Preliminary Design of Tully Heads Seawall - Option ......2015/07/09 · Table 3-6 Peak inundation...
Transcript of Preliminary Design of Tully Heads Seawall - Option ......2015/07/09 · Table 3-6 Peak inundation...
Tully Heads and Hull Heads Seawall Renewal Project
Preliminary Design of Tully Heads Seawall - Option Assessment Report
Cassowary Coast Regional Council
4 June 2015
Revision: 1
Reference: 243333
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1
Tully Heads and Hull Heads Seawall Renewal Project
Date 4 June 2015
Reference 243333
Revision 1
Aurecon Australasia Pty Ltd
ABN 54 005 139 873
Level 1, 242 Mulgrave Road Cairns QLD 4870
PO Box 7625 Cairns QLD 4870 Australia
T
F
E
W
+61 7 4019 6400
+61 7 4051 2540
aurecongroup.com
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page I Page I
Tully Heads Seawall Background
Tully Heads Seawall includes 2 seawalls on the southern part of Googarra Beach. The southern
seawall is named Seawall 1 and the northern seawall named Seawall 2 as shown on the locality plan
below.
A detailed condition assessment was undertaken for both walls, as presented in Aurecon’s report
“Condition Assessment Report – Tully Heads Seawall”, recommending a series of short term and long
term considerations for management of the assets.
This report is aimed at presenting long term remediation options to address the issues identified in the
aforementioned Condition Assessment report.
Seawall 1
Various options exist to protect coastal foreshores. The selection of the most appropriate option
depends on the site and environmental conditions. Five options are proposed for the protection of
Tully Heads Foreshore. Indicative costs (exclusive of GST) associated with the construction of those
options are also estimated.
Option 1 – Rock armoured revetment
Variant A – Toe buried underneath beach surface - approx. $4,200,000
Variant B – Toe on existing beach surface - approx. $2,550,000
Variant C – New rock revetment - approx. $6,620,000
Option 2 – Geocontainer revetment - approx. $10,300,000
Option 3 – Reinforced concrete seawall - approx. $26,100,000
A Multi Criteria Analysis has been undertaken to compare the mentioned options above. These
options are evaluated against criteria such as impact, effectiveness, social value, government process
and economics. Following this analysis, the rock revetment repair with buried toe is found to be the
Executive summary
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page II Page II
best suited for Seawall 1 at Tully Heads, provided that sufficient armour stone can be procured
economically. These proposed works are however subject to relevant stakeholder feedback.
Ultimate replacement/upgrade of the seawall will trigger the requirement to obtain new development
approvals to support lawful construction of the works. Notwithstanding this, any interim management
works, or works carried out prior to the ultimate replacement should be cognisant of these existing
approvals.
Seawall 2
Seawall 2 is believed to be mostly buried under the existing beach. The rocks that can be seen are
assumed to be the crest rocks. It is assumed that the rest of the seawall structure is complete under
the existing beach. Reconstructing Seawall 2 will imply large excavation and is not considered as
critical works at this time. Regular monitoring inspections are recommended to remediate any scouring
issue or crest damage, especially after storm event.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page III Page III
Contents Executive summary I
1 Introduction 1
1.1 Purpose 1
1.2 Methodology 1
1.3 Assumptions and limitations 1
2 Review of existing data 2
2.1 Locality and subject site 2
2.2 Land tenure 3
2.3 Project background 4
2.4 Previous studies 4
2.5 Desktop design review 5
2.6 Site conditions 6
3 Design basis 8
3.1 Design considerations 8
3.2 Design risk 10
3.3 Design parameters 11
4 Concept design option assessment 15
4.1 Proposed concept design layout 15
4.2 Seawall 1 upgrade/reconstruction options 15
4.3 Cost estimate of options 22
5 Multi-criteria analysis 26
5.1 Analysis criteria 26
5.2 Option analysis 28
6 Conclusion 30
7 References 31
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page IV Page IV
Appendices
Appendix A
Document register
Appendix B
Option Assessment Drawings
Appendix C
Approved Plans of Development – existing Seawall 1 and Seawall 2
Figures
Figure 2-1 Locality plan of the existing seawalls at Tully Heads 2 Figure 2-2 Project site land tenure 3 Figure 2-3 Bathymetry in the vicinity of Tully Heads (AUS 829 chart) 7 Figure 4-1 Example of geocontainer seawall 20 Figure 4-2 Example of concrete stepped seawall 21
Tables
Table 2-1 Summary of land tenure within the Project footprint 3 Table 2-2 Tully Heads Seawall chronology 4 Table 2-3 Tidal planes at Clump Point published by Maritime Safety Queensland (MSQ), 2014 6 Table 3-1 Key standards used in seawall design 9 Table 3-2 Risk of encountering various ARI events in 20 and 50 year period 10 Table 3-3 Wind speed conversion from m/s to km/h and knots 11 Table 3-4 Extreme wind recurrences at Tully Heads (10 m above sea level) 11 Table 3-5 Storm tide levels at Tully Heads (including wave set-up) from JCU 12 Table 3-6 Peak inundation levels at Tully / Hull Heads from the Cardwell Inundation Study project 12 Table 3-7 Design water levels 13 Table 3-8 Earthquake parameters for Tully Heads 14 Table 4-1 Indicative material quantity associated with Option1 - Variant A 17 Table 4-2 Indicative material quantity associated with Option 1 - Variant B 18 Table 4-3 Indicative material quantity associated with Option 1 - Variant C 19 Table 4-4 Indicative material quantity associated with Option 2 20 Table 4-5 Material quantity associated with Option 3 22 Table 4-6 Assumed material rates 23 Table 4-7 Proposed contingencies 23 Table 4-8 Indicative cost estimate for Option 1 – Variant A 24 Table 4-9 Indicative cost estimate for Option 1 – Variant B 24 Table 4-10 Indicative cost estimate for Option 1 – Variant C 24 Table 4-11 Indicative cost estimate for Option 2 25 Table 4-12 Indicative cost estimate for Option 3 25 Table 5-1 Multi-criteria analysis 29
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page V Page V
Acronyms and abbreviations
Abbreviation Explanation
ACH Act Aboriginal Cultural Heritage Act 2003
AHD Australian Height Datum
BCA Building Code of Australia
CCRC Cassowary Coast Regional Council
CHMP Cultural Heritage Management Plan
CMD Coastal Management District
D50 Median grain diameter
DAFF Department of Agriculture, Fisheries and Forestry
DEHP Department of Environment and Heritage Protection
DNRM Department of Natural Resources and Mines
DoE Department of the Environment
EIS Environmental Impact Statement
EPBC Act Environment Protection and Biodiversity Conservation Act 1999
FHA Fish Habitat Area
GPS Global Positioning System
GBRMPA Great Barrier Reef Marine Park Authority
GBRMP Act Great Barrier Reef Marine Park Act 1975
HAT Highest Astronomical Tide
IDAS Integrated Development Assessment System
LAT Lowest Astronomical Tide
MCA Multi-Criteria Analysis
MGA Map Grid of Australia
MHWS Mean High Water Springs
MHWN Mean High Water Neaps
MLWN Mean Low Water Neaps
MLWS Mean Low Water Springs
MSL Mean Sea Level
NDDRA Natural Disaster Relief and Recovery Arrangements
NES National Environmental Significance
SEMP Shoreline Erosion Management Plan
SPA Sustainable Planning Act 2009
SP Reg Sustainable Planning Regulation
TC Tropical Cyclone
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page VI Page VI
Glossary
Term Definition
Wave overtopping Wave overtopping of seawalls is caused by the direct (and often violent) impact of waves on a structure, which can result in structural damage. More importantly, the water discharged above the structure crest constitutes a hazard to not only the crest itself, but also to people and infrastructure located directly behind the seawall.
Overtopping can also cause saturation of the soil profile, increasing pore water pressure and the chance of failure from sliding, overturning or removal of retained soil.
Sea level rise Sea level rise is defined by an increase of the mean water level due to an increase of greenhouse gases in the atmosphere.
Storm surge A storm surge is a rise in water level due to an offshore low pressure system such as a cyclone.
Wave set-up
After incoming waves break, the average level of the water inside the surf zone to the beach is set up higher than the sea level offshore from the breaker zone
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 1
1.1 Purpose Aurecon has been commissioned by Cassowary Coast Regional Council (CCRC) to complete Stage 1
of a preliminary design required for the replacement, extension and modification of the existing
seawalls at Tully Heads and Hull Heads. Stage 1 includes the development of risk management
solutions to manage both Tully Heads and Hull Heads seawalls in their existing conditions. Moreover
Stage 1 incorporates the review of permits and approvals for both seawalls and the preparation of a
preliminary design for the Tully Heads Seawall.
Tully Heads Seawall is an erosion protection structure but is not a flood control structure. Aurecon has
issued a condition assessment report for both Hull Heads and Tully Heads Seawall including risk
management solutions and review of existing permits and approvals.
This option assessment report is part of the preliminary design phase relating to the Tully Heads
seawall. An Environmental Design Report (EDR) has been prepared concurrently for this site.
1.2 Methodology In preparing this option assessment report for the Tully Heads seawall, it was necessary to:
Complete a desktop review of all existing information pertaining to the Tully Heads seawalls, including previous designs, regulatory approvals, studies and investigations
Establish design criteria associated with the seawall design
Undertake an option assessment of five coastal revetment options
Carry out a multi-criteria analysis to identify a preferred option
Once relevant stakeholders have reviewed and indicated any comments on this report, a
recommended option may be selected and detailed in the recommendation report.
1.3 Assumptions and limitations The following assumptions and limitations apply to this study:
The review and assessment undertaken, with respect to past works, design and investigations completed to date in relation to the Tully Heads seawalls has been limited to those documents listed in Appendix A which were provided to Aurecon by CCRC as part of this study.
In undertaking this assessment, Aurecon has made assumptions that the team could reasonably be expected to make in accordance with sound professional practice.
1 Introduction
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 2
2.1 Locality and subject site The project site is situated approximately 120 km south of Cairns and 160 km north of Townsville on
the Queensland eastern coast.
Located within the Cassowary Coast Regional Council Local Government area (LGA) (former Cardwell
Shire), Tully Heads seawalls are accessed via Carron Esplanade and Taylor Street. Tully Heads
seawalls are bounded by the coastline to the east and the mouth of the Tully River to the south. The
beach along Tully Heads township is named Googarra Beach. Within the immediate area to the west
are residential properties which form the township of Tully Heads.
The seawalls of interest are located from the southern end of Taylor Street to the junction of Taylor
Street and Carron Esplanade, as shown on Figure 2-1. For the purposes of this report, the larger
seawall located to the south-east of Taylor Street has been referred to as ‘Seawall 1’ and the smaller
seawall located to the north as ‘Seawall 2’.
Figure 2-1 Locality plan of the existing seawalls at Tully Heads
2 Review of existing data
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 3
2.2 Land tenure
The Project site is identified as a mixture of State reserve land and local government road reserve. A
summary of the land tenure, noting the parcels of land to which each wall section relates, is provided
in and illustrated in Figure 2-2. It should be noted that ownership details for portions of land other than
road reserve were obtained from the online database, RP Data and not through purchasing formal
Certificates of Title. As such, the information should be treated as preliminary reference only.
Table 2-1 Summary of land tenure within the Project footprint
Lot Plan Tenure Ownership/Lessee Wall Section
Carron Esplanade Local road reserve
State of Queensland (Represented by DNRM) Seawall 1 and Seawall 2
10 CWL802853 Reserve State of Queensland (Represented by DNRM) – Reserve for Local Government Purposes(Camping Park and Recreation)
Seawall 2
Figure 2-2 Project site land tenure
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 4
2.3 Project background
Various sections of Tully Heads Seawalls have been constructed, upgraded and repaired since the
1980’s. Table 2-2 summarises a chronology which has been drawn from various reports and
information provided during the Project inception meeting with CCRC.
