Communication Critical Test Results Safe Practice Recommendations
Practice Test 1 Results
-
Upload
anirbanchat -
Category
Documents
-
view
227 -
download
0
Transcript of Practice Test 1 Results
-
8/6/2019 Practice Test 1 Results
1/75
15/03/11 1:44 PMprint.html
Page 1 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
Exam Results for
PgMP Practice Test#1
You correctly answered 99 out of 170questions for a score of 58%.
On the real PgMP exam, you'll face 170
questions, 20 of which do not count towardyour PgMP, but are not identified as such.(The 20 unscored questions are "pretest"
questions that PMI is trying out todetermine their validity.) You will receive a
score that indicates whether you passed orfailed the exam. You will not know the
number of questions you answered correctly.Instead, you will find out by Domain (Defining
the Program, Initiating the Program, Planningthe Program, Executing the Program,
Controlling the Program, and Closing theProgram) whether you are Proficient,
Moderately Proficient, or Below Proficient.
Your goal is to be Proficient in each domain.
If you are not Below Proficient in any domain,statistically you have a very high likelihood of
passing. If you receive a score of BelowProficient in any domain, you will need to
earn enough extra points in another domainto make up for the deficiency.
For your study purposes and for your goal tobe Proficient in all domains, we are
interpreting Proficient as correctly answeringat least 90% of the questions in each domain,
Moderately Proficient as 75% to 90%, andBelow Proficient as less than 75%. Note: This
is ESI's interpretation and is not an official
response from PMI.
The table below shows how you performed onyour Practice Test in each of the domains
described by the Program Management
Professional (PgMP) Examination
Specification.
Domain
Number Correct
/ Number ofQuestions
Percentage
Correct
Defining
theProgram
13/24 54%
Initiating
theProgram
12/20 60%
PlanningtheProgram
16/34 47%
Executingthe
Program
32/42 76%
Controllingthe
Program
16/36 44%
Closingthe 10/14 71%
-
8/6/2019 Practice Test 1 Results
2/75
15/03/11 1:44 PMprint.html
Page 2 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
Program
Questions
Question:
[QID: 6488] For seven years, you have
managed a program that involvedbreakthrough scientific research. You are
now in the closing stage. You have alreadymet with each scientist involved in the
program at the time his or her work wasfinished. You have also met with a member
of your enterprise program managementoffice (EPMO) who specializes in knowledge
management to ensure that the intellectualproperty developed in the program is
captured and documented for future reuse.You are
A) Ensuring legal protection of thisvaluable asset
B) Promoting collaboration in the scientificcommunity
C) Recognizing individual efforts as well as
the efforts of the entire project team
D) Officially releasing each scientist to his
or her functional organization
Explanation:
It is important not only to capture and
document knowledge assets from eachproject and the intellectual property that hasbeen developed, but also to do so in a
manner that ensures legal protection ofthese assets. This is necessary to ensure
that data privacy and confidentially laws arenot violated.
The Standard for Program Management, p.
66
Question:
[QID: 6579] You are managing a business
process management program for a largeinsurance company. After six months of
effort, you have noticed that the keystakeholders seem to be losing interest in
the effort and that friction has surfacedbetween your key staff members and key
client contacts. You devise a plan to uncoverthe reasons for these apparent issues. Youadvise your deputy program manager to
have lunch with her client counterpart atleast once a week; likewise, you will start
taking the clients vice president out todinner every month. This activity can be
viewed as
A) Ineffective, because clients can seethrough such actions
B) Positive, but bordering on beingunethical
C) Positive, because you will be buildingstronger relationships with your client
D) Negative, because it is a calculated
attempt to gain information that could beobtained through more direct means
Explanation:
-
8/6/2019 Practice Test 1 Results
3/75
15/03/11 1:44 PMprint.html
Page 3 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
Provided the clients code of ethics does not
prohibit such entertainment activities,internal politicking is a skill and competencythat successful program managers practice.
