PRE-FEASIBILITY REPORT Contents Details 1. Executive...

22
M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd Authorized signatory EIA Consultant PRE-FEASIBILITY REPORT (As per Ministry of Environment and Forests Letter dated: 30-12-2010) Contents Details 1. Executive Summary Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra Nos.- 394, 395, 397, 396, 402, 446, 403, Near Village- Rampura, Tehsil- Neem Ka Thana, District- Jaipur, Rajasthan. It is a non forest mining project. The mine will be operated by semi mechanized mining method, which will require little blasting. Blasting will be done if necessary after taking pre-consent from DGMS and other concerning district and tehsil level authorities/officials. It is proposed to avoid blasting as much as possible as blasting creates cracks in the marble block. Total Reserves [Proved (111) & Probable (121) as per UNFC] of Marble are estimated at 6,00,900 T and 6,95,760 T respectively. The life of the mine is expected to be 11 Years. The ML area is plane land. Topographically the mining lease area is hilly land. The highest contour is 346 mRL and the lowest contour is 324 mRL. Slope of the natural drainage is towards NE to SW. The mining operations will include drilling, cutting of blocks from thadi, separating the required size block from big block, lifting of mineral and material, loading of mineral and material and transportation of material. The mined out mineral from stock site will be dispatched to destination through hired trucks. No beneficiation is required at site. Khanda will be dispatched to grinding units and block will be dispatched to cutting units. Total mining area is 3.0 ha. At the end of life of mine, total excavated area will be 2.70 ha., which will be left over for water reservoir which would have a positive impact by recharging the ground water table. As the continuity of mineral may be goes in depth beyond the present reserves limit. Thus at this stage reclamation is not proposed. The scheme of reclamation will be provided at proper time. Presently the excavated land is proposed to use as water reservoir, which would have a positive impact by recharging the ground water table. It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33% of the total lease area. 120 trees will be planted in 0.30 ha. land along the barrier of 7.5 m along the boundary of mine lease and all around haul roads and rest 280 trees will be planted in 0.70 ha. Gram Panchyat land after getting due permission. Certain Species like Khejri, Ker, Babool, Neem, Mango & other fruit bearing trees which are more suitable to local soil are proposed to be planted. Brief Description about the Project: Project Name Rampura Marble Mine Mining Lease Number ML No.- 420/91 Lessee M/s Continental Minerals Pvt. Ltd. Directors: 1. Shri Anand Kumar Agarwal 2. Smt. Neelam Modi 3. Smt. Bhagwati Devi Agarwal Location of Mine Near Village- Rampura, Tehsil- Neem Ka Thana, District- Sikar, Rajasthan Geographical Location Latitude- 27°48’00.12”N

Transcript of PRE-FEASIBILITY REPORT Contents Details 1. Executive...

Page 1: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

PRE-FEASIBILITY REPORT

(As per Ministry of Environment and Forests Letter dated: 30-12-2010)

Contents Details

1. Executive Summary Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The

Mine Lease area consists of 3.0 ha, which is located at Khasra Nos.- 394, 395, 397, 396, 402,

446, 403, Near Village- Rampura, Tehsil- Neem Ka Thana, District- Jaipur, Rajasthan. It is a non

forest mining project.

The mine will be operated by semi mechanized mining method, which will require little

blasting. Blasting will be done if necessary after taking pre-consent from DGMS and other

concerning district and tehsil level authorities/officials. It is proposed to avoid blasting as much

as possible as blasting creates cracks in the marble block.

Total Reserves [Proved (111) & Probable (121) as per UNFC] of Marble are estimated at

6,00,900 T and 6,95,760 T respectively. The life of the mine is expected to be 11 Years. The ML

area is plane land. Topographically the mining lease area is hilly land. The highest contour is 346

mRL and the lowest contour is 324 mRL. Slope of the natural drainage is towards NE to SW.

The mining operations will include drilling, cutting of blocks from thadi, separating the required

size block from big block, lifting of mineral and material, loading of mineral and material and

transportation of material. The mined out mineral from stock site will be dispatched to

destination through hired trucks. No beneficiation is required at site. Khanda will be dispatched

to grinding units and block will be dispatched to cutting units.

Total mining area is 3.0 ha. At the end of life of mine, total excavated area will be 2.70 ha.,

which will be left over for water reservoir which would have a positive impact by recharging the

ground water table. As the continuity of mineral may be goes in depth beyond the present

reserves limit. Thus at this stage reclamation is not proposed. The scheme of reclamation will be

provided at proper time. Presently the excavated land is proposed to use as water reservoir,

which would have a positive impact by recharging the ground water table.

It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33% of the total lease area. 120

trees will be planted in 0.30 ha. land along the barrier of 7.5 m along the boundary of mine lease

and all around haul roads and rest 280 trees will be planted in 0.70 ha. Gram Panchyat land after

getting due permission. Certain Species like Khejri, Ker, Babool, Neem, Mango & other fruit

bearing trees which are more suitable to local soil are proposed to be planted.

Brief Description about the Project:

Project Name Rampura Marble Mine

Mining Lease Number ML No.- 420/91

Lessee M/s Continental Minerals Pvt. Ltd.