Table 2-2 Tully Heads Seawall chronology
Date Event Comment
Late 1980s / Early 1990s
Main portion of Seawall 1 constructed by property owners
Constructed without relevant approvals and no design drawings available
Early 1990’s Investigation of Seawall 1 stability and recommendation on upgrade works
Mid 1990’s Upgrade of Seawall 1 (Stage 1- approximately 100 m of upgrade)
Approved under Section 86 of the Harbours Act 1955 on 10 December 1992, design drawings prepared by GHD on behalf of Cardwell Shire Council (refer Appendix F)
Late 1990’s Construction of the southern end of Seawall 1 Approved under Section 86 of the Harbours Act 1955 on 02 December 1996, design drawings prepared by Cardwell Shire Council (refer Appendix F)
2006 Damage to Tully Heads Seawall 1 as a result of Tropical Cyclone Larry in March 2006.
-
2006 Design and approvals of Seawall 2 Approved by EPA permit no: IPCC004199906CV, design drawings prepared by International Coastal Management on behalf of Cardwell Shire Council (refer to Appendix F)
2007 Reconstruction of Seawall 1 No formal design understood to be undertaken as part of these minor works
2009 Shoreline Environmental Management Plan (SEMP) developed by BMT WBM on behalf of CCRC
-
February 2011
Significant damage to both seawalls occurs as a result of Tropical Cyclone Yasi, especially on the upper sections and at the crest.
Displaced rocks were pushed back on the wall by property owners.
2011 Applications submitted to gain funds from the Natural Disaster Relief and Recovery Arrangements (NDRRA) in order to restore the seawalls to appropriate standard.
The applications were rejected on the grounds that the seawalls do not constitute an essential public asset (not seen as protecting a community thoroughfare or esplanade).
2.4 Previous studies
2.4.1 Tully Heads seawall stability investigation –1992
GHD undertook a stability and condition assessment of the original seawall constructed by property
owners. Recommendations and cost estimates of seawall upgrades were provided.
2.4.2 Shoreline erosion management plan (SEMP) - 2009
In 2009, BMT WBM were engaged by CCRC to undertake a review of coastal processes, and the
status of erosion impacts along the Tully Heads to Hull Heads shoreline. Key management measures
were proposed to address the identified impacts to develop a Shoreline Erosion Management Plan
(SEMP) for implementation. In preparing the SEMP, BMT WBM considered the options and feasibility
of engineering works and management actions that could be carried out.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 5
Whilst it is noted that the SEMP was prepared before the Tropical Cyclone Yasi event in 2011, the
report recommended that, in relation to the Tully Heads seawall specifically, that the northern section
of the seawall at the southern end of Taylor Street to an approved and appropriate standard of
defence. It was also recommended taking no action in front of Council reserve, which creates a pocket
beach.
2.4.3 Restoration of Tully Heads and South Mission Beach Seawalls - 2011
J T Smith and Associated Pty Ltd prepared a seawall restoration report detailing the nature and costs
of works required to reconstruct the seawalls along South Mission Beach and Tully Heads following
Tropical Cyclone Yasi. This report was compiled to assist CCRC to plan the reconstruction of the
seawalls.
2.4.4 Post-Yasi cyclone inspection - 2011
GHD undertook a seawall damage assessment following TC Yasi and inspected Tully Heads Seawalls
in April 2011. Most of the observed damage was on the crest of the seawall, where numerous rocks
were displaced onto the Esplanade and private properties. In addition, severe erosion occurred at the
crest. Remediation works were recommended to restore the seawalls. This report was prepared to
support the funding application to NDDRA which was ultimately unsuccessful in securing funding.
2.5 Desktop design review
2.5.1 Seawall 1
Tully Heads Seawall 1 was built over several decades as described in Section 2.3. The existing
seawall, as shown on the Design Drawing 16566-1 dated 17 November 1992 and drawing BP 97.01
dated 13 November 1996 (refer to Appendix C) consists of a filled rock structure, approximately 410 m
in length, with the following details:
Armour rock mass of approximately 3t on top of existing armour (from the private owners’ construction)
1v:2h slope
Crest level at 3.5 m AHD and toe at approximately 0.5 m below AHD.
It is noted that the seawall was reconstructed and reshaped following storm events, in particular
following TC Larry and TC Yasi.
2.5.2 Seawall 2
Tully Heads Seawall 2 was designed and approved in 2006 as a partially buried two layer rock
seawall, approximately 160 m in length, with the following attributes:
Primary armour rock mass of 1t to 2t
Slope no steeper than 1v:1.5h
Crest level at 3.7 m AHD and toe at approximately -2.36 m AHD
Similarly to Seawall 1, Seawall 2 was reshaped following TC Yasi.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 6
2.6 Site conditions
2.6.1 Tides
Maritime Safety Queensland (MSQ) doesn’t provide tidal planes at Tully Heads. However tidal planes
are published at Clump Point (approximately 20km north from the site). CCRC indicated that
information on tidal variance along the Cassowary Coast is provided in the Innisfail – Mission Beach
Storm Tide Study, Final Report, June 2009, GHD. A ratio of 1.080 and 1.088 is recommended to be
applied to the Mourilyan Harbour tidal planes to determine the tidal planes at Clump Point and Tully
Heads respectively. Since the variance in ratio between Clump Point and Tully Heads is minor, the
tidal planes at Clump Point have been used as tidal reference for this assessment. Table 2-3
summarises the tidal planes at Clump Point.
Table 2-3 Tidal planes at Clump Point published by Maritime Safety Queensland (MSQ), 2014
Tide Level (m to AHD)
Highest Astronomical Tide (HAT) 1.94
Mean High Water Springs (MHWS) 1.04
Mean High Water Neaps (MHWN) 0.33
Mean Sea Level (MSL) 0.05
Australian Height Datum (AHD) 0.00
Mean Low Water Neaps (MLWN) -0.19
Mean Low Water Springs (MLWS) -0.89
Lowest Astronomical Tide (LAT) -1.68
2.6.2 Bathymetry
Figure 2-3 indicates an approximate bathymetry in the vicinity of Tully Heads, sourced from the marine
chart AUS 829 – Brook Islands to Russell Island. Depths are referenced to Chart Datum,
approximately Indian Spring Low Water level (which is close to LAT).
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 7
Figure 2-3 Bathymetry in the vicinity of Tully Heads (AUS 829 chart)
It is understood that no bathymetric or topographic survey is available. Ground level data surveyed
during the existing seawall condition assessment at Tully Heads will be included in the concept
design.
2.6.3 Geotechnical conditions
No geotechnical information is available at the site. Laboratory testing of beach and dune material, as
part of a geotechnical investigation, would be recommended should CCRC progress investigations to
undertake the detailed design of a complete repair/replacement of the seawall.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 8
3.1 Design considerations
3.1.1 Seawall functionality
The design of the seawall is driven by the following functional requirements:
Protect Carron Esplanade and adjacent residential properties from shoreline erosion;
Have reduced environmental and visual impact.
The seawall design purpose is to mitigate shoreline erosion along Carron Esplanade. It is important to
note that the seawall is not a flood control structure. During an extreme weather event, the area
behind the seawall (including Carron Esplanade and the private properties located behind) may be
inundated and damaged due to seawater flooding. It will be unsafe for pedestrian or vehicles to stand
behind the seawall at times. However, the seawall structure will protect the shoreline from ongoing
erosion threat during the design weather conditions.
The seawall is not designed to be a pedestrian access therefore is not suitable for pedestrians to
cross the structure. Warning signs, fencing, access points and other measures are recommended to
discourage the public from crossing the seawall.
3.1.2 Statutory requirements
The design work shall comply with the requirements of the following:
Acts of the Commonwealth of Australia
Statutory Laws and Regulations of the State of Queensland (QLD), Australia
Work Health and Safety Regulation 2011
Great Barrier Reef Marine Park Act, 1975
Environment Protection and Biodiversity Conservation Act (EPBC Act)
Relevant Commonwealth and State legislation (Acts and regulations)
Integrated Development Assessment System (IDAS) Code for Prescribed Tidal Work – Schedule 4A of the Coastal Protection and Management Regulation 2003
Relevant provisions of the Cardwell Shire Planning Scheme 2007 as called up by the Schedule 4A code
Consideration of any proposed new provisions under the Draft Cassowary Coast Regional Council Planning Scheme 2014
3 Design basis
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 9
Any relevant provisions of the State Development Assessment Provisions (SDAP) State Code and State Planning Policy
Far North Queensland Regional Organisation of Councils (FNQROC) Development Manual
Any other authority having jurisdiction over the site
Regarding public access, there is no standard that provide requirements for pedestrian access
associated with a seawall construction. However the State Development Assessment Provisions
(SDAP) Code for Tidal Works makes reference to public access in Performance Outcome (PO) 10,
with the following conditions:
AO10.1 Development adjacent to state coastal land or tidal water:
(1) demonstrates that restrictions to public access are necessary for:
(a) the safe or secure operation of development, or
(b) the maintenance of coastal landforms and coastal habitat
(2) separates residential, tourist and retail development from tidal water with public areas or public access facilities, or
(3) maintains existing public access (including public access infrastructure that is in the public interest) through the site to the foreshore for:
(c) pedestrians, via access points including approved walking tracks, boardwalks and viewing platforms, or
(d) vehicles, via access points including approved roads or tracks.
AO10.2 Development adjacent to state coastal land, including land under tidal water: (1) is located and designed to:
(a) allow safe and unimpeded access to, over, under or around built structures located on, over or along the foreshore
(b) ensure emergency vehicles can access the area near the development, or
(2) minimises and offsets any loss of access to and along the foreshore within two kilometres of the existing access points, and the access is located and designed to be consistent with (1)(a) and (b).
3.1.3 Design standards
Table 3-1 highlights the design documents and Australian Standards relevant to the Project that may
be relevant to the concept design of Tully Heads seawall.
Table 3-1 Key standards used in seawall design
Key Standards and Usage
Designation Title Typical Usage
AS 1000 The International System of Units (SI) and its application
Units to be used on the Project.
AS 1170 (Parts 0 to 4) Minimum design loads on structures (SAA Loading Code – Australian Standard)
General loadings including wind load and earthquake loads
Load combinations
AS 4997 Guidelines for the Design of Maritime Structures
General Design Requirements
Design Loads
Load combinations
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 10
Key Standards and Usage
Designation Title Typical Usage
AS 3600 Concrete Structures Design of concrete elements
AS 4678 Earth Retaining Structures Design of soil retaining structure
AS 3962 Guidelines for Design of Marinas Design of walkways, stairway and boat ramp
AS 1657 Fixed platforms, walkways, stairways and ladders – Design, construction and installation
Design of walkways and stairway
BS 6349 (Part 1 & 7) British Standard Code of Practice for Maritime Structures
Design wave loadings
Design of revetment
CEM (2006) Coastal Engineering Manual (USACE)
Design of seawall and rock armour unit
Rock Manual (2007) The Rock Manual. The Use of Rock in Hydraulic Engineering (2nd Edition)
Design of seawall and rock armour unit
SPM (1988) Shore Protection Manual (USACE) Design of seawall and design wave criteria
Coastal Engineering Guidelines for working with the Australian coast in an ecologically sustainable way
Coastal Engineering Guidelines for working with the Australian coast in an ecologically sustainable way, Engineers Australia, 2012
Design of coastal structures
3.2 Design risk According to “Coastal Engineering Guidelines for working with the Australian coast in an ecologically
sustainable way” (Engineers Australia 2012), there is approximately a 39% risk of encountering a 100
year ARI event in a 50 year period. Table 3-2 indicates the risk to encounter a 50, 100, 500 and 1,000
year ARI event in a 20 and 50 year period.
Table 3-2 Risk of encountering various ARI events in 20 and 50 year period
Average Recurrence Interval (ARI) 50 year 100 year 500 year 1,000 year
Annual Exceedance Probability (AEP) 2% 1% 0.2% 0.1%
Probability of encounter over 20 years 33% 18% 4% 2%
Probability of encounter over 50 years 63% 39% 10% 5%
The primary action on the seawall is wave impacts that affect:
Structural strength, undermining and stability of the revetment
Inundation risk due to overtopping (during extreme storms)
Changes to the surrounding environment (e.g. scour in front of and erosion at either end of the wall or
at the crest) may be ongoing over the design life of the seawall. This will involve ongoing maintenance
costs. Additional seawall and beach material may be required in the design life of the revetment.
