duties to review these impacts. The agency
admits that Resolution has proposed a large-scale mine
in the area- indeed this Project is part of that proposal.
Yet, the scoping letter states that the USFS does not
intend on reviewing the cmnulative impacts (or any
impacts at all) from Resolution’s proposed mine.
Resolution has submitted other minerals-related
proposals to the Forest, such as the General Plan of
Operations. However, the impacts of that and other
proposals would be evaluated in separate NEP A
reviews. ...The agency s attempt to bypass review of
what clearly is a proposed mining plan for the “General
Mine (or “Main Mine’) violates NEPA. The fact that the
agency has yet to complete its review of this proposed
Main Mine does not mean that it is not “reasonably
foreseeable” under NEP A, as the company already
acknowledges it as a viable “proposed proj ect.” In New
Mexico x rel. Richardson v. Bureau of Land
Management, 565 F.3d 683,718-19 (lOth Cir. 2009), the
Tenth Circuit determined that future mineral activity
was “reasonably foreseeable” due to the fact that
“considerable exploration has already occurred on
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-52
Comment
Number Comment Response
parcels adjacent to the [challenged] parcel,” a
developable mineral deposit “is known to exist beneath
these parcels,” and the company “has concrete plans to
build” a mineral project on these lands. All of these
conditions are present here - as acknowledged by
Resolution. http://resolutioncopper.com/the-
project/mine-plan-of-operations/ (viewed June 22, 2014)
(Attachment B).
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
10 The Ninth Circuit has clearly held that proposed mining
projects must be fully reviewed in NEPA documents for
nearby projects. See Te-Moak Tribe of Western
Shoshone v. U.S. Dept. of / Interior, 608 F.3d 592, 603
(9th Cir. 2010) (rejecting EA for mineral exploration
that had failed to include detailed analysis of impacts
from nearby proposed mining operations). Even projects
that have not reached the formal proposal stage (which
is not the case here, since Resolution has already
submitted its Main Mine proposal to the USFS) are
considered “reasonably foreseeable” and must be
reviewed in this EA or EIS.
Section 3.2 of the preliminary EA describes the cumulative impact
methodology including the reasonably foreseeable future actions
considered. All of the resources considered in Chapter 3 were evaluated
for cumulative impacts.
11 [P]rojects need not be finalized before they are
reasonably foreseeable. “NEPA requires that an EIS
engage in reasonable forecasting. Because speculation is
... implicit in NEP A, [ ] we must reject any attempt by
agencies to shirk their responsibilities under NEPA by
labeling any and all discussion of future environmental
effects as crystal ball inquiry.” Selkirk, 336 F.3d at 962
(internal quotation marks and citation omitted). As the
Environmental Protection Agency (EPA) also has noted,
“reasonably foreseeable future actions need to be
considered even ifthey are not specific proposals.” EPA,
Consideration of Cumulative Impact Analysis in EPA
Review ofNEP A Documents, Office ofFederal
Activities, 12-13 (May 1999), available at http://www.
Section 3.2 of the preliminary EA describes the cumulative impact
methodology including the reasonably foreseeable future actions
considered. All of the resources considered in Chapter 3 were evaluated
for cumulative impacts.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-53
Comment
Number Comment Response
epa. gov I compliance/resources/policies/nepal
cumulative. pdf. (Attachment A)
12 Northern Plains Resource Council, Inc. v. Surface
Transp. Bd., 668 F.3d 1067, 1078-79 (9th Cir. 2011 ).
Additionally, the federal courts have routinely required
the agencies to review the ‘< impacts from future, not-
yet-proposed mineral activity when preparing EAs or
EISs for mineral leasing projects.
Section 3.2 of the preliminary EA describes the cumulative impact
methodology including the reasonably foreseeable future actions
considered. All of the resources considered in Chapter 3 were evaluated
for cumulative impacts.
13 Center for Biological Diversity v. Bureau of Land
Management, 937 F.Supp.2d 1140, 115’7 (N.D. Cal.
2013) citing City of Davis v. Coleman 521 F.2d 661,
676 (9th Cir.l975~ and Northern Plains, 668 F.3d at
1079. ee also, Connor v. Burford, 848 F.2d 1441 (9t Cir.
1988)(future impacts of drilling must be analyzed when
preparing NEPA document for oil and gas lease);
Colorado Environmental Coalition v. Office of Legacy
Management, 819 F.Supp.2d 1193, 1209-09 (D. Colo.
2011)(impacts from future, as-yet-un-proposed mining
must be considered when preparing NEP A document
for leasing decision).
Section 3.2 of the preliminary EA describes the cumulative impact
methodology including the reasonably foreseeable future actions
considered. All of the resources considered in Chapter 3 were evaluated
for cumulative impacts.
14 This [Resolution’s Main Mine] is in addition to any
other “past, present, or reasonably foreseeable futw-e
activity” in the area (e.g., grazing, ORV use, road use,
etc.). For example, federal and state agencies are
planning a major re-route/improvement of Highway 60
in the immediate area of the Project, with obvious
effects on natural resources, recreation, etc. See ADOT,
“U.S. Route 60 Superior to Globe Design Concept and
Environmental Impact Study,”
https://www.azdot.gov/projects/south-central!US- 60-
Superior-to-Globe-Design-Concept-and-EIS (viewed
June 22, 2014) (Attachment C); ADOT, “Scoping
Report, US 60 Superior to Globe,” (Attachment D).
Preliminary EA Section 3.2 and Table 3-1, describe the cumulative
projects evaluated including ADOT’s proposed improvement to
U.S. 60. The effects from past actions are described in the affected
environment for each resource analyzed in detail in Chapter 3 of the
preliminary EA.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-54
Comment
Number Comment Response
15 The scoping letter is wrong to argue that because this
Project is aimed at providing technical analysis for the
Main Mine, this means that the Main Mine is somehow
not “reasonably foreseeable.” Scoping letter at 5. NEPA
does not allow the agency to bifurcate its review on
these grounds. The USFS cannot ignore the undisputed
fact that the Main Mine is a proposal that has been
submitted by Resolution. Nov. 15,2013 letter from
Vicky Peacey, Senior Manager, Environmental and
External Affairs for Resolution Copper Mining LLC, to
Tonto Forest Supervisor Neil Bosworth (Attachment E).
Indeed, Resolution has highlighted to the public and
potential investors the fact that the Main Mine is a
viable mining proposal. “As promised, on November
15,2013 Resolution Copper filed a Mine Plan of
Operations with the U.S. Forest Service, which outlines
our detailed plans to design, construct and operate a
world-class mine. ‘ http://resolut.ioncopper.com/the-
project/mineplan- of-operations/ (viewed June 22, 2014)
(Attachment B).
Section 3.2 and Table 3-1 of the preliminary EA describes the
reasonably foreseeable projects included in the cumulative effects
analysis. These projects do not include the potential development of the
deep underground copper ore body; however, there are reasons given in
Section 3.2 as to why Resolution’s General Mine Plan of Operations is
not included in the cumulative effects analysis.
16 As the Main Mine PoO has been submitted to the USFS,
it (and any revisions) are part of the administrative
record for this Project, and incorporated into these
comments (along with all documents submitted by
Resolution regarding the Main Mine and this Project).
(Attachment B). Chapter One of the Main Mine PoO
also lists additional activities related to Main Mine that
have been proposed and/or approved (Tables 1.3-2 and
1.1.-3). Shown at:
http://49ghjw30ttw221aqro12vwhmu6s.wpengine.netdn
a-cdn.com/wp- content/uploads/20 13/12/resolution-
copper-plan-of-operations-volume-one-introduction.pdf
(viewed June 22, 2014) (attachment H). Each of these
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-55
Comment
Number Comment Response
activities are either direct, indirect, or cumulative
impacts that must be fully reviewed.
17 In addition to, and separate from, the agency’s duty to
review the cumulative and other impacts from the Main
Mine, NEP A requires that the Main Mine and the
Project be considered in one EA/EIS (certainly an EIS in
this case) as a “cmmected action” under NEP A. This is
because the Main Mine and the Project are part of one
interdependent mining project, as acknowledged by
Resolution. See Table 1.3-2 of the Main Mine PoO
http://49ghjw30ttw221aqro12vwhmu6s.wpengine.netdn
a-cdn.com/wpcontent/ uploads/20 13/ 12/reso lution-
copper-plan-of-operations-volume-one-introduction. pdf
(Attachment I) In that PoO Table and associated text,
Resolution admits that the “Baseline Hydrological &
Geotechnical Data Gathering Activities” “is being
conducted in support of the Resolution Copper Project
[the Main Mine].” Main Mine PoO at Vol. 1, p. 5.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
18 Even if the Mine could conceivably occur without the
previous or simultaneous occurrence of the Project (or
vice versa), which is not the case here, if it could not
occur without such actions it is a connected action and
must be considered within the same NEP A document as
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-56
Comment
Number Comment Response
the underlying action. “[E]ven though an action could
conceivably occur without the previous or simultaneous
occurrence of another action, if it would not occur
without such action it is a ‘connected action’ and must
be considered within the same NEPA document as the
underlying action.” Dine Citizens Against Ruining Our
Env’t v. Klein, 747 F. Supp. 2d 1234, 1254 (D. Colo.
2010). That is certainly the case here, as acknowledged
by Resolution, that the Project is an integral part of the
Main Mine, and would not occur but for the Main Mine.
Similarly, as also admitted by Resolution, the Main
Mine would not occur without this Project. As such,
they are considered “connected actions” under NEP A
and must be considered in one EIS.
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
19 Yet, as admitted by the scoping letter, the Project is not
proposed to explore or mine mineral resources. It is
simply a proposal to gather geologic, water, and related
information. The only legal way that Resolution can
arguably claim any “rights” or “entitlement” to use these
public lands is if the Project was part of an exploration
or mining project on public lands. But here, the scoping
letter, in an attempt to justify the agency’s refusal to
review the impacts from the Main Mine and related
proposals, says that the Project is not part of any mining
or exploration project. The agency and Resolution
cannot have it both ways. They cannot argue that the
The scoping letter primarily serves to notify the public of proposed
activities and includes a short summary of general legal issues. It is not
required to, nor can it exhaustively describe the nuances of the U.S.
Mining Laws. In summary, Congress has provided a limited delegation
of authority to the United States Forest Service in 16 U.S.C. 551, which
provides general authority to regulate use of the National Forests.
However that authority is limited in the context of management of
locatable mineral operation authorized under the Mining Laws. “Nor
shall anything in such sections prohibit any person from entering upon
such national forests for all proper and lawful purposes, including that
of prospecting, locating, and developing the mineral resources thereof.
Such persons must comply with the rules and regulations covering such
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-57
Comment
Number Comment Response
company has rights/entitlements under the Mining Law
based on the exploration or development of mineral
resources, yet divorce the Project from any plan to
conduct such exploration/development of minerals. In
other words, the Project is either part of an
exploration/mining proposal (and it is not exploration
since the company has already submitted its plan to
mine/develop the minerals), and the Mining Law
applies, or it is not. The scoping letter says that the
Project is not part of a mining plan. Thus, the alleged
rights/entitlements under the Mining Law do not apply.
On the other hand, for the Mining Law to apply the
USFS must consider the Project and the Main Mine
linked, and thus the “connected action” and/or
“cumulative impacts” requirements under NEPA
necessarily apply.
national forests.” 16 U.S.C. 478. The mining laws provide for a
statutory right of access and extraction (30 U.S.C. 22 & 26) and allow
for reasonable and incidental use without material interference (30
U.S.C. 612). The judicial interpretation of this complex set of laws is
that the Forest Service cannot categorically prohibit mining activity or
deny reasonable mineral operations under the mining laws (Havasupai
Tribe v. U.S. 752 F. Supp. 1471, 1492 (9th Cir. 1990)) and that the
Forest Service may not unreasonably restrict or delay approval of a
proposed plan of operations. (Baker v. USDA, 928 F. Supp. 1513 (D.
Id. 1996))
Resolution’s Baseline Plan, as described in Section 1.1 of the
preliminary EA, is subject to the regulations found at 36 CFR part 228,
subpart A. These regulations apply to all functions, work, and activities
in connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on NFS lands. Determining
the feasibility of a potential location for a tailings facility is considered
a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Plan
represents part of a logical sequence of activities, and has been found to
be reasonable for the stage proposed by Resolution (Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10). Resolution’s
Baseline Plan would provide baseline information on hydrologic,
geochemical, and geotechnical data from mining claims on NFS lands.
This information would be used to inform later separate actions and
proposals related to Resolution’s proposed General Plan of Operations.
As described in the EA, the Baseline Plan has independent utility from
the General Plan of Operations and that separate action would be
subject to a separate review and approval under NEPA and 36 CFR
Part 228, subpart A. Resolution is entitled to conduct operations that
are reasonably incidental to exploration and development of mineral
deposits on its unpatented mining claims pursuant to U.S. Mining
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-58
Comment
Number Comment Response
Laws. Under regulations of the U.S. Secretary of Agriculture,
Resolution must conduct mining operations with the requirements
found at 36 CFR Part 228, subpart A and in accordance with a plan of
operations that has been approved by the Forest Service.
20 Further, even if the USFS could ignore its duties under
its multiple use and other mandates and assume that the
company had a right under the Mining Law (which as
noted herein is wrong), ~j rights do not attach to the
right-of-ways and other FLPMA approvals needed for
the roads. Roads, even those across public land related
to a mining operation, are not covered by statutory
rights under the Mining Law. Alanco Environmental
Resources Corp., 145 IBLA 289, 297
(1998)(“construction of a road, was subject not only to
authorization under 43 C.F .R. Subpart 3809 [BLM
mining regulations], but also to issuance of a right-of-
way under 43 C.F.R. Part 2800 [BLM FLPMA Title V
regulations].”). “[A] right-of-way must be obtained prior
to transportation ofwater across Federal lands for
mining.” Far West Exploration, Inc., 100 IBLA 306,
308 n. 4 (1988) citing Desert Survivors, 96 IBLA 193
(1987). See also; Wayne D. Klump, 130 IBLA 98, 100
(1995) (“Regardless ofhis right of access across the
public lands to his mining claims and of his prior water
rights, use of the public lands must be in compliance
with the requirements of the relevant statutes and
regulations [FLPMA Title V and ROW regulations].”).
Although these cases dealt with BLM lands, they apply
equally to Forest Service lands. As noted in Alanco,
ROWs for access roads are subject to FLPMA’s Title V
requirements. The leading treatise on federal natural
resources law confirms this rule: “Rightsof- way must
be explicitly applied for and granted; approvals of
mining plans or other operational plans do not implicitly
Section 1.3 of the preliminary EA describes the laws, regulations, and
ordnances that the Forest Service must comply with, or will use in their
decision making process. Travel, transportation, and road management
on the Tonto National Forest are governed by the Tonto National
Forest Management Plan and Title 36 CFR, Part 212. Section 3.10 of
the preliminary EA also describes travel management and public safety
impacts.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-59
Comment
Number Comment Response
confer a right-of-way.” Coggins and Glicksman,
PUBLIC NATURAL RESOURCES LAW, §15.21
(emphasis added). ...USFS mining regulations consider
roads associated with the Project part of the mineral
“operations,” 36 CFR §228.3, does not override these
holdings or somehow create statutory rights where none
exist. The court in Mineral Policy Center v. Norton, 292
F.Supp.2d, 30 (D.D.C. 2003) specifically rejected the
federal government’s argument that all mining-related
operations were exempt from FLPMA’s ROW
requirements. 292 F.Supp.2d at 49-51 (“[I]f there is no
valid claim and the claimant is doing more than
engaging in initial exploration activities on lands open
to location, the claimants’ activity is not explicitly
protected by the Mining Law.”). Id.at 50.
21 Overall, the USFS must apply the proper discretionary
and public interest review applicable to Title V and its
USFS implementing regulations. This permitting regime
governs the agency’s position regarding NEP A
alternatives and mitigation analysis, as well as the
fundamental errors in assuming that Resolution has a
statutory right to receive approval of these roads.
Operations not conducted on “valid and perfected
claims” must comply with all ofFLPMA’s requirements,
including Title V’s SUP/ROW requirements. Mineral
Policy Center v. Norton, 292 F.Supp.2d 30, 49-51
(“[I]fthere is no valid claim and the claimant is doing
more than engaging in initial exploration activities on
lands open to location, the claimants’ activity is not
explicitly protected by the Mining Law.”). ld. at 50.
On National Forest system lands reserved from public domain and open
to entry under the Mining Law, the Forest Service is not required to
inquire into claim validity before processing and approving proposed
plans of operations. In order to prospect, explore, and make a discovery
of a valuable mineral deposit or establish valid mining claims, the
operator has a right under the 1872 Mining Law to enter upon national
forests and to conduct upon those lands reasonable activities to
prospect and explore for mineral resources. Exercise of this right does
not even require the staking of a mining claim, a fact recognized in the
Forest Service locatable mineral regulations at 36 CFR 228.3(a), where
mineral operations are defined and it is clearly stated that the Forest
Service’s regulations apply to all functions, work, activities, and uses
reasonably incidental to all phases of mineral exploration and mining
under the 1872 Mining Law, whether located on or off mining claims.
The General Mining Law of 1872, the Multiple Use Mining Act of
1955, and the regulations at 36 CFR 228 Subpart A, provide a
framework for the decision and the FLPMA requirements for
evaluation and collection of fair market value are not applicable to this
project.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-60
Comment
Number Comment Response
In its 2001 rulemaking BLM adopted a similar policy to the Forest
Service current policy. See 43 CFR 3809.5, defining ‘operations’
subject to approval under that part to include “reasonably incidental
uses, whether on a mining claim or not”. This policy of approving all
‘reasonably incidental uses’ under one approval mechanism for
locatable mineral operations was discussed at length in a judicial
challenge to the rule. See Mineral Policy Center v Norton, 292
F.Supp.2d 30 (D. D. C., 2003). This court upheld BLM’s regulation.
However it remanded to the Department of Interior for the limited
purpose of considering whether fair market value should be required
for use of unclaimed lands. In subsequent rulemakings BLM confirmed
that the normal practice of industry is to conduct activities on claimed
lands. See 72 Fed. Reg. 8139 (February 23, 2007) and 73 Fed. Reg.
73789 (December 4, 2008) “None of the comments presented factual
scenarios in which such ancillary uses took place in association with
operations on unclaimed lands that amount to more than initial
exploration activities” 73 Fed. Reg at 73791. BLM further noted that
the “court concluded that the Mining Law authorizes operations,
including possession, occupancy, and mineral extraction activities,
without payment of fair market value for that use.” Id. BLM adopted an
interim final rule that did not require FLPMA ‘fair market value’ fees
for such ancillary uses. Id.; see also 43 C.F.R. 3800.6
The Forest Service regulations and policy is consistent with existing
BLM regulation and policy and with the provisions of FLPMA and the
Mining Laws. The Forest Service interpretation in its regulations
implements a longstanding policy of the Forest Service to efficiently
administer locatable mineral operations including their ancillary uses
whether or not they are on mining claims. As indicated in BLM’s
lengthy rulemakings and litigation, many initial activities might occur
before claims are located. The application of 36 CFR Part 228 to the
authorization of all reasonably incidental and ancillary uses of Forest
Service lands, whether on or off mining claims, is consistent with
applicable law.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-61
Comment
Number Comment Response
22 the USFS has a mandatory duty under Section 505(a) to
impose conditions that “will minimize damage to scenic
and esthetic values and fish and wildlife habitat and
otherwise protect the environment.” Id. §1765(a)
(emphasis added). The terms ofthis section do not limit
“damage” specifically to the land within the ROW
corridor. Rather, the repeated use of the expansive term
“the environment” indicates that the overall effects of
the SUP/ROW on cultural, environmental, scenic and
aesthetic values must be evaluated and these resources
protected. In addition, the oblig’ation to impose terms
and conditions that “protect Federal property and
economic interests” in Section 505(b) supports an
expansive reading that the USFS must impose
conditions that protect not only the 1and crossed by the
right-of-way, but all federal land affected by the
approval of the SUP/ROW.2 ...the discretionary
requirements in Section 505(b) require a USFS
determination as to what conditions are “necessary” to
protect federal property and economic interests, as well
as “otherwise protect[ing] the public interest in the lands
traversed by the right-of-way or adjacent thereto.”
(emphasis added). This means that the agency can only
approve the SUP/ROW if it “protects the public interest
in lands” not only upon which the roads would traverse,
but also lands and resources adjacent to and associated
with the SUP/ROW. Thus, in this case, the USFS can
only approve the SUP/ROWs if all aspects of the
Project, and the Main Mine itself, “protect the public
interest.” The agency has made no showing that this is
the case here.
Section 3.12 of the preliminary EA describes potential effects on visual
resources including any proposed mitigation measures to minimize
effects. Section 2.3 describes revisions to the proposed action that also
minimized potential effects on resources including visual resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-62
Comment
Number Comment Response
23 The USFS cannot issue a SUP/ROW that fails to
“protect the environment” as required by FLPMA,
including the environmental resource values outside the
immediate ROW corridor. “FLPMA itself does not
authorize the Supervisor’s consideration of the interests
of private facility owners as weighed against
environmental interests such as protection of fish and
wildlife habitat. FLPMA requires all land-use
authorizations to contain terms and conditions which
will protect resources and the environment.” Colorado
Trout Unlimited v. U.S. Dept. of Agriculture, 320
F.Supp.2d 1090, 1108 (D. Colo. 2004)(emphasis in
original) appeal dismissed as moot, 441 F.3d 1214 (lOth
Cir. 2006). ...the agency must consider its duties under
FLPMA to protect public resources. “Federal law,
including the Federal Land Policy Management Act of
1976 (“FLMPA”) ‘specifically authorizes the Forest
Service to restrict such rights-of-way [granted by an
SUP] to protect fish and wildlife and maintain water
quality standards under federal law, . without any
requirement that the Forest Service defer to state water
law.’ County of Okanogan v. Nat’l Marine Fisheries
Serv .. 347 F.3d 1081,1086 (9th Cir.2003).” Sequoia
Forestkeeper v. U.S. Forest Service, 2010 WL 5059621,
*19 (E.D. Cal. 2010), amended on reconsideration, 2011
WL .902120 (E.D. Cal. 2011). The court also held that
the USFS failed to consider its SUP authorities during
the scoping process in violation ofNEPA: “The USPS’s
erroneous conclusion that it had no authority to
condition the SUP to require minimum bypass flows or
other rights-ofway restrictions led to its unreasonable
failure to consider the requests to do so in its scoping
period.” Sequoia Forestkeeper v. U.S. Forest Service,
2010 WL 5059621, *21. The fact that that case dealt
Section 2.3.6 of the preliminary EA includes the Applicant-proposed
environmental commitments. Additional mitigation measures proposed
to protect the environment are included in applicable resource sections
of Chapter 3 and also summarized in Section 2.5.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-63
Comment
Number Comment Response
with an SUP for a water conveyance, rather than a road,
is not relevant, as the same SUP/ROW requirements to
protect public resources apply equally in both situations.
24 The Department specifically noted that under FLPMA
Title V: “[A]s BLM has held, it is not private interests
but the public interest that must be served by the
issuance of a right-of-way.” 126 IBLA at 342, 1993 WL
417949 at *3 (emphasis added). The Forest Service
Manual also requires that the project be covered by the
ROW/SUP regime. Forest Service Manual 2730
provides direction regarding road rights of way. It states
the following regarding FLMP A rights of way: “Grant
all road rights-of-way under Title V of the Federal Land
Policy and Management Act with the exception of: 5.
Road constructed on valid mining claims or mineral
lease areas when the construction is authorized by an
approved operating plan (36 CFR part 228 and FSM 281
0).” Thus, regarding the roads in this case, the Manual
requires that a FLPMA Title V authorization is required
for roads “except’ for Roads constructed on valid
mining claims.” Thus, even ifthe agency’s legal position
that authorization of roads and related facilities is
considered a “right” under the Mining Law and
approved via the Part 228 regulations was correct -
which as shown herein it is not - this is true only for
such facilities/uses “on valid mining claims.’
Section 1.5.2 of the preliminary EA discusses the Forest Service
decision framework in relation to the proposed Baseline Plan of
Operations.
25 The record contains no evidence whatsoever that the
lands to be crossed by the roads and technical facilities
are covered by “valid mining claims.” Under the Mining
Law, in order to be valid, mining claims must contain
the “discovery of a valuable mineral deposit.” 30 U.S.C.
§ 22. Under the “marketability” test, it must be shown
that the mineral can be “extracted, removed and
marketed at a profit.” United States v. Coleman, 390
On National Forest system lands reserved from public domain and open
to entry under the Mining Law, the Forest Service is not required to
inquire into claim validity before processing and approving proposed
plans of operations. The Forest Service has the discretion to challenge
claim validity at any time before patent of the claim. Forest Service
Manual, § 2814.11. However it is not required to review claim validity
to review and approve a plan of operations for a mine on lands open to
mineral entry. Western Shoshone Defense Project, 160 IBLA 32, 56
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-64
Comment
Number Comment Response
U.S. 599, 600 (1968). According to the “prudent-
person” test, “the discovered deposits must be of such a
character that a person of ordinary prudence would be
justified in the further expenditure of his labors and
means, with a reasonable prospect of success, in
developing a valuable mine.” Id. at 602. The Supreme
Court has held that profitability is “an important
consideration in applying the prudent-man test and the
marketability test,” and noted that” ... the prudent-man
test and the marketability test are not distinct standards,
but are complementary in that the latter is a refinement
of the former.” I d. at 602-603.