Directors:

1. Shri Anand Kumar Agarwal

2. Smt. Neelam Modi

3. Smt. Bhagwati Devi Agarwal

Location of Mine Near Village- Rampura, Tehsil- Neem Ka Thana,

District- Sikar, Rajasthan

Geographical Location Latitude- 27°48’00.12”N

Page 2: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Longitude - 76°02’15.91”E

Toposheet Number 54A/1

Mineral Marble

Total Mineable Reserves

(Proved + Probable)

12,96,660 T (6,00,900 T + 6,95,760 T)

Average Annual

Production

1,48,770 TPA

Method of Mining Semi Mechanized Opencast Method

Lease Validity 30 Years

Life of Mine 11 Years

Water Demand 2 KLD

Sources of Water Bore well near the lease area

Power Supply Electric power will be fulfilled by JVVNL, Rampura

Man Power 32 Personnel (Skilled Labour- 6, Semi- Skilled Labour- 6,

Unskilled Labour- 20)

Nearest Railway Station Dabla Railway Station- 13.31Kms towards NNW

Jhilo Railway Station- 15.95 Kms towards WNW

Nearest National Highway NH- 8 -18.82 Kms towards NE

SH- 37B- 2.53 Kms towards SW

Nearest Airport Jaipur International Airport- 110.22 Kms towards SSW

Seismic Zone Seismic zone - Zone II

Topography Topographically the mining lease area is hilly land. The highest

contour is 346 mRL and the lowest contour is 324 mRL. Slope

of the natural drainage is towards NE to SW.

Land Status Private & Government Waste Land

Land Degradation and

Reclamation

Total Mine Lease Area - 3.0 ha .

Area to be water reservoir- 2.70 ha.

Mining Operations The mining operations will include drilling, cutting of blocks

from thadi, separating the required size block from big block,

lifting of mineral and material, loading of mineral and material

and transportation of material.

Plantation Proposal It is proposed to plant total 400 trees in 1.0 Hectare land i.e.

33.33% of the total lease area. 120 trees will be planted in 0.30

ha. land along the barrier of 7.5 m along the boundary of mine

lease and all around haul roads and rest 280 trees will be planted

in 0.70 ha. Gram Panchyat land after getting due permission.

Certain Species like Khejri, Ker, Babool, Neem, Mango & other

fruit bearing trees which are more suitable to local soil are

proposed to be planted.

Ground Water Table 55 m bgl (in Rainy Season) to 60 m bgl (in Dry Season)

Ultimate Depth of Pit 285 mRL

Project Cost Rs. 25 Lacs

2. Introduction of the project Background information

i. Identification of Rampura Marble Mine (M.L. No- 420/91) is proposed by M/s

Page 3: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

project and project

proponent. In case of

mining project, a

copy of mining

lease/ letter of intent

should be given.

Continental Minerals Pvt. Ltd.

The Mine Lease area consists of 3.0 ha, which is located at Khasra

Nos.- 394, 395, 397, 396, 402, 446, 403, Near Village- Rampura,

Tehsil- Neem Ka Thana, District- Jaipur, Rajasthan.

Directorate of Mines & Geology, Sikar, Govt. of Rajasthan has

allotted the mine lease in favor of M/s Oriental Talc Products Pvt.

Ltd. vide order No.- 1443 dated 30.11.1992 for a period of 10

years (15.02.1993 to 14.02.2003). Then mine lease was transferred

to M/s Continental Minerals Pvt. Ltd. vide Directorate of Mines &

Geology, Sikar, Govt. of Rajasthan order No.- निद/ेप-2(ए-

3)/िीम/साख/92/163 dated 21.03.1995. The lease period was

extended for 10 years (from 10 years to 20 years) by Directorate of

Mines & Geology, Sikar, Govt. of Rajasthan vide order No.- 1885

dated 29.06.2002. Again lease period was extended from 20 years to

30 years by Directorate of Mines & Geology, Sikar, Govt. of

Rajasthan vide order No.- खअ/सीकर/अप्र/खप-420/91/801 dated

28.02.2012. The renewed period is 15.02.1993 to 14.02.2023.

Copy of lease documents and lease period extension letter is

enclosed as Annexure.

The mining scheme with progressive mine closure plan for Marble

Mine (M. L. No.- 420/91), lease area- 3.0 ha, Near village-

Rampura, Tehsil- Neem Ka Thana, District- Sikar State- Rajasthan

is submitted under rule 18(1) of Marble Development and

Conservation Rules-2002 for the exiting lease area.

ii. Brief description of

nature of the project.

The total ML area spreads in an area of 3.0 ha. The mine will be

operated to produce Marble mineral. The mineralized area is

almost free from soil. The mine will be operated by manual slice

wise, opencast method with proper benching.

Total Reserves [Proved (111) & Probable (121) as per UNFC] of

Marble are estimated at 6,00,900 T and 6,95,760 T respectively.

The life of the mine is expected to be 11 Years.

Total mining area is 3.0 ha. At the end of life of mine, total

excavated area will be 2.70 ha., which will be left over for water

reservoir which would have a positive impact by recharging the

ground water table. As the continuity of mineral may be goes in

depth beyond the present reserves limit. Thus at this stage

reclamation is not proposed. The scheme of reclamation will be

provided at proper time. Presently the excavated land is proposed

to use as water reservoir, which would have a positive impact by

recharging the ground water table.

Page 4: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

iii. Need for the project

and its importance to

the country and or

region.

Marble occurrences are widely distributed in India. However,

occurrences of economic importance are limited to a few states

namely Rajasthan, Madhya Pradesh, Gujarat, Haryana and Andhra

Pradesh. Makrana marble and green marble have became famous

world over. Rajasthan has the largest rescores of good quality

marble in India. Total recoverable reserves of marble in India are

estimated at 825 million tonnes by IBM, out of which 563 million

tonnes alone are found in Rajasthan. As per the information from

Stona-2000, Rajasthan possesses 11,000 million tonnes of mineable

marble reserves. The following statement shows reserves of various

marble belts/ deposits of Rajasthan.

Rajasthan has a large spectrum of minerals in which building stones

enjoy an important place. Marble occupies a unique position among

building stones due to its pleasant look and easy carving. The term

marble is derived from the Latin world "marmor" which itself

comes from the Greek root "marmarous", meaning thereby a shining

stone.