CCRC should set a maintenance budget to carry out required repairs and monitoring investigations.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 11
3.3 Design parameters
3.3.1 Design life and design event
According to the Department of Environment and Heritage Protection (DEHP) building and
engineering standards for tidal works operational policy, the minimum development standard for a
seawall is a 50 year ARI design standard for a design life of 50 years.
It is proposed to follow this recommendation for the Tully Heads Seawall.
3.3.2 Design wind
Winds play a dominant role in wave generation. While the ambient wind climate at Tully Heads is mild,
high wind speeds occur when storms and cyclones are in the vicinity of the area. Wind speeds are
mainly reported in m/s in this study. Table 3-3 indicates the conversion of m/s to km/h and knots.
Table 3-3 Wind speed conversion from m/s to km/h and knots
Wind speed in m/s Wind speed in km/h Wind speed in knots
5 18 9.7
10 36 19.4
15 54 29.2
20 72 38.9
25 90 48.6
30 108 58.3
35 126 68.0
40 144 77.8
Structural design wind conditions are given in from the AS/NZS 1170.2 standard. This wind code gives
3-second wind gust measured at 10 m above ground for all Australian regions. Tully Heads lies in
Cyclonic Region C. The Coastal Engineering Manual (CEM) Part II, Chapter 2, Figure II-2-1
relationship between a 3-second wind speed and an hourly averaged wind speed based on a large
sample of wind measurements 10 m above sea level was adopted to derive hourly winds. Table 3-4
presents the 3-second and hourly averaged wind speeds for a range of Average Recurrence Interval
(ARI) events for a Region C location.
Table 3-4 Extreme wind recurrences at Tully Heads (10 m above sea level)
Average Recurrence Interval (year)
3s gust wind (m/s)
Hourly wind (m/s)
1 23.0 15.5
5 33.0 22.0
10 39.0 26.0
20 45.0 30.0
50 52.0 34.7
100 56.0 37.3
200 61.0 40.7
500 66.0 44.0
1000 70.0 46.7
Those wind speeds would be used in the detailed design phase for any wave modelling and to design
structural elements affected by wind.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 12
3.3.3 Design water levels
3.3.3.1 Sea level rise
According to the DEHP building and engineering standards for tidal works operational policy, it is
recommended allowing a minimum of 0.3m to take sea level rise into account in a seawall
development.
3.3.3.2 Storm tide level
Storm surge is an increase in water elevation due to the influence of wind shear (wind set-up) and
decreased atmospheric pressure associated with low weather systems such as tropical depressions
and cyclones. Storm tide is the combination of tide and storm surge. The extreme shoreline water
level includes both storm tide and wave set-up (due to breaking waves).
A comprehensive Monte Carlo storm tide model study was undertaken in 2004 by James Cook
University (JCU) for the Queensland East Coast region looking at the combined probability of
exceedance of storm surge and tide. This study proposed storm tide levels for extreme cyclonic events
at various locations, based on offshore cyclonic modelling. Table 3-5 indicates the extreme shoreline
water levels, inclusive of wave set-up, in the vicinity of Tully Heads for various extreme events
Average Recurrence Intervals (ARI) provided by the JCU study.
Table 3-5 Storm tide levels at Tully Heads (including wave set-up) from JCU
Average Recurrence Interval (ARI)
50 year 100 year 500 year
2004 storm tide level 2.02 m AHD 2.13 m AHD 2.66 m AHD
2064 storm tide level(*) 2.35 m AHD 2.46 m AHD 2.95 m AHD
(*) based on the 2004 JCU study - Greenhouse scenario, including 0.3m of sea level rise
In addition, BMT WBM carried out a coastal inundation investigation in 2007 during the Cardwell
Inundation Study project focusing on Tully and Hull Heads area. Table 3-6 provides peak inundation
levels for return period events greater than 100 year ARI assessed by BMT WBM.
Table 3-6 Peak inundation levels at Tully / Hull Heads from the Cardwell Inundation Study project
Average Recurrence Interval (ARI)
100 year 200 year 500 year
Peak inundation levels (including wave set-up)
2.70 m AHD 3.17 m AHD 3.79 m AHD
By extrapolation, a 50 year ARI peak inundation level is approximately 2.25 m AHD. It is understood
that no sea level rise or climate change effects were considered in the peak inundation levels given in
Table 3-6.
The Cardwell Inundation Study levels have been derived locally and seem slightly higher than the JCU
numbers. A storm tide level of 2.25 m AHD will be taken as the 50 year ARI design storm tide level for
the project.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 13
3.3.3.3 Design water levels
Table 3-7 displays the total water level that will be considered in the design of the seawall elements
(includes sea level rise and wave set-up).
Table 3-7 Design water levels
Average Recurrence Interval (ARI)
50 year
Storm tide level (m AHD) 2.25
Sea level rise (m) 0.3
Total water level (m AHD) 2.55
3.3.4 Design waves
Ambient waves in the region are typically short period wind-waves generated from local winds blowing
across the fetch between the Great Barrier Reef and the site. According to the Tully Heads to Hull
Heads Shoreline Erosion Management Plan (SEMP) (BMT WBM, 2009), most ambient waves come
from the ESE direction and significant wave heights are less than 1m most of the time.
Extreme offshore significant wave heights are indicated in the SEMP for events greater than 100 year
ARI events and are not available for a 50 year ARI event.
To define a significant wave height in front of the seawall that may be used to design the seawall
elements, a depth-limited wave estimate was carried out.
From the SEMP storm erosion assessment, it is noted that the beach profile would be similar prior and
post storm around -1 m AHD. Therefore the water depth at -1 m AHD (located approximately 60 – 80m
of the existing seawall) was considered in the depth-limited wave assessment. Considering a water
level at 2.55 m AHD, a 50 year ARI significant wave height is estimated at approximately 2.75 m. This
significant wave height will be considered for the concept design phase. However it is recommended
undertaking wave modelling to support the determination of design waves for the detailed design
phase of the project.
Approximate peak period for a 50 year RI event would be in the range of 5 s to 7 s and this would
need to be confirmed during the wave modelling in the detailed design phase.
3.3.5 Design overtopping
There is no specific standard provision for overtopping rate for seawalls as these structures are not
designed to mitigate both erosion and flooding.
When constructing erosion protection revetments, the averaged overtopping discharges generally
dictate the revetment crest levels. Average overtopping rates may be assessed with the Eurotop
(2008) “Overtopping Manual”, the Coastal Engineering Manual and the online Overtopping Neural
Network (Deltares). Average overtopping rates acceptable to prevent damage to paved surface behind
a seawall are generally lower than 200 L/s/m. Yet those overtopping rates along the revetment crest
would be unsafe for pedestrians and vehicles. It is also important to note that individual wave
overtopping flows may be up to 100 times larger than the average overtopping rate. Moreover it is
noted that overtopping estimates are only used to provide an order of magnitude estimates and are
not precise estimates. If accurate estimates are required, site specific physical modelling is needed.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 14
3.3.6 Long term beach erosion
Tully Heads to Hull Heads Shoreline Erosion Management Plan (SEMP), 2007, states that the area
has experienced periods of considerable erosion but that were followed by periods of accretion. This
document also mentions that there is no evidence that the coastal system has experienced persistent
sediment volume losses or progressive erosion.
3.3.7 Longshore sediment transport
The SEMP reported that the total annual longshore sand transport potential along Googarra Beach is
in the order of 25,000 and 30,000 m3 per year. The net sediment transport is small and on average
northwards. However the magnitude and direction of the net longshore sediment transport is not
constant through the year. In addition, cyclonic events may have a significant influence on the
magnitude of the net longshore sediment transport.
3.3.8 Sediment characterisation
From a visual assessment of beach material, it is noted that well sorted (uniform grain sizes) medium
sand (approx. D50 350 – 500 μm) is characteristic of Googarra Beach in front of Tully Heads existing
seawall.
3.3.9 Design scour level
According to the DEHP building and engineering standards for tidal works operational policy, the toe
of the seawall must be designed to accommodate potential long term erosion for at least 50 years and
the toe of the seawall needs to be located, as a minimum, at or lower than LAT.
Since the SEMP didn’t report any long term erosion trend, it is proposed to design the toe of the
seawall at LAT and to include a collapsible toe in front of the seawall. Maintenance might be required
over the life of the seawall to mitigate any scour that may appear overtime.
3.3.10 Tidal currents
No data is available regarding tidal currents in the area however it is not anticipated that tidal effects
will be significant. In addition, the seawall elements (i.e. rock, concrete unit, geotextile bags etc)
dimension will most likely be greater than what would be required to withstand tidal effects.
3.3.11 Density of seawater
The density of seawater will be adopted as 1026 kg/m3 (as per AS 4997).
3.3.12 Seismic condition
According to AS 1170.0-2002 and AS1170.4-2007, the earthquake return period of 500 years (1/500)
shall be applied for a marine structure with an importance level of 2 and a design life of 50 years.
Table 3-8 summarises earthquake parameters at the site assumed for the design.
Table 3-8 Earthquake parameters for Tully Heads
Earthquake Parameters (in general accordance with AS1170.0-2002 and AS1170.4-2007)
Annual probability of exceedance 1/500
Hazard Coefficient 0.07
Structural Importance factor 2
Ductility factor 1
Structural performance factor 0.77
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 15
4.1 Proposed concept design layout In 2009, the SEMP recommended upgrading the northern section of Tully Heads existing seawall
(seawall 1) but that no action is taken in front of Council’s Reserve, indicating that a pocket beach
would create between the two seawalls. It is proposed to follow the SEMP recommendation in this
concept design phase. The proposed works extent is presented in Drawing LA-002 in Appendix B.
4.1.1 Seawall 1
Seawall 1 is approximately 400m long and has been damaged during past severe storm events. It is
proposed to upgrade or replace Seawall 1. Conceptual options for this work are presented in the
following sections.
4.1.2 Seawall 2
Seawall 2 is believed to be mostly buried under the existing beach. The rocks that can be seen are
assumed to be the crest rocks. Those crest rocks have been displaced following storm and cyclone
events. It is proposed to relocate those rocks in an orderly manner and to add large 6,000kg rocks as
well to increase the crest stability. However it is assumed that the rest of the seawall structure is
complete under the existing beach. Therefore no other works is considered in this option assessment
report regarding Seawall 2. Reconstructing Seawall 2 will imply large excavation and is not considered
as critical works. Regular monitoring inspections are recommended to remediate any scouring issue or
crest damage, especially after storm event.
4.2 Seawall 1 upgrade/reconstruction options Various options exist to protect coastal foreshores. The selection of the most appropriate option
depends on the site and environmental conditions. Five options are proposed for the protection of
Tully Heads Foreshore.
Option 1 – Rock armoured revetment
Variant A – Toe buried underneath beach surface
Variant B – Toe on existing beach surface
Variant C – New rock revetment
Option 2 – Geocontainer revetment
Option 3 – Reinforced concrete seawall
4 Concept design option assessment
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 16
Other options such as irregular and regular concrete blocks, Seabees, masonry seawall, terraced
concrete blocks, timber and steel sheetpiles are other revetment options that have not be looked into
as they are not considered suitable for the site.
The following assumptions were made in the option assessment and material quantity estimate
described in the following sections:
No detailed survey was undertaken to obtain the dimensions of the existing seawall, therefore the actual volume of material required may increase once the detailed design and a survey is carried out.
It is assumed that the toe of the existing seawall is buried
No geotechnical information was available at the time of writing. A detailed geotechnical investigation will be required to confirm the selected option feasibility and details.
The concept design options are designed to a 50 year ARI event and would be damaged in severe weather events that would be similar to TC Yasi.
The seawall is not intended for pedestrian access. However consideration should be given to inclusion of a Building Code of Australia (BCA) compliant public access stair to provide a safe access to the beach, or alternate means of deterring unauthorised access on the wall. Such measures have been excluded from the quantity estimate but a unit cost has been included in the contingency table.
