Pre feasibility Report for Welspun Iron & Steel Pvt....
Transcript of Pre feasibility Report for Welspun Iron & Steel Pvt....
Pre feasibility Report
for
Welspun Iron & Steel Pvt. Limited
New Project
Pig Iron, Billets, Rebars, Slabs, BF Coke, WHRB
At
Village: Varsamedi, Taluka: Anjar, District: Kutch,
State: Gujarat
Prepared by
M/s Detox Corporation Private Limited
Surat, Gujarat
NABET Accreditation vide letter no. NABET/EIA/RA002/034 and list of QCI approved consultant uploaded on 5th April 2015
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 1 2015
CONTENT
1 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION ................... 4
1.1 Identification of project and project proponent ................................................. 4
1.2 Project Proponent ........................................................................................ 4
1.3 Proposed Project .......................................................................................... 4
1.4 Brief description of nature of project ............................................................... 5
1.5 Employment Generation (Direct and Indirect) due to the project Employment ...... 5
2 Project SITE Description .................................................................................. 5
2.1 Interdependent project ................................................................................. 5
2.2 Location (map showing general location, specific location, and project boundary &
project site layout) with coordinates ............................................................... 5
2.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environment considerations gone into should be highlighted ........ 9
3 Project description with process ...................................................................... 9
3.1 Raw material details ..................................................................................... 9
3.2 Equipment Details ...................................................................................... 10
3.3 Brief Description of Manufacturing Process and Flow Diagram ........................... 12
4 Availability & Source of water & Wastewater generation ............................... 15
4.1 Source of water and its availability ............................................................... 15
4.2 Waste Water generation & Management plan ................................................. 15
5 Solid waste & hazardous waste generation & Management plan .................... 16
5.1 Solid waste generation and its management plan ........................................... 16
5.2 Hazardous waste generation and its management plan .................................... 16
6 Stack details and Air Pollution Control Measures ........................................... 17
7 Source of electricity and its availability .......................................................... 18
8 SITE ANALYSIS .............................................................................................. 19
8.1 Connectivity .............................................................................................. 19
8.2 Land Form, Land use and Land ownership ..................................................... 19
8.3 Topography (along with map) ...................................................................... 19
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 2 2015
8.4 Existing land use pattern (agriculture, non agriculture, forest, water bodies –
including CRZ), shortest distances from the periphery of the project to periphery of
the forests, national park, wild life, sanctuary, eco sensitive areas, water bodies
(distance from HFL of the river), CRZ. In case of notified industrial area, a copy of
Gazette notification should be given. ............................................................ 19
8.5 Existing infrastructure ................................................................................ 19
8.6 Soil classification ....................................................................................... 19
8.7 Climatic data from secondary sources ........................................................... 19
8.8 Social Infrastructure available ...................................................................... 20
9 Planning Brief ................................................................................................ 20
9.1 Planning Concept (type of industries, facilities, transportation etc) Town and
country planning/ Development authority classification ................................... 20
9.2 Population Projection .................................................................................. 20
9.3 Land use planning (break up along with green belt etc) ................................... 20
9.4 Amenities/ Facilities ................................................................................... 21
10 PROPOSED INFRASTRUCTURE ........................................................................ 21
10.1 Industrial area (Processing area) .................................................................. 21
10.2 Residential area (Non processing area) ......................................................... 21
10.3 Green belt ................................................................................................ 21
10.4 Social infrastructure ................................................................................... 21
10.5 Drinking water Management (Source & Supply of water) ................................. 22
10.6 Sewerage system ....................................................................................... 22
11 Rehabilitation and Resettlement (R & R) Plan ................................................ 22
11.1 Policy to be adopted (Central/ state) in respect of the project affected persons
including home oustees, land oustees and landless laborers ............................. 22
12 PROJECT SCHEDULE & COST ESTIMATES ........................................................ 22
12.1 Likely date of start of construction and likely date of completion ....................... 22
12.2 Estimated project cost along with analysis in terms of economic viability of the
