Pre-Proposal Conference
Ten Architectural & Engineering Design Requirements Contracts for Mega Projects
Program
Ana Barrio, Acting Commissioner
Thomas Foley, Deputy Commissioner
Margaret Castillo, Chief Architect
Eric Boorstyn, Associate Commissioner
Nicholas Mendoza, ACCO
Q&A
Ana Barrio
Acting CommissionerNYC Department of Design and Construction
$12.8billion
current portfolio
value
$17billion
expected
by 2020
billion
completed
since 1996$20.5
605active
infrastructure
portfolio
562active
public buildings
portfolio
4285projects
completed
since 1996
New Construction / Major Renovation
Quality-Based Selection
Interagency Collaboration
Quality Design and Construction
Schedule and Budget
Peer Review
Thomas Foley, PE, CCM
Deputy Commissioner, Public Buildings
10
25
20
13
59
76
$130,341,000
$112,459,000
$312,019,000 $369,478,000
$213,933,000
$144,392,000
Public Buildings Contracts Pre-Design and Design
TOTAL: 203 TOTAL: $1.3B
Culturals/DCAS/Parks/Pass Through
DEP/Sanitation/ Transportation
Human Services/ OneNYC/ Health
Libraries
Fire/ Police
Corrections/ Courts
Public Buildings Contracts Construction and Close-Out
TOTAL: 398 TOTAL: $2.8B
Culturals/DCAS/Parks/Pass Through
DEP/Sanitation/ Transportation
Human Services/ OneNYC/ Health
Libraries
Fire/ Police
Corrections/ Courts
21
112
57
18
73
117
$147,434,125
$879,356,265
$351,798,925
$1,073,146,586
$233,148,465
$185,155,456
Public Buildings - Upcoming Contracting Opportunities
FDNY & DOC Fort Totten Training AcademiesCapital Project Scope DevelopmentEstimated Construction Budget $400-700M
Public Buildings - Upcoming Contracting Opportunities
NYPD Property Clerk FacilityCapital Project Scope DevelopmentEstimated Construction Budget $300M
Public Buildings - Upcoming Contracting Opportunities
DOHMH Bronx Animal ShelterEstimated Construction Budget $70M
Public Buildings - Upcoming Contracting Opportunities
DEP Maspeth FacilityCapital Project Scope Development Estimated Construction Budget TBD
Public Buildings - Upcoming Contracting Opportunities
DEP Clove Road FacilityCapital Project Scope Development Estimated Construction Budget $30M
Public Buildings - Upcoming Contracting Opportunities
DOC Borough-Based Justice CentersCapital Project Scope DevelopmentEstimated Construction Budget TBD
Margaret Castillo, FAIA, LEED AP
Chief Architect
Times Square Plaza ReconstructionSnøhetta
DSNY Manhattan District 1/2/5 Salt ShedDattner Architects and WXY
DSNY Manhattan District 1/2/5 Salt ShedDattner Architects and WXY
DSNY Manhattan District 1/2/5 GarageDattner Architects and WXY
Queens MuseumAmmann & Whitney with Grimshaw
Queens MuseumAmmann & Whitney with Grimshaw
Queens MuseumAmmann & Whitney with Grimshaw
Ocean Breeze Athletic CenterSage and Coombe Architects
Ocean Breeze Athletic CenterSage and Coombe Architects
Ocean Breeze Athletic CenterSkycycles by Paul Villinski
NYPD Police AcademyPerkins + Will with Michael Fieldman
NYPD Police AcademyPerkins + Will with Michael Fieldman
NYPD Police AcademyDiamond Matrix by Erwin Redl
40th Police Precinct Station HouseBIG
40th Police Precinct Station HouseBIG
40th Police Precinct Station HouseBIG
TLC Woodside Inspection FacilityExisting Conditions
TLC Woodside Inspection Facility (proposed)TEN Arquitectos
TLC Woodside Inspection FacilityTEN Arquitectos
Rodman’s Neck Training Facility – Capital Project Scope DevelopmentRice + Lipka Architects
Rodman’s Neck Training Facility – Capital Project Scope DevelopmentRice + Lipka Architects
Clean, Safe, and Livable
Skills Programming
Active and Productive Programming
Positive Community Integration
Resource Efficiency
Conscious Shelter Design
80% Greenhouse Gas Reduction
Energy Efficient Buildings
Build Upon One City Built to Last
80 X 50
198projects
awarded since
2004
$992million in
construction
value
architecture
firms100
1100: Architect · Abruzzo Bodziak Architects · Agrest and Gandelsonas Architects · Allied Works Architecture · Ammann & Whitney
Andrew Berman Architect · Architecture in Formation · Architecture Research Office · Arquitectonica · Asymptote Architecture · Atelier
Pagnamenta Torriani Architects Planners · Audrey Matlock Architect · Bade Stageberg Cox · Belmont Freeman Architects · Bentel &
Bentel, Architects/Planners · Bernheimer Architecture · Beyhan Karahan & Associates Architects · Biber · Bjarke Ingels Group · BKSK
Architects · Body Lawson Associates · Buro Koray Duman Architecture · BWA + de.Sign · Caples Jefferson Architects · Charles
