PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/05...Vide Memo No....
Transcript of PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/05...Vide Memo No....
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 0
PRE FEASIBILITY REPORT
FOR
PROPOSED INSTALLATION OF SPONGE IRON PLANT (1x350 TPD), WHRB
(1x35 TPH), INDUCTION FURNACE (1X7 T), HOT ROLLING MILL (1,00,000
TPA), SINTER PLANT (35 TPD), SUBMERGED ARC FURNACE (2x4.5 MVA)
AND TG SET (1X8 MW) UNDER FORWARD INTEGRATION, EXPANSION AND
PRODUCT DIVERSIFICATION PROGRAMME OF EXISTING MINI STEEL PLANT
AT
Palitpur Road, Village & P.O. Mirzapur,
PS + District: Bardhaman, PIN -713102, West Bengal
PROJECT PROPONENT:
SALAGRAM POWER AND STEEL PVT. LTD. 29 Ganesh Chandra Avenue, 1st Floor,
Kolkata-700 013
DECEMBER, 2017
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 1
CONTENTS
1.0 INTRODUCTION
2.0 THE PROJECT
3.0 INDUSTRY SCENARIO
4.0 LAND AND SITE LOCATION
5.0 MAJOR PLANT UNITS AND AUXILIARY UNITS
5.1 Sponge Iron Plant
5.2 Induction Furnace
5.3 Continuous Casting Plant
5.4 Rolling Mill
5.5 Sinter Plant
5.6 Submerged Arc Furnace
5.7 Power Plant
6.0 RAW MATERIALS, CHEMICALS & UTILITIES
6.1 Raw Materials
6.2 Fuel
6.3 Water
6.4 Other Utilities
6.5 Power
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 2
7.0 ENVIRONMENTAL ASPECTS
7.1. Air Pollution Control
7.2 Water Pollution Control
7.3 Solid Waste Management
7.4 Noise Pollution Control
8.0 FIRE PROTECTION SYSTEM
9.0 GREEN BELT DEVELOPMENT OBJECTIVE
10.0 RAIN WATER HARVESTING
11.0 MANPOWER REQUIREMENT
12.0 PROJECT SCHEDULE
13.0 FINANCIAL DETAILS
14.0 CONCLUSION
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 3
PRE-FEASIBILITY REPORT
1.0 INTRODUCTION
M/s Salagram Power and Steel Pvt. Ltd. (SPSL), a Private Limited Company, was
incorporated on September 29, 2011, having its registered office at 29, Ganesh Chandra
Avenue, First Floor, Kolkata - 700013.
The Company was previously known as M/s SHYAM SEL & POWER LIMITED under
Shyam Group of Industries. Shyam Group was subsequently demerged.
Vide Memo No. 1983-7/WPBD-Cont(752)/99 (Pt.-II) dated 03.10.2016, West Bengal Pollution
Control Board has recorded change of Name of the Company as SALAGRAM POWER
AND STEEL PRIVATE LIMITED (SPSL) for the existing Mini Steel Plant at village Mirzapur,
Bardhaman. Mirzapur Village is about 5 Km away from Burdwan Town.
Vide Consent Letter Number CO 100575, Memo Number 1212-7/WPBD-Cont.(752)/99 dated
29.06.2016 (and also Memo on Renewal of Consent to Operate dated 27.06.2014 and Memo
on Change of name and correction of capacity dated 03.10.2016), WBPCB has granted the
Company (SPSL) “Consent to Operate” for 3 years (from 01.07.2016 till 30.06.2019) this
Existing Mini Steel Plant having DRI Kilns (3 x 50 TPD producing 45,000 TPA Sponge Iron),
Induction Furnaces (1x4 T, 2x3.5T and 1x6 T producing 56.000 TPA liquid steel), one Twin
Strand Billet Caster (54,000 TPA MS Billets), WHR Boilers (3x4.5 TPH), one AFBC Boiler
(1X24 TPH) and Power Plant (1x8 MW TG Set).
Salagram Power and Steel Pvt. Ltd. is promoted by Mr. Pawan Kumar Agarwal, Mrs.
Santosh Devi Agarwal and Mr. Suyash Agarwal.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 4
2.0 THE PROJECT
To take full advantage of improved market scenario in near future as projected by the
Industry, SPSL intends to undertake forward integration, expansion and also product
diversification of the Mini Steel Plant.
Existing Process Route of DR-IF-CC (Direct Reduction – Induction Furnace –
Continuous Casting) will be adopted for rationalization and ease of operation by existing
manpower, which has already gained adequate skill and experience to operate these units.
Additional manpower of required skill will be employed for operation and maintenance of all
units under expansion.
The Company is contemplating forward integration to produce TMT Bars and Rods, Flats and
Structurals. It is proposed to install a Hot Rolling Mill of 1,00,000 TPA capacity.
About 1,05,000 TPA of MS Billets will be required for production of above quantity of
1,00,000 TPA TMT bars and rods. Existing 6/11 m Twin Strand Billet Caster is having
adequate in-built capacity to produce 1,05,000 TPA MS Billets. No additional Billet Caster is
therefore envisaged under expansion.
About 1,10,000 TPA liquid steel (which is almost double of existing capacity) will be required
for production of 1,05,000 TPA MS Billets. To meet above liquid steel demand, it is proposed
to expand Steel Making Capacity by installing one No. 7 T Induction Furnace in addition to
modernization / up gradation of existing 4 Induction Furnaces to higher capacity (3x 7 T +
1x6T) as indicated by Equipment Suppliers.
Sponge iron is a major feed material for Induction Furnace Steel Making and constitutes
about 80% of Charge Mix. Sponge Iron requirement will be about 1,00,000 TPA for
production of 1,10,000 TPA liquid steel. The Company presently operates 3 Nos. 50 TPD
DRI kilns to produce 45,000 TPA Sponge Iron. To meet requirement of Sponge Iron for
enhanced Steel Making Capacity under expansion and also additional quantity for Sale, 1
No. of standard sized 350 TPD DRI Kilns will be installed. This will ensure adequate steam
from WHRB for 8 MW Power Generation. Total Capacity of Sponge Iron after expansion will
be 1,50,000 TPA. After meeting the requirement of 1,00,000 TPA Sponge Iron for steel
making, 50,000 TPA Sponge Iron will be available for Sale in Domestic Market improving
Plant Economics.
Existing 8 MW TG Set of Power Plant is designed based on steam generated in 3 WHRB
utilizing waste hot flue gases of DRI Kilns and AFBC Boiler burning Char / Coal / Husk. Char
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 5
generation in existing DRI Kilns being insufficient to meet steam balance, the Company has
to purchase costly fuel (Coal / Husk) for existing AFBC Boiler.
Proposed 1x350 TPD DRI Kilns will be designed with one WHR Boiler (1x35 TPH).
All Char generated in 4 DRI Kilns (3 existing and 1 proposed) will be utilized in the existing
AFBC Boiler.
Total Steam generation from existing and proposed WHR Boilers and existing AFBC Boiler
will be about 72.5 TPH. Above steam will be sufficient to generate 16 MW of Power. It is
therefore proposed to install an additional 1x8 MW TG set in the expansion stage increasing
Captive Power Plant Capacity to 16 MW.
It is further proposed to diversify into production of Silico Manganese (Si-Mn) by installing
2x4.5 MVA Submerged Arc Furnace (SAF). In these SAF it will be possible to produce Ferro
Chrome (Fe-CR) depending on Market Demand.
To utilise fines generated during handling of coal and iron ore lumps / iron ore pellets (raw
material feed to DRI Kilns), a 35 TPD Sinter Plant will be installed. Dust recovered from Bag
Filters & ESP of DRI Plant and scales from CCP & Rolling Mill will also be utilised in Sinter
Plant. Sinter produced will form a part of the Charge Mix to SAF.
SPSL has rightly decided to expand the capacity of the Plant by installing additional Sponge
Iron Kiln (1x350 TPD), WHR Boiler (1x35 TPH Steam), modernization / up gradation of
existing Induction Furnaces, one additional Induction Furnace (1x7 T), one Rolling Mill
(1,00,000 TPD) for forward integration, one Sinter Plant (35 TPD), two Submerged Arc
Furnaces (2x4.5 MVA) producing Ferro Alloys for product diversification and a TG Set (8
MW).
Existing CCM is having adequate in-built Capacity to produce 1,05,000 TPA Billets required
in Rolling Mill to produce 1,00,000 TPA TMT Bars, rods etc.
