Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata...

18
PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH BULK DRUGS AND DRUG INTERMEDIATES MANUFACTURING UNIT at Sy No. 290 & Parts, Dondapadu Village, Chinthalapalem Mandal , Suryapet District, Telangana State By SRR LABORATORIES Plot No.l05, Lakshmi Nivas, Czech colony, Opp: FCI Godown, Sanath Nagar, Hyderabad January, 2019

Transcript of Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata...

Page 1: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE - FEASIBILITY REPORT

For

PROPOSED TO ESTABLISH BULK DRUGS AND DRUG

INTERMEDIATES MANUFACTURING UNIT

at

Sy No. 290 & Parts, Dondapadu Village,

Chinthalapalem Mandal , Suryapet District,

Telangana State

By

SRR LABORATORIES

Plot No.l05, Lakshmi Nivas, Czech colony, Opp: FCI Godown,

Sanath Nagar, Hyderabad

January, 2019

Page 2: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Contents

S. No. Description Page no.

1.0 Executive Summary 1

2.0 Introduction of The Proposed Project 2

2.1 Project Proponent 2

2.2 Brief description of nature of the project. 2

2.3 Need for the project and its importance to the country and

or region 2 -3

2.4 Demand-Supply Gap. 3 - 4

2.5 Employment Generation(Direct and Indirect) due to the project

4

3.0 Project description 4

3.1 Product and Production Capacity 7

3.2 Raw materials required and Quantities 8

3.3 Manufacturing Process 8

3.4 Resource – Utilize and Recycling 9

3.4.1 Water 9

3.4.2 Power Requirement 10

3.4.3 Fuel Requirement 10

3.5 Quantity of wastes to be generated 10

3.5.1 Waste Water Generation and utilization 10

3.5.2 Solid waste generation and Disposal 11

3.6 Schematic representations of the feasibility drawing which give information of EIA purpose.

11

4.0 Site Analysis 12

4.1 Connectivity 12

4.2 Land Form, Land use and Land ownership. 12

4.3 Existing Infrastructure 12

4.4 Soil classification 12

4.5 Climatic data from secondary sources. 12

4.6 Social Infrastructure available. 12

5.0 Planning brief 13

6.0 Proposed infrastructure 13

6.1 Industrial Area 13

6.2 Residential Area 13

6.3 Green Belt: 13

6.4 Social Infrastructure 13

6.5 Water management 14

6.6 Sewerage System 14

6.7 Industrial Waste Management 14

7.0 Rehabilitation and Resettlement (R&R) Plan 14

Page 3: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

S. No. Description Page no.

8.0 Project Schedule and Cost estimates 14

9.0 Analysis of project 14

LIST OF TABLES

Table No Description Page no.

2.1 Details of Proposed Employment for Proposed Project. 4

3.1 Proposed Products and Quantities 7 - 8

3.2 Water Requirement Details 9

3.3 Wastewater generation and Treatment Method 10

3.4 Solid and hazardous waste generation and Disposal 11

LIST OF FIGURES

Figure No Description Page no.

1.1 Location Map 5

1.2 Google Earth Map Showing SRR Laboratories 6

LIST OF FLOW CHART

Flow Chart No

Description Page no.

3.1 Generalized Flow Chart for Bulk Drug Manufacturing 9

Page 4: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 1

1.0 EXECUTIVE SUMMARY

SRR Laboratories is proposing to establish Bulk drug and intermediates

manufacturing unit at Dondapadu Village.

S. No Parameter Description

1 Project Location

SRR Laboratories

Sy No. 290 & Parts, Dondapadu Village

Chinthalapalem Mandal, Suryapet District,

Telangana State

2 Category of Project as per EIA Notification & Amendments

5(f) “A”

3 Project cost 15 Crores

4 Plot area 8.00 Acres (32368 Sq.m)

5 Proposed Products Proposed Products List is mentioned in section

3.1

6 Resources

7 (I)Electricity

Requirement 2100 KVA

Source of electricity Telangana State Power Distribution Company

Limited (TSPDCL)