(August 21, 2003) (BLM not required to review mining claim validity
before approving mining plan of operations.)
The Forest Service regulations and policy are consistent with existing
Department of Interior policy on determination of mining claim
validity. See M- 37012, Legal Requirements for Determining Mining
Claim Validity Before Approving A Mining Plan of Operations
(November 14, 2005); Great Basin Resource Watch and Western
Shoshone Defense Project, 182 IBLA 55 (2012).
26 In order to successfully defend rights to occupy and use
a claim for prospecting and mining, a claimant must
meet the requirements as specified or implied by the
mining laws, in addition to the rules and regulations of
the USFS. These require a claimant to: ... 2. Discover a
valuable mineral deposit. ... (and) 7. Be prepared to
show evidence of mineral discovery. FSM 2813.2. “A
claim unsupported by a discovery of a valuable mineral
deposit is invalid from the time of location, and the only
rights the claimant has are those belonging to anyone to
enter and prospect on National Forest lands.” FSM
§2811.5.
The Forest Service is not required to inquire into claim validity before
processing and approving proposed plans of operations. Consistent
with Forest Service Manual 2800, Minerals and Geology, Chapter
2810, Section 2817.23, approval of an operating plan does not
constitute now or in the future recognition or certification of the
validity of any mining claim to which it may relate or to the mineral
character of the land on which it lies. Forest Service regulations require
that all locatable mineral operations must be conducted to minimize,
prevent or mitigate adverse environmental impacts to surface resources.
The purpose of this project is to collect hydrological, geochemical and
geotechnical data in order to provide baseline information on these
aspects of the environment over an area being considered for a potential
tailings storage site; therefore, the proposed Plan is considered to be
reasonably incident to mining.
27 In addition to the lack of any evidence that the claims to
be crossed by the roads are valid under the Mining Law,
it is almost certain the Project’s activities are on lands
far from the mineralized zone and do not contain the
requisite valuable mineral deposit. Indeed, it is likely
that these lands contain common varieties of rock that
are not even considered locatable minerals under federal
mining law.
In order to prospect, explore, and make a discovery of a valuable
mineral deposit or establish valid mining claims, the operator has a
right under the 1872 Mining Law to enter upon national forests and to
conduct upon those lands reasonable activities to prospect and explore
for mineral resources. Exercise of this right does not even require the
staking of a mining claim, a fact recognized in the Forest Service
locatable mineral regulations at 36 CFR 228.3(a), where mineral
operations are defined and it is clearly stated that the Forest Service’s
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-65
Comment
Number Comment Response
regulations apply to all functions, work, activities, and uses reasonably
incidental to all phases of mineral exploration and mining under the
1872 Mining Law, whether located on or off mining claims.
28 Forest Service rules (Region 3’s FSM 2500, Chapter
2540 Water Use and Development) (Attachment J) also
state that special use authorization is necessary for this
project as it is a consumptive water use on the National
Forest. Since 1872 General Mining Law does not apply
here, a special use permit would be required and would
also require an examination of the water developments
in the project and consideration of their potential to
impact groundwater, streams, springs, seeps and
associated riparian and aquatic ecosystems. ...
Accordingly, the agency’s decision to review and
approve these facilities solely through the Part 228 PoO
process violates federal law. Any review and regulation
ofthe proposed activities must occur under the legally-
correct permitting regime.
As described in Section 2.3 of the preliminary EA, water sources for
the proposed Baseline activities would be provided by privately held
water suppliers. Section 3.3 evaluates water resources including surface
and ground water sources.
29 the scoping letter states that: “Resolution is entitled to
conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its
unpatented mining claims pursuant to U.S. Mining
Laws.” Scoping letter at 1. The agency further states,
that due to this alleged “entitlement,” the agency must
approve the Project and cannot choose the no action
alternative: “[D]ue to the statutory rights afforded by the
U.S. Mining Laws; the Forest Service cannot select the
No Action alternative as a preferred alternative.”
Scoping letter at 4. “The statutory right of Resolution to
mine mineral resources on federally administered lands
is recognized in the General Mining Law of1872.” ld.
Consistent with 36 CFR part 228 subpart A, and Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10, reasonably
incident is defined as “prospecting, mining, or processing operations
and uses reasonably incident thereto” (30 U.S.C. 612). It means
reasonable and necessary uses of National Forest System lands for
purposes that reflect sound practices that avoid or minimize adverse
environmental impacts and are required for the various stages of
mineral operations.
30 Yet this position violates the FLPMA and the 1872
Mining Law, by not requiring Resolution to pay Fair
Market Value (FMV) for the use of public lands not
The General Mining Law of 1872, the Multiple Use Mining Act of
1955, and the regulations at 36 CFR 228 Subpart A provide a
framework for the decision and the FLPMA requirements for
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-66
Comment
Number Comment Response
covered by valid mining claims, based on the lack of
any evidence that the vast majority of the mining claims
(or indeed any claims at all) at the Project site contain
locatable minerals and the requisite discovery of a ~~
valuable mineral deposit. Similarly, the agency’s
position also violates provisions ofFLPMA and the
Multiple Use Sustained Yield Act, NFMA, 1897
Organic Act, and other laws mandating that the agencies
manage, or at least consider managing, these lands for
non-mineral uses - something which the USFS refuses
to do or consider in this case.
evaluation and collection of fair market value are not applicable to this
project. Multiple-use management of the National Forest System lands
within the proposed project area will continue during implementation
of Resolution’s Baseline plan. Please see responses to submission letter
number 155, comments 232 and 226.
31 The scoping letter is based on the overriding assumption
that Resolution has statutory rights to use all of the
public lands at the site under the 1872 Mining Law.
However, where Project lands have not been verified to
contain, or do not contain, such rights, the USFS’ s
more discretionary multiple-use authorities apply. See
Mineral Policy Center v. Norton, 292 F.Supp.2d 30, 46-
51 (D.D.C. 2003) (although that case dealt with Interior
Department lands, the same analysis applies to USFS
lands).
Consistent with 36 CFR part 228 subpart A, and Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10, reasonably
incident is defined as “prospecting, mining, or processing operations
and uses reasonably incident thereto” (30 U.S.C. 612). It means
reasonable and necessary uses of National Forest System lands for
purposes that reflect sound practices that avoid or minimize adverse
environmental impacts and are required for the various stages of
mineral operations.
32 The Mineral Policy Center court specifically recognized
the federal government’s duty to apply its broader,
multiple use authority when mineral-related operations
are proposed on lands not subject to valid and perfected
claims: While a claimant can explore for valuable
mineral deposits before perfecting a valid mining claim,
without such a claim, she has no property rights against
the United States (although she may establish rights
against other potential claimants), and her use of the
land may be circumscribed beyond the UUD standard
because it is not explicitly protected by the Mining Law.
292 F.Supp.2d at 47 (emphasis added). Although the
“UUD standard” was at issue in that case (BLM’s duty
Consistent with 36 CFR part 228 subpart A, and Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10, reasonably
incident is defined as “prospecting, mining, or processing operations
and uses reasonably incident thereto” (30 U.S.C. 612). It means
reasonable and necessary uses of National Forest System lands for
purposes that reflect sound practices that avoid or minimize adverse
environmental impacts and are required for the various stages of
mineral operations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-67
Comment
Number Comment Response
to “prevent unnecessary or undue degradation” under
FLPMA), the holding that development “rights” under
the mining laws only apply to lands covered by valid
claims applies equally to the USFS and BLM. The court
was equally clear as to what was required to “perfect” a
mining claim: The Mining Law gives individuals the
right to explore for mineral resources on lands that are
“free and open” in advance of having made a
“discovery” or perfected a valid mining claim. United
States v. Locke, 471 U.S. 84, 86, 105 S.Ct. 1785, 85
L.Ed.2d 64 (1985). The Mining Law provides, however,
that a mining claim cannot be perfected “until the
discovery of the vein or lode.” 30 U.S.C. § 23.
33 in its review of the Project, the USFS erroneously
believes that it does not have this “wide discretion” to
“approve or disapprove” any part of the PoO. The fact
that Resolution proposes to use mining claims for
ancillary operations does not mean automatically, that
each mining claim is invalid. The Mining Lav does not
prohibit any and all uses of a mining claim for milling
or processing activities. Indeed, a 1955 enactment of
Congress specifically authorizes the use of mining
claims for prospecting mining or pr cessing operations
and uses reasonably incident thereto.” Surface
Resources Act of 1955, 30 U.S.C. § 601,603, 611-615.3
However, the 1955 Act did not create any surface use
rights independent of the underlying mining clmm. This
is because the overall intent ofthe 1955 Act was to limit,
not expand, mining claimants’ rights. See generally
Clayton J. Parr & Dale A. Kimball, “Acquisition ofNon-
Mineral Land for Mine Related Purposes,” 23 Rocky
Mtn. Min. L. Inst. 595,635-36 (1977). The 1955 Act
must therefore be read as not altering the principle that
the right of a mining claimant to use the surface of a
Consistent with 36 CFR part 228 subpart A, and Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10, reasonably
incident is defined as “prospecting, mining, or processing operations
and uses reasonably incident thereto” (30 U.S.C. 612). It means
reasonable and necessary uses of National Forest System lands for
purposes that reflect sound practices that avoid or minimize adverse
environmental impacts and are required for the various stages of
mineral operations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-68
Comment
Number Comment Response
mining claim is derived from the right to mine the
discovered mineral deposit. In other words, although the
1955 Act authorizes “reasonably incident” uses,
discovery is still required on each claim in order to
establish rights against the United State;j Consequently
{if a mining claim is proposed to be used solely for
activities that are “reasonably incident” to extracting
minerals from other lands, it must be supported by the
requisite discovey. This is especially true because
federal courts have long and consistently held that a
mining claimant’s right to use an unpatented mining
claim is limited to purposes connected with the removal
of minerals from that claim, and not for other purposes.
See, e.g., Teller v. United States, 113 F. 273 (8th Cir.
1901); United States v. Rizzinelli, 182 F. 675 (D. Idaho
19l.0).
34 The leading mining industry treatise stated: Several
early cases recognized the right of an operator to occupy
and use unoccupied public domain in connection with
mining operations. However, it is doubtful that such
rights continue to exist in light of the comprehensive
land use procedures adopted in the Federal Land Policy
and Management Act of 1976. When ground is held by a
mining claim that is not valid, an operator’s rights are
limited to those conferred under the doctrine of pedis
possesio.
It is not common practice, nor is it Forest Service policy to challenge
mining claim validity, except when (a) proposed operations are within
an area withdrawn from mineral entry; (b) when a patent application is
filed; and (c) when the agency deems that the proposed uses are not
reasonably incidental to mineral exploration. For operations proposed
in accordance with Forest Service regulations, and where the above
situations do not exist, conducting a validity exam is not consistent
with Forest Service policy.
35 USFS cannot in this case determine that Resolution is
“entitled” under the Mining Law to use its claims for
roads and scientific studies, etc., when there is no
evidence in the record that those claims are supported by
any rights under the Mining Law against the United
States.
Consistent with 36 CFR part 228 subpart A, and Forest Service
Handbook 2809.15, Minerals and Geology, Chapter 10, reasonably
incident is defined as “prospecting, mining, or processing operations
and uses reasonably incident thereto” (30 U.S.C. 612). It means
reasonable and necessary uses of National Forest System lands for
purposes that reflect sound practices that avoid or minimize adverse
environmental impacts and are required for the various stages of
mineral operations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-69
Comment
Number Comment Response
36 A proper application ofUSFS’s multiple use, public
interest, and sustained yield mandates to those areas not
covered by valid claims would result in a very different
Project review, alternatives, and level of protection for
public land resources and values, as well as reducing or
eliminating the adverse impacts to the use of these lands
by members of the public. Regarding the requirement
for the federal government to obtain FMV [fair market
value]for the use of lands not covered by valid claims,
under FLPMA, “the United States [must] receive fair
market value of the use of the public lands and their
resources unless otherwise provided for by statute.” 43
U.S.C. §1701(a)(9). The Mineral Policy Center court
held that unless the lands were covered by valid claims
(i.e. the situation “otherwise provided for by statute” in§
01(a)(9)), the agencies must comply with their FMV
duty.
It is not common practice, nor is it Forest Service policy to challenge
mining claim validity, except when (a) proposed operations are within
an area withdrawn from mineral entry; (b) when a patent application is
filed; and (c) when the agency deems that the proposed uses are not
reasonably incidental to mineral exploration. For operations proposed
in accordance with Forest Service regulations, and where the above
situations do not exist, conducting a validity exam is not consistent
with Forest Service policy. The activities proposed in Resolution’s
Baseline Plan are considered to be reasonably incidental to mineral
exploration as per 36 CFR part 228, subpart A, and as such they can be
authorized regardless of whether they are on or off mining claims.
37 USFS has failed to even consider the application of its
multiple use authority, and related FMV requirements as
mandated by Mineral Policy Center- a violation
ofFLPMA, the Mining Law, and their multiple-use
mandates, as well as being an arbitrary and capricious
decision under the Administrative Procedure Act (AP
A). As noted above,ftis likely that these lands contain
common varieties of rock that are not even considered
locatable minerals under federal mining law, which is a
prerequisite for claim validity. See 30 U.S.C. § 22 (only
“valuable mineral deposits” are covered by the Mining
Law); 30 U.S.C. § 611 (“common varieties” of minerals
are not locatable under the Mining Law).
Section 1.4 of the preliminary EA contains a description of the purpose
and need for the proposed Baseline activities. At this time a decision
regarding the proposed Baseline activities has not been made and the
preliminary EA is part of the Forest Service decision process as
described in Section 1.5.2.
38 As stated in the USFS Minerals Manual: “In order to
successfully defend rights to occupy and use a claim for
prospecting and mining, a claimant must meet the
requirements as specified or implied by the mining laws,
Resolution Copper Mining, LLC has proposed to conduct baseline data
gathering activities on the Tonto National Forest in their proposed
Baseline Plan. It is not Forest Service policy to inquire as to the mineral
composition of the subsurface. Consistent with Forest Service Manual
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-70
Comment
Number Comment Response
in addition to the rules and regulations of the USFS.
These require a claimant to: ... 2. Discover a valuable
mineral deposit .... (and) 7. Be prepared to show
evidence of mineral discovery.” FSM 2813.2 (emphasis
added). Under the Mining Law, in order to be valid,
mining claims must contain the “discovery of a valuable
mineral deposit.” 30 U.S.C. § 22. See herein discussion
of the test for valid claims. According to the USFS
Minerals Manual: “A claim unsupported by a discovery
of a valuable mineral deposit is invalid from the time of
location, and the only rights the claimant has are those
belonging to anyone to enter and prospect on National
Forest lands.” FSM §2811.5. The term “valid claim”
often is used in a loose and incorrect sense to indicate
only that the ritualistic requirements of posting of
notice, monumentation, discovery work, recording,
annual assessment work, payment of taxes, and so forth,
have been met. This overlooks the basic requirement
that the claimant must discover a valuable mineral
deposit. Generally, a valid claim is a claim that may be
patented.
2800, Chapter 2810 Mining Claims, Section 2811.5, a mining claim
may lack the elements of validity and be invalid in fact, but it must be
recognized as a claim until it has been finally declared invalid by the
Department of Interior or Federal courts.
39 the USFS should inquire as to whether the Project lands
contain “common varieties” or “valuable mineral
deposits.” The USFS recognizes that a valid claim under
the Mining Law cannot be made for common variety
minerals. “The 1955 Multiple-Use Mining Act (69 Stat.
367; 30 U.S.C. 601, 603, 611-615) amended the United
States mining laws in several respects. The act provides
that common varieties of mineral materials shall not be
deemed valuable mineral deposits for purposes of
establishing a mining claim.” FSM §2812. Alhough a
complete mineral report and claim validity verification
is not required for every single proposal, the agency
must have evidence that the claims meet the legal
Resolution Copper Mining, LLC has proposed to conduct baseline data
gathering activities on the Tonto National Forest in their proposed
Baseline Plan. It is not Forest Service policy to inquire as to the mineral
composition of the subsurface. Consistent with Forest Service Manual
2800, Chapter 2810 Mining Claims, Section 2811.5, a mining claim
may lack the elements of validity and be invalid in fact, but it must be
recognized as a claim until it has been finally declared invalid by the
Department of Interior or Federal courts.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-71
Comment
Number Comment Response
prerequisites to establish rights under the Mining Law.
At a minimum, evidence needs to be in the record
supporting val.id rights under the mining law if the
agency revjews and approves land uses tmder an
assumed right under the Mining Law- rights that accrue
on1y if based on valid claims as shown by the legal
decisions noted herein.
40 The Project proposes an extensive network of roads,
drilling sites, and support facilities across a large area.
These activities will adversely impact a number of
critical public resources such as air, water (surface and
ground, quantity and quality), wildlife, recreation
visual/scenic, cultural/religious historical, etc. As noted
above, each of these potential impacts must be fully
reviewed, not just in the immediate location of the
impact, but on a regional scale. In addition, the agency
must prepare for public review a detailed analysis of the
current baseline conditions for all potentially affected
resources, both at the immediate site locations, but also
nearby and regionally (e.g., baseline current conditions
of Queen Creek and any and all impacts to the nearby
Boyce Thompson Arboretum).
The affected environment, or baseline conditions for Baseline
activities, was evaluated for Water Resources, Soil Resources,
Vegetation Communities and Fire Regimes, Invasive Species, Wildlife
and Special Status Species, Range, Cultural Resources, Travel
Management and Public Safety, Recreation, Visual Resources, Air
Quality, Climate Change, and Noise in Chapter 3 of the preliminary
EA.
41 The impacts from this project to the towns of Superior
and Queen Creek must also be fully reviewed.
The baseline conditions evaluated in the preliminary EA for Baseline
activities, include: Water Resources, Soil Resources, Vegetation
Communities and Fire Regimes, Invasive Species, Wildlife and Special
Status Species, Range, Cultural Resources, Travel Management and
Public Safety, Recreation, Visual Resources, Air Quality, Climate
Change, and Noise. Please refer to Chapter 3 to review the analysis.
42 The USFS is required to “describe the environment of
the areas to be affected or created by the alternatives
under consideration.” 40 C.F.R. § 1502.15. The
establishment ofthe baseline conditions ofthe affected
environment is a fundamental requirement ofthe NEPA
process: “NEP A clearly requires that consideration of
Chapter 3 of the preliminary EA includes a description of the affected
environment that is consistent with 40 CFR 1502.15. The affected
environment descriptions establish the baseline for the environmental
consequences analysis. Chapter 3 of the preliminary EA includes a
description of the environmental consequences as well.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-72
Comment
Number Comment Response
environmental impacts of proposed projects take place
before [a final decision] is made.” LaFlamme v. FERC,
842 F.2d 1063, 1071 (9th Cir.1988) (emphasis in
original). Once a project begins, the “pre-project
environment” becomes a thing of the past, thereby
making evaluation of the project’s effect on pre-project
resources impossible. Id. Without establishing the
baseline conditions which exist in the vicinity ... before
[the project] begins, there is simply no way to determine
what effect the proposed [project] will have on the
environment and, consequently, no way to comply with
NEPA.
43 Such baseline information and analysis must be part of
the EA/EIS and be subject to public review and
comment under NEP A. The lack of an adequate
baseline analysis fatally flaws an EA or EIS. “[O]nce a
project begins, the pre-project environment becomes a
thing ofthe past and evaluation of the project’s effect
becomes simply impossible.” Northern Plains v. Surf.
Transp. Brd., 668 F.3d 1067, 1083 (9th Cir. 2011).
“[W]ithout [baseline] data, an agency cannot carefully
consider information about significant environment
impacts. Thus, the agency fail[s] to consider an
important aspect of the problem, resulting in an arbitrary
and capricious decision.” Id. at lO85.
Chapter 3 of the preliminary EA includes a description of the affected
environment that is consistent with 40 CFR 1502.15. The affected
environment descriptions establish the baseline for the environmental
consequences analysis. Chapter 3 of the preliminary EA includes a
description of the environmental consequences as well.
44 In Idaho Conservation League, 2012 WL 3758161 (D.
Idaho 2012), the Idaho federal court concluded that the
Forest Service acted arbitrarily and capriciously by
authorizing exploratory hardrock mineral drilling
without fully analyzing the baseline groundwater and
hydrology. Id. at * 17. Such analysis should include “a
baseline hydrogeologic study to examine the existing
density and extent of bedrock fractures, the hydraulic
conductivity of the local geologic formations, and
The purpose of this project is to collect baseline hydrological,
geochemical, and geotechnical data on these aspects of the environment
on an area that may be considered for a potential tailings storage site
(Section 1.4).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-73
Comment
Number Comment Response
[measures ofJ the local groundwater levels to estimate
groundwater flow directions.” Idaho Conservation
League, 2012 WL 3 7 5 8161, at * 16. See also
Shoshone- Bannock Tribes of Fort Hall Reservation v.
U.S. Dept. oflnterior, 2011 WL 1743656, at *10 (D.
Idaho 2011).
45 prior to considering or approving any exploration, the
Forest Service must first obtain this required baseline
information and subject the information and analysis to
public review and comment in a Draft EA or EIS. I
“NEP A requires that the agency provide the data on
which it bases its environmental analysis. Such analyses
must occur before the proposed action is approved, not
afterward.” Northern Plains, 668 F.3d at 1083 (internal
citations omitted) (concluding that an agency’s “plans to
conduct surveys and studies as part of its post-approval
mitigation measures,” in the absence of baseline data,
indicate failure to take the requisite “hard look” at
environmental impacts). This requirement applies not
only to ground and surface waters, but any potentially
affected resource such as air quality, recreation, soils,
cultural/historical, wildlife, etc.
Chapter 3 of the preliminary EA includes a description of the affected
environment that is consistent with 40 CFR 1502.15. The affected
environment descriptions establish the baseline for the environmental
consequences analysis. Chapter 3 of the preliminary EA includes a
description of the environmental consequences as well.
46 The Project poses potentially significant risks to wildlife
(including indicator, sensitive, II threatened and
endangered species) and wildlife habitat, groundwater
and surface water resources, cultural/historical, air
quality, recreation, and other resources. It should be
noted that, without the required baseline analysis, it is
impossible to fully ascertain the level of threats to public
land resources. Because of the potentially significant
impacts, an EIS is required.
The preliminary EA addresses effects to Wildlife and Special Status
Species (Section 3.7), Water Resources (Section 3.3), Cultural
Resources (Section 3.9), Air Quality ( Section 3.13), Recreation
(section 3.11), and several other resources for Baseline activities. If,
after preparation and review of the EA, the Forest Service determines
there are no significant impacts from the Baseline activities, then they
would prepare a Finding of No Signification Impact (FONSI), or they
may determine an EIS is required if there are significant impacts
identified.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-74
Comment
Number Comment Response
47 due to the agency’s decision not to review all
cumulative impacts or connected actions, the agency’s
decision to not prepare an EIS (i.e., proposed FONSI)
violates NEP A, as the lack of an adequate connected
action/cumulative actions/impacts analysis necessarily
renders any FONSI inadequate and arbitrary and
capricious.
Section 3.2 of the preliminary EA contains a discussion of the
cumulative impact analysis methodology used to evaluate potential
effects on resources.
48 in this case, the agency’s admitted failure to fully review
all direct, indirect, and cumulative impacts, and
connected and cumulative actions, will necessarily
render the EA deficient. As such, the USPS cannot issue
a FONSI. Without the required review of baseline
information, and the potential direct, indirect, and
cumulative impacts ofthe Project, any decision not to
prepare an EIS would be without sufficient evidentiary
support.
Chapter 3 of the preliminary EA describes the potential direct, indirect,
and cumulative impacts on resources.
49 Under NEP A, the agency must have an adequate
mitigation plan to minimize or eliminate all potential
project impacts. NEPA requires the agency to: (1)
“include appropriate mitigation measures not already
included in the proposed action or alternatives,” 40 CFR
§ 1502.14(f); and (2) “include discussions of: ... Means
to mitigate adverse environmental impacts (if not
already covered under 1502.14(±)).” 40 CFR §
1502.16(h). NEPA regulations define “mitigation” as a
way to avoid, minimize, rectify, or compensate for the
impact of a potentially harmful action. 40 C.F.R. § §
1508.20( a)-( e). “[O]mission of a reasonably complete
discussion of possible mitigation measures would
undermine the ‘action-forcing’ function ofNEP A.
Without such a discussion, neither the agency nor other
interested groups and individuals can properly evaluate
the severity of the adverse effects.” Robertson v.
Methow Valley Citizens Cow1ciJ, 490 U.S. 332, 353
Chapter 3 of the preliminary EA includes additional mitigation
developed to minimize potential impacts from the proposed Baseline
activities. Section 2.3.6 describes the environmental commitments
proposed by Resolution, and Section 2.5 provides a summary of the
mitigation measures developed in Chapter 3.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-75
Comment
Number Comment Response
(1989). NEPA requires that the agency discuss
mitigation measures, with “sufficient detail to ensure
that environmental consequences have been fairly
evaluated.” Methow Valley, 490 U.S. at 352, 109 S.Ct.
1835.
50 Even if an EA leads to a FONSI, it is essential for the
agency to consider all reasonable alternatives to the
proposed action.
