Pre feasibility Report for Welspun Iron & Steel Pvt....

25
Pre feasibility Report for Welspun Iron & Steel Pvt. Limited New Project Pig Iron, Billets, Rebars, Slabs, BF Coke, WHRB At Village: Varsamedi, Taluka: Anjar, District: Kutch, State: Gujarat Prepared by M/s Detox Corporation Private Limited Surat, Gujarat NABET Accreditation vide letter no. NABET/EIA/RA002/034 and list of QCI approved consultant uploaded on 5 th April 2015

Transcript of Pre feasibility Report for Welspun Iron & Steel Pvt....

Page 1: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

Pre feasibility Report

for

Welspun Iron & Steel Pvt. Limited

New Project

Pig Iron, Billets, Rebars, Slabs, BF Coke, WHRB

 

 

At

Village: Varsamedi, Taluka: Anjar, District: Kutch,

State: Gujarat

Prepared by

M/s Detox Corporation Private Limited

Surat, Gujarat

NABET Accreditation vide letter no. NABET/EIA/RA002/034 and list of QCI approved consultant uploaded on 5th April 2015

Page 2: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 1 2015

CONTENT

1  INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION ................... 4 

1.1  Identification of project and project proponent ................................................. 4 

1.2  Project Proponent ........................................................................................ 4 

1.3  Proposed Project .......................................................................................... 4 

1.4  Brief description of nature of project ............................................................... 5 

1.5  Employment Generation (Direct and Indirect) due to the project Employment ...... 5 

2  Project SITE Description .................................................................................. 5 

2.1  Interdependent project ................................................................................. 5 

2.2  Location (map showing general location, specific location, and project boundary &

project site layout) with coordinates ............................................................... 5 

2.3  Details of alternate sites considered and the basis of selecting the proposed site,

particularly the environment considerations gone into should be highlighted ........ 9 

3  Project description with process ...................................................................... 9 

3.1  Raw material details ..................................................................................... 9 

3.2  Equipment Details ...................................................................................... 10 

3.3  Brief Description of Manufacturing Process and Flow Diagram ........................... 12 

4  Availability & Source of water & Wastewater generation ............................... 15 

4.1  Source of water and its availability ............................................................... 15 

4.2  Waste Water generation & Management plan ................................................. 15 

5  Solid waste & hazardous waste generation & Management plan .................... 16 

5.1  Solid waste generation and its management plan ........................................... 16 

5.2  Hazardous waste generation and its management plan .................................... 16 

6  Stack details and Air Pollution Control Measures ........................................... 17 

7  Source of electricity and its availability .......................................................... 18 

8  SITE ANALYSIS .............................................................................................. 19 

8.1  Connectivity .............................................................................................. 19 

8.2  Land Form, Land use and Land ownership ..................................................... 19 

8.3  Topography (along with map) ...................................................................... 19 

Page 3: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 2 2015

8.4  Existing land use pattern (agriculture, non agriculture, forest, water bodies –

including CRZ), shortest distances from the periphery of the project to periphery of

the forests, national park, wild life, sanctuary, eco sensitive areas, water bodies

(distance from HFL of the river), CRZ. In case of notified industrial area, a copy of

Gazette notification should be given. ............................................................ 19 

8.5  Existing infrastructure ................................................................................ 19 

8.6  Soil classification ....................................................................................... 19 

8.7  Climatic data from secondary sources ........................................................... 19 

8.8  Social Infrastructure available ...................................................................... 20 

9  Planning Brief ................................................................................................ 20 

9.1  Planning Concept (type of industries, facilities, transportation etc) Town and

country planning/ Development authority classification ................................... 20 

