PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF...
Transcript of PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF...
![Page 1: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/1.jpg)
PRE-FEASIBILITY REPORT
FOR
PROPOSED EXPANSION IN PRODUCTION CAPACITY OF
CARBON DI SULPHIDE (CS2) AND EXPORT OF STEAM
[Schedule 5 (b) Category “A” as per EIA notification 2006 and its
amendment thereof]
At
Z-7/1, SEZ area, SEZ-1, GIDC Dahej, PCPIR Ta: Vagra, Dist- Bharuch, Gujarat.
Land/Plot Area: 50,000 m2
Production Capacity: Carbon Di Sulphide (CS2): 75,000 to 100,000 TPA
Steam: 65,000 to 85,000 TPA
APPLICANT CONSULTANT
M/S. INDOBAIJIN CHEMICALS PVT LTD ECO CHEM SALES & SERVICES Z-7/1, SEZ area, SEZ-1, GIDC Dahej, PCPIR
Village: Dahej, Ta: Vagra, Dist- Bharuch 392130 Gujarat. E-Mail: [email protected]
Tel No: 02642-277202
Office Floor, Ashoka Pavilion - A New Civil Road, Surat, 395001
NABET/EIA/1720/RA 051 E-mail: [email protected] Tel No. +91 261 2231630
Document No.: 2018_ECSS_EIAI2_1800032 December 2018
![Page 2: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/2.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
2 | P a g e
EXECUTIVE SUMMARY
India is one of the leading manufacturers and suppliers of pesticides intermediates. India has good
engineering & research scientist pool along with long proven expertise of producing quality products.
The proposed project is an expansion project proposed by Indo-Baijin Chemicals Pvt. Ltd. with a total
product capacity of Carbon Di-Sulphide of 100,000 MTPA. Carbon disulfide has been an important
industrial chemical since the late nineteenth century. It is used in a variety of applications like
production of regenerated cellulose (rayon and cellophane) and the manufacture of organic sulfur
compounds including agricultural, pharmaceutical, rubber chemicals and especially as Pesticide
intermediate. The proposed project will be undertaken within the existing premises of Indo-Baijin
Chemicals Pvt. Ltd. located at Plot No: Z-7/1, SEZ area, SEZ-1, Village: Dahej, Tehsil: Vagra, District:
Bharuch, PCPIR, Gujarat.
As per the provision of the SO 1533, the proposed project falls under the item no. 5(b) -“A” and the
project is to be appraised at the MoEFCC, New Delhi. Further, the proposed project is located in the
Notified industrial estate/park (as described in Item 3(b) of notification), Hence Public hearing shall be
exempted (A copy of Gazette notification is attached as Annexure-5)
This pre-feasibility report has been prepared as a part of the ToR application, which includes a brief
introduction of the company, need and justification of the project, manufacturing process description,
required and available resources, proposed Environment Management Systems, existing land-use and
proposed infrastructure, project schedule and cost estimate, and proposed Terms of reference for
conducting the EIA studies.
The industry has engaged Eco Chem Sales & Services (ECSS) as their Environment Consultant to
conduct the EIA studies for obtaining EC for the proposed project. ECSS is a NABET accredited (QCI
approved) Environmental Consultant.
![Page 3: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/3.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
3 | P a g e
1.0 PROJECT BRIEF
PROJECT BRIEF
No. Description Proposed Project Details
1 Name of project &
Address
Indo Baijin Chemicals Pvt Ltd
Plot No: Z-7/1, SEZ area, SEZ-1,
GIDC Dahej, PCPIR, Taluka – Vagra,
Dist: Bharuch,
Gujarat
2 Project Category 5 (b)-A of EIA notification – 2006
3 Project capital cost Existing cost: Rs. 193 Crores Expansion cost: Rs. 100 Crore Total Cost: 293 Crore
4 Products Enhancement of production capacity of Carbon Di-Sulphide
(CS2) from 75,000 MTPA to 100,000 MTPA and steam
export capacity from 65,000 MTPA to 85,000 MTPA
No Product Existing
capacity
(MTPA)
Proposed
Capacity
(MTPA)
Total
Capacity
(MTPA)
1 Carbon Di-
Sulphide
75,000 25,000 100,000
2 Steam Export 65,000 20,000 85,000
5 By-products No By-Product will be generated
6 Resource Requirement
Land 50,000 m2
(No additional land will be required due to proposed
expansion)
Water Source: GIDC water supply
Existing Water Consumption:
Domestic Activities: 50 KLD
Industrial Activities: 700 KLD
Total Water Consumption after Proposed Expansion:
Construction phase: 5-10 KLD
Operation phase:
Total water consumption: 1000 KLD
Domestic Activities: 50 KLD
Industrial Activities: 950 KLD
Existing Proposed Total
Domestic
Activity
50 KLD Nil 50 KLD
Industrial
Activity
700 KLD 250 KLD 950 KLD
Electricity Source: Torrent Energy Ltd
![Page 4: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/4.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
4 | P a g e
Existing Contract Demand - 1900 KVA
Proposed additional Contract Demand – 1250 KVA
Total Contract Demand - 3150 KVA
Fuel Existing:
Natural gas: 97,469.17 SCM/day
Proposed:
Natural Gas: 21,183.3 SCM/day
Total:
Natural gas: 118,652.47 SCM/day
Manpower Existing: 104 Nos.
Proposed additional Manpower:
Construction phase –25 Nos.
Operation phase – 12 nos.
7 Source of Pollution
Waste Water Generation No industrial wastewater is discharged from the existing
unit hence the unit is a zero liquid discharged unit. After
the proposed expansion same shall be achieved.
Existing sewage is treated in STP and treated water is
partly reused gardening and partly send to cooling tower
for evaporation. After the proposed expansion additional
sewage will be treated in existing STP having spare
capacity.
Air Emission Flue stack Emission:
SPM, SO2, NOx
Process stack Emission:
SPM, SO2, NOx
Solid/Hazardous Waste
Generation
Hazardous waste:
Furnace Slag from furnace pipe and reactor cleaning, Used
Spent Oil, Discarded Containers/liners/Barrels
contaminated with Hazardous waste/chemicals,
Evaporation salt, Sludge from Sulfur Filter, , Spent Catalyst
and Molecular sieves, Residue Carbon, Wastage or
residue containing oil, Contaminated Cotton rags or other
cleaning materials
Solid Waste:
STP Sludge
8 Mode of Treatment
Wastewater 1) Due to proposed expansion additional 200 KLD Industrial
effluent will be generated.
