Preferred destination for setting up solar projects · 5 LHS 500 MW (Progress) At recently...
Transcript of Preferred destination for setting up solar projects · 5 LHS 500 MW (Progress) At recently...
1
Solar Park from Saurya UrjaPreferred destination for setting up solar projects
State‐of‐the‐art infrastructure for Solar Project Development
RHS 500 MW
Power Purchaser: Uttar Pradesh Government | Evacuation: PGCIL (CTU)
2
Joint Venture Agreement: Snapshot
Joint Venture signed between Government of Rajasthan (GoR) and IL&FS Energy Development Company Limited(IEDCL) to form a 50:50 JV in the name of Saurya Urja Company of Rajasthan Limited (SURAJ) on October 28, 2014.
Company Incorporated on April 07, 2015.
Mandate to develop 5000 MW of Solar Parks in Rajasthan.
Main Purpose:
Provide land to Developers of Solar Power Producers, Implement Infrastructure Facilities in Solar Park, Facilitate CTU and/or STU connectivity, Carry out O&M of the Solar Park
Board of Directors: Three (3) from GoR and Three (3) from IEDCL and Two (2) Independent Directors.
3
1000 MW Bhadla – III Solar Park: The Company & Management
Saurya Urja Company of Rajasthan Limited (SURAJ) Management
SURAJ is promoted jointly by Government of Rajasthanand IL&FS Energy, the IL&FS Group’s energy arm. IL&FSis a pioneer infrastructure developer in the countrycutting across sectors like Roads, Power, Water, Ports,Tourism, SEZs, Industrial Parks and sectors likeEducation and Skill development.
SURAJ a 50:50 Joint Venture Company of Govt. ofRajasthan and IL&FS Energy and is mandated todevelop Solar Parks of 5000 MW capacity in the stateof Rajasthan. Bhadla–III 1000 MW Solar Power Park isthe first in series of the solar parks to be developed bythe company.
Board of Directors Chief Secretary, GoR, Chairman Secretary Revenue, GoR Managing Director, RREC, GoR Mr. K Ramchand, IL&FS Mr. Haziq Beg, IL&FS Energy Mr. Keshav Prasad, IL&FS Energy
Independent Directors Mr. Arun Kumar Purwar, former CMD, SBI Mr. Bhanu Bhushan, former member, CERC
Senior Management Mr. S Prakash, Chief Executive Officer Mr. Bibhu Biswal, Vice President
4
LHS 500 MW(Progress | July 2017)
5
LHS 500 MW (Progress)
At recently concluded reverse auction conducted by SECI on May 11, 2017, M/s Acme Solar Holdings Pvt. Ltd. wasawarded 200 MW capacity at Rs. 2.44 per kWh and M/s SBG Cleantech One Ltd. was awarded 300 MW capacity at Rs.2.45 per kWh
As per current schedule, Saurya Urja would achieve substantial completion of all the infrastructure for LHS by December,2017.
The above delivery schedule would enable the Solar Project Developers (SPDs) to complete the project ahead of theircommitted schedule under the PPA.
6
RHS 500 MW(Salient Features)
7
1000 MW Bhadla – III Solar Park: Snapshot
Item Details
Location: Bhadla – III, Bap, District Jodhpur, Rajasthan27°28'53.9"N 71°59'26.1"E27.481632, 71.990598
Location Advantages: High Solar Radiation (GHI: 1890 W/m2), (300‐330 Clear Sunny Days)
Nearest NH: NH 15 (45 Kms)
Nearest Railway Station: Phalodi (80 Kms)
Nearest Airport: Jodhpur (230 Kms)
Total Area for 500 MW: Minimum 1000 Hectares
Land Classification: 100% Govt. Land
Accessibility: Well developed & connected Road Network up to the Park.