9.2  Population Projection .................................................................................. 20 

9.3  Land use planning (break up along with green belt etc) ................................... 20 

9.4  Amenities/ Facilities ................................................................................... 21 

10  PROPOSED INFRASTRUCTURE ........................................................................ 21 

10.1  Industrial area (Processing area) .................................................................. 21 

10.2  Residential area (Non processing area) ......................................................... 21 

10.3  Green belt ................................................................................................ 21 

10.4  Social infrastructure ................................................................................... 21 

10.5  Drinking water Management (Source & Supply of water) ................................. 22 

10.6  Sewerage system ....................................................................................... 22 

11  Rehabilitation and Resettlement (R & R) Plan ................................................ 22 

11.1  Policy to be adopted (Central/ state) in respect of the project affected persons

including home oustees, land oustees and landless laborers ............................. 22 

12  PROJECT SCHEDULE & COST ESTIMATES ........................................................ 22 

12.1  Likely date of start of construction and likely date of completion ....................... 22 

12.2  Estimated project cost along with analysis in terms of economic viability of the

project ..................................................................................................... 22 

13  Analysis of proposal (Final Recommendations) .............................................. 22 

Page 4: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 3 2015

13.1  Financial and social benefits with special emphasis on the benefit to the local

people including tribal population, if any, in the area ...................................... 22 

13.2  Budgetary allocation for social welfare in the area .......................................... 23 

13.3  Expenditure on Environmental Matters: estimated ......................................... 23 

14  Schematic representation of the feasibility drawing which give information of

EIA purpose ......................................................................................................... 23 

List of Table

Table 1: Product Profile for proposed project ................................................................ 4 

Table 2: Salient Features of Site ................................................................................ 6 

Table 3: Raw Material Consumption for project ............................................................. 9 

Table 4: Fuel Consumption ...................................................................................... 10 

Table 5: List of Equipments ..................................................................................... 10 

Table 6: Net Water Consumption .............................................................................. 15 

Table 7: Wastewater generation ............................................................................... 15 

Table 8: Solid waste generation ............................................................................... 16 

Table 9: Hazardous Waste generation ....................................................................... 17 

Table 10: Stack details with APC measures for point source emissions ........................... 17 

Table 11: APC measures for fugitive emissions ........................................................... 18 

Table 12: Electricity allocation ................................................................................. 18 

Table 13: Connectivity ............................................................................................ 19 

Table 14: Meteorology data ..................................................................................... 20 

List of Figure

Figure 1: Satellite image showing project location with surrounding features .................... 7 

Figure 2: Location map of 10 Km radius ...................................................................... 8 

Figure 3: Flow diagram ........................................................................................... 12 

Figure 4: Typical flow diagram of Blast Furnace .......................................................... 14 

Page 5: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 4 2015

1 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

1.1 Identification of project and project proponent

India is emerging as one of the leading producer of steel in the international market.

Government of India has received large number of proposals to set up steel making

facilities. Government is taking all steps to attract investment in steel sector and facilitate

speedy implementation of the projects.

India is the 4th largest producer of crude steel in the world with a total Production of around

90 MTPA (projected) in the year 2014-15 and is poised to take Third position by 2015-16.

Ministry of Steel has received proposals to set up steel making facilities for capacities of

around 276 million tons per year. Investment plans are mainly in the states of Orissa,

Jharkhand, Chhattisgarh, West Bengal, Karnataka, Gujarat and Maharashtra. Government is

taking steps for speedy implementation of these projects to meet with the expectations.

1.2 Project Proponent

M/s. Welspun Iron and Steel Private Ltd, is a Company registered under Indian Companies

Act, 1956 promoted by Welspun Group. Welspun is a business house of repute with annual

turn over INR 2000 crores. The group has interest spread across textile & Steel industry

with product range of Terry towels, bed liner Bathrobes, Specialty polyester yarns, cotton

yams, Saw pipes, ERW pipes and pipe coatings.

The company now proposes to install manufacturing plant for Slabs, Pig iron, Billets and

Rebars. The proposed capacity of the Pig iron plant is 1, 64,100 MTPA. During the

manufacturing of the Pig iron, the waste heat generated will be utilized in waste heat

recover boiler to produce 126 MW electricity in Captive Power Plant. The additional

electricity load will be procured from SEB.