![Page 5: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/5.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
5 | P a g e
2) Additional Domestic sewage will be treated in existing
Sewage Treatment Plant (STP) and treated water shall
be reused in gardening and partially fed to combination
cooling tower.
Air One no. of Tail Gas Treatment Unit & heating furnace will
be installed during the proposed expansion as process gas
and one no D.G.Set with 1650 KVA will be installed for
emergency power back up.
Adequate Air pollution control device (i.e Sulphur Recovery
Unit & Tail Gas Treatment Unit) will be provided to achieve
GPCB norms.
Solid Waste Solid/hazardous waste for collection, storage and disposal
will be carried out as per Hazardous Waste Management
Rules 2016.
2.0 INTRODUCTION OF THE PROJECT
2.1 Details of Project Proponent
Indo-Baijin Chemicals Private Limited is a Joint Venture Company of Indofil Industries Limited, India &
Shanghai Baijin Chemicals Group Co. Ltd., China. Proponent is proposing to expand its current
manufacturing plant for producing Carbon Di-sulphide using Natural Gas (NG) as raw material at its
existing plant located at Special Economy Zone (SEZ), Dahej, Gujarat, India.
Indofil Industries Limited is a company from K.K. Modi Group of India an Industrial Conglomerate with
diverse businesses in the Agro Chemicals, Fine Specialty Chemicals, Entertainments, Healthcare etc.
Indofil Industries Limited is uniquely placed both in Agriculture chemical as well as Specialty and
Performance chemical business. In India, Indofil is successful in strategic marketing of insecticides
including IGRs, Fungicides, Bactericides, Herbicides, Acaricides, Surfactants and Plant growth
regulators. Indofil is working for betterment of farmers, operating in Indian Market for more than 4
decades. INDOFIL is an ISO-9001-2000 and ISO 14001 Company and famous for excellence in
product quality. Indofil have stringent safety regime and an ability to handle hazardous chemicals such
as carbon disulphuide.
Shanghai Baijin Chemicals Group Co. Ltd., China was established in 1990. With Carbon Di-sulphide
production as the major business, Baijin group, consistently extending the industrial chain of fine
chemicals, chemical fibers, coke chemicals as well as endeavoring in international trade, technical
export and R&D, is a group company with the largest production scale, the most complete technical
processes and latest technologies. Shanghai Baijin Chemical Group Co., Ltd, has a total asset of 2.6
billion Chinese yuan and 8 subordinates. The company also owns 14 proprietary patents and is
![Page 6: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/6.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
6 | P a g e
applying 2 international patents at present. Successively, 7 carbon disulfide manufacturing plants in
Shanxi, Chongqing, Sichuan, Xinjiang, Anhui, Shandong, and Jiangsu respectively have been
established, with an annual output of 3,50,000 tons.
2.2 Description of Nature of the Project
The company is located at Plot No: Z-7/1, SEZ area, SEZ-1, GIDC Dahej, PCPIR, Taluka-Vagra,
District: Bharuch, Gujarat. The unit is involved in manufacturing of Carbon Di-Sulphide, having granted
capacity of 75,000 MT/Annum and steam export with capacity 65,000 MT/Annum.
The unit has also obtained Environmental Clearance for existing products vide letter No: J-
11011/361/2016-IA II (I), dated: 30/08/2017 (Attached as Annexure-1) & the unit holds
Consolidated Consent having Order no. AWH-64179 dated 02/04/2014, unit has also amended the
CC&A dated 11/12/1018 which is valid up to: 01/04/2019 (Attached as Annexure-2)
2.2.1 Need of Proposed Project
As India is a developing country with increasing population, pesticides‟ and pesticides intermediates‟
demand is increasing day by day. Asia is accounted for about 72% of world production and nearly 75%
of world consumption of carbon disulfide.
Carbon disulfide has been an important industrial chemical since the late nineteenth century. It is used
in a variety of applications like production of regenerated cellulose (rayon and cellophane) and the
manufacture of organic sulfur compounds including agricultural, pharmaceutical, rubber chemicals and
especially as Pesticide intermediate.
China is the dominant global player in this industry, with 49% of global consumption, followed by India
(13%). Both the countries have expanding industries, which account for the majority of carbon disulfide
consumption. The situation is similar in Western Europe, which accounted for 12% of world
consumption in 2010. In total, 98% of the world consumption of carbon disulfide was accounted for
Asia, Europe and America (74.5%, 15.8% and 7.7% of global demand, respectively). The rise of Asia
as the powerhouse where carbon disulfide is consumed (and produced) is closely related to the
changes in the global pattern of the textile, rubber, mining and agricultural chemicals industries, which
have increasingly relocated their manufacturing bases to this region. Hence, the demand of carbon Di-
Sulphide is increasingly gradually.
2.2.2 Demand Supply Gap
As discussed above, the consumption of carbon disulfide is consumed (and produced) is closely related
to the changes in the global pattern of the textile, rubber, mining and agricultural chemicals industries,
which have increasingly relocated their manufacturing bases to this region. The following pie chart
shows world consumption of carbon disulfide in the past few years:
![Page 7: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/7.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
7 | P a g e
Figure 1: world consumption of carbon disulfide
Current Production Capacity in India : 2,42,000 MTPA
Current Demand in India : 2,77,000 MTPA
Current Gap in India : 21,000 MTPA
Indian CS2 consumption is on growing path considering the growing Agro Chemicals, Rayon & Fiber,
Rubber Chemicals & Pharma Intermediate industries. The production of regenerated cellulose (in the
form of rayon fibers, cellophane, sponges and casing) is the dominant industrial application of carbon
disulfide, accounting for 70% of total demand. In the absence of new applications, the health of the
overall carbon disulfide market will depend on sustainable growth in the fibers application, which on a
global scale is expected to rise in the near future. Other important areas where carbon disulfide is
being used are in the production of rubber chemicals (predominantly as vulcanization accelerators)
and agricultural chemicals (as fumigants). With the increasing prices of basic raw materials, the use of
carbon disulfide in the manufacture of mining chemicals (as flotation agents) is gaining in importance
and has the highest forecast growth rate among the different applications.