8
1000 MW Bhadla – III Solar Park: Comparison
State Monthly Averaged Direct Normal Radiation (kWh/m2/day)
Rajasthan (Latitude 27.658, Longitude 72.144) 5.60
Madhya Pradesh(Latitude 22.847, Longitude 81.135) 5.27
Andhra Pradesh (Latitude 14.55, Longitude 78.053) 5.17
Karnataka (Latitude 13.975, Longitude 76.098) 5.04
Source: NREL (India Solar Resource), NASA (Surface Meteorology and Solar Energy)
Expected CUF at the Bhadla – III site: 21 – 22 %
9
1000 MW Bhadla – III Solar Park: Master Plan: Overview
Item Details
Project Size: 1000 MW
Division: Park Divided into LHS and RHS
LHS: 500 MW
RHS: 500 MW
10
RHS 500 MW | Master Plan
Details
RHS Divided in 5 Plots of 100 MWac Each
Detailed Land Use given at the next slide
11
RHS 500 MW | Land Use
AREA STATEMENT ‐ RHS
# DESCRIPTION UNIT R1 R2 R3 R4 R5 TOTAL
1 Power Generation MW 100 100 100 100 100 500
2 Minimum Plot Area* Hectares 200 200 200 200 200 1000
*Note: Based on 2 Ha/MW
12
1000 MW Bhadla – III Solar Park: Land Details
# Land Details
1 Master Lease agreement has been signed between GoR and Saurya Urja on Nov 18, 2015.
2 A Sub‐Lease Agreement to be signed between SPD and Saurya Urja for Project Implementation within 15 days ofsigning the ISA.
3 Term of Sub‐Lease Agreement: The lease term shall be of 27 Years from the date of execution of the PPA.
4 Land would be handed over on as is where is basis.
5 Soil Resistivity Report/Geo‐Technical Report & Water Test Report (IGC) has been submitted to SECI and may bedownloaded from SECI’s TCIL Portal.
13
RHS 500 MW | Power Evacuation & Metering
14
Essential Solar Park Facilities
15
Essential Solar Park Facilities | 220/33 kV Pooling Sub‐Station
220/33 kV Pooling Sub‐Station
Brief Scope: 220/33 kV PSS for Pooling & Transmission of 500MW Power (5 x 125 MVA Transformers) to PGCIL765/400/220 kV Sub‐Station.
Status: Contractor ‐M/s GE T&D – Finalized.
Expected Completion: August 2018.
16
Essential Solar Park Facilities | 220 kV Transmission Lines
220 KV Transmission Lines
Brief Scope: 220 kV Transmission Lines to transfer of powerfrom 220/33 kV Pooling Sub‐Station (PSS) to 765/400/220 kVPGCIL S/S. (D/C AL‐59 Lines Equivalent to Moose, 9 Kms)
Status: Contract Awarded to M/s Karnimata ConstructionCompany (KMCC) in November 2016, Work in Progress.
Expected Completion: January, 2018.
Approvals & Clearances: Route Survey Completed., Section 68and 164 Granted.
17
Essential Solar Park Facilities | Connectivity to 765/400/220 kV PGCIL S/S
765/400/220 kV PGCIL S/S
Brief Scope: To provide connectivity of the Solar Park withthe CTU network. Commercial Billing shall be done at the220 kV side of the PGCIL’s 765/400/220 kV S/S andassociated transmission system
Status: Contract Awarded, Work in Progress.
Expected Completion: October, 2018
Approvals & Clearances: Bay Allocation to be Done.
18
Essential Solar Park Facilities | PGCIL Network Map
19
Essential Solar Park Facilities | Common Facilities & Facility Complex
Infrastructure Scope Time Lines
Common Facilities & Facility Complex (Located in LHS Area)
Guest House (4 Double OccupancyBedrooms and 2 Suites, Approx.5000 Sq. Ft)
Facility Complex (Medical andTraining Complex) [2000 Total Sq. FtSpace, 350 Sq. Ft Training Hall,Canteen Facilities for 20 Persons ata time, Medical 125 Sq. Ft]
Security Office at Entrance.
February2018
20
Essential Solar Park Facilities | Water System
Head Scope Time Lines
Water System
Proposed 175 KLD supply from RREC for1000 MW 25 KLD to be used in commonservices. 15 KLD per 100 MWac Plotproposed to be allotted.
Single Point Connection at eachIndividual Solar Plots of 100 MWthrough common pipeline.