All existing Service Facilities will be suitably augmented as well as additional Service
Facilities are proposed to be installed to meet the requirement of the Mini St.eel Plant after
Expansion.
Configuration of Major Existing Units and Units under Expansion is indicated in Table 2.1
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 6
CONFIGURATION OF MAJOR UNITS OF THE PLANT: TABLE 2.1
*Present Production Capacity is as per WBPCB’s Memos.
Sl. No.
Existing Units Present Production
Capacity
Proposed Units under Expansion
Total Production
Capacity after Expansion
Product (For Sale)
1. 3x50 TPD Sponge Iron
Kilns
48,000 TPA * Sponge Iron
1x350 TPD Sponge Iron Kiln
500 TPD or 1,50,000 TPA
Sponge Iron (50,000 T/Y)
2.
1x4 T, 2x3.5 T and 1X6 T Induction Furnaces
56,000 TPA Liquid Steel
1x7 T Induction Furnace
and modernization / up gradation of
existing Furnaces to augment capacity (to
3x7 T + 1x6 T)
1,10,000 TPA
Liquid Steel (Nil)
3.
6/11 m, 2 Strand Continuous
Casting Machine
54,000 TPA * MS Billets for sale -100x100 mm, 125x125 mm & 160x160
mm
Nil
1,05,000 TPA (existing CCM is having In-
built Capacity)
MS Billets
(Nil) Nil)
4.
Nil
Nil
1 No. Hot Rolling Mill
1,00,000 TPA
TMT Bars, Rods, Flats
and Structurals
(1,00,000 T/Y)
5.
Nil
Nil
1x 35 TPD Sinter Plant
10,500 TPA (to be used as part of Charge
Mix of SAF)
Sinter (Nil)
6. Nil
Nil
2x4.5 MVA Submerged Arc Furnaces (SAF)
12,960 TPA
Silico - Manganese /
Ferro - Chrome
(12,960 T/Y) 7. 3XWHR Boilers 3x4.5 TPH 1XWHR Boiler
(1x35 TPH) 48.5 TPH
Steam (Nil)
8. 1x AFBC Boiler 1x24 TPH Nil 24 TPH
Steam (Nil)
9. 1x 8 MW TG Set for Captive Power Plant
8 MW
1x8 MW TG Set
16 MW
Power (Nil)
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 7
Adequate Pollution Control Facilities will be installed to conform to Pollution Norms.
SPSL is having 25.8 Acres of land in their Possession. The proposed expansion will be
accommodated within the existing Plant Boundary and also some adjoining land
(approximately 3.0 Acres) which will be acquired. The land is generally flat and does not
come under flood zone. There is no human settlement in the project site. Adjoining land (to
be acquired) will be reformed / developed from its existing land use.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 8
3.0 INDUSTRY SCENARIO
Indian steel industry is the major backbone in the country’s economic growth.
According to Joint Plant Committee (JPC), Ministry of Steel, Govt. of India, India produced
about 95.6 Million Tonne of Crude Steel in 2016 and remained, for two consecutive years,
Third Largest Crude Steel Producer in the World after China (808.4 MT) and Japan (104.8
MT). In 2016, the world crude steel production reached 1628 million tonnes and showed a
growth of 0.8% over 2015.
Demand-Supply Gap
On a conservative estimate, the steel demand in India is expected to touch around 150
MTPA by 2020. Steel supply is, however, expected to reach only around 145 MTPA by same
time.
World Steel Association has projected Indian steel demand to grow by 5.7% in 2017 while
globally steel demand has been projected to grow by 0.5% in 2017
The National Steel Policy 2017 has been formulated keeping in mind the rapid developments
in the domestic steel industry (both on the supply and demand sides) as well as the stable
growth of the Indian economy. The National Steel Policy 2017 aims to achieve 300 million
tonne of steel-making capacity which will require an additional investment of Rs 10 lakh crore
by 2030-31 setting a target of 160 kilograms per capita steel consumption by 2030. In
comparison, per capita finished steel consumption in 2015 is placed at 208 kg for world, 489
kg for China and only 61 kg for India.
As a facilitator, the Government monitors the steel market conditions and adopts fiscal and
other policy measures based on its assessment. In view of rising imports, the Government
had earlier raised import duty on most steel items twice, each time by 2.5% and imposed a
gamut of measures including anti-dumping and safeguard duties on a host of applicable iron
and steel items.
The liberalization of industrial policy and other initiatives taken by the Government
have given a definite impetus for entry, participation and growth of the private sector
in the steel industry. This had led to expansion, forward integration, diversification and
modernization of existing units.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 9
The Cabinet also cleared another policy which will mandate giving preference to iron and
steel products that are manufactured in India for all government tenders. At least 15 percent
value has to be added to the notified steel product in India to qualify as domestic steel.
There is a distinct relation between steel consumption and the GDP growth rate world over.
In India, GDP is expected to remain a figure of above 7% in Current and Next Financial
Years while it is expected to touch thereafter Double Digit Figures of 11-12%. This will be
possible with National Focus on Large Infrastructure Development with huge Investment and
India is bound to witness sustained growth in the steel requirement in the years to come.
India will emerge as the Second Largest Producer of Crude Steel in near future.
It is foreseen that there will be sufficient demand in local/Indian Market of Sponge Iron
for Steel Making, TMT Bars and Rods for constructional needs and Silico Manganese
for Steel Making.
M/s SPSL has drawn up a growth plan with the objective of increasing its market share in
Indian steel industry. Keeping all these in mind, the Company has planned expansion,
forward integration and diversification of the existing Mini Steel Plant in a effective
environment friendly way.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 10
4.0 LAND AND SITE LOCATION
The Plant is located at Palitpur Road in Village & P.O. Mirzapur, Saraitikar Gram Panchayat,
P.S.& Dist. Burdhaman, West Bengal, Pin – 713102. Its graphical coordinates are Latitude
23°17'09.25" N and Longitude 87°52'09.76" E with mean sea level as 107 ft.
The Plant is located adjacent to and at the west side of M/s Shyam Ferro Alloys on Palitpur
Road. Plant location is indicated in subsequent Maps and satellite Pictures.
-
Pic. 1 - Burdwan District Map
Pic.2 – Satellite Picture showing Burdwan Railway Station and Palitpur
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 11
Pic. 3 – Satellite picture showing Dewandighi and Palitpur Road
Pic. 4 – Satellite Picture showing Dewandighi, Palitpur Road and Shyam Ferro Alloys
Bardhaman Town (District H.Q.) is about 4.5 km from project site. Burdwan Railway Station
is about 4.3 km from the Plant Site. National Highway-2 (NH-2) is passing through the south
direction, at a distance of around 4.0 km away. River Damodar is passing approx. 7.5 km
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 12
distance in south direction. There is no National Park & Reserve Forest within 10 km radius
of the project site.
The Plant Site Area is well developed and has all necessary infrastructure facilities such as
motorable road up to the plant site, nearness to rail head, Power lines and Sub Stations,
telephone facilities etc.
The nearest industrially developed town Durgapur is situated at around 60 km away in the
north-west direction. Kolkata city is located at a distance of about 95 km from the Plant.
Distance from Howrah Railway station to the plant site is about 92 km. The nearest airport is
Kolkata which is about 93 km from the plant site. Kolkata Port is around 95 km away and
Haldia Port is 135 km away from the plant site.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 13
5.0 MAJOR PLANT UNITS AND AUXILIARY UNITS
5.1 SPONGE IRON PLANT
As already indicated earlier, one (1) Sponge Iron Rotary Kiln, having a capacity of 350 TPD,
will be installed for production of 1,05,000 TPA sponge iron. With this expansion measures,
Production Capacity of Sponge Iron will be increased to 1,50,000 TPA. The Charge Mix of
Induction Furnace for steel making consists of Sponge Iron (80%) and Scrap / Pig Iron
(20%). After meeting internal demand for steel making, about 50,000 TPA of Sponge Iron
will be available for Sale.
Manufacturing Process
In the Existing Plant, Sponge Iron is produced through well established Non Coking Coal
based Technology in Rotary Kilns. Same Technology will be adopted for Expansion. Iron ore
lump/ pellet will be reduced with non coking coal in rotary kilns to produce sponge iron.
