Prefabricated structures

30
1 PRE FABRICATED MODULAR STRUCTURES GUIDED BY: SOUMYA MISS ASST PROFFESSOR, UKFCET, KOLLAM PRESENTED BY: FAIZAL.A.M 7 TH SEMESTER CIVIL ENGINEERING UKFCET, KOLLAM

description

 

Transcript of Prefabricated structures

Page 1: Prefabricated structures

1

PRE FABRICATEDMODULAR STRUCTURES

GUIDED BY: SOUMYA MISS ASST PROFFESSOR, UKFCET, KOLLAM

PRESENTED BY: FAIZAL.A.M 7TH SEMESTER CIVIL ENGINEERING UKFCET, KOLLAM

Page 2: Prefabricated structures

2

Contents Introduction Features Comparison Design concept Components Types of precast

system Design

consideration

Equipments Assembling scheduling Advantages Limitations Conclusion references

Page 3: Prefabricated structures

3

Introduction The concept of precast structures also

known as prefabricated/ modular structures.

The structural components are standardized and produced in plants in a location away from the building site.

Then transported to the site for assembly. The components are manufactured by

industrial methods based on mass production in order to build a large number of buildings in a short time at low cost.

Page 4: Prefabricated structures

4

FeaturesThe division and specialization of the

human workforce. The use of tools, machinery, and other

equipment, usually automated, in the production of standard, interchangeable parts and products.

Compared to site-cast concrete, precast concrete erection is faster and less affected by adverse weather conditions.

Plant casting allows increased efficiency, high quality control and greater control on finishes.

Page 5: Prefabricated structures

5

ComparisonSite-cast

no transportation the size limitation is

depending on the elevation capacity only

lower quality because directly affected by weather

proper, large free space required

Precast at plant transportation and

elevation capacity limits the size-

higher, industrialized quality – less affected by weather

no space requirement on the site for fabrication

unlimited opportunities of architectural appearance

option of standardized components

Page 6: Prefabricated structures

6

Design concept for precast concrete

buildingsThe design

concept of the precast buildings is based on

1.build ability.

2.economy 3.standardization of precast components.

Page 7: Prefabricated structures

7

Precast concrete structural elements

Precast slabs

Precast Beam & Girders

Page 8: Prefabricated structures

8

Precast Columns

Precast Walls

Page 9: Prefabricated structures

9

Precast stairs

Precast concrete StairsSteel plates supported on 2 steelbeams

Page 10: Prefabricated structures

10

Design considerations final position and loads transportation requirements – self load

and position during transportation storing requirements – self load and

position during storing – (avoid or store in the same position as it transported / built in)

lifting loads – distribution of lifting points – optimal way of lifting (selection of lifting and rigging tools)

vulnerable points (e.g. edges) – reduction of risk (e.g. rounded edges)

Page 11: Prefabricated structures

11

Types of pre cast system

1. Large-panel systems2. Frame systems3. Slab-column systems with walls4. Mixed systems

Page 12: Prefabricated structures

12

box-like structure.both vertical and

horizontal elements are load-bearing.

one-story high wall panels (cross-wall system / longitudinal wall system / two way system).

one-way or two way slabs.

1. Large-panel systems

Page 13: Prefabricated structures

13

2. Frame systems

Components are usually linear elements.

The beams are seated on corbels of the pillars usually with hinged-joints (rigid connection is also an option).

Joints are filled with concrete at the site.

Page 14: Prefabricated structures

14

3.Lift-slab systems - partially precast in plant

(pillars) / partially precast on-site (slabs).

- one or more storey high pillars (max 5).

- up to 30 storey high constructions.

- special designed joints and temporary joints.

-slabs are casted on the ground (one on top of the other) – then lifted with crane or special elevators.

Page 15: Prefabricated structures

15

Lift-slab procedure

1. pillars and the first package (e.g. 5 pieces) of slabs prepared at ground level2. lifting boxes are mounted on the pillars + a single slab lifted to the first floor level3-8. boxes are sequentially raised to higher positions to enable the slabs to be lifted to their requiredfinal position - slabs are held in a relative (temporary) positions by a pinning system

Page 16: Prefabricated structures

16

Planning traffic route

How long transporter vehicle is required?

What is the required load capacity of the transporter vehicle?

What is the maximum vertical extension of the shipment

Routs on the site

• Is route permission required?

Page 17: Prefabricated structures

17

Equipmentscranes: mobile crane tower crane

(above 3stories)

lifting tools: spreader beams wire rope slings

rigging tools: eye bolt shakles hooks

Page 18: Prefabricated structures

18

Assembling….Column to column connection

Page 19: Prefabricated structures

19

Beam to column connection

Page 20: Prefabricated structures

20

Beam-slab joints

Page 21: Prefabricated structures

21

Precast concrete structure consisting of solid wall panels and hollow core

slabs.

Wall to slab connection

Page 22: Prefabricated structures

22

AdvantagesQuick erection timesPossibility of conversion, disassembling and moving to another sitePossibility of erection in areas where a

traditional construction practice is not possible or difficult

Low labor intensivityReduce wastage of materialsEasier management of construction sitesBetter overall construction qualityIdeal fit for simple and complex structures

Page 23: Prefabricated structures

23

Limitationssize of the units. location of window openings has a

limited variety. joint details are predefined.site access and storage capacity.require high quality control.enable interaction between design

phase and production planning.difficult to handling & transporting.

Page 24: Prefabricated structures

24

Schedulingsome approximate data for installationemplacement of hollow core floor slabs -

300 m2/dayerection of pillars/columns - 8 pieces/dayemplacement of beams - 15 pieces/dayemplacement of double tee slabs - 25

pieces/dayemplacement of walls - 15 pieces/dayconstruction of stair and elevator shafts -

2 floors/day

Page 25: Prefabricated structures

25

Examples….

The hospital will feature multi-trade prefabricated racks in the corridors, an

approach that is still new in the U.S.

Page 26: Prefabricated structures

26

Miami Valley Hospital Dayton,OH

Page 27: Prefabricated structures

27

ConclusionoThe use of prefabrication and preassembly is estimated to have almost doubled in the last 15 years, increasing by 86%.oThe use of precast concrete construction can significantly reduce the amount of construction waste generated on construction sites.o Reduce adverse environmental impact on

sites.o Enhance quality control of concreting work.o Reduce the amount of site labour.o Increase worker safety .o Other impediments to prefabrication and

preassembly are increased transportation difficulties, greater inflexibility, and more advanced procurement requirements.

Page 28: Prefabricated structures

28

References [1] Szőnyi L.: Construction of prefabricated reinforced

concrete buildings, 2011 [2] Benett, D.: Concrete Elegance 2004. Concrete Centre,

2005 [3] Precast Concrete Structures. www.paradigm.in

2012.10.10 [4] S. Brzev, T. Guevara-Perez: Precast Concrete

Construction. http://business.management6.com/PRECAST-CONCRETE-CONSTRUCTION-pdfe13174.

[5] Sonjoy Deb: Precast Concrete for Building Systemshttp://masterbuilder.co.in/Archives/Building%20Materials/Concrete/Precast%20 Concrete%20for%20Building%20Systems.pdf 2012.10.10

[6] Lift slab systemhttp://webs.demasiado.com/forjados/patologia/lift_slab/aspect/index.htm2012.10.23

[7] http://www.liftplanner.net/steamdrum.html 2012.10.23

Page 29: Prefabricated structures

29

Questions ?.....

Page 30: Prefabricated structures

30

Thank you