1.3 Proposed Project

Company now proposes to establish a new project at Village: Varsamedi, Taluka: Anjar,

District: Kutch, State: Gujarat. The detail break up of production capacity for each product

is given as given in Table 1: Product Profile for proposed project Table 1.

Table 1: Product Profile for proposed project

SR. NO PROPOSED PRODUCT PROPOSED CAPACITY (TPA)

1 Total Slabs 1,500,000

2 Rebars 1,200,000

Page 6: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 5 2015

3 Billets 305,800

4 Pig Iron 1,64,100

5 BF Coke 47,400

6 WHRB 126 MW (2 x 250 TPH)

1.4 Brief description of nature of project

The project fall under category A, section 3 (a) & 1 (d) of EIA notification September 2006

and amendment thereof vide notification no. S.O 3067 (E) dated 1st December 2009.

1.5 Employment Generation (Direct and Indirect) due to the project

Employment

Direct Employment

Sr. Executive (VP / GM) : 20

Managerial : 170

Supervisor : 300

Skilled / Semi Skilled worker : 1,120

Unskilled Worker : 540

Total : 2,150

Indirect Employment

• There is a vast scope of indirect employment opportunity once the plant is set up in

the area.

• It is estimated that for each 1 job created in direct employment there would be

potential for creation of 5 jobs under indirect employment.

• Thus there is a potential of creation of 10,750 jobs under indirect employment

2 PROJECT SITE DESCRIPTION

2.1 Interdependent project

There is no interlinked or interdependent project with the proposed project.

2.2 Location (map showing general location, specific location, and project

boundary & project site layout) with coordinates

The location of site with type of land and boundary coordinates is as indicated in Figure 1.

Site description is shown in below table.

Page 7: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 6 2015

Table 2: Salient Features of Site

Project survey no.

Village

Taluka

District

State

594(1), 597, 609, 611(1), 611(2), 614,

615(1), 615(2), 615(3), 616, 617(1),

617(2), 618, 619, 620(1), 620(2), 620(3),

620(4), 620(5), 621, 624, 718, 629(1),

629(2), 632, 633, 634(1), 636, 641, 643,

644(1), 645(1)

Varsamedi,

Anjar,

Kutch

Gujarat

Latitude 23°07'43.12"N,

Longitude 70°05'28.55"E

Existing land use pattern Industrial Land

Nearest railway station Anjar: 3.5 Km

Highway Anjar-Bhachau Rd: ∼ 0.5 Km

Nearest port Kandla port: ∼ 10 Km

Human settlement from the site Varsamedi: ∼ 0.7 Km Total population of

Varsamedi village is 10654 population as per

Census 2011.

National Park and wildlife sanctuary None within the 10 km radius

Page 8: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 7 2015

Figure 1: Satellite image showing project location with surrounding features

Existing plant

Village:

Varsamedi

NH 8A: 0.5 Km

Approch road: 0.5 Km

Existing Rain water harvesting structure

Page 9: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 8 2015

Figure 2: Location map of 10 Km radius

Page 10: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 9 2015

2.3 Details of alternate sites considered and the basis of selecting the proposed

site, particularly the environment considerations gone into should be highlighted

The suitability of a site, for locating the proposed project is determined by the following

major considerations.

• Availability of adequate land, adjacent to the existing unit for installation of main plant,

transformer yard, switchyard and all other supporting facilities such as cooling towers,

pump houses, raw water storage reservoir etc.

• Minimum haulage distance for transportation of fuel; i.e. imported coal can be procured

from Kandla Port located at ~10 Km from proposed site.

• Suitability of the land from topographical and geological considerations.

• Location away from forests, national park/sanctuaries, sea coast, other places of

defence, religious, cultural and ecologically sensitive elements.

• Nearest village, Varsamedi is ~ 0.7 km away from the location.