Available Domestic Market : 2,77,000 PTPA
Average Regular Export by IBJ : 10,000 MTPA
There is export market available and Indobaijin is exporting on regular basis to countries like
Indonesia, Taiwan, Iran, Israel, Maxico, Peru, Korea etc. and export is expected to grow in the coming
years.
Future growth is expected to be most significant in Asia, whereas other regions with significant
demand are expected to stagnate or to grow at only about 1–2% annually over the forecast period.
![Page 8: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/8.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
8 | P a g e
2.2.5 Employment Generation
The proposed expansion project shall generate employment during the construction for local skilled
and semi-skilled workers. Thus no need to provide housing facility to workers. Approx. 25 nos. of
people will get direct employment during construction phase.
During the operation phase, additional 12 nos. of individuals will get direct employment during
operation phase depending on their education background and technical skills.
3.0 PROJECT DESCRIPTION
3.1 Proposed Project & Applicability of EIA
The existing unit of Indo Baijin Chemicals Pvt Ltd is located at Plot No: Z-7/1, SEZ area, SEZ-1, GIDC
Dahej, PCPIR, Taluka-Vagra, District: Bharuch, Gujarat. The unit is now planning to increase its
production capacity from 75,000 MT/Annum to 100,000 MT/Annum.
The applicability of the SO 1533 for the proposed expansion project was explored by considering
different possibilities & provisions made in the said EIA notification, SO 1533 amended on 14th
September 2006. Considering the products, the proposed expansion project falls under Category 5 (b)
- “A”.
3.2.3 Site Selection Criteria:
The land for the proposed expansion project is already in the possession of Indo Baijin as the
proposed project is an expansion project. All the infrastructure facilities are available with the
existing unit of Indo Baijin.
The project site is in Special Economic Zone (SEZ), which has all the facility such as RCC road,
water supply, effluent disposal line, power supply from Torrent Energy Ltd, Gas supply, Fire and
Safety Services.
The existing project site is well connected by road to National Highway No. 8.
Easy availability of infrastructure facilities.
No prime agricultural land / forest land needed to be converted for industrial use.
There is enough extra land to raise required green belt / green cover.
Area where proposed site is to be located has no history of natural calamities like floods, cloud
burst etc.
Proximity to raw material suppliers.
The human resource required for the proposed project will be easily available.
In addition to the above, the following factors within the study area have also been considered:
There is no National Park or Wild Life Sanctuary.
There are no metropolitan cities.
There are no ecologically sensitive areas.
![Page 9: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/9.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
9 | P a g e
3.2 Project Location
The company is located at Dahej SEZ in Vagra Taluka in western part of the Bharuch district, Gujarat.
It is well connected with National Highway (NH-8). Road and Railway both are having the connectivity
to New Delhi, the National Capital and Mumbai, the commercial Capital of India. SEZ is a part of Dahej
Petroleum, Chemicals and Petrochemicals Investment Region (PCPIR) and is within Delhi-Mumbai
Investment Corridor (DMIC).
Connectivity:
Road: SEZ is on 4 lane State Highway connecting at Bharuch (40 km) and National Highway No. 8
Rail: 40 km from Bharuch, Main Rail Head connecting Mumbai – Delhi.
Port: Gujarat Chemical Port Terminal Company Limited for chemical cargo and Adani-Petro LNG for
solid bulk cargo handling.
Airport: Baroda-150 km and Surat-120 km (Daily flights to Mumbai & Delhi).
Four corners Latitudes and Longitudes of the proposed project are as under:
Project Co-ordinates
Corner Latitude Longitude
A 21°42'35.74"N 72°37‟06.78"E
B 21°42'36.02"N 72°37'10.94"E
C 21°42'27.10"N 72°37'11.04"E
D 21°42'30.92"N 72°37'10.30"E
![Page 10: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/10.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
10 | P a g e
Figure 2: Short view of the project site
Source: Google Earth Image
![Page 11: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/11.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
11 | P a g e
Figure 3: Site Plant Layout with nearby industries
![Page 12: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/12.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
12 | P a g e
Figure 4: Plant Layout
![Page 13: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/13.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
13 | P a g e
3.2.2 Alternative Studies:
As the proposed project is capacity enhancement project, alternative site has not been considered.
Since, by nature, the project is an expansion project, the existing premises of operational unit is the
most convenient site for the proposed expansion project. Moreover all the utilities & infrastructure
facilities are available in the present set up. Hence the existing premise with available infrastructure &
ease of operation is the best option available for the proposed expansion.
3.3 Resource Requirement
To carry out the proposed expansion, various resources like raw materials, power, fuel, water,
manpower, etc will be utilized.
3.3.1 Land Requirement
As mentioned above, the proposed expansion shall be developed within existing premises by using the
existing infrastructure. No additional land will be purchased/procured for the proposed expansion. Plant
layout is attached as Figure No: 4. Land document is attached as Annexure-7.
Total Plot Area - 50,000 m2
Existing spare land of 2000 m2 will be utilized for the proposed expansion.
Table 1: Land Breakup
No. Description Existing Area (m2)
Proposed Area (m2)
Total Area (m2)
Percentage %
1. Plant Area 16,219 2000 18219 36.44
2. Ground coverage Area 13,931 -- 13,931 27.86
3. Future expansion 3,349 -2000 1349 2.70
4. Greenbelt area 16,501 -- 16,501 33.00
Total Area 50,000 0.0 50,000 100
3.3.2 Man Power Requirement:
The company has already employed maximum nos. of manpower from the nearby area. Same policy of
local employment will be followed for the proposed expansion project as well.
The existing unit has existing manpower of 104 nos. Additional manpower shall be employed during the
construction & operation phase directly and indirectly through contracts for Civil Construction, Piping
Works and Associated Amenities. Approximately 25 nos. of people will get direct employment during
the construction phase.
Based on the unit‟s organizational pattern, 12 nos. of additional technical staff will be required to
operate the plant for the proposed expansion.
![Page 14: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/14.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
14 | P a g e
3.3.3 Electricity Requirement:
Source: Torrent Energy Ltd
Existing Contract Demand - 1900 KVA
Proposed additional Contract Demand – 1250 KVA
Total Contract Demand - 3150 KVA
Permission letter for the additional 1250 KVA load from Torrent Power is attached as Annexure-3.