S.

No. Deposit/belt District

Reserves

(Million

tonnes)

1. Agaria- Amet- Kelwa-Morwad Rajsamand 387

2. Makrana Nagaur 56

3. Keshariaji Udaipur 40

4. Babarmal (Devimata) Udaipur 60

5. Tripura Sundari- Talai-Odabasi-

Bhimkund - Vithaldeo Banswara 230

6. Andhi- Bhainslana Jaipur 50

7. Jhiri -Sariska Alwar 20

8. Selwara-Dhanvav- Koteswar Sirohi 80

9. Jahajpur- Kekri Bhilwara 60

10. Kalyanpura-Narwar-Saradhana Ajmer 60

11. Patan-Rampura Sikar 10

12. Umar Bundi 25

13. Dungarpur Dungarpur 10

14. Chittaurgarh Chittaurgarh 7

15. Pali Pali 3

16. Jaisalmer Jaisalmer 2

Total 1100

Page 5: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

About 85% country's production is shared by Rajasthan. It has

produced 4278.63 thousand tonnes of marble during 1999-2000

worth for Rs. 42903.15 lacks rupees (Sale value).

From the times immemorial marble has been used to perpetuate the

memory of individual, to immortalise their achievements and to

glorify the deities. A number of temples (Ranakpur and Delwara

Jain temples), mosques (Taj Mahal) and monuments (Victoria

Memorials) etc. have been built in the past under the lavish

patronage of kings and noblemen. For these purpose, marble has

been much preferred because of its easy workability, pleasing

colours, attractive patterns and resistance to failure under abrasive

traffic. The use of marble not only enhances the aesthetic beauty of

a building but also imparts a feeling of dignity to the structure.

Marbles: Rajasthan is the largest producer and resource holder of

marble in India (marmaros in Greek means shining stone). The state

accounts for ~90% of India’s marble production. Marble has

fascinated man for ages and it has been used for innumerable

attractive buildings, temples, monuments, statues, carvings, etc.

Over the centuries, any attractive stone has been indifferently called

marble (sensu lato). Even now any good quality ornamental and

decorative stone is referred to as marble; the world famous

serpentine of Rikhabdev area (south of Udaipur) is unhesitantly

called green marble! Besides marble, sensu stricto, Rajasthan also

has well-liked and admired resources of limestones, granites,

sandstones, slates, etc.

Page 6: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Decorative and dimensional stones from Rajasthan have been used

in construction of numerous landmark buildings – forts, palaces,

temples, mosque, monuments, etc., especially in the national capital

Delhi, Agra, Fatehpur Sikri. Some of the renowned buildings are:

the imposing Rashtrapati Bhawan (the Presidential Estate, formerly

the Viceregal Lodge completed in 1929) and accompany

Government of India Buildings, the historic Red Fort, Delhi; the

captivating Taj Mahal and Red Fort, Agra; Fatehpur Sikri - the

capital city built by the Mughal Emperor Akbar (1556-1605); the

intricately carved Dilwara Jain Temples (11-13 centuries), Mt. Abu;

the magnificent Umed Bhawan Place, Jodhpur; the appealing

Havelies of Jaisalmer and scores of other villages.

Availability: In districts of Nagaur, Udaipur, Banswara, Jaipur

Sirohi, Bhilwara, Ajmer, Bundi, Pali, Dungarpur,Chittorgarh,

Jaisalmer and Sikar, Rajsamand, Alwar.

Color & Pattern: Snow white, Creamish white, White with

grayish/ black bands and Wavy patterns, pink, pink with

bluish bands, green, yellow, black, multi-color etc.

Export varieties: Snow white - very fine-grained, green and

pink. Indian green is highly priced and is the most desired marble

in demand the world over.

Number of mining leases: About 3600

Marble Processing Capacity: Slabs-1000 million sq.ft. p.a Tile-

300 million sq.ft. p.a.

Marble the pride of India

Practically inexhaustible marble deposits-over 1200 million

tons

Splendid varieties of white, green, black, grey, pink, yellow

Physical and mechanical properties complying with

international standards.

Amongst the top 5 countries in marble exports.

A Vibrant Industry

Total Investment - over Rs.40, 000 million (US $1,000

million).

About 4,000 mining leases.

Block production 3.7 million tons in 1996-97.

About 1,100 modern gang saw units and 50 Automatic tiling

plants.

More than 5,000 trading companies.

Employing about 1 million people.

Fast developing modern mechanized quarries.

Page 7: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Over 300 quarries using diamond wire saw & chainsaw cutter

quarrying technology.

Modern & well equipped factories with advanced Italian

technology for cutting, processing, polishing and handling.

Marble slab & tile production: 1300 million sq. ft per annum.

Impressive Marble Export

Increase of over 300% from US $ 9 million in 1992-93 to US

$ 27 million in 1996-97.

Excellent quality export varieties - Green, Onyx, Indo Italian,

White and Pink marble.

High quality polished marble tiles & slabs and green & white

marble blocks correspond to demand in the foreign market.

High export demand for marble handicrafts.

Key marble export markets - USA, Canada, Japan, Singapore,

UAE, EC countries.

Rajasthan's share in Indian Stone production

Mineral % of India's total production

Marble 91%

Kota stone (Flaggy

limestone) 90%

Sandstone 90%

Slate 10%

Granite 2.2%

Page 8: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

iv. Demand-Supply Gap Rajasthan has been bestowed with huge reserves of marble. So far

there is no problem as such of shortage of supply of marble in the

state. Estimated reserves of the state are 1100 million tones, which

are more than 9% of the total marble reserve in the country. The

present hard times faced by the industry in the state are in fact a

result of imbalance of demand and supply of marble in the market.