The major driving force behind the selection of the proposed site is that the plant will be

adjacent to existing Manufacturing units which has already been scrutinized by MoEF for

setting up and subsequent expansions. Apart from the above requirements, other

considerations such as water availability, availability of land, good transportation facilities

for receipt of fuel and other environmental considerations have also been looked into for

proposed project.

3 PROJECT DESCRIPTION WITH PROCESS

3.1 Raw material details

Raw material requirement for proposed project is as mentioned in table below

Table 3: Raw Material Consumption for project

Sr. No. Name Of Raw

Material

Quantity Per

Month (Mt) Source

Mode Of

Transport

1. Cooking Coal 2,22,000 Imported Sea And Road

2. Iron Ore Fines 4,00,000 Domestic Rail And Road

3. Dolomite Fins 34,000 Domestic Rail And Road

4. Limestone 20,000 Imported/

Domestic Sea And Road

Page 11: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 10 2015

5. Iron Ore Lump 1,00,000 Domestic Rail And Road

6. Coal 38,000 Domestic/

;Imported Sea And Road

7. Raw Lime Stone And

Dolomite 73,000 Domestic Rail And Road

8. Quartzite 2,100 Domestic Road

9. Ferroalloys 5,000 Domestic Road

10. Additive 2,000 Domestic Road

The raw material shall be sourced from local market or imported. The transportation shall

be through the existing road network in the area

Coal shall be utilized for operation of boiler and CPP (captive power plant). The total

quantity of coal required for same is as mentioned in table below

Table 4: Fuel Consumption

Fuel Total Coal Consumption Source

Coal 4,50,000 MT/ annum Imported/ local sources

Cooking Coal 27,00,000 MT/ annum Shall be procured from

local sources

3.2 Equipment Details

The furnaces to be installed for the proposed project is as Table 5.

Table 5: List of Equipments

Name of Furnaces/

boiler

No. of furnaces/

boiler

Capacity of each

furnaces/ boiler

Blast Furnace 1 No. 330 Tons/Hour.

WHRSB 2 Nos. 250 Ton/Hr.

Billet Reheating

Furnace 2 Nos. 250 Ton/Hr.

Page 12: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 11 2015

Twin Ladle furnace 2 Nos. 160 Ton

Pig casting machine 2 nos. 4900 TPD

Basic oxygen furnace 2 nos. 160 Tons

Twin Vacuum Degassi 1 nos. 160 Tons

Lime Lolocalcining

Plant 2 nos. 600 TPD

Oxygen Plant 1 nos. 940 TPD

Sinter plant 1 nos. 330 Sq. meters.

Slab caster 200 Tons/Hr.

Billet Caster 150 Tons/Hr.

Rebar Mill 1200000 TPA

Slag granulation unit 1 MTPA

Page 13: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 12 2015

3.3 Brief Description of Manufacturing Process and Flow Diagram

Figure 3: Flow diagram

Page 14: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 13 2015

Manufacturing Process for Pig Iron Plant

The purpose of a blast furnace is to chemically reduce and physically convert iron oxides

into liquid iron called “hot metal”. The blast furnace is a huge, steel stack lined with

refractory brick, where iron ore, coke and limestone are dumped into the top, and

preheated air is blown into the bottom. The raw materials require 6 to 8 hours to descend to

the bottom of the furnace where they become the final product of liquid slag and liquid iron.

These liquid products are drained from the furnace at regular intervals. The hot air that was

blown into the bottom of the furnace ascends to the top in 6 to 8 seconds after going

through numerous chemical reactions. Once a blast furnace is started it will continuously

run for four to ten years with only short stops to perform planned maintenance.

Manufacturing Process:- The blast furnace is a counter-current reaction where solids

descend and gases ascend. In this reaction there are numerous chemical and physical

reactions that produce the desired final product which is hot metal. The main inputs for the

blast furnace are iron ore (sinter); coke and lime stone.