project ..................................................................................................... 22
13 Analysis of proposal (Final Recommendations) .............................................. 22
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 3 2015
13.1 Financial and social benefits with special emphasis on the benefit to the local
people including tribal population, if any, in the area ...................................... 22
13.2 Budgetary allocation for social welfare in the area .......................................... 23
13.3 Expenditure on Environmental Matters: estimated ......................................... 23
14 Schematic representation of the feasibility drawing which give information of
EIA purpose ......................................................................................................... 23
List of Table
Table 1: Product Profile for proposed project ................................................................ 4
Table 2: Salient Features of Site ................................................................................ 6
Table 3: Raw Material Consumption for project ............................................................. 9
Table 4: Fuel Consumption ...................................................................................... 10
Table 5: List of Equipments ..................................................................................... 10
Table 6: Net Water Consumption .............................................................................. 15
Table 7: Wastewater generation ............................................................................... 15
Table 8: Solid waste generation ............................................................................... 16
Table 9: Hazardous Waste generation ....................................................................... 17
Table 10: Stack details with APC measures for point source emissions ........................... 17
Table 11: APC measures for fugitive emissions ........................................................... 18
Table 12: Electricity allocation ................................................................................. 18
Table 13: Connectivity ............................................................................................ 19
Table 14: Meteorology data ..................................................................................... 20
List of Figure
Figure 1: Satellite image showing project location with surrounding features .................... 7
Figure 2: Location map of 10 Km radius ...................................................................... 8
Figure 3: Flow diagram ........................................................................................... 12
Figure 4: Typical flow diagram of Blast Furnace .......................................................... 14
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 4 2015
1 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
1.1 Identification of project and project proponent
India is emerging as one of the leading producer of steel in the international market.
Government of India has received large number of proposals to set up steel making
facilities. Government is taking all steps to attract investment in steel sector and facilitate
speedy implementation of the projects.
India is the 4th largest producer of crude steel in the world with a total Production of around
90 MTPA (projected) in the year 2014-15 and is poised to take Third position by 2015-16.
Ministry of Steel has received proposals to set up steel making facilities for capacities of
around 276 million tons per year. Investment plans are mainly in the states of Orissa,
Jharkhand, Chhattisgarh, West Bengal, Karnataka, Gujarat and Maharashtra. Government is
taking steps for speedy implementation of these projects to meet with the expectations.
1.2 Project Proponent
M/s. Welspun Iron and Steel Private Ltd, is a Company registered under Indian Companies
Act, 1956 promoted by Welspun Group. Welspun is a business house of repute with annual
turn over INR 2000 crores. The group has interest spread across textile & Steel industry
with product range of Terry towels, bed liner Bathrobes, Specialty polyester yarns, cotton
yams, Saw pipes, ERW pipes and pipe coatings.
The company now proposes to install manufacturing plant for Slabs, Pig iron, Billets and
Rebars. The proposed capacity of the Pig iron plant is 1, 64,100 MTPA. During the
manufacturing of the Pig iron, the waste heat generated will be utilized in waste heat
recover boiler to produce 126 MW electricity in Captive Power Plant. The additional
electricity load will be procured from SEB.
1.3 Proposed Project
Company now proposes to establish a new project at Village: Varsamedi, Taluka: Anjar,
District: Kutch, State: Gujarat. The detail break up of production capacity for each product
is given as given in Table 1: Product Profile for proposed project Table 1.
Table 1: Product Profile for proposed project
SR. NO PROPOSED PRODUCT PROPOSED CAPACITY (TPA)
1 Total Slabs 1,500,000
2 Rebars 1,200,000
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 5 2015
3 Billets 305,800
4 Pig Iron 1,64,100
5 BF Coke 47,400
6 WHRB 126 MW (2 x 250 TPH)
1.4 Brief description of nature of project
The project fall under category A, section 3 (a) & 1 (d) of EIA notification September 2006
and amendment thereof vide notification no. S.O 3067 (E) dated 1st December 2009.
1.5 Employment Generation (Direct and Indirect) due to the project
Employment
Direct Employment
Sr. Executive (VP / GM) : 20
Managerial : 170
Supervisor : 300
Skilled / Semi Skilled worker : 1,120
Unskilled Worker : 540
Total : 2,150
Indirect Employment
• There is a vast scope of indirect employment opportunity once the plant is set up in
the area.
• It is estimated that for each 1 job created in direct employment there would be
potential for creation of 5 jobs under indirect employment.
• Thus there is a potential of creation of 10,750 jobs under indirect employment
2 PROJECT SITE DESCRIPTION
2.1 Interdependent project
There is no interlinked or interdependent project with the proposed project.