The rotary kiln used in Sponge Iron Making Process functions as:
a conveyor of solids
a vessel for carrying out complex chemical reactions
a heat exchanger
From Day Bins, metered quantity of Iron Ore lumps ( 5-18mm) and Iron Ore Pellets (12 mm
MPS) along with Coal (3-20 mm) and Dolomite (- 6 mm) are conveyed at the feed end of the
Rotary Kiln and fed into the preheated kiln through a feed pipe mounted through the feed end
housing. Because the rotary kiln is inclined from the feed end to the discharge end, its rotation
causes the feed material mix to traverse downward towards the exit. The rotational speed of the
rotary kiln can be adjusted to maintain the desired loading of the kiln and ensuring the required
time to complete the reduction of the iron ore.
Inside the bed of Charge Mix in rotary kiln, CO gas is generated from coal at around 950°C.
The CO reacts with Fe2O3 in iron ore lump / pellet and reduces it to metallic Fe. Shell air fans
are mounted on the kiln Shell, which inject air in controlled manner into the kiln for creating
reducing atmosphere and also to generate heat. The kiln is lined with refractory for sustaining
high temperature at desired level (up to 1050°C) in different points of preheating and
reducing zones of the rotary kiln. Coal fines are pneumatically injected into the kiln from
discharge end to keep desired temperature profile and carbon balance at different zones.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 14
Main reduction reactions in Rotary Kiln are:
Fe2O3+CO=FeO+CO2
FeO+CO=Fe+CO2
C+CO2=2CO
2CO+O2=2CO2
C+O2=CO2
Iron Ore reducing reactions are endothermic in nature. This heat requirement is met by
combustion of over bed gas which heats up the refractory lining as well as the bed surface.
Tumbling of material transfers the heat from the surface particles to the bed. The hot kiln wall
which enters the bed also releases its heat to the bed. By the end of its travel through the
Rotary Kiln (about 8 hours), iron ore is metalized to about 90% and falls through a transition
chute into the Rotary Drum Cooler at about 1000°C.
The Cooler is an inclined steel cylinder. The cooler shell is sprayed with water. The water
serves as the indirect coolant of the sponge iron. Heat from the product is conducted through
the cooler shell to water. The water is collected in a trough beneath the cooler and is re
circulated through cooling tower and pump house. The product gets cooled to 150°C at the
outlet of cooler. The cooled product will be conveyed to the product processing building by a
system of belt conveyors.
Product Separation
The sponge iron along with unburnt coal in the form of Dolo Char comes out of the cooler. The
cooled product is subjected to screening and magnetic separation to separate magnetic product
and non-magnetic Dolo Char. Sponge Iron Lumps and fines are stored in their designated
product bins. Bypass arrangement will be provided at discharge end of the cooler for
emergency discharge of materials.
The gases generated in the rotary kiln flow counter current to the flow of solids and exit the
reactor at the feed end. The gases leave the reactor at about 800-850o C through reactor
feed end housing. The flue gas that contains coal volatile matter, fine carbon particles, iron
ore fines and sponge iron dust is treated separately in the waste gas handling system before
releasing through the Chimney to the atmosphere ensuring environmental norms.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 15
In-plant de-dusting system
Reverse air jet bag filters shall be installed for catching the dust from various conveyors,
material handling equipment and-product handling equipment.
Raw Materials
The main raw materials for sponge iron production are iron ore lump / pellet, non-coking coal,
and dolomite. The specific consumption and annual requirement of these raw materials for
1,50,000 TPA Sponge Iron from existing 3x50 TPD Kilns and proposed 1x350 TPD Kilns are
shown in Table 5.1
ANNUAL REQUIREMENT OF RAW MATERIAL FOR SPONGE IRON PLANT: TABLE 5.1
The iron ore lump/pellet should have Fe - 65%, SiO2+Al2O3 -5%, Sulphur – 0.01%,
Phosphorus -0.05%; Tumbler Index of Iron Ore – 90%.
Non Coking Coal should have high reactivity, FC – 45%, low ash content (20% max.),
medium volatile matter (25-30%), high ash fusion temperature (1400°C), low Sulphur (less
than 1%) and low caking index (3% max.).
Dolomite is used as desulphuriser to fix Sulphur present in coal and should have MgO – 22%
minimum and CaO – 28% maximum.
Product characteristics of coal based Sponge Iron is as follows:
Sl. No.
Raw material
Specific
Consumption
T/T
Quantity in TPA
1. Iron Ore Lump/Pellet 1.5 2,25,000
2. Coal 1.0 1,50,000
3. Dolomite 0.03 4,500
Item Value
Fe (total) 92% min
Fe (met) 83 % max
Metallization 90 %
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 16
Major plant facilities
The major plant facilities for the sponge iron plant envisaged are as follows:
1. Day Bins
2. Rotary Kiln and Cooler
3. Off-gas System including WHRB
4. The Water Circuit
5. Product Processing and Storage.
Day bins
There shall be a day bin building to cater to raw material requirement of the kiln. These bins
will generally have storage of about one day’s requirement of iron ore lump/pellet, feed coal
and injection coal & dolomite. Weigh feeders will be provided to draw the required quantity of
various materials in proportion from the bins and the same will be conveyed to the kiln feed
and discharge end Buildings.
Rotary kiln and cooler
The 350 TPD Rotary Kiln with 4.2 m diameter and 72/76 m long will be installed. The kiln will
be lined with abrasion resistant refractory castables throughout its length with dams at feed
end and discharge end.
The rotary kiln will be supported on 3 piers. A slope of about 2.5% shall be maintained. The
main drive of the kiln will be by D.C dual drive. The speed of the kiln will be in the range of
0.25-0.75 rpm. There are two auxiliary drives which are powered by DG Set.
Rotary Kiln is mounted on tyres and supported by support rollers. The transverse motion of
the Kiln is controlled with the help of hydro thruster and thrust rollers. The kiln is rotated with
the help of a girth gear mounted on the kiln and connected with pinion drives, which in turn
are coupled with gear boxes and motors.
Carbon 0.25 % max
S 0.025% max
P 0.05% max
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 17
The other main components of the kiln will be as given below:
a. Feed end and discharge end transition housing of welded steel construction with refractory lining including feed chute.
b. Pneumatic cylinder actuated labyrinth air seal complete with auto lubricating at feed end and discharge end.
c. On board equipment like fans, slip ring, instrumentation etc. d. Cooling fans at feed end and discharge end. e. Feed end double pendulum valve & dust valves.
Rotary Drum Cooler of 3.4 m diameter and 46 m long will be installed. Coolers will be
supported on 2 piers and will have a slope of 2.5% and is rotated at variable speed of 0.7 to 1
rpm with the help of a girth gear mounted on the cooler and connected with single pinion
drive, which is coupled with a gearbox and an AC motor with VVVF drive. An auxiliary drive is
provided to rotate the cooler in case of emergency.
To facilitate conduction of heat from hot product through Cooler to Cooling Water (sprayed on
to Cooler Shell), lifters are provided inside the cooler.
The cooler shell is perforated up to a certain distance from the discharge end to form a
trommel inside the discharge end housing. The trommel serves to screen the normally sized
product from over-sized lumps or fused materials which may have been formed in the rotary
kiln during processing. Some quantity of accretion material/aggregate comes out of the Kiln
into the Cooler. These are separated from the product at the trommel and stored at the lump
gate. This lump gate is opened time to time for discharging.
Off-gas System
The Off-gas System consists of:
(a) Feed End Housing and Dust Settling Chamber (DSC) – Coarse dust particles
from waste flue gases, coming out of the Rotary Kiln, is settled in DSC.
(b) After Burning chamber (ABC) - Air is blown by Fans into the ABC for converting
any un-burnt CO (in waste flue gases) to CO2. Water is injected in ABC to control
temperature rise.
(c) Auxiliary Stack and Stack Cap – These are provided in the off gas circuit to
evacuate the Kiln off gases in case of any failure of equipment in the downstream
side after ABC. Normally the cap will remain closed. The stack cap is opened
through a hydraulic power pack either from operator’s desk in control room or from
local control panel as per requirement.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 18
(d) Waste heat recovery boiler (WHRB) – Latent heat of waste flue gases is utilised
to produce steam for power generation. Gases are then passes to ESP at 200°C
(e) Electrostatic precipitator (ESP) – Fine dust particles gets electrically charged and
is deposited in electrodes. Clean waste gases are then let out to the atmosphere
at around 80°C.
(f) ID fan –Creates required draft in the Kiln and forcing clean waste gases to
atmosphere through a chimney. The motor of ID Fan is provided with necessary
control system to vary the Draft as required.
(g) Chimney – The height of Chimney will conform to Environmental Norms.