Please refer to Section 2.4 of the preliminary EA (Alternatives
Considered but Eliminated) for a description of a range of reasonable
alternatives that were considered; however, they were not carried
forward in the EA for further analysis.
51 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Approval of only
activities on current existing roads.
Approval of only activities on current existing roads was not reviewed
as an alternative to the Proposed Action because it would not meet the
purpose of and need for Resolution’s Baseline activities. Please refer to
Section 2.4 of the preliminary EA for other alternatives to the Proposed
Action that were considered.
52 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Access to activities
not on existing roads should be conducted via
helicopter.
Access to activities not on existing roads by helicopter was considered
as an alternative to the Proposed Action. Please refer to Section 2.4 of
the preliminary EA for a description of this alternative and the
reason(s) it was not carried forward in the EA for further analysis.
53 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Reduction in the
amount, scope, and impact of each activity or group of
activity.
Resolution made modifications to their Proposed Action based on
internal and external scoping comments received during the Scoping
Period (Section 2.3 preliminary EA), which would serve to reduce
impacts to environmental resources.
54 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Timing restrictions to
protect wildlife, recreation, and other public resources;
Please refer to Section 2.4 of the preliminary EA (Alternatives
Considered but Eliminated) for a description of a range of reasonable
alternatives that were considered. Also refer to Sections 2.3.5, 2.3.6,
and 2.5 for a description of reclamation, applicant-proposed
environmental protection measures, and mitigation measures that
would reduce the impact to wildlife, recreation and other public
resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-76
Comment
Number Comment Response
55 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Avoidance of any
impact to recreational users of the Arizona Trail (visual,
scenic, noise, etc.).
Please refer to Section 2.4 of the preliminary EA (Alternatives
Considered but Eliminated) for a description of a range of reasonable
alternatives that were considered. Also refer to Sections 2.3.5, 2.3.6,
and 2.5 for a description of reclamation, applicant-proposed
environmental protection measures, and mitigation measures that
would reduce or avoid the impact to recreation users of the Arizona
Trail. Also refer to Sections 3.12 and 3.15 for a discussion of the
potential visual and noise impacts from the Baseline activities.
56 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Avoidance of cultural
and historic areas.
Please refer to Section 3.9 (Cultural Resources) of the preliminary EA.
All known cultural resources would be avoided under the Proposed
Action.
57 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Review of Project
under the correct legal regime as noted above, with
mitigations to protect the public interest from adverse
impacts.
With regards to 40 CFR part 1508.9(b), the preliminary EA includes a
discussion of the following: project need (Section 1.4); alternatives to
the Proposed Action (Sections 2.2, 2.3); environmental impacts of the
Proposed Action and alternatives (Chapter 3); listing of agencies and
persons consulted (Chapter 4).
58 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Controls to prevent
adverse impacts from future mine dumping (e.g.,
prevention of possibility that project drill holes would
be a conduit for leakage/pollution from eventual tailings
disposition.
Please refer to Sections 2.3.5, 2.3.6, and 2.5 of the preliminary EA for a
description of reclamation, applicant-proposed environmental
protection measures, and mitigation measures that would reduce or
avoid the impact to resources. And refer to Section 2.3 for a description
of the Proposed Action including reclamation.
59 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: reviewing the Project
along with the Main Mine in one EIS.
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Section 1.5.1 of
the preliminary EA evaluates connected actions including the potential
development of the deep underground copper ore body and Section 2.4
discusses other reasonable alternatives considered.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-77
Comment
Number Comment Response
60 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: Examining the use of
a cut and fill method of mining. This method would
drastically reduce the amount of tailings that would be
generated thereby changing entirely the size and
composition for a possible tailings facility as a result of
this action.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
61 the Draft EA or EIS must consider, at a minimum, the
following reasonable alternatives: An examination of
other tailings locations such as tailings on State Trust
lands near Florence Junction that would eliminate the
need for this study.
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A.
62 In addition to ensuring compliance with all applicable
environmental standards (which has not been shown
here due to the inadequate NEP A compliance), the
USFS has a mandatory duty to require “all practicable
measures to maintain and protect fisheries and wildlife
habitat which may be affected by the operations” under
36 CFR § 228.8(e)). See Rock Creek Alliance v. Forest
Service, 703 F.Supp.2d 1152, 1170 (D. Montana 201 0)
(Forest Service violated Organic Act and 228
regulations by failing to protect water quality and
fisheries in approving mining PoO). “Under the Organic
Act the Forest Service must minimize adverse
environmental impacts where feasible and must require
[the operator] to take all practicable measures to
maintain and protect fisheries and wildlife habitat.” I d.
at 1170. This duty applies to all wildlife, not just
indicator, sensitive, threatened, and endangered species.
Importantly, a simple and generalized reduction of
impacts does not equate to the strict requirements for
Refer to Sections 2.3.5, 2.3.6, and 2.5 of the preliminary EA for a
description of measures that would reduce or avoid impacts to
resources. Additionally, avoidance, minimization and mitigation
measures are discussed in the analysis of resources in Chapter 3.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-78
Comment
Number Comment Response
minimization of impacts and protection of resources.
The Forest Service’s duty to minimize impacts is not
met simply by somewhat reducing those impacts. Trout
Unlimited v. U.S. Dep’t. of Agriculture, 320 F.Supp.2d
1090, 1110 (D. Colo. 2004). In interpreting the Federal
Land Policy and Management Act (FLPMA)’s duty on
the agency to “minimize damage to ... fish and wildlife
habitat and otherwise protect the environment,” 43
U.S.C. § 1765(a), the court specifically stated the
agency’s finding that mitigation measures would
“reasonably protect” fisheries and habitat failed to meet
its duty to “minimize” impacts. Id.
63 The agency must demonstrate that all feasible means
have been required to minimize all adverse impacts to
all potentially affected resources.
Refer to Sections 2.3.5, 2.3.6, and 2.5 of the preliminary EA for a
description of measures that would reduce or avoid impacts to
resources. Additionally, avoidance, minimization and mitigation
measures are discussed in the analysis of resources in Chapter 3.
64 in order to minimize all adverse impacts, the agency
must, among other restrictions to protect wildlife and the
environment, limit project activities to existing roads,
etc.(assuming that the Project was reviewed and
approved under the proper legal regime, which the
Scoping letter does not do). Also, as noted herein, the
agency must fully consider such limitations as
reasonable alternative( s) under NEPA.
The Forest Service, in compliance with 36 CFR part 228.1, is required
to minimize environmental effects of proposed actions whenever
possible. As a result of internal and external scoping comments
received on the proposed Plan, Resolution took into consideration
requests to minimize effects to environmental resources by reducing
the number of drill sites; reducing the use of existing Forest System
roads; and reducing the number of proposed previously disturbed areas
to be used as temporary access roads. The Purpose and Need of the
proposed Plan is to collect hydrological, geochemical, and geotechnical
data to provide baseline information of these elements of the
environment over an area being considered for a potential tailings
storage site (Section 1.4 preliminary EA). Reducing the number of drill
sites was found to not meet the purpose and need. Reasonable
alternatives which were determined to meet the Purpose and Need were
evaluated in the pre-decisional EA (Chapter 2).
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-79
Comment
Number Comment Response
65 water quality must be protected. For example, pursuant
to the Clean Water Act, the USFS must require
Resolution to obtain Arizona Pollutant Discharge
Elimination System (AZPDES) permit coverage for the
sediment and other pollutants discharged from the road
culverts and other water management structures.
Effects to Water Resources from Baseline activities, including water
quality, are discussed in Section 3.3 of the preliminary EA. Applicant-
proposed environmental protection measures and mitigation measures
are described in Sections 2.3.6 and 2.5.
66 One potential serious issue regards the intended use of
these lands by Resolution for tailings dumps, especially
the immediate areas of the drill holes created by the
Project. Although the . company would have to meet
basic state drill/well hole closure requirements, these
requirements do not account for the fact that millions of
tons of tailings could be placed directly on the
holes/wells. This could result in the serious condition of
these holes/wells becoming conduits for
leakage/seepage of contaminants from the tailings. The
USFS must ensure against this possibility -more than
simply referring to Arizona’s generalized well/drill
closure requirements.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). The Proposed Action, including
reclamation and applicant-proposed environmental protection
measures, is described in Section 2.3 of the preliminary EA. Effects
from the Baseline activities to Water Resources are discussed in
Section 3.3.
67 Compliance with the NFMA is also required. The
NFMA requires that all site-specific actions 1 authorized
by the USFS be consistent with Forest Plan tandards and
guidelines. 16 U.S.C. Sec. 1604(i). “Pursuant to the
NFMA, the Forest Service must demo.nstmte that a site-
specific project would be consistent with the land
resource management plan of the entire forest.”
Neighbors of Cuddy Mountain v. U.S. Forest Service,
137 F.3d 1372, 1377 (9111 Cir.1998). ... USFS
authorization of mining and mineral exploration must
comply with all Forest Plan and NFMA
requirements.rsee Hells Canyon Preservation Council v.
Haines 2006 WL 2252554 *7- * 1 0 (D. Oregon 2006)
(approval of mining op ration violated Forest Plan
minerals management standards); Rock Creek Alliance
Chapter 3 of the preliminary EA includes the relevant Tonto National
Forest management direction for each of the resources evaluated.
Dependent upon the determination of effect to resources, a project-
specific plan amendment may be necessary in order to maintain
consistency between the proposed Baseline activities and the Forest
Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-80
Comment
Number Comment Response
v. U.S. Forest Service, 703 F.Supp.2d 1152, 1187, n. 23
(D. Mont. 2010)(same). Thus,at a minimum, all
standards in the Forest Plan and NFMA requirements
must be met. There is no “mining exemption” from any
of these standards.
68 NEP A requires that the USFS fully disclose the
Project’s impacts on all potentially affected threatened
and endangered species and their designated critical
habitats. See 40 C.F.R. § 71 c. , 1508.27(b )(9). Impacts
to threatened or endangered species short of ‘jeopardy”
or the “destruction or adverse modification of critical
habitat” (the standard used under Section 7 of the ESA,
16 U.S.C. § 1536(a)(2)) may still be significant and
must be examined under NEPA. This includes engaging
in the ESA Section 7 consultation process with the U. S.
Fish and Wildlife Service (FWS).
Section 3.7 of the preliminary EA evaluates potential effects on
Wildlife and Special Status Species.
69 4 4 The Tonto National Forest and the San Carlos
Apache Tribe are jointly conducting an ethnographic
survey of the entire Oak Flat area potentially impacted
by Resolution Copper’s mine plans included this project
area. The survey should be allowed to run is course
before scoping moves ahead.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. The Forest Service will
consider the findings of the Study, in conjunction with Tribal
comments, which come out of government to government consultation
in the final decision on the Baseline Plan.
70 If an undertaking is the type that “may affect” an
eligible site, the agency must make a reasonable and
good faith effort to seek information from consulting
parties, other members of the public, and Native
American tribes to identify historic properties in the area
of potential effect. See 36 CFR § 800.4(d)(2). See also
Pueblo of Sandia, 50 F.3d at 859-863 (agency failed to
make reasonable and good faith effort to identify
historic properties). Consultation “must be initiated
early in the undertaking’s planning, so that a broad
range of alternatives may be considered during the
Section 3.9 of the preliminary EA describes the potential effects on
cultural resources including historic resources. Government to
government consultation in accordance with the National Historic
Preservation Act was initiated shortly after the Baseline Plan was
determined to be administratively complete, approximately May 2014.
Government to government consultation is in progress and is ongoing
until the Forest Supervisor makes a decision. Tribal consultation is
ongoing and will conclude for this action when a final decision
regarding Resolution’s Baseline Plan is reached.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-81
Comment
Number Comment Response
planning process for the undertaking.” Pit River Tribe v.
U.S. Forest Service, 469 F.3d 768, 787 (91 Cir. 2006).
71 The NHPA also requires that federal agencies consult
with any “Indian tribe ... that attaches religious and
cultural significance’ to the sites. 16 U.S.C. §
470(a)(d)(6)(B). Consultation must provide the tribe “a
reasonable opportunity to identify its concerns about
historic properties, advise on the identification and
evaluation of historic properties, including those of
traditional religious and cultural importance, articulate
its views on the undertaking’s effects on such properties,
and participate in the resolution of adverse effects.” 36
CFR § 800.2(c)(2)(ii). “The agency official shall ensure
that the section 106 process is initiated early in the
undertaking’s planning, so that a broad range of
alternatives may be considered during the planning
process for the undertaking.” 36 CFR § 800.1 (c)
(emphasis added.) The NHPA requires that consultation
with Indian tribes recognize the government-to- J tJ
government relationship between the Federal
Governmenl and Indian tribes.” 36 CFR § “7
800.2(c)(2)(ii)(C). See also Presidential Executive
Memorandum entitled “Government-to- ~ ·Government
Relations with Native American Tribal Governments”
(April29, 1994), 59 Fed. Reg. 22951, and Presidential
Executive Order 13007, “Indian Sacred Sites” (May 24,
1996), 61 Fed. Reg. 26771.
Section 3.9 of the preliminary EA describes the potential effects on
cultural resources including historic resources. Government to
government consultation in accordance with the National Historic
Preservation Act was initiated shortly after the Baseline Plan was
determined to be administratively complete, approximately May 2014.
Government to government consultation is in progress and is ongoing
until the Forest Supervisor makes a decision. Tribal consultation is
ongoing and will conclude for this action when a final decision
regarding Resolution’s Baseline Plan is reached.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-82
Comment
Number Comment Response
72 The USFS must also protect archeological and grave
resources, Sacred Sites and Native American religious
and cultural uses pursuant to the above laws and
requirements as well as: (1) the American Indian
Religious Freedom Act (AIFRA), 42 U.S.C. 1996 et
seq.; (2) the Archaeological Resources Protection Act
(ARPA), 16 U .S.C. 470aa-mm · and (3) the Native
American Graves Protection and Repatriation Act
(NAGPRA), 25 U.S.C. 3001 et seq.
Section 3.9 of the preliminary EA provides information regarding laws,
regulations, and policies that are relevant to the proposed Baseline
activities and cultural resources. This section includes laws and
regulations pertinent to the protection of Native American graves and
cultural resources.
73 under the Tonto Forest Plan: For any proposed surface
disturbing activity, the following standards will apply:
1. The Forest Service will comply with the National
Historic Preservation Act (as amended) and the P A. 2.
The standards specified in the P A will be followed.
Where the settlement document does not specify
standards, those in the Forest Service Manual and
Handbook will apply. 3. During the conduct of
undertakings, the preferred management of sites listed
in, nominated to, eligible for, or potentially eligible for
the National Register is avoidance and protection.
Exceptions may occur in specific cases where
consultation with the SHPO indicates that the best use
of the resource is data recovery and interpretation. 4.
Sites listed in, nominated to, eligible for, or potentially
eligible for the National Register will be managed
during the conduct of undertakings to achieve a “No
Effect” finding, in consultation with the State Historic
Preservation Officer. Forest Plan Amendment No. 21,
5/311995, Replacement Page- 38-1. Under the NFMA
and NHP A, thus, there must be “no effect” to these
resources.
The Forest Service is complying with the NHPA and NEPA regulations
in its preparation of this EA. Please refer to Section 1.6 of the
preliminary EA for a summary of the ongoing consultation efforts and
also Section 3.9 for a discussion of Cultural Resource existing
conditions and potential environmental consequences from the
proposed Baseline Plan.
74 it appears that lands to be used or disturbed by the
Project are currently the subject of an Ethnographic
Study conducted by or for the USFS and/or Resolution
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. The Forest Service will
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-83
Comment
Number Comment Response
to attempt to ascertain the cultural, religious, and
historical resources of the area. Under NEP A, the NHP
A, and the other laws, policies and requirements noted
herein, the USFS cannot approve this Project until the
Ethnographic Study has been completed and subject to
public review (as part ofthe NEPA process) and full
government-to-government consultation with all
potentially affected Tribes.
consider the findings of the Study, in conjunction with Tribal
comments, which come out of government to government consultation,
in the final decision on the Baseline Plan. As noted in the preliminary
EA, a potential project specific forest plan amendment will be
considered to ensure consistency if a ‘no effect’ determination cannot
be reached.
75 WE RESERVE THE RIGHT TO SUPPLIMENT
THESE COMMENTS IF THE SCOPING COMMENT
DEADLINE IS EXTENDED BEYOND THE
CURRENT JUNE 23 DEADLINE.
The Tonto National Forest welcomes your comments throughout the
NEPA process. During the NEPA process comments are considered as
they are received consistent with Forest Service NEPA regulations and
36 CFR 218. Public notification regarding the initial preparation of the
EA was conducted in accordance with CEQ and Forest Service NEPA
regulations.
76 On June 4, 2014, the Arizona Mining Reform Coalition
send a Freedom oflnformation Act (FOIA) request to the
USFS (Attachment K) (2014-FS-R3-03882-F) asking
for: “ ... the most recent copy of a proposed “General
Plan of Operations” for the Resolution Copper Mine
Project ... On June 5, 2014, the Arizona Mining Reform
Coalition sent a second FOIA request (attached) (2014-
FS-R3-03883-F)5 (Attachment L) asking for: “ ... all
records and documents regarding the Resolution Copper
Baseline Hydrological & Geotechnical Data Gathering
Activities Plan for the Resolution Copper Mine Project
(the subject of the May 13th scoping letter) ... As
AMRC explained in a letter to USFS dated June 11,
2014, Request for Extension of Deadline for Scoping
Comments on Resolution Baseline Hydrological &
Geotechnical Data Gathering Activities (Attachment
M): “The purpose ofthe NEPA process is to provide
you, the decision-maker in this case, with a complete,
robust, and wide range of alternatives to assist you in
your decision. Adhering to a timeline that will not allow
The Tonto National Forest welcomes your comments throughout the
NEPA process. During the NEPA process comments are considered as
they are received consistent with Forest Service NEPA regulations and
36 CFR 218. Public notification regarding the initial preparation of the
EA was conducted in accordance with CEQ and Forest Service NEPA
regulations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-84
Comment
Number Comment Response
this to happen would not serve the public or the Forest
well.”
77 On June 20,2014, Chairman /Terry Rambler of the an
Carlos Apache Tribal Council send a letter to USFS
(Attachment N) asking for an extension to the comment
deadline “ ... the Notice and the concurrent legal affects
of that Notice runs counter to the MOU that the Tribe
signed with TNF in June 2013, regarding the ongoing
Ethnographic-Ethnohistorical Survey. The purpose of
the Survey is to inform the very scoping that is to be
undertaken by the Baseline Activities. It is premature to
go to this scoping while the Ethnographic-
Ethnohistorical Survey is incomplete. The entire
purpose of the MOU between the Tribe and TNF is to
avoid situations such as this. The purpos of the MOU
wa to establish an informed process to gather
information directly applicable to the Proposed Plan.
Section I VI. A. of the MOU provides, “The parties shall
manage their respective resources and activities in a
separate, coordinated, and mutually beneficial manner to
meet the purposes of the MOU” Jumping to scoping on
the Proposed Plan before the Survey is complete
violates this provision and disregards the Tribe’s
processes and timetables. This is an egregious violation
of TNF’s trust and fiduciary obligations to the Tribe. In
short, the Tribe and TNF agreed to rules for the Survey
consultation and the timelines built in to that process.
The Tribe is playing by the rules, and so should TNF.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on Resolution’s Baseline Plan. It is the Forest’s
intent to take into consideration the findings of the Study, in
conjunction with Tribal comments which come out of government-to-
government consultation in the final decision on the Baseline Plan.
The purpose of the Memorandum of Understanding (MOU) between
the San Carlos Apache Tribe and the Tonto National Forest was to
establish cooperation and document a procedure for working together
during the Study. This document discusses funding, roles,
communication and confidentiality, specific and limited to the Study.
78 the [San Carlos Apache] Tribe respoctfully requests that
TNF postpone the public comment period on
Resolution’s Proposed Plan until completion of TNF’s
Management Plan and the Ethnographic-Ethnohistorical
Survey called for in the MOU. Alternatively, the Tribe
requests that TNF extend the time for providing
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on Resolution’s Baseline Plan. It is the Forest’s
intent to take into consideration the findings of the Study, in
conjunction with Tribal comments which come out of government-to-
government consultation in the final decision on the Baseline Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-85
Comment
Number Comment Response
comments by the Tribe for 180 days so that the Tribe
may fully develop its comments to the Notice.”
79 In response to an AMRC June 11, 2014, letter to USFS
referenced above, the USFS replied on June 18, 2014,
USFS denied the request for an extension. However, in
its denial (Attachment 0), USFS states: “Therefore, the
scoping period will not be extended, however we
welcome your comments at any time during the
National Environmental Policy Act process.” We
anticipate that we will have additional comments based
on new information contained in our FOIA responses
(when eventually fulfilled) and upon receipt of
additional studies completed pertaining to the area to be
impacted by the proposed action (such as the
Ethnographic Survey mentioned in Chairmen Rambler’s
comment extension letter referenced earlier in these
comments.
The Tonto National Forest welcomes your comments throughout the
NEPA process. During the NEPA process comments are considered as
they are received consistent with Forest Service NEPA regulations and
36 CFR 218. Public notification regarding the initial preparation of the
EA was conducted in accordance with CEQ and Forest Service NEPA
regulations.
80 Determining a threshold beyond which cumulative
effects significantly degrade a resource, ecosystem, or
human community is sometimes very difficult because
of a lack of data. Without a definitive threshold, the
NEPA practitioner should compare the cumulative
effects of multiple actions with appropriate national,
regional, state, or community goals to determine
whether the total effect is significant. These desired
conditions can best be defined by the cooperative efforts
of agency officials, project proponents, environmental
analysts, nongovernmental organizations, and the public
through the NEPA process.
Section 3.2 in the preliminary EA includes the cumulative impact
analysis methodology. The information in the cumulative impact
analysis uses the best available information and the analysis follows
CEQ’s Considering Cumulative Effects under the National
Environmental Policy Act and Forest Service NEPA regulations and
policies.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-86
Comment
Number Comment Response
81 Because federal projects cause or are affected by
cumulative impacts, this type . of impact must be
assessed in documents prepared under the National
Environmental Policy Act (NEPA). The purpose of this
guidance is to assist EPA revie~ers of NEPA documents
in providing accurat~realistic, and consistent comments
on the assessment of cumulative impacts.
Section 3.2 in the preliminary EA includes the cumulative impact
analysis methodology. The information in the cumulative impact
analysis uses the best available information and the analysis follows
CEQ’s Considering Cumulative Effects under the National
Environmental Policy Act and Forest Service NEPA regulations and
policies.
82 To improve how cumulative impacts are assessed in
environmental impact analysis, CEQ developed a
handbook entitled “Considering Cumulative Effects
under the National Environmental Policy Act” (CEQ
1997). CEQ’s handbook offers the most comprehensive
and useful information to date on practical methods for
addressing cumulative effects in NEPA documents.
Consequently, the concepts presented in the handbook
serve as the foundation for this guidance. Reviewers are
urged to use this guidance and the CEQ handbook
simultaneOuSly.
Section 3.2 in the preliminary EA includes the cumulative impact
analysis methodology. The information in the cumulative impact
analysis uses the best available information and the analysis follows
CEQ’s Considering Cumulative Effects under the National
Environmental Policy Act and Forest Service NEPA regulations and
policies.
83 cumulative impact assessment entails a more extensive
and broader review of possible effects. Reviewers
should recognize that while no “cookbook” approach to
cumulative impacts analysis exists, a general approach
is described in the CEQ handbook. As with the review
of direct or indirect impacts, EPA review of cumulative
impacts analysis is most effective if done early in the
process, especially in the scoping phase. Federal
agencies have the responsibility of determining how and
the extent to which cumulative impacts are assessed in
NEPA documents and documenting that effort. In
reviewing the analysis, the EPA reviewer should
determine if the information presented is commensurate
with the impacts of the project1 i.e., a greater degree of
detail is needed for more potentially serious impacts.
The boundaries for cumulative impacts are described in Section 3.2 of
the preliminary EA. The spatial and temporal boundaries for the
cumulative impact analysis take into consideration the potential effects
on resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-87
Comment
Number Comment Response
84 NEPA documents do not necessarily require cumulative
impact assessments in every case. However, EPA
expects that the action agency consider whether
cumulative impacts is a significant issue that should be
addressed every time a NEPA document is prepared.
NEPA documents in this context includes both
environmental assessments and environmental impact
stateme~Js.fAs with most NEPA assessments, the
analysis should be commensurate with the project’s
impacts and the resources affected. In all phases of the
cumulative impact assessment, EPA should ensure that
the level of analysis and scope are commensuraie with
the potential impacts, resources affected, project scale,
and other factors.
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
85 The EPA’s manual on reviewing and commenting on
federal actions under NEPA and section 309 of the
Clean Air Act (EPA, 1984) states that EPA’s comments
should include mitigation measures “ ... to avoid or
minimize damage to the environment, or to protect,
restore, and enhance the environment”
The preliminary EA includes Resolution-proposed Environmental
Protection Measures (Section 2.3.6), and Mitigation Measures
developed by the Forest Service (Section 2.5). Both types of measures
are designed to minimize or avoid impacts to environmental resources.