Warning signs, fencing and other public safety features have not been detailed in this assessment but are recommended to be implemented in the detailed design phase
Regular monitoring and maintenance is critical with any type of coastal protection revetment
4.2.1 Option 1 - Rock revetment
A conventional double layer rock armour seawall is generally the most economical and robust solution
if an appropriate rock quarry, able to produce the required rock sizes, is available near the site.
Advantages of a rock revetment include:
High degree of coastal protection
Durable structure with little maintenance
Adaptable revetment to beach erosion and sea level rise
Relatively cost-effective if material is available
Easily repaired, if damaged during a storm event
Reduced overtopping due to porosity of the slope
Disadvantages of a rock structure include:
Potential community concerns over visual amenity (although as the existing seawall is a rock structure, this may be minimal)
Reduction of beach or foreshore space – a sloping wall reduces foreshore space
Beach access restricted to stairways – the top of seawall should be fenced off for safety reasons
Additional environmental impacts relating to rock quarry
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 17
4.2.1.1 Variant A - Rock revetment repair with buried toe
This option consists of reusing the existing rock armour as secondary armour and adding a primary
layer of armour rock on a 1v:1.5h slope with a buried toe. A cross-section is presented on Drawing LA-
003 in Appendix B.
Structure shape
The existing rock armour shall be shaped to form a layer of at least 1m thick. Any gaps in the armour
shall be filled. A minimum 2.1 m thick armour layer of rocks of M50=3,000 kg shall be installed once the
layer of existing rocks is shaped.
To limit average overtopping rates lower than 200 L/s/m in the design event for a 50 year period, a
crest at 4m AHD is suitable. This is approximately 0.5 m higher than the existing foreshore level. It is
understood that Tully Heads community desires keeping the visual aspect of the current foreshore. A
crest at 3.5m AHD would be suitable for current climatic conditions but would eventually have to be
raised when sea level rises. It is proposed to increase the seawall height at a later date, therefore
keeping the current visual amenity at this stage.
The toe of the rock revetment shall be buried to LAT to mitigate scour issues. This assumes that the
existing seawall is also buried. This will have to be confirmed from a survey carried out to identify any
buried material at the site. Secondary armour rocks of M50=300 kg will have to be added to construct
the toe. The seawall toe will require monitoring and additional stones may be required to maintain the
seawall if and when scour develops.
Quantity estimate
Table 4-1 presents an indicative quantity estimate of material associated with this option.
Table 4-1 Indicative material quantity associated with Option1 - Variant A
Material type Unit Approximate quantity
Excavation/backfill m3 4,500
Primary and crest armour t 25,000
Secondary armour (toe) t 3,000
This quantity estimate excludes any additional material that may be required to repair and reshape the
existing rock layer.
Conclusion
The main advantages of the rock revetment upgrade with buried toe are:
Scour mitigation
No demolition of the existing seawall
The principal disadvantages associated with this option are:
Reuse of existing material (potentially of lower quality)
Geotextile layer presence unknown
4.2.1.2 Variant B - Rock revetment repair with toe on existing surface
This option is similar to Variant A and reuses the existing rock armour as secondary armour. An
additional primary rock armour layer is added and the toe is formed on the existing beach. A cross-
section is presented on Drawing LA-003 in Appendix B.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 18
Structure shape
The existing rock armour shall be shaped to form a layer of at least 1 m thick. Any gaps in the armour
shall be filled. A minimum 2.1 m thick armour layer of rocks of M50=3,000 kg shall be installed once the
layer of existing rocks is shaped.
To limit average overtopping rates lower than 200 L/s/m in the design event for a 50 year period, a
crest at 4m AHD is suitable. This is approximately 0.5 m higher than the existing foreshore level. It is
understood that Tully Heads community desires keeping the visual aspect of the current foreshore. A
crest at 3.5m AHD would be suitable for current climatic conditions but would eventually have to be
raised when sea level rises. It is proposed to increase the seawall height at a later date, therefore
keeping the current visual amenity at this stage.
The toe of the rock revetment of this option shall be placed on the existing beach surface. Such a toe
may be subject to scour during larger wave events. The rocks placed on the seabed act as a sacrificial
apron but regular monitoring would be required to investigate any scouring issues. This toe shape
triggers a loss of beach space for recreational use.
Quantity estimate
Table 4-2 presents an indicative quantity estimate of material associated with this option.
Table 4-2 Indicative material quantity associated with Option 1 - Variant B
Material type Unit Approximate quantity
Primary and crest armour t 15,000
Secondary armour (toe) t 3,000
This quantity estimate excludes any additional material that may be required to repair and reshape the
existing rock layer.
Conclusion
The main advantages of the rock revetment upgrade with a toe on the existing surface are:
Limited excavation
No demolition of the existing seawall
The principal disadvantages associated with this option are:
Reuse of existing material (potentially of lower quality)
Geotextile layer presence unknown
Potential scour issues and increase in monitoring exercises
Loss of beach area
4.2.1.3 Variant C – Total rock revetment reconstruction
This option consists of demolishing the existing seawall and constructing a new seawall with new rock
material and a geotextile layer. A cross-section is presented on Drawing LA-003 in Appendix B.
Structure shape
The existing rock armour shall be demolished and a new profile of 1v:1.5h prepared. A geotextile
equivalent to 600R Elcomax geotextile shall be laid on the shaped profile. A secondary layer of
M50=300kg rock and a primary layer of rocks of M50=3,000kg shall be placed on the geotextile layer.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 19
To limit average overtopping rates lower than 200 L/s/m in the design event for a 50 year period, a
crest at 4m AHD is suitable. This is approximately 0.5 m higher than the existing foreshore level. It is
understood that Tully Heads community desires keeping the visual aspect of the current foreshore. A
crest at 3.5m AHD would be suitable for current climatic conditions but would eventually have to be
raised when sea level rises. It is proposed to increase the seawall height at a later date, therefore
keeping the current visual amenity at this stage.
The toe of the rock revetment shall be buried to LAT to mitigate scour issues. The seawall toe will still
require monitoring and additional stones may be required to maintain the seawall if and when scour
develops.
Quantity estimate
Table 4-3 presents an indicative quantity estimate of material associated with this option.
Table 4-3 Indicative material quantity associated with Option 1 - Variant C
Material type Unit Approximate quantity
Excavation/backfill m3 15,000
Primary and crest armour t 25,000
Secondary armour t 11,500
Geotextile m2 7,500
Conclusion
The main advantages of the total rock revetment reconstruction are:
Complete reconstruction of the seawall to current design standards
Scour mitigation
The principal disadvantages associated with this option are:
Demolition of the existing structure
4.2.2 Option 2 - Sand filled geotextile bags
An alternative sloping seawall option to the rock armoured seawall is a wall comprised of geocontainer
sandbags. This option consists of demolishing the existing seawall and constructing a new seawall
consisting of geocontainers (e.g. Elcorock) with the toe of the seawall being buried in the existing
seabed level. A cross-section is presented on Drawing LA-004 in Appendix B.
A geocontainer seawall can be used in less severe wave climates with design wave heights typically
less than 2m. The design wave height criterion is greater than 2m at the site. However, compared to
other options, the geocontainer wall provides better visual amenity and improved beach access as the
community can walk down and over the geocontainers.
The geocontainer seawall advantages include:
Relatively cost-effective, particularly if the sand is sourced from local beaches
Beach access friendly – the smooth, sloping wall would not require hand railing and may enable direct access to the beach
Adaptable to beach erosion and sea level rise
Limited trucking requirement if the sand can be sourced from the local beach(es)
Re-useable construction material, except geocontainers
The geocontainer seawall disadvantages include:
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 20
Durability – bags with constant UV exposure can typically deteriorate within 20 years, and would not meet the design life of 50 years
Reduction of beach or foreshore space – sloping wall reduces flat foreshore space
Vandalism potential – cutting of bags by vandals
Reduced erosion protection compared to the rock revetment in higher wave climate
Less repairable as compared to rock revetment
Higher overtopping due to smooth surface and less porosity
Figure 4-1 Example of geocontainer seawall
4.2.2.1 Structure shape
The geocontainer seawall design would require a double layer of 2.5 m3 geocontainer bags to
withstand the design wave with minimal damage. A slope of 1v:1.5h is proposed and a geotextile layer
would be required between the sloped profile and the geocontainer bags. A reinforced concrete wave
deflector structure is proposed at the crest, to mitigate overtopping damage to the seawall crest. This
structure would reduce the risk of overtopping failure and associated erosion immediately behind the
seawall.
The toe of the wall shall be buried to LAT to mitigate scour issues. The seawall toe will require
monitoring and additional material may be required to maintain the seawall if and when scour
develops.
4.2.2.2 Quantity estimate
Table 4-4 presents an indicative quantity estimate of material associated with this option.
Table 4-4 Indicative material quantity associated with Option 2
Material type Unit Approximate quantity
Excavation/backfill m3 15,000
Geocontainers unit 4,100
Geotextile m2 9,200
Reinforced concrete m3 1,000
4.2.2.3 Conclusion
The main advantages of the geocontainer seawall are:
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 21
Visually and pedestrian friendly
Scour mitigation
Easily removed (bags can be cut open and the sand distributed on the beach)
The principal disadvantages associated with this option are:
Demolition of the existing structure
Not appropriate for higher wave climate – containers will have to be replaced during the seawall design life
Not as robust as a rock structure
4.2.3 Option 3 - Reinforced concrete stepped seawall
This option consists of demolishing the existing rock structure and constructing a concrete stepped
seawall along Tully Heads foreshore. A cross-section is presented on Drawing LA-004 in Appendix B.
The advantages of this type of revetment include:
High degree of coastal protection
Low maintenance
Less quantity of material required for construction
Re-usable construction material (after processing)
The disadvantages of this type of revetment include:
Reflection of large portion of the wave energy due to low porosity of the structure which may cause reduction in beach amenity
More expensive as compared to rock armoured revetment
Beach access restricted to stairways - the top of seawall should be fenced off for safety reasons
More difficult to repair as compared to rock revetment, if damage occurs during a storm event
Stability of this type of construction is sensitive to toe erosion (toe sheetpiling may be required for Tully Heads site conditions)
Figure 4-2 Example of concrete stepped seawall
4.2.3.1 Structure shape
The seawall is a stepped gravity earth retaining structure which is attached to a precast toe. The upper
stepped portion of the cross-section is cast in-situ reinforced concrete. Typically the seawall has
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 22
380mm rises to 710mm goings. Engineered fill and moisture barrier would be required to support the
seawall.
Heavy overtopping can cause the seawall rear side to scour and the backfill to lose resistance. A layer
of rocks is proposed to be installed behind the seawall crest. This rock layer will assist in maintaining
the soil at the back of the seawall and will mitigate any piping or scouring issue that may occur at the
back of the seawall crest due to potential seawater inundation. The concrete stepped seawall can be
raised in the future, if sea level rises and seawater inundation becomes permanent. An additional
reinforced concrete barrier can be cast on top of the existing crest and tied in using stainless steel
bars. This would require some preparation to the existing concrete surface and include core drilling
and chemical anchoring to set the stainless bars into place.
It is proposed to construct the toe of the seawall at LAT. The toe will consist of precast concrete units
and large rocks that will mitigate any potential scouring issue that may occur. Monitoring should still be
implemented to identify any scour issues that may occur.
4.2.3.2 Quantity estimate
Table 4-5 presents an indicative quantity estimate of material associated with this option.
Table 4-5 Material quantity associated with Option 3
Material type Unit Approximate quantity
Excavation/backfill m3 15,000
Reinforced concrete t 6,500
Moisture barrier m2 4,000
Armour rock t 6,500
4.2.3.3 Conclusion
The main advantages of the concrete stepped seawall are:
Scour mitigation
The principal disadvantages associated with this option are:
Demolition of the existing structure
Wave reflection
4.3 Cost estimate of options The following assumptions were made in the cost estimate
Estimate is preliminary only, and requires confirmation from Council’s preferred suppliers.
Detailed site survey (including buried material) and geotechnical investigation would also be required to confirm estimated quantities.