D. G. Sets 750 KVA

8 (II)Water consumption 194 KLD

Source of water Ground Water through Bore Well

Waste water generation 82.8 KLD

9 (III)Boiler 3.0 TPH Coal fired Boiler & 4.0 TPH Coal fired Boiler

10 (IV)Fuel Coal Requirement – 28 MT /Day for proposed boilers

11 Mode of disposal Zero Liquid Discharge System

12 Solid waste generation Mentioned in Para 3.5.2 of report

13 Nearest Highway National Highway 9 – 16 kms (ENE) (Hyderabad – Vijayawada Road ) Dondapadu –Muktyala Road – 410 mtrs (ENE)

14 Nearest Railway Station Motumari Railway Station – 33.00 kms (ENE)

15 Nearest Airport Vijayawada Airport – 87.0 kms (ESE)

Page 5: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 2

2.0 INTRODUCTION OF THE PROJECT

The objective of this pre- feasibility study is to provide information for the proposed

Bulk Drugs and Drug Intermediates Manufacturing unit of SRR Laboratories located

at Sy No. 290 & Parts, Dondapadu Village, Chinthalapalem Mandal, Suryapet

District, Telangana State.

2.1 Project Proponents

A. Koti Reddy Partner, studied B.Sc and having 30 years experience in Chemical Industry.

R. Venkata Manikanta, Partner, studied B.Tech Mechanical Engineering and having experience in Maintenance Department.

Dr. A. Kavitha Partner, studied MBBS and having 10 years of experience.

K. Rameshbabu Partner, studied B.Sc and having 35 years experience in various Industries.

R. Raghavendra Partner, studied B.Tech Electrical Engineering and having 9 years experience in Software Company.

2.2 Brief description of nature of the project.

SRR Laboratories is proposing to manufacture Bulk Drugs and Drug Intermediates

manufacturing unit located at Sy No. 290 & Parts, Dondapadu Village,

Chinthalapalem Mandal, Suryapet District, Telangana State .

2.3 Need for the project and its importance to the country and or region

SRR Laboratories is a Greenfield project intended to start a manufacturing unit of

Bulk Drugs and Drug Intermediates at Sy No. 290 & Parts, Dondapadu Village,

Chinthalapalem Mandal, Suryapet District, Telangana State.

Availability of the well-connected road and railway network for easy

transportation of the construction equipments and materials, Raw materials

and finished products.

Easy availability of skilled and unskilled labor for construction of Plant and its

operation.

The Indian pharmaceutical industry currently tops the chart amongst India's science-

based industries with wide ranging capabilities in the complex field of drug

Page 6: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 3

manufacture and technology. A highly organized sector, the Indian pharmaceutical

industry is estimated to be worth $ 4.5 billion, growing at about 8 to 9 percent

annually. It ranks very high amongst all the third world countries, in terms of

technology, quality and the vast range of medicines that are manufactured. It ranges

from simple headache pills to sophisticated antibiotics and complex cardiac

compounds; almost every type of medicine is now made in the Indian

pharmaceutical industry.

The Indian pharmaceutical sector is highly fragmented with more than 20,000

registered units. It has expanded drastically in the last two decades. The

Pharmaceutical and Chemical industry in India is an extremely fragmented market

with severe price competition and government price control The Pharmaceutical

industry in India meets around 70% of the country's demand for bulk drugs, drug

intermediates, pharmaceutical formulations, chemicals, tablets, capsules, orals, and

injectibles. There are approximately 250 large units and about 8000 Small Scale

Units, which form the core of the pharmaceutical industry in India (including 5 Central

Public Sector Units).

The Indian pharma industry, which is expected to grow over 16 per cent per annum

between 2017 and 2020, will outperform the global pharma industry, which is set to

grow at an annual rate of 5 per cent between the same periods. The market is

expected to grow to US$ 55 billion by 2020, thereby emerging as the sixth largest

pharmaceutical market globally by absolute size, as stated Indian Ambassador to the

US. Branded generics dominate the pharmaceuticals market, constituting nearly 80

per cent of the market share (in terms of revenues).

India has also maintained its lead over China in pharmaceutical exports with a year-

on-year growth of 11.44 per cent to US$ 12.91 billion in FY 2016-17, according to

data from the Ministry of Commerce and Industry. Imports of pharmaceutical

products rose marginally by 0.80 per cent year-on-year to US$ 1,641.15 million.