Lured by the high profit and margins of the trade, several

entrepreneurs have entered in the industry. With the advent of

modern technology in the past few decades, the production of

Marble has increased like anything. The cost of production has

come down and the speed and quality of production have improved

a lot. Moreover, the reduction in wastage has also resulted in

increased production. All this resulted in supply of huge surplus to

the demand in the market.

It is well known fact that marble now has become a thing of

necessity, rather than a luxury. Marble has now become the

cheapest and best option for the building constructions besides the

other uses. The demand of marble has grown steadily in the past few

decades. Through the supply of marble in market is much more than

the demand. (Production Trends (in Thousand Tons)

2005-06 2006-07 2007-08 2008-09 2009-10

8147.29 7572.71 8719.81 9511.50 11634.26

v. Imports vs.

Indigenous

production

Indigenous production.

vi. Export Possibility Increase of over 300% from US $ 9 million in 1992-93 to US $

27 million in 1996-97.

Excellent quality export varieties - Green, Onyx, Indo Italian,

White and Pink marble.

High quality polished marble tiles & slabs and green & white

marble blocks correspond to demand in the foreign market.

High export demand for marble handicrafts.

Key marble export markets - USA, Canada, Japan, Singapore,

UAE, EC countries.

vii. Domestic/export

Markets

Domestic Markets

The mineral will be sold out in the local and nearby city market to

fulfill the requirements of the local people.

viii. Employment

Generation (Direct

and Indirect) due to

the project.

The operational manpower requirement of the mine will be about

32 Personnel (Skilled Labour- 6, Semi- Skilled Labour- 6,

Unskilled Labour- 20). Man power will be sourced from the nearby

villages. Another 30-40 personnel will be benefited from the

indirect employment generated due to mining operations.

Page 9: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Management and Supervisory Personnel:

The following supervisory personnel are proposed with

management chart:-

Management Chart

Labours- Skilled, Semi- Skilled and Un-Skilled

S. No. Particular Exiting Expansion

1. Skilled 12 6

2. Semi Skilled 4 6

3. Un-Skilled 45 20

Total 61 32

3. Project Description

i. Type of project

including interlinked

and interdependent

projects, if any.

It is an opencast mining project, with little mechanization. The

mined out mineral from stock site will be dispatched to destination

through hired trucks.

The mining scheme with progressive mine closure plan for Marble

Mine (M. L. No.- 420/91), lease area- 3.0 ha, Near village-

Rampura, Tehsil- Neem Ka Thana, District- Sikar State- Rajasthan

is submitted under rule 18(1) of Marble Development and

Conservation Rules-2002 for the exiting lease area.

The ML area is well connected with the roads and highways. The

mineral will be transported by means of trucks and sold out in the

local market.

ii. Location (map

showing general

location, specific

location, and project

boundary & project

site layout) with

coordinates.

The Mine Lease area consists of 3.0 ha, which is located at Khasra

Nos.- 394, 395, 397, 396, 402, 446, 403, Near Village- Rampura,

Tehsil- Neem Ka Thana, District- Jaipur, Rajasthan.

Toposheet No.- 45 M/10

Geographical Location:

Latitude- 27°48’00.12”N

Mining Engineer

Mines Manager

Mining Mate

Store Keeper

Watchman

Mine Labours

Timekeeper

Drivers

Page 10: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Longitude - 76°02’15.91”E

Google imagery showing 10 Km radius around the ML area is

enclosed as Annexure.

Lease Description Report

From To Bearing Distance (meter)

NW Corner

FRP

X 238˚00’ 200

X A 311˚00’ 050

A B 244˚00’ 200

B C 154˚00’ 150

C D 064˚00’ 200

D A 334˚00’ 150

Lease Area- 3.0 Hectare

iii. Details of alternate

sites considered and

the basis of selecting

the proposed site,

particularly the

environmental

considerations gone

into should be

highlighted.

No alternate sites were considered as the project is mineral specific.

iv. Size or magnitude of

operation.

ML area spreads in an area of 3.0 ha. The mine is capable of

producing 148770 TPA of marble. As per proposals required

production will be achieved every year. 20% variation may take

place in target as per market requirement.

Size or Magnitude

S. No. Particulars Exiting Proposed

1 Lease Area 3.0 ha 3.0 ha

2 Mineable Reserve

(Marble)

8,61,840 T 12,96,660 T

3 Average

Production

1,20,000 TPA 148770 TPA

4 Mine Waste 500 TPA 79,580 TPA

5 Life of mine 7 Years 8 Years

6 Period of lease 20 years 30 years

7 Total Man Power 61 36 Ultimate Extent and Size of the pit:

The ultimate extent and size of the pit is the surface limit of

proposed excavation up to end of mining. The ultimate extent will

Page 11: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

be as follows:

Size Deposit

Length of deposit 200 m

Width of deposit 142 m

Depth of deposit 60 m

Yearwise Production of Minerals (in tonnes)

Year ROM Waste Mineral

2014-2015 - - -

2015-2016 73370 44350 29020

2016-2017 139520 51900 87620

2017-2018 117930 23580 94350

2018-2019 185950 37180 148770

Total 516770 157010 359760

This production may increase or decrease 10% as per fluctuation in market.

Extent of Mechanization

Item Quantity Capacity

Compressors (Tractor mounted or stable) 1 120 PSI

Jackhammer and other pneumatic or

hydraulic drill

As needed -

Mobile Crane 1 15-20 tonne

Derrick Crane 2 -

Excavator 1 0.3 or 0.9 cu. meter

Tippers 4 -

Rock Breakers attachment 1 -

Wagon drill 1 -

Slot Liners As needed -

Line Drilling Machines As needed -

Diamond Wire Saw 3 -

Wire Saws or Diamond Belt Saws As needed -

Hydraulic Jack As needed -

Tractor with water tank 1 -

v. Project description

with process details

(a schematic

diagram, flow chart

showing the project

layout, components

of the project etc.

should be given)

Rampura Marble Mine is proposed by M/s Continental Minerals

Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at

Khasra Nos.- 394, 395, 397, 396, 402, 446, 403, Near Village-

Rampura, Tehsil- Neem Ka Thana, District- Jaipur, Rajasthan. It is

a non forest mining project.