Assumed rates are assumed to be supply/install but are exclusive of GST
4.3.1 Assumed rates
Table 4-6 indicates the units rates assumed for the materials.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 23
Table 4-6 Assumed material rates
Material type Unit Assumed rates
Excavation/backfill m3 $50
Crest and primary armour t $70
Secondary armour t $65
Reinforced concrete m3 $2,000
Geotextile m2 $35
Geocontainers (Vandal deterrent) unit $600
Moisture barrier m2 $60
4.3.2 Contingencies
Table 4-7 indicates contingencies proposed for the project.
Table 4-7 Proposed contingencies
Contingency and fees Typical range Proposed value
Contractor overheads [+5%, +30%], +15%
Contractor mobilisation and demobilisation [$30,000-$150,000] $100,000
Quarry risk (applicable to quarry material only) [0, +100%] +30%
Weather and program risk [0, +100%] +5%
Geotechnical risk (Acid Sulphate Soil, loose material)
[0, +30%] +10%
Escalation during detailed design (*) [-30% to +30%] +10%
Engineering, procurement, construction management
[+5%, +15%] +10%
Furniture / railing [$2,000, $10,000] $7,000
Pedestrian access stairs [$10,000, $40,000] $20,000
Tree clearing [$30,000, $60,000] $50,000
Re-vegetation [$20,000, $100,000] $50,000
Fees and surveys N/A $50,000
(*) Detailed design escalation covers features which may become required during the consultation and
detailed design process.
A risk assessment is recommended to be developed at the onset of the detailed design phase to
reduce the range of uncertainties on these contingencies.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 24
4.3.3 Indicative cost breakdown
Table 4-8 to Table 4-12 present an indicative cost estimate for each proposed options.
4.3.3.1 Option 1 - Variant A - Rock revetment repair with buried toe
Table 4-8 Indicative cost estimate for Option 1 – Variant A
Material Unit Cost
Excavation/backfill m3 $250,000
Crest and primary armour t $1,750,000
Secondary armour t $200,000
Fees and contingencies (Table 4-7)
N/A $2,000,000
Total $4,200,000
4.3.3.2 Option 1 - Variant B - Rock revetment repair with toe on existing surface
Table 4-9 Indicative cost estimate for Option 1 – Variant B
Material Unit Cost
Crest and primary armour t $1,050,000
Secondary armour t $200,000
Fees and contingencies (Table 4-7)
N/A $1,300,000
Total $2,550,000
4.3.3.3 Option 1 – Variant C – Total rock revetment reconstruction
Table 4-10 Indicative cost estimate for Option 1 – Variant C
Material Unit Cost
Excavation/backfill m3 $750,000
Crest and primary armour t $1,750,000
Secondary armour t $750,000
Geotextile m2 $270,000
Fees and contingencies (Table 4-7)
N/A $3,100,000
Total $6,620,000
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 25
4.3.3.4 Option 2 - Sand filled geotextile bags
Table 4-11 Indicative cost estimate for Option 2
Material Unit Cost
Excavation/backfill m3 $750,000
Geocontainers unit $2,500,000
Reinforced concrete m3 $2,000,000
Geotextile m2 $350,000
Fees and contingencies (Table 4-7)
N/A $4,700,000
Total $10,300,000
4.3.3.5 Option 3 - Reinforced concrete stepped seawall
Table 4-12 Indicative cost estimate for Option 3
Material Unit Cost
Excavation/backfill m3 $750,000
Reinforced concrete m3 $13,000,000
Moisture barrier m2 $150,000
Armour rock t $450,000
Fees and contingencies (Table 4-7)
N/A $11,750,000
Total $26,100,000
Important note regarding cost estimates
The above opinions of cost have been prepared by Aurecon at the request of Council, solely for use in
connection with the Tully Heads Seawall Condition Assessment project. Aurecon does not accept any
legal liability or responsibility in respect of the use of this opinion of cost for any purpose other than the
purpose defined above. Aurecon has exercised due skill, care and attention in preparing the opinion of
cost. Since Aurecon has no control over the cost of labour, materials, equipment or services furnished
by others, or over contractors’ methods of determining prices, or over competitive bidding or market
conditions, any opinion of costs is made on the basis of Aurecon's experience and qualifications and
represents its best judgement as an experienced and qualified professional engineer, familiar with the
construction industry; but Aurecon cannot and does not guarantee that proposals, bids or actual
construction cost will not vary from Aurecon’s opinion of cost
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 26
A Multi Criteria Analysis has been undertaken to compare a range of options plausible to mitigate the
erosion problem at Tully Heads.
Multi Criteria Analysis is a tool that can be used for complex problems where multiple criteria need to
be assessed in the process of making decisions about proposals for future action. Multi Criteria
Assessments (MCAs) attempt to incorporate all criteria simultaneously within the analysis, to arrive at
a single conclusion or ranking. As such, those assessments can consider a range of complex issues,
impacts and opportunities and can therefore be applied to more complex situations than a Cost
Benefit Analysis. For these reasons, an MCA process is used to inform the selection of a preferred
seawall option at Tully Heads.
5.1 Analysis criteria
The seawall options are assessed on the following themes: impact, effectiveness, social value,
government process and economics. The following sections outline factors taken into consideration for
each theme.
5.1.1 Impact
The impact or influence of a proposed option is a key consideration and generally relates to the
degree to which an option may change conditions from the status quo (perceived or otherwise
defined). Impacts can occur to the environment and to the community.
Marine biodiversity – the degree to which the option may impact marine biodiversity at Tully Heads, considering the benthic species associated with the beach, intertidal flats and the sub-tidal areas
Beach/dune biodiversity – the degree to which the option may impact beach and dune biodiversity (those areas typically above high tide mark), considering suitability to promote dune vegetation (re-vegetation) and the opportunity for re-colonisation by dune animal species
Environmental impacts beyond Carron Esplanade – the impact of the option on areas farther afield, including the impact on materials source areas, and up/down coast impacts due to changes in sand supply or generation of plumes etc.
Construction impact – in relative terms, the area directly affected by the proposed option, both in terms of option footprint as well as construction impacts for the materials sourcing areas. This criteria may also capture issues relating to the degree to which construction works may interfere with beach use
Construction timing – the time and flexibility taken to undertake construction (i.e. the degree to which external influences may restrict the timing of works)
5 Multi-criteria analysis
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 27
Non-beach users – the degree to which the option may impact on non-beach users within the community. For example, nourishment options that use quarried sand may impact non-beach users by way of increased truck traffic on local roads
5.1.2 Effectiveness
The effectiveness of the option to address the erosion problem is assessed via a range of criteria.
Consideration is given to both the upside (addressing the problem) and downside risks (failure
consequence) of each option as well as to specific uncertainties.
Longevity of design – consideration of design life under typical conditions
Incident wave problem – degree to which a solution directly attenuates incident waves, creating a reduced wave energy condition at the beach
Sand budget imbalance – degree to which a solution ameliorates the recognized imbalance between longshore supply and storm sediment transport
Shoreline recession – degree to which a solution reduces or eliminates beach recession
Failure consequence – the downside risk of failure of the proposed option, perhaps due to exposure to conditions beyond design criteria, where consequences could include potential loss of life or damage to public/private property and/or infrastructure
Technology challenges – measure of the uncertainty associated with proven versus new technology, and considers options proven/suitable for conditions at Tully Heads through to new technology unproven along the Cassowary Coast
Integration/compatibility with existing – measure of the difficulty to integrate the proposed option with the existing infrastructure
Adaptation to short term cyclic variations – degree to which the option can accommodate short term (seasonal, storm) cycles in sand supply, wave climate, water levels
Adaptation to long term changes – degree to which the option can accommodate long term (annual, climate change, ENSO) cycles in sand supply, wave climate, water levels
5.1.3 Social value/community expectations
The local and extended community of beach users have expectations about Googarra Beach. An
important measure of the appropriateness of the proposed solution option is the degree to which the
values held by the community can be preserved.
Visual amenity – degree to which the option meets with the community’s expectation of what Googarra Beach should look like, and/or the degree to which an option may detract from such expectations about the beach. It is understood that Tully Heads residents wish to protect the visual amenity and may be resistant to a higher wall.
Beach safety – issues such as safe access to the beach, safe beach user area, safe swimming, or safe use of recreational water craft
Sense of place – degree to which the option may alter the sense of place, or community connectedness to Googarra Beach
Suitability of materials – degree to which the community may accept proposed materials, recognizing the materials’ adaptability for use (or not) for stairs, walkways, informal seating and an assessment of other material specific issues including user-friendliness, colonization of pests, litter, maintenance and odour
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 28
5.1.4 Government processes
This theme considers the governmental process challenges associated with each option.
Roles and responsibilities – degree to which various local, state and federal government roles and responsibilities are clearly defined, and one end of the scale requiring significant effort to resolve (perhaps outside the existing policy scope) to being clearly set out within existing arrangements
Compliance with Coastal Protection and Management Act (CPMA) and Marine Park Act (MPA) – as a guiding principal, the CPMA and MPA is a crucial reference for proposed actions at Googarra Beach. This measure captures the degree to which the option is consistent with the CPMA and MPA policies and objectives
Approvals process – considers the requirements of approving the proposed option, whether secured via existing well understood pathways or requiring significant additional levels of approval not typical of “business as usual”
5.1.5 Economics
Cost is a major factor in any infrastructure project. Once completed, the seawall will become part of
the Cassowary Coast Regional Council portfolio of coastal assets and accordingly, capital cost is not
the only consideration.
Capital Cost – in relative dollar terms the up-front cost of the option, including material costs, site construction activities, and any environmental (or other) monitoring linked to the option
Maintenance Cost – the cost of periodic routine maintenance
Lifecycle cost – the total cost of the asset each year, over its design life
5.2 Option analysis
Table 5-1 summarises the findings of a MCA, prepared as a desktop level. It is important to consider
that this is not a final assessment and is subject to feedback from relevant stakeholders.
Colour coded cells have been included for each criterion and for each option. A green cell indicates a
low impact, an orange cell shows a medium impact and a red cell means the option triggers a high
impact.
The geotextile seawall would require more intervention year on year than most other seawall types. A
reinforced concrete stepped seawall is typically expensive to build and difficult to repair.
The rock revetment repair with buried toe is best suited for Seawall 1 at Tully Heads, provided that
sufficient armour stone can be procured economically. It is recommended to investigate local quarries
to confirm what armour stones can be provided locally and economically.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 29
Table 5-1 Multi-criteria analysis
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 30
Various options were assessed to upgrade/replace Seawall 1 at Tully Heads. It is proposed to
upgrade Seawall 1 by adding a primary rock armour layer and burying the revetment toe under the
existing beach surface. Repairs of the crest of Seawall 2 are also proposed. This however is subject to
relevant stakeholder feedback.
Both Seawall 1 and Seawall 2 are mitigating the shoreline erosion along Tully Heads foreshore
however they are not flood control structures. Overtopping may occur behind the seawall crest. In
addition, the seawalls are not pedestrian accesses to the beach. A BCA compliant pedestrian access
stair should be considered as part of detailed design, or an alternate system implemented to deter
unauthorised access across the wall.
Detailed geotechnical investigations and site survey (including buried material) are required to confirm
the concept option assessment details.
Detailed design, development approval consultations, project management, selection of an
appropriate contract for construction, contractor engagement and on-going construction management
are recommended to detail the cost estimates further and to provide control on future cost changes.
Physical model testing is recommended during the detailed design phase to optimise the seawall
structure and reduce capital costs.