The Iron ore; as naturally available on earth is either in the form of Hematite (Fe2O3) or in

the form of Magnetite (Fe3O4) and the iron content ranges from 60% to 68%. Sinter is

produced from fine raw ore, small coke, sand-sized limestone and numerous other steel

waste materials that contain some iron. These fine materials are proportioned to obtain

desired product chemistry then mixed together. This raw material mix is then placed on a

sintering strand, which is similar to a steel conveyor belt, where it is ignited by gas fired

furnace and fused by the heat from the coke fines into larger size pieces that are from 10

mm to 30 mm. The iron ore, pellets and sinter then become the liquid iron produced in the

blast furnace with any of their remaining impurities going to the liquid slag.

The coke is produced from a mixture of coals. The coal is crushed and ground into a powder

and then charged into an oven. As the oven is heated the coal is cooked so most of the

volatile matter such as oil and tar are removed. The cooked coal, called coke, is removed

from the oven after 18 to 24 hours of reaction time. The coke contains 90 to 93% carbon,

some ash and sulphur but compared to raw coal is very strong. The strong pieces of coke

with a high energy value provide permeability, heat and gases which are required to reduce

and melt the iron ore, pellets and sinter.

The final raw material in the iron making process is limestone; which can be in pure calcium

chloride, calcium oxides or dolomite limestone containing magnesia or a blend of the two

types of limestone.

Page 15: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 14 2015

All of the raw materials are stored in separates silos and transferred to the stock-house

before charging. Once these materials are charged into the furnace top, they go through

numerous chemical and physical reactions while descending to the bottom of the furnace.

]The major chemical reactions consists of reduction of iron ore; oxidation (burning) of carbon

in the coke. Another important series of reaction takes place at high temperature is the

reaction of lime with impurities; resulting in slag.

Another product of the iron making process, in addition to molten iron and slag, is hot dirty

gases. These gases exit the top of the blast furnace and proceed through gas cleaning

equipment where particulate matter is removed from the gas and the gas is cooled. This gas

has a considerable energy value so it is burned as a fuel in the “hot blast stoves” which are

used to preheat the air entering the blast furnace to become “hot blast”. Any of the gas not

burned in the stoves is sent to the boiler house and is used to generate steam which turns a

turbo blower that generates the compressed air known as “cold blast” that comes to the

stoves.

Gas Cleaning System of Blast Furnace:

The hot dirty gases generated from the top of the blast furnace shall be cleaned in the Gas

cleaning system. Dry gas cleaning system, in which series of bag filters will be installed.

Figure 4: Typical flow diagram of Blast Furnace

Page 16: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 15 2015

4 AVAILABILITY & SOURCE OF WATER & WASTEWATER GENERATION

4.1 Source of water and its availability

Required water for domestic and industrial purposes shall be obtained from GWIL (Gujarat

Water Infrastructure Limited).

The water consumption for proposed project activities is as mentioned in Table 6.

Table 6: Net Water Consumption

Purpose Quantity (m3/Day) For

Proposed Project

Cooling 13600

Boiler 7200

Drinking 300

Process 20140

Washing, Sprinkling 1600

Other (Firefighting, Gardening) 850

Total Water Consumption 43690

Welspun group has a rain water harvesting installed for existing project with capacity of

more than 300 crores ltrs. Company is committed to recycle and reuse of wastewater at

possible extent.

4.2 Waste Water generation & Management plan

The total quantity of waste water generated is as mentioned in Table 7.

Table 7: Wastewater generation

Purpose Quantity (m3/Day)

Proposed Disposal Plan

Cooling Blow Down 27 Shall be treated and later reused within the

plan premises for gardening and dust

suppression

Boiler Blow Down 299

Process 511

Domestic 18 Shall be treated in STP and reused for flushing

Total 855

Page 17: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 16 2015

All the process effluent streams will be collected and treated into Effluent Treatment Plant.