Rose Architects · Christoff : Finio Architecture · CR Studio Architects · Dattner Architects · Dean/Wolf Architects · Deborah Berke &
Partners Architects · Elmslie Osler Architect · Ennead Architects · Fox & Fowle · Frederic Schwartz Architects · G Tects Architecture
Gans Studio: Architecture · Garrison Architects · Gluckman Mayner Architects · Gray Organschi Architecture · Grimshaw Architects · H3
Hardy Collaboration Architecture · Hanrahan Meyers Architects · HS2 Architecture and FREE · Huff + Gooden Architects · IKON.5
Architects · Jaklitsch/Gardner Architects · Jordan Parnass Digital Architecture · Karen Bausman + Associates · Keenen/Riley
Kiss + Cathcart, Architects · LARC Studio · Leeser Architecture · Leroy Street Studio · LEVENBETTS · Locascio Architect · LTL
Architects · Marble Fairbanks · Marpillero Pollak Architects · Marvel Architects · Matthew Baird Architects · Michielli + Wyetzner
Architects · Monica Ponce de Leon Studio · Moorhead & Moorhead · Murphy Burnham & Buttrick Architects · nARCHITECTS · OBRA
Architects · Ogawa/Depardon Architects · Ohlhausen DuBois Architects · Pasanella + Klein Stolzman + Berg · Pendergast Laurel Architects
Rafael Vinoly Architects · Rice + Lipka Architects · Rietveld Architects · Rogers Marvel Architects · Sage and Coombe Architects
Selldorf Architects · Sen Architects · Skidmore, Owings and Merrill · Slade Architecture · Smith-Miller + Hawkinson Architects
Snøhetta · Spacesmith · Stephen Yablon Architecture · Steven Harris Architects · Steven Holl Architects · Studio Gang · Studio Joseph
Studio SUMO · TEN Arquitectos · The Galante Architecture Studio · Thomas Phifer and Partners · Toshiko Mori Architect · Urbahn
Architects · W Architecture and Landscape Architecture · Wallance + Hibbs Architects · Weiss/Manfredi Architects · Weisz + Yoes
Architecture · WORK Architecture Company · Yoshihara McKee Architects · Zakrzewski + Hyde Architects
2004
2007
2010
2013
2016
micro small medium large
10 firmsunder $5 million
10 firms$2 – 15 million
3 firms$10 – 35 million
3 firms$25 – 50 million
24 firmsprojects under $5 million
24 firmsunder $10 million
20 firmsunder $15 million
20 firmsunder $15 million
8 firmsover $5 million
8 firmsover $10 million
8 firmsover $15 million
6 firmsover $15 million
2004
2007
2010
2013
2016
micro small medium large
10 firmsunder $5 million
10 firms$2 – 15 million
3 firms$10 – 35 million
3 firms$25 – 50 million
24 firmsprojects under $5 million
24 firmsunder $10 million
20 firmsunder $15 million
20 firmsunder $15 million
8 firmsover $5 million
8 firmsover $10 million
8 firmsover $15 million
6 firmsover $15 million
2018up to 10 firmsover $50 million
Eric Boorstyn, AIA
Associate Commissioner, Public Buildings
Up to 10 Firms
Architecture and Engineering
51+ Full-Time Technical Professionals
Projects Over $50 Million
NYPD, FDNY, DOC, ACS, DHS,
DOHMH, & more
Mega RFP
Stage One Requirements
Prime Firm Only Quality of Firm’s Project Experience [50%]
Relevance of Firm’s Project Experience
[50%]
Stage One Evaluation
Portfolio of Completed Projects
Up to 5 Projects
Stage Two Requirements
Experience of Key Personnel [50%]
Technical Methodology [30%]
Stage Two Evaluation
Short-Listed Firms Only
Technical Proposal
Experience of Key Personnel
Technical Methodology
Team Capability and Organization
Team Capability and Organization [20%]
Prime + Subconsultants on
Attachment 3 of RFP
Structural
MEP/FP
Cost Estimating
Presentation
Up to 10 Firms Selected
Contract
1 Agreement
2 Design Consultant Guide and
Appendix
3 Task Order, including the Project
Objectives
Project Award Process
Client Agency Transfers Project
“Mini” RFP Issued to Consultants
Consultant Submits Proposal
Evaluation and Selection by
Committee
Design Fee
Base Fee
Complexity Factor
Time Card [Direct Salary + Multiplier]
Goals
Competitive Sealed Bid
Bid Documents to be Clear and
Coordinated
Challenges
Functional & Practical: Meets Client
Needs
Design to Budget
On-Time Delivery
Aspirational: Enhances Public Realm
Specifications to Comply with DDC
Requirements
New Tools
DDC Master Specs
Digital Design Review
Design Excellence Round 6 in 2018
Exterior Envelope Restoration in 2018
Historic Preservation in 2018
Multi-Trade in 2018
Upcoming Opportunities
Nicholas Mendoza
Agency Chief Contracting Officer (ACCO)
Inquiries - All inquiries must be submitted in writing or email no later than
Tuesday, March 6, 2018.
