2016 Intern Experience Shelbie Prater August 4, 2016

Transcript of Prater_ Intern Experience - SP

Page 1: Prater_ Intern Experience - SP

2016 Intern ExperienceShelbie PraterAugust 4, 2016

Page 2: Prater_ Intern Experience - SP

2Agenda Overview

Personal Background Gas Compression Overview Goals & Objectives Projects and Assignments Intern Challenge Internship Reflection

Page 3: Prater_ Intern Experience - SP

3Shelbie Prater

Page 4: Prater_ Intern Experience - SP

Gas Compression Overview

Gas Compression and Compressor Stations

Page 5: Prater_ Intern Experience - SP

5

Energy Resources | Gas Transmission & Storage Compressor Stations:

Located along natural gas pipeline Compress gas to help move along to next location

Gas Compression Overview

Page 6: Prater_ Intern Experience - SP

6Compressor Station - General

Page 7: Prater_ Intern Experience - SP

7Northville Compressor Station

Page 8: Prater_ Intern Experience - SP

8Northville – Schematics

Page 9: Prater_ Intern Experience - SP

9Consumer’s Compression Stations

Ray Compressor Station(interior)

Ray Compressor Station(exterior)

Page 10: Prater_ Intern Experience - SP

Goals and Objectives

Page 11: Prater_ Intern Experience - SP

11

• Complete Northville 2016 Relief Valve Documentation

Goal 1:

• Visit at least (4) different compressor stationGoal 2:

• Visit at least (2) non-compression sitesGoal 3:

• Be able to identify key components of an on-site project

Goal 4:

Goals & Objectives

Page 12: Prater_ Intern Experience - SP

12Goal 1: NVL 2016 Relief ValvesRaw Data

Calculations and comparisons

Page 13: Prater_ Intern Experience - SP

13Goal 2: Visit (4) Different Compression Stations

Page 14: Prater_ Intern Experience - SP

14Goal 3: (2) Non-Compressor Sites

1. Jackson Gas Plant

2. CMS Innovation Center

3. Webber Hydro Dam

Page 15: Prater_ Intern Experience - SP

15Goal 4: Understanding Onsite Projects

Page 16: Prater_ Intern Experience - SP

Projects and AssignmentsNorthville CS

Other Projects

Page 17: Prater_ Intern Experience - SP

17

Initial Problem Over-pressured inter-stage piping caused by an Engine Emergency Shutdown

(ESD) allowing field discharge pressure to short-circuit through unit piping and expand rapidly into a small volume inter-stage header.

Solution Install check valves on Unit 3 and 4 Discharge piping and

a Relief Valve on the Common Inter-stage Piping

GC-00466: NVL Discharge Check Valves

Page 18: Prater_ Intern Experience - SP

18

Northville• Storage – Vented

Gas Reports• Pipeline work

order binders

Freedom• Temporary

compressor site• Cooling pump

St. Clair• Station upgrade• Details on Tank 2

oily water pump

Ray• Engine Analysis

– Vibration Tests• Exhaust Tests

Projects and Assignments

Page 19: Prater_ Intern Experience - SP

Internship ChallengeRoyal Oak Public Library

Summer Science Festival

Page 20: Prater_ Intern Experience - SP

20Intern Challenge

Page 21: Prater_ Intern Experience - SP

Internship ReflectionTechnical Skills

Non Technical Skills

Page 22: Prater_ Intern Experience - SP

22

TechnicalNatural Gas compression system functionality

Engines

Material (metal) grading

Beams and foundations

Construction Management

Non-technicalConsumer’s Energy company culture

Energy (utility) market

Taking ownership of the experience

The importance of enforcing a safe environment

Internship ReflectionSKILLS LEARNED:

Page 23: Prater_ Intern Experience - SP

23