86 it is appropriate to suggest mitigation to address
cumulative impacts that ar caused by activities other
than the proposed project. For example, mitigation could
include forming partnerships among the different
governmental agencies and private organizations to
work on environmental restoration when those entities
have contributed to cumulative impacts over a long
period of time. It is important to note that EPA
suggestions for mitigation are not necessarily
constrained by whether the action agency has
jurisdiction to implement the measures but the measures
should be realistic and technically feasible.
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-88
Comment
Number Comment Response
87 EPA reviewers should determine whether the NEPA
analysis has identified thJ resources and ecosystem
components cumulatively impacted by the proposed
action and other actions. The reviewer can determine
which resources are cumulatively affected by
considering: (1) whether the resource is especially
vulnerable to incremental effects; (2) whether the
proposed action is one of several similar actions in the
same geographic area; (3) whether other activities in the
area have similar effects on the resource; (4) whether
these effects have been historically significant for this
resource; and (5) whether other analyses in the area have
identified a cumulative effects concern.
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts were considered if the resource was vulnerable
to incremental effects, other projects with similar effects, significance
of the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
88 Cumulative impacts can affect a broad array of
resources and ecosystem components. In addition to
considering the biological resources that are the staple
of NEPA analysis, examples of other resources that
should be considered include historic and archaeological
sites, socioeconomic services and issues, and
community structure and chara~ter, While a broad
consideration of . resources is necessary for the adequate
assessment of cumulative impacts” the analysis should
be expanded for only those resources that are
significantly I affected. In similar fashion, ecosystem
components should be considered when they are
significantly affected by cumulative impacts. The
measure of cumulative effects is any change to the
function of these ecosystem components.
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts were considered if the resource was vulnerable
to incremental effects, other projects with similar effects, significance
of the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
89 A framework for this consideration for forested areas is
modified from Bedford V and Preston (1988). Certain
types of forests are more likely to be affected by
cumulative effects as described by the following
examples: 1) forests downwind from major sources of
air pollution that contain plant organisms that are
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts were considered if the resource was vulnerable
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-89
Comment
Number Comment Response
susceptible to ozone and other airborne pollutants; 2)
forested areas lower in a watershed because they are
often closer to development and pollutants follow the
movement of water; 3) forests that are susceptible to
fragmentation because, with increasing fragmentation,
areas will have a large perimeter in relation to their area;
and 4) areas experiencing development pressue.
Resources of concern may also be identified by
considering actions that alter ecological processes and
therefore can be expected to produce cumulative effects.
Changing hydrologic patterns, for example, is likely to
elicit cumulative effects.
to incremental effects, other projects with similar effects, significance
of the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
90 The NEPA document should identify which resources or
ecosystem components of concern might be affected by
the proposed action or its alternatives within the project
area.
Please see Chapter 3 of the preliminary EA for a discussion of the
resources or ecosystem components analyzed in the EA.
91 Geographic boundaries and time periods used in
cumulative impact analysis should be based on all
resources of concern and all of the actions that may
contribute, along with the project effects, to cumulative
impacts. Generally, the scope of analysis will be broader
than the scope of analysis used in assessing direct or
indirect effects. To avoid extending data and analytical
requirements beyond those relevant to decision making,
a practical delineation of the spatial and temporal scales
is needed. The selection of geographic boundaries and
time period should be, whenever possible, based on the
natural boundaries of resources of concern and the
period of lime that the proposed action’s impacts will
persist, even beyond the project life.
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-90
Comment
Number Comment Response
92 The EPA reviewer can determinel an appropriate spatial
scope of the cumulative impact analysis by considering
how the resources are being affected. This determination
involves two basic steps: (1) identifying a geographic
area that includes resources potentially affected by the
proposed project and (2) extending that area, when
necessary, to include the same and other resources
affected by the combined impacts of the project and
other actions.
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
93 Determining the temporal scope requires estimating the
length of time the effects of the proposed action will
last. More specifically, this length of time extends as
long as the effects may singly, or in combination with
other anticipated effects, be significant on the resources
of concern. At the point where the contribution of
effects of the action, or combination of all actions, to the
cumulative impact is not significant the analysis should
stop. Because the important factor in determining
cumulative impact is the condition of the resource (ie.,
to what extent it is degraded), analysis should extend
until the resource has recovered from the impact of the
proposed action.
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
94 There are no set or required formulas for determining
the appropriate scope of the cumulative impact analysis.
Both geographic boundaries and time periods need to be
defined on a case-by-case basis. Determining the
boundaries and periods depends on the characteristics of
the resources affected, the magnitude and scale of the
project’s impacts, and the environmental setting. In
practice, a combination of natural and institutional
boundaries may be required to adequately consider both
potential impacts and possible mitigation measures.
Ultimately, the scope of the analysis will d:Jd on an
Section 3.2 of the preliminary EA describes the cumulative impact
analysis process and boundaries for the evaluation cumulative impacts
that are commensurate with the proposed Baseline activities. Each
resources section in Chapter 3 also has a cumulative impact
assessment.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-91
Comment
Number Comment Response
understanding of how the effects are occurring in the
assessment area.
95 To successfully assess cumulative impacts, NEPA
documents should consider a , broad range of activities
and patterns of environmental degradation that are
occurring in the vicinity of the project. The following
considerations (as modified from Klein and Kingsley,
1994) can assist in identifying actions that may relate to
the project under review: 1) the proximity of the projects
to each other either geographically or temporally; 2) the
probability of actions affecting the same environmental
system, especially systems that are susceptible to
development pressures; 3) the likelihood that the project
will lead to a wide range of effects or lead to a number
of associated projects; and 4) whether the effects of
other projects are similar to those of the project under
review. 5) the likelihood that the project will occur --
final approval is the best indicator but long range
planning of government agencies and private
organizations and trends information should also be
used; 6) temporal aspects, such as the project being
imminent;
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts considered if the resource was vulnerable to
incremental effects, other project with similar effects, significance of
the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
96 The NEPA analysis should establish the magnitude and
significance of cumulative impacts by comparing the
environment in its naturally occurring state with the
expected impacts of the proposed action when combined
with the impacts of other actions. Use of a “benchmark”
or “baseline” for purposls of comparing conditions is an
essential part of any environmental analysis.
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts considered if the resource was vulnerable to
incremental effects, other project with similar effects, significance of
the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
97 To determine how the project will affect the resource’s
ability to sustain itself, the NEPA document should
include a description of the baseline condition that
Sections 3.5 to 3.8 of the preliminary EA describe the existing
conditions and the environmental consequences on vegetation, wildlife
and range in the project area from the Baseline activities.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-92
Comment
Number Comment Response
considers “ ... how conditions have changed over time
and how they are likely to change in the future without
the proposed action”. (CEQ, 1997) If it is not possible to
establish the “naturally occurring” condition, a
description of a modified but ecologically sustainable
condition can be used in the analysis. In this context,
ecologically sustainable means the system supports
biological processes, maintains its level of biological
productivi;1mctions with minimal external management,
and repairs itself when stressed. While a description of
past environmental conditions is usually included in
NEPA documents, it is seldom used to fully assess how
the system has changed from previous conditions. The
comparison of the environmental condition and
expected environmental impacts can be incorporated
into the environmental consequences or affected
environment sections of NEPA documents.
98 The condition of the environment should, however,
address one or more of the following: 1) how the
affected environment functions naturally and whether it
has been significantly degraded; 2) the specific
characteristics of the affected environment and the
extent of change, if any, that has occurred in that
environment; and 3) a description of the natural
condition of the environment or, if that is not available,
some modified, but ecologically sustainable, condition
to serve as a benchmark. Two practical methods for
depicting the environmental condition include use of the
no-action alternative and an environmental reference
point. Historically, the no-action alternative (as
reflecting existing conditions) has usually been used as .
a benchmark for comparing the proposed action and
alternatives to existing conditions. The no-action
alternative can be an effective benchmark if it
Chapter 3 of the preliminary EA describes the existing condition and
the environmental consequences (direct, indirect and cumulative
impacts) to resources from the Baseline activities. This discussion
includes a description of the regulatory framework for each resource
and also a description of the methodologies used to analyze impacts to
resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-93
Comment
Number Comment Response
incorporates the cumulative effects of past activities and
accurately depicts the condition of the environment.
99 Determining what environmental condition to use in the
assessment may not be immediately clear. Choosing and
describing a condition should be based on the specific
characteristics of the area. In addition, the choice of
condition can be constrained by limited resources and
information. For these reasons, the environmental
condition described by the environmental reference
point or noaction alternative should be constructed on a
case-by-case basis so that it represents an ecosystem
able to sustain itself in the larger context of activities in
the region. In this respect, there is no predetermined
point in time that automatically should represent the
environmental condition. In addition, it may not be
practical to use a pristine condition in situations of
intensive development. For example, it may not be very
useful to use a pre-development condition to assess the
extent of degradation in a heavily urbanized setting. It
may be more useful in this situation to consider the
condition of several important resources of concern (i.e.,
water quality, air quality, or quality of life) in
comparison with expected environmental consequences
of the action. Since most ecosystems can be delineated
and have distinct characteristics, determination of the
environmental condition does not need to be a
subjective process leading to speculation about the
condition of the environment before it was degraded.
Chapter 3 of the preliminary EA describes the existing condition and
the environmental consequences (direct, indirect and cumulative
impacts) to resources from the Baseline activities. This discussion
includes a description of the regulatory framework for each resource
and also a description of the methodologies used to analyze impacts to
resources.
100 Selecting the best environmental condition for
comparative purposes can be J based on the following:
1) consider what the environment would look like or
how it would behave without serious human alteration;
2) factor in the dynamic nature of the environment; 3)
define the distinct characteristics and attributes of the
Chapter 3 of the preliminary EA describes the existing condition and
the environmental consequences (direct, indirect and cumulative
impacts) to resources from the proposed Baseline activities. This
discussion includes a description of the regulatory framework for each
resource and also a description of the methodologies used to analyze
impacts to resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-94
Comment
Number Comment Response
environment that best represent that particular type of
environment (focus on characteristics and attributes that
have to do with function); and 4) use available or
reasonably obtainable information.
101 Qualitative and quantitative thresholds can be used to
indicate whether a resource(s) of concern has been
degraded and whether the combination of the action’s
impacts with other impacts will result in a serious
deterioration of environmental functions. In the context
of EPA reviews, thresholds can be used to determine if
the cumulative impacts of an action will be significant
and if the resource will be degraded to unacceptable
levels.
Chapter 3 of the preliminary EA describes the existing condition and
the environmental consequences (direct, indirect and cumulative
impacts) to resources from the proposed Baseline activities. This
discussion includes a description of the regulatory framework for each
resource and also a description of the methodologies used to analyze
impacts to resources.
102 Since cumulative impacts often occur at the landscape
or regional level, , th’resholds should be developed at
similar scales whenever possible. Indicators at a
landscape level can be used to develop thresholds as
well as assess the condition of the environment. By
using the following landscape indicators as modified
from O’Neil et al. (1997) and Jones et al. (1996),
thresholds can be crafted by determining the levels,
percentages, or amount of each that indicate a
significant impact for a particular area. Examples of
thresholds include: • • The total change in land cover is
a simple indicator of biotic integrity; thresholds for
areas with high alterations would generally be lower
than areas that are not as degraded; if open space or
pristine areas are a management goal then the threshold
would be a small percentage change in land cover. •
Patch size distribution and distances between patches
are important indicators of species change and level of
disturbance. Thresholds would be set to determine the
characteristics of an area needed to support a given plant
or animal species. • Estimates of fragmentation and
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis. Each resource section
(Sections 3.3 to 3.15) contains a cumulative impact assessment that
evaluates each resource where there are potential cumulative impacts.
The cumulative impacts considered if the resource was vulnerable to
incremental effects, other project with similar effects, significance of
the impacts, and if there were any other analyses in the area that
identified concerns with potential cumulative effects.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-95
Comment
Number Comment Response
connectivity can reveal the magnitude of disturbance,
ability of species to survive in an area, and ecological
integrity. Thresholds would indicate a decrease in cover
pattern, loss of connectivity, or amount of fragmentation
that would significantly degrade an area. • Indicators of
water quality and watershed integrity can be used to set
thresholds. Specific concentrations and levels of
nitrogen, phosphorous, turbidity, dissolved oxygen, and
temperature can be used. • Thresholds for a decline in
water quality can take the form of size and amount of
riparian buffer zones. Condition of riparian zones and
changes in percent of buffer areas can inditate a decline
in water quality due to soil erosion, sediment loading,
and contaminant runoff.
103 approval of roads is not a right covered by the 1872
Mining Law (especially when the roads are not
proposed to access mineral deposits)- even if the
company could show that its mining claims were valid,
which it has not done.
Section 2.3.1 of the preliminary EA describes the access proposed for
conducting the Baseline activities, and Section 1.5.2 describes the
Tonto National Forest’s decision framework.
104 If the agency does not consider the Project and the Main
Mine part of the same operation- so as to attempt to
avoid them being considered connected actions under
NEPA- then the Project cannot be considered a mining
project under the Mining Law or 36 CFR Part 228
regulations. As such, the Project can only be reviewed
and considered under the USFS Special Use permitting
regime. Thus, the USFS must require the company to
submit right-of-way or other special use permit
authorizations and require that all mandates of Title V of
the Federal Land Policy Management Act (“FLPMA”)
and its implementing regulations are adhered to (e.g., no
permit can be issued unless it can be shown that the
issuance of the permits is in the best interests of the
public, payment of fair market value, etc.). See 36 CFR
Connected actions are defined by CEQ as those actions that are closely
related and should therefore be analyzed together. “Actions are
connected if they (i) Automatically trigger other actions which may
require environmental impact statements; (ii) Cannot or will not
proceed unless other actions are taken previously or simultaneously;
and (iii) Are interdependent parts of a larger action and depend on the
larger action for their justification” (40 CFR part 1508.25). Please refer
to Section 1.5.1 in the preliminary EA for an explanation of
independent utility and connected actions relative to Resolution’s
Baseline Plan.
Because the activities proposed by Resolution in their Baseline Plan are
considered a use that is reasonably incident to mineral exploration, they
are explicitly exempted from special use authorization. 36 CFR part
251.50(a) designates special uses as “[a]ll uses of National Forest
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-96
Comment
Number Comment Response
Part 251 (USFS special use permit regulations). System lands, improvements, and resources, except those authorized by
the regulations governing … minerals (part 228).” Therefore, Forest
Service special use authorization does not apply.
105 As stated in the USFS Minerals Manual: “In order to
successfully defend rights to occupy and use a claim for
prospecting and mining, a claimant must meet the
requirements as specified or implied by the mining laws,
in addition to the rules and regulations of the USFS.
These require a claimant to: ... 2. Discover a valuable
mineral deposit. ... (and) 7. Be prepared to show
evidence of mineral discovery.” FSM 2813.2 (emphasis
added). In other words, if the agency’s review and
approval of the Project is based on “rights” under the
Mining Law, the record must contain evidence that the
legal prerequisites for establishing those rights exist in
fact and law. Any policy or decision to the contrary is
illegal.
Consistent with Forest Service Manual 2800, Chapter 2810 Mining
Claims, Section 2811.5, a mining claim may lack the elements of
validity and be invalid in fact, but it must be recognized as a claim until
it has been finally declared invalid by the Department of Interior or
Federal courts.
On National Forest system lands reserved from public domain and open
to entry under the Mining Law, the Forest Service is not required to
inquire into claim validity before processing and approving proposed
plans of operations. In order to prospect, explore, and make a discovery
of a valuable mineral deposit or establish valid mining claims, the
operator has a right under the 1872 Mining Law to enter upon national
forests and to conduct upon those lands reasonable activities to
prospect and explore for mineral resources. Exercise of this right does
not even require the staking of a mining claim, a fact recognized in the
Forest Service locatable mineral regulations at 36 CFR 228.3(a), where
mineral operations are defined and it is clearly stated that the Forest
Service’s regulations apply to all functions, work, activities, and uses
reasonably incidental to all phases of mineral exploration and mining
under the 1872 Mining Law, whether located on or off mining claims.
106 Resolution’s Main Mine, along with the “other
minerals-related proposals to the Forest” submitted by
Resolution, scoping letter at 4, must be fully reviewed in
the Draft EA/EIS.
As described in the preliminary EA (Section 1.5), Resolution’s
Baseline Plan has independent utility from their General Plan of
Operations, and other related proposals submitted to the Forest.
Section 1.5.1 of the preliminary EA considers connected actions
including Resolution’s other proposed actions. The potential connected
actions are evaluated consistent with Council of Environmental Quality
(CEQ) regulations found at 40 CFR 1508.25.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-97
Comment
Number Comment Response
107 The agency must fully comply with the NHP A. It
would be a violation of the NHP A and NEP A to
complete the EA/EIS before consultation and a complete
review of cultural/historical resources has been
completed.
The Forest Service is complying with the NHPA and NEPA regulations
in its preparation of this EA. Please refer to Section 1.6 for a summary
of the ongoing consultation efforts and also Section 3.9 for a discussion
of cultural resources’ existing conditions and potential environmental
consequences from the Baseline Plan.
108 The Yavapai people also have a religious, cultural and
traditional connection to this area, though they view it
differently than the Apache and should also be consulted
about this project.
The Tonto National Forest is consulting with 10 Native American
Tribes regarding the project including the Fort McDowell Yavapai
Nation, the Yavapai-Prescott Tribe, and the Yavapai-Apache Nation.
Letter 156 - Balderas, Ruben
No Comments
Letter 157 - Arnst, Diane
1 The area of your project located in Township Range IS
13E and 2S and 13E is located in a nonattainment area
for 10-micron particulate matter (PM I 0). ADEQ
recommends that the Tonto National Forest request
estimated PMIO and PM2.5 emissions from the tailings
storage pile within Township Ranges IS 13E and 2S and
13E including PMIO emissions estimated for proposed
new construction disturbance on 31.74 acres.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects on the area from the Baseline
activities in regards to air quality are discussed in the preliminary EA in
Section 3.13.
Letter 158 - Rambler, Terry
1 TNF is required to ensure that Resolution’s Proposed
Plan complies with 36 CFR Part 228 and to analyze the
impacts of the proposed activities in accordance with the
requirements of the National Environmental Policy Act
(‘‘NEPA”). Further, according to the Notice, TNF is
required to ensure that Resolution’s Proposed Plan is
consistent with the Tonto National Forest Land and
Resource Management Plan (“LRMP”) of 1985.
Section 1.3 of the preliminary EA discusses the Tonto National Forest
decisions in relation to the U.S. 1872 Mining Law. The Forest Service
derives the authority to regulate such activities from the 1897 Organic
Act (16 USC 478, 551), the Multiple Use Mining Act of 1955 (30 USC
612), and the Mining and Minerals Policy Act of 1970 as reissued in
the 1990s. The Forest Service decisions are made in accordance with its
mining regulations at 36 CFR 228A.
2 As stated in the correspondence transmitted to you of
June 20, 2014, the Tribe repeats its request for a
postponement of the comment period for the reasons set
forth in that letter.
The Tonto National Forest considered the requests made to extend the
scoping period for the project. The San Carlos Apache Tribe is
welcome to submit comments regarding the project at any time, either
during the NEPA process or during consultation with the Forest.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-98
Comment
Number Comment Response
3 The Tribe fully endorses and incorporates by reference
the comments submitted by the Arizona Mining Reform
Coalition, et al. The Tribe, in t’he interests of economy
and duplicating the same legal and factual arguments,
requests that you consider the comments made by the
Arizona Mining Reform Coalition, et al. as though those
comments were the Tribe’s separate comments. The
Tribe further calls your attention to the fact that the
Tribe is a signatory to the comments submitted by the
Arizona Mining Reform Coalition, et al. In June of
2013, TNF signed a Memorandum of Understanding
(“MOU’’) with the Tribe. Under the MOU, the Tribe
and 1NF agreed to cooperate in the preparation and
completion of an ongoing Ethnographic/Ethnohistorical
Study (‘‘Study”) of Forest Service managed lands in and
around Superior, Arizona. The purpose of the Study is
for the Tribe and TNF to work together to collect data
for the completion of the Study. The very purpose of the
Study was to inform the very scoping that is to be
undertaken by the Baseline Activities. The entire
purpose of the MOU between the Tribe and TNF is to
avoid situations such as this. The purpose of the MOU
was to establish an informed process to gather
information directly applicable to the Proposed Plan.
Section VI. A. of the MOU provides, “The parties shall
manage their respective resources and activities in a
separate, coordinated, and mutually beneficial manner to
meet the purposes of the MOU” Jumping to scoping on
the Proposed Plan before the Survey is complete
violates this provision and disregards the Tribe’s
processes and timetables. In the Tribe’s view, this is an
egregious violation of1NF’s trust and fiduciary
obligations to the Tribe and a breach of the MOU.
The Tonto National Forest considers all comments received on the
proposed Baseline activities.
The purpose of the Memorandum of Understanding (MOU) between
the San Carlos Apache Tribe and the Tonto National Forest was to
establish cooperation and document a procedure for working together
during the “Ethnographic/Ethnothistoric Study of the Superior Area,
Arizona.” This MOU discusses funding, roles, communication and
confidentiality, specific and limited to the Study.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-99
Comment
Number Comment Response
4 The Proposed Plan indicates that a Class III cultural
resources survey report was prepared and completed by
WestLand Resources for Resolution. Plan of Operations
at 67. The Proposed Plan further indicates that this
report was submitted to TNF. Id. TNF failed to share
this report with the Tribe. Failure to provide the Tribe
with a copy of this report violated the MOU. See MOU,
Section III. B. (TNF’s obligation to timely communicate
with the Tribe). The Proposed Plan states “some of the
proposed activities occur in proximity of existing or
eligible sites.” Without knowledge of which “existing or
eligible sites” are at risk, it is presumptuous and rash to
conclude that the “proximity” of Resolution’s “proposed
activity” would not impact and degrade an area viewed
as sacred by the Tribe and Apaches.
By letter dated August 21, 2014, addressed to Terry Rambler,
Chairman, San Carlos Apache Tribe, the Tonto National Forest
provided responses to your questions. In summary, two copies of the
cultural resources report, “Resolution Project: A Cultural Resources
Inventory of Baseline Hydrologic and Geotechnical Data-Gathering
Sites and Access Roads in the Foothills of the Superstition Mountains,
Northwest of Superior, Arizona,” dated April 30, 2014 were sent to the
Tribe. To provide information to the Tribe in the most efficient manner
possible we would be willing to update our mailing list and ensure any
appropriate staff and/or Tribal members receive copies of Forest
Service correspondence and/or documents, upon your request.
Potential effects to cultural resources from the Baseline activities are
described in Section 3.9 of the preliminary EA. There are no known or
currently identified cultural resource sites that would be affected by the
proposed Baseline Plan.
5 Furthermore, the Tribe’s will consider it a breach of the
MOU if the Proposed Plan proceeds without honoring
Section IV. B. of the MOU. That section provides that
“appropriate cultural representatives and other
knowledgeable Tribal members [shall] ... identify issues,
locations and areas of special importance to the Tribe
that may be located in the Project study area, and work
with Forest Tribal Liaison to located these areas on the
ground .... “ The premature issuance of the Notice for
Resolution’s Proposed Plan prevents the Tribe from
fulfilling this provision of the MOU. There is
undoubtedly a substantial dispute about the size, nature,
and impact of the Proposed Plan, particularly with
regard to Native American and Apache concerns. These
concerns do not reflect mere opposition to well drilling
and road improvements, or a simple disagreement over
the Proposed Plan itself. Rather, this dispute is
substantial, involves the trust responsibility of the
The Tonto National Forest considers all comments received on the
proposed Baseline activities.
The purpose of the Memorandum of Understanding (MOU) between
the San Carlos Apache Tribe and the Tonto National Forest was to
establish cooperation and document a procedure for working together
during the “Ethnographic/Ethnothistoric Study of the Superior Area,
Arizona.” This MOU discusses funding, roles, communication and
confidentiality, specific and limited to the Study.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-100
Comment
Number Comment Response
United States government as exercised by TNF. Despite
having entered into the MOU, it appears that the Tribe
has made little progress with TNF in an area of
significant legal and regulatory concern. In a prior round
of dispute between the Tribe and TNF on Resolution
activities on Forest Service lands, the Forest Service was
dismissive of the Tribe’s cultural, historic and sacred
concerns in the Environmental Assessment (“EA”)
issued for Resolution Copper Mining Pre-Feasibility
Activities Plan of Operations (“Prefeasibility
Activities”) issued on May 24,2010. See e.g., EA at 3-
66 (“Some effect to their subjective religious experience
may occur from the proposed action; however, it is not
anticipated that this experience would be substantially
burdened.”); 3-86. The disregard of the MOU by TNF is
troublesome.
6 It is TNF’s responsibility to identify and analyze how
Resolution’s Proposed Plan will impact the religious
concerns and practices of Native Americans and
Apaches. This is the clear responsibility of the Forest
Service. To require otherwise would undermine one of
the primary purposes ofNEPA; that is “ensuring that the
agency will inform the public that it has indeed
considered environmental [and cultural] concerns in its
decision-making process.” Bait. Gas & Elec. Co. v.
Natural Res. Def Council, Inc., 462 U.S. 87, 97, 103
S.Ct. 2246 (1983).
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known or currently
identified cultural resource sites that would be affected by the Baseline
activities.