In this instance, such activity can be veryhelpful in uncovering underlying problems.
Program Management Professional (PgMP)
Examination Specification, p. 20
Question:
[QID: 6467] You are the program managerfor a sixth-generation cell phone product. Anumber of component projects are
associated with this program. You were onthe core program team for the fifth-
generation phone, so you can apply thelessons learned from that program. The
schedule is the dominant constraint, andthere is a chance that you will miss the
user-acceptance test milestone even thoughit is six months away. Your next step is to
A) Ask your program steering committeefor additional resources to ensure that you
can meet the milestone
B) Inform the executive team that you willmiss this critical milestone unless preventive
action is taken
C) Revisit the program architecture
baselineD) Implement your plan
Explanation:
The program architecture baseline is the
output of the Develop Program Architectureprocess. It is useful in examining current
risks and determining whether new risksexist.
The Standard for Program Management, pp.
114 and 161
Question:
[QID: 6582] You manage the development
of an off-shore liquefied natural gas facility.Several contractors will be used in the
component projects, and you are creatingspecific procurement strategies. After you
determine which program work breakdownstructure (PWBS) elements will be handled
internally and which will be contracted, yournext step is to
A) Analyze the product description
B) Use make-or-buy decision techniques
C) Prepare a procurement managementplan
D) Analyze the program scope statement
Explanation:
After you analyze the PWBS, scope
statement, and product description, youapply make-or-buy decision techniques to
determine which of the PWBS elements willbe produced using internal resources and
which will be obtained from outsidesuppliers.
-
8/6/2019 Practice Test 1 Results
4/75
15/03/11 1:44 PMprint.html
Page 4 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
The Standard for Program Management, p.
187
Question:
[QID: 6527] One of the issues on yourprogram is difficult to resolve because it
concerns serious personality conflicts.Although it was raised by Project Manager A,
it affects Projects B and C. Each of the threeproject managers has a different solution,
and there is a stalemate. You cannot resolve
this issue on your own and still maintain agood relationship with all three, so youescalate it to your executive sponsor for
resolution at the next governance boardmeeting. This unresolved issue is
A) An output of the Manage Program
Issues process
B) Best analyzed by a neutral party who
will make a recommendation to theexecutive sponsor
C) Sent to the enterprise programmanagement office (EPMO) to see whether it
has been encountered and resolved onsimilar projects
D) Put in a parking lot on the issuesregister until it is resolved
Explanation:
Ideally, issues should be resolved by theprogram manager or the component projectmanagers. If resolution is not possible, then
an issue is escalated progressively higher onthe authority scale until resolution is
achieved. Escalated issues are an output ofthe Issue Management and Control process.
The Standard for Program Management, p.
95
Question:
[QID: 6461] Communications planning and
execution focus on
A) Reacting to stakeholder concerns
B) Proactively targeting development and
delivery of key messagesC) Taking corrective actions in response to
program issues
D) Identifying suitable technologies fordistributing program information
Explanation:
The emphasis of communications planning
and execution is on the proactive and
targeted development of key messages.Program stakeholders should be engaged atthe right time and in the right way.
The Standard for Program Management, p.227
Question:
[QID: 6521] Your organization is embarkingon a program to establish a culture of
knowledge management. You established alessons-learned register on your last project.
-
8/6/2019 Practice Test 1 Results
5/75
15/03/11 1:44 PMprint.html
Page 5 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
The enterprise program management office
(EPMO) was impressed and suggested to theCEO that a program focusing on knowledgemanagement is needed. The CEO concurred,
and you were appointed program manager.Two people from the EPMO have been
assigned to the core program team. Theymay be replaced by permanent staff during
which one of the following processes?
A) Human Resource Planning
B) Manage Program Resources
C) Acquire Program Team
D) Initiate Team
Explanation:
Many organizations set up a program teamto participate in initiation or program start-
up and then replace team members withpermanent staff during the Manage Program
Resources process, which tracks and adaptsthe use of program resources throughout the
life cycle.
