Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE AIRFIELD GEOMETRY ANALYSIS LOGAN INTERNATIONAL AIRPORT, EAST BOSTON, MA L.G. HANSCOM FIELD, BEDFORD, MA WORCESTER REGIONAL AIRPORT, WORCESTER, MA RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Transcript of Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant...

Page 1: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Pre-Submission Consultant Briefing January 12, 2016

L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE AIRFIELD GEOMETRY ANALYSIS

LOGAN INTERNATIONAL AIRPORT, EAST BOSTON, MA

L.G. HANSCOM FIELD, BEDFORD, MA WORCESTER REGIONAL AIRPORT, WORCESTER, MA

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 2: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Agenda

• Opening Remarks – Flavio Leo, Director of Aviation Planning and Strategy, Strategic and Business Planning, Massport – Gail Lattrell, Lead Planner, FAA

• Introduction

• Project Overview, Management and Selection Process – Shailesh Gongal, Senior Airport Planner, Strategic and Business Planning, Massport – Project Manager

• Questions

2 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 3: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Opening Remarks

• Flavio Leo • Gail Lattrell

3 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 4: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Introductions

• Massport team

• FAA

• Attendees

4 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 5: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Project Management Team

• Managed by Strategic and Business Planning Department – Project Director: Flavio Leo – Project Manager: Shailesh Gongal

• Supported by Capital Programs and Aviation – Richard Bessom – Sarah Dennechuk – Vincent Cardillo – Bobby Lynch

5 RIM STUDY RFQ: Pre-Submission Briefing;

1/12/16

Page 6: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Overview

• Context – What is runway incursion? – Why this study now? • FAA Initiative • BOS hotspots

– Selection Process

– Preliminary Partial Airfield Geometry Analysis

6 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 7: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Runway Incursion Any occurrence at an aerodrome involving the incorrect presence of an aircraft, vehicle or person on the protected area of a surface designated for the landing and take off of aircraft

7 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 8: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Runway Incursion Severity Classification

8 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 9: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Why this study now? FAA Initiative: • Following the successful completion of RSA Program, the FAA has initiated

a Runway Incursion Mitigation Program • FAA Preliminary Inventory of Airport Locations with Runway Incursions

2007-13 • Primary cause: FAA has identified Airfield Geometry as a primary cause of

Runway Incursions Nationwide: 74 Airports/ 113 locations/60 hot spots • 804 Cumulative Runway Incursions • 395 Peak Annual Runway Incursions

BOS: Incursions at 3 out of 4 hot spots • 31 Cumulative Runway Incursions • 9 Peak Annual Runway Incursions

9 RIM STUDY RFQ: Pre-Submission Briefing;

1/12/16

Page 10: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

BOS RI Breakdown by Hot Spots Hot Spot 1 (HS1) • Cumulative RI: 7 • Peak Annual RI : 2

Hot Spot 3 (HS3) • Cumulative RI: 15 • Peak Annual RI : 4

Hot Spot 4 (HS4) • Cumulative RI: 9 • Peak Annual RI : 3

10 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 11: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Preliminary Scope of Work Inventory and Analysis: • Analyze the complete airfield geometry for non-standard geometry and potential runway incursion risks

• Analyze the risk associated with Group VI aircraft taxiing on existing taxiways

• Analyze the potential locations for deicing pads without creating adverse airfield geometry issues

• High Fidelity Simulation of Runway and Taxiway Operations

Runway Incursion Mitigation Alternatives: • Propose RIM Alternatives • Conduct Safety Risk Assessment of incursion mitigation alternatives

• Prepare preliminary engineering design/cost estimates for various alternatives

• Identify potential environmental issues/permit considerations

• Prepare Recommendations Deliverables: • Updated ALP and prepare related NEPA documents

• Final Report and Executive Summary

11 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 12: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Consultant Qualifications

Demonstrated expertise and experience in • Aviation Planning • Airfield Design Standards • Air traffic operations/planning • Airfield Simulation • And Other engineering disciplines – Civil, environmental, electrical,

12 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 13: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Selection Criteria

13 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 14: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Schedule

14

EVENT DATE/TIME

Solicitation: Release Date 1/6/16

Consultant Briefing: 1/12/16 (12 PM, noon)

Deadline for submission of written questions 1/20/16 (12 PM, noon)

Official answers published (Estimated) 1/27/16

Solicitation: Close Date / Submission Deadline 2/9/16 (12 PM, noon)

Selection March 2016

Negotiate Scope of Work and Contract April 2016

Submit FAA Grant Application 5/2/16 (Monday)

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 15: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Preliminary Partial Airfield Geometry Analysis

Boston Logan International Airport

15 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 16: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

16 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 17: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

DRAFT 17

Potential Areas of Studies

Logan’s Taxiway System and Alternatives for Evaluation

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 18: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

Potential Design Alternatives to Evaluate

DRAFT 18 RIM STUDY RFQ: Pre-Submission Briefing;

1/12/16

Page 19: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

DRAFT 19

Potential Design Alternatives to Evaluate

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 20: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

DRAFT 20

Potential Design Alternatives to Evaluate

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 21: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

DRAFT 21

III. Par/401.b (5)(f) Runways used as taxiways and taxiways used as runways can lead to confusion. A runway should always be clearly identified as a runway and only a runway.

Potential Design Alternatives to Evaluate

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 22: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

DRAFT 22

Potential Design Alternatives to Evaluate

RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Page 23: Pre-Submission Consultant Briefing January 12, 2016...2016/01/12  · Pre-Submission Consultant Briefing January 12, 2016 L1408-S1, RUNWAY INCURSION MITIGATION STUDY AND COMPREHENSIVE

QUESTIONS?

23 RIM STUDY RFQ: Pre-Submission Briefing; 1/12/16

Ask Away Or Not!

Everything you say will be monitored or recorded!!