2.2 Location (map showing general location, specific location, and project
boundary & project site layout) with coordinates
The location of site with type of land and boundary coordinates is as indicated in Figure 1.
Site description is shown in below table.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 6 2015
Table 2: Salient Features of Site
Project survey no.
Village
Taluka
District
State
594(1), 597, 609, 611(1), 611(2), 614,
615(1), 615(2), 615(3), 616, 617(1),
617(2), 618, 619, 620(1), 620(2), 620(3),
620(4), 620(5), 621, 624, 718, 629(1),
629(2), 632, 633, 634(1), 636, 641, 643,
644(1), 645(1)
Varsamedi,
Anjar,
Kutch
Gujarat
Latitude 23°07'43.12"N,
Longitude 70°05'28.55"E
Existing land use pattern Industrial Land
Nearest railway station Anjar: 3.5 Km
Highway Anjar-Bhachau Rd: ∼ 0.5 Km
Nearest port Kandla port: ∼ 10 Km
Human settlement from the site Varsamedi: ∼ 0.7 Km Total population of
Varsamedi village is 10654 population as per
Census 2011.
National Park and wildlife sanctuary None within the 10 km radius
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 7 2015
Figure 1: Satellite image showing project location with surrounding features
Existing plant
Village:
Varsamedi
NH 8A: 0.5 Km
Approch road: 0.5 Km
Existing Rain water harvesting structure
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 8 2015
Figure 2: Location map of 10 Km radius
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 9 2015
2.3 Details of alternate sites considered and the basis of selecting the proposed
site, particularly the environment considerations gone into should be highlighted
The suitability of a site, for locating the proposed project is determined by the following
major considerations.
• Availability of adequate land, adjacent to the existing unit for installation of main plant,
transformer yard, switchyard and all other supporting facilities such as cooling towers,
pump houses, raw water storage reservoir etc.
• Minimum haulage distance for transportation of fuel; i.e. imported coal can be procured
from Kandla Port located at ~10 Km from proposed site.
• Suitability of the land from topographical and geological considerations.
• Location away from forests, national park/sanctuaries, sea coast, other places of
defence, religious, cultural and ecologically sensitive elements.
• Nearest village, Varsamedi is ~ 0.7 km away from the location.
The major driving force behind the selection of the proposed site is that the plant will be
adjacent to existing Manufacturing units which has already been scrutinized by MoEF for
setting up and subsequent expansions. Apart from the above requirements, other
considerations such as water availability, availability of land, good transportation facilities
for receipt of fuel and other environmental considerations have also been looked into for
proposed project.
3 PROJECT DESCRIPTION WITH PROCESS
3.1 Raw material details
Raw material requirement for proposed project is as mentioned in table below
Table 3: Raw Material Consumption for project
Sr. No. Name Of Raw
Material
Quantity Per
Month (Mt) Source
Mode Of
Transport
1. Cooking Coal 2,22,000 Imported Sea And Road
2. Iron Ore Fines 4,00,000 Domestic Rail And Road
3. Dolomite Fins 34,000 Domestic Rail And Road
4. Limestone 20,000 Imported/
Domestic Sea And Road
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 10 2015
5. Iron Ore Lump 1,00,000 Domestic Rail And Road
6. Coal 38,000 Domestic/
;Imported Sea And Road
7. Raw Lime Stone And
Dolomite 73,000 Domestic Rail And Road
8. Quartzite 2,100 Domestic Road
9. Ferroalloys 5,000 Domestic Road
10. Additive 2,000 Domestic Road
The raw material shall be sourced from local market or imported. The transportation shall
be through the existing road network in the area
Coal shall be utilized for operation of boiler and CPP (captive power plant). The total
quantity of coal required for same is as mentioned in table below
Table 4: Fuel Consumption
Fuel Total Coal Consumption Source
Coal 4,50,000 MT/ annum Imported/ local sources
Cooking Coal 27,00,000 MT/ annum Shall be procured from
local sources
3.2 Equipment Details
The furnaces to be installed for the proposed project is as Table 5.
Table 5: List of Equipments
Name of Furnaces/
boiler
No. of furnaces/
boiler
Capacity of each
furnaces/ boiler
Blast Furnace 1 No. 330 Tons/Hour.
WHRSB 2 Nos. 250 Ton/Hr.