The Standard for Program Management, p.91
Question:
[QID: 6495] As each project manager beginsto identify the work to be done on their
projects, you want to make sure that allwork will be integrated into a program plan.The best way to ensure this linkage is
through a common
A) Scheduling methodology
B) Project management standard
C) Work breakdown structure (WBS)
methodology
D) Organizational breakdown structure(OBS) methodology
Explanation:
Because the WBS defines all work in aproject and program, this is the best tool to
use for integration. The program workbreakdown structure (PWBS) typically
corresponds to the first one or two levels ofthe WBS of each component project. As the
PWBS is developed, the managementplanning process is a key tool and technique
to use.
The Standard for Program Management, pp.115117
Question:[QID: 6433] The person who is ultimatelyresponsible for ensuring program success is
the
A) Program manager
B) Head of the program governance board
C) Executive sponsor
D) Program director
Explanation:
The executive sponsor is the group or
person who is responsible for providing
-
8/6/2019 Practice Test 1 Results
6/75
15/03/11 1:44 PMprint.html
Page 6 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
project resources and ultimately for ensuring
program success.
The Standard for Program Management, p.
245
Question:
[QID: 6562] You are a member of your
insurance companys Program SelectionCommittee, which is considering a number of
potential programs. Program A is estimated
to cost $100,000 to implement and will haveannual net cash inflows (ANCI) of $25,000.Program B is estimated to cost $250,000 to
implement and have ANCI of $75,000.Program C is estimated to cost $600,000 to
implement and have ANCI of $125,000.Program D is estimated to cost $125,000 to
implement and have ANCI of $50,000. Yourselection criteria are based on the shortest
payback period. You recommend that yourcompany select
A) Program C
B) Program A
C) Program B
D) Program D
Explanation:
The payback period can be determined by
dividing the initial fixed investment in theprogram by the estimated annual net cashinflows. In this example, the payback period
for Program D is 2.5 years, so it should beselected.
Program Management Professional (PgMP)
Examination Specification, p. 17
Question:
[QID: 6458] A best practice in program
management is to identify and documentlessons learned throughout the program as it
moves through the various phases of its lifecycle. The next step in this process is to
A) Have experts examine each one to
determine whether it should be included inthe organizations process asset library
B) Appoint one of the core program teammembers as a knowledge broker to pass on
these lessons learned
C) Analyze and archive them as part of
the Closing Process Group
D) Formally document these lessons
learned in the knowledge management
system
Explanation:
Lessons learned are an output of manyprogram management processes. Theyshould be identified during the life of the
program and should be inputs to the CloseProgram process, where they are analyzed
and archived.
The Standard for Program Management, p.39
-
8/6/2019 Practice Test 1 Results
7/75
15/03/11 1:44 PMprint.html
Page 7 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
Question:
[QID: 6584] You are managing a programthat lengthened existing icebreaker vessels
so that they could be used in the waterssurrounding Antarctica. During extensive
testing off the coast of Labrador, the vesselsperformed well, and the reliability and
maintainability (R&M) data were well withinan acceptable variance range. Many of the
vessels are now in use off the coast ofAntarctica, and the R&M data have a much
wider range of variance; however, vessel
performance remains acceptable. It is nowtime to close the program. You need to
A) Support corrective actions as required
B) Leave in place a legacy of operational
benefits sustainment
C) Continue to provide governance
oversight
D) Track all benefits even after the
program closes
Explanation:
The Closing Process Group formalizesacceptance of the products, services, or
results that define the programs successfulcompletion. It is intended to leave in place a
legacy of operational benefits sustainment,thus deriving optimal value from the
programs objectives.
The Standard for Program Management, pp.6667
Question:
[QID: 6520] After the program benefits arerealized, it is important to ensure that they
are sustained after they are transferred tothe organization. This is the purpose of the
A) Transition Realization process
B) Program road map update
C) Program transition plan
D) Transition Monitