Pre-feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/... · Pre-feasibility...

24
Pre-feasibility Report For Modification in existing 2.0 MTPA Deshaled Coal Crushing Unit to 2.0 MTPA Wet Coal Washery At Survey No. 131/2, 131/3, 131/4 Village: Muthara, Tehsil: Rajura, District: Chandrapur (MS) Promoter N. N. GLOBAL MERCANTILE PVT.LTD Plot No. 75/2, Wadgaon, Nagpur Road, District: Chandrapur EIA Consultant: Pollution and Ecology Control Services, Nagpur NABET No.: 111

Transcript of Pre-feasibility Reportenvironmentclearance.nic.in/writereaddata/Online/... · Pre-feasibility...

Pre-feasibility Report

For

Modification in existing 2.0 MTPA Deshaled

Coal Crushing Unit to 2.0 MTPA Wet Coal

Washery

At Survey No. 131/2, 131/3, 131/4 Village: Muthara, Tehsil: Rajura,

District: Chandrapur (MS)

Promoter

N. N. GLOBAL MERCANTILE PVT.LTD Plot No. 75/2, Wadgaon, Nagpur Road, District: Chandrapur

EIA Consultant: Pollution and Ecology Control Services, Nagpur NABET No.: 111

2

Contents 1.0 Executive Summary:........................................................................................................ 4

2.0 Introduction of the Project /Background Information ........................................................ 6

2.1 Identification of project and project proponent .............................................................. 6

2.2 Brief description of nature of the project ...................................................................... 6

2.3 Need of the project its importance to the country and or region.................................... 6

2.4 Employment Generation (Direct and Indirect) due to project ........................................ 7

3.0 Project Description .......................................................................................................... 8

3.1 Type of project ............................................................................................................. 8

3.2 General Location ......................................................................................................... 8

3.3 Details of alternate sites considered ...........................................................................10

3.4 Size or magnitude of operation ...................................................................................10

3.5 Manufacturing Process. ..............................................................................................11

3.5.1 Process Description of Dry washery ....................................................................11

3.5.2 Raw Coal receipt and arrangement ......................................................................13

3.5.3 Capacity of Main Equipment .....................................................................................13

3.5.4 Weigh Bridge ............................................................................................................14

3.5.5 Receiving Pit Hopper ................................................................................................14

3.5.6 Screening and Crushing Building ..............................................................................14

3.5.7 Sizing Double Deck Screen .......................................................................................15

3.5.8 Advantages of Washed Coal: ...............................................................................17

3.6 Raw Material requirement ...........................................................................................17

3.6.1 Raw material requirement and its sources ..........................................................17

3.6.2 Mode of Transport for raw material and finished product .....................................17

3.6.3 Market of Final Product ........................................................................................17

3.7 Availability of water its source, Energy/power requirement and source .......................17

3.7.1 Water requirement and its sources ......................................................................17

3.7.2 Source of Energy/power ......................................................................................18

3.8 Generation and disposal of waste ...............................................................................18

3.8.1 Waste water Generation .....................................................................................18

3.8.2 Solid Waste Generation and its disposal ...................................................................18

3.8.3 Air Pollution Control / Management ...........................................................................18

4.0 Site Analysis ...................................................................................................................19

4.1 Connectivity ...............................................................................................................19

3

4.2 Land Form, Land Use and Land ownership ................................................................20

4.2.1 Land Form ...........................................................................................................20

4.2.2 Land use of the Project site ..................................................................................20

4.3 Topography.................................................................................................................20

4.4 Existing land use pattern ............................................................................................20

4.4.1 Land use pattern of the project site ......................................................................20

4.5 Existing Infrastructure .................................................................................................20

4.6 Soil Classification ........................................................................................................21

4.7 Climatic data from secondary sources ........................................................................21

5.0 Planning brief .................................................................................................................21

5.1 Planning Concept .......................................................................................................21

5.2 Population Projection ..................................................................................................21

5.3 Amenities/Facilities .....................................................................................................21

5.4 Green Belt ..................................................................................................................22

5.5 Social Infrastructure ....................................................................................................22

