Page 1: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Pre Engineering

Risk Management

Rajesh Kandhai

Page 2: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Recap - Hazard

Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially cause harm in terms of human injury, or ill health, damage to property, damage to the workplace environment, or a combination of these (adapted from OHSAS 18001:2007)

Page 3: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Recap - Risk

The combination of the likelihood (probability) and the consequence (s) of a specific hazardous event occurring.

Risk = likelihood x consequences (x no. of people affected)

Page 4: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Risk Assessment – 5 steps to risk assessment

A risk assessment is simply a careful examination of what, in your work, could cause harm to people, so that you can weigh up whether you have taken enough precautions or should do more to prevent harm. Workers and others have a right to be protected from harm caused by a failure to take reasonable control measures.

Page 5: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Assessing workplace risk

Step 1 Identify the hazards Step 2 Decide who might be harmed

and how Step 3 Evaluate the risks and decide on

precautions Step 4 Record your findings and

implement them Step 5 Review your assessment and

update if necessary

Page 6: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Step 1 - Identify the Hazard Walk around your workplace and look at what

could reasonably be expected to cause harm. Ask your employees or their representatives

what they think. They may have noticed things that are not immediately obvious to you.

If you are a member of a trade association, contact them. Many produce very helpful guidance.

Check manufacturers’ instructions or data sheets for chemicals and equipment as they can be very helpful in spelling out the hazards and putting them in their true perspective.

Remember to think about long-term hazards to health (eg high levels of noise or exposure to harmful substances) as well as safety hazards.

Page 7: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Types of Hazards Hazards may be of varying types:

Physical Mechanical Electrical Chemical Biological Ergonomic Psychological

Page 8: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Hazards continued After understanding the work to be

done, try to identify the possible scenarios:

Physical – noise from equipment, temperature in room

Mechanical – pinch points, crush points, vehicle collisions

Electrical Chemical – exposure, storage, compatibility Ergonomic – strains form tasks (manual handling

etc) Psychological – stress from deadlines, work load,

unrealistic management requests.

Page 9: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Step 2 – Who might be harmed

For each hazard you need to be clear about who might be harmed; it will help you identify the best way of managing the risk. That doesn’t mean listing everyone by name, but rather identifying groups of people (eg ‘people working in the storeroom’ or ‘passers-by’).

Page 10: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Step 3 – Evaluate the risk and decide on precautions look at what you’re already doing, think about

what controls you have in place and how the work is organised. Then compare this with the good practice and see if there’s more you should be doing to bring yourself up to standard. In asking yourself this, consider:

Can I get rid of the hazard altogether? If not, how can I control the risks so that harm is unlikely?

When controlling risks, apply the principles below, if possible in the following order:

try a less risky option (eg switch to using a less hazardous chemical); prevent access to the hazard (eg by guarding); organise work to reduce exposure to the hazard (eg put barriers between

pedestrians and traffic); issue personal protective equipment (eg clothing, footwear, goggles etc); and provide welfare facilities (eg first aid and washing facilities for removal of contamination

Page 11: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Risk evaluation - likelihood

Likelihood of occurrence Description of rating Rating

Very Unlikely Impact highly unlikely to occur 1

Unlikely Impact unlikely to occur 2

Possible Impact likely to occur 3

Likely Impact highly likely to occur 4

Very Likely Impact Certain to occur 5

Page 12: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Risk Evaluation - Consequence

Severity       rating

Negligible No observable effect 1

SlightImpact restricted to fewer than three

Lost time days 2

ModerateMinor Fracture - permanent injury/

disability 3

High Single Fatality 4

Very high Multiple fatalities 5

Page 13: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Risk Matrix

    Hazard Severity

    1 Negligble 2 Slight 3 Moderate 4 High 5 Very High

Likelihood of occurrence

1 Very Unlikely 1 2 3 4 5

2 Unlikely 2 4 6 8 10

3 Possible 3 6 9 12 15

4 Likely 4 8 12 16 20

5 Very Likely 5 10 15 20 25

Page 14: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Action levels

 

No new action required. Continual Monitoring of existing controls

 

Implement control measures and conduct monitoring to ensure effectiveness

 

Activity should not be started or continued until risk reduction measures implemented. Immediate action required

Page 15: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Step 4 – Record and implement findings Putting the results of your risk assessment into

practice will make a difference when looking after people and your business.

Writing down the results of your risk assessment, and sharing them with your staff, encourages you to do this. If you have fewer than five employees you do not have to write anything down, though it is useful so that you can review it at a later date if, for example, something changes.

When writing down your results, keep it simple, for example ‘Tripping over rubbish: bins provided, staff instructed, weekly housekeeping checks’, or ‘Fume from welding: local exhaust ventilation used and regularly checked’.

Page 16: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Step 5 – Review and update Few workplaces stay the same. Sooner or later, you will bring

in new equipment, substances and procedures that could lead to new hazards. It makes sense, therefore, to review what you are doing on an ongoing basis. Every year or so formally review where you are, to make sure you are still improving, or at least not sliding back.

Look at your risk assessment again. Have there been any changes? Are there improvements you still need to make? Have your workers spotted a problem? Have you learnt anything from accidents or near misses? Make sure your risk assessment stays up to date.

When you are running a business it’s all too easy to forget about reviewing your risk assessment – until something has gone wrong and it’s too late. Why not set a review date for this risk assessment now? Write it down and note it in your diary as an annual event.

During the year, if there is a significant change, don’t wait. Check your risk assessment and, where necessary, amend it. If possible, it is best to think about the risk assessment when you’re planning your change – that way you leave yourself more flexibility.

Page 17: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Example of a Job Hazard Analysis

Page 18: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Failure to identify and evaluate the hazard and risk

Page 19: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 20: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 21: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 22: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 23: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 24: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 25: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 26: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 27: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 28: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 29: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.
Page 30: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Exercise 4

Cleaning the Cafeteria

How can I get hurt? (Hazards)

What would my injuries be? (Hazard Effect)

What can I do to prevent my being hurt? (Control)

Page 31: Pre Engineering Risk Management Rajesh Kandhai.  Hazard – source (e.g. substance, activity, event or environment) or situation that could potentially.

Exercise 4

1. How might this person be injured?

(Note; NOT what the injury might be but (Note; NOT what the injury might be but what might or would what might or would CAUSECAUSE him to be him to be injured)injured)

An Electrician is drilling through a wall with an electric hand drill.