The treated water shall be reused within plant and utilized partly for dust suppression in

approach roads and Green belt development.

A sewage treatment plant has been proposed to treat sewage generated from different

toilets of total plant area. One number of STP has been envisaged. However, the flow

quantity will be varying during different period of the day and the peak flow may go up to

three times the average flow for a certain period of the day

5 SOLID WASTE & HAZARDOUS WASTE GENERATION & MANAGEMENT PLAN

5.1 Solid waste generation and its management plan

The total quantum of Solid waste generated from proposed facility is as given in table below.

Table 8: Solid waste generation

Type Of Waste Total Quantity Of Proposed

Waste Generation Disposal Plan

Blast furnace

Slag 88500 MT/ Month

Company proposes to install

slag granulation plant. The

same shall be later used for

construction of roads

BOF slag 37100 MT/ Month

The same shall be used for

Brick/Road filling and area

grading in form of pellets.

Flue dust 4700 MT/ Month Disposal after Treatment.

Mill Scale 1900 MT/ Month Partly reuse and selling as low

grade Iron Contain item.

STP Sludge This quantity will be very low in

tune of 5 mt /month

It will be treated biologically ,

neutralize & disposed off

5.2 Hazardous waste generation and its management plan

Hazardous waste generated from the proposed unit is as mentioned in table below

Page 18: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 17 2015

Table 9: Hazardous Waste generation

Waste Generated Proposed

Quantity Disposal Plan

Lube oil sludge/Coolant oil

sludge

1.5 MT/annum

Recycled to coke plant/Power

plant

Lead acid batteries 1.5 MT/annum Auctioned to registered

recycler

Used Lube oil 1.5 MT/annum Injected in BF/CO/Power

Plant

ETP Sludge This will be

almost negligible

This will be treated with

neutralizing agents, stabilized

& disposed

6 STACK DETAILS AND AIR POLLUTION CONTROL MEASURES

The list of stacks to be installed for proposed project is as mentioned in table below. For

abatement of air pollution, Air pollution control equipment will be installed at point source.

Table 10: Stack details with APC measures for point source emissions

Stack attached to Stack Height from GL,

meters, m APC

BF-HBS - Chimney 55 Bag filter/ electrostatic

precipitators

BF Dedusting

Chimney(Tapered)-cast house 50

Bag filter/ electrostatic

precipitators

Secondary Dedusting System of

BOF 30

Bag filter/ electrostatic

precipitators

Sinter Plant Dedusting

Chimneys-3 nos for screening,

proportioning & crusher house

50 Bag filter/ electrostatic

precipitators

Coke oven heat recovery power

plant 126 MW (WHRB) 110

Bag filter/ electrostatic

precipitators

Page 19: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 18 2015

Sinter Plant ESP Chimney 70 Bag filter/ electrostatic

precipitators, etc.

BF stock house bag filter

chimney 30

Bag filter/ electrostatic

precipitators, etc.

Pushing Emission Control

System 30

Bag filter/ electrostatic

precipitators

Bar mill - stack 70 Bag filter/ electrostatic

precipitators,

SMS-Chimney BOF flare stack 80 Bag filter/ electrostatic

precipitators,

Lime & dolo plant kiln (2

stacks) 60 Bag filters

Table 11: APC measures for fugitive emissions

Shop / Unit Proposed facilities

Steel melting shop Gas coolers, scrubber, chimney,

etc.

Material handling

system

Bag filters, dust suppression

system, etc.

7 SOURCE OF ELECTRICITY AND ITS AVAILABILITY

Electricity shall be obtained partly from SEB. The total power requirement for the plant for

proposed project is given in Table 12.

Table 12: Electricity allocation

Source Of Power Quantum For Proposed Project

SEB /Grid 130.5 MW

Captive Power Plant 126 MW

DG Sets (Stand By) 6 MW (2 MW× 3 nos.)