The proponent is energy conscious and has taken various actions to reduce the power
consumption:
Replacing higher HP pumps with lower HP pumps
Replacing various lights with LED lights
Avoiding double pumping at various locations
Replacing cooling tower fans by FRP fans
Replacing electrical driven pump & blower with steam turbine driven etc.
3.3.4 Water Requirement:
Source of water: GIDC Water Supply
Total water requirement after proposed expansion will be 1000 KLD which will be supplied from GIDC
water supply. (Copy of the water withdrawal permission is attached as Annexure-4)
Table 2: Water Consumption
Existing (KLD)
Proposed (KLD)
Total (KLD)
i) Domestic Horticultural 50 00 50
ii) Industrial
a) Processing 17 06 23
b) Waste heat recovery
Boiler
595 201 796
c) Combination Cooling 80 35 115
d) Washing 8 8 16
Total Requirement 750 250 1000
![Page 15: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/15.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
15 | P a g e
4.0 RAW MATERIAL AND PRODUCT DETAILS
4.1 Raw Material Details
An estimated requirement of various raw materials for the proposed expansion is given in following
table. The basic raw materials required are given below:
Table 3: Raw Material Consumption
No. Raw Material Existing Quantity
Per annum
Proposed Quantity
Per annum
Total Quantity Per annum
Mode of transportatio
n
1 Sulphur 65,250 MT 21,750 MT 87000 MT By Road
2 Natural Gas 97,469.17 SCM/Day 21,183.3 SCM/Day 118,652.47
SCM/Day Pipe line from
GSPC
3. Water 750 KLD 250 KLD 1000 KLD GIDC water supply Pipe
Line
4. Electric Power 1900 kVA 1250 KVA 3150 KVA -
4.2 Product Details
The unit is engaged in manufacturing CS2 with capacity of 75,000 MT/Annum and increase the
production capacity up to 100,000 MT/Annum.
Table 4: Details of Product
No. Product Existing
Quantity
Proposed
Quantity
Total
Quantity
1 Carbon Di-sulphide 75,000 MTPA 25,000 MTPA 100,000 MTPA
2 Steam Export 65,000 MTPA 20,000 MTPA 85,000 MTPA
5.0 MANUFACTURING PROCESS:
This plant will produce liquid Carbon Di sulphide (CS2) by using natural gas and melting sulfur as raw
materials, the whole process consists various units like of Molten Sulfur Preparation Unit, Natural Gas
Purification Unit, CS2 Synthesis Unit, CS2 Refining Unit, Sulfur Recovery Unit, Tail Gas Treatment Unit,
CS2 Tank Farm and Utilities to meet the requirements of process. The natural gas based proprietary
technology of CS2 production for this project has been provided by Shanghai Baijin Chemical Group
Company and same procedure will be adopted for the continued in the proposed expansion. The
synthesis process is as under:
![Page 16: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/16.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
16 | P a g e
a) Liquid Sulfur Unit
Solid sulphur powder, granular or flake sulfur is acceptable and large lump sulfur is not permissible.
The Sulphur is stored in solid sulfur storage yard. It is then fed to melting sulfur tank and then the
molten sulfur is pumped into sulfur filter for filtration. Finally this on-spec liquid sulfur is flown into the
underground molten sulfur storage pit for pumping into the reacting furnace as the raw material of CS2
synthesis. While the liquid sulfur recovered by the flash system of the CS2 production and Sulfur
Recovery Unit, shall enter directly the underground pit of the liquid sulfur, where it is also transmitted by
the liquid sulfur feed pump to the CS2 reacting furnace for reaction. Provisions for receiving molten
liquid sulfur from outsource and unloading from liquid sulfur tankers directly into molten sulfur storage
tank are provided.
b) Natural Gas Purification Unit
Natural gas received is purified by the Natural Gas Purification Unit with Pressure Swing Adsorption
(PSA) unit to desired purity for the reaction. Off gases are used for reactor heating purposes.
c) Reaction Unit
Natural Gas – Sulfur Method is adopted with natural gas as feed for CS2 production.
CH4 + 2S2 CS2 + 2H2S
After the natural gas (feed natural gas), with its pressure stabilized via PSA purified gas buffer tank, is
metered accurately, it enters the preheating section of tubular heating furnace. After mixing with the
liquid sulfur (excess sulfur) from the liquid sulfur Unit via mixer, it enters the heating section of tubular
heating furnace, where the material is fluidized severely and the liquid sulfur vaporized. The gaseous
sulfur and natural gas (mainly methane) are heated with partial chemical reaction inside furnace. The
mixed gas coming from the tubular heating furnace enters the adiabatic reactor, while the unreacted
gaseous sulfur and natural gas continue to react inside the adiabatic reactor. Upon completion of
reaction, the reaction process gas coming from the adiabatic reactor is sent to the refining unit.
d) Refining Unit
The hot gases received from reaction section are cooled to recover Sulphur/H2S & CS2 is refined.
Recovered Sulphur is send to Sulphur tanks while H2S is send to Claus unit for further conversion to
elemental Sulphur.
e) CS2 Tank Farm
For the convenience of production management, the on-spec CS2 produced by CS2 Refinery Unit
enters the finished product intermediate tanks separately. The finished product produced in each shift,
after qualified via laboratory test, is sent by the finished product forwarding pumps, to the large CS2
tank in the tank farm or to the pitch-arm loading station for tank truck loading.
![Page 17: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/17.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
17 | P a g e
f) Sulfur Recovery Unit
The sulfur recovery unit (SRU) comprises of one thermal reaction section and two catalytic reaction
sections. Here Sulphur is recovered from H2S based on partial oxidation of H2S, and subsequent
reaction of H2S and SO2.
g) Tail Gas Treatment Unit
In the tail gas treatment unit, the residual H2S containing gas from the Claus unit is recovered via
Amine absorption and regeneration process. The recovered gas is fed back to the Claus furnace for
recovery. The treated gas from the Amine section is then taken to a thermal oxidizer furnace, where
the traces of H2S remaining are converted to SO2, before the gases leave from the stack. This ensures
a recovery Efficiency of 99.9% in SRU.
h) Energy Saving & Heat Recovery Plan
The proposed plant will consist of various waste heat recovery boilers /turbines to recover energy in
most economical way. The plant will be self-sufficient in Steam production and also export steam to
neighboring company. An optimized energy saving scheme will be part of Basic Energy
Package.