The mine will be operated by semi mechanized mining method,

which will require little blasting. Blasting will be done if necessary

after taking pre-consent from DGMS and other concerning district

and tehsil level authorities/officials. It is proposed to avoid blasting

as much as possible as blasting creates cracks in the marble block.

Total Reserves [Proved (111) & Probable (121) as per UNFC] of

Page 12: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Marble are estimated at 6,00,900 T and 6,95,760 T respectively.

The life of the mine is expected to be 11 Years. The ML area is

plane land.

The mining operations will include drilling, cutting of blocks from

thadi, separating the required size block from big block, lifting of

mineral and material, loading of mineral and material and

transportation of material. The mined out mineral from stock site

will be dispatched to destination through hired trucks. No

beneficiation is required at site. Khanda will be dispatched to

grinding units and block will be dispatched to cutting units.

Total mining area is 3.0 ha. At the end of life of mine, total

excavated area will be 2.70 ha., which will be left over for water

reservoir which would have a positive impact by recharging the

ground water table. As the continuity of mineral may be goes in

depth beyond the present reserves limit. Thus at this stage

reclamation is not proposed. The scheme of reclamation will be

provided at proper time. Presently the excavated land is proposed

to use as water reservoir, which would have a positive impact by

recharging the ground water table.

It is proposed to plant total 400 trees in 1.0 Hectare land i.e.

33.33% of the total lease area. 120 trees will be planted in 0.30 ha.

land along the barrier of 7.5 m along the boundary of mine lease

and all around haul roads and rest 280 trees will be planted in 0.70

ha. Gram Panchyat land after getting due permission.

vi. Raw material

required along with

estimated quantity,

likely source,

marketing area of

final products, Mode

of transport of raw

Material and

Finished Product.

No raw materials are required, since it is a mining project. No

mineral processing will be carried out in the ML area; mineral will

be sold as such.

vii. Resource

optimization /

recycling and reuse

envisaged in the

project, if any,

should be briefly

outlined.

The mine will be closed during monsoon season, if the water is

accumulated in mine pit prior to the post monsoon mining

operations, it will be pumped out, for the irrigation purpose in the

nearby agricultural fields, after ensuring it is free from any

suspended solids.

viii. Availability of water

its source, Energy/

power requirement

Drinking water will be procured from the bore well outside the ML

area. It will be stored in a container and used for drinking purpose.

Page 13: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

and source should be

given.

ix. Quantity of wastes to

be generated (liquid

and solid) and

scheme for their

Management/

disposal.

Liquid Waste:

Domestic waste water (0.56 KLD) will be generated from office

toilet. Generated domestic waste water will be disposed through

septic tank followed by soak pit.

Solid Waste:

Top Soil Top soil is observed on surface in thin layer. It is proposed to scrape

the soil and stacked separately which will be used for plantation.

Overburden

The waste will be weathered marble and marble having foreign

intrusions and soil. The generation of waste during first five years

will be as followed:

Year Waste (in tonne)

2014-2015 -

2015-2016 44350

2016-2017 51900

2017-2018 23580

2018-2019 37180

Total 157010

About 1,57,010 tonnes of waste will be generated during next five

years. Waste will be dumped outside the lease area on common

dump sites located in nearby lease area and Some waste will be

lifted by local habitants and rest waste will be dumped within the

ML area, in an earmarked area of 0.06 hectare for 5.0 m height. The

waste dump is proposed to stabilize by retaining wall of rubble

stones. Stone wall is proposed of 1.0 m height and 2.0 m width

towards lower altitude side which will prevent the spreading of

waste. Further, a garland drain is proposed towards lower side of the

dumps to check the wash off from the dumps/ to check the silt

during monsoon. Plantation is also proposed over the matured

dumps for stabilization.

No watercourse is proposed to disturb/obstruct by proposed

dumping activities.

x. Schematic

representations of

the feasibility

drawing which give

information of EIA

purpose.

Map showing Composite Plan & Year wise Sections is enclosed.

Page 14: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

4. Site Analysis

i. Connectivity. The ML area is well connected with the following.

Nearest Roadways:

NH- 8 - 18.82 Kms towards NE

SH- 37B- 2.53 Kms towards SW

Nearest Railway Station:

Dabla Railway Station- 13.31Kms towards NNW

Jhilo Railway Station- 15.95 Kms towards WNW

Nearest Airport:

Jaipur International Airport- 110.22 Kms towards SSW

ii. Land Form, Land use

and Land ownership.

It is a Non Forest Land which is owned by M/s Continental

Minerals Pvt. Ltd.

iii. Topography (along

with map).

ML area is having plane topography. Google imagery showing 10

Km radius around the ML area is enclosed as Annexure.

Regional Geology:

Intrusive Post Bhilwara Quartz venes & pegmatite’s etc.

Bhilwara

Super group

Sawar group Morhi Formation

Calc- Silicate/Diplomatic

Marble/ Biotite Schist/Quartzite

Glatiali Formation/ Quartzite

marble, Diplomatic

Marble/Mica schist/ phyalite/

carbonate phyalite

iv. Existing land use

pattern (agriculture,

non-agriculture,

forest, water bodies

(including area under

CRZ)), shortest

distances from the

periphery of the

project to periphery

of the forests,

national park, wild

life sanctuary, eco

sensitive areas, water

bodies (distance from

the HFL of the

river),CRZ. In case

of notified industrial

area, a copy of the

Gazette Notification

Directorate of Mines & Geology, Sikar, Govt. of Rajasthan has

allotted the mine lease in favor of M/s Oriental Talc Products Pvt.