The Water Circuit
Make up water will be available at the battery limit of the plant to provide water for the following
circuits. :
a) Rotary cooler water circuit
b) Kiln bearing cooling water circuit
c) Dust Handling System
d) Off Gas Circuit.
e) Misc. Equipment like compressor, DG etc.
Product Processing and Storage
There shall be one product processing unit for handling the cooler discharge. The product
containing sponge iron and dolochar from the cooler discharge will be conveyed to the
product processing building. The product will first be screened in a double deck screen
having 3 mm and 10 mm screens. +10 mm materials shall be passed through magnetic Drive
Pulley of the Belt conveyor to separate non-magnetic particles. The screened product i.e. +3
– 10 mm and -3 mm fraction shall be separately subjected to magnetic separation for
removal of dolo char. Magnetic Product will be sent to the product storage bins and fines
bunker. The sponge iron lump and fines will be further conveyed from the respective bunkers
by truck to the steel making unit as per the requirement.
The dolo char shall be stored in separate bins from where it will be sent to the existing AFBC
Boiler for generation of steam for Power Plant.
Typical Process Flow Diagram of Sponge Iron Plant is presented below.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 19
I.Coal – Injection Coal; DSC – Dust Settling Chamber; ABC – After Burning
Chamber; WHRB – Waste Heat Recovery Boiler; ESP – Electro Static Precipitator;
ID Fan – Induced Draft Fan; TG Set – Turbo Generator Set; MS -Magnetic
Separator; PB 1 – Product Bunker for Sponge Iron Lumps; PB 2 – Product Bunker
for Sponge Iron Fines; PB 3 &
PB 4 – Bunkers for Dolo Char
5.2 INDUCTION FURNACE
In addition to the existing 4 Nos. 7 T Induction Furnaces, it is proposed to install one (1) more
7 T Induction Furnace under expansion. With installation of above, Steel Making Capacity of
the Plant will increase from present 54,000 TPA to 1,10,000 TPA Liquid Steel. Liquid Steel
will be cast into MS Billets (100x100mm, 125x125 mm & 160x160 mm) in the existing 2
Strand Billet Caster which has sufficient in-built capacity to produce 105,000 TPA MS Billets.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 20
The process flow sheet for steel making and continuous casting is shown below.
Steel Making by Induction Furnace
Induction Furnace (IF) is used for melting of metals and holding it in liquid condition.
Due to improved reliability and technological advancement of power electronics, Inverters
are now available at economical rate and application of Induction Furnace has spread widely
for Steel Making.
Melting the Charge
Sponge Iron (80%), Pig Iron and Scrap constitute major raw material for steel making in the
induction furnace. This is because elimination of some element from the molten steel is
difficult in an induction furnace melting. In the case where these are present in high
quantities, a secondary metallurgical unit (Ladle Refining Furnace etc.) is required to refine
the metal up to a desired extent. The only exception is phosphorus, when present in the
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 21
molten metal cannot be eliminated even with the help of a secondary refining unit and thus
procurement of the appropriate kind of raw material is of utmost importance in Induction
Furnace melting practice.
The charge should be compact. It should consist of good quality sponge iron mixed with
clean turnings, pig iron and a moderate amount of heavy melting of commercial grade scrap.
This is to provide the initial conditions of a high flux path through the charge for facilitating
generation of heat and commencement of melting.
The process for manufacturing steel in IF may be broadly divided into the following stages:
i) Melting the charge mix and
ii) Ladle teeming practice for Casting
Induction Furnaces are Steel Framed and rugged in construction. It consists of a Coil, which
works like Primary Coil of a Transformer. The Coil is lined with Refractory Material. Charge to
be melted is put inside the lined Coil. The Charge acts like Secondary Coil of the
Transformer.
The furnace is switched on, current starts flowing at a high rate and a comparatively low
voltage through the induction coils of the furnace, producing an induced magnetic field inside
the central space of the coils where the crucible is located.
As the magnetic fluxes pass through the scrap and complete the circuit, they generate induce
eddy current in the scrap. This induced eddy current, as it flows through the highly resistive
bath of scrap, generates tremendous heat and melting starts. Melting rate depends primarily
on the density of magnetic fluxes and compactness of the charge. The magnetic fluxes can
be controlled by varying input of power to the furnace, especially the current and frequency.
In a medium frequency furnace, the frequency range normally varies between 150-10K
cycles per second. Heat is developed mainly in the outer rim of the metal in the charge but is
carried quickly to the center by conduction. A metal pool is quickly formed at the bottom
causing the charge to sink. At this point remaining charge mix is added gradually. The eddy
current, which is generated in the charge, imparts a motor effect on the liquid steel, which is
thereby stirred and mixed and heated more homogeneously. This stirring effect is inversely
proportional to the frequency of the furnace. Furnace frequency is selected in accordance
with the purpose for which the furnace will be utilized.
The melting continues till all the charge is melted and the bath develops a convex surface.
However, as the convex surface is not favorable to slag treatment, the power input is then
decreased to flatten the convexity and to reduce the circulation rate when refining under a
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 22
reducing slag. The reduced flow of the liquid metal accelerates the purification reactions by
constantly bringing new metal into close contact with the slag. Before the actual reduction of
steel is done, the liquid steel which might contain some trapped oxygen is first treated with
some suitable deoxidizer. When no purification is attempted, the chief metallurgical
advantages of the process attributable to the stirring action are uniformity of the product,
control over the super heat temperature and the opportunity afforded by the conditions of the
melt to control de-oxidation through proper addition of deoxidizer.
At the end slag is skimmed off and necessary alloying elements are added. When these
additives have melted and diffused through the bath, the power input may be increased to
bring the temperature of metal to the point required for pouring. The current is then turned off
and the furnace is tilted for pouring into a ladle. After pouring of metal, slag adhering to the
wall of the crucible is scrapped out and the furnace is prepared for next charging cycle.
As the furnace is equipped with a tight cover over the crucible, very little oxidation occurs
during melting. Such a cover also serves to prevent cooling by radiation from the surface of
the molten metal. Hence, the use of slag covering for preventing heat loss and protecting the
metal is unnecessary. Another advantage of the induction furnace is that there is hardly any
melting loss compared with Arc Furnace.
Ladle Preparation
Adequate number of bottom pouring and refractory lined ladles will be provided for tapping of
liquid steel from Induction Furnaces. After teeming of liquid steel from ladles into CCM, ladles
are cleaned by removing skull and refractory lining is patched up as required. The ladle is
then preheated, as and when necessary, in oil fired ladle pre-heaters to a maximum
temperature of about 1000°C. Preheating of ladle is done to reduce the thermal shock to the
brick lining while pouring hot liquid steel and to reduce the chilling effect. Further, preheating
will also remove any moisture from the refractory lining thus preventing explosion due to
generation of steam when liquid steel is poured.
Slide gate mechanism is adopted for bottom pouring of liquid steel from the ladle. A refractory
plate with a hole is made to slide on the nozzle surface for closing and opening of the flow of
liquid steel. Hydraulic mechanism is provided for sliding operation of the refractory plate. The
ladle is prepared after each heat by patching of its refractory lining and changing the slide
gate. These ladles are lined with basic or neutral refractory. Since the slide gate can be
changed from outside, this can be undertaken in a very hot condition of the ladle, if needed.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 23
View of a Typical Induction Furnace
5.3 CONTINUOUS CASTING MACHINE
SPSL is presently operating one 6/11 m Twin Strand Continuous Casting machine. The CCM
is having in-built capacity to produce 1,05,000 TPA MS grade Billets of 100x100mm,
125x125 mm and 160x160 mm size. As such no additional CCM is envisaged in the
expansion phase. The molten steel from the ladle is bottom poured into the Tundish of the
Continuous Casting Machine to produce billets.
The process of casting is continuous. Liquid steel is continuously poured into a ‘bottomless’
mould of CCM at the same rate as a continuous steel casting is extracted. Before casting
begins, a dummy bar is inserted to close the bottom of the mould. A ladle with hot molten
steel is lifted above the casting machine and the slide gate is opened for pouring / teeming.
As the steel’s outer surface solidifies in the mould, the dummy bar is slowly withdrawn
through the machine, pulling the steel with it. Water is sprayed along the machine to cool /
solidify the steel into billets.
At the end of the machine, the steel Billet is cut to the required length by gas torches and
transported hot to the hot rolling mill for further processing. A Reheating Furnace will also be
installed for heating cold billets prior to rolling.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 24
Schematic Flow Diagram of CCM is shown below.