Figure 5: Manufacturing Process flow sheet
![Page 18: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/18.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
18 | P a g e
Salient Features of the Process/Technology adopted /to be adopted from old PFR
Existing CS2 manufacturing plant in India requires 350 kg charcoal per MT CS2 production
which comes from 1000 kgs of wood which results in to deforestation of 58 km2 per year.
SBC technology is well proven and replaces charcoal by Natural gas.
Proposed plant will be zero effluent discharge plant.
SRU is based on SCOT process technology, which shall achieve recovery efficiency of 99.9%.
6.0 ENVIRONMENTAL MANAGEMENT PLAN
6.1 Air Environment:
Adequate and efficient measures shall be provided to keep the process and dust emission at a minimum
level. The particulars of most specific individual sources and their pollution control measures are as
follows:
Table 5: Details of Air Emission
Sr. No.
Stack attached to Type of
Boiler/Furnace
Height of stack
(m)
Expected pollutants
APC
Existing
1. Tail Gas Treatment Unit & Flue Gas from Reaction heating Furnace
Incinerator
80 SPM, SO2,
NOx, Sulphur
recovery unit
2. Emergency System Venting (Emergency Flare Stack)
Flare
30 SPM, SO2,
NOx, --
3. D G Set of capacity 1650 kVA
Emergency Backup DG Set 11
SPM, SO2, NOx,
--
4. D G Set of capacity 1650 kVA
Emergency Backup DG Set 11
SPM, SO2, NOx,
--
Proposed
1. Tail Gas Treatment
Unit & Flue Gas
from Reaction
heating Furnace
Incinerator
Common Stack
with the
existing Unit
shall be used.
--
SPM, SO2,
NOx,
Tail Gas
Treatment
Unit, SRU
2. D G Set of capacity
1650 kVA Emergency
Backup DG
Set
11
SPM, SO2,
NOx, --
![Page 19: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/19.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
19 | P a g e
Water Environment:
Water Consumption
Existing water requirement for domestic and industrial purposes is 750 KLD and is obtained from the
GIDC water supply.
Table 6: Water Consumption
Existing (KLD)
Proposed (KLD)
Total (KLD)
iii) Domestic Horticultural 50 00 50
iv) Industrial
e) Processing 17 06 23
f) Waste heat recovery
Boiler
595 201 796
g) Combination Cooling 80 35 115
h) Washing 8 8 16
Total Requirement 750 250 1000
Unit has implemented various schemes for water conservation such as –
Using treated waste water for make up in dyke wall
Steam condensate recovery system
Replacing filter press in waste water treatment plant with pressure sand filter
Providing side stream filter for cooling tower etc.
With all these actions, unit is able to operate plant with around 750 KL/day water consumption.
Additional 250 KLD water will be required for the proposed expansion.
Wastewater Generation:
Indo Baijin is/will be using high cost Hydrogen Reduction Technology instead of cheaper and generally
used desulphurization technology to eliminate generation of high quantities of waste water.
The wastewater is mainly the blow down water from various waste heat recovery units (waste heat
boiler), DM plant wash water, the unrecovered steam condensate (majority of which is recovered),
moisture separated in the oxidation tower, the ground flush water, etc. They are/will be collected, mixed
and cooled inside the plant, and then sent to the wastewater treatment unit.
![Page 20: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/20.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
20 | P a g e
Table 7: Wastewater Generation
Existing wastewater
(KLD)
Proposed Wastewater
(KLD)
Total (KLD)
i) Domestic/ Horticultural 20 - 20
ii) Industrial
a) Processing 17 6 23
b) Waste heat recovery
Boiler 460 154 614
c) Combination Cooling 0 0 0
d) Washing 8 8 16
Total 505 168 673
Existing wastewater Generation:
1. The evaporation losses of 585 KLD from combination cooling tower, these water is coming from
80 KLD of fresh water and 505 KLD of recycle water steams from process, waste heat recovery
boiler, washing and domestic activities.
2. The total fresh water intake of 750 KLD is the sum of evaporation losses of 585 KLD in cooling
tower + 135 KLD steam export + 30 KLD horticulture consumption.
Proposed additional wastewater Generation:
1. The evaporation losses of 203 KLD from combination cooling tower, these water will coming
from 35 KLD of fresh water and 168 KLD of recycle water steams from process, waste heat
recovery boiler, washing and domestic activities.
2. The total additional fresh water intake of 250 KLD will the sum of evaporation losses of 203
KLD in cooling tower + 47 KLD steam export.
Conclusion:
Additional 250 KLD water will be required for proposed expansion as quantity of total proposed water
consumption will be greater than the granted water withdrawal permission from GIDC, Additional
water permission will be required due to proposed expansion. Permission has been obtained for the
additional 250 KLD water, which will be supplied from GIDC.
All the generated effluent is/will be evaporated in Combination Cooling Tower hence unit is/will be a
zero liquid discharge unit. Water permission letter has been attached as Annexure 4.
![Page 21: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/21.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
21 | P a g e
Figure 6: Water balance diagram after proposed expansion, in KLD
![Page 22: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/22.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
22 | P a g e
Action Plan for Zero Discharge of Effluent
a) Wastewater Streams :
i) Water from the Boiler feed water treatment plant comprising rejects from the demineralizing
section, and blow down water from boilers. The average composition of this stream is within 800
ppm of dissolved salts. The maximum quantity is 134 m3/day.
ii) From the tail gas treatment section of Sulphur recovery unit, the excess water condensed from
the flue gas is separated in the water removal tower. This water called Sour water has traces of
H2S. This is treated in an oxidation tower to convert the H2S into safe salt Na2S2O3. The maximum
quantity is 24 m3/day. The concentration of dissolved salts is within 200 ppm.
iii) The third stream is from general washing of plant and lab areas, this quantity is maximum
46m3/day. The concentration of dissolved salts is within 200 ppm.
Action Plan for Zero Waste Water Discharge:
As all the waste water streams are not having any COD and BOD, and only have shall quantity of
dissolved solids (salts), the design Philosophy of the plant has included the concept of „Zero Waste
Water Discharge”. In existing practice, Indo Baijin is using “Combination Type Cooling Towers” to
achieve zero liquid discharge and same shall be utilized after proposed expansion.