5.6 Drinking Water Management ......................................................................................22

5.7 Solid Waste Management ...........................................................................................22

6.0 Rehabilitation and Resettlement Scheme: ......................................................................22

7.0 Project Schedule & Cost estimates ................................................................................22

7.1 Likely date of start of construction ...............................................................................22

7.2 Estimated Project Cost ...............................................................................................23

The estimated project cost is about Rs.9.5 Cr. approx. ..........................................................23

8.0 Analysis of proposal .......................................................................................................23

8.1 Financial and social benefit .........................................................................................23

8.2 Socio-Economic Development Activity ........................................................................23

4

1.0 Executive Summary:

Sr. No. Description Details

1 Name of The project Modification in existing 2.0MTPA Deshaled crushing unit

to 2.0MTPA Wet coal washery.

2 Location Survey no. 131/2, 131/3,131/4, Village: Muthara,

Tehsil:Rajura, District: Chandrapur (MS)

Geographical Co-ordinates:

Latitude: 19045’17.16’’N

Longitude: 79016’19.36’’E

3 Existing Capacity (raw

coal)

Existing Capacity: 2.0MTPA Deshaled Coal crushing

Plant

Modification in existing 2.0MTPA Deshaled crushing unit

to 2.0MTPA Wet coal washery.

4 Project Area 5.57 ha

5 Process Technology Heavy Media Bath

6 Water requirement The water requirement after modification of existing 2.0MTPA deshaled coal crushing plant to Wet coal washery will be 120m3/day , including for Industrial, Domestic and Dust Suppression purpose water will be pumped out from existing bore well in plant premises.

7 Power requirement &

Source

The total power requirement after modification will be 11KV. 400KVA transformer will be installed to be connected by isolating switch after getting approval from MSEDCL. 125KVA DG set will be provided for emergency power failure.

8 Working Hours The plant will operate in three shifts each of 8 hours for 330days in a year and approximately 6000 annual working hours i.e. effective of 18 hours in a day.

9 Rehabilitation and

Resettlement

No R & R issue involved.

10 Total manpower

(Construction and

Operation)

About 50 Construction workers for temporary period. About 51 Number of workers and staff required for operation of plant.

11 Estimated Cost of the

project (Modification Cost)

Rs. 9.5Crore including EMP.

5

Layout Plan

6

2.0 Introduction of the Project /Background Information

2.1 Identification of project and project proponent

N.N. GLOBAL MERCANTILE PVT. LTD. is a Private Limited company duly

registered under the companies Act. The directors of the company are Mr.

Inishpal Singh Bhatia, Mr. Ravinderpal Singh Bhatia.

N .N. GLOBAL MERCANTILE PRIVATE LIMITED is engaged mainly is

beneficiation and sizing of raw coal for different end users of coal. The company

supplies coal to various bulk consumers who desire quality coal. Company

acquires coal from the mines of Western Coalfields Limited (WCL) through other

available sources and supplies the upgraded coal to customers as per their size

and quality requirement.

2.2 Brief description of nature of the project

This is a modification project of existing 2.0MTPA Deshaled Coal crushing plant

to 2.0MTPA wet coal washery at survey no.131/2, 131/2, &131/4 village:Muthara,

Tehsil:Rajura, District: Chandrapur(MS).Total area of the project is 5.57ha. In

existing project coal is crushed sized as per requirement of end user. Now it is

proposed to modify the process by up gradation to wet coal washery.

2.3 Need of the project its importance to the country and or region Indian coal has drift origin, resulted in intimate mixing of mineral matter with coal,

giving rise to the ash content. The coal-ash distribution in the coal matrix in

Indian coal is so interwoven that coal is essentially required to be crushed to

small sizes for affecting liberation of coal and ash particles.

Coal beneficiation largely depends on gravity difference of coal and ash particles.

The Near Gravity Material (NGM) at any specific gravity of cut is high, which

means at any specific gravity of cut there is quite good amount of misplacement

of coal towards sink and vice versa.

7

Coal based power plants will continue to play a leading role in power generation

in our country. About 70% of country’s power is generated from coal-based

power plants. The quality of the coal plays an important role in the environmental

aspects of a power plant.