1: Ladle. 2: Stopper. 3: Tundish. 4: Shroud. 5: Mold. 6: Roll support. 7: Turning zone. 8:
Shroud. 9: Bath level. 10: Meniscus. 11: Withdrawal unit. 12: Billets
A: Liquid metal. B: Solidified metal. C: Slag. D: Water-cooled copper plates. E: Refractory
material.
5.4 ROLLING MILL
SPSL has planned to set up a Rolling Mill of 1,00,000 TPA capacity for production of TMT
Bars, Rods, Strips and Structural as finished product.
Rolling of TMT product is a process of converting feed stock (billets) to desired finished
section in hot condition by way of passing the material between sets of grooved rolls (put in
pairs) and providing suitable draft at various stages. The whole rolling operation has to be
conducted at a particular temperature range and within a limited time span.
The stages of rolling operation are comprised of heating of feed stock to roll-able
temperature (in case of cold billets), rolling the feed stock in different mill stands, cropping
the hot bar during process of rolling between mill stands as necessary and subsequently
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 25
finishing same in the form of hot rolled deformed bar in straight length. The hot bar coming
out of last pass will be then conveyed through TMT Line and collected in a cooling bed after
shearing. The bars at almost ambient temperature are sheared to commercial length, stored
and kept ready for dispatch.
Rod Mill with TMT Facilities
To produce 8 to 16 mm dia. hot rolled deformed bar in straight length and converting the
same to TMT bar, it is proposed to use 1.2 M long 100 mm sq. & 125 mm sq. Billets as feed
stock. The semi continuous mills are equipped with cross-country primary & intermediate
mills followed by continuous finishing mills.
Stock Preparation
Billets shall be checked for any surface defect. Any defective cold billet should not be
charged to reheating furnace. The billets will be then stacked on charging grid of the furnace.
Billet Reheating
It is envisaged to normally feed hot Billets to Rolling Mill as it will be located near CCM. In
case cold billets are to be rolled, same will be heated prior to rolling. An Oil-fired Re-Heating
Furnace has been envisaged for this purpose.
Heat from Waste Gases coming out of Reheating Furnace will be used for preheating air
required for Oil Burners. Heat Exchangers will be installed for this purpose. Subsequently
waste gases will be let out to atmosphere through a Chimney.
Cold billets are charged from one end to oil fired reheating furnace by suitably rated pusher.
After heated and soaked to desired rolling temperature level at about 1200°C, hot billets are
side discharged at the other end. Temperature is maintained at 650°C in Heating Zone and at
1250°C in Soaking Zone. Thermo Couples are provided to measure temperature in various
zones of the Re-Heating Furnace. In order to avoid de-carburisation on heating, the ingots
are heated slowly and uniformly up to 800°C and then rapidly to 1200°C. At this temperature,
ingots are soaked properly for maintaining almost uniform temperature across the cross-
section for better deformation during rolling. After soaking, billets are discharged to a delivery
table and from where with the help of roller table the billets are conveyed to the roughing mill
stand.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 26
Rolling
A Y-table is connected at entry side and a drop wall arrangement at exit side of the first 400
mm Roughing Mill stand. Hot billets directly from CCM or cold billets after heating in the
reheating furnace is first conveyed over Y-table and enters to top pass of Roughing Mill
Stand-I. The bar coming out shall turn 90° over drop wall and fall on delivery roller table and
enter the bottom pass. The bar will be conveyed out of bottom of Y-table through flap and
allowed to travel over Y-table for top pass. Such to and fro rolling in top and bottom passes in
the first stand shall be carried out till a definite square section shall be obtained in 6th pass.
The bar will be then fed to 7th pass at top to get an oval pass and then will be allowed to feed
to bottom pass of Roughing Mill Stand-II over a repeater for formation of a square. In
Roughing Mill Stand-III an inter-stand repeater has been provided and as such the square
thus formed shall be fed to top pass of same stand for formation of an oval. The oval bar will
then be allowed to pass through one pass in each 280 mm Intermediate Mill comprising
four stands. Repeaters are provided on either side of mill stands for material transfer. The
oval bar coming out of second stand of Intermediate Mill shall be conveyed to pass through
two 260 mm stands of First Continuous Finishing Mill and with a repeater the bar will pass
through to 260 mm stands of Second Continuous Finishing Mill form where 8 mm dia. Hot
rolled ribbed bars shall be produced. The higher sizes of the deformed bar shall be finished
from last stand of First Continuous Finishing Mill.
The roughing mill speed shall be 125 rpm. The roughing mill stands shall be driven by a 1000
HP A.C. motor through pinion stand & gear box. The four (4) stands of intermediate mill shall
be driven by a 800 HP motor through pinion stand & gear box. A speed increaser drives the
first continuous finishing mill while a 600 HP A.C. motor drives each stand of second
continuous mill. Depending upon the requirement, the speed in these stands can be adjusted
during process.
Thermo Mechanical Treatment (TMT)
It is a metallurgical process that combines mechanical process with thermal process where
low carbon bars are quenched in a controlled manner to produce high strength bar. The
quenching converts bar’s surface layer to martensite and causes it to shrink. The shrinkage
pressurizes the core, helping to form the correct crystal structures. The core remains hot and
its micro structure is austenitic. A microprocessor controls the water flow to the quench box,
to manage the desired temperature difference through the cross-section of the bars. As the
bar cools, heat flows from the bar's centre to its surface so that the bar's heat and pressure
correctly tempers an intermediate ring of martensite and bainite. Finally, the slow cooling in
the cooling bed automatically tempers the austenitic core to ferrite and pearlite. These bars
therefore exhibit a variation in microstructure in their cross section, having strong, tough,
tempered martensite in the surface layer of the bar, an intermediate layer of martensite and
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 27
bainite, and a refined, tough and ductile ferrite and pearlite core. This is the desired micro
structure for high quality construction rebar. TMT bars resist corrosion better than cold,
twisted and deformed (CTD) bars. Prodtion of TMT Bar will cover Fe: 415/500/550/600
grades.
A Crank type Flying Shear cuts the bars to suit cooling length. For production of 8 & 10 mm
deformed bar, the finishing speed is about 14.7 m/s & 10.0 m/s respectively. However, it is
always necessary to reduce its speed to the acceptable limit of cooling bed. The cut piece
from flying shear shall be allowed to pass through a pinch roll and a tail end speed breaker.
The breaker engages and rebases for a brief period depending upon bar speed and bar
length. The breaker can take two bars at a time and engage/disengage of breaking of these
bars can be taken up independently. After releasing, the breaking bar will smoothly enter into
the cooling bed. In cooling bed the cut pieces are stored for a pre-determined period of time
for further surface cooling to ambient temperature. However, here the heat from the core of
the bar will flow to the surface causing tempering. With the ambient cooling in cooling bed the
hardened zone is tempered by temperature homogenization in the cross-section and the
austenitic core is transformed to fine grained ferrite-pearlite. The bar is then conveyed to a
roller table to shear to cut to commercial length. The cut pieces are then stored and kept
ready for dispatch.
Changes in micro structure of TMT Bars at different stages of processing are shown below.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 28
Rolling Mill Process Flow Sheet for Production of TMT Bars & Rods is shown below.
5.5 SINTER PLANT
Sinter Plant is an excellent scavenger in a Steel Plant. It uses all raw material fines and dusts
generated in the plant (during handling and operation) and convert same into agglomerate
that can be reused in steel making / Ferro Alloys production. It is proposed to install one 35
TPD Pot Type Sinter Machine under Expansion Phase of the Mini Steel Plant.
Fines, generated during handling of Iron Ore Lumps and Pellets and other Raw Materials and
Dust and sludge from Process and waste gases captured in cyclones, bag filters and Electro
Static Precipitators will be utilised as feed-mix in Sinter Plant in effective manner. Scales
generated in CCM and Rolling Mill will also be utilised thereby solving disposal and
environmental problems of Solid Wastes. The Agglomerate Sinter produced will be used in
the Charge Mix of SAF.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 29
Iron ore lump / pellet fines, mill scale as well as dust and sludge ESP will be thoroughly
mixed with water and fuel (coke breeze and coal fines) in a rotary mixer and placed in a pot
having perforations at the bottom. Upward and downward suctions are employed for drying,
preheating and sintering and also preheating of air. Sinter Cakes formed are then removed
from Pots, broken and sent to SAF as feed.
Adequate Dedusting facilities (cyclones, bag filters) will be installed before the waste flue
gases are let out to atmosphere through a Stack.