Figure 7: Flow Diagram of Combination Cooling Tower
Inside this cooling tower, the circulating cooling water flows through the inside of the cooling tube
bundles. This tube bundle is cooled from the outside in set up similar to a conventional cooling tower.
![Page 23: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/23.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
23 | P a g e
The outside water is circulated and sprayed on top of the tube bundle, and also a draft is maintained by
a fan across the cooling tower. By evaporation of outside water, the water inside the tube bundle is
cooled and returned to the plant supply. As the outside water is not taken directly to the plant cooling
duties it can be used and circulated with high solid content.
Combination Cooling Tower Treatment Scheme
To understand the concept of this Combination type of cooling tower, we need to compare this with the
conventional cooling tower working.
Working of Conventional Cooling Tower:
In a conventional cooling tower, the cooling water return streams from the plant are cooled by direct
contact with air, and the cooling takes place by part evaporation from the circulating water. During this
process the salt concentration of the water increases, and some water is drained off as blowdown to
limit the concentration of salts in the cooling water circuit. This is required to ensure water quality fit for
heat transfer in the plant equipment. This demands that only clean good water is added for making up
the losses in the cooling water system which are based on conventional cooling towers.
The Working of Combination Cooling Tower:
In this cooling tower, the cooling operation in the cooling tower is separated & isolated from the
circulating cooling water used to remove heat from the plant equipment. This ensures a closed circuit for
cooling in the plant, and hence no contamination of this stream takes place. The hot return stream from
the plant is cooled by indirect contact in the cooling tower, by a local circulation of water which in turn is
cooled by evaporative cooling by contact with air.
The local circulation water stream in the cooling tower can be used continuously till it reaches a critical
concentration of dissolved solids, after which it is discharged to a final evaporator for separation of salts
for disposal. The design of the cooling tower ensures continuous wetting of heat transfer surface to
enable required evaporative cooling and maintaining clean surfaces without any scales formation. This
design feature is achieved by the patented co-current air-water flow technology by the supplier.
Due to these design features it is not necessary to add clean water make up in this type of cooling
tower. Hence in our units set up we add recycle water streams as part of makeup water to the cooling
tower. This enables recycling of all waste water streams (after suitable pre-treatment) of the plant as
make up to this cooling tower. Therefore the plant facility does not discharge any waste water from the
premises.
![Page 24: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/24.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
24 | P a g e
The addition of recycle streams also enable saving of fresh water consumption of over 200 KLD for our
unit. Elimination of blowdown from the cooling tower saves another 80 KLD considering a concentration
cycle of 7. Therefore this system saves about 300 KLD or 100,000 m3/Annum for our unit.
In our existing project these is served as the Heat Sink and also Zero Discharge Unit, by combining the
functions of the cooling tower and also a water evaporator. Adequate overdesign has been built into this
system to ensure sufficient spare capacity. After proposed expansion there will be additional 3 nos. of
Combination cooling tower.
Domestic Waste Water:
The domestic waste water streams shall be treated in a modern packaged sewage treatment unit with
capacity of 50 KLD, and the treated water shall be available for reuse in toilets, and feeding to the Zero
Discharge cooling tower unit. After proposed expansion,12 nos. of additional workers will be employed
for process work. Thus existing STP will be sufficient for the domestic wastewater generation after
proposed expansion.
Figure 8: Sewage Treatment Plant (STP) Flow Diagram
![Page 25: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/25.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
25 | P a g e
Table 8: Sizing of Sewage Treatment Plant
S. No Unit Size
1. Collection tank 3 m X 1 m X 3 m
2. Aeration tank 3 m X 3 m X 3 m
3. Clarifier 1 m X 1 m X 2 m
4. Treated water tank 2 m X 2 m X 3 m
5. Filtered water tank 2 m X 2 m X 3 m
6. Sand filter cum solid collection tank 2 m X 2 m X 3 m
7. Sludge Drying Bed, 3 nos. 3 (1 m X 1 m X 2 m)
6.2 Solid/Hazardous Waste
The entire quantity of hazardous waste is handled and disposed as per Hazardous Waste
(Management, Handling and Trans-boundary Movement) Rules - 2016. Furnace slag from furnace pipe
and reactor cleaning, Used spent Oil, Discarded Container/Barrels/Liners, Evaporation salt and Sludge
from sulfur filter are generated from existing unit. Unit has obtained membership for BEIL (Attached as
Annexure-6). After expansion, no additional quantity of Hazardous waste will be generated except
Sludge from sulfur filter. As a solid waste STP sludge is generated, this is used as manure in the
premises.
Table 9: Hazardous/Solid Waste Generation
No. Name of Waste Waste category
Existing Total after Proposed expansion
Solid waste Disposal / Management
1 Furnace slag from furnace pipe and reactor cleaning
1.1 55 MTPA 85 MTPA Collection, Storage, Transportation & Disposal at common incineration facility.
2 Used spent Oil 5.1 1.0002 MTPA
1.5002 MTPA
Collection, Storage, Transportation & Disposal by selling to register refiners
3 Discarded Container/Barrels/Liners
33.3 100 MTPA 100 MTPA Collection, Storage, Transportation & Disposal by GPCB approved scrap dealer
4 Evaporation salt Sch: I/35.3 144 MTPA 144 MTPA Collection, Storage, Transportation & Disposal at TSDF, BEIL.
5 Sludge from sulfur filter -- 78 MT/Year
78 MTPA
Collection, Storage, Transportation & Disposal at common incineration facility.
6 STP Sludge -- 30 kg/day -- Used as manure
![Page 26: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/26.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
26 | P a g e
No. Name of Waste Waste category
Existing Total after Proposed expansion
Solid waste Disposal / Management
7 Spent Catalyst and Molecular sieves
1.6 -- 67 MT Collection, Storage,
Transportation &
Disposal at common
incineration facility.
8 Residue Carbon 18.2 - 2 MT Collection, Storage,
Transportation &
Disposal at common
incineration facility.
9 Spent Ion Exchange Resin
35.2 - 2 MT Collection, Storage,
Transportation &
Disposal at common
incineration facility.
10 Wastage or residue containing oil,
5.2 - 2 MT Collection, Storage,
Transportation &
Disposal at common
incineration facility.
11 Contaminated Cotton rags or other cleaning materials
33.2 - 1 MT Collection, Storage,
Transportation &
Disposal at common
incineration facility.