Billet Reheating
Furnace 2 Nos. 250 Ton/Hr.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 11 2015
Twin Ladle furnace 2 Nos. 160 Ton
Pig casting machine 2 nos. 4900 TPD
Basic oxygen furnace 2 nos. 160 Tons
Twin Vacuum Degassi 1 nos. 160 Tons
Lime Lolocalcining
Plant 2 nos. 600 TPD
Oxygen Plant 1 nos. 940 TPD
Sinter plant 1 nos. 330 Sq. meters.
Slab caster 200 Tons/Hr.
Billet Caster 150 Tons/Hr.
Rebar Mill 1200000 TPA
Slag granulation unit 1 MTPA
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 12 2015
3.3 Brief Description of Manufacturing Process and Flow Diagram
Figure 3: Flow diagram
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 13 2015
Manufacturing Process for Pig Iron Plant
The purpose of a blast furnace is to chemically reduce and physically convert iron oxides
into liquid iron called “hot metal”. The blast furnace is a huge, steel stack lined with
refractory brick, where iron ore, coke and limestone are dumped into the top, and
preheated air is blown into the bottom. The raw materials require 6 to 8 hours to descend to
the bottom of the furnace where they become the final product of liquid slag and liquid iron.
These liquid products are drained from the furnace at regular intervals. The hot air that was
blown into the bottom of the furnace ascends to the top in 6 to 8 seconds after going
through numerous chemical reactions. Once a blast furnace is started it will continuously
run for four to ten years with only short stops to perform planned maintenance.
Manufacturing Process:- The blast furnace is a counter-current reaction where solids
descend and gases ascend. In this reaction there are numerous chemical and physical
reactions that produce the desired final product which is hot metal. The main inputs for the
blast furnace are iron ore (sinter); coke and lime stone.
The Iron ore; as naturally available on earth is either in the form of Hematite (Fe2O3) or in
the form of Magnetite (Fe3O4) and the iron content ranges from 60% to 68%. Sinter is
produced from fine raw ore, small coke, sand-sized limestone and numerous other steel
waste materials that contain some iron. These fine materials are proportioned to obtain
desired product chemistry then mixed together. This raw material mix is then placed on a
sintering strand, which is similar to a steel conveyor belt, where it is ignited by gas fired
furnace and fused by the heat from the coke fines into larger size pieces that are from 10
mm to 30 mm. The iron ore, pellets and sinter then become the liquid iron produced in the
blast furnace with any of their remaining impurities going to the liquid slag.
The coke is produced from a mixture of coals. The coal is crushed and ground into a powder
and then charged into an oven. As the oven is heated the coal is cooked so most of the
volatile matter such as oil and tar are removed. The cooked coal, called coke, is removed
from the oven after 18 to 24 hours of reaction time. The coke contains 90 to 93% carbon,
some ash and sulphur but compared to raw coal is very strong. The strong pieces of coke
with a high energy value provide permeability, heat and gases which are required to reduce
and melt the iron ore, pellets and sinter.
The final raw material in the iron making process is limestone; which can be in pure calcium
chloride, calcium oxides or dolomite limestone containing magnesia or a blend of the two
types of limestone.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 14 2015
All of the raw materials are stored in separates silos and transferred to the stock-house
before charging. Once these materials are charged into the furnace top, they go through
numerous chemical and physical reactions while descending to the bottom of the furnace.
]The major chemical reactions consists of reduction of iron ore; oxidation (burning) of carbon
in the coke. Another important series of reaction takes place at high temperature is the
reaction of lime with impurities; resulting in slag.
Another product of the iron making process, in addition to molten iron and slag, is hot dirty
gases. These gases exit the top of the blast furnace and proceed through gas cleaning
equipment where particulate matter is removed from the gas and the gas is cooled. This gas
has a considerable energy value so it is burned as a fuel in the “hot blast stoves” which are
used to preheat the air entering the blast furnace to become “hot blast”. Any of the gas not
burned in the stoves is sent to the boiler house and is used to generate steam which turns a
turbo blower that generates the compressed air known as “cold blast” that comes to the
stoves.
Gas Cleaning System of Blast Furnace:
The hot dirty gases generated from the top of the blast furnace shall be cleaned in the Gas
cleaning system. Dry gas cleaning system, in which series of bag filters will be installed.