5.6 SUBMERGED ARC FURNACE (SAF)
Ferro alloys are intermediate products used in steel making as deoxidizers and as a specified
addition to give particular properties to the steel. Ferro Alloy Industry is an essential and vital
industry producing basic alloys, which are required for the growth of the steel industry. With
Increase in domestic steel production, requirement of Ferro Alloys also increases. Ferro Alloy
industry in India is making inroads into exports market as well.
Demand for medium carbon Si Mn and low carbon Si Mn has gone up due to usage of these
Ferro-alloys in stainless steel making. Silico Manganese is an alloy containing high amount of
manganese and silicon. It finds extensive applications as deoxidizer and an alloying element.
Under Product Diversification, SPSL proposes to manufacture 12,960 TPA Silico Manganese
(Si Mn) by installing 2 Nos. 4.5 MVA Submerged Arc Furnace (SAF) in the Mini Steel Plant at
Mirzapur Village. Depending on Market Demand it will be possible to produce Ferro Chrome.
Production of Ferro Alloys is highly energy intensive process. Si Mn will be produced by
carbo-thermic reduction of oxidic raw materials in SAF. Same type of furnace is also used for
production of other Ferro Alloys.
Raw materials required for production of Si Mn in SAF are Mn Ore, Mn slag from Fe Mn
operation, Iron Scrap, Quartzite, dolomite and Pearl Coke. Low volatile coal is also used as a
source of carbon for reduction. Sinter produced utilizing Iron ore fines, scales and dust in Mini
Steel Plant will also be used as Raw material.
Raw materials from Storage Yards are brought to a Ground Hopper. It is then conveyed to
Raw Material Storage Bins. Mix Material after weighing, batching and blending is taken to
Charging Hoppers above SAF furnace. The mix is then gravity-fed through a feed chute.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 30
The principle of a conventional SAF is electric resistance heating. Electric energy is
converted into heat & reduction energy by using the resistance (R) of the molten slag and
reinforced by the electrical resistance of an arc between the slag and carbon electrodes.
During the initial period of melting, the applied power is kept low to prevent damage to
furnace walls and the roof from radiation, while allowing the electrodes to bore into the
mixture of raw materials. As soon as the arcs have become shielded by the surrounding raw
material mixture, the power is increased to complete melting. As the charge enters the
smelting zone, the alloy formed by chemical reactions of the oxides and the reductants, being
heavy, gradually settles at the bottom. At regular intervals the furnace is tapped. The tap-hole
is opened by oxygen lancing pipe and after tapping is completed, it is closed by clay plugs.
The liquid Ferroalloy is collected and cast in dressed beds. After solidification the cakes are
broken manually to required lump size.
Unlike in EAF, the electrodes of SAF penetrate the raw material. The lower ends of the
electrodes are maintained at about 0.9 to 1.5 meters (3 to 5 feet) below the charge surface.
Normally the slag penetrates into this coke bed, but not as far as to be in contact with the tip
of the electrode. Reaction gases from the smelting zone, mainly CO gas, pass upwards
through the descending raw materials partly preheating them giving off its sensible heat and
partly causing solid state reduction of the higher iron oxides.
However, the thickness of the zone where materials are heated to reaction temperature is so
small that the gases do not have sufficient retention time to give an extensive reduction. 10 -
20 % pre-reduction is normal in cold charge operation.
Without considering the power factor on the electric grid, the ohmic resistance on the hearth
and the allowable amperage in the electrodes are the determining parameters for the load in
a furnace. However, the effect of a low power factor can easily be compensated by
installation of capacitor banks to correct the power factor on the grid.
The quality of the raw material has the biggest impact on the process. The physical
properties determine whether the SAF can run in the (i) conventional resistance mode using
the electrical resistance of slag, or (ii) shielded arc mode using the electrical resistance of the
slag and arc or using the electrical resistance of the feed mix.
High-carbon Silico-Manganese is made in 4.5 MVA SAF operating at a voltage of 90-100
Volt.
The charge for making high-carbon Silico-Manganese is composed of manganese ore,
Quartz and coke.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 31
Silico Manganese will contain 60 -70% Mn and 14-18%Si, 0.04% S and o.25-0.30% P.
In the Ferro Silicon process, the important reactions are:
SiO2 + C = SiO + CO
SiO + 2C = SiC + CO
2SiO2 + SiC = 3SiO + CO
SiO + SiC = 2Si + CO
The following processes take place when making high-carbon Silico Manganese:
(a) Removal of volatiles and moisture from the charge and heating of the charge
(b) Reduction of iron and manganese ores with simultaneous formation of metal carbides
(c) Melting of the elements reduced with the formation of molten metal
(d) Formation and melting of slag and
(e) Reduction of Manganese and silicon from the slag.
Features of SAF
SAF comprises a circular shaped furnace shell with separate tap holes for slag and metal.
The furnace is lined with fire bricks, silicon carbide bricks and carbon tamping paste.
Furnace Shell is water cooled by a special sidewall cooling system. The shell bottom is
cooled by forced air ventilation. The electrodes are consumed by the furnace bath. The self
baking electrodes with casings are periodically extended by new pieces. The electrode is
semi automatically slipped into the bath with the furnace at full electric load and with no
interruptions of the furnace operation.
The electrode column assemblies contain all facilities to hold, slip, and regulate the
penetration into the bath. All electrode operations are performed hydraulically. The electric
power is supplied from the furnace transformer via high current water cooled flexible bus
tubes at the electrodes and the contact clamps to the electrodes. The major normal features
of AC based furnaces are as follows
Low maintenance electrode columns for various electrode types
Fail safe, robust designed electrode holding and slipping device
Robust furnace design does not allow bulging/movement
Hollow electrode charging system
Gas tight water cooled roof design provides high quality CO rich gas
Application of energy recovery system possible
Presently more than 99 % of Ferro Alloys production is carried out in AC Submerged Arc
Furnaces.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 32
View of a Typical Submerged Arc Furnace
Adequate Pollution Control Facilities like Smoke Hood, Spark Arrestor, Forced Draft
Cooler/Heat Exchangers, Cooling Towers, Cyclone, Bag Filter, ID Fan and Chimney will be
installed.
Slag Processing Unit
To recover metallic Iron (scrap) from slag generated in Induction Furnaces and SAF, a Slag
Processing Unit is be installed, capacity of same will be augmented as required under
expansion.
5.7 POWER PLANT
SPSL is already operating one 8 MW Power Plant. It is designed based on Steam generated
from existing WHR Boilers (3 Nos.) and AFBC Boiler (1 No.).
About 72.5 TPH Steam will be generated from existing WHR Boilers (3x4.5 TPH), existing
AFBC Boiler (1x24 TPH) and Proposed WHR Boiler (1x35 TPH). This will be sufficient to
generate 16 MW Power. It is therefore proposed to increase Power Generation Capacity from
present 8 MW to 16 MW by installing 1x8 MW TG Set.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 33
Configuration of WHR Boilers is shown Table 5.2
CONFIGURATION OF WHR BOILERS: TABLE 5.2
SL.
NO.
UNITS FACILITIES WASTE GAS
GENERATION
EXISTING FACILITIES
1
WHR
BOILERS
3 NOS.
(ONE FOR
EACH 50
TPD DRI
KILNS)
3X12,000
NM3/HR AT
900-1000 °C
PROPOSED FACILITIES UNDER EXPANSION
2
WHR
BOILER
1 NO.
(ONE FOR
350 TPD DRI
KILN)
1X90,000
NM3/HR AT
900-1000 °C
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 34
6.0 RAW MATERIALS, CHEMICALS & UTILITIES
All Existing Service Facilities and Utility Systems in the Plant will be suitably augmented.
In addition, New Facilities will be created to cater to requirement under Expansion.
6.1 RAW MATERIALS
The major raw materials to be handled will consist of Iron Ore Lump / Pellet, Non Coking
Coal, Dolomite, Pig Iron, Ferro Alloys etc. The annual requirement of raw materials and their
sources are shown in Table 6.1
SOURCES AND ANNUAL REQUIREMENT OF RAW MATERIALS: TABLE 6.1
SUBMERGED ARC FURNACE (2X4.5 MVA)
(RAW MATERIAL REQUIREMENT SHOWN HERE IS FOR SI-MN PRODUCTION)
1 QUARTZITE 4,000 MARKET
2 MANGANESE ORE 6,400 MARKET
3 COKE 6,500 MARKET
SL.