6 Conclusion
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page 31
1. Australian/New Zealand wind load standard AS/NZS 1170.2:2011
2. BMT WBM (2009) Tully Heads to Hull Heads Shoreline Erosion Management Plan – Final
Report
3. CIRIA (2007) The Rock Manual – The use of rock in hydraulic engineering
4. Coastal Engineering Guidelines for working with the Australian coast in an ecologically
sustainable way, Engineers Australia, May 2012
5. Department of Environment and Heritage Protection Operational Policies for Coastal
Development
http://www.ehp.qld.gov.au/coastal/development/operational_policies.html
6. Building and engineering standards for tidal works, DEHP, 2013
7. GHD (1992) Tully Heads Seawall, Report on Stability of Seawall
8. GHD (2011) Post Yasi Cyclone Inspections, Tully Heads Rock Seawall (portion of the report)
9. JT Smith and Associates Pty Ltd (2011) Restoration of seawalls and other works, South
Mission Beach and Tully Heads
10. Hardy T, Mason L, Astorquia A, Queensland Climate Change and Community Vulnerability to
Tropical Cyclones: Ocean Hazards Assessment Stage 3 – The Frequency of Surge Plus Tide
During Tropical Cyclones for Selected Open Coast Locations Along the Queensland East
Coast. Marine Modelling Unit, School of Engineering, James Cook University, August 2004
11. Overtopping Neural Network online calculator
http://www.deltares.nl/en/software/630304/overtopping-neural-network
12. Maritime Safety Queensland (2014) Tidal planes [online] www.msq.qld.gov.au/Tides/Tidal-
datam-information.aspx
13. Tully Heads Original Design Drawings
14. U.S. Army Corps of Engineers (2006) Coastal Engineering Manual – Part II, Chapter 2
15. U.S. Army Corps of Engineers (2006) Coastal Engineering Manual – Part VI, Chapter 5
16. Wave overtopping of sea defences and related structures: assessment manual, 2007,
EurOtop
7 References
Appendices
Appendix A Document register
Project 243333 File Appendix A - Document Register.docx 24 October 2014 Revision 1 Page 1
Title Description Prepared by Date
1992 Upgrade of Seawall 1
s.86 Harbours Act – Beach Protection Authority Assessment
Correspondence from the Beach Protection Authority to Cardwell Shire Council stating no objection letter to proposed upgrade of 370 m rock wall at Tully Heads.
Beach Protection Authority
20.11.1992
s.86 Harbours Act Correspondence from Queensland Transport to Cardwell Shire Council granting sanction – Tully Heads Rock Wall – Stages 1 and 2 (Ref 2-19-3396T)
Queensland Transport
10.12.1992
Drawing 16566-1 (in 4 prints)
Tully Heads Seawall, Seawall Plan and Details
GHD 1992
s.47 Approval of Rock Seawall at Tully Heads
Correspondence from the Beach Protection Authority to Cardwell Shire Council granting a s.47 approval.
Beach Protection Authority
11.01.1993
1996 Revetment Wall Extension (16 m) Seawall 2
Extension of Revetment Wall at Tully Heads
Correspondence from the Queensland Department of Environment – Sanction under s.86 of the Harbours Act – 16 m Revetment Wall Extension
Queensland Department of Environment
2.12.1996
Drawing BP97.01 Tully Heads Seawall Extension South End at Taylor Street, Site Plan and Details
Cardwell Shire Council
1996
2006 Construction of Seawall 2
Decision Notice Approval in Full with Conditions – Prescribed Tidal Works (Installation of a Rock Wall) Taylor Street, Tully Heads (Reserve) Lot 10 on CWL802853
Cardwell Shire Council
15.12.2006
Concurrence Agency Response
Environmental Protection Agency to Cardwell Shire Council – Concurrence Agency Response – Granted in full with conditions
Environmental Protection Agency (ecoaccess)
30.10.2006
Plan 3811 Cross-Section Adjacent to Pocket Beach (Lot 9 T9483)
International Coastal Management (ICM)
2006
Drawing TH-A3-01 Location and Site Plan ICM 2006
Drawing TH-A3-02 Plan ICM 2006
Drawing TH-A3-03 X-Section ICM 2006
- Cardwell Shire Council – Prescribed Tidal Works – Application File 146/06
IDAS Forms and Design Drawings
Cardwell Shire Council
-
- Correspondence from International Coastal Management (ICM) to the Department of Natural Resources and Mines (DNRM) requesting resource consent
ICM March 2006
April 2006
Project 243333 File Appendix A - Document Register.docx 24 October 2014 Revision 1 Page 2
Title Description Prepared by Date
Correspondence from International Coastal Management (ICM) to the Environmental Protection Agency (EPA) submitting application for assessment – extension of existing rock wall at Tully Heads
ICM November 2004
Officer Report DA 146/06 Report Number W655
Officer’s Recommendation Report – Development Application for Prescribed Tidal Works
John Pettigrew (Deputy Director Engineering Services)
November 2006
Contract T01/06-07 Construction of a Seawall at Tully Heads
Correspondence –Cardwell Shire Council to Jenkins Earthmoving
22 June 2007
Construction of Rock wall, Taylor Street, Tully Heads, at and adjacent to Lot 10 CWL802853
Correspondence – Condition A1C3 – Results of Site Inspection undertaken by EPA officer on Thursday 17 January 2008
1 February 2008
Reference
Report on Stability of Seawall, Tully Heads Seawall
- GHD 1992
Post Yasi Cylcone Inspections, Tully Heads Rock Seawall
Section of report GHD 2011
Restoration of Seawalls and other Works, South Mission Beach and Tully Heads
- J T Smith and Associates Pty Ltd
March 2011
Tully Heads and Hull Heads Shoreline Erosion Management Plan
Final Report BMT WBM April 2009
Other Documents Received (Outside Scope)
Drawing BP97.02 Installation of a Trial Groyne at Tully Heads Cardwell Shire Council
1997
Appendix B Option Assessment Drawings
CLIENT
DATE
TITLE
REVISION DETAILSDATEREV APPROVED
CHECKED
APPROVED
PROJECT
DRAWN
DESIGNED
PROJECT No. TYPE REVWBS DISC NUMBER
DRAWING No.
SCALE SIZE
A1
.
CONCEPT DESIGN SEAWALLTULLY HEADS
DRAWING SCHEDULE AND NOTES
243333 0000 DRG LA 0001 A
NOT TO SCALEPRELIMINARY
NOT FOR CONSTRUCTION
K.HADZIVUKOVIC
J.FARNES
A 15.12.14 ISSUED FOR CLIENT REVIEW GC
Filen
ame:
Plot
Date:
Offic
e:P:
\MRN
\2433
33_C
ASSO
WAR
YCOA
STSE
AWAL
LS\3
PROJ
ECT
DELIV
ERY\
CADD
\DRA
WIN
GS\24
3333
-000
0-DR
G-LA
-000
1.DW
G15
/12/20
14 12
:55:10
PM
AUBN
E
243333-0000-DRG-LA-0001 DRAWING SCHEDULE AND NOTES
243333-0000-DRG-LA-0002 SITE LAYOUT
243333-0000-DRG-LA-0003 SEAWALL OPTION 1 - TYPICAL SECTIONS
243333-0000-DRG-LA-0004 SEAWALL OPTIONS 2 & 3 - TYPICAL SECTIONS
243333-0000-DRG-LA-0005 SEAWALL OPTIONS - PUBLIC ACCESS STAIR
CONCEPT DESIGNTULLY HEADS SEAWALL
SCHEDULE OF DRAWINGS
HAT 1.941.040.33
-0.19
-1.68
LEVEL AHD (m)
-0.89
TIDAL LEVELS *
MHWSMHWNMSLMLWNMLWSLAT
* - TIDAL LEVELS ASSUMED TO BE SIMILAR TO CLUMP POINT
50 2.55
AVERAGE RECURRENCEINTERVAL (A.R.I. YEAR)
STORM TIDE LEVELS **
PRESENT SEA LEVEL(m AHD)
2.25
** - BASED ON CARDWELL INUNDATION STUDY
2064 SEA LEVEL(m AHD)
50 34.7
AVERAGE RECURRENCEINTERVAL (A.R.I. YEAR)
DESIGN PARAMETERS
WATER LEVEL(m AHD)
2.55
# - WIND SPEED IS PER AUS STD AS1170.2 (HOURLY SPEED AT 10m/s)
WIND SPEED(m/s) #
2.75
SIGNIFICANT WAVEHEIGHT Hs (m)
5 to 7
DESIGN WAVE PEAKPERIOD Tp (s)
GREENHOUSE EFFECT
1. SEA LEVEL RISE = 0.3m (2064)
SCOUR ALLOWANCE
1. SEAWALL TOE IS BURIED TO LAT (-1.68m AHD)
GENERAL NOTES:
1. THE POSITION AND DIMENSIONS OF SEAWALL OPTIONSARE INDICATIVE ONLY.
2. DRAWINGS SHALL BE READ IN CONJUNCTION WITH TULLYHEADS SEAWALL OPTION ASSESSMENT REPORT
3. THE SEAWALL IS ONLY AN EROSION CONTROL STRUCTUREAND IS NOT DESIGNED FOR FLOOD CONTROL
4. EXISTING SOIL ELEVATIONS ARE APPROXIMATE ONLY
DRAWING No. DESCRIPTION
0.05
25T948624T9486 22RP846516 12T9486 11T9486 10T9486 9T9486
14T9486 15T9486 16T9486 17T9486 18T9486 19T9486 20T9486
1T9486
2T94861RP7381555T94866T94867T9486
8T9486
13T948514T9485 15T9485 16T9485 17T9485 18T9485
7T94858T94859T948510T948511T948512T9485
12T9487
11T9487 10T9487 9T9487 8T9487 7T9487
642T9484
39T9482
40T9482
1RP735394
43T9482 1RP738156
35T9482
36T948237T9482
38T9482
906T9482 905T9482 904T9482 903T9482 902T9482 901T9482 9T9483 1RP865399
4RP736730
3RP736730
2T9483 1T9483
10CWL802853
2RP865399
1AP5889
2AP5889
16T948222T948223T948224T948225T9482
26T9482
27T9482
28T9482
907T9482908T9482909T9482910T9482911T9482912T9482
13T9484
CLIENT
DATE
TITLE
REVISION DETAILSDATEREV APPROVED
CHECKED
APPROVED
PROJECT
DRAWN
DESIGNED
PROJECT No. TYPE REVWBS DISC NUMBER
DRAWING No.
SCALE SIZE
A1
.
CONCEPT DESIGN SEAWALLTULLY HEADS
SITE LAYOUT
243333 0000 DRG LA 0002 A
1:1000PRELIMINARY
NOT FOR CONSTRUCTION
S.LEMON
J.FARNES
A 15.12.14 ISSUED FOR CLIENT REVIEW GC
Filen
ame:
Plot
Date:
Offic
e:P:
\MRN
\2433
33_C
ASSO
WAR
YCOA
STSE
AWAL
LS\3
PROJ
ECT
DELIV
ERY\
CADD
\DRA
WIN
GS\24
3333
-000
0-DR
G-LA
-000
2.DW
G15
/12/20
14 12
:53:12
PM
AUBN
E
TAYLOR ST
CARRON ESP
X
TULLY RIVER
GALM
AHRA
ST
LEGENDWARNING SIGN LOCATION (APPROXIMATE)READING: "ROCK WALL MAY BE UNSTABLE. TOAVOID INJURY DO NOT CLIMB OR CROSS WALLS"
TAYLOR ST
CARRON ESP
TOE OFEXISTINGSEAWALL
TOP OF EXISTINGSEAWALL
TOE OFEXISTINGSEAWALL
TOP OFEXISTINGSEAWALL
BEACH ACCESS(PRIVATELY BUILT)
SEAWALL 1 SEAWALL 2
HAT
MHWS
HAT
MHWS
NOTES1. AERIAL IMAGE CIRCA 2011
LOCATION OF EXISTINGSURFACE FOR CROSSSECTION PURPOSES
EPROPOSEDPUBLICACCESS STAIR
PROPOSEDSEAWALL EXTENT
PROPOSED CRESTREPAIR EXTENT.REFER TO SECTION 4OF THE OPTIONASSESSMENT REPORT
CLIENT
DATE
TITLE
REVISION DETAILSDATEREV APPROVED
CHECKED
APPROVED
PROJECT
DRAWN
DESIGNED
PROJECT No. TYPE REVWBS DISC NUMBER
DRAWING No.
SCALE SIZE
A1
.