Ltd. vide order No.- 1443 dated 30.11.1992 for a period of 10

years (15.02.1993 to 14.02.2003). Then mine lease was transferred

to M/s Continental Minerals Pvt. Ltd. vide Directorate of Mines &

Geology, Sikar, Govt. of Rajasthan order No.- निद/ेप-2(ए-

3)/िीम/साख/92/163 dated 21.03.1995. The lease period was

extended for 10 years (from 10 years to 20 years) by Directorate of

Mines & Geology, Sikar, Govt. of Rajasthan vide order No.- 1885

dated 29.06.2002. Again lease period was extended from 20 years to

30 years by Directorate of Mines & Geology, Sikar, Govt. of

Rajasthan vide order No.- खअ/सीकर/अप्र/खप-420/91/801 dated

28.02.2012. The renewed period is 15.02.1993 to 14.02.2023.

Copy of lease documents and lease period extension letter is

enclosed as Annexure.

The mining scheme with progressive mine closure plan for Marble

Page 15: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

should be given. Mine (M. L. No.- 420/91), lease area- 3.0 ha, Near village-

Rampura, Tehsil- Neem Ka Thana, District- Sikar State- Rajasthan

is submitted under rule 18(1) of Marble Development and

Conservation Rules-2002 for the exiting lease area.

No forests, national park, wild life sanctuary, eco sensitive areas,

CRZ etc in the nearest proximity of the project site.

v. Existing

Infrastructure.

It is a Greenfield project, mines office and rest shelter is already

constructed in mine lease area.

vi. Soil classification Soils of this area are classified as alkaline and saline soils with a

calcareous base.

vii. Climatic data from

secondary sources.

Meteorological data table of Jaipur district is enclosed.

Viii. Social Infrastructure

available.

Communication: Post office/ telephone facilities are accessible for

almost all surrounding villages of project site in study area.

Educational Facilities: Primary schools are available at all villages.

For higher education various colleges are there in District.

Nearest Hospital: Nearest Primary Health Centre (PHC) is

available at Hasampur- 4.30 Kms towards SW & Government

Hospital is available at Neem Ka Thana- 26.02 Kms towards SW.

5. Planning Brief

i. Planning Concept

(type of industries,

transportation etc)

Town and Planning/

Development

authority

Classification.

It is an opencast mining project. The ML area is well connected

with the roads and highways. The mineral will be transported by

means of trucks and sold out in the local market.

Total Reserve

Total Mineral Reserve Code Reserve

A. Mineral Reserve Marble

1.Proved Mineral Reserve

2.Probable Mineral Reserve

111

121

6,00,900 Tonnes

6,95,760 Tonnes

B. Remaining Mineral Reserve : Marble

1.Feasibility Mineral Resources

2.Pre-Feasibility Mineral Resources

3.Inferred Mineral Resources

211

222

333

Lease Barrier + locked

in UPL

66,780 Tonnes

2,31,920 Tonnes

4,63,840 Tonnes

ii. Population

Projection

There will not be any significant population influx. The operational

manpower requirement of the mine will be 32 Personnel (Skilled

Labour- 6, Semi- Skilled Labour- 6, Unskilled Labour- 20). Man

power will be sourced from the nearby villages.

Page 16: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

iii. Land use planning

(breakup along with

green belt etc).

At the end of life of mine, total excavated area will be 2.70 ha.,

which will be left over for water reservoir which would have a

positive impact by recharging the ground water table.As the

continuity of mineral may be goes in depth beyond the present

reserves limit. Thus at this stage reclamation is not proposed. The

scheme of reclamation will be provided at proper time. Presently

the excavated land is proposed to use as water reservoir, which

would have a positive impact by recharging the ground water table.

Total mining area is 3.0 ha. Landuse planning is given below:

Part-(A) LAND: STAGE WISE LAND USE AND RECLAMATION AREA (Ha.)

S. No. Land use Category Present

(ha)

5th

Year

(ha)

End of life of mine

(ha)

1 Top Soil Dump - 0.03 -

2 Waste Dump 0.02 0.06* -

3 Excavation (Voids Only) 1.90 2.30 2.70

4 Road 0.05 0.05 -

5 Built Up Area - 0.01 -

6 Township Area - - -

7 Afforestation 0.01 0.15 0.30**

8 Reclamation (Backfilled) - - -

9 Mineral Storage - - -

10 Processing (Crushing) - - -

11 Undisturbed Area 1.02 0.40 -

Total 3.0 3.0 3.0

*Waste will be dumped within the ML area, in an earmarked area of 0.06 hectare and outside the

lease area on a common dump site located in nearby lease area.

** It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33% of the total lease area.

120 trees will be planted in 0.30 ha. land along the barrier of 7.5 m along the boundary of mine

lease and all around haul roads and rest 280 trees will be planted in 0.70 ha. Gram Panchyat land

after getting due permission.

Post Mining Plan (Conceptual) Land Pattern of ML Area (Ha.) Part-(B) POST MINING LAND USE OF CORE ZONE WITH ENVIRONMENT MANAGEMENT

S.

No.

Description Land Use (in Ha.)