7 The Tribe has repeatedly requested that TNF examine
all direct, indirect and cumulative impacts of
Resolution’s activities. In objecting to the 2010
Prefeasibility Activities, the Tribe requested that 1NF
examine the cumulative impacts. In providing our
comments to Travel Management on the Tonto National
Forest, the Tribe questioned 1NF’s failure to address the
Section 3.2 and Table 3-1 of the preliminary EA discusses potential
cumulative projects, and also describes cumulative impact assessment.
Potential direct, indirect, and cumulative impacts on resources are
discussed in each resource analyzed in Chapter 3. Section 1.5.1
discusses connected actions including the potential development of the
deep underground copper ore body and the Tonto National Forest’s
Travel Management Planning.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-101
Comment
Number Comment Response
impacts of Resolution’s proposed mining operations on
travel in the Forest. As stated in the Tribe’s June 20,
2014 correspondence, the Tribe again requests that TNF
fully examine all direct, indirect and cumulative impacts
of Resolution’s activities in conjunction with this
Proposed Plan.
8 Resolution’s Proposed Plan documents are inadequate to
inform the Tribe and the public of what Resolution
intends to do.
Resolution’s proposed Baseline Plan was made available to the public
and Tribes in May of 2014, on the internet at the project website. The
Baseline Plan has been available since May 13, 2014, prior to the
publication of the scoping notice.
9 Is Resolution examining one potential tailings storage
site or multiple sites? What facilities, structures or other
construction is envisioned for such site(s)?
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
10 Are the Baseline Activities intended to provide data for
determining foundation conditions beneath the tailings
facility, ponds, dams, waste rock storage areas, plant
facilities, or other planned mine structures? Are the
Baseline Activities intended to provide data for
determining material and mass properties of the bedrock
for foundations, including permeability to support
hydrogeologic assessments? Are the Baseline Activities
intended to provide data for determining any and what
groundwater regimes? Are the Baseline Activities
intended to provide data for estimating quantities and
quality of borrow materials for facilities construction,
including granular soils and rock materials? Are the
Baseline Activities intended to provide data for
determining seismic probabilities or activities? Are the
Baseline Activities intended to provide data for
providing engineering properties for design of structure
foundations?
By letter dated August 21, 2014, addressed to Terry Rambler,
Chairman, San Carlos Apache Tribe, the Tonto National Forest
provided responses to your questions. In summary, Resolution’s
Baseline Plan proposes hydrological, geochemical, and geotechnical
data collection methods over an area being considered for a potential
tailings site.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-102
Comment
Number Comment Response
11 Does Resolution have the resources to present a
Stormwater Pollution Prevention Plan (“SWPPP”)
which more readily conforms to the type and
topography of Forest Service lands which will be
impacted by the Baseline Activities instead of measures
for the highway design and construction?
By letter dated August 21, 2014, addressed to Terry Rambler,
Chairman, San Carlos Apache Tribe, the Tonto National Forest
provided a response to this question. In summary, the SWPPP
submitted as a part of Resolution’s Baseline Plan is currently under
review by the Forest, and will be revised to reflect approved Plan
elements through the NEPA process.
Section 2.3.6 of the preliminary EA provides a description of
Resolution-proposed environmental protection measures; Section 3.3
provides a description and discussion of water resources, including
proposed mitigation measures.
12 Independently of any Arizona Department of
Environmental Quality analysis, has TNF examined the
SWPPP to determine whether it adequately addresses
the impaired waters of the Queen Creek watershed?
By letter dated August 21, 2014, addressed to Terry Rambler,
Chairman, San Carlos Apache Tribe, the Tonto National Forest
provided a response to this question. In summary, the SWPPP
submitted as a part of Resolution’s Baseline Plan is currently under
review by the Forest, and will be revised to reflect approved Plan
elements through the NEPA process.
Section 2.3.6 of the preliminary EA provides a description of
Resolution-proposed environmental protection measures; Section 3.3
provides a description and discussion of water resources, including
proposed mitigation measures.
13 TNF should complete its adoption of its new Land
Management Plan before it passes on Resolution
Proposed Plan TNF is currently in the process of
revising its 1985 LMRP pursuant to the National Forest
Management Act (“NFMA”) of 1976 (P.L. 94-588) and
36 C.P.R. Part 219 (“2012 Management Ru1e”). TNF
must comply with and present a new land management
plan pursuant to the 2012 Management Ru1e within
approximately the next three years. The Tribe considers
that by proceeding with any examination of Resolution’s
Proposed Plan, TNF is acting prematurely and is in
likely violation of36 C.P.R. Part 219 and the NFMA.
Every project and activity proposed on the Tonto National Forest must
be consistent with the 1985 land and resource management plan (Forest
Plan), as amended. The new Forest Plan, which is expected to be
finalized at the end of 2017, will not change the Forest’s legal
obligations. Accordingly, the Forest still has to adhere to the U.S
mining laws. Every decision document which authorizes a proposed
project or activity (e.g. Environmental Assessment [EA] or
Environmental Impact Statement [EIS]) describes how the project or
activity is consistent with the Forest Plan in place when the decision is
rendered. While in need of revision, the 1985 Forest Plan was designed
to provide for multiple use and sustained yield of goods and services
from the Forest in a way that maximizes long-term net public benefits
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-103
Comment
Number Comment Response
Under the 2012 Management Rule, Forest Service
Management Plans are to be collaboratively developed
and science-based. Plans are to provide a framework for
integrated resource management and for guiding project
future decision-making by TNF. The public is involved
in developing the new land management plans and will
provide TNF with guidance for the future of the Forest.
fGiven the anticipated duration of the Proposed Plan
(ten years) and the overall duration of Resolution
Copper’s mining operations (decades into the future), it
is disingenuous for TNF to rush this Proposed Plan
through at this time. Instead of waiting until a new
management plan is adopted, TNF proposes to examine
Resolution’s Proposed Plan under an almost thirty (30)
year old management plan which is admittedly
antiquated and severely outdated. Resolution’s Proposed
Plan seeks an authorization period of at least ten years.
To judge and examine Resolution’s Proposed Plan
under an outmoded land management plan is insincere, a
violation of Congressional and agency intent and in
contravention of TNF’s duties to develop a new land
management plan under the 2012 Management Rule.
in an environmentally sound manner.
14 The Tribe requests and anticipates that the same
extension that was granted to Arizona Mining Reform
Coalition, et al. in 1NF’s June 18, 2014 correspondence
be extended to the Tribe.
The scoping period for the proposed Baseline activities was from May
24, 2014 through June 23, 2014. The Tonto National Forest considers
all comments received consistent with Forest Service NEPA
regulations and 36 CFR part 218.
15 The Tribe anticipates that it will have additional
comments based upon its review of the response to the
Arizona Mining Reform Coalition FOIA requests and
upon completion of the Survey contemplated by the
MOU with the Tribe.
The Tonto National Forest welcomes and encourages the San Carlos
Apache Tribe to provide additional input on the proposed Baseline
activities and other projects. The Forest considers all input received
during the NEPA process.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-104
Comment
Number Comment Response
16 The Tribe incorporates by reference all of our prior
comments on Resolution activities which have been
submitted to 1NF. The Tribe also incorporates by
reference all of our prior comments which have been
submitted to TNF on Forest-wide matters in which the
Tribe specifically called TNF’s attention to the Tribe’s
opposition to Resolution Copper’s mining related
activities.
The Tonto National Forest considers all comments received on the
proposed Baseline activities. All of the comments received are
considered and evaluated consistent with the Forest Service NEPA
regulations and 36 CFR Part 218, subparts A and B.
17 The Tribe repeats its request that TNF postpone the
public comment period on Resolution’s Proposed Plan
for the reasons set forth above.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. Comments from the San Carlos
Apache Tribe will be accepted at any time during the NEPA process
before the Responsible Official makes a decision on Resolution’s
proposed Plan.
18 Deciding Resolution’s Proposed Plan under the 1985
LMRP is a breach of faith with the public and a
violation of TNF’ s trust obligations to the Tribe. The
Tribe encourages TNF to postpone the current action
until after the new land management plan for TNF has
been adopted.
Every project and activity proposed on the Tonto National Forest must
be consistent with the 1985 land and resource management plan (Forest
Plan), as amended. The new Forest Plan, which is expected to be
finalized at the end of 2017, will not change the Forest’s legal
obligations. Accordingly, the Forest still has to adhere to the U.S
mining laws. Every decision document which authorizes a proposed
project or activity (e.g. Environmental Assessment [EA] or
Environmental Impact Statement [EIS]) describes how the project or
activity is consistent with the Forest Plan in place when the decision is
rendered. While in need of revision, the 1985 Forest Plan was designed
to provide for multiple use and sustained yield of goods and services
from the Forest in a way that maximizes long-term net public benefits
in an environmentally sound manner.
Letter 159 - Jarrell, Joseph
No Comments
Letter 160 - McCollister, Michael
No Comments
Letter 161 - Chadwick, Karen
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-105
Comment
Number Comment Response
Letter 162 - Bourke, Jessie
No Comments
Letter 163 - Featherstone, Roger
No Comments
Letter 164 - Swanson, Lesly
1 The Resolution Copper baseline hydrological and
geotechnical data gathering activities are proposed for
areas near 500 kilovolt (kVL 230 kV and 115 kV power
lines operated and maintained by SRP. SRP must be
able to access and maintain the power lines, structures
and rights-of-way associated with the lines in order to
ensure the safe and reliable delivery of power to our
customers. Maintenance routes within power line rights-
of-way or on SRP easements must remain clear. SRP
requests that Resolution Copper and their contractors
refrain from drilling, grading or storing equipment or
material within the SRP rights-of-way.
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public. Baseline activities will not occur within SRP rights-of-way.
Letter 165 - Champagne, Carla
No Comments
Letter 167 - Hood, Chris
No Comments
Letter 168 - Klopatek, Carole
1 Fort McDowell Yavapai Nation (Nation) cannot provide
adequate or informed comments, ask questions, and
compile a list of complete objections to Tonto National
Forest (TNF) letter of May 13,2014 regarding the Plan
of Operations (POO) submitted by Resolution Copper
Mining (RCM) to conduct a hydrologic and
geotechnical testing and monitoring activities on Tonto
National Forest (TNF).
The Tonto National Forest takes scoping comments at any time in the
NEPA and consultation process. Requested due dates on scoping
notices are in place to ensure that all comments can be used most
effectively in the planning process and are consistent with 36 CFR part
218 A and B and Forest Service NEPA regulations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-106
Comment
Number Comment Response
2 The legal obligation of Federal Agencies to consult with
Tribes on a government-to-government basis begins in
the Constitution, in Article I Section 8 (the Commerce
Clause), where Congress is empowered to regulate
commerce with foreign governments, between the states
and with the Ly Indian Tribes. The government of the
United States has an obligation to consult with Tribes as
sovereign nations on matters of interest and concern to
Tribes. Furthermore, Federal agencies programs and
activities must be consistent with and respect Indian
treaty rights and fulfill the Federal government’s legally
mandated trust responsibility with Trib~ Presidential
Orders and memoranda include: Executive Order 12875
(1993) Tribal Governance- specifies that the federal
government must consult with Indian Tribal
governments on matters that significantly or uniquely
affect Tribal government. By Executive Memorandum
of April 29, 1994, the federal government must consult
with federally-recognized Tribal governments prior to
taking actions that will affect those Tribal governments.
Executive Order 12898 ( 1994) Environmental Justice-
specifies that the federal Agency will consult with
Tribal leaders on steps to be taken to insure that
environmental justice requirements are applied to
federally-recognized Tribes. Executive Order 13084
(1998) Consultation and Coordination with Indian
Tribal Governments reaffirms the unique government-
to-government relationship between Agencies and
Tribes. The Order clarifies that the obligation is upon
the federal government and not the Tribes to instigate
and ensure that consultation occurs on a timely basis.
Consultation is defined as an activity to obtain
meaningful and timely input from Tribes on matters that
significantly or uniquely affect Tribal communities.
Government to government consultation in accordance with the
National Historic Preservation Act was initiated shortly after the
Baseline Plan was determined to be administratively complete,
approximately May 2014. Government to government consultation is in
progress and is ongoing until the Forest Supervisor makes a decision.
Tribal consultation is ongoing and will conclude for this action when a
final decision regarding Resolution’s Baseline Plan is reached.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-107
Comment
Number Comment Response
Executive Order 13175 (2000) Consultation and
Coordination with Indian Tribal Governments was
necessitated as Agencies had failed to develop Tribal
consultation policies and the courts were slow to
enfranchise Tribes. This Order firmly establishes the
policy of the administrative branch of government as
one that institutionalizes regular and meaningful
consultation with Tribes in the development of federal
policies affecting Tribes. Executive Memorandum
(2004), Government-to-Government Relationship with
Tribal Governments, recognizes the unique legal and
political relationship of Tribes, and reaffirms that each
executive Department and Agency fully respect the
rights of self-government and selfdetermination in their
working relationships with federally-recognized Tribal
governments.
3 Presidential Orders and Constitutional mandates are
expressed in statutes and the policies of the several
Federal Agencies that relate to Tribal matters. The
Department of Agriculture and the Service is thereby
mandated to interact with Tribes on a government-to-
government basis. The Service, has defined Tribal
government consultation and coordination requirements
in the Forest Service Manual under section 1560 dealing
with State, Tribal, County, and Local Agencies; Public
and Private Organizations. Section 1563 outlines
consultation procedures with American Indian and
Alaska Natives. Under this section, table 1563.11
outlines Tribal Government Consultation and
Coordination Requirements, documenting the authority,
whom to contact, subject matter, and time frame in
which to complete the necessary consultation. The
aforementioned mandates that the Service must abide by
include: AIRF A - American Indian Religious Freedom
The Forest Service is complying with the NHPA and NEPA regulations
in the preparation of this preliminary EA. Please refer to Section 1.6 for
a summary of the ongoing consultation efforts. The Tonto National
Forest has initiated consultation with 10 Native American Tribes
including the Fort McDowell Yavapai Nation. This consultation is
consistent with all applicable federal laws, regulations, and Forest
Service policies. Government to government consultation is in progress
and is ongoing until the Forest Supervisor makes a decision. Tribal
consultation is ongoing and will conclude for this action when a final
decision regarding the proposed Baseline Plan is reached.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-108
Comment
Number Comment Response
Act of 1978 ARPA- Archeological Resources Protection
Act of 1979, as amended and implementing regulations.
Federal Land Policy and Management Act of 1976 and
implementing regulations. NFMA- National Forest
Management Act of 1976, as amended and
implementing regulations. NAGPRA -Native American
Graves Protection and Repatriation Act of 1990, as
amended. NEPA- National Environmental Policy Act of
1969, as amended (and CEQ regulations at 40 CFR parts
1500-1509). NHPA- National Historic Preservation Act
of 1996, as amended. RFRA - Religious Freedom
Restoration Act of 1993. Executive Order 13007 of
1996 -Indian Sacred Sites on federal land directs the
Federal Agencies to accommodate access to and
ceremonial use of Indian sacred sites by Indian religious
practitioners, as well as to avoid adversely affecting the
physical integrity of such sacred sites.
4 As we understand, the purposes of the aforementioned
activities are to “collect hydrologic, geochemical and
geotechnical data in order to provide baseline
information on these aspects of the environment over an
area being considered for a potential tailings storage
site.” The TNF provided the Nation with, in our onion,
an incomplete survey conducted by archaeologists from
WestLand Resources to supposedly define the
boundaries of those cultural sites that occur within the
proximity of any ground disturbing activities.
By letter dated August 21, 2014, addressed to Ruben Balderas,
President, Fort McDowell Yavapai Nation, with carbon copies sent to
Carole Klopatek, Government Relations, and Phil Dorchester, General
Manager of the Fort McDowell Yavapai Nation, the Tonto National
Forest responded to your concern. In summary, on May 13, 2014, the
Forest sent copies of the “Resolution Project: A Cultural Resources
Inventory of Baseline Hydrologic and Geotechnical Data-Gathering
Sites and Access Roads in the Foothills of the Superstition Mountains,
Northwest of Superior, Arizona,” dated April 30, 2014 to the President
and General Manager. This was done prior to the release of the legal
notice initiating scoping, in order to provide you with the most
information possible to provide comments and concerns. The final
decision on this project will take into consideration the findings of the
archaeological survey.
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known or currently
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-109
Comment
Number Comment Response
identified cultural resource sites that would be affected by the Baseline
activities.
5 This was the only information that as provided to the
Nation in regard to the POO. The Nation is unclear why
other documents were not directly provided.
The Tonto National Forest provided copies of the Cultural Resource
survey report to the Fort McDowell Yavapai Nation on May 13, 2014
in addition to the information included in the scoping letter. Additional
information about the proposed Baseline activities is available online at
the project website.
6 Moreover, the Nation wishes to consult on the entire
document not just what was contained on the 78 pages.
The Tonto National Forest initiated consultation with 10 Native
American Tribes including the Fort McDowell Yavapai Nation in May
of 2014. The Forest continues to consult with the Fort McDowall
Yavapai Nation and other Native American Tribes relative to
Resolution’s Baseline Plan. This consultation is consistent with all
applicable laws, regulations and policies, and the Forest will continue
to consult with the Fort McDowell Yavapai Nation until a decision on
Resolution’s proposed Plan is reached. .
7 As the U.S. Forest Service, including TNF, are well
aware the Yavapai’s were and are currently stewards of
the land area and including where RCM has and
continues to seek mine and mine related activities-
including where the proposed tailings are to be located.
We are deeply concerned and frustrated that RCM’s
current and planned activities will cause irreparable
harm to the environment including, but not limited to,
contaminating scarce water supplies, decimating the
land base directly through mining practices and post
mining subsidence, destroying habitat for endangered
species, and causing massive surface damage.
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and would be addressed in a separate
environment document. Therefore specific resource discussions do not
address the deep underground copper ore body. Chapter 3 does address
and discuss impacts to several resources including endangered species,
water resources, and several other resources from the Baseline
activities.
8 Mining will also impact lands that are tied to our
cultural and religious heritage as this region is part of
the Yavapai ancestral territory. Dewatering, land sub
idence polluting of the land and water; all of these
activities will desecrate this sacred area.
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known/identified
cultural resource sites that would be affected by the Baseline activities.
The purpose and need for Baseline activities is to gather additional
baseline hydrological and geotechnical data (Section 1.4) to determine
the area’s suitability as a tailings storage location. Section 1.5.1
describes the consideration of connected actions. Potential effects of
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-110
Comment
Number Comment Response
mining the deep underground copper ore body will be described based
on Resolution’s general mine plan, and they would be addresses in a
separate and appropriate NEPA document.
9 We cannot express in words how deeply felt this land is
to the Yavapai - it simply transcends words. Damage
that will result from this mine cannot be mitigated away.
\with thi document, the Nation also incorporates here by
reference all prior statements and · testimony the Nation
has given to U.S Forest Service (FS) personnel, the
Department of /, 3.3 3
As discussed in the preliminary EA, Section 1.5.1, the development of
the deep underground copper ore body is not a connected action to the
proposed Baseline activities, and would be addressed in a separate
environment document. Therefore specific resource discussions do not
address the deep underground copper ore body. Chapter 3 does address
and discuss impacts to several resources including endangered species,
water resources, and several other resources from the Baseline
activities.
10 With this document, the Nation also incorporates here
by reference all prior statements and · testimony the
Nation has given to U.S Forest Service (FS) personnel,
the Department of Agriculture, Congress, administration
officials, and other federal officials on RCM and those
of other Tribal entities, including, but not limited to, San
Carlos Apache Tribe and Inter Tribal Council of
Arizona (ITCA).
The Tonto National Forest takes scoping comments at any time in the
NEPA and consultation process. Requested due dates on scoping
notices are in place to ensure that all comments can be used most
effectively in the planning process and are consistent with 36 CFR part
218 A and B and Forest Service NEPA regulations.
11 It is apparent from the Cultural Resources Survey and
other activities by RCM and TNF have undertaken or
have failed to undertake that the TNF believe the
Yavapai are not connected to this land and area as
intimately and as strongly as other Tribes. It also
appears to the Nation that TNF categorizes Tribes as
having similar sacred sites, backgrounds, religious
beliefs and practices, ties to the land, cultural beliefs and
practice, etc. However, we are not, for a lack of a better
word, under one functional Tribal belief. The Yavapai
have a very distinct linage unrelated to other Tribes such
as the Apache. Traditions, cultural beliefs, and religious
practices, etc. may appear to overlap to the casual
observer, but upon examination, there are clearly very
distinct differences. It is true that certain lands are held
Beginning in April of 2014, Anthropological Research, LLC, (on
behalf of the Tonto National Forest) initiated an “Ethnohistoric/
Ethnographic Study of the Superior Area, Arizona.” We are eager for
you to accept our invitation of May 28, 2014 to participate in the
ongoing study.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-111
Comment
Number Comment Response
sacred by various Tribes, but those traditions and beliefs
that are known to be carried down since time
immemorial are very distinct and often distinct in origin.
Yet, the TNF, on a number of occasions, has chosen not
include information regarding the Yavapai- this includes
actions taken under this POO. Thus, we believe and
request, among other items, that an Ethnographic Study
be completed in order to help minimize the gaps in
information the TNF has in the understanding of the
Yavapai beliefs and behaviors. We trust such as study is
appropriate for studying issues and problems that the
Nation has regarding this project and RCM’s overall
mining project.
12 To some extent, there are no readily amenable
traditional or quantitative or experimental methods
alone that can explain and identify the Yavapai ties to
this area. Thus, we wish to begin a dialog as to how to
accomplish this process.
The Tonto National Forest will discuss methods and information that is
available that can explain or identify the Yavapai ties to the region.
This information may be included as part of the Section 106
consultation process or other formats consistent with all applicable
federal laws, regulations and Forest Service policies.
13 The Nation objects to this entire scoping procedure as it
is premature, especially without regard to direct
Consultation and the lack of knowledge the TNF has to
Yavapai religious, cultural, and traditional ties to the
land, sacred sites, etc. The Nation has not been
consulted or questioned as to the aforementioned survey
or on the next steps in RCM overall mining plan (i.e., in
an all-inclusive step-by-step Plan of Operation to mine
this area.
The purpose of scoping is to collect information from stakeholders
including Native American Tribes regarding their interests and
concerns regarding a proposed action. The cultural resource survey
report has been provided for your reviews and the Tonto National
Forest welcomes your input on the report. Also, see Section 1.6 of the
preliminary EA for additional detail on consultation efforts.
Resolution has submitted a General Mine Plan of Operations to the
Tonto National Forest and the Forest considers the plan complete.
Copies of Resolution’s General Mine Plan of Operations are available
for downloading from Resolution’s website.
14 the FS has taken the positiOn to allow each separate
activity that RCM performs as a single individual
activity without cumulative impacts analysis (although
the purpose of RCM is to mine and, therefore all
activities surrounding this entire project is all under one
Section 3.2 of the preliminary EA and each resource
described/discussed in Chapter 3 of evaluates potential cumulative
impacts from the Proposed Action. Section 1.5.1 evaluates connected
actions including the potential development of the deep underground
copper ore body.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-112
Comment
Number Comment Response
aegis - RESOLUTION COPPER MINE). POO’s are
being proposed on every portion of their proposed
activities, including current and proposed operations, as
opposed to ONE SINGLE POO for the entire mining
operation.
15 This so called POO encompass hydrologic and
geotechnical testing and monitoring activities. To be
clear, the Nation does not view the proposed activities
as an independent or routine event. These activities are
not occurring in a vacuum separate from all other
activities that RCM and others have and are planning
to/proposing to undertake in and around this area.
Rather, these activities are all related, cannot be
segmented, and must be considered by TNF
concomitantly.
As described in the preliminary EA (Section 1.5), Resolution’s
Baseline Plan has independent utility from their General Plan of
Operations, and other related proposals submitted to the Forest.
Section 1.5.1 of the preliminary EA considers connected actions
including Resolution’s other proposed actions. The potential connected
actions are evaluated consistent with Council of Environmental Quality
(CEQ) regulations found at 40 CFR 1508.25.
16 Your May 13th letter states that the mining operations
are allowable under currently mining laws. However,
this is not truly the case. The TNF letter potentially
indicates - and we strongly oppose to this line of inquiry
if this is indeed the case - that they may view this
proposed activity as a stand-alone project not connected
with any other RCM mining actions. It appears that the
review of the direct, indirect, and cumulative
environmental impacts will be limited and may
disregard the cumulative impacts from RCM’s other
operations and other approved POO’s directly linked to
this and the entire mining operations ofRCM. Yet under
the National Environmental Policy Act (“NEP A”), the
USFS must fully review the impacts from all not
isolated “past, present, and reasonably foreseeable
future actions.” Thus, your review must not be limited in
scope nor narrow in view of the entire project as it
would not be congruent under the referenced 36 CFR
Part 228 as the National Environmental Policy Act
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis (including other RCM
projects). Each resource section (Sections 3.3 to 3.15) contains a
cumulative impact assessment that evaluates each resource where there
are potential cumulative impacts. The cumulative impacts considered if
the resource was vulnerable to incremental effects, other project with
similar effects, significance of the impacts, and if there were any other
analyses in the area that identified concerns with potential cumulative
effects.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-113
Comment
Number Comment Response
(“NEPA”) clearly demands the FS to fully analyze
impacts from all RCM”s “past, present, and reasonably
foreseeable future actions” for the entire mining
operation.