CONCEPT DESIGN SEAWALLTULLY HEADS
SEAWALL OPTION 1TYPICAL CROSS SECTIONS
243333 0000 DRG LA 0003 A
1:50PRELIMINARY
NOT FOR CONSTRUCTION
S.LEMON
J.FARNES
A 15.12.14 ISSUED FOR CLIENT REVIEW GC
Filen
ame:
Plot
Date:
Offic
e:P:
\MRN
\2433
33_C
ASSO
WAR
YCOA
STSE
AWAL
LS\3
PROJ
ECT
DELIV
ERY\
CADD
\DRA
WIN
GS\24
3333
-000
0-DR
G-LA
-000
3.DW
G15
/12/20
14 2:
37:51
PM
AUBN
E
1. REFER DRG. LA-0001 FOR NOTES.2. EXISTING SURFACE VARIES. REFER DRG.
LA-0002 FOR LOCATION OF EXISTINGSURFACE SHOWN ON OPTION SECTIONS.
3. ALL LEVELS IN METRES TO AHD.4. ALL DIMENSIONS IN MILLIMETRES UNO.
NOTES:
EXISTING ROCK ARMOUR TO BERELOCATED. LAYER THICKNESSSHALL BE GREATER THAN1000mm. ALL HOLES TO BE FILLED
ADDITIONAL ROCKSM 50 = 300kgTHICKNESS = 1000mm (MIN.)
OPTION 1 - VARIANT BREVETMENT REPAIR WITH SURFACE TOE
SECTION XB-1:50
OPTION 1 - VARIANT AREVETMENT REPAIR WITH BURIED TOE
SECTION XA-1:50
ARMOUR ROCKSM 50 = 3000kgTHICKNESS = 2100mm (MIN.)
RL 0.05 (MSL)
RL -1.68 (LAT)
RL -0.89 (MLWS)
RL 1.94 (HAT)
RL 1.04 (MHWS)
RL 0.00 (AHD)
ARMOUR ROCKSM 50 = 3000kgTHICKNESS = 2100mm (MIN.)
ADDITIONAL ROCKSM 50 = 300kgTHICKNESS = 1000mm (MIN.)
EXISTING ROCK ARMOUR TO BERELOCATED. LAYER THICKNESSSHALL BE GREATER THAN1000mm. ALL HOLES TO BE FILLED
1.5
1
1
1RL 3.50(APPROX.)
RL 3.50(APPROX.)
1.5
1
RL 2.55DESIGN WATER LEVEL
RL 2.55DESIGNWATER LEVEL
RL 4.00 (NOM.)
CREST ROCKSM 50 = 6000kg APPROX.PATTERN PLACED
RL 4.00 (NOM.)
EXISTING ROCKPROTECTION/SEAWALL TO BECONFIRMED BY SURVEY
EXISTING SURFACE(REF. NOTE 2)
EXISTING SURFACE (REF. NOTE 2)
OPTION 1 - VARIANT CTOTAL ROCK REVETMENT RECONSTRUCTION
SECTION XC-1:50
CREST ROCKSM 50 = 6000kg APPROX.PATTERN PLACED
RL 3.50(APPROX.)
RL 4.00 (NOM.)1.5
1
1
1
SECONDARY ARMOURM 50 = 300kgTHICKNESS = 1000mm (MIN.)
ARMOUR ROCKSM 50 = 3000kgTHICKNESS = 2100mm (MIN.)
3200 (MIN.)1.5
1GEOTEXTILEELCOMAX 600R(OR EQUIVALENT)
NEW PROFILE
CREST ROCKSM 50 = 6000kg APPROX.PATTERN PLACED
RL 0.05 (MSL)
RL -1.68 (LAT)
RL -0.89 (MLWS)
RL 1.94 (HAT)
RL 1.04 (MHWS)
RL 0.00 (AHD)
RL 2.55DESIGN WATER LEVEL
EXISTING SURFACE (REF. NOTE 2)
3200 (MIN.)
3200 (MIN.)
2400
600 18
00
CLIENT
DATE
TITLE
REVISION DETAILSDATEREV APPROVED
CHECKED
APPROVED
PROJECT
DRAWN
DESIGNED
PROJECT No. TYPE REVWBS DISC NUMBER
DRAWING No.
SCALE SIZE
A1
.
CONCEPT DESIGN SEAWALLTULLY HEADS
SEAWALL OPTIONS 2 & 3TYPICAL CROSS SECTIONS
243333 0000 DRG LA 0004 A
1:50PRELIMINARY
NOT FOR CONSTRUCTION
S.LEMON
J.FARNES
A 15.12.14 ISSUED FOR CLIENT REVIEW GC
Filen
ame:
Plot
Date:
Offic
e:P:
\MRN
\2433
33_C
ASSO
WAR
YCOA
STSE
AWAL
LS\3
PROJ
ECT
DELIV
ERY\
CADD
\DRA
WIN
GS\24
3333
-000
0-DR
G-LA
-000
4.DW
G15
/12/20
14 12
:55:54
PM
AUBN
E
1. REFER DRG. LA-0001 FOR NOTES.2. EXISTING SURFACE VARIES. REFER DRG.
LA-0002 FOR LOCATION OF EXISTINGSURFACE SHOWN ON OPTION SECTIONS.
3. ALL LEVELS IN METRES TO AHD.4. ALL DIMENSIONS IN MILLIMETRES UNO.
OPTION 2GEOCONTAINER SEAWALL
RL 0.05 (MSL)
RL -1.68 (LAT)
RL -0.89 (MLWS)
RL 1.94 (HAT)
RL 1.04 (MHWS)
RL 0.00 (AHD)
RL 2.55DESIGN WATER LEVEL
REINFORCEDCONCRETE CREST
EXISTING SURFACE (REF. NOTE 2)
NEW PROFILE
GEOTEXTILE ELCOMAX600R (OR EQUIVALENT)
2.5m³ ELCOROCKGEOCONTAINERS
1.5
SECTION A-1:50
1
OPTION 3REINFORCED CONCRETE STEPPED SEAWALL
SECTION C-1:50
ENGINEEREDFILL
TYP. 2.5m³ GEOCONTAINER DIMENSIONS
RL 3.50(APPROX.)
RL 4.00 (NOM.)
1.5
1
ARMOUR ROCKSM 50 = 3000kgTHICKNESS = 2100mm (MIN.)
710TYP.
380
TYP.
REINFORCED CONCRETESEAWALL
ROCK SCOURPROTECTION
ENGINEEREDFILL
ROCK SIZE TO BECONFIRMED PENDINGGEOTECHNICALINVESTIGATION.
PRECAST REINFORCEDCONCRETE TOE
RL 2.55DESIGN WATER LEVEL
1
1
RL 3.50(APPROX.)
1
1
EXISTING SURFACE (REF. NOTE 2)
TURFSURFACING
NOTES:
MOISTUREBARRIER
CLIENT
DATE
TITLE
REVISION DETAILSDATEREV APPROVED
CHECKED
APPROVED
PROJECT
DRAWN
DESIGNED
PROJECT No. TYPE REVWBS DISC NUMBER
DRAWING No.
SCALE SIZE
A1
.
CONCEPT DESIGN SEAWALLTULLY HEADS
SEAWALL OPTIONSPUBLIC ACCESS STAIR
243333 0000 DRG LA 0005 A
1:50PRELIMINARY
NOT FOR CONSTRUCTION
S.LEMON
J.FARNES
A 15.12.14 ISSUED FOR CLIENT REVIEW GC
Filen
ame:
Plot
Date:
Offic
e:P:
\MRN
\2433
33_C
ASSO
WAR
YCOA
STSE
AWAL
LS\3
PROJ
ECT
DELIV
ERY\
CADD
\DRA
WIN
GS\24
3333
-000
0-DR
G-LA
-000
5.DW
G15
/12/20
14 12
:44:56
PM
AUBN
E
PROPOSED PUBLIC ACCESS STAIRSECTION ELA-00021:50
RL 0.05 (MSL)
RL -1.68 (LAT)
RL -0.89 (MLWS)
RL 1.94 (HAT)
RL 1.04 (MHWS)
RL 0.00 (AHD)
RL 2.55DESIGN WATER LEVEL
RL 3.50(APPROX.)
REFER SECTION D ONDRG. LA-0003 FOR TYPICALROCK SEAWALL DETAILS.
ADDITIONAL ROCK ANDGEOTEXTILE BELOWCONCRETE STAIR BASE
RL 4.65 NOM.
DRIVEN PILES(8 TOTAL)
TIMBER ACCESS STAIRSAND HANDRAILING (TOB.C.A. STANDARDS)
1. REFER DRG. LA-0001 FOR NOTES.2. EXISTING SURFACE VARIES. REFER DRG.
LA-0002 FOR LOCATION OF EXISTINGSURFACE SHOWN ON OPTION SECTIONS.
3. ALL LEVELS IN METRES TO AHD.4. ALL DIMENSIONS IN MILLIMETRES UNO.
NOTES:
EXISTING SURFACE(REF. NOTE 2)
Appendix C Approved Plans of Development – existing Seawall 1 and Seawall 2 C1 – Sanctioned Plans under Section 86 of the Harbours Act 1955 (repealed) prepared by GHD, dated 1992 – Seawall 1
C2 – Sanctioned Plans under Section 86 of the Harbours Act 1955 (repealed) prepared by the former Cardwell Shire Council, dated 1996 – Extension of Seawall 1
C3 – Sanctioned Plans under Development Permit for Operational Works that are Prescribed Tidal Works prepared by International Coastal Management, dated December 2006 (Permit IPCC00419906C11) – Seawall 2
Page 1
15 December 2006
Decision Notice APPROVAL
Integrated Planning Act 1997 S 3.5.15
D/A146/06
John Pettigrew (Deputy Director, Engineering Services)
07 40439101
Cardwell Shire Council
PO Box 401
TULLY QLD 4854
Dear Sir
RE: Application for Prescribed Tidal Works (Installation of a Rock Wall)
Taylor Street, Tully Heads (Reserve)
Lot 10 on CWL802853; Parish of Rockingham
I wish to advise that, on 14 December 2006, the above development application was -
� approved in full;
OR
� approved in part;
OR
� approved in full with conditions. The conditions relevant to this approval are attached.
These conditions are clearly identified to indicate whether the assessment manager or a concurrence agency imposed them;
OR
� approved in part with conditions.
416348:JWP/tn
Planning Services 4043 9101
4068 1772
Page 2
1. Details of the approval -
The following type of approval has been issued - Development Permit
Preliminary Approval
• Carrying out building work (assessable against the Standard Building Regulation 1993)
• Reconfiguring a lot
• Material change of use made assessable by the planning scheme;
• Associated work made assessable by the planning scheme -
• building works
• operational works
• Material change of use for an environmentally relevant activity
• Material change of use for a licensed brothel
• Material change of use on strategic port land, inconsistent with an approved land use plan
• Making a material change of use for a major hazard facility or possible major hazard facility
• Planning scheme works -
• building works
• operational works
• Operational works for the clearing of native vegetation on land protected under the Vegetation Management Act
• Operational work for a referable dam or that will increase the storage capacity of a referable dam by more than 10%
• Operational work for tidal work or work within a coastal management district
�
• Development for removing quarry material from a watercourse or lake (if an allocation notice is required under the Water Act 2000)
• Operational work that allow taking, or interfering with, water (other than using a water truck to pump water)
• Development in a heritage registered place -
• Building work assessable against the Standard Building Regulation 1993
• Building work assessable against the planning scheme
• Material change of use
• Reconfiguring a lot
• Operational work
2. The relevant period -
�the standard relevancy periods stated in section 3.5.21 of IPA apply to each aspect of
development in this approval;
Page 3
OR
� An alternative relevant period.