The quality of Indian coal is mainly attributed to its origin. Due to drift origin of

Indian coal, inorganic impurities are intimately mixed in the coal matrix, resulting

in difficult beneficiation characteristics. Over 200 million tonnes of coal reach the

consumers with ash content averaging 40 percent as per the CPCB report (Clean

Coal Initiatives June 2000). High ash content in the coal supplied to the power

plants not only poses environmental problems but also results in poor plant

performance and high cost for Operation & Maintenance and ash disposal.

Based on review undertaken by MOEF, use of beneficiated/blended coal

containing ash not more than 34 percent in power plants was stipulated by

MOEF vide Notification GSR 560 (E) & GSR 378 (E) dated 19th September 1997

and 30th June 1998):

Clean coal technologies are being practiced in coal washeries in India, as pre-

combustion clean coal technology, mainly focus on cleaning of coal by removing

ash from coal.

Earlier only coking coal was being washed because steel making needs coking

coal of ash of 17 to 18%. The raw coal ash in Indian coal varies from 35 to 40%.

Now-a days, Min. of Environment & Forests has put restriction on the use of high

ash coal in power sectors, which necessitated priority to wash non-coking coal

also.

In view of the above M/s N .N. GLOBAL MERCANTILE PRIVATE LIMITED has

proposed to modify the existing deshaled coal crushing plant to wet coal washery

with total annual production 2.0 Million tons.

2.4 Employment Generation (Direct and Indirect) due to project The local area will be benefited by way of generation of employment

opportunities, increased demand for local product and services. There will be an

overall improvement in the income level of the local people.

8

The project creates employment to about 51 person ones the plan comes to the

operational stage and for 50people during construction stage. Top priority will be

given to local for semi-skilled and unskilled jobs. With development of this plant

there will be lot of scope for more ancillary development, which in turns will

benefit the nation.

3.0 Project Description

3.1 Type of project This is a modification project of existing 2.0 MTPA Deshaled Coal crushing plant to 2.0 MTPA wet coal washery at village:Muthara, Tehsil:Rajura, District: Chandrapur(MS)

3.2 General Location

9

Location of project site on Toposheet

Location of Project site Covering 10Km (Google Image)

10

Environmental Setting of Study Area

Sr.No Particular Distance from the site

1 National Park = No National Park is situated within the 10 Km radial distance

2 Wild life sanctuaries = Nil

3 Eco Sensitive Area = Nil

4 River /Nallah = Nallah adjacent to boundary wall at West direction. Chinna Vagur river 7.0km at North direction Wardha River 11Km NE direction Sondo Nallah 9.0Km at South direction.

5 Costal regulation Zone = Nil

6 Industrial area = Yes

7 Industries in the vicinity = There are two coal washeries in operation at the distance of 1.0Km & 1.5 km East direction.

8 Road = Gadchandur Road 0.1Km (South Direction) (SH 264) Chandrapur Nagpur Road 9.0Km SE direction

9 Forest = Patches of Rajura (R.F) at 6.0Km NE to 7.0Km East direction

3.3 Details of alternate sites considered

The identified location of coal washery is in existing 2.0MTPA deshaled coal crushing plant. All modification activity will be done in existing plant to be modified to wet coal washery. The proposed plant site is identified considering following,

There are no National Park/Sanctuaries within 10Km radius Nearest village is situated at a distance 1.0km from project site. No forest land is involved in the site No R & R is involved. Raw Material Source Availability of water, Industrial Infrastructure. Near to Railway siding.

3.4 Size or magnitude of operation

Modification in existing 2.0 MTPA Deshaled crushing unit to 2.0 MTPA Wet coal washery.