Due Date - Stage One proposals due Tuesday, March 13, 2018, by 4:00 PM.
(DDC entrance is on 30th Place, not Thomson Avenue)
Acknowledgement of Addenda - All addenda shall become part of the
requirements of the RFP. Please sign and return Attachment 5 with your
portfolio.
Helpful Reminders
Two separate packages will be required for submission:
1) Portfolio (1 original, 5 copies, 1 electronic version saved as a single PDF on a
clearly labeled disc
(CD) or USB flash drive)
• Items listed in Section IV.A of the RFP
• Completed Part II of SF330 Form from the Prime Firm only
• Statement of Understanding and Certification (Attachment 1)
• Certification of Compliance with Iran Divestment Act (Attachment 2)
• Acknowledgement of Addenda (Attachment 5)
2) Doing Business Data Form (Attachment 7)
Stage One - Proposal Package Contents (RFP-16 to RFP-18)
Two separate packages will be required for submission:
1) Technical Proposal (1 original, 5 copies, 1 electronic version saved as a
single PDF on a clearly labeled
disc (CD) or USB flash drive)
• Items listed in Section IV.B of the RFP
• Completed Part I of SF330 Form from the Prime Firm and Completed Part I and II of
SF330 Form for the Subconsultants
• Statement of Understanding and Certification (Attachment 1)
• Identification of Subconsultants (Attachment 3)
• Identification of Key Personnel (Attachment 4)
2) Schedule B: M/WBE Utilization Plan (Attachment 6)
Stage Two - Proposal Package Contents (Short-List Only)
Procurement and Sourcing Solutions Portal (PASSPort) Disclosure Filing
(formerly known as Vendor Information Exchange System (VENDEX) Forms
or Certificate of No Change)
All organizations intending to do business with the City of New York should
complete an online disclosure process to be considered for a contract. This
disclosure process was formerly completed using Vendor Information Exchange
System (VENDEX) paper-based forms. In anticipation of awards, proposers to
Ten Architectural & Engineering Design Requirements Contracts for Mega
Projects must create online accounts in the new Procurement and Sourcing
Solutions Portal (PASSPort) and file all disclosure information. Paper
submissions, including certifications of no changes to existing VENDEX
packages will not be accepted in lieu of complete online filings.
For more information about PASSPort, please visit nyc.gov/passport.
PASSPort (RFP-20, Section V)
General Information (RFP-21 to RFP-23, Section VI)
Proposers are advised to read the entire section.
Subcontractor Reporting (RFP-38)
As of March 2013, the City has implemented a new web-based subcontractor
reporting system through the City’s Payee Information Portal (PIP), available at
www.nyc.gov/pip.
Helpful Reminders
• Master Service Agreement Schedule B, Attachment 6, required for submission.
• Goal percentage will be established on individual task order.
• M/WBE requirement can be achieved by:
1) M/WBE Prime Vendor
2) Qualified M/WBE Joint Venture
3) M/WBE Subcontractor(s)
• New York City Department of Small Business Service certified M/WBE firms
are listed at: http://mtprawvwsbswtp1-1.nyc.gov/Search.aspx
M/WBE Participation Requirement
• HireNYC Goods and Services is a hiring process that requires businesses that
contract with the City to share entry- and mid-level positions with the City, and
interview qualified candidates that the City refers.
• Consultants will be required to:
• Enroll with the HireNYC Portal within (30) days of contract registration;
• Indicate if entry- to mid-level opportunities will arise from the contract; if no applicable
employment opportunity related to a contract arose, to certify as such;
• Post job openings for entry- and mid-level positions arising from the contract.
• For additional guidance on HireNYC, please contact Donna Pope at
• For questions about the HireNYC Portal, contact [email protected]
HireNYC: Goods and Services
Questions & Answers
Thank you
Stage One Proposals DueTuesday, March 13, 2018 by 4:00 PM