6.3 Noise Environment
The industry is in the SEZ area and located 8-km away from the nearest settlement. There are two
categories of noise generated due to the unit.
Noise due to plant operation
Noise due to transportation of vehicles.
Noise Control Measures:
All the vibrating parts are checked periodically and serviced to reduce the noise generation. The
equipment, which is prone to generate excessive noise, is already provided with enclosures. To
minimize the adverse effect on the health, ear muffs/ earplugs is provided to the workers working
under high noise area.
The industry has already developed 16500 m2 area for green belt around the periphery of the plant.
This will help in reducing the adverse effect of noise pollution in general. All the equipment in the
complex is designed/operated in such a way that the noise level shall not exceed 85 dB (A).
![Page 27: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/27.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
27 | P a g e
All rotating equipment in the plant would be designed/operated to have a total noise level not
exceeding 85 to 90 dB (A) as per the requirement of OSHA (Occupational Safety and Health
Administration) standard and the Environment (Protection) Rules.
However, if during operation, the noise level exceeds the above norms then the protective measures
given in Environmental Management Plan will be followed. Hence, no impact due to proposed plant on
ambient noise is anticipated.
6.4 Occupational Health & Safety Management
The company is very much concerned in terms of health, safety and environment protection. Indo
Baijin commitment towards safety can be reflected from its „Health, Safety & Environment Policy‟
prepared for the existing project.
No major accident has taken place in the factory so far in the existing project. From their previous
performance, same dedication is to be continued for the proposed expansion. To maintain high
standards in Health, Safety and Environment, various activities are undertaken at the site.
The following key safety measures are implemented in the existing plant and the same shall be a part
of proposed expansion project:
1. Safety Training is provided to the employees.
2. Safety Sirens with Alarm System in case of emergency are provided.
3. Emergency Control Room is established.
4. Assembly point is provided.
5. Sprinkler Systems will be provided as needed.
6. Fire Hydrant System is installed.
7. Fire Extinguishers are provided.
8. Mock drills are periodically conducted and factors like response time are evaluated.
9. Fire squad team is formed for handling any emergency situation.
10. First Aid Facility and training are provided.
11. Personal protective gears and equipments are provided to employees.
12. Health check-ups are organized at regular intervals.
13. Safety / Health records are maintained.
14. MSDS for all the chemicals are easily available.
Details of Fire Protection System:
Outdoor Fire Hydrant 20
Indoor Fire Hydrants 36
Fire Hose – Size – 15 mtr. 120
Water Monitor – Manual 10
Water Monitor – Electrically Remote Operated 02
Water Spray Cooling System at CS2 Tank Farm 01
![Page 28: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/28.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
28 | P a g e
Water spray system at CS2 loading area 01
Dedicated storage of water for firefighting in lit 3218 M3
Manual Call Points 48
Continuous Gas Detectors CS2 14
Continuous Gas Detectors H2S 26
Continuous Gas Detectors CH4 16
Heat Detectors 04
Breathing Sets 17
Fixed Air-line system 10
7.0 SITE ANALYSIS
7.1 Connectivity
The project location is well connected with road, rail and air route to transport raw materials,
machineries, etc. and hence it exhibits good potential for industrial growth. The salient features
mentioned below, indicate favorable conditions for industrial development at the project location.
Table 10: Salient Features of the project site
Particulars Details
Approx. Geographical Co-ordinates
Latitude Longitude
A 21°42'35.74"N 72°37‟06.78"E
B 21°42'36.02"N 72°37'10.94"E
C 21°42'27.10"N 72°37'11.04"E
D 21°42'30.92"N 72°37'10.30"E
Village Vadadla(@ 2.4 km in NE direction)
Nearest Town Bharuch (@ 40.0 km in E direction)
Nearest City Bharuch (@ 40.0 km in E direction)
River/Streams Narmada Estuary (@3.00 km in S direction)
Sea Arabian Sea (@ 11.0 km in W direction)
Nearest Highway
N. H. No – 228 (@ 36 km in E direction)
N. H. No –8 (@ 36 km in E direction)
S. H. No – 6 (@ 42 km in EEN direction)
Nearest Railway Station Dahej Railway Line (@ 2.50 km in WWN direction)
Bharuch (@ 40 km in E direction)
Nearest Airport Surat Airport (@ 66 km in SSE direction)
National parks/ sanctuaries None within 10 km radial area
![Page 29: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/29.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
29 | P a g e
Defense installations None within 10 km radial area
Note: All the above – mentioned distances are aerial distances from the project site.
7.2 Topography
Proposed expansion is between 20007” to 21005” North Latitude and 72043” to 73000” East Longitude
having elevation of 25 meters above sea level. The topography of the proposed site for the project is
plain terrain.
No forests, national park or wild life sanctuary is located within 10 km periphery of the project site. No
change in Land use/Topography is envisaged as the proposed project is expansion project and is
established in SEZ-1, Dahej.
7.3 Existing Infrastructure
Key infrastructure such as hospitals, schools, bank, places of worship and social/ community facilities
such as park, market, playground etc. education, health care, community development, income
distribution, employment and social welfare are available in the study area of project site.
7.4 Soil Classification
Proposed expansion will be carried out in existing premises located in SEZ, where land is already
developed for industrial purpose. Quality of soil is not considerably fertile for agriculture activities and
no evidence of any influence of soil contaminant has been noticed.
7.5 Climate Data From Secondary Source
Table 11: Climate Data
Climate Type and Details
Climate Temperate climate-Semi Arid
Seismic Zone Zone III
Maximum temperature, °C 44 °C
Minimum temperature, °C 12°C
Relative Humidity Max.:- 97 %; Min.:- 20%
Max Rainfall 1500 – 2200 mm
Climate Temperate climate
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 Project Schedule
Proposed expansion activities will be started after getting statutory clearance from related authorities.
![Page 30: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/30.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
30 | P a g e
8.2 Project Cost Estimation
No. Project Estimate cost
1 Proposed expansion cost 100 crore
8.3 Activities
Indobaijin which is a part of Indofil Group Company has always engaged in social welfare activities &
programs. It directly organizes various programs for social welfare & upliftment or indirectly contributes in
such activities conducted by other organizations by providing financial & other aid. Indobaijin is
committed to contribute in social welfare & upliftment activities on a regular basis. Indobaijin will continue
such activities to fulfill the requirements of its social responsibility under CER Programs. With
development of community services like medical services, blood donation camp, donation for schools etc
will also be developed as a part of corporate social responsibility. Medical camps and education
programmes would be conducted for the welfare of employees and their families.