Plantation Water

Body

Public

Use

Undisturbed Total

1 Top Soil Dump - - - - -

2 Waste Dump - - - - -

3 (a) Excavation

(Voids)

- 2.70 - - 2.70

(b) Excavation

(Backfilled)

- - - - -

4 Road - - - - -

Page 17: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

5 Built Up Area - - - - -

6 Township Area - - - - -

7 Afforestation 0.30 - - - 0.30

8 Mineral Storage - - - - -

9 Undisturbed Area - - - - -

Total 0.30 2.70 - - 3.0

Part-(C) REQUIREMENTS FOR PLANTS FOR AFFORESTATION AND RECLAMATION

Year Un-worked Area Waste Dump

(Outside)

Inside Dump

(Reclaimed Area)

Top Soil

Dumps

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Existing - - - - - - - - - -

I 0.06 24 - - - - - - 0.06 24

II 0.06 24 - - - - - - 0.06 24

III 0.06 24 - - - - - - 0.06 24

IV 0.06 24 - - - - - - 0.06 24

V 0.06 24 - - - - - - 0.06 24

VIth Year

Onwards

0.70 280 - - - - - - 0.70 280

Total 1.0 400 - - - - - - 1.0 400

Note: It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33% of the total lease

area. 120 trees will be planted in 0.30 ha. land along the barrier of 7.5 m along the boundary of

mine lease and all around haul roads and rest 280 trees will be planted in 0.70 ha. Gram

Panchyat land after getting due permission. Certain Species like Khejri, Ker, Babool, Neem,

Mango & other fruit bearing trees which are more suitable to local soil are proposed to be

planted.

iv. Assessment of

Infrastructure

Demand (Physical &

Social).

The lessee is committed to the social upliftment of the area by

implementing need based ESR activities. Emphasis will be given to

education, health and employment generation.

v. Amenities/ Facilities. Mines office and rest shelter is already constructed in mine lease

area. Water Requirement is being fulfilled by a nearby well present

outside the ML area. Toilet is already constructed for mine workers.

6. Proposed Infrastructure

i. Industrial Area

(Processing Area)

The proposed project does not involve any processing.

ii. Residential Area

(Non Processing

Area)

Local people will be employed, no residential area/ housing is

proposed.

Page 18: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

iii. Green Belt It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33%

of the total lease area. 120 trees will be planted in 0.30 ha. land

along the barrier of 7.5 m along the boundary of mine lease and all

around haul roads and rest 280 trees will be planted in 0.70 ha.

Gram Panchyat land after getting due permission. Certain Species

like Khejri, Ker, Babool, Neem, Mango & other fruit bearing trees

which are more suitable to local soil are proposed to be planted.

During first five years about 120 saplings of local varieties at a rate

of 24 saplings/0.06 ha at a spacing of 5.0 m×5.0 m will be planted

along the barrier of 7.5 m along the boundary of mine lease and all

around haul roads. Native species shall be preferred in green belt

development plan.

All safeguards for growing trees will be taken care and if any lost

would be replaced. The rate of survival is expected 83%. The

plantation program for the first five years is given below:

GREEN BELT DEVELOPMENT PROGRAMME FOR FIRST FIVE YEARS

Year No. of saplings Area (ha) Replacement Proposed Species

I 24 0.06 4 Khejri, Ker, Babool,

Neem, Mango & other

fruit bearing trees II 24 0.06 4

III 24 0.06 4

IV 24 0.06 4

V 24 0.06 4

Total 120 0.30 20

Ecology: Stage wise Cumulative Plantation REQUIREMENTS FOR PLANTS FOR AFFORESTATION AND RECLAMATION

Year Un-worked Area Waste Dump

(Outside)

Inside Dump

(Reclaimed Area)

Top Soil

Dumps

Total

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Area

(Ha.)

No. of

Trees

Existing - - - - - - - - - -

I 0.06 24 - - - - - - 0.06 24

II 0.06 24 - - - - - - 0.06 24

III 0.06 24 - - - - - - 0.06 24

IV 0.06 24 - - - - - - 0.06 24

V 0.06 24 - - - - - - 0.06 24

VIth Year

Onwards

0.70 280 - - - - - - 0.70 280

Total 1.0 400 - - - - - - 1.0 400

Note: It is proposed to plant total 400 trees in 1.0 Hectare land i.e. 33.33% of the total lease

area. 120 trees will be planted in 0.30 ha. land along the barrier of 7.5 m along the boundary of

mine lease and all around haul roads and rest 280 trees will be planted in 0.70 ha. Gram

Panchyat land after getting due permission. Certain Species like Khejri, Ker, Babool, Neem,

Page 19: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Mango & other fruit bearing trees which are more suitable to local soil are proposed to be

planted.

Post Plantation Care:

The post plantation care will be an important aspect to be taken care of for better survival and

growth rate of plantation. The following care will be taken:

Stone fencing will be provided at the plantation site. Fencing will help in preventing cattle

from entering in to such area and will protect unauthorized entry of outside person and from

fire. Due care will be taken to protect plantation as well as guard to be appointed for

supervision.

During dry weather, water will be sprinkled over plantation using pipe line connected to bore

well.

Initially fertilizer will be given to the pits before and after plantation. Thereafter, manuring

will be continued on reduced scale till the plant attains growth of 2 to 3 m height. Provision of

utilizing bio-manure will also be made within the lease area.

Protection from pest like white ant etc will be done during the plantation and in the proposed

pit 10gms of BSC powder will be given before scheme plantation. After a few months liquid

pesticide mixed with 100 time water will be spread near the scheme planted sapling.

Man power will be engaged in mulching the soil frequently along with removal of weeds.

All safeguards for growing trees will be taken care and if any lost would be replaced. The rate

of survival is expected 83%.

iv. Social Infrastructure The project proponent is committed to improve the social

infrastructure of this area by well planned ESR activities. The ESR

will give much emphasis on need based improvement of health

facilities/ services, development of educational facilities

/infrastructure, employment generation etc. And overall social

development with a view to upliftment of the area.

ESR Activities

S. No. Particulars Expenditure

(in Rs.)