Each SPD is to build it’s own Sump Tankfor Storage and Distribution of waterwithin the Solar Project.
SPD to opt for water less cleaningservice in case the above supply isinsufficient
June 2018
21
Essential Solar Park Facilities | Access Roads & Fencing around Dhanis
Infrastructure Scope
Access Roads
Access roads to all the plots along with street lighting.
Approx. 4 Kms total length. 7 Mtrs wide Carriage Way, GSB Road.
Fencing around Dhanis Pre‐Cast Fencing around the resettlement area.
22
1000 MW Bhadla – III Solar Park: Local Area Development (LAD)
LAD Studies & Strategy LAD Action Plan
Study conducted to assess/understand the needs of thelocal community and the impact of development of solarpark in the area.
Following are the key areas of interest to the locals:
Alternative Livelihood | Education Infrastructure | VillageInfrastructure | Water Availability | Health Services |Access to Government Programs
Imperative to address the interests of the localpopulation for active community participation in thedevelopment of the solar park.
Saurya Urja in partnership with the SPDs shall ensure thefollowing for the locals under CSR activities:
Upgradation of the Infrastructure around the solar park.
Water availability & Health Services.
Training & Development of the Locals in the relevant skill sets of that of the Solar Plants/Parks.
23
Mandatory Additional Facilities
24
Mandatory Additional Facilities | Cable Trays & Structure
Infrastructure Scope
Compulsory Facilities
Cable Trays & Structure
Installation of Cable Trays &Structure for laying of 33 kV Powercables & OFCs from individual SPDplots to Pooling Sub‐Station
Charges As detailed in Summary of ChargesSlide
25
Mandatory Additional Facilities | Fencing & Patrol Roads with Street Lighting
Infrastructure Scope
Pre‐Cast Fencing &Patrol Roads with Street Lighting
Precast RCC fencing and patrol roads along the periphery of the park and street lighting.
Charges As detailed in Summary of ChargesSlide
26
Mandatory Additional Facilities | Weather Monitoring System (WMS) – 1
Concept
A central weather monitoring system for all the SPDs (LHS &RHS) of the park. Weather Data to be shared with SuccessfulBidders
Availability of Historical & Instantaneous Data
27
Mandatory Additional Facilities | Weather Monitoring System (WMS) – 2
Source : Bodana Weather Station
On Site Actual Weather Data is Now Available from Weather Monitoring Stations Installed at Site.
The data can be obtained at a nominal price.
Global Horizontal Insolation (1 Day) Ambient Temperature (1 Day) Wind Speed (1 Day)
Weather Monitoring System (Pyranometer, Pyrheliometer, Sensors for: Module Surface Temperature Measurement, Ambient Temperature Measurement, Wind Speed Measurement, Wind Direction Measurement, Soiling Monitoring Station) Installed at the Solar Park since June 14, 2017.
Custom Reports as per the Requirements.
Currently 1 No. WMS + 1 No. Soil Monitoring Station is Installed at Site | To cover thewhole Solar Park 2 Nos. more WMS are envisaged to be installed.
Remote Monitoring | Accessibility to Live Data for Successful Bidders.
Instantaneous Data
28
Mandatory Additional Facilities | Forecasting & Scheduling – 1
Concept
As per CERC ‘Procedure for implementation of the framework on Forecasting, scheduling and imbalance handling for renewable energy (re) generating stations Including power parks based on wind and solar at Inter‐state level’dated March 03, 2017:
Clause 7.2 of Clause 7 (Connectivity) states that:
The SPPD shall act as the nodal and accountable entity at the connection point. SPPD shall be responsible for sending the SCADA data to the RLDC and to the Renewable Energy Management Centre (REMC).
Saurya Urja being the SPPD for Bhadla – III shall undertake the responsibility for Forecasting & Scheduling as per the provisions of the CERC Procedure dated March 03, 2017.
29
Mandatory Additional Facilities | Forecasting & Scheduling – 2
Feature Details
Forecasting & Scheduling
Forecasting & Scheduling at Park (500 MW) level using latest analytical models includes real timedata from weather stations, coordination with SLDC/RLDC.