11

3.5 Manufacturing Process. 3.5.1 Process Description of Dry washery

The Raw coal of (0-250MM) at 335 TPH fed to BC1 Belt Conveyor through

vibro feeder of 350 TPH Capacity ,fitted below 60 Tons Capacity underground

Coal receiving steel hopper and it will discharge coal to double deck primary

screen having top deck of 50 mm and bottom deck of 12/16 mm opening .The

bottom deck coal will be Conveyed through BC 3 Conveyor of 100 TPH capacity

. discharging the same to BC7 Conveyor carrying the underflow of single Deck

Screen The plus 12/16 mm coal of top deck will discharge.on 1400 mm. wide &

1200mm long Picking belt. The Extraneous materials will be manually Picked &

Stacked on ground. There will be two way chute at the Discharge point of

picking belt Conveyor to be fed either to 150 TPH Double Roll Crusher or to BC

3A bell Conveyor of 150 TPH Capacity

PROCESS FOR TWO-WAY CHUTE FEEDING TO 150 TPH D/R CRUESHR :

The plus 12/16 mm picked Coal will be fed to D/R Crusher for Crushing plus 50

mm Coal to minus 50 mm and thus 0-50 Crushed Coal will be fed to Single

Deck Secondary Screen of 150 TPH Capacity having12 mm top deck opening

The overflow of Secondary Screen of plus 12/16 mm will be conveyed by 150

TPH BC 5 Conveyor to 50 Tone Steel Hopper ( H2) for onward processing

through wet Washery . The minus 12 mm Coal ( Underflow of Secondary

Screen) along with minus 16 mm underflow of Primary Screen will be Conveyed

through BC 6 Belt Conveyor of 150 TPH Capacity to stack the same in 50 Tone

steel hopper ( H1) for dispatch to Prospective consumer.

PROCESS FOR TWO WAY CHUTE FEEDING TO BC3A CONVEYOR :

THE BC3A will discharge the Coal to Double Deck Sizing Screen having

top deck 100 mm & bottom deck of 50 mm opening .The discharge of top

deck plus 100 mm Coal will be Conveyed by BC7 Conveyor of 100 TPH

Capacity to be fed to H3 Steel hopper fitted with rake & pinion gate

12

arrangement for feeding the truck standing below H3 steel hopper.

The discharge of bottom deck of 100 THP Capacity ( 50 To 100 mm ) Coal to

be Stacked on to the ground through BC 7 Conveyer . The underflow of Sizing

Screen ( 12 To 50 mm) Coal to be conveyed by BC 8 Conveyer to be

Stacked on the ground. Latter on H4, & H5 Steel hoppers would be provided

for Stacking the discharges of BC 7& BC8 in H 4 & H 5 Steel hopper

respectively for Containing picked 50 To 100 mm & picked 16 To 50 mm Coal

for onward transport by trucks to desirous buyers.

Process Description of 2 MTPA Wet Washery:

BC10 belt of 150 TPH would draw 12-50mm size prepared coal from H3 steel

hopper of 400 Ton capacity and feed to Desliming screen of 200 Ton capacity &

the coal would be sprayed by circulating water to segregate fines from prepared

coal. The deslimed coal will be fed along with heavy media pulp to 150 TPH

Dense Media Wemco Drum Separator. The float along with media will be

discharged on 2/3rd length of 200 TPH Depulping & Ringing screen & the sink of

Wemco Drum Separator would be collected through lifter plates fitted on inner

periphery of wemco drum and will be discharged along with media on 1/3 rd

length of Pertitioned D/R screen. The media of float& sink will be depulped on

1/3rd length of D/R screen to be diverted to correct media sump. The depulped

float & sink will be sprayed with fresh water on 2/3rd length of D/R screen to

recover the media sticked on the surface of depulped float & sink and finally will

be diverted to Dliute Media Sump and would be pumped to 900mm dia x1300

long Magnetic Separator. The media recovered from magnetic separator will be

diverted to correct media sump and its tailing containing water & fine coal along

with the underflow of desliming screen will be diverted to 23 meter dia coal

thickener.

The overflow D/R screen containing clean coal and reject will be stacked on the

ground through BC11& BC12 conveyor respectively of 100 TPH capacity each.

The underflow of coal thickener would be pumped to belt filter press of 30 TPH to

recover fines as dry cake to be discharged on either to BC11 or to BC12 clean or

reject conveyor depending upon the ash percentage of dry cake.