Indo Baijin Chemicals Pvt Ltd. in collaboration with a non-government organization (NGO) Ballygunge
Society for Environment & Development undertakes CER activities in the village Purba Gopinathpur. The
following activities are evident of the fact that Indo Baijin is a promoter of CER Programs:
Donation given to JCI - Bharuch for Election Awareness Campaign organized by them at
Dahej.
Donation given to former CM of Gujarat (Mrs. Anandiben Patel) under Clean India Campaign.
Food Packets distributed to poor villagers of Vagra Taluka who attended “Garib Kalyan Mela”
at Jambusar.
Organised various seed to seed demonstrations, soil testing and training on safe and judicious
use of pesticides.
Operated Agril Library having more than 200 books on agriculture thrice a week at the local
club premises.
Provided computer training through two trainers to 80 students thrice a week.
Trained 65 young people, mostly girls, for athletics and 40 youths for football, twice every
week, under eminent coaches.
Organised health camps once in every fortnight to provide treatment for ailment and health
counseling.
Constructed sanitary facilities, especially for girls and women, at the village club premises.
Planted around 250 saplings throughout the village.
Organised cultural programmes, rally and competitions to increase awareness about the
environment.
Provided Shoe stand for Dahej School and Hostel for the students in tribal Area.
Houses for Poor Villagers of Dahej: Construct 5 (five) houses for poors of Dahej village. This
will be sample houses. Based on the success of this; new project will be assigned.
Development of Digital Classroom: Two digital class rooms have been constructed at Dahej
Girls‟ School by The Industry.
![Page 31: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/31.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
31 | P a g e
Blood donation camp has been organized by the industry at Indofil industries Ltd.(Unit-2) on
October 2018.
About 30 students have been visited Unit 1 & 2 on 18 January 2019 to get Industrial exposure
of latest lab instruments.
Donation of Rs. 50,000 to the Bhootnath Trust of Dahej for “Samooh Lagan” (marriage of 48
couples from needy family) at Dahej.
Donation of computer set to the school of Dahej.
Financial & Social Benefits
The proposed activities will be carried out in the existing unit itself. Hence, no additional land is to
be purchased.
This project utilizes natural gas as one of the raw materials for the synthesis of the product.
Currently all the existing CS2 manufacturing units in India use wood charcoal for this purpose.
Considering 350 kilograms of charcoal consumption per ton of CS2, one ton of wood is used per
ton of CS2. Thus at 100,000 tons of CS2 production per annum, this project will reduce
deforestation to the extent of 58 km2 per year in the country. Thus, the project entails financial
benefits in terms of energy saving.
The company has also allocated some budget for CER activities, which can lead to improved
social infrastructure, if planned properly.
Temporary employment of 25 people during the construction phase of the proposed expansion.
Employment to approx. 12 people is a direct benefit.
Conclusion:
As summarized in the above sections, it has been noticed that the proposed project for expansion in
capacity will not have any major impacts, which can lead to serious issue of environmental pollution
or any other hazards.
Considering the probability of impacts, proponent has planned adequate mitigation measures and
EMP. Further, it is also planned by proponent to organize CER programs, rainwater harvesting,
energy conservation, which will have considerable beneficial impacts. Looking to the employment
potentials and other allied developmental potentials, it is noticed that the proposed project will
significantly help in improving social status of the region.
![Page 32: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/32.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
32 | P a g e
Annexure 1: Existing Environmental Clearance
![Page 33: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/33.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
33 | P a g e
![Page 34: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/34.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
34 | P a g e
![Page 35: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/35.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
35 | P a g e
![Page 36: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/36.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
36 | P a g e
![Page 37: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/37.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
37 | P a g e
![Page 38: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/38.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
38 | P a g e
![Page 39: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/39.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
39 | P a g e
Annexure 2: Consent to Operate (CC&A)
![Page 40: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/40.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
40 | P a g e
CC&A
![Page 41: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/41.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
41 | P a g e
![Page 42: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/42.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
42 | P a g e
![Page 43: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/43.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
43 | P a g e
![Page 44: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/44.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
44 | P a g e
![Page 45: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/45.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
45 | P a g e
![Page 46: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/46.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
46 | P a g e
Amended CC&A
![Page 47: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/47.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
47 | P a g e
![Page 48: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/48.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
48 | P a g e
![Page 49: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/49.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
49 | P a g e
Annexure 3: Electricity Permission Letter
![Page 50: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/50.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
50 | P a g e
![Page 51: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/51.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
51 | P a g e
Annexure 4: Water withdrawal Permission from GIDC
![Page 52: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/52.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
52 | P a g e
![Page 53: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/53.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
53 | P a g e
Annexure 5: EC letter for Dahej SEZ
![Page 54: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/54.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
54 | P a g e
![Page 55: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/55.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
55 | P a g e
![Page 56: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/56.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
56 | P a g e
![Page 57: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/57.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
57 | P a g e
![Page 58: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/58.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
58 | P a g e
![Page 59: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/59.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
59 | P a g e
![Page 60: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/60.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
60 | P a g e
Annexure 6: BEIL Membership Letter
![Page 61: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/61.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
61 | P a g e
![Page 62: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/62.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
62 | P a g e
BEIL Application for Catalyst/Resin
![Page 63: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/63.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
63 | P a g e
BEIL NOC for receiving Incinerable/co-process waste
![Page 64: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/64.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
64 | P a g e
Annexure 7: Land Documents
![Page 65: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/65.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
65 | P a g e
![Page 66: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/66.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
66 | P a g e
![Page 67: PRE-FEASIBILITY REPORT...PRE-FEASIBILITY REPORT FOR PROPOSED EXPANSION IN PRODUCTION CAPACITY OF CARBON DI SULPHIDE (CS 2) AND EXPORT OF STEAM [Schedule 5 (b) Category “A” as per](https://reader030.fdocuments.in/reader030/viewer/2022040203/5e97ce919339886a9725f203/html5/thumbnails/67.jpg)
INDOBAIJIN CHEMICALS PVT LTD.
Pre – Feasibility Report for Capacity Expansion Project
67 | P a g e