Overall drug approvals given by the US Food and Drug Administration (USFDA) to

Indian companies have nearly doubled to 201 in FY 2016-17 from 109 in FY 2015-

16. The country accounts for around 30 per cent (by volume) and about 10 per cent

(value) in the US$ 70-80 billion US generics market.

Page 7: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 4

2.4 Demand-Supply Gap.

There is a quite considerable gap between supply and demand for, fine chemicals,

bulk drugs and intermediates. Very few players are in the market who can offer

continuous supply. The company wants to bridge this gap between demand and

supply by expanding the production capacity and thereby, making good business.

Company's marketing edge comes from its direct and close contact with the

customers. Their products are major strength of their customers. Each stage of their

product is been monitored /checked for their quality to ensure quality product

reaches their customer. They plan to launch new products every year to satisfy the

need of their customers as per the market demand.

2.5 Employment Generation (Direct and Indirect) due to the project

Approximate employment generation due to proposed unit is 90. Apart from this

there will be significant non estimated employment generation at the supplier firms

and service industry providing services to the company. Company shall be giving

preference to people from economically weaker sections for employment in various

semi-skilled/unskilled jobs thereby contributing to their upliftment.

Table 2.1: Details of Proposed Employment for Project

Sl. No. Manpower Total No.

1 Un-Skilled 60

2 Skilled 20

3 Managerial &Supervisory 10

3.0 Project Description

SRR Laboratories is proposing to Manufacture Bulk Drugs and Drug Intermediates

with production capacity of 129 TPM

The Location map is shown at Figure - 3.1 and Google earth map showing SRR

Laboratories plant is shown at Figure - 3.2.

The site central coordinates are

Latitude: 16°49'31.74"N

Longitude: 80° 2'56.67"E

The project site does not offer any negative impact on the local area, but rather has

Page 8: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 5

a positive impact on socio economic conditions of the habitants around it because of

employment to locals.

The SRR Laboratories is 16.0 kms away from National Highway No - 9 and 33 kms

from Motumari Railway Station.

Page 9: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 5

FIGURE 1.1: LOCATION MAP

SRR Laboratories

Sy No. 290 & Parts, Dondapadu Village

Chinthalapalem Mandal, Suryapet

District, Telangana State

Page 10: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

Pre Feasibility Report

SRR Laboratories Page 6

FIGURE 1.2: GOOGLE EARTH MAP SHOWING SRR LABORATORIES

Page 11: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 7

3.1 Product and Production Capacity

SRR Laboratories to produce below mention products with Manufacturing Capacity

of 129 TPM and the list of products are shown in Table 3.1.

Table 3.1: Proposed Product and Quantity

S No

Product name

Quantity

in

Tonne

/Month

CAS no Therapeutic

category

1 Carvedilol 10 72956-09-3 Antihypertensive

2 Cyano diol hydrochloride 5 717133-25-0 Drug intermediate

3 Dabigatran 5 211915-06-9 Anticoagulant

4 Fexofenadine hydrochloride 10 153439-40-8 Anti allergic

5 Fluconazole 10 88386-73-4 Antifungal

6 Folic acid 20 59-50-3 Hematinic (Vit-B)

7 Itraconazole 10 84625-61-6 Antifungal

8 Ketoconazole 10 65277-42-1 Antifungal

9 Levocetirizine dihydrochloride 5 130018-77-8 Antihistamine

10 Linagliptin 5 668270-12-0 Anti diabetic

11 Meropenem 5 119478-56-7 Antibacterial

12 Montelukast sodium 2 151767-02-1 Anti asthmatic

13 Rosuvastatin calcium 2 147098-20-2 Anti lipemic agent

14 Sitagliptin Phosphate Monohydrate 5 654671-77-9 Anti Diabetic

15 Teneligliptin 5 760937-92-6 Anti Diabetic

16 Tri butyl tin chloride 5 1461-22-9 Organic Reagent

17 Valacyclovir Hydrochloride Monohydrate

10 124832-27-5 Anti Viral

18 Vildagliptin 5 274901-16-5 Anti diabetic

Total 129

3.2 Raw materials required and Quantities

All the raw materials required for manufacturing of above products will be sourced

from local market. The products wise required raw materials and quantities are

enclosed in Additional information.