Relationship
Saurya Urja shall facilitate Forecasting & Scheduling for the entire 500 MW fed to CTU SPD shall be responsible for sharing data required on 15 Mins basis and appropriate annual
charges. SPD shall be responsible for the Deviation Settlement Mechanism (DSM) and penalties ifany.
Current Scenario CERC already issued order mandating solar projects to do Forecasting & Scheduling. Provision of Penalties for deviation beyond +/‐ 15% variation.
Benefits Deviation from schedule (actual vs scheduled generation) to be minimized resulting in low
deviation charges/penalty due to aggregation at the overall level Cost Advantages due to Economies of Scale of operation
Charges Commercial Model & Customer Term Sheets to be Shared in Due Course.
30
Mandatory Additional Facilities | Alternate Module Cleaning – 1
Concept
Availability of water supply in the solar parknot sufficient for efficient cleaning of solarpanels by water manually.
Adequate water supply will always be aconstraint in the desert region.
This will lead to higher soiling losses in thesolar plant, less efficient plants means loss ofrevenue.
Hence, alternate cleaning technologies needto be explored which provides efficientautomated cleaning without the dependencyon water.
31
Mandatory Additional Facilities | Alternate Module Cleaning – 2
Feature Details
Water Less Module Cleaning
Water Less Module Cleaning provides high efficiency by rail mounted, self cleaning robots withspecialized brushes for cleaning the surface.
Relationship Saurya Urja would provide water cleaning service across the park as integrated service provider SPD shall be responsible for fulfilling of the installing appropriate panel mounting structures and
sharing layout
Benefits
Maximise revenue generation Benefit from economies of scale Remote management ‐monitor, manage, reporting and optimize performance Protection of AR Coating Immediate recovery post dust storm
Next Steps To be implemented on a park wide basis for maximum benefits. Commercial Model & CustomerTerm Sheet to be Shared in Due Course.
32
1000 MW Bhadla – III Solar Park: O&M Services
O&M Services
Saurya Urja would be responsible for operation and maintenance of the assets created.
Checking, Repairing and Maintenance including preventive and corrective maintenance shall be carried out for the following:
220/33 kV Pooling Sub‐Stations Common Facilities (Guest House, Facility Complex Etc.) 220 kV Transmission Lines Water System Security Office at Entrance Access Road along with Lighting Cable Trays & Structure Pre‐Cast RCC Fencing & Patrol Road along with Street Lighting
33
1000 MW Bhadla – III Solar Park: Proposed Timelines
# Milestones Proposed Dates
(RHS)
1 Readiness for handing over plots to SPDs November 2017
2 Signing of Power Purchase Agreement (PPA) October 2017 (Expected)
3 Signing of Implementation and Support Agreement (ISA) 45 Days from the PPA
4 Signing of Sub‐Lease Agreement 15 Days from the ISA
5 Readiness of Power System for Evacuation from the Solar Park August 2018
6 Readiness of PGCIL Evacuation System October 2018
34
RHS 500 MW | Documents Downloads
Documents/Drawings that are not available on SECI’s TCIL Portal can be downloaded from the following link:
http://www.sauryaurja‐ilfs.com/resources.html
Respective files can be downloaded by clicking ‘Download’ next to it.
35
Optional Solar Park Facilities
36
Optional Solar Park Facilities | Master Control Center – 1
CEA Regulation on Connectivity – Draft
Regulations applicable for solar projects connected after 6 months of CEA final regulations.
Introduction of LVRT for solar generators – Generators to continue generating active power proportion to rated voltage during system voltage dips up to 15% for 300 ms till it reaches 85%
between 300 ms to 3 sec. Maximise reactive power till voltage starts recovering till 300 ms.