13

There will be two emergency concrete slurry pond of 40mx5mx2.5m for recovery

of fines in emergency case when the thickener or the belt press will be under

heavy breakdown stage. When the pond will be filed up with fine coal it would be

excavated mechanically through JCB Excavator and stacked on the hard stand

built along three sides of slurry ponds. The clarified water of slurry pond will be

pumped to plant for reuse thus making the wet washery as zero discharge plant.

3.5.2 Raw Coal receipt and arrangement The raw coal will be sourced from Sasti, Gouri & Dhoptala O/C Mines of

Ballarpur Area of WCL. The beneficiated and sized coal will be dispatched from

prepared coal stocks in the premises to the cement industries/ other consumers

by Road or Rail.

3.5.3 Capacity of Main Equipment

1. Steel Hopper : 60 MT 2. Belt Conveyor BC -1 : 335 TPH 3. Vibrating Screen : 350 TPH 4. Picking belt BC- 1 A : 150 TPH 5. Crusher : 150 TPH 6. Belt Conveyor BC -2 : 200 THP 7. Belt Conveyor BC -3 : 150 TPH 8. Belt Conveyor BC -4 : 150 TPH 9. Coal Dust Collector : 28000 m3 / hr.( 28000 M3/ Hr)

10. Blet Conveyor BC- 5 : 150 THP 11. Blet Conveyor BC -6 : 100 THP 12. Belt Conveyor BC -7: 100 THP 13. Blet Conveyor BC- 8: 100 THP 14. Steel Hopper H-1 : 50 Tone 15. Steel Hopper H2 : 50 Tone 16. Steel Hopper H3 : 50 Tone

17. Proposed 2 steel Hopper : H4 & H5 ( 50 Torne each ) 18. Dense media Wemco Drum Separator: 150 TPH 19. Desliming screen : 150 TPH 20. Depulping & Ringing screen : 150 TPH 21. Magnetic separator : 900 dia x 1300 mm long 22. Correct media sump : 2 cum capacity 23. Dilute media sump : 1.5 cum capacity 24. Heavy media pump : 340 cum / hr capacity 25. Dilute media pump : 150 cum/ hr capacity 26. Coal thickener : 23 media 27. Belt filter press : 30 TPH

14

28. Emergency concrete slurry ponds : 2 nos of 40mx5mx2.5m each 29. High pressure Pump : 15 HP 30. D G Set, 3 ph : 125 KVA 31. vibro feeder : 350 TPH

3.5.4 Weigh Bridge

An electronic road weighbridge of 100 MT Capacity shall be installed near the

Muthara entry gate for weighing the Tipper / Truck.

All the vehicle carrying ROM coal from collieries will be weighed on the

weighbridge. The sized coal dispatched to consumers will also be weighed on

this weighbridge. Another electronic weighbridge of 100 TPH shall be installed on

back side to dispatch clean coal to railway siding.

3.5.5 Receiving Pit Hopper

Receiving pit Shall have a Steel hopper of size 5mx 5m x 5m having Capacity 60

MT fabricated from steel plates to be installed underground. The receiving

hopper will have three sides opening.

(As top level of Hopper is only 500 mm above ground level) for unlonding of

ROM Coal transported from the mines. Electrical Vibrator shall be fitted at the

bottom of steel hopper to feed the ROM Coal to belt conveyor BC-1.

3.5.6 Screening and Crushing Building

A 25mx6mx9m size Screening building shall be Constructed for suitably

accommodating drive arrangement of BC-1, primary vibrating Screen, tail pulley

of picking belt BC-2. The Vibrating Screen Shall be installed at 6.5 meter level.

The picking belt of 12 meter long and 1400 mm wide shall be installed at 4.8

meter level. The picking belt discharges the picked coal to crusher installed at

2.0 meter level. The crushed coal is conveyed through belt BC-3 to be

discharged on Secondary Screen.

The underflow of Screen( 0 to 13 mm) natural coal is conveyed by belt Conveyor

BC -4 to Steel hopper( H1) The picked stone & shale shall be stacked on the

ground through suitable chute.