Page 12: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 8

3.3 Manufacturing Process

The manufacturing process of bulk drugs consists of chemical synthesis extending

to stages of processing involving different type of chemical reactions. The

generalized Flow chart for bulk drug manufacturing is shown in Flow chart 3.1.

Flow Chart 3.1: Generalized Flow Chart for Bulk Drug Manufacturing

3.4 Resource – Utilize & Recycling

3.4.1 Water

Water requirement of the project for domestic and industrial activity during operation

phase will be 194 KLD. The water requirement will be met through bore well. The

detailed water requirement shown in below Table 3.2

Table 3.2: WATER REQUIREMENT DETAILS

S.No Purpose Water input KLD

1 Process 52

2 Washings 5

3 Boiler make up 42

4 Cooling towers make up 79

5 Scrubbing system 7

Page 13: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 9

S.No Purpose Water input KLD

6 Domestic 4

7 Gardening 5

Total 194

3.4.2 Power Requirement

Power requirement of proposed project will be made available through Telangana

State Power Distribution Company Limited (TSPDCL). The total power requirement

for the unit is 2100 KVA respectively

D.G. sets of 750 KVA is proposed to install to meet the emergency power

requirement of the plant.

3.4.3 Fuel Requirement

The company proposed to install 3.0 TPH Coal fired Boiler & 4.0 TPH Coal fired

Boiler and total Coal requirement will be around 28 TPD and it will be procured

from local sources.

3.5 Quantity of wastes to be generated

3.5.1 Waste Water Generation and utilization

Total effluent generated in the project is 54.50 KLD. The treated water will be reused

for plant operations.

The HTDS waste water from Process after neutralization taken for treatment in

stripper followed by MEE and ATFD. LTDS waste water including domestic sewage,

floor Washes, Utilities waste water taken along with Vapour Condensate from MEE &

ATFD for Biological Effluent Treatment plant. Treated effluent from ETP sent to RO

and RO permeate water is recycled and RO rejects are sent to MEE followed by

ATFD for evaporation. Evaporation salts collected and sent to TSDF. MEE & ATFD

vapour condensate reused along with RO permeate.

Table 3.3: Wastewater generation and Treatment Method

S. No

Purpose HTDS KLD

LTDS KLD

Total Effluent in

KLD

Disposal Method

1 Process 30 25 55

ZLD System 2 Washings 0 5 5

3 Boiler Blow down 0 6 6

Page 14: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 10

S. No

Purpose HTDS KLD

LTDS KLD

Total Effluent in

KLD

Disposal Method

4 Cooling towers blow down

0 11 11

5 Scrubbing system 2 0 2

6 Domestic 0 3.8 3.8

Total 32 50.8 82.8

3.5.2 Solid / Hazardous waste generation and Disposal

The types of Solid and Hazardous wastes generated from the project, method of

disposal is shown in below table 3.4.

Table 3.4: Solid / Hazardous waste generation and Disposal

S. No

Name of the Hazardous Waste

Quantity Kg/Day

Disposal Method

1 Organic Solid Waste 1657

Sent to Cement Industries

2 Spent Carbon 145

3 Solvent distillation residue

1091

4 Organic Evaporate liquid from MEE stripper

640

5 Mixed Solvents 3945 Sent to paint industries

6 ETP Sludge 1000 Sent to TSDF

7 Inorganic solid waste 359

8 MEE Salts 3151

9 Used Oils

500 Ltrs/Annum

SPCB Authorized Agencies for Reprocessing /Recycling

10 Detoxified Containers

500 No’s/Month

After Detoxification sent back to suppliers/sent to outside Parties

11 Used Lead Acid Batteries 2 No’s/Year

Send back to suppliers for buyback of New Batteries

Solid Waste Details

12 Fly ash from boiler

7700 Kg/Day

Sent to Brick Manufacturers

3.6 Schematic representations of the feasibility drawing which give

information of EIA purpose.

The applicability of the S.O 1533 for the proposed project was explored by

considering different possibilities & provision made in the said notification.

Considering the products & project location of the proposed project it is noticed that

Page 15: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 11

the proposed project falls under Category 5 (f) “A” of the Schedule-I of EIA

Notification SO 1533.

As per the provision of the SO 1533, it is necessary to get Environmental Clearance

by applying to MoEF&CC along with the Environmental Impacts Assessment Study

Report for the proposed project prior to commissioning of the project activities.