Figure 4: Typical flow diagram of Blast Furnace
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 15 2015
4 AVAILABILITY & SOURCE OF WATER & WASTEWATER GENERATION
4.1 Source of water and its availability
Required water for domestic and industrial purposes shall be obtained from GWIL (Gujarat
Water Infrastructure Limited).
The water consumption for proposed project activities is as mentioned in Table 6.
Table 6: Net Water Consumption
Purpose Quantity (m3/Day) For
Proposed Project
Cooling 13600
Boiler 7200
Drinking 300
Process 20140
Washing, Sprinkling 1600
Other (Firefighting, Gardening) 850
Total Water Consumption 43690
Welspun group has a rain water harvesting installed for existing project with capacity of
more than 300 crores ltrs. Company is committed to recycle and reuse of wastewater at
possible extent.
4.2 Waste Water generation & Management plan
The total quantity of waste water generated is as mentioned in Table 7.
Table 7: Wastewater generation
Purpose Quantity (m3/Day)
Proposed Disposal Plan
Cooling Blow Down 27 Shall be treated and later reused within the
plan premises for gardening and dust
suppression
Boiler Blow Down 299
Process 511
Domestic 18 Shall be treated in STP and reused for flushing
Total 855
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 16 2015
All the process effluent streams will be collected and treated into Effluent Treatment Plant.
The treated water shall be reused within plant and utilized partly for dust suppression in
approach roads and Green belt development.
A sewage treatment plant has been proposed to treat sewage generated from different
toilets of total plant area. One number of STP has been envisaged. However, the flow
quantity will be varying during different period of the day and the peak flow may go up to
three times the average flow for a certain period of the day
5 SOLID WASTE & HAZARDOUS WASTE GENERATION & MANAGEMENT PLAN
5.1 Solid waste generation and its management plan
The total quantum of Solid waste generated from proposed facility is as given in table below.
Table 8: Solid waste generation
Type Of Waste Total Quantity Of Proposed
Waste Generation Disposal Plan
Blast furnace
Slag 88500 MT/ Month
Company proposes to install
slag granulation plant. The
same shall be later used for
construction of roads
BOF slag 37100 MT/ Month
The same shall be used for
Brick/Road filling and area
grading in form of pellets.
Flue dust 4700 MT/ Month Disposal after Treatment.
Mill Scale 1900 MT/ Month Partly reuse and selling as low
grade Iron Contain item.
STP Sludge This quantity will be very low in
tune of 5 mt /month
It will be treated biologically ,
neutralize & disposed off
5.2 Hazardous waste generation and its management plan
Hazardous waste generated from the proposed unit is as mentioned in table below
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 17 2015
Table 9: Hazardous Waste generation
Waste Generated Proposed
Quantity Disposal Plan
Lube oil sludge/Coolant oil
sludge
1.5 MT/annum
Recycled to coke plant/Power
plant
Lead acid batteries 1.5 MT/annum Auctioned to registered
recycler
Used Lube oil 1.5 MT/annum Injected in BF/CO/Power
Plant
ETP Sludge This will be
almost negligible
This will be treated with
neutralizing agents, stabilized
& disposed
6 STACK DETAILS AND AIR POLLUTION CONTROL MEASURES
The list of stacks to be installed for proposed project is as mentioned in table below. For
abatement of air pollution, Air pollution control equipment will be installed at point source.
Table 10: Stack details with APC measures for point source emissions
Stack attached to Stack Height from GL,
meters, m APC
BF-HBS - Chimney 55 Bag filter/ electrostatic
precipitators
BF Dedusting
Chimney(Tapered)-cast house 50
Bag filter/ electrostatic
precipitators
Secondary Dedusting System of
BOF 30
Bag filter/ electrostatic
precipitators
Sinter Plant Dedusting
Chimneys-3 nos for screening,
proportioning & crusher house
50 Bag filter/ electrostatic
precipitators
Coke oven heat recovery power
plant 126 MW (WHRB) 110
Bag filter/ electrostatic
precipitators
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 18 2015
Sinter Plant ESP Chimney 70 Bag filter/ electrostatic
precipitators, etc.
BF stock house bag filter
chimney 30
Bag filter/ electrostatic
precipitators, etc.