15

Wet washery building will be built to accommodate 150 TPH Dense Media

Wemco Drum Separator, Desliming screen, D/R Screen, Magnetic Separator,

Heavy media & Dilate media sumps & pumps, 23m dia coal thickener, Filter belt

press of 30 TPH capacity , two nos of concrete emergency slurry ponds of 40m x

5m x 2.5m each.

BC10 belt conveyor will feed prepared coal (13-50 mm) to wet washery. BC11

belt conveyor of 100 TPH capacity will be stacking wet clean coal on ground as

well as BC12 belt conveyor of 100 TPH will be stacking wet reject on ground.

3.5.7 Sizing Double Deck Screen

6mX 4mX 4m steel structure will be installed for accommodating D/D Sizing

Screen, tail pulleys of BC 6, BC 7,& BC 8, Belt Conveyor and the drives of BC

6, BC 7,& BC 8, will be installed at 10 meter height respectively just to

accommodate. proposed steel hopper H3, H 4, & H5, for dispatching coal by

trucks to prospective buyer through Rake & Pinion arrangement fitted below all

three Steel Hoppers.

16

Flow Chart for Coal Beneficiation of a Coal Washery

RECEINING HOPPER

ROM ( 0 - 250 mm )

PRIMARY D/D SCREEN

PICKING BELT

PICKING BELT SIZING D/D SCREEN

H3 HOPPER H4 HOPPER H5 HOPPER

SECONDARY

SCREEN

H2 HOPPER

H1 HOPPER

DESLIMING

SCREENDENSE MEDIA SEPERATOR D/R SCREEN

BAG

FILTER

DUST COLLECTION

H.M. SUMP DM SUMP

MAG. SEP

THUKENER

BELT FILTER

PRESSREJECT

REJECT

CLEAN COAL

17

3.5.8 Advantages of Washed Coal:

Benefits of Using Washed Coal

Increased generation efficiency, mainly due to the reduction in energy loss as

inert material passes through the combustion process.

Reduced investment costs.

Reduced operation and maintenance (O&M) costs due to less wear and reduced

costs for fuel and ash handling

Energy conservation in the transportation sector and lower transportation costs

Less impurities and improved coal quality

Reduced load on the air pollution control system; and

Reduction in the amount of ash that has to be disposed off

3.6 Raw Material requirement 3.6.1 Raw material requirement and its sources

Coal will be the only raw material required for wet washery. Annual requirement of Coal is envisaged to the tune of 2.0 MTPA.

3.6.2 Mode of Transport for raw material and finished product

The raw coal will be sourced from Sasti, Gauri & Dhoptala O/C Mines of

Ballarpur Area of WCL. The beneficiated and sized coal will be dispatched from

prepared coal stocks in the premises to the cement industries/ other consumers

by Road or Rail.

3.6.3 Market of Final Product

The washed coal will be utilized as fuel in power plant and reducing agent in

sponge Iron manufacturing unit, cement industries.

3.7 Availability of water & its source, Energy/power requirement & its source

3.7.1 Water requirement and its sources It is envisages that about 120 m3 / day of water will be required for industrial,

Domestic and horticulture. The desired quantity of water will be drawn from the

existing bore well in the premises.

18

3.7.2 Source of Energy/power

11 KV H T Supply shall be taken from MSEDCL & Suitable H T Switch yard will

be constructed for accommodating 400 KVA 11 KV / 415 V Transformer.

Moreover 125 KVA D G set has also been installed near the receiving pit

hopper. A Suitable room will be constructed to accommodate HT, LT & MCC

Panel.

3.8 Generation and disposal of waste

3.8.1 Waste water Generation Closed loop water system will be implemented in coal washery. A well designed

effluent treatment plant consisting of Thickener, High frequency screen,

classifying cyclone etc is proposed. Entire effluent after treatment shall be

reused in process. It shall be zero discharge unit. It is estimated that total effluent

generation from the proposed installation will be 1.5m3/day as domestic effluent

only, which will be treated in packaged type STP.

3.8.2 Solid Waste Generation and its disposal

Coal reject @ of 15-20% will be generated to the tune of maximum0.40million

tons/annum. domestic waste will be treated in packaged type STP and rejected

coal will be sold out to nearby reject based power plant and to other units.