Therefore the EIA is required to conduct to comply with provisions of SO 1533 made

for Category 5(f) “A” of schedule –I of the notification.

4.0. Site Analysis

4.1 Connectivity

SRR Laboratories located at Sy No. 290 & Parts, Dondapadu Village

Chinthalapalem Mandal, Suryapet District, Telangana State

The nearest habitation from the site is Dondapadu Village at a distance of 1.30

kms (W).

The nearest railway station is Motumuri Railway Station at a distance of 33 kms

(ENE) from the site.

The nearest airport is Vijayawada Airport at a distance of 87 kms

The Nearest National Highway is NH 9 – 16 kms

4.2 Land form, Land use and Land ownership.

The land use of the 8.00 Acres (32368 Sq.m) will be permanently changed to

industrial purpose.

4.3 Existing Infrastructure.

The Proposed project is a Greenfield project which is 16 kms away from NH-9 and

Mandal head quarter Chinthalapalem is 10 kms (SW) from the project site.

4.4 Soil classification

The predominant soils in the district are Red soils, Black soils, Alkaline soils and

Alluvium.

4.5 Climatic data from secondary sources.

Temperature Maximum: 46.5 oC

Minimum: 12 oC

Page 16: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 12

Normal annual rainfall : 750.7 mm

(Source: IMD Climatological Normals 1981-2010)

4.6 Social Infrastructure available.

Well developed social infrastructure facilities are available at nearby Habitations.

5.0 Planning Brief

Proposed plant activities will be started after getting statutory clearance form related

authorities. The project will be completed within two years.

Further proposed project activities will take care of all the rules and regulation of

statutory authority and provide the control measure and devices to achieve the

standard norms

6.0 Proposed Infrastructure

6.1 Industrial Area

The infrastructure and other facilities are already well developed in Chinthalapalem

which is a Mandal head quarter.

6.2 Residential Area

The employees who will work in the industry are from nearby villages and hence no

proposal for residential area for employees.

6.3 Green Belt:

Approximately 34.27 % of Green Belt will develop and it will be maintained.

6.4 Social Infrastructure:

Facilities like road and communication are good; Banks, ATM's and medical facilities

are also adequate.

Amenities:

Education- schools including middle, secondary and higher secondary schools,

social welfare hostels.

Medical and Health- Community Health Centre & Primary Health center are

available in Chinthalapalem which is 10 kms SW of proposed project site.

Page 17: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 13

Power and water- All the villages are electrified and drinking water facilities are

extended to all villages.

Rail and Road- The project site is very well connected by road through National

Highway No. 9 and nearest railway station is Motumari.

6.5 Water management

Water requirement will be met through ground water.

6.6 Sewerage System:

There will be no discharge of industrial effluent as company proposing Zero Liquid

Discharge (ZLD) system. The treated effluent will be reused.

6.7 Industrial Waste Management:

Due to proposed Proposal, the effluent from cooling and Plant/Equipment washing

will be generated and treated in the well designed Effluent Treatment Plant. The

treated effluent will be reused.

7.0 Rehabilitation and Resettlement (R & R) Plan

Rehabilitation & Resettlement (R&R) plan is not applicable to this proposed project.

8.0 Project Schedule & Cost Estimates

Proposed project activities will be started after getting statutory clearance form

related authorities. The project will be completed within two years.

Proposed activity will provide benefits to the local people in terms of financial and

social welfare.

The project cost for proposed Project is 15 Crores will be used for constructing

additional building, Equipments & misc.

TABLE 8.1: PROJECT COST

S. No Particulars Rs. Crores

1 Land 0.65

2 Civil Works 4.0

3 Plant & Machinery 9.0

4 Miscellaneous 1.35

Total 15

9.0 Analysis of proposal (Final Recommendations)

Local people will get direct financial benefit by way of employment.

Page 18: Pre Feasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in › writereaddata › Online › TOR › 07_Jan_2… · PRE - FEASIBILITY REPORT For PROPOSED TO ESTABLISH

PRE FEASIBILITY REPORT

SRR Laboratories Page 14

Local people will get some contracts of supply and services to get indirect

income.

Company will contribute in improving education and health facilities in nearby

area.