Pushing Emission Control
System 30
Bag filter/ electrostatic
precipitators
Bar mill - stack 70 Bag filter/ electrostatic
precipitators,
SMS-Chimney BOF flare stack 80 Bag filter/ electrostatic
precipitators,
Lime & dolo plant kiln (2
stacks) 60 Bag filters
Table 11: APC measures for fugitive emissions
Shop / Unit Proposed facilities
Steel melting shop Gas coolers, scrubber, chimney,
etc.
Material handling
system
Bag filters, dust suppression
system, etc.
7 SOURCE OF ELECTRICITY AND ITS AVAILABILITY
Electricity shall be obtained partly from SEB. The total power requirement for the plant for
proposed project is given in Table 12.
Table 12: Electricity allocation
Source Of Power Quantum For Proposed Project
SEB /Grid 130.5 MW
Captive Power Plant 126 MW
DG Sets (Stand By) 6 MW (2 MW× 3 nos.)
Type of fuel to be used in DG set - Dual fuel (Diesel and Gas)
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 19 2015
8 SITE ANALYSIS
8.1 Connectivity
The project site is well connected to Anjar-Bhachau road. The site is well connected by road
and rail to rest of country. The details of highway and rail network are as mentioned below:
Table 13: Connectivity
Description Distance
Transportation
Anjar-Bhachau Rd: ∼ 0.5 Km
Rail : Anjar (~ 3.5 Km)
Port: Kandla (~ 10 Km)
Nearest Town/City Town: Anjar (~ 3.5 Km)
City: Gandhidham (~ 5 km )
Nearest Village Varshamedi (~ 0.7 Km)
8.2 Land Form, Land use and Land ownership
The proposed project will be set up in industrial land. NA has been already taken.
8.3 Topography (along with map)
The topography map shall be submitted at the time of presentation.
8.4 Existing land use pattern (agriculture, non agriculture, forest, water bodies
– including CRZ), shortest distances from the periphery of the project to periphery
of the forests, national park, wild life, sanctuary, eco sensitive areas, water bodies
(distance from HFL of the river), CRZ. In case of notified industrial area, a copy of
Gazette notification should be given.
There is no forest, national park, wild life sanctuary, eco sensitive areas in surrounding 10
Km of the plant boundary.
8.5 Existing infrastructure
No
8.6 Soil classification
Detail soil testing report will be provided at the time of presentation.
8.7 Climatic data from secondary sources
The climatic data for December 2014 to January 2015 in the study are as below
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 20 2015
Table 14: Meteorology data
Average Wind speed 5.71 m/s.
Temperature 10oC to 34oC
Average Relative humidity 15 % to 68 %.
8.8 Social Infrastructure available
The project site is located approximately 2 km from the human settlement (village:
Varshamedi). Basic amenities of life are easily available in the area. Primary health centre,
school, drinking water, electricity, communication, road network, transportation facility is
available in the vicinity.
The existing infrastructure is sufficient to cater the additional load due to the proposed
project.
9 PLANNING BRIEF
9.1 Planning Concept (type of industries, facilities, transportation etc) Town
and country planning/ Development authority classification
The industrial area and the related facilities for integrated Steel plant would be developed.
Additionally, the nearby towns have all the modern facilities.
9.2 Population Projection
There would not be any significant increase in the population of surrounding area as the
additional workers for the proposed project will come from the local residents in the
surrounding villages. There won’t be any influx of people in the area due to proposed
project
9.3 Land use planning (break up along with green belt etc)
The total area of site where the plant is to be located is Around 576 acres. The area will be
bifurcated for following utilities and plant area
• Raw material yard
• Sinter plant
• Blast Furnace
• SMS (Steel Melt Shop) with Casters including bar Mill
• Oxygen Plant
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 21 2015
• Water Facilities
• Producer Gas Plant
• Coke Oven
• Coke Oven waste material storage for disposal
• Water reservoir
The green area is about 60 acres. The balance area is free area used for transportation,
railway tracks, stores, canteen, workshop etc.
9.4 Amenities/ Facilities
Major basic facilities are available for the proposed project. Road, electricity, water,
transportation facility etc are well developed in the surrounding area.
All the amenities related to project on the site will be installed
10 PROPOSED INFRASTRUCTURE
10.1 Industrial area (Processing area)
The total industrial area of the company is approx 183 acres.
10.2 Residential area (Non processing area)
Group is having existing housing for workers which will be expanded. Canteen is also
proposed to set up.