3.8.3 Air Pollution Control / Management

A coal dust collector of 28000m3/hr shall be installed to take care of dust

emission of crusher & screen. There are five nos. of bore well with suitable

submersible pumps for meeting requirement of water in the plant. In addition to

dust suppression system there will be plantation all along inside road, boundary

wall & office building area.

To make the plant zero discharge , 24 m dia coal thickener including, 30 TPH

belt filter Press & 2 nos of 40x5x2.5m cement emergency ponds are to provided .

All the equipments viz, KVA Transformer, ABC for H.T. substation, switch gear of

19

plant L.T screens & crusher are to be procured from reputed firms with an

emphasis to keep noise level within the permissible limit.

Suitable number of sprinklers & rain guns are envisaged to be provided for dust

control on ROM coal receiving pit, road and coal ground stock yard as under:

1. Raw Coal Receiving pit hopper : 8 nos mist nozzles

2. BC-1 tail pulley : 2 nos mist nozzles

3. BC-2 tail pulley : 2 nos mist nozzles

4. BC-2 Head pulley : 2 nos mist nozzles

5. Along the road : 6 nos Rain Gun (15 meter range)

6. Coal Stock Yard : 6 no. 15 meter range rain gun

7. Fines Coal Stock Yard : 4 no. 15 meter range rain gun

8. BC-4 : 02 mist nozzle

9. BC-5 : 02 mist nozzle

10. Mobile Water Tanker for Spray of Water on : 01

Road & Coal Stock

All the equipments viz. receiving pit Conveyor belts, Crusher and screens will be

covered with suitable sheet M.S. Sheets. Moreover there will be suitable sheds

with fiber sheet over receiving underground hopper, crusher & screening

building & wet washery.

There would be 400 tone steel hopper with rake and pinion gate arrangement for

0-12mm coal, plus 100 mm coal product & 12-50 mm coal product avoiding the

ground stock to keep the dust pollution inside plant under control.

4.0 Site Analysis This chapter gives details regarding type of land use, topography and site connectivity etc. The details are as follows

4.1 Connectivity The site is well connected with road network. Nearest railway station is Ballarshah on South railway line. The following table gives brief regarding connectivity of the proposed site.

Components Description

Road : Gadchandur Road (SH236) = 0.1KmSouth direction Chandrapur- Nagpur Road(SH264) =90.Km East direction

Rail : Nearest Station 13.0Km (Ballarshah) on South Railway line.

Air Port : Nagpur 152.0Km

20

List of Industries near Project Site

Sr. No. Name of Industry Distance Direction

1 Bhatia Coal Washery 1 Km East

2 Aryan Coal washery 1.5 Km East

3 Coal mine 3Km NE

4.2 Land Form, Land Use and Land ownership

4.2.1 Land Form Present land is more or less flat terrain.

4.2.2 Land use of the Project site

Present land is in Industrial use.

4.3 Topography Topography of land is more or less flat terrain without much undulation

4.4 Existing land use pattern 4.4.1 Land use pattern of the project site

Existing 5.57 ha of land. No forest or government land is involved within the site. 4.5 Existing Infrastructure

S No.

Equipment / Plant Size (Mtr) Area (Sq. M)