17 (l) Connected actions, which means that they are closely
related and therefore should be discussed in the same
impact statement.
As described in the preliminary EA (Section 1.5), Resolution’s
Baseline Plan has independent utility from their General Plan of
Operations, and other related proposals submitted to the Forest.
Section 1.5.1 of the preliminary EA considers connected actions
including Resolution’s other proposed actions. The potential connected
actions are evaluated consistent with Council of Environmental Quality
(CEQ) regulations found at 40 CFR 1508.25.
18 Alternatives, which include: (1) No action alternative.
(2) Other reasonable courses of actions. (3) Mitigation
measures (not in the proposed action).
Please refer to Section 2.4 of the preliminary EA for a description of a
range of reasonable alternatives that were considered. Also refer to
Sections 2.3.5, 2.3.6, and 2.5 for a description of reclamation,
applicant-proposed environmental protection measures, and mitigation
measures that would reduce or avoid the impact to resources.
19 The vague area of impact of the Project as purported by
RCM and TNF state that the total area of
disturbance/impact would be 92.98 ac. However,
RCM’s calculations do not scientifically/correctly
reflect the total area of impact- the area, in fact, is much
greater. Unfortunately, impact was not calculated
according to and consistent with required scientific
methodologies under NEPA guidance documents. For
example, the calculations that are reported by RCM are
only based on a very small consideration of each of the
41 “installations” and 33 geotechnical test “trenches.” In
reality, to minimize their impact, RCM incorrectly
stated the impact (as they report) as a partial
representation of the total combined disturbance area of
each ofthe 74 ‘sites’ (41 “installations” and 33
geotechnical test trenches equal 74 sites) that are to be
analyzed. Of course, this does not include the other
listed activities. Each site will have consultants,
The information provided during the Scoping period for this Proposed
Action was intended to present a general idea of the Proposed Action
and the area in which it would take place. Section 2.3 of the
preliminary EA provides a more developed description of the Proposed
Action (including access roads, heavy equipment use, anticipated time
at each site, etc.). Chapter 3 of the EA describes and discusses the
resources potential impacted by the Proposed Action. Additionally,
Resolution modified their original Proposed Action based on comments
received during the Scoping period. Updated and more detailed
disturbance acreage estimates are provided in Table 2-1 of Chapter 2
and Section 2.3 discusses the changes to the Proposed Action that
would serve to minimize disturbance to environmental resources.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-114
Comment
Number Comment Response
surveyors, etc. that will dig and place hydrological and
non-hydrological related machinery, transmitters,
piping, heavy equipment, etc. They will carry, using
various modes of transport from site to site, equipment
and ancillary accessories needed to both construct and
monitor those 74 sites -along with a host of other causal
agents including, but not limited to employing water
trucks- that will cause damage to the areas resources -
will disrupt surface and subsurface of soil - will disrupt
cultural resources and sacred sites within what appears
to be 21 sections ofTNF lands (see vicinity Map, Fig. 1
RCM’s POO). This entire referenced area becomes the
disturbance envelop (area impacted) not each individual
installation, trenches, etc. RCM’s strategy and
propensity to dissect their in.di.vidual POO’s to give the
appearance of no coordinated and cumulative activities,
thereby mm1m1Ze cumulative and mmmg actiVIties,
are clearly demonstrated within this specific project.
Their total area of impact analysis does not include
coordinated activity between each of the 72 sites,
laydown yards, road access, equipment access, etc. For
example, each geotechnical drilling and piezometer
installation proposed would have a disturbance footprint
of approximately 15 feet by 40 feet (0.0 1 acre)- again-
this activity is not isolated and our scientific calculations
show this area to be much greater. Thus, the entire area
that they are using becomes the disturbance envelope.
We specifically request to see RCM’s calculations as to
the areas of impacts and discuss this with the FS as our
total area of impact calculations are orders of magnitude
greater than what is reported. Please provide the correct
impact information. It appears that rather than
scrutinizing RCM’s calculations, TNF used RCM’s area
of impact calculations without question. Errors made by
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-115
Comment
Number Comment Response
RCM and concurrence by the TNF as to the area of
impact must be addressed by TNF. RCM appears to be
attempting to minimize the project’s impact. l owever,
as we can demonstrate by our calculations, RCM’s
calculations are not only scientifically incorrect, but are
meant to mislead the public. The TNF must reanalyze
the area of impact usmg the aforementiOned rational.
Thus, there are so many unanswered questions as to
describe what activities and their impacts- it is
impossible to fully comment as there is not enough
information provided by either RCM or the FS to make
an informed and meaningful decision as to the impacts.
The Nation requires clarification and consultation on
this matter.
20 We also have questions including, but not limited to,
impacts from installation of bentonite seals described
under Sec. 4.2 Water Quality. These drilling practices
and potential impacts of the entire drilling program to
the existing groundwater aquifer system and the area
must be discussed.
The Proposed Action, including a description of the drilling activities,
is described in Section 2.3 of the preliminary EA. Potential effects from
Resolution’s Baseline Plan to water resources are presented and
discussed in Section 3.3. Resolution would be obligated to comply with
Arizona Department of Water Resources drill hole abandonment
procedures (AAC R12-15 and ARS Title 45, Chapter 2, Article 10).
21 The use of excavated pits under Sec. 4.3, Solid Wastes-
how and where would they be located and how would
they be reclaimed. What is their impact? What are “open
settling pits at unoccupied drill sites” that are referred to
throughout the document?
Test trenches require a 60’x30’ area where vegetation and soils will be
disturbed to allow safe access of personnel to inspect and perform soil
infiltration tests. Reclamation would occur immediately after test
trench activities have concluded. Settling pits would be used to store
saturated drill cuttings within the footprint of each drill pad. More
detailed information regarding Resolution’s Baseline activities can be
found in the preliminary EA Section 2.3.
22 We further have questions as to RCM’s reliance on
Arizona’s water laws as opposed to Federal water rights
and Federal laws as these activities are occurring on
Federal lands.
Resolution is obligated to comply with Clean Water Act regulations
and permitting requirements, and Arizona Department of Water
Resources regulations throughout the life of the project.
23 These activities are actually scheduled for long-term
use. In fact, they are of an indeterminate use which
misrepresents the shorter-term nature as stated within
The Proposed Action, including a description of the Baseline activities
timeframes (up to 10 years for monitoring), is described in Section 2.3
of the preliminary EA. Effects from the Baseline activities to Water
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-116
Comment
Number Comment Response
your May 13th letter and within the POO. For example-
under Sec. 5.1 Hydrologic Testing & Monitoring Well
Sites it states- “For sites that would continue to be used
long-term for scheduled groundwater monitoring, it may
be possible to reclaim a portion of the drill site while
still maintaining access to and parking at the monitoring
well.” Hydrologic monitoring of wells and piezometers
testing and monitoring activities as well as monitoring
wells and road maintenance and drill site access for
hydrological monitoring are proposed for 10 years - yet
these activities and maintenance of equipment are
required for the entire time this mine and tailing site will
be active- 60, 70 or more years! Plus, this does not
include the required monitoring for purposes post-
mining as this will well exceed the 10 year period
referenced. Clearly, that the nature of what is being
proposed is not being considered in its entirety or
longevity. Please provide the correct longevity
information.
Resources are discussed in Section 3.3. The purpose and need for
Baseline activities is to gather additional baseline hydrological and
geotechnical data (Section 1.4) to determine the area’s suitability as a
tailings storage location. Section 1.5.1 describes the consideration of
connected actions. Potential effects of mining the deep underground
copper ore body will be described based on Resolution’s general mine
plan, and they would be addresses in a separate and appropriate NEPA
document.
24 As mentioned above and in previous correspondence to
the FS, the Nation requests government-to-government
consultation on this matter- at the appropriate local
AND D.C. Federal level. We believe, in regard to RCM,
TNF has demonstrated a lack of understanding and
disregard of the applicable laws as well as FS
policies/regulations/rules, USDA
policies/regulations/rules, executive orders, and other
federal policies and regulations as they apply to NEPA,
Tribal entities, sacred sites, traditional and cultural
properties, etc. In fact, we believe TNF has favored and
has shown prejudice in favor of RCM activities
regardless of requirements within the laws, FS directives
and regulations, and certain executive orders, and
federal policies. We wish to discuss what information
The Tonto National Forest initiated consultation with 10 Native
American Tribes including the Fort McDowell Yavapai Nation in May
of 2014. The Forest continues to consult with the Fort McDowall
Yavapai Nation and other Native American Tribes relative to
Resolution’s Baseline Plan. This consultation is consistent with all
applicable laws, regulations, and policies, and the Forest will continue
to provide the Fort McDowell Yavapai Nation with information.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-117
Comment
Number Comment Response
the TNF and FS considers “meaningful,” how this
information has and will be used to evaluate this project
and all other RCM activities, who has and will further
evaluate the Project (and all other activities related to
RCM), qualifications of individual performing the
reviews and analysis, who is/are the Responsible
Official(s), and how the why the TNF has and will come
to their decisions.
25 In relation to the area where RCM is and is planning
activities, ethnographic studies be conducted on and
with Tribal entities that have ties to this area. Such
studies should document and map the cultural
landscapes as they are viewed by and important to
Tribal entities. Such studies would assist in developing
the needed protocols for dealing with Native American
Graves Protection and Repatriation Act (NAGPRA)
issues as well as for FS planning and decision making in
this area. Developing a human ecology mapping
approach to understand the Tribal connections to these
lands and natural resources and understanding values,
attitudes, and practices of the effected Native American
communities is essential. We request a formal response
as to when they will be performed or, conversely,
justification as to why the TNF or FS will not perform
such studies as there is countless documentation stating
that this area is significant to not only the Yavapai but
many Tribal entities. This was requested to TNF in
previous correspondence. The Nation takes issue with a
number of items in the Cultural Resources Survey. We
request to see a complete data set that went into the
Cultural Resources Survey that TNF mailed to the
Nation on May 13, 2014. We wish to see any and all
data collected including data that was not comprised in
the final report.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. It is the Forest’s intent to
take into consideration the findings of the Study, in conjunction with
Tribal comments which come out of government to government
consultation in the final decision on the Baseline Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-118
Comment
Number Comment Response
26 A written and digital color copy of the final TNF
approved and accepted Cadastral Survey that RCM was
required to complete and submit under the RCM Pre-
feasibility Activities Plan of Operations Environmental
Assessment (EA) (submitted May 201 0). We
understand that there were delays in processing this
survey; however, the Nation assumes this survey must
have been completed by now given that it was a specific
requirement (prior to related RCM activities proposed or
taking placed) and a considerable length of time has
elapsed since this pre-feasibility decision was filed. was
requested to TNF in previous correspondence.
By letter dated August 21, 2014, addressed to Ruben Balderas,
President, Fort McDowell Yavapai Nation, with carbon copies sent to
Carole Klopatek, Government Relations, and Phil Dorchester, General
Manager of the Fort McDowell Yavapai Nation, the Tonto National
Forest provided a hardcopy and digital copy of the Cadastral Survey
conducted as a part of Resolution Copper Mining’s Pre-feasibility
Activities Plan of Operations dated May 2010.
27 what filed techniques will be employed? Will they be
GPS’ed? How will specific sites be selected/criteria?
How closely spaced will they be? Who will be
performing these tasks? Will there be separate data
loggers/computers attached to each unit or will there be
someone collecting data using one computer? Will
telemetry be employed? If so, how and where will it be
located and how constructed? How often and how many
people will be in the field collecting this data?
Please refer to Section 2.3 of the preliminary EA for a description of
the Proposed Action including the location and description of access
roads, hydrological testing and monitoring wells, geotechnical drill and
piezometer sites, geotechnical test trench sites, and reclamation
activities.
28 What exact protocols and methods would be taken
regarding cultural resources and any finds? What is
specifically being done to assure integrity of sacred
sites? Will there be a cultural resource specialist
accompanying RCM or their subcontractors? Further
information is required on cultural resource protections
other than a sentence stating that there will be avoidance
of these resources?
By letter dated August 21, 2014, addressed to Ruben Balderas,
President, Fort McDowell Yavapai Nation, with carbon copies sent to
Carole Klopatek, Government Relations, and Phil Dorchester, General
Manager of the Fort McDowell Yavapai Nation, the Tonto National
Forest provided responses to your questions.
As described in Section 2.3.6 of the preliminary EA, there are several
measures that would be followed for cultural resource protection and/or
monitoring. Section 3.9 describes the cultural resources
identified/known in the proposed project area. The Proposed Action
would not impact any known cultural resource sites.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-119
Comment
Number Comment Response
29 what vegetation will be affected (if the well and other
sites are not pre-selected you cannot know) and what
specific protections are being made for vegetation?
Effects to Vegetation Communities are evaluated in Section 3.5 of the
preliminary EA.
30 What exact protocols and methods would be taken
regarding cultural resources and any finds? What is
specifically being done to assure integrity of sacred
sites? Will there be a ?.$ ·/ cultural resource specialist
accompanying RCM or their subcontractors? Further
information is required on cultural resource protections
other than a sentence stating that there will be avoidance
of these resource~ lwhat vegetation will be affected (if
the well and other sites are not pre-selected you ~ Z
cannot know) and what specific protections are being
made for vegetation? The same questions are asked
regarding wildlife. [what vegetation will be affected (if
the well and other sites are not pre-selected you cannot
know) and what specific protections are being made for
vegetation?]
As described in Section 2.3.6 of the preliminary EA, there are several
measures that would be followed for cultural and biological resource
protection and/or monitoring. Sections 3.5, 3.6, 3.7, 3.8, and 3.9
describe the biological and cultural resources environment and discuss
potential impacts. The Proposed Action would not impact any known
cultural resource sites.
31 will the Nation be prohibited from entering into this
area? If so, to what extent and for how long?
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public.
32 what resource surveys have been completed by TNF in
the area of this project? (This is assuming that the well
and other sites have been pre-selected. If sites are not
pre-selected, who in TNF will be examining these sites
to determine the resources and if they are viable sites?)
There have been several resource surveys conducted for this proposed
project, including, but not limited to: cultural resources, vegetation,
wildlife, special status plant and wildlife species, visual resources, air
emissions, noise and vibration. The Forest Service did not conduct
these surveys; however, representatives of the Forest Service and
Resolution conducted the surveys. Please refer to Chapter 3 of the
preliminary EA to review analysis of resources based on the surveys
completed for the project.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-120
Comment
Number Comment Response
33 what TNF personnel/specialist will review this project in
the field (i.e., pre- and postproject actions) to assure that
impacts/damages did not occur? If impacts/damages do
occur, what will TNF do to ensure that reclamation and
restoration will be conducted? Who will conduct and
pay for such reclamation and restoration activities?
Forest Service Minerals administrators conduct field reviews pre-, post-
and during implementation of a project. Other resource specialists
assist as needed, such as archaeologists, wildlife biologists and
engineers. The Tonto National Forest will hold a reclamation
performance bond to cover the cost of disturbance on National Forest
System lands, including contingency costs, until it is determined that
satisfactory reclamation has been completed by Resolution.
34 what are the liabilities/bonding would TNF hold RCM
responsible for?
The Tonto National Forest will determine the appropriate liabilities and
bonding requirements for the project after the Forest Supervisor has
made a decision regarding the proposed Baseline activities. The bond
will be required to cover the estimated reclamation costs should the
Forest be required to complete reclamation.
35 What is the real and exact time-frame of this project -in
total-including restoration? Are there any extensions
that are built-in?
Please refer to Section 2.3 of the preliminary EA for a description of
the Proposed Action including a description of the timeframe proposed
for the Baseline activities and reclamation. There are no extensions to
the timeframe built-in to the Proposed Action.
36 In order to assure accuracy, the Nation, under
government-to-government consultation,requests to
discuss the aforementioned are of impact/disturbance
envelope and calculations prior to re-analysis.
By letter dated August 21, 2014, addressed to Ruben Balderas,
President, Fort McDowell Yavapai Nation, with carbon copies sent to
Carole Klopatek, Government Relations, and Phil Dorchester, General
Manager of the Fort McDowell Yavapai Nation, the Tonto National
Forest expressed eagerness for open dialogue extended a request to the
tribe to participate in face to face government consultation. In addition,
this letter also provided a description of how estimated surface
disturbances proposed by Resolution were evaluated and clarified
based on revised conceptual project layouts, schematics, typical project
equipment, and plan and profile views of proposed disturbance areas
(see Appendix B of the Baseline Plan). Surface disturbance calculations
include considerations for access by personnel and the various forms of
equipment proposed to be used.
The Tonto National Forest recognizes and respects the sovereign nature
of the Fort McDowell Yavapai Nation as a federally-recognized Indian
Tribe, entitled to government to government consultation, which the
Tonto National Forest is amenable to and willing to conduct at any time
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-121
Comment
Number Comment Response
during the NEPA process. As stated in our August 21, 2014 letter,
comments will be accepted at any time during the NEPA process
before the Responsible Official makes a decision.
37 REMEDY -SCOPING SHOULD BE WITHDRAWN
UNTIL: Ethnographic surveys be conducted.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. It is the Forest’s intent to
take into consideration the findings of the Study, in conjunction with
Tribal comments which come out of government to government
consultation in the final decision on the Baseline Plan.
38 REMEDY -SCOPING SHOULD BE WITHDRAWN
UNTIL: Answers to the Nation’s questions are satisfied.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. The Forest Service will
consider the findings of the Study, in conjunction with Tribal
comments which come out of government to government consultation
in the final decision on the Baseline Plan.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. Comments from the Fort McDowell
Yavapai Nation will be accepted at any time during the NEPA process
before the Responsible Official makes a decision on Resolution’s
proposed Plan.
39 All scoping documents using this erroneous 92.98 ac
area of impact must be republished/reissued with the
correct information so that the Public has an accurate
understanding ofthe Project and comprehension ofthe
resulting impacts.
Please refer to Section 2.3 of the preliminary EA for a description of
the Proposed Action including a description of the Project Area, and
the area of disturbance from the Baseline activities.
40 IN CONCULSION, over the last several years, the FS
has taken a position regarding RCMrepeatedly stating
the requirement for RCM to follow and comply with a
FULL NEPA review. This position has been reiterated
in testimony by FS officials in different House and
Senate hearings on various version of legislation
concerning RCM. The Nation has met with Forest
Service and Department of Agriculture officials in DC
The preliminary EA prepared by the Tonto National Forest complies
with a full NEPA review for the proposed Baseline Activities. This
includes (in Section 3.9) an evaluation of potential effects on Native
American cultural, religious, and sacred sites. Section 1.5.1 describes
evaluation of connected actions including the potential development of
the deep underground copper ore body. Additionally, it is anticipated
that the “Ethnographic/Ethnohistoric Study of the Superior Area,
Arizona” (Study) will be completed prior to a final decision being
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-122
Comment
Number Comment Response
and they had promised that this project, as a whole,
would comply with NEPA. In fact, the requirement for
NEP A and the requirement to examine how RCM will
affect Native American cultural, religious, and sacred
sites for the entire RCM operation is clear to the FS at
the National level. Current and past FS Associate Chiefs
have testified before Congress on this matter. For
example, FS Associate Chief Mary Wagner before the
U.S. House Subcommittee on National Parks, Forests
and Public Lands Natural Resources Committee on June
14,2011 Concerning H.R. 1904: the Southeast Arizona
Land Exchange and Conservation Act of2011, stated
that the FS had a principal concern regarding RCM and
NEPA mining exploration activities under an area that is
sacred should not continue “without a review or study.”
Associate Chief Wagner continued her testimony
making additional statements as to the sacred and
religious nature of this area to Native Americans. Ms.
Wagner clearly articulated that: “it is important to more
fully understand the scope of the project before
proceeding and address potentially significant
environmental concerns and sites of high importance to
local Tribes.”
reached on the Baseline Plan. The Forest Service will consider the
findings of the Study, in conjunction with Tribal comments which
come out of government to government consultation in the final
decision on the Baseline Plan.
41 We have repeatedly noted that RCM operation will
cause irreparable damage to the environment of this area
whose resources are inextricably linked to sacred sites,
archeological, and the cultural and religious heritage of
the Yavapai People. Thus, requesting that Scoping be
indeterminately withdrawn until Consultation and an
Ethnographic survey be completed is warranted. The
Nation has discussed and is on record regarding sacred
sites of this area. The very integrity of these sites (as
well as cultural resources) will be unavoidably damaged
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. It is the Forest’s intent to
take into consideration the findings of the Study, in conjunction with
Tribal comments which come out of government to government
consultation in the final decision on the Baseline Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-123
Comment
Number Comment Response
given the breath and actual longevity of this project
POO.
42 The Nation has a great concern and opposes how the FS
can evaluate the project independently from all other
actions that RCM is undertaking and will undertake
along with their resulting direct and indirect impacts.
As described in the preliminary EA (Section 1.5), Resolution’s
Baseline Plan has independent utility from their General Plan of
Operations, and other related proposals submitted to the Forest.
Section 1.5.1 of the preliminary EA considers connected actions
including Resolution’s other proposed actions. The potential connected
actions are evaluated consistent with Council of Environmental Quality
(CEQ) regulations found at 40 CFR 1508.25.
43 The Nation agrees and supports the joint comments
submitted on this matter by the Arizona Mining Reform
Coalition, Center for Biological Diversity, Concerned
Citizens and Retired Miner Coalition, Maricopa
Audubon Society, Sierra Club- Grand Canyon Chapter,
Mr. John Krieg, Mr. Roger Featherstone, and others.
Thus, the Nation has included these comments rather
than repeat them here within our letter. However, please
understand that these comments should not be taken as
secondary, we have included them as an attachment for
brevity - not to minimize them - and wish to consult on
each of the points outlined within the letter.
Consistent with Forest Service NEPA regulations, the Tonto National
Forest considers all comments received.
44 What we also found disturbing is that the TNF only
elected to publish on their website one part of this POO
co~taining 7~ pages. Whereas, the entire P.O.O from
RCM is approximately 511 pages. Why isn’t the entire
POO hsted under the FS website or IS It posted m
another area that the Nation missed? If this was a TNF
error, we request that this entire document be placed for
the public.
Resolutions Plan of Operations for the Baseline Hydrological and
Geotechnical Data Gathering Activities (Baseline Plan) is available on
the internet at the project website. The Baseline Plan has been available
since May 13, 2014, prior to the publication of the scoping notice.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-124
Comment
Number Comment Response
Letter 169 - Klopatek, Carole
No Comments
Letter 170 - Klopatek, Carole
No Comments
Letter 171 - Nordan, Laura
1 the proposed access from US 60 is located in an area of
planned roadway widening. The project, known as the
“Silver King” segment (ADOT project number
H790001C), is anticipated to begin construction in early
2015 with an approximate duration of 18 months.
Based on comments received during Scoping, Resolution agreed not to
use FR 2395 to access the Baseline activities (Section 2.3 of
preliminary EA). As a result, access to the previously disturbed areas
that connect to FR 2395 and FR 2397 in Section 6 would no longer be
necessary.
Letter 172 - Macias, Tom
1 I have alsways been amazed at all the diversity of life
there. From elf owls, desert tortoises, every kind of
Sonoran desert animal lives there. Its the stronghold of
our mule deer population. We cannot continue to
sacrifice our fellow Earth inhabitants for our own greed.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
2 Before we know, we won’t have anything to protect
except designated parks which already look like money
producing amusement parks. Over crowded with people
trying to get the feel of a wild place. This property is a
wild place! We must set a presidence and stop the abuse
of our natural environment.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Letter 175 - Rambler, Terry
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-125
Comment
Number Comment Response
Letter 176 - McMullen, Patrick
1 These comments are not intended to speak specifically
on behalf of any one Member Tribe or to address any
specific, traditional, religious and cultural concerns that
any one of our Member Tribes may have on this project.
The Forest Service is required to seek these specifics
through informed one-on-one consultation with each
interested individual Tribes in Arizona as required by
applicable law.
The Tonto National Forest is consulting with 10 Native American
Tribes and considers all comments received regarding the proposed
Baseline activities consistent with NEPA, Section 106 of the NHPA,
and Forest Service policies.
2 The environmental impact statement (“EIS”) or
environmental assessment (“EA’’) must fully analyze all
direct, indirect, and cumulative impacts- including from
Resolution’s Main Mine proposal at Oak Flat, pursuant
to the requirements of the National Environmental
Policy Act (‘‘NEPA”), 42 U.S.C. § 4321 et seq., and
applicable law.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.4 and
1.5.1 describe that this project is “stand alone” and has separate utility;
the development of the deep underground copper ore body is not a
connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body, potential
effects on resources, including Native American Tribes religious and
cultural practices, would be considered in a separate NEPA document.
3 The Main Mine at Oak Flat is a connected action that
must be reviewed in a single EA or EIS document under
NEPA.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-126
Comment
Number Comment Response
hydrologic, geochemical, and geotechnical data from mineral
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
4 The Forest service cannot assume that Resolution has
“rights” to proceed with the Baseline Activities and PoO
and yet, at the same time, contend that the Baseline
Activities and PoO are not part of the Main Mine
proposal.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.4 and
1.5.1 describe that this project is “stand alone” and has separate utility;
the development of the deep underground copper ore body is not a
connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body, potential
effects on resources, including Native American Tribes religious and
cultural practices, would be considered in a separate NEPA document.