Introduction of HVRT for solar generators – Generators to remain connectedunder high voltage scenario ‐
Introduction of Frequency range for solar projects to respond For frequency variation <0.3 Hz – generator response (addl. real power) proportional to frequency deviation For frequency variation >0.3 Hz – generator required to provide immediate real power frequency response of
10% of maximum active power capacity within 1 sec. In case Energy storage systems used, during frequency below 49.7 Hz, generator frequency response to act
within 1 sec and to be maintained at least 10 min. Further, ramp rate control tolerance to be ±10%
Over Voltage Min time (sec)
1.3<V≤1.4 1
1.1<V≤1.3 3
V<1.1 Indefinitely
37
Optional Solar Park Facilities | Master Control Center – 2
CEA Regulation on Connectivity – Draft
Introduction of voltage regulation services – Generator to have a continuously variable, continuously acting, closed loop control Voltage Regulation System
(VRS) like AVR VRS set point should be adjustable in a range prescribed by SERC and by SLDC via SCADA VRS controller strategy to be based on Proportional plus Integral control actions with parallel reactive droop
compensation VRS to be calibrated such that change in reactive power will achieve 95% of its final value no later than 1 sec
with step change in voltage VRS to be in service as long as generator connected to grid irrespective of MW output including Nil generation VRS dead band not to exceed ±0.1%
Review of harmonics limits – Limits of voltage/current harmonics, point of harmonics measurement, method of harmonics measurement to
be in accordance with IEEE 519‐2014 standards Measuring & metering of harmonics shall be a continuous process with permanent meters complying to IEC
61000‐4‐30 class A capable of detecting direction of harmonics Measurement of power quality parameters voltage sag, swell, disruptions to be done every month
38
Optional Solar Park Facilities | Master Control Center – 3
Concept
Utilities to approve connectivity only pursuantto compliance to CEA Regulations
The concept is to have all the control &monitoring stations at one central location.
Monitoring and Control Work Stations shall beprovided to individual SPDs in one centrallocation having all the feeds from the solarpark (Eg. Weather Data, Battery StorageControl, Forecasting & Scheduling andInterface with SLDC/RLDC)
This helps in smooth interface management ofthe solar plants and as well as with Grid(STU/CTU), SLDC/RLDC.
39
Optional Solar Park Facilities | Master Control Center – 4Feature Details
Master Control Center (MCC)
MCC would be compatible with CEA Guidelines of Technical Standards for Connectivity to the GridRegulations, 2007 and its amendments and subsequent modifications.
Relationship Saurya Urja shall facilitate the technology selection, vendor arrangement/management,
implementation and maintenance on the site at Master Control Center. SPD shall be responsible for initial upfront charges and fulfilling the installation requirements.
Intended Benefits
Monitoring & Controlling of all plant SCADA from one location – regulation of Inverter Generation tomaintain Load‐Generation balance as per the requirements of Regulator/RLDC/SLDC.
SPDs do not have to interface with Regulators/RLDC/SLDC directly. Capex & Opex Savings and faster commissioning as Cost of Control Room and SCADA to SPDs
eliminated. Integrated yet scalable system. Single point management and single Database.
Next Steps Saurya Urja would carry out the above work provided all SPDs express interest. Charges to beintimated separately.
40
Saurya Urja | Business Pipeline | 2000 – 4000 MW
Land for Next 2000 MW of Solar Parks Identified.
Land Identified in the Districts of Jodhpur & Jaisalmer
Saurya Urja has Envisaged to Complete the Next 2000 MW Solar Parks before December 2019 (Free TransmissionDeadline)
IPPs can expect the same level of commitment from Saurya Urja for it’s upcoming Solar Parks.
41
1000 MW Bhadla – III Solar Park: Park Advantages
High Irradiation: More Generation
Assured CTU/STUConnectivity
Plug & Play
Pedigreed Promoters
Benefits from Economies of Scale
Lowest Cost of Generation
Ready to Generate Power in FY 2018‐19
World Class Facilities
INVEST WHERE ‘SURAJ’ SHINES
Lowest Solar Tariff of Rs. 2.44/KWh in India
42
1000 MW Bhadla – III Solar Park: Contact Details
Contact Details
For any Additional Information Related to the Project and for Site Visit(s), Please Contact the following Person:
Name:Mr. Bibhu BiswalContact No: +91‐9717322665 | 0141 – 4271512/514Email: [email protected]
43