1. Gate 6 x 0.5 3.00

2. Weigh Bridge 3.5 x 23 80.50

3. WB Cabin, Time office & Security 3.5 x 7 x 3 73.50

4. Receiving Hopper 9 x 35 315.00

5. Primary,sizing & secondary screens 25 x 6 150.00

6. Crusher 9 x 9 81.00

7. Store 10 x 15 150.00

8. Fresh Water Tank BG A 6 x 8 48.00

9. Conveyor Belt-BC-1 ,BC- 2,BC-3,BC-4,BC- 5,BC 6,BC 7,BC 8

700.00

10. 33KV Switch Yard & Transformer 10 x 20 m 200.00

11. H T ,L T & MCC Panel 7 x 12 m 84.00

12. Control Room 6 x 10 m 60.00

13. Flooring & Drainage Area & coal stock yard 5000.00

14. Steel hopper H1,H2,H3,H4, & H5 4 X 4X 5 80.00

21

4.6 Soil Classification

The soils in the area are generally of clayey loam types with sandy loam soil in

some areas. The soils have been classified as Ustocherpts/ Ustorthents/

Rhodustalfs/ Haplustalfs/ Haplusterts, as per pedological taxonomy

4.7 Climatic data from secondary sources

The climatic condition of this area is semi arid. The maximum temperature goes

Up to 48ºC during summer in the month of May and the minimum temperature

goes down to 4.0ºC during winter in the month of January-February. The winds in

the area are light to moderate during summer and winter. The rainfall of the

district is 790.6 mm to 1182.0 mm. Generally light to moderate winds prevails

throughout the year. Winds were light and moderate particularly during the

morning hours.

5.0 Planning brief 5.1 Planning Concept

It is proposed to modify existing 2.0MTPA Deshaled crushing unit to 2.0MTPA

Wet coal washery at village: Muthara, tehsil: Rajura, District Chandrapur.

5.2 Population Projection

There are no major human settlement in the close vicinity of project site.The

manpower requirement will be sourced from the local area to the extent possible,

hence not much of settlement of outside people in the area.

5.3 Amenities/Facilities

Facilities like canteen, rest room, toilet will be provided in the proposed plant as

basic facility to workers. No other additional facilities are proposed.

22

5.4 Green Belt Area for Green Belt Development 1.0 Ha.A green belt of 02 Rows of trees will be

developed around the periphery of the Plant road and open space Saplings of

native species like Neem, Amla & Gulmohar will be planted during the rainy

season.

It is proposed to plant 200 trees each year for the first three year and thereafter

to maintain them. Proper irrigation facilities shall be provided to ensure good

survival. Additional plantation will be taken up to ensure 95 % survival rate.

5.5 Social Infrastructure

Social infrastructure will be developed as per need in the village of close vicinity

of the project.

5.6 Drinking Water Management

It is estimated that approx 2KL/day of water will be required during operation of

proposed plant. The desired amount of water will be from ground water sources.

5.7 Solid Waste Management

Only washery reject will be generated as result of operation of wet coal washery.

These rejects have considerable amount of carbonaceous material hence the

same will be utilized as blend with coal to make fuel mix for generation of power.

6.0 Rehabilitation and Resettlement Scheme:

All the modification will be carried out within the existing deshaled coal crushing plant premises and modification does not required any additional land. So no rehabilitation and resettlement is required as there is no habitation in the project site.

7.0 Project Schedule & Cost estimates 7.1 Likely date of start of construction

23

Construction activity pertaining to modification will be started within 6 month from

the date of Environmental Clearance.

7.2 Estimated Project Cost

The estimated project cost is about Rs.9.5 Cr. approx.

Description Cost Rs in Lac

Land & Site development 25.00

i) Building & Premises 150.00

ii) Plant Machineries 600.00

iii) Furniture Fixer 10.00

iv) 33 line shifting substations 25.00 and L.T Switch gear

v) 400 KVA, 11KV /440 V transformer 10.00

and incoming substation

vi Roads &culverts 30.00

vii OtherMiscellaneous 100.0

TOTAL = 950.00

Means of Finance

Rs. In Lac

i) Equity 332.00

ii) Loan 618.00

_________

TOTAL = 950.00

8.0 Analysis of proposal 8.1 Financial and social benefit

With the implementation of the proposed project, the socio-economic status of

the local people will improve substantially.

8.2 Socio-Economic Development Activity

24

The management is committed to uplift the standards of living of the villagers by

undertaking following activities/responsibilities as the part of Corporate Social

Responsibility.

Health &Sanitation Drinking water Education for poor Village road Lighting Health & Hygiene

Personal and domestic hygiene

Maintaining clean neighborhood,

Weekly health camps offering free-check up and medicines

Ambulance services

Education and drug de-addiction, aids.

Drinking Water

Making drinking water available at centralized location in the village

Supporting Education

Providing books to all poor children

Conducting annual sports festival in the village schools,

Providing amenities like fan, lavatories

Maintain play ground etc.