1. Providing Study Materials (books, school bags, stationary

etc) and Uniform Kit to economically backward & girl

students in the village school.

10,000/-

2. Construction of separate toilets for boys and girls in the

village school.

35,000/-

3. Providing clean drinking water facility in the village school. 10,000/-

4. To arrange eye check up camps for villagers. 20,000/-

Total 75,000/-

Proponent proposed to spent Rs. 75,000 per year during life of mine

v. Connectivity (Traffic

and Rail /Metro/

Water ways etc)

The ML area is well connected with the following:-

Nearest Roadways:

NH- 8- 18.82 Kms towards NE

SH- 37B- 2.53 Kms towards SW

Page 20: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

Nearest Railway Station:

Dabla Railway Station- 13.31Kms towards NNW

Jhilo Railway Station- 15.95 Kms towards WNW

Nearest Airport:

Jaipur International Airport- 110.22 Kms towards SSW

vi. Drinking Water

Management (Source

water)

Water will be required for dust suppression, water sprinkling on

haulage roads, domestic purpose, plantation and during marble

cutting with diamond wire saw.

Total Water Demand- 2.0 KLD

Drinking & Domestic Usage- 0.75 KLD

Dust Suppression (water sprinkling on haulage roads)- 0.25 KLD

During marble cutting with diamond wire saw- 0.5 KLD

Plantation- 0.5 KLD

Source:

Water will be sourced from the bore well outside the ML area.

Drinking water will be stored in a container and used for drinking

purpose. The water used during marble cutting with diamond wire

saw will be collected in a settling tank and will be reused. Rain

water collected in the mine pits will also be utilized for plantation

and dust suppression.

WATER BALANCE

*The water used during marble cutting with diamond wire saw will be collected in a settling tank

and will be reused for the same purpose.

vii. Sewerage System Domestic waste water will be channelized into septic tank followed

by soak pit.

viii. Industrial Waste

Management

Not applicable

25% loss

Domestic Use

0.75 KLD

Dust Suppression

0.25 KLD

Plantation

0.5 KLD

To Septic Tank

followed by Soak

Pit

1.5 KLD

Marble Cutting

0.5 KLD

Settling

Tank*

Total Water Requirement

2.0 KLD

Page 21: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

ix. Solid Waste

Management Solid Waste:

Top Soil Top soil is observed on surface in thin layer. It is proposed to scrape

the soil and stacked separately which will be used for plantation.

Overburden

The waste will be weathered marble and marble having foreign

intrusions and soil. The generation of waste during first five years

will be as followed:

Year Waste (in tonne)

2014-2015 -

2015-2016 44350

2016-2017 51900

2017-2018 23580

2018-2019 37180

Total 157010

About 1,57,010 tonnes of waste will be generated during next five

years. Waste will be dumped outside the lease area on common

dump sites located in nearby lease area and Some waste will be

lifted by local habitants and rest waste will be dumped within the

ML area, in an earmarked area of 0.06 hectare for 5.0 m height. The

waste dump is proposed to stabilize by retaining wall of rubble

stones. Stone wall is proposed of 1.0 m height and 2.0 m width

towards lower altitude side which will prevent the spreading of

waste. Further, a garland drain is proposed towards lower side of the

dumps to check the wash off from the dumps/ to check the silt

during monsoon. Plantation is also proposed over the matured

dumps for stabilization.

x. Power Requirement

& Supply / Source

Power is required for Jack hammers, Diamond Wire Saw and

illumination in mines office. Apart from this one water pump is

available near mine lease area for mine dewatering in post monsoon.

Power requirement will be met from 33/ 11KV supply of JVVNL is

available in Rampura.

Fuel is required for the operation of tractor mounted compressor,

truck/ tipper, which will be taken care by the contractor.

7. Rehabilitation and Resettlement (R&R) Plan

i. Policy to be adopted

(Central/ State) in

respect of the project

affected persons

including home

ousters, land ousters

and landless laborers

The proposed mining project does not require any Rehabilitation

and Resettlement.

Page 22: PRE-FEASIBILITY REPORT Contents Details 1. Executive …environmentclearance.nic.in/writereaddata/Online/TOR/24_Jun_2016... · PRE-FEASIBILITY REPORT ... Rajasthan has the largest

M/s Continental Minerals Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd

Authorized signatory EIA Consultant

Contents Details

(a brief outline to be

given).

8. Project Schedule & Cost Estimates

i. Likely date of start of

construction and

likely date of

completion (Time

schedule for the

project to be given).

No major construction activities are required except a mines office

and rest shelter which is already constructed.

ii. Estimated project

cost along with

analysis in terms of

economic viability of

the project.

Total cost of the project is Rs. 25 Lacs.

9. Analysis of proposal (Final Recommendations)

i. Financial and social

benefits with special

emphasis on the

benefit to the local

people including

tribal population, if

any, in the area.

The mining operations will generate employment directly to 32

Personnel (Skilled Labour- 6, Semi- Skilled Labour- 6, Unskilled

Labour- 20) and indirectly to 30-40 personnel. The quality and

living standards of the people and communities in this area will be

enhanced due to the mining operations. No tribal population is

exists near the ML area and in its nearest vicinity.

The proposed project will help in meeting the demand of marble

in the region as well as country.

There will be positive impact of project by getting opportunity

for employment and development of this area.

Better socio economic conditions in the surrounding villages.

Improvement of local and regional economy.

Improvement of standard of living condition of the local people.

Due to frequent failure of the monsoon in the region, area is

facing acute water crisis. There for mining pit will be converted

into a small water reservoir, which shall be a gainful post mining

scenario to the society.

Corporate social responsibility activities will be further strengthened

for the development of nearby villages. Details of which are given

above at Point No. - 6 (iv).

*****