NO.
RAW MATERIALS ANNUAL
REQUIREMENT
IN TPA
SOURCE
DRI PLANT (3X50 TPD + 1X350 TPD)
1. IRON ORE LUMP /
PELLET
2,25,000 MARKET
2. COAL 1,50,000 MARKET / SOUTH AFRICA
3. DOLOMITE 4,500 MARKET
INDUCTION FURNACE (4X7 T + 1X6 T)
1. SPONGE IRON 1,00,000 IN HOUSE GENERATION
2. STEEL SCRAP 6,000 IN HOUSE GENERATION
3. PIG IRON 20,000 MARKET
4. FERRO ALLOYS 1,500 MARKET
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 35
4 PIG IRON 1,300 MARKET
5 MN. SLAG 18,000 MARKET
6 DOLOMITE 3,500 MARKET
7 SINTER 3,500 IN HOUSE PRODUCTION
FROM RAW MATERIAL FINES
AFBC BOILER (1X24 TPH)
1 DOLOCHAR 45,000 IN PLANT GENERATION
2 COAL/HUSK 20,000 IN PLANT GENERATION,
MARKET
Raw materials will be received at plant site by road. All the trucks for raw material and
finished product transportation shall comply with the applicable environmental norms.
Liquid Steel from Induction Furnaces will be converted into MS Billets in the Continuous
Casting Machine. MS Billets from CCM will be fed to Rolling Mill for producing Long Products
(TMT Bars, Rods, Flats and Structurals)
6.2 FUEL
For meeting the requirement of Furnace oil and Light Diesel Oil of the plant, adequate
infrastructure in terms of tanks, pumps, pipe lines and dispensing units have been set up
which shall be further augmented to meet the requirements at Expansion Stage. The required
fuel is being sourced locally from Indian Oil Corporation.
6.3 WATER
Water systems of the Plant shall comprise of the following:
Make-up water
Re-circulating water
Once through water
Emergency water
Drinking water
Fire water
Dust suppression water
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 36
Water will be mainly required for cooling of equipment, dust suppression etc.
Space provision has been kept in the Plant General Layout for installation of an intake well
pump, raw water treatment plant, ground reservoir etc.
Emergency water system:
Emergency water will be required to cool the vital parts of cooler during the transition period
between normal power failure and emergency power supply. Emergency water will also be
required for cooling of vital equipment of other Production Units.
Emergency water shall be supplied from a structural overhead tank.
Drinking and sanitary water system:
Drinking and sanitary water requirement for the plant is met from drinking water overhead
tank. A portion of the make-up water is chlorinated by gaseous or liquid type chlorinator and
is stored in the above overhead tank for further distribution to consuming points and for fire
fighting.
Fire water system:
The emergency water pipelines will be led throughout the steel division complex for fire
fighting. These fire fighting pipelines will be connected to the emergency water storage tank.
In addition to the fire fighting pipelines, additional fire hydrants would also be provided at
suitable locations.
Distribution pipe work:
In general, mild steel pipes are considered for re-circulating and make-up water piping.
Mainly buried pipes are considered except for shop internal pipes. Pipe work shall comprise
all necessary valves, fittings, hydrants etc.
Source of water
Ground water will be used for meeting the daily make up water requirement of the plant. As
per initial estimate, additional make up water to the tune of 160 cu.m /day will be needed for
the proposed expansion including 10 cu.m /day for in-plant domestic use. Total make-up
water requirement for the Plant after Expansion will be 365 cu.m /day
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 37
The estimated unit wise and phase wise (existing and expansion) make up water requirement
for the Mini Steel Plant are given in Table 6.2
RAW WATER DEMAND: TABLE 6.2
Sl.
No.
Description Water
Demand for
existing
plant
(in cu.m/day)
Water
Demand for
expansion
(in
cu.m/day)
Daily Total
Water Demand
(in cu.m/day)
1. Sponge Iron Plant
(3x50 TPD + 1x350 TPD)
21.0 49.0 70.0
2. Steel Melting Shop
(Induction Furnaces [5x7
T] + Twin Strand
Continuous Billet Caster)
10.0
10.0
20.0
3. Rolling Mill (1,00,000
TPA)
NIL 13.0 13.0
4. Captive Power Plant
(8 MW+8 MW)
160.0 60.0 220.0
5 Submerged Arc Furnaces
(2X4.5 MVA SAF) + Sinter
Plant
NIL 18.0 18.0
6. Domestic 14.0 10.0 24.0
TOTAL 205.0 160.0 365.0
The Company has the sanction to operate 2 Bore Wells for groundwater withdrawal.
Permission will be taken for sinking additional Bore Wells to meet increased make up water
demand of the Plant under expansion.
6.4 OTHER UTILITIES
COMPRESSED AIR SYSTEM
Major utilization of compressed air will be in pneumatic cylinder of various plant units and
especially for rotary shears in Rolling Mill. Air receiver with adequate capacity will also be
provided to cope up the temporary peak requirement of various units. The compressors,
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 38
dryers and associated pipe work will be located in one place, within a building. Compressed
air to various consumers will be distributed through compressed air piping system.
AIR CONDITIONING AND VENTILATION SYSTEMS
Ventilation system with fan-filter units will be provided for protection of equipment from
excessive thermal loading. These systems will generally be installed in the electric rooms
and other closed premises requiring protection of equipment.
Air conditioning will be provided in the plant control rooms, PLC room, laboratory and Plant
offices and Administrative Building. The air conditioning will be achieved by providing window
model/package type air conditioners.
COMMUNICATION SYSTEM
Suitable communication network has been envisaged for quick transmittal of information
within the plant. The network shall contain automatic internal telephone system (PAX) and
two-way audio communication system.
AUXILIARY FACILITIES
Various services facilities like repair and maintenance shop, central stores, administrative
building, canteen, guesthouse, time office, laboratory etc. will be provided during
construction of expansion phase.
6.5 POWER
The estimated power demand of the Mini Steel Plant after expansion will be 24.5 MW. The
power requirement will be met from Captive Power Plant which will generate 16 MW after
proposed expansion. Balance Power will be drawn from nearby grid of WBSEB / DVC.
Total Power Demand and unit wise and phase wise (existing and expansion) breakup for the
Mini Steel Plant is shown Table 6.3
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 39
POWER DEMAND WITH UNIT WISE BREAKUP: 6.3
SL
NO
UNITS
POWER
DEMAND
FOR
EXISTING
PLANT
ADDITIONAL
POWER
DEMAND FOR
EXPANSION
TOTAL
POWER
DEMAND IN
MW
1. Sponge Iron Plant
0.65 1.50 2.15
2. Steel Melting Shop and
Continuous Billet Caster
5.0
5.0
10.0
3. Rolling Mill NIL 3.0 3.0
4 SAF and Sinter Plant NIL 6.0 6.0
5. Captive Power Plant
(in-house consumption)
1.0 1.0 2.0
6. Auxiliary & other loads 0.7 0.65 1.35
TOTAL 7.35 17.15 24.5
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 40
7.0 ENVIRONMENTAL ASPECTS
This chapter covers all aspects of pollution – sources and nature of pollution & proposed
measures required for meeting the prevailing statutory requirements of gaseous emissions,
solid wastes and waste water discharge characteristics, noise level etc. for environmental
management purpose in connection with the installation and operation of Mini Steel Plant
under Expansion Phase.
Salagram Power and Steel Pvt. Ltd. operate the Mini Steel Plant at Palitpur Road,
Dewandighi Village. The Company is well aware about the importance of Pollution Control.
The Company has installed adequate Pollution Control Measures in this Plant. Strict
Monitoring is done regularly through Approved Agencies/Laboratories of WBPCB. WBPCB
also checks whether pollution levels are within Stipulated Norms and issues Analyses and
Test Reports to the Company. Based on various Reports, WBPCB on 29.06.2016 has
granted the Company “Consent to Operate” this Plant for 3 years from 01.07.2016 till
30.06.2019.
In general Pollution Prevention and Control Measures are enumerated as below:
Genesis of Pollution:
The genesis of industrial pollution can be assessed from the project concept described in
earlier chapters. The specific aspects, which need to be looked into for assessing the
pollution potential, are:
(i) Physical and chemical characteristics of raw materials,
(ii) Manufacturing technology involving a set of physical and chemical conversions of
raw materials and
(iii) The generation of all types of wastes, namely, gaseous, liquid and solid having
specific characteristics.