Type of fuel to be used in DG set - Dual fuel (Diesel and Gas)

Page 20: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 19 2015

8 SITE ANALYSIS

8.1 Connectivity

The project site is well connected to Anjar-Bhachau road. The site is well connected by road

and rail to rest of country. The details of highway and rail network are as mentioned below:

Table 13: Connectivity

Description Distance

Transportation

Anjar-Bhachau Rd: ∼ 0.5 Km

Rail : Anjar (~ 3.5 Km)

Port: Kandla (~ 10 Km)

Nearest Town/City Town: Anjar (~ 3.5 Km)

City: Gandhidham (~ 5 km )

Nearest Village Varshamedi (~ 0.7 Km)

8.2 Land Form, Land use and Land ownership

The proposed project will be set up in industrial land. NA has been already taken.

8.3 Topography (along with map)

The topography map shall be submitted at the time of presentation.

8.4 Existing land use pattern (agriculture, non agriculture, forest, water bodies

– including CRZ), shortest distances from the periphery of the project to periphery

of the forests, national park, wild life, sanctuary, eco sensitive areas, water bodies

(distance from HFL of the river), CRZ. In case of notified industrial area, a copy of

Gazette notification should be given.

There is no forest, national park, wild life sanctuary, eco sensitive areas in surrounding 10

Km of the plant boundary.

8.5 Existing infrastructure

No

8.6 Soil classification

Detail soil testing report will be provided at the time of presentation.

8.7 Climatic data from secondary sources

The climatic data for December 2014 to January 2015 in the study are as below

Page 21: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 20 2015

Table 14: Meteorology data

Average Wind speed 5.71 m/s.

Temperature 10oC to 34oC

Average Relative humidity 15 % to 68 %.

8.8 Social Infrastructure available

The project site is located approximately 2 km from the human settlement (village:

Varshamedi). Basic amenities of life are easily available in the area. Primary health centre,

school, drinking water, electricity, communication, road network, transportation facility is

available in the vicinity.

The existing infrastructure is sufficient to cater the additional load due to the proposed

project.

9 PLANNING BRIEF

9.1 Planning Concept (type of industries, facilities, transportation etc) Town

and country planning/ Development authority classification

The industrial area and the related facilities for integrated Steel plant would be developed.

Additionally, the nearby towns have all the modern facilities.

9.2 Population Projection

There would not be any significant increase in the population of surrounding area as the

additional workers for the proposed project will come from the local residents in the

surrounding villages. There won’t be any influx of people in the area due to proposed

project

9.3 Land use planning (break up along with green belt etc)

The total area of site where the plant is to be located is Around 576 acres. The area will be

bifurcated for following utilities and plant area

• Raw material yard

• Sinter plant

• Blast Furnace

• SMS (Steel Melt Shop) with Casters including bar Mill

• Oxygen Plant

Page 22: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 21 2015

• Water Facilities

• Producer Gas Plant

• Coke Oven

• Coke Oven waste material storage for disposal

• Water reservoir

The green area is about 60 acres. The balance area is free area used for transportation,

railway tracks, stores, canteen, workshop etc.

9.4 Amenities/ Facilities

Major basic facilities are available for the proposed project. Road, electricity, water,

transportation facility etc are well developed in the surrounding area.

All the amenities related to project on the site will be installed

10 PROPOSED INFRASTRUCTURE

10.1 Industrial area (Processing area)

The total industrial area of the company is approx 183 acres.

10.2 Residential area (Non processing area)

Group is having existing housing for workers which will be expanded. Canteen is also

proposed to set up.

10.3 Green belt

Company is committed to develop dense green belt area in proposed project plant as per

government rules. Green belt is proposed to develop in approx 60 acres area. Following are

the proposed species of trees which are planned to be plant

• Ashoka trees

• Neem trees

• Mango trees

• Gul-mahor

10.4 Social infrastructure

Basic amenities of life are easily available in the area. Primary health centre, school,

drinking water, electricity, communication, road network, transportation facility is available

in the vicinity.