5 If the USFS does not consider the current proposed
project and the Main Mine as part of the same project,
then the proper permitting authority is not the 1872
Mining Law or 36 C.P.R., Part 228 regulations, but the
Forest Service’s special use permitting regulations and
requirements.
The Tonto National Forest is required under the Organic
Administration Act of 1897, (which recognizes the rights of U.S.
citizens to access National Forest System lands for all proper and
lawful purposes, including prospecting, locating, and developing
mineral resources) to consider Resolution’s proposed Baseline Plan of
Operation. The activities proposed by Resolution in their Baseline Plan
are considered a use that is reasonably incident to mineral exploration,
they are explicitly exempted from special use authorization. 36 CFR
part 251.50(a) designates special uses as “[a]ll uses of National Forest
System lands, improvements, and resources, except those authorized by
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-127
Comment
Number Comment Response
the regulations governing…minerals (part 228).” Therefore, Forest
Service special use authorization does not apply.
Refer to Section 1.3.2 of the preliminary EA for a more detailed
discussion.
6 Resolution is not “entitled” to have the Baseline
Activities and PoO approved under the Mining Law.
Please refer to Section 1.3 of the preliminary EA for a description of
United States Mining Laws and NEPA and other Forest Service mining
and mineral policy as it relates to this Baseline activities project.
Resolution’s General Mine Plan would be addressed under a separate
and appropriate NEPA document.
7 The draft EA or EIS must fully explain all baseline
conditions prior to analyzing or approving the project.
The baseline conditions evaluated in the preliminary EA for Baseline
activities, include: Water Resources, Soil Resources, Vegetation
Communities and Fire Regimes, Invasive Species, Wildlife and Special
Status Species, Range, Cultural Resources, Travel Management and
Public Safety, Recreation, Visual Resources, Air Quality, Climate
Change, and Noise. Please refer to Chapter 3 to review the analysis.
8 Without the required adequate analysis, any potential
fmding of no significant impact (“FONS I”) would be
inadequate- necessitating preparation of an EIS. The
draft EA or EIS must include an adequate mitigation
plan, including a detailed review of the impacts from,
and effectiveness of, any mitigation measures.
Chapter 3 of the preliminary EA contains the analysis of environmental
consequences and Section 1.5.2 describes the Tonto National Forest
decision framework. From the analysis presented in the EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice.
9 The draft EA or EIS must fully review all reasonable
alternatives.
Please refer to Section 2.4 of the preliminary EA for a description of a
range of reasonable alternatives that were considered.
10 The Forest Service must minimize all adverse impacts
from the project and ensure compliance with all
environmental and public land Iaws.
Chapter 3 of the preliminary EA contains the analysis of environmental
consequences and Section 1.5.2 describes the Tonto National Forest
decision framework. From the analysis presented in the EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-128
Comment
Number Comment Response
11 The Forest Service must fully analyze the project’s
impacts to threatened and endangered species.
Section 3.7 of the preliminary EA evaluates potential effects on
Wildlife and Special Status Species.
12 The Forest Service must fully comply with the National
Historic Preservation Act (“NHPA”), 16 U.S.C. § 470 et
seq.
The Forest Service is fully complying with the NHPA and NEPA
regulations in its preparation of this EA. Please refer to Section 1.6 of
the preliminary EA for a summary of the ongoing consultation efforts.
13 Given the scope of the Baseline Activities and PoO, and
in light of the project’s connection to and interdependent
relationship with the Main Mine as discussed in greater
detail in AMRC’s comments, the Forest Service should
continue the public scoping period( a) until ITCA’s
Freedom oflnformation Act (“FOIA”) request has been
fulfilled by the USFS; [b) to provide sufficient time for
meaningful government-to-government consultation
with affected Indian tribes; and((c) until ongoing and
needed ethnographic studies in the project area are
completed.
The Tonto National Forest has complied with the FOIA request from
the Inter-Tribal Council of Arizona. The response to the FOIA request
was made consistent with regulations. Preliminary EA Section 1.3 and
each of the resources analyzed in detail in Chapter 3 provide
information on the laws, regulations, policies, ordinances, and guidance
that are relevant to the proposed Baseline Activities. This includes
NRHP Section 106 compliance and consideration of traditional cultural
practices based on information provided by Native American Tribes. It
is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. The Forest Service will
consider the findings of the Study, in conjunction with Tribal
comments which come out of government to government consultation
in the final decision on the Baseline Plan.
14 In light ofthe failure of the Forest Service to provide the
requested documents, by email dated June 18, 2014,
ITCA (through its legal counsel) requested that the
USFS extend the time for comments on the scoping
document until such time as these documents could be
produced in accordance with ITCA’s request
(Attachment D). As of this writing, ITCA has yet to
receive a response to ITCA’s request for an extension as
explained in the original FOIA request, the purpose
ofiTCA’s request for information on the Baseline
Activities, the PoO and all related documents and
materials was to provide ITCA’s Member Tribes with
sufficient information to adequately comment on the
project as outlined in the Forest Service’s May 24,2014,
scoping letter and to engage in informed government-to-
The Tonto National Forest has complied with the FOIA request from
the Inter Tribal Council of Arizona. The response to the FOIA request
was made consistent with regulations.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. Comments from the ITCA will be
accepted at any time during the NEPA process before the Responsible
Official makes a decision on Resolution’s proposed Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-129
Comment
Number Comment Response
government consultation with the USFS on the project.
Because the Forest Service has failed to comply with
this request (and the FOIA), the ITCA reserves the right
to additional comments regarding the project when the
USFS finally does comply with its obligations under
FOIA.
15 The Forest Service, as an agency of the United States, is
required to engage in informed, meaningful and
advanced government-to-government consultation with
interested ITCA Member Tribes as part of its
consideration of the proposed Baseline Activities and
PoO, as well as the Main Mine as a connected action, as
required by the United States’ trust responsibility to
Indian Tribes, NEPA, 42 U.S.C. § 4321 et seq. and
applicable law. As not,ed by AMRC’s comments, this
should be completed as part of a single EA or EIS
process.
The Tonto National Forest initiated consultation with 10 Native
American Tribes consistent with NEPA and other applicable laws,
regulations, and policies in May of 2014. During the consultation
process, the Tonto National Forest will continue to provide the Native
American Tribes with information. Section 1.5.1 of the preliminary EA
evaluates connected actions including the potential development of the
deep underground copper ore body.
16 Consultation is critical if the Forest Service is to take the
necessary “hard look” at the project and all connected
actions, and their direct, indirect and cumulativ·e
impacts as required by the NEPA, as well as the NHPA,
16 U.S.C. § 470 et seq. and other laws. Anything less
could wrongfully disregard significant impacts that the
current project and the connected Main Mine (separately
or collectivity) might have on the religious, cultural,
traditional and historic relationship that certain of
Member Tribes of ITCA, including but not limited to
the Western Apache Tribes, the Yavapai and the Zuni,
have with the project area and the Oak Flat region in
general.
The preliminary EA incorporates information received during
consultation as appropriate in taking the required “hard look” at the
potential direct, indirect, and cumulative impacts. See Sections 1.6 and
3.9. Section 1.5.1 of the preliminary EA evaluates connected actions,
including the potential development of the deep underground copper
ore body.
17 By focusing the agency’s attention on the environmental
consequences of its proposed action, NEPA “ensures
that important effects will not be overlooked or
underestimated only to be discovered after resources
The Forest Service is fully complying with the NHPA and NEPA
regulations in its preparation of this EA. Please refer to Section 1.6 of
the preliminary EA for a summary of the ongoing consultation efforts
and also Section 3.9 for a discussion of Cultural Resources existing
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-130
Comment
Number Comment Response
have been committed or the die otherwise cast.”
Robertson, 490 U.S. at 349. This includes effects to
traditional cultural properties and landscapes, holy and
sacred sites, and other areas of historical concern to
Indian tribes.
conditions and potential environmental consequences from the Baseline
Plan.
18 ITCA urges the Forest Service to take a different tact
here and to comply with its trust responsibility in
conjunction with its obligations under NEPA and all
rovisions of relevant law. Furthermore,the Forest
Service is reminded that simply sending “public scoping
letters” to potentially affected tribal governments,
without more, fails to fulfill the United States’ trust
responsibility to the tribes, and disregards the plain
requirements for consultation found in NEP A and in
Section 106 of the NHP A, that also “recognize the
government-to-government relationship between the
Federal Government and Indian tribes.” This violates
the law and trust responsibility of the United States. See,
e.g., Te-Moak Tribe, 608 F.3d at 598-600 (describing
BLM’s numerous meetings, field visits, ethnographic
studies, and other consultation efforts as part of a
legitimate consultation process). ITCA urges the Forest
Service to set this past histozy aside and to engage fully
with affected tribes as required by law on all aspects of
Resolution’s proposed Baseline Activities. the PoO and
the Main Mine.
In addition to the information contained in the scoping letter, the Tonto
National Forest has provided information to Native American Tribes
during the ongoing consultation process. The government-to
government consultation process initiated by the Tonto National Forest
meets the requirements of NEPA and Section 106 of the NHPA.
19 In analyzing the direct, indirect, and cumulative impact
of the proposed project under NEPA, it is important to
understand that “[t]he [federal agency] cannot simply
offer conclusions. Rather, it must identify and discuss
the impacts that will be caused by each successive
[project], including how the combination of those
various impacts is expected to affect the environment, so
as to provide a reasonably thorough assessment of the
Section 3.2 of the preliminary EA describes the cumulative impact
assessment methodology and provides a list (Table 3-1) of projects that
are considered in the cumulative impact analysis (including other RCM
projects). Each resource section (Sections 3.3 to 3.15) contains a
cumulative impact assessment that evaluates each resource where there
are potential cumulative impacts. The cumulative impacts considered if
the resource was vulnerable to incremental effects, other project with
similar effects, significance of the impacts, and if there were any other
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-131
Comment
Number Comment Response
project’s cumulative impacts.” Klamath Sisldyou
Wildlands Center v. BLM, 387 F.3d 989, 1001 (9th Cir.
2004) (emphasis added). This includes impacts to
traditional, cultural and religious interests of Member
Tribes of ITCA.
analyses in the area that identified concerns with potential cumulative
effects.
20 to do this, the Forest Service should extend the scoping
period to provide sufficient time for the Apache Tribes
and Forest Service to complete the ongoing
Ethnographic/Ethnohistory Study that is presently being
undertaken relative to the Superior Area (including
within the current location of the Baseline Activities and
PoO) under the Memorandum of Understanding
between the San Carlos Apache Tribe and the Forest
Service, dated August 16, 2013.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. Comments from the ITCA will be
accepted at any time during the NEPA process before the Responsible
Official makes a decision on Resolution’s proposed Plan.
21 In addition, it may also be appropriate under applicable
principles of law to conduct a similar
ethnographic/ethnohistory study within the larger
Superior area, including the current project site, in
coordination with the Yavapai and perhaps other tribes,
as the Forest Service has previously been made aware
(on multiple occasions) of the importance ofthis region
to the traditional, religious and cultural interests ofthese
other ITCA Member Tribes. This is required by, among
other things, Section 106 of the NHP A and Executive
Order 13007.
It is anticipated that the “Ethnographic/Ethnohistoric Study of the
Superior Area, Arizona” (Study) will be completed prior to a final
decision being reached on the Baseline Plan. It is the Forest’s intent to
take into consideration the findings of the Study, in conjunction with
Tribal comments which come out of government to government
consultation in the final decision on the Baseline Plan.
22 Traditional Cultural Properties or TCPs, are eligible for
inclusion in the National Register under the NHP A and
are subject to the same protections and “hard look”
requirements as any other property that meets the
criteria for evaluation of historic properties found in 36
C.F.R. § 60.4.
The Forest Service is fully complying with the NHPA and NEPA
regulations in its preparation of this EA. Please refer to Section 1.6 of
the preliminary EA for a summary of the ongoing consultation efforts
and also Section 3.9 for a discussion of Cultural Resources existing
conditions and potential environmental consequences from the Baseline
Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-132
Comment
Number Comment Response
23 Under Section 106 of the NHPA the Forest Service must
(a) make a reasonable and good faith effort to identify
historic properties; determine whether identified
properties are eligible for listing on the National
Register; (b) assess the effects of the undertaking on any
eligible historic properties found; (c) determine whether
the effect will be adverse; and avoid or mitigate any
adverse effects.
The Forest Service is fully complying with the NHPA and NEPA
regulations in its preparation of this EA. Please refer to Section 1.6 of
the preliminary EA for a summary of the ongoing consultation efforts
and also Section 3.9 for a discussion of Cultural Resources existing
conditions and potential environmental consequences from the Baseline
Plan.
24 ACHP regulations reguire the agency. at all stages of the
Section 106 process. to consult in good faith with tribes
that “attach[] religious and cultural signitibance to
historic properties that may be affected by an
undertaking.”
The Tonto National Forest’s ongoing consultation process with Native
American Tribes is consistent with ACHP regulations, and Section 3.9
of the preliminary EA considers potential effects on cultural resources.
25 It is important to understand that Section 800.3(b) of
ACHP’s regulations specifically encourages
coordination of Section 106 responsibilities ‘‘with any
reviews required under other authorities such as the
National Environmental Policy Act, the Native
American Graves Protection and Repatriation Act, the
American Indian Religious Freedom Act, the
Archeological Resources Protection Act, and agency-
specific legislation.” However, compliance with one or
more of these other statutes does not substitute for
compliance with ACHP’s regulations, 36 C.F.R. Part
800. Thus, while~HP regulations allow Federal agencies
to comply with Section 106 through the use of the
NEPA process and documentation, compliance is only
lawful when the steps and standards of Section 800.8(c)
of ACHP’s regulations are met, including the
identification of eligible sites through appropriate
ethnographic and ethno-historical studies. All of these
steps must be met and the results considered as part of
the Forest Service’s consideration of the PoO. the
Baseline Activities and the Main Mine.
The Forest Service is fully complying with the NHPA and NEPA
regulations in its preparation of this EA. Please refer to Section 1.6 of
the preliminary EA for a summary of the ongoing consultation efforts
and also Section 3.9 for a discussion of Cultural Resources existing
conditions and potential environmental consequences from the Baseline
Plan.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-133
Comment
Number Comment Response
26 Accordingly, the Forest Service must comply with
NEPA, E.O. 13007, and Section 106 of the NHPA in
both identifying and evaluating the impacts of
Resolution’s proposed Baseline Activities, the PoO and
the Main Mine (separately and collectively) on those
sacred sites and TCPs in the affected area. To do this,
the Forest Service should extend the scoping period to
provide sufficient time for the Apache Tribes and Forest
Service to complete the ongoing and needed
ethnographic/ethnohistory studies that are presently
being undertaken and needed relative to the Superior
Area (including within the current location of the
Baseline Activities and PoO).
Preliminary EA Section 1.3 and each of the resources analyzed in detail
in Chapter 3 provide information on the laws, regulations, policies, and
guidance that are relevant to the proposed Baseline Activities. This
includes NRHP Section 106 compliance and consideration of
traditional cultural practices based on information proved by Native
American Tribes. It is anticipated that the “Ethnographic/Ethnohistoric
Study of the Superior Area, Arizona” (Study) will be completed prior
to a final decision being reached on the Baseline Plan. The Forest
Service will consider the findings of the Study, in conjunction with
Tribal comments which come out of government to government
consultation in the final decision on the Baseline Plan.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. Comments from the ITCA will be
accepted at any time during the NEPA process before the Responsible
Official makes a decision on Resolution’s proposed Plan.
27 NEPA mandates that public scoping include sufficient
information for the public at large to participate in the
decision making process under NEPA. The USFS has
thus far failed to fulfill these requirements.
The May 13, 2014 scoping letter was based on information made
available to the Tonto National Forest regarding Resolution’s proposed
Baseline activities. Since that time, the Proposed Action has been
revised based on consideration of internal and external scoping
comments (Section 2.3).
Letter 177 - Rambler, Terry
No Comments
Letter 178 - McDonald, Tom
No Comments
Letter 179 - Miller, Russ
1 Any action has to have an overall Watershed Analysis to
protect the public. Historically most of copper mining
operations in Arizona have created water quality issues.
And it is tragic that so many of our mines have become
Superfund Cleanup Sites. It is critical that all future
projects address and prevent these problems. ... What
will be the environmental effects of trenching? ...this
Test trenches require a 60’x30’ area where vegetation and soils will be
disturbed to allow safe access of personnel to inspect and perform soil
infiltration tests. Effects to Water and Soil Resources are evaluated in
Sections 3.3 and 3.4 of the preliminary EA. The purpose and need for
Baseline activities is to gather additional baseline hydrological and
geotechnical data (Section 1.4) to determine the area’s suitability as a
tailings storage location. Section 1.5.1 describes the consideration of
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-134
Comment
Number Comment Response
action need to be addressed along with the soil and
watershed issues.
connected actions. Potential effects of mining the deep underground
copper ore body will be described based on Resolution’s general mine
plan, and they would be addresses in a separate and appropriate NEPA
document.
2 This project as proposed will add to the loss of Sonoran
Desert bajada habitats. The bajada’ s are not a wise
choice for tailings. You can reclaim tailing sites but they
cannot be restored. What are the options? ... The
Sonoran Desert is home to 60 species of mammals,
more than 350 kinds of birds, at least 100 reptiles and 20
amphibians. How will this project affect them? This
issue needs to be addressed in detail.
Effects to Wildlife and Special Status Species are evaluated in
Section 3.7 of the preliminary EA. The purpose and need for Baseline
activities is to gather additional baseline hydrological and geotechnical
data (Section 1.4) to determine the area’s suitability as a tailings
storage location. Section 1.5.1 describes the consideration of connected
actions. Potential effects of mining the deep underground copper ore
body will be described based on Resolution’s general mine plan, and
they would be addresses in a separate and appropriate NEPA
document.
3 Recreation is a major use of the proposed area. Large
numbers of people from the surrounding Phoenix area
use it for a variety outdoor recreation including
camping, off road vehicles, hunting, sight- seeing, etc. A
baseline of recreational use needs to be developed.
Section 3.11 of the preliminary EA evaluates potential effects on
recreation.
4 Well over 2000 native species of plants occur within the
Sonoran Desert. How many of these species are present
in the project area and how will they be affected? This is
issue that needs to be qualified and quantified. The
world famous Boyce Thompson Arboretum is adjacent
to the proposed site. Is this project a compatible use with
such important asset?
Baseline activities would not preclude activities at the arboretum.
Effects to Vegetation Communities are evaluated in Section 3.5 and
Visual effects are evaluated in Section 3.12 of the preliminary EA.
5 Improvements to current secondary roads should be
minimized.
Resolution made modifications to their Proposed Action based on
scoping comments from the public and agencies received during the
Scoping Period (Section 2.3 preliminary EA). Resolution made
modifications that would result in fewer disturbances to “secondary”
roads. Reclamation would be implemented for previously disturbed
areas and short-term temporary access roads once Baseline activities
have concluded
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-135
Comment
Number Comment Response
6 The visuals of this action need to be addressed A visual analysis was conducted for Baseline activities and impact
results documented in a Visual Resource Technical Report were used to
develop the analysis in Section 3.12 of the preliminary EA.
7 Why is this proposal is being presented as a minor
action when it is really a major environmental action
with long term affects?
From the analysis presented in the preliminary EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice.
8 Resolution was committed to sending all residents of
Queen Valley a notice of this proposed action along
with the opportunity to comment. Since this may not
have occurred I request an extension of the comment
period if there was indeed no such mailing.
The Legal Notice announcing the opportunity to comment on
Resolution’s proposed Baseline Plan was published in the Arizona
Capitol Times, the newspaper of record, on May 23, 2014, and on May
21, 2014 in the Arizona Silver Belt. Consistent with CEQ Regulations
found at 40 CFR part 1501.7, affected and interested persons were
notified of the proposal with the mailing of a scoping letter dated May
13, 2014. In addition, the proposal was uploaded to the Forest’s
Schedule of Proposed Actions (SOPA) on May 22, 2014. Please notify
the ID Team Leader at [email protected] of any
other residents in Queen Valley or neighboring communities who wish
to be included in the project mailing list.
9 The proposed action is connected to the proposed main
mine and should be treated as one environmental
review. This action should not be separated from the
overall proposed action.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.4 and
1.5.1 describe that this project is “stand alone” and has separate utility;
the development of the deep underground copper ore body is not a
connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body, potential
effects on resources, including Native American Tribes religious and
cultural practices, would be considered in a separate NEPA document.
10 Since this proposal is in support of a speculative and an
uncertain mine should new road construction be
allowed. I would think not.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.5.1
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-136
Comment
Number Comment Response
describes and discusses potential connected actions to the Baseline
activities. Resolution would complete the appropriate environmental
document to review potential tailings storage site alternatives when
they complete the environmental document for the General Mining
Plan.
11 What will be the environmental effects of trenching? Test trenches require a 60'x30' area where vegetation and soils will be
disturbed to allow safe access of personnel to inspect and perform soil
infiltration tests. The test trenches would be reclaimed immediately
after all tests are complete.
Letter 182 - Perea, Orlando
1 Can we preserve the hunting areas that will be
destroyed- the natural habitats of deer, pig, numerous
species of birds etc. Will it all be eliminated?
Hunting would not be precluded by or during the Baseline activities.
The Proposed Action would result in 33.63 acres of disturbance and
would utilize several existing forest roads and previously disturbed
areas.
2 Being that we are in a 15 yr draught with (no near end in
sight) what affect is it going to have on this area- again
wildlife, vegetation, etc. already dealing with extreme
fire dangers.
Section 3.7 of the preliminary EA evaluates potential effects on
Wildlife and Special Status Species. Section 3.5 evaluates the potential
effects on Vegetation Communities and Fire Regimes, and Section 3.3
discussing Water Resources.
3 The petroglyphs in the area! What are their cultural
importance to Native Americans? How many more are
here? Are we willing to destroy local history? can we in
good conscious just turn a blind eye to these concerns.
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known or currently
identified cultural resource sites that would be affected by the Baseline
activities.
Letter 183 - Witzeman, Bob
1 The agency cannot assume that Rio Tinto has “rights” to
proceed with the project yet at the same time argue that
the project is not part of the proposed main mine
proposal.
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.4 and
1.5.1.4 describe that this project is “stand alone” and has separate
utility; the development of the deep underground copper ore body is
not a connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body, potential
effects on resources, including Native American Tribes religious
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-137
Comment
Number Comment Response
and cultural practices, would be considered in a separate NEPA
document.
2 If the Forest Service does not consider the project and
the proposed main mine as part of the same project, then
the proper permitting authority is not the mining law or
the Forest Service 36 part 228 regulations, but the Forest
Service’s special use permitting regulations. • Rio Tinto
is not “entitled” to have the project approved under the
1872 Mining Law.
The Tonto National Forest is required under the Organic
Administration Act of 1897, (which recognizes the rights of U.S.
citizens to access National Forest System lands for all proper and
lawful purposes, including prospecting, locating, and developing
mineral resources) to consider Resolution’s proposed Baseline Plan of
Operation. The activities proposed by Resolution in their Baseline Plan
are considered a use that is reasonably incident to mineral exploration,
they are explicitly exempted from special use authorization. 36 CFR
part 251.50(a) designates special uses as “[a]ll uses of National Forest
System lands, improvements, and resources, except those authorized by
the regulations governing…minerals (part 228).” Therefore, Forest
Service special use authorization does not apply.
Refer to Section 1.3.2 for a more detailed discussion.
3 The draft EA or EIA must fully explain all baseline
conditions prior to analyzing or approving the project. •
Without the required adequate analysis, any potential
finding of no significant impact (FONSI) would be
inadequate- necessitating preparation of an EIS.
The affected environment was evaluated for potential effects to Water
Resources, Soil Resources, Vegetation Communities and Fire Regimes,
Invasive Species, Wildlife and Special Status Species, Range, Cultural
Resources, Travel Management and Public Safety, Recreation, Visual
Resources, Air Quality, Climate Change, and Noise in Chapter 3 of the
preliminary EA. The Forest Service will determine the necessity for the
preparation of an EIS, taking effects to the aforementioned resources
into consideration.
4 The draft EA or EIA must include an adequate
mitigation plan, including a detailed review of the
impacts from, and effectiveness of, any mitigation
measures. ... The Forest Service must minimize all
adverse impacts from the project and ensure compliance
with all environmental and public land laws.
Section 2.3.6 of the preliminary EA lists the Applicant- proposed
environmental commitments and Section 2.3 describes the
modifications made to the proposed action to reduce potential impacts.
Additional mitigation measures developed to reduce adverse
environmental impacts are included in Chapter 3, and summarized in
Section 2.5.
5 The draft EA or EIA must fully review all reasonable
alternatives.
Please refer to Section 2.4 of the preliminary EA for a description of a
range of reasonable alternatives that were considered.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-138
Comment
Number Comment Response
6 The Forest Service must fully analyze the project’s
impacts to threatened and endangered species.
Section 3.7 of the preliminary EA evaluates potential effects on
Wildlife and Special Status Species.
7 The Forest Service must fully comply with the National
Historic Preservation Act (NHPA) and all other cultural
and religious freedom protection laws.
Section 1.6 and Section 3.9 of the preliminary EA both discuss Forest
Service compliance with NHPA and other cultural and religious
freedom protection laws in the preparation of this EA. Effects to
Cultural Resources from the Baseline activities are described in
Section 3.9. There are no known or currently identified cultural
resource sites that would be affected by the Baseline activities.