The pollutants in the form of solids, liquids and gases are expected to be generated from
various Units of the proposed Steel Plant. Release of such pollutants without proper care
may affect the environment adversely. Pollution of the environment not only adversely affects
the human beings, flora and fauna but also shortens the life of plant and equipment. This vital
aspect, therefore, has been taken into account while planning the plant and equipment and
adequate measures have been proposed to limit the emission of pollutants within the
stipulations of statutory norms.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 41
7.1 AIR POLLUTION CONTROL
Air pollution is of two categories:
i) Pollution from Process Emissions and
ii) Pollution from Non-process Emission
Process emissions arise during production/operation of the plant while non-process
emissions are generated during handling of various raw materials. The main air pollutants
from process emissions would be SO2, NOx and to some extent Particulate Matter while for
non-process emission the main pollutant would be Particulate Matter.
A number of systems have been proposed for air pollution control which will provide safe
environmental conditions in the working area and will ensure acceptable air quality in the
surrounding area of the steel plant. Different air pollution control facilities / equipments that
would be considered include dry fog dust suppression systems, dust extraction systems,
cyclones, bag filters, ESP etc. Cleaned waste gases would be discharged through
Stacks/Chimneys, of adequate height commensurate with Norms, to ensure adequate
dispersion and dilution of pollutants.
The Company presently operates a Captive Power Plant of 8 MW Capacity based on steam
generated in 3 WHR Boilers and an AFBC Boiler. Adequate Pollution Control Measures have
been installed for all above facilities.
In the Expansion Phase, no additional TG Set is planned and Capacity of Power Plant will
remain at 8 MW. However, WHR Boilers will be installed to utilise Waste Gases from 2x100
TPD DRI Kilns. Steam generated in these two (2) WHR Boilers will help in Steam Balance
and the Company will avoid purchase of costly fuel (coal/husk). Adequate Pollution Control
Equipment have been planned for new WHR Boilers.
Contribution to air pollution would be from Particulate emission from the stack and this would
be governed according to the Central Pollution Control Board Emission Regulation.
Cyclones, Bag Filters and Electrostatic Precipitators (having efficiency of 99.89% or better)
will achieve the limit of particulate emission within Environmental Norms.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 42
7.2 WATER POLLUTION CONTROL
Waste water generated from the different areas of the plant will be treated to the desired
extent in suitable treatment facilities and recycled back to the process, as far as practicable.
This will ensure adequate reuse of water in the respective re-circulating systems and
economizing on the make-up water requirement.
Sewage generated from toilet blocks etc. shall be treated in the existing Sewage Treatment
Plant (which will be augmented as required) and the treated effluent shall be collected in the
existing sump, located in a low lying area. The water thus collected shall be used for dust
suppression at raw material handling system, landscaping etc.
Thus, Water system will be designed for “Zero Discharge” wherein all discharges will be
treated and reused in the plant.
Surface run-off will be settled in a settling basin prior to reuse/ disposal.
7.3 SOLID WASTE MANAGEMENT
Adequate Dust Extraction Systems (cyclones, bag filters and ESP) will be planned. All dust
captured in these Pollution Control Equipment will be used in Sinter Plant.
Dolo-char generated in DRI units will be used in AFBC boiler. The fly ash generated will be
stored in ash silo and sold as a raw material for cement plants and also used for brick
manufacturing and land filling.
The hot slag generated from IF and SAF will be transferred to slag yard after cooling and
scrap recovery. It will be used as construction material/sold to cement manufacturers.
Mill scales generated from CCM and RM will be used in sinter plant.
Scraps (Billet crops, end cuts in Rolling Mills etc.) will be used in Charge Mix of Induction
Furnace.
Thus all solid wastes generated in the Plant will either be reused / recycled in various
Production Units or will be sold / utilised for land filling and other gainful purposes.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 43
7.4 NOISE POLLUTION CONTROL
Noise generation will be considered while selecting equipment. Equipment would not
generate noise more than 85 dB (A) at 1 m distance. Wherever required noisy equipment will
be placed on vibration isolators or housed in a separate enclosure or surrounded by baffles
covered with noise absorbing material. As the operator would be stationed in the control
room, there will be minimum chance of exposure to high noise levels. However personnel
working in high noise zones will be provided with personal noise protection equipment (e.g.
ear muffs, ear plugs) and their duty hours will be regulated to control noise exposure levels.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 44
8.0 FIRE PROTECTION SYSTEM
In addition to the yard fire hydrant system, the fire protection systems envisaged for the plant
are as follows:
Internal fire hydrant for multi storied buildings to be tapped-off from the outdoor fire
water header
Fire detection and alarm system for electrical rooms, cable basements/cellars, cable
tunnels, selected oil/hydraulic cellars
Portable fire extinguishers such as CO2, foam and dry chemical powder in all areas of
the plant with fire hazard.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 45
9.0 GREEN BELT DEVELOPMENT OBJECTIVE
To capture the fugitive emission, if any from the plant and to attenuate the noise generated
from the plant machinery, and to improve the aesthetics of the plant site, a green belt will be
developed within the plant area.
The green belt is a set of rows of trees planted in such a way that they form an effective
barrier between the plant and the surrounding. Prevalent wind directions shall be taken into
considerations to ensure adequate capture of the air pollutants around the Plant.
Open spaces, where tree plantation is not possible shall be covered with shrubs and grass.
The plantations shall match with the general landscape of the area and be aesthetically
pleasant. Adequate attention will be paid to planting of trees and their maintenance and
protections.
SPSL is presently having 25.8 Acres of Land. Additional 3 Acres will be acquired. Out of 28.8
Acres, Green Belt Cover will be about 10.0 Acres (more than 33% of total area).
The plant layout showing the proposed facilities with Green Belt area has been shown in
Drawing No. KKS/SPSL/2017/L-0 Rev.2
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 46
10.0 RAIN WATER HARVESTING
It is proposed to achieve proper utilization of rain water by harvesting through rainwater
harvesting mechanism in the plant area. Rain water harvesting will be done following the
guidelines of the concerned Authority.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 47
11.0 MANPOWER REQUIREMENT
Operation and maintenance of proposed plant require human resources in different
categories like managers, engineers of different discipline like metallurgical, mechanical,
electrical, electronics, computer, civil, structural, chemical, etc., highly skilled, skilled and
semi-skilled work force in different disciplines, commercial, accountants and financial
managers, unskilled labour force, clerical, security personal, etc.
Factory human resources
In order to operate and maintain the plant facilities, including its technical and general
administration needs, the estimated additional manpower requirement for the proposed
project has been estimated to be 334 persons (including 195 through Labour Contractors).
This is over and above existing manpower of 596 persons (including 405 through Labour
Contractors) employed at present.
The above estimate covers the top management, middle and junior level executives and
other supporting staff.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 48
12.0 PROJECT SCHEDULE
The installation of several production units along with utilities and services will involve award of
all contracts, procurement of plant and equipment, construction & erection and supervision of
all activities at plant site.
The factors which are responsible for timely implementation of the project are :
i) Arrangement of proper finance for the project.
ii) Finalization of layout of the proposed plant.
iii) Design of utilities and services.
iv) Placement of orders for plant and machinery.
v) Arrangements for Govt. sanctions and supply of power.
vi) Recruitment of personnel.
As per an initial estimate around 24 months will be needed for implementation of the
Expansion Phase of the project.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 49
13.0 FINANCIAL DETAILS
The focus of proposed project is cost reduction by producing quality material as per the
required specification. There will be complete integration right from the beginning to finished
products (viz Sponge Iron, TMT Bars & Rods and Silico Manganese/Ferro Chrome). The
estimated cost of the project is expected to be around Rs. 108 Crores.
There will be substantial savings due to the said project as company will also be eligible for
various incentives. The company has good track record of implementing and commissioning
projects within schedule time. The Company will be able to implement the proposed project
as per schedule. The total project is expected to be commissioned over a period of 24
months in phased manner. The benefit from the project planned will start accruing from very
first year of Operation Phase.
Salagram Power and Steel Pvt. Ltd.
Proposed expansion of existing Steel Plant at Palitpur Road, Village & P.O. Mirzapur, PS + District: Bardhaman, West Bengal
.
Pre-feasibility Report 50
14.0 CONCLUSION
The feasibility of the project has been examined from 3 angles, which are backbone of any
project to succeed:
Environmental feasibility
Commercial and financial viability and
Pre and post project scenario in which company will operate.
The outcome shows that results are positive which indicate a positive feasibility.
PLANT LAYOUT