Page 23: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 22 2015

10.5 Drinking water Management (Source & Supply of water)

Water shall be obtained from Gujarat Water Infrastructure Ltd.

10.6 Sewerage system

A sewage treatment plant has been proposed to treat sewage generated from different

toilets of total plant area. One number of STP with average flow of 10 m3 / hr capacity has

been envisaged. However, the flow quantity will be varying during different period of the

day and the peak flow may go upto three times the average flow for a certain period of the

day. And treated waste water will be utilized for green belt development and ground water

recharge.

11 REHABILITATION AND RESETTLEMENT (R & R) PLAN

11.1 Policy to be adopted (Central/ state) in respect of the project affected

persons including home oustees, land oustees and landless laborers

Not applicable

12 PROJECT SCHEDULE & COST ESTIMATES

12.1 Likely date of start of construction and likely date of completion

Likely date of start of construction: With in one month after obtaining EC

Likely date of completion of construction: August 2016

12.2 Estimated project cost along with analysis in terms of economic viability of

the project

Total project cost: 7885 Crores

13 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

13.1 Financial and social benefits with special emphasis on the benefit to the

local people including tribal population, if any, in the area

The following activities will be done for social welfare –

• Contributions in Schools and colleges in near by villages.

• Tree Plantation at nearby villages.

• Contributions to Prime minister’s Swachha Bharat Abhiyan. Under this campaign,

company has decided to provide toilet to 30 poor families.

Page 24: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 23 2015

13.2 Budgetary allocation for social welfare in the area

Rs. 15 lakhs will be spent annually on Social Welfare Activity.

13.3 Expenditure on Environmental Matters: estimated

Environmental Issues Capital Cost (Rs)

Air Pollution Control 2000 Lacs

Water Pollution Control 1000 Lacs

Noise Pollution Control 150 Lacs

Environmental Monitoring

And Management

10 Lacs per year

Occupational Health 7 Lacs per year

Green Belt 15 Lacs per year

14 SCHEMATIC REPRESENTATION OF THE FEASIBILITY DRAWING WHICH GIVE

INFORMATION OF EIA PURPOSE

The proposed project of integrated steel plant and captive power plant falls under category

A, section 3 (a) and 1 (d) of EIA notification September 2006 and amendment there of vide

notification no. S.O 3067 (E) dated 1st December 2009, which require prior Environmental

Clearance before starting construction, production or any other allied activities related to

the project. For getting the Environmental Clearance; it is required to carry out the

Environmental Impact Assessment (EIA) study report.

Definition of EIA

Environmental Impact Assessment (EIA) is a formal process used to predict how industrial

development or construction project will affect natural resources such as water, air, land,

socioeconomic and bio ecological environment.

An EIA usually involves a sequence of steps:

(1) Screening to decide if a project requires assessment and to what level of detail.

(2) Preliminary assessment to identify key impacts, their magnitude, significance, and

importance.

Page 25: Pre feasibility Report for Welspun Iron & Steel Pvt. Limitedenvironmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 5. 12. · Pre feasibility Report for Welspun Iron

PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED

DETOX CORPORATION PRIVATE LIMITED 24 2015

(3) Scoping to ensure the EIA focuses on key issues and to determine, where more detailed

information is needed.

(4) Implementing the main EIA study, which involves detailed investigations to predict

impacts, assess their consequences, or both.

Methodology

Environmental Impact Assessment (EIA) studies include identification, assessment,

quantitative evaluation and prediction of possible impacts. To minimize the impact of the

project on various environmental attributes, mitigation measures are suggested for

implementation along with the project.

The methodology of this study can be schematized as detailed below:

To gather information on present environmental conditions and relevant national

environmental guidelines and EIA procedures.

Scoping of impacts.

Assessment of significant impacts.

Description of residual impacts.

Development of monitoring plans.

To inform all relevant and involved authorities regarding the impact of the project on

the environment and the proposed mitigation measures.