8 The EIS or EA must fully analyze all direst, indirect,
and cumulative impacts - including from Rio Tinto’s
main mine proposal. • The proposed main mine is a
connected action that must be reviewed in one EA/EIS
As described in Section 1.4 of the preliminary EA, the purpose of and
need for the proposed action is to collect hydrological, geochemical,
and geotechnical data to provide baseline information on an area that
may be considered for a potential tailings storage site. Section 1.4 and
1.5.1 describe that this project is “stand alone” and has separate utility;
the development of the deep underground copper ore body is not a
connected action to the Proposed Action, and therefore was not
evaluated in the preliminary EA. If Resolution were to proceed with
development of the deep underground copper ore body or other actions
not addressed in this preliminary EA, the potential effects on resources
would be considered in a separate review under NEPA and 36 CFR
part 228A
Letter 184 - Witzeman, Bob
1 In addition, any USFS plan to continue its review of the
PoO must comply with federal law as detailed herein.
Please refer to Section 1.3 of the preliminary EA for a description of
United States Mining Laws and NEPA and other Forest Service mining
and mineral policy as it relates to this Baseline activities project.
Resolution’s Mine Plan would be addressed under a separate and
appropriate NEPA document.
2 an Environmental Impact Statement (“EIS”) must be
prepared, due to the potential for significant impacts
from the Project alone, and especially when viewed with
its cumulative impacts from other and/or related
activities as well as connected actions.
Based on the analysis presented in the preliminary EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice. If Resolution were to proceed
with development of the deep underground copper ore body or other
actions not addressed in this preliminary EA, the potential effects on
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-139
Comment
Number Comment Response
resources would be considered in a separate review under NEPA and
36 CFR part 228A.
3 The US Forest Service’s (“USFS’s”) review outlined in
the scoping letter contains numerous legal and factual
errors and as such should be revised in order to comply
with federal law.
The May 13, 2014 scoping letter was based on the information
available at that time regarding Resolution’s proposed Baseline
activities. Since that time, the proposed action has been revised based
on internal and external scoping comments. Section 2.3 of the
preliminary EA describes the revisions made by Resolution to the
Proposed Action.
Letter 185 - McMullen, Patrick
No Comments
Letter 186 - Montgomery, Esq., Susan B.
1 I re-read it again after we talked and still think that you
can extend the scoping period. As you can see, the 30
day limitation is applicable ONLY once the EA process
has been undertaken, while there is 45 days for an EIS. I
agree that it says there shall be no extension (though that
is dumb) under the EA process. However, at this point
you have not prepared a draft EA or EIS (probably not
formally sure what process you will follow) and THUS,
the 30 day limitation and correlating prohibition on
extensions is not yet triggered. This is because you are
only in SCOPING and under NEPA should yet have
decided where to go from here (EA/EIS) — because this
is informed by scoping.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. The 30-day public scoping period,
which was offered for Resolution’s Baseline Plan, is consistent with the
36 CFR 218. The Tonto National Forest considers all comments
received during and outside of the comment periods and evaluates these
consistent with the Forest Service NEPA regulations.
2 Scoping should be wide open and you should take as
much time as you need to develop the issues and
understand all the concerns and aspects of the issue, in
particular BECAUSE afterscoping you are on these
crazy timelines and no extensions would seem to be
permitted under this dumb rule – at lease where we are
talking EA.
Consistent with 36 CFR part 218.6(d), time extensions are not
permitted for comment periods. The 30-day public scoping period,
which was offered for Resolution’s Baseline Plan, is consistent with the
36 CFR 218. The Tonto National Forest considers all comments
received during and outside of the comment periods and evaluates these
consistent with the Forest Service NEPA regulations.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-140
Comment
Number Comment Response
Letter 189 - Pemberton, Celeste
1 The County currently maintains a courtesy graded dirt
roadway along the Hewitt Station Road alignment which
falls within this area of drilling, trenching, etc. ... we ...
would like to see some considerations at the time of
construction in regards to Traffic Control for safety of
the traveling Public. Please ensure that whoever is
awarded the construction to provide and maintain at all
times during the existence of said hazard (excavation
areas/machinery) sufficient barriers, hanger signals,
lanterns, detours in accordance with the Manual of
Uniform Traffic Control Devices (MUTCD).
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public. Public safety and resource protection would be in accordance
with FSMs 7700 and 7730 guidelines as established in the Forest Plan.
In addition, public safety would also be managed through the use of
Applicant-proposed EPMs identified in Section 2.3.6 of the preliminary
EA.
2 we would also like to see a schedule as to when exactly
the work will take place so that we are able to notify the
traveling Public that may use this route and are also out
of your way in regards to our regular maintenance
equipment.
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public.
Letter 190 - Hickman, Vanessa
1 As an owner of adjacent property, land managed and
held in trust by the ASLD ... according to the draft Plan
of Operation submitted by RCM to the USFS in
November 2013, [using state land] is no longer a viable
option because of existing and competing plans (page
139). As this data gathering activities plan on USFS
land is currently proposed, the ASLD has no problems,
concerns or issues with the project.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-141
Comment
Number Comment Response
Letter 191 - Urman, Michael R
1 (d) that Resolution agree that any indications of
mineralization that might be encountered in conducting
the Baseline Activities on lands subject to Bronco
Creek’s claims shall inure to the benefit of Bronco
Creek. Resolution shaH not be entitled to any claim of
discovery based on any information or data arising from
activities on the Bronco Creek claims.
The Tonto National Forest has provided Resolution with a copy of all
comments received during scoping. Consistent with Forest Service
Manual 2800, Chapter 2810, Section 2813.11, the locator of a mining
claim acquires rights against other possible (peaceable) locators when
the locator has complied with the applicable Federal and State laws.
Where more than one locator is involved on the same land, Forest
Service actions should be impartial to all known locators of that land,
as the controversy is the responsibility of the locators, not the Forest
Service, to settle.
2 the Forest Service’s approval of Resolution’s proposed
Baseline Activities should be made subject to the
following conditions: (a) that all hydrological and
geotechnical data generated from the proposed Baseline
Activities be contemporaneously shared with Bronco
Creek;
The Tonto National Forest has provided Resolution with a copy of all
comments received during scoping. Consistent with Forest Service
Manual 2800, Chapter 2810, Section 2813.11, the locator of a mining
claim acquires rights against other possible (peaceable) locators when
the locator has complied with the applicable Federal and State laws.
Where more than one locator is involved on the same land, Forest
Service actions should be impartial to all known locators of that land,
as the controversy is the responsibility of the locators, not the Forest
Service, to settle.
3 (b) that any approval of Resolution’s proposed Baseline
Activities not prevent the approval of exploration
activities by Bronco Creek to occur simultaneously with
Resolution’s Baseline Activities;
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public.
4 (c) that any approval of Resolution’s proposed Baseline
Activities not unreasonably prevent or limit Bronco
Creek’s ability to drill exploration holes on the Bronco
Creek claims;
No road closures are expected to take place and road improvements
would be conducted in a manner that would allow continued use by the
public.
Letter 192 - Urman, Michael R
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-142
Comment
Number Comment Response
Letter 193 - Wright, David Thomas
1 What about the effects of wind potentially carrying
tailings westward towards Queen Valley? Seems like
this is not an environmental consideration per the above
statement of purpose. Will this specific environmental
concern be addressed in future assessments or has it
already been addressed in previous assessments in
which case is there a document I can reference?
Otherwise, I would argue that we are missing a key
component of the overall environmental assessment
here.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Effects on the area from the Baseline
activities in regards to air quality are discussed in the preliminary EA in
Section 3.13.
2 what document defines the appropriate depth to
groundwater level that would be acceptable?
Additionally, are there mining standards in general that
serve to define compliance for (l), (2), (3), and (4) -
above - [(1) depth to groundwater level; (2) lithology
and geochemistry of drill cuttings; (3) aquifer hydraulic
parameters, including transmissivity, hydraulic
conductivity, and storage coefficients; and (4) chemical
quality of groundwater] and if not, what entity is
defining compliance in this case?
As a part of Resolution’s Plan, 16 groundwater testing and monitoring
wells are proposed. These wells would be used to collect data on depth
to groundwater; lithology and geochemistry of drill cuttings; aquifer
hydraulic parameters, including transmissivity, hydraulic conductivity,
and storage coefficients; and chemical quality of groundwater.
Additionally, Resolution has proposed to install piezometers in the
geotechnical drill holes to define baseline soil and bedrock
hydrological and geotechnical conditions (depth to groundwater). The
Baseline Plan proposes hydrologic data collection methods in order to
further the present understanding of hydraulic conditions over an area
being considered for a potential tailings site. In doing these activities,
Resolution would be required to comply with, at a minimum, Forest
Service mining regulations found at 36 CFR part 228, subpart A.
3 Appendix K dealt with evaluating the cause of water
level declines - and reading through Appendix K, I don’t
see how it is relevant to the data gathering activities per
Baseline Hydrological and Geotechnical Data Gathering
Activities Plan_50S. They sound like completely
different assessments to me.
The report in Appendix K, “Results of Queen Creek Corridor Survey,
Superior Basin, Pinal County, Arizona,” February 19, 2013, prepared
by Montgomery & Associates, provides background information for
the discussion presented in Chapter 3 of the preliminary EA.
Letter 194 - Lewis, Barnaby V.
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-143
Comment
Number Comment Response
Letter 195 - Kuwanwisiwma, Leigh
1 we consider the archaeological sites of our ancestors to
be “footprints” and Traditional Cultural Properties.
Therefore we appreciate the Forest’s continuing
solicitation of our input and your efforts to address our
concerns. ... we request continuing consultation on this
proposal and accept your invitation for a government
top government in person consultation.
The Tonto National Forest consultation with Native American Tribes
including the Hopi Tribe will be ongoing throughout the proposed
Baseline activities NEPA process.
2 We do not believe adverse effects to numerous
prehistoric sites are justified by Resolution Copper
Mining’s proposed tailings storage site pursuant to the
1872 General Mining Law. ...
Effects to Cultural Resources from the Baseline activities are described
in Section 3.9 of the preliminary EA. There are no known or currently
identified cultural resource sites that would be affected by the Baseline
activities. The purpose and need for Baseline activities is to gather
additional baseline hydrological and geotechnical data (Section 1.4) to
determine the area’s suitability as a tailings storage location.
Section 1.5.1 describes the consideration of connected actions.
Potential effects of mining the deep underground copper ore body will
be described based on Resolution’s general mine plan, and they would
be addresses in a separate and appropriate NEPA document.
3 We concur that the proposed activities associated with
this project and its reasonably foreseeable purpose, a
tailings storage site, has the potential to disturb and
adversely affect numerous surface and subsurface
cultural properties significant to the Hopi Tribe. Sites
adversely affected by this proposal will be permanently
adversely affected. Therefore, we support the
development of an environmental impact statement for
this proposal and its reasonably foreseeable purpose.
The purpose of Resolution’s proposed Plan is to collect data which will
provide baseline information on an area that may be considered for a
future tailings site by Resolution. This information would be used to
inform later separate actions and proposals related to Resolution’s
proposed General Plan of Operations. Resolution’s Baseline Plan has
independent utility from their General Plan of Operations, and that
separate action would be subject to a separate review under NEPA and
36 CFR part 228A.
Based on the analysis presented in the preliminary EA the Forest
Supervisor will determine if an Environmental Impact Statement (EIS)
would be necessary. If an EIS is not necessary, the Forest Supervisor
will document that determination in a Finding of No Significant Impact
(FONSI) and issue a Decision Notice.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-144
Comment
Number Comment Response
Letter 196 - Kelley, Lawrence
No Comments
Letter 198 - Hester, Vicki
1 My concern is the inevitable water and ground pollution
that would occur at this site and the impact it would
have not only on wildlife and cattle, but potentially the
groundwater that many of us rely on daily.
Effects to Water Resources from Baseline activities, including water
quality, are discussed in Section 3.3 in the preliminary EA. Impacts to
vegetation, wildlife and range are discussed in Sections 3.5, 3.7 and
3.8, respectively.
Letter 199 - Steinmetz, Frank
1 The state is running out of water + we don’t need to
waste it on a leaching process. The water runs under
ground into the valley of Arizona
Effects from the Baseline activities to Water Resources are discussed in
Section 3.3 in the preliminary EA. The purpose and need for Baseline
activities is to gather additional baseline hydrological and geotechnical
data (Section 1.4) to determine the area’s suitability as a tailings
storage location. Section 1.5.1 describes the consideration of connected
actions. Potential effects of mining the deep underground copper ore
body will be described based on Resolution’s general mine plan, and
they would be addresses in a separate and appropriate NEPA
document.
Letter 200 - Sohocki, Dennis and Dena
1 The United States Forest Service (USFS) must include
the analysis of this proposed drilling and exploration as
an integrated part of the impacts associated with the full
mining plans. Otherwise, the Forest Service will be in
violation of both NEPA and the CEQ regulations, which
do not allow segmentation of impact analysis on
projects. ... If the USFS were to proceed hand in hand
with Rio Tinto to try to avoid the full, required NEPA
analysis, it will be responsible for taking an active part
in the destruction of our public lands rather than merely
neglecting its duties.
Resolution’s Baseline Plan, as described in Chapter 1 of the
preliminary EA is subject to the regulations found at 36 CFR part
228A. These regulations apply to all functions, work, and activities in
connection with prospecting, exploration, development, mining, or
processing of mineral resources and all uses reasonably incident
thereto, including data collection conducted to determine the feasibility
of a location for a potential tailings facility on National Forest System
lands. Determine the feasibility of a potential tailings facility is
considered a use that is reasonably incident to mineral exploration and
development of a potential mine. Additionally, the proposed Baseline
Plan represents part of a logical sequence of activities, and has been
found to be reasonable for the stage proposed by Resolution (Forest
Service Handbook 2809.15, Minerals and Geology, Chapter 10).
Resolution’s Baseline Plan would provide baseline information on
hydrologic, geochemical, and geotechnical data from mineral
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-145
Comment
Number Comment Response
exploration on National Forest System lands. This information would
be used to inform later, separate actions and proposals related to
Resolution’s proposed General Plan of Operations. As described in the
preliminary EA, the Baseline Plan has independent utility from the
General Plan of Operations and that separate action would be subject to
a separate review under NEPA and 36 CFR part 228A. Resolution is
entitled to conduct operations that are reasonably incidental to
exploration and development of mineral deposits on its unpatented
mining claims pursuant to U.S. Mining Laws. Under regulations of the
U.S. Secretary of Agriculture, Resolution must conduct mineral
exploration consistent with 36 CFR part 228A, and in accordance with
a plan of operations that has been approved by the Forest Service.
2 if the mine is allowed to proceed, not only would the
environmental impacts be both serious and broad‐based,
but the long‐term economic impacts would also be very
negative. Arizona’s economic future lies with
sustainable tourism and appreciation of, rather than
destruction, of our national treasures, such as the Boyce
Thompson Arboretum and the Superstition Wilderness
area.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
3 Currently, the USFS seems to have a management
approach to much of the Tonto National Forest based
upon neglect.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
Letter 201 - Conner, Charles
No Comments
Letter 202 - Flowers, Christopher
No Comments
Letter 203 - Marks, Darrell
No Comments
Letter 204 - Dyer, Dawn
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-146
Comment
Number Comment Response
Letter 205 - Steuter, Don
No Comments
Letter 206 - Begalke, Donald
No Comments
Letter 207 - Sloan, Dylan
No Comments
Letter 208 - Beltrane, Edward
No Comments
Letter 209 - Champagne, Gene
No Comments
Letter 210 - Hill, Ginger
No Comments
Letter 211 - Kay, Greg
No Comments
Letter 212 - S, J
No Comments
Letter 213 - Gordon, Janine
No Comments
Letter 214 - Kozma, John
No Comments
Letter 215 - Fitzner, Lisa E.
No Comments
Letter 216 - Pina, Loren
No Comments
Letter 217 - Bethka, Lorraine
No Comments
Letter 218 - Shores, Michael
No Comments
Letter 219 - Glover, Nanette
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-147
Comment
Number Comment Response
Letter 220 - Fugate, Peggy
No Comments
Letter 221 - Scanlon, Peter
No Comments
Letter 222 - Lambertus, Sharon
No Comments
Letter 223 - Magill, Sue
No Comments
Letter 224 - Nosie, Vanessa
No Comments
Letter 225 - Russell, Wendy
No Comments
Letter 226 - Dearstyne, William
No Comments
Letter 227 - Leslie, Darlene
1 As a tribal member of the San Carlos Apache Tribe,
there has been no consultation to our community. This
passing of legislation will violate and disregard our right
of citizens of this country. ... I strongly oppose because
of the lack of communication and the disregard of
showing respect to our tribe. Enough is enough.
The Tonto National Forest initiated government to government
consultation with 10 Native American Tribes in May of 2014 relative
to Resolution’s proposed Baseline Plan. Consultation is ongoing and
comments from the San Carlos Apache Tribe will be considered at any
time prior to the Responsible Official making a decision on the
proposal.
2 As a tribal member of the San Carlos Apache Tribe, ... I
say no to this legislation because this site is scared. The
focused land binds families together and should be there
for future generations.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-148
Comment
Number Comment Response
Letter 228 - Lintecum, Kelly
1 I am against this project as it is harmful to the
environment. Boyce Thompson arboretum is one area
that would be affected. ...Please help keep the arboretum
safe so that our family can continue to gather there each
year and remember our lost love one. Polluting the
environment upstream would have negative impacts on
the health and well being of the native plants and
animals.
Effects to Boyce Thompson Arboretum are evaluated in the
preliminary EA in Section 3.12 Visual Resources. Sections 3.5 and 3.7
evaluate effects to Vegetation and Wildlife for the Proposed Action.
Letter 229 - Wilson, Melissa
1 in simple words, clean up this mess. This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4).
Letter 230 - Richards, Pat
1 As a homeowner + resident of Superior I am very
concerned this project will have on my quality of life ...
Lets preserve this beautiful area we live in for our
children and grandchildren....These are just a few of the
many social + environmental impacts of this project in
conjunction with the main mine.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Chapter 3 of the preliminary EA
describes the potential environmental impacts from this proposed
project on resources and considers visual, noise, recreation and adjacent
landowners.
2 As a homeowner + resident of Superior I am very
concerned this project will have on ... our water quality
+ quality air pollution, to have our soil [?] from surface
contaminants present + long term. ...These are just a few
of the many social + environmental impacts of this
project in conjunction with the main mine.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5). The purpose of this project is to collect baseline
hydrological, geochemical, and geotechnical data on these aspects of
the environment on an area that may be considered for a potential
tailings storage site (Section 1.4). Chapter 3 of the preliminary EA
describes the potential environmental impacts from this proposed
project on resources and considers visual, noise, recreation and adjacent
landowners.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 2-149
Comment
Number Comment Response
3 The 1872 mining law does not make this project a shoe-
in.
The Forest Service appreciates your time and effort to participate in this
NEPA process and hopes that you will continue to provide additional
input to further our efforts in managing public resources. Personal
preferences and opinions expressed by the public are one of many
viewpoints considered by the Forest Service when making decisions,
however individuals submitting comments must meet the requirements
specified in 36 CFR Part 218, Subparts A and B, in order to be
considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 3-1
Table 3: Responses to Public Scoping Comments Submitted After the Public Scoping Period Ended
Comment
Number Comment Response
Letter 84 – O’Connor, Cornelia
No Comments
Letter 166 - Barchas, Sarah
No Comments
Letter 173 - Valencia, Ruth
No Comments
Letter 174 - Pastor, Mike
1 Resolution is entitled to conduct operations that are
reasonably incidental to exploration and development of
mineral deposits on its unpatented mining claims
pursuant to U.S. Mining Laws. In addition, we believe
that this proposed Plan of Activities is consistent with
the Tonto National Forest Land and Resource
Management Plan (LRMP) of 1985 as amended, and
that the mineral exploration, development and
operational activities as outlined in this proposed plan
will be conducted in a manner that minimizes adverse
environmental impact on the Tonto Nation Forest
surface resources as codified in 36 CFR Part 28.
Section 1.3 of the preliminary EA discusses the Tonto National Forest
decisions in relation to the U.S. 1872 Mining Law. In addition, in
Chapter 3 of the preliminary EA each resource section describes the
relevant sections of the Tonto National Forest Land and Resource
Management Plan that may pertain to that resource.
2 The economic benefit to the local area as well as to
Arizona will continue for at least another 50 years with
an estimated economic benefit of more than $61 Qillion
over the expected 60 year lifespan of the operation,
including an estimated $20 billion in federal, state and
local tax revenue and more than $14 billion in wages.
The Forest Service appreciates your time and effort to participate in
this NEPA process and hopes that you will continue to provide
additional input to further our efforts in managing public resources.
Personal preferences and opinions expressed by the public are one of
many viewpoints considered by the Forest Service when making
decisions, however individuals submitting comments must meet the
requirements specified in 36 CFR Part 218, Subparts A and B, in order
to be considered eligible to file an objection.
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 3-2
Comment
Number Comment Response
3 we recognize and understand the importance of
protecting our natural resources while providing
opportunities and access to those whose livelihoods
depend on resources located on federal land as well as
access for multiple use, multi-cultural activities, and
multi-recreational opportunities to the public.
Historically, our economy and our residents have
depended heavily upon resource-based industries and,
more recently, upon recreation opportunities on federal
land. We appreciate that we must take care of the land,
but we need to be able to use the land to take care of
ourselves.
The Forest Service appreciates your time and effort to participate in
this NEPA process and hopes that you will continue to provide
additional input to further our efforts in managing public resources.
Personal preferences and opinions expressed by the public are one of
many viewpoints considered by the Forest Service when making
decisions, however individuals submitting comments must meet the
requirements specified in 36 CFR Part 218, Subparts A and B, in order
to be considered eligible to file an objection.
4 the proposed new construction would create disturbance
on a total of 31.74 acres of previously undisturbed
Tonto Forest Land, while the majority of the proposal
would impact another 61.24 acres of previously
disturbed land or existing roadways. Given that the
Tonto Forest is comprised of nearly three million acres,
this represents an ·incredibly small amount of impacted
land, for the return benefit of gathering the baseline data
necessary to advance this project to the neXt stage.
Based on comments received during Scoping and from the Forest
Service, Resolution modified their Proposed Action (preliminary EA
Section 2.3). Total disturbance for the Proposed Action is 33.63 acres
which includes previously disturbed areas. The total project area is
75.40 acres and includes existing forest roads.
Letter 180 - Featherstone, Roger
No Comments
Letter 181 - Featherstone, Roger
No Comments
Letter 187 - Balderas, Ruben
No Comments
Letter 188 - Jacobs, Sky
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 3-3
Comment
Number Comment Response
Letter 231 - Gavelek, Joe
1 Hydrologic Drill Sites: 16 sites. Range in depth; 328' >
2297' What is the need for so many well’s, and why
such a variance in depth? Geotechnical Drill Sites:
41 sites. What is the purpose of these sites? Is there
going to any type of construction in this area? I am
under the impression this area is going to be used for a
Tailing area. Test Trench Sites: 33 sites. Why is there
such a widespread need for all these trenches?
As described in Section 1.4 of the preliminary EA, the purpose of the
Baseline activities is to collect hydrological, geochemical, and
geotechnical data to provide baseline information on an area that may
be considered for a potential tailings storage site. See Section 2.3 for a
description of the Proposed Action, to include access, hydrological
drill sites, geotechnical drill sites, and test trenches.
2 Forest Roads: TBD by Travel Management Decision
10 years from approval of the proposed of the proposed
plan. Will FR650, FR252, FR2359, FR518 be closed
for 10 years or any parts of them?
FR 650, FR 252, and FR 518 are existing forest road that will remain
open during construction and operation of Baseline activities. No road
closures are expected to take place and road improvements would be
conducted in a manner that would allow continued use by the public.
Based on comments received during Scoping, Resolution agreed not to
use FR 2395 to access the Baseline activities. As a result, access to the
previously disturbed areas that connect to FR 2395 and FR 2397 in
Section 6 would no longer be necessary (see Section 2.3 of the
preliminary EA).
3 Land Exchange/Where: Is there going to be a land
exchange? If, so what area will be allocated to the F.S.
This comment is outside the scope of analysis of the preliminary EA
(Section 1.5).
Letter 232 - Sohocki, Dennis and Dena
No Comments
Letter 233 - Thiel, Dianne
No Comments
Letter 234 - Ogo, Linda
No Comments
Resolution Baseline Hydrological and Geotechnical Data Gathering Activities Preliminary EA Scoping Comment and Response Report
Table 3-4
Comment
Number Comment Response
Letter 235 – various, Queen Valley Petition
We oppose the current design of Resolution Copper’s
proposed mine and tailings location because it will
negatively impact our air, water, economic well-being,
and recreational opportunities. We request that you find
a more suitable location for the toxic tailings and that
we be notified of every opportunity to express our
concerns.
The Forest Service appreciates your time and effort to participate in
this NEPA process and hopes that you will continue to provide
additional input to further our efforts in managing public resources.
Personal preferences and opinions expressed by the public are one of
many viewpoints considered by the Forest Service when making
decisions, however individuals submitting comments must meet the
requirements specified in 36 CFR Part 218, Subparts A and B, in order
to be considered eligible to file an objection.