3. The approved plans -
The approved plans and / or documents for this development approval are listed in the following table -
Plan / Document
Number
Plan / Document Name Date
TH-A3-01 Location & Site Plan – Erosion Protection Works prepared by
International Coastal Management
1/3/2006
TH-A3-02 Plan – Erosion Protection Works prepared by International Coastal
Management
1/3/2006
TH-A3-03 X-Section – Erosion Protection Works prepared by International Coastal
Management
1/3/2006
4. Other necessary development permits – Nil.
5. Codes for self-assessable development – Not applicable.
6. Superseded planning scheme – Not applicable.
7. Preliminary approval overriding the planning scheme – Not applicable.
8. IDAS referral agencies -
The IDAS referral agencies applicable to this application are –
A. Referrals - triggered by building work assessable against the Standard Building Regulation 1993 – Nil.
B. Referrals – triggered by other assessable development under schedule 8 of the IPA
OPERATIONAL WORK
Operational work… Name of agency Status Address
1. For filling or excavation (not associated with reconfiguration) impacting on a State-
controlled road
Dept. of Main Roads � Concurrence
� Advice
2. For clearing native
vegetation
Dept. of Natural
Resources & Mines
Concurrence
Page 4
Operational work… Name of agency Status Address
3. That allows taking or interfering with water
under the Water Act 2000
Dept. of Natural Resources & Mines
Concurrence
4. Controlling the flow of water in drainage and
embankment areas
Dept. of Natural Resources & Mines
Concurrence
5. For a referable dam or that
will increase the storage of a referable dam by more than
10%
Dept. of Natural
Resources, Mines & Energy
Concurrence
� 6. That is tidal work other than
Prescribed Tidal Work in a Canal.
Environmental Protection Agency
�Concurrence Cairns District Office
(EPA)
PO Box 2066
CAIRNS QLD 4870
7. Within a coastal management district, that
is the disposing of dredge
spoil or other solid waste material in tidal water, other
than under an allocation notice under the Coastal Protection and Management Act 1995
Environmental Protection Agency &
Qld Transport
Concurrence
8. Within a coastal
management district, for draining or allowing drainage
or flow of water or other matter across State coastal
lands above high water mark
Environmental
Protection Agency
Concurrence
9. Within a coastal management district, in a
watercourse and not assessable under schedule 8,
part 3, items 3B and 3C of the IPA
Environmental Protection Agency
Concurrence
10. Within a coastal management district, that is reclaiming
land under tidal water
Environmental Protection Agency
and Qld Transport
Concurrence
11. Within a coastal management district, that
is constructing an artificial waterway associated with
reconfiguration
Environmental Protection Agency
and Qld Transport
Concurrence
Page 5
Operational work… Name of agency Status Address
12. Within a coastal management district, that
is constructing an artificial waterway not associated with
reconfiguration, on land other
than State coastal land, above high water mark if the
surface area of water in the waterway is at lease 5 000m2
Environmental Protection Agency
Concurrence
13. Within a coastal management district, that
is constructing a bank or
bund wall to establish a ponded pasture on land,
other than State coastal land, above high water mark
Environmental Protection Agency
Concurrence
14. Within a coastal management district, that
is removing or interfering
with coastal dunes on land other than State coastal land,
that is in an erosion prone area and above high water
mark.
Environmental Protection Agency
Concurrence
15. That is tidal work that involves a marina with
more than 6 vessel berths
Queensland Fire and Rescue Service
Advice
ALL ASPECTS OF DEVELOPMENT
Development… Name of agency Status Address
16. Below high water mark and within the limits of a port
The Port Authority for the land
� Concurrence
� Advice
17. For the removal of quarry material if an allocation
notice is required under the
Water Act 2000
Environmental Protection Agency
Concurrence
18. In a heritage registered
place
Queensland Heritage
Council
Concurrence
19. For a mobile and
temporary environmentally relevant
activities (ERA)
Environmental
Protection Agency
Concurrence
C. Referrals – triggered by the assessment of the application against a local government planning instrument – Nil.
Page 6
9. Submissions -
The application was not subject to public notification and therefore no submissions were received.
10. Appeal rights -
Attached is an extract from the Integrated Planning Act 1997 which details your appeal rights regarding this decision.
11. When the development approval takes effect -
This development approval takes effect -
• from the time the decision notice is given, if there is no submitter and the applicant does not appeal the decision to the court
OR
• when the submitter’s appeal period ends, if there is a submitter and the applicant does not appeal the decision to the court
OR
• subject to the decision of the court, when the appeal is finally decided, if an appeal is made to the court.
This approval will lapse unless substantially started within the above stated currency periods (refer to sections 3.5.19 and 3.5.20 of IPA for further details).
If you wish to discuss this matter further, please contact Council’s Deputy Director, Engineering Services, Mr John Pettigrew, on the above telephone number.
Yours faithfully MARK KELLEHER CHIEF EXECUTIVE OFFICER cc: Referral agency Environmental Protection Agency Cairns District Office PO Box 2066 CAIRNS QLD 4870
Page 7
ASSESSMENT MANAGER’S CONDITIONS:
1. Works are to be performed generally in accordance with plans dated 1 March 2006 and documentation submitted to Council on 15 May 2006 by International Coastal Management all relating to Development Application No. 146/06.
2. Prior to the commencement of any construction, the Design Engineers must submit certification that the design complies with all requirements of the “IDAS Code for Development Applications for Prescribed Tidal Works”.
Concurrence Agency Conditions:
Prescribed Tidal Work Agency Interest: Coastal - structures
EPA Permit Number: IPCC00419906C11
Assessment Manager reference: 146/06 Date application received by EPA: 02-JUN-2006 Permit Type: Concurrence Response for Operational
Work
Decision: Granted in full with conditions Relevant Laws and Policies: Coastal Protection and Management Act
1995 and any subordinate legislation.
Jurisdiction: Item 9 in Table 2 of Schedule 2 of the
Integrated Planning Regulation 1998.
Development Description
Property Lot/Plan Aspect of Development
Carron Esplanade, Lot 10 Plan CWL802853 Prescribed Tidal Work -
Tully Heads and adjacent to Lot 1 and Rock Revetment 2 RP865399.
CONDITIONS OF APPROVAL: (A1C1) All works are to be constructed in accordance with the attached
approved drawings listed in the approved plans section in the notice
attached to this concurrence agency response. (A1C2) Record, compile and keep all monitoring results required by this
document and present this information to the Environmental Protection
Agency upon request. (A1C3) Sand nourishment to cover the rock revetment must be
commenced immediately following the completion of the rock revetment and must be completed within thirty (30) days. The sand nourishment to
Page 8
be undertaken to cover the rock revetment must be to a minimum level of RL2.0 metres (Australian Height Datum), and maintained to this level, with a profile slope 1 on 4.
(A1C4) If the erosion scarp at the pocket beach adjacent to the Public
Park Reserve (Lot 9 on T9483) advances onto this Reserve, sand nourishment must be immediately undertaken and maintained to the
profile as shown on Cardwell Shire Council drawing 3811, Sh. 2 of 2, and be completed within thirty (30) days. The end walls (wings) of the rock
revetment must be covered with sand at all times to ensure erosion does not progress in behind the rock revetment.
(A1C5) Monitoring (beach profile surveying) must be undertaken at a
distance of 25 and 50 metres north of the northern end wall of the revetment. Such monitoring must be undertaken annually, and this
monitoring information be made available to the EPA upon request.
(A1C6) All temporary works associated with the construction of the revetment wall are to be removed from the site at the completion of the
works and all wastes shall be collected from the site by the permittee and
disposed of at a licensed waste facility. (A1C7) All reasonable and practicable measures must be taken to
prevent contamination of the beach and coastal waters as a result of silt run-off, oil and grease spills from machinery and concrete truck washout.
Concrete agitator wash out must only be conducted in a specified area to facilitate the removal of waste concrete from the area to landfill.
Wastewater from cleaning equipment must not be discharged directly or in-directly to any watercourses or stormwater systems.
(A1C8) No sand is to be removed from the coastal dune system within the erosion prone area or coastal management district. Material identified
as untreated Potential or Actual Acid Sulfate Soil is excluded from this
requirement provided the material is sufficiently treated to prevent the release of contaminants to water.
(A1C9) All organically enriched sand removed from the top layer
(topsoil) within the proposed development area must be stockpiled separately prior to excavation and used landward of the crest of the revetment wall. On completion of the works any excess organically
enriched sand material may be removed from the site. The area landward from the crest of the revetment wall must be maintained as a pedestrian
and maintenance access.
(A1C10) Acid sulfate soils must be managed such that contaminants are not directly or indirectly released from the works to any waters.
Page 9
(A1C11) The sand being placed on the beach shall be clean and free of silt, clay, organic material or any other deleterious substance and must be of a grain size compatible with the existing beach sand.
(A1C12) The Cardwell Shire Council shall be responsible for the ongoing
maintenance of the revetment wall and the removal of any debris from the beach as a result of any damage to the wall.
DEFINITIONS:
Words and phrases used throughout this permit are defined below. Where a definition for a term used in this permit is sought and the term is not defied within this permit the definitions provided in the relevant legislation shall be used.
“administering authority” means the Environmental Protection Agency or its successor.
“approval” means ‘notice of development application decision’ or ‘notice of
concurrence agency response’ under the Integrated Planning Act 1997. “approved plans” means the plans and documents listed in the approved plans
section in the notice attached to this development approval. “artifical waterway” means an artificial channel, lake or other body of water.
Artificial waterway includes –
• An artificial channel that is formed because the land has been reclaimed from
tidal water and is intended to allow boating access to allotments on subdivided land;
• Other artificial channels subject to the ebb and flow of the tide; and
• Any additions or alterations to an artificial waterway. “canal” means an artificial waterway surrendered to the State. A canal is an artificial
waterway connected, or intended to be connected, to tidal water; and from which
boating access to the tidal water is not hindered by a lock, weir or similar structure. “coastal dune” means a ridge or hillock of sand or other material on the coast and
built up by the wind.
“dredge spoil” means material taken from the bed or banks of waters by using dredging equipment or other equipment designed for use in extraction of earthen material.
“Environmental Protection Agency” means the department or agency (whatever called) administering the Coastal Protection and Management Act 1995 or the Environmental Protection Act 1994. “erosion prone area” means an area declared to be an erosion prone area under section 70(1) of the Coastal Protection and Management Act 1995.
“high water mark” means the ordinary high water mark at spring tides.
Page 10
“ponded pasture” means the ordinary high water mark at spring tides.
“quarry material” means material on State coastal land, other than a mineral within the meaning of any Act relating to mining. Material includes for example
stone, gravel, rock, clay, mud, silt and soil, unless it is removed from a culvert, stormwater drain or other drainage infrastructure as waste material.
“site” means land or tidal waters on or in which it is proposed to carry out the
development approved under this development approval. “tidal water” means the sea and any part of a harbour or watercourse ordinarily
within the ebb and flow of the tide at spring tides.
“watercourse” means a river, creek or stream in which water flows permanently or
intermittently –
• In a natural channel, whether artificially improved or not; or
• In an artificial channel that has changed the course of the watercourse.
“waters” includes river, stream, lake, lagoon, pond, swamp, wetland, unconfined surface water, unconfined water natural or artificial watercourse, bed and bank of any waters, dams, non-tidal or tidal waters (including the sea), stormwater
channel, stormwater drain, roadside gutter, stormwater run-off, and groundwater and any part thereof.
“works” or “operation” means the development approved under this development
approval.
“you” means the holder of this development approval or owner/occupier of the land which is the subject of this development approval.
APPROVED PLANS:
Plan/Document No.
Plan/Document Name Date
TH-A3-01 Location and Site Plan 1/03/06
TH-A3-02 Rev.B Plan 1/03/06
TH-A3-03 Rev.A X-Section 1/03/06
3811 Cross Section Adjacent to pocket beach (Lot 9 T9483)
Showing Profile to be
maintained by council.
Aug 06
End of Conditions.
Aurecon Australasia Pty Ltd
ABN 54 005 139 873
Level 1, 242 Mulgrave Road Cairns QLD 4870
PO Box 7625 Cairns QLD 4870 Australia
T +61 7 4019 6400
F +61 7 4051 2540
W aurecongroup.com
Aurecon offices are located in: Angola, Australia, Botswana, Chile, China, Ethiopia, Ghana, Hong Kong, Indonesia, Lesotho, Libya, Malawi, Mozambique, Namibia, New Zealand, Nigeria, Philippines, Qatar, Singapore, South Africa, Swaziland, Tanzania, Thailand, Uganda, United Arab Emirates, Vietnam.