10.3 Green belt
Company is committed to develop dense green belt area in proposed project plant as per
government rules. Green belt is proposed to develop in approx 60 acres area. Following are
the proposed species of trees which are planned to be plant
• Ashoka trees
• Neem trees
• Mango trees
• Gul-mahor
10.4 Social infrastructure
Basic amenities of life are easily available in the area. Primary health centre, school,
drinking water, electricity, communication, road network, transportation facility is available
in the vicinity.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 22 2015
10.5 Drinking water Management (Source & Supply of water)
Water shall be obtained from Gujarat Water Infrastructure Ltd.
10.6 Sewerage system
A sewage treatment plant has been proposed to treat sewage generated from different
toilets of total plant area. One number of STP with average flow of 10 m3 / hr capacity has
been envisaged. However, the flow quantity will be varying during different period of the
day and the peak flow may go upto three times the average flow for a certain period of the
day. And treated waste water will be utilized for green belt development and ground water
recharge.
11 REHABILITATION AND RESETTLEMENT (R & R) PLAN
11.1 Policy to be adopted (Central/ state) in respect of the project affected
persons including home oustees, land oustees and landless laborers
Not applicable
12 PROJECT SCHEDULE & COST ESTIMATES
12.1 Likely date of start of construction and likely date of completion
Likely date of start of construction: With in one month after obtaining EC
Likely date of completion of construction: August 2016
12.2 Estimated project cost along with analysis in terms of economic viability of
the project
Total project cost: 7885 Crores
13 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
13.1 Financial and social benefits with special emphasis on the benefit to the
local people including tribal population, if any, in the area
The following activities will be done for social welfare –
• Contributions in Schools and colleges in near by villages.
• Tree Plantation at nearby villages.
• Contributions to Prime minister’s Swachha Bharat Abhiyan. Under this campaign,
company has decided to provide toilet to 30 poor families.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 23 2015
13.2 Budgetary allocation for social welfare in the area
Rs. 15 lakhs will be spent annually on Social Welfare Activity.
13.3 Expenditure on Environmental Matters: estimated
Environmental Issues Capital Cost (Rs)
Air Pollution Control 2000 Lacs
Water Pollution Control 1000 Lacs
Noise Pollution Control 150 Lacs
Environmental Monitoring
And Management
10 Lacs per year
Occupational Health 7 Lacs per year
Green Belt 15 Lacs per year
14 SCHEMATIC REPRESENTATION OF THE FEASIBILITY DRAWING WHICH GIVE
INFORMATION OF EIA PURPOSE
The proposed project of integrated steel plant and captive power plant falls under category
A, section 3 (a) and 1 (d) of EIA notification September 2006 and amendment there of vide
notification no. S.O 3067 (E) dated 1st December 2009, which require prior Environmental
Clearance before starting construction, production or any other allied activities related to
the project. For getting the Environmental Clearance; it is required to carry out the
Environmental Impact Assessment (EIA) study report.
Definition of EIA
Environmental Impact Assessment (EIA) is a formal process used to predict how industrial
development or construction project will affect natural resources such as water, air, land,
socioeconomic and bio ecological environment.
An EIA usually involves a sequence of steps:
(1) Screening to decide if a project requires assessment and to what level of detail.
(2) Preliminary assessment to identify key impacts, their magnitude, significance, and
importance.
PREFEASIBILITY REPORT WELSPUN IRON & STEEL PVT. LIMITED
DETOX CORPORATION PRIVATE LIMITED 24 2015
(3) Scoping to ensure the EIA focuses on key issues and to determine, where more detailed
information is needed.
(4) Implementing the main EIA study, which involves detailed investigations to predict
impacts, assess their consequences, or both.
Methodology
Environmental Impact Assessment (EIA) studies include identification, assessment,
quantitative evaluation and prediction of possible impacts. To minimize the impact of the
project on various environmental attributes, mitigation measures are suggested for
implementation along with the project.
The methodology of this study can be schematized as detailed below:
To gather information on present environmental conditions and relevant national
environmental guidelines and EIA procedures.
Scoping of impacts.
Assessment of significant impacts.
Description of residual impacts.
Development of monitoring plans.
To inform all relevant and involved authorities regarding the impact of the project on
the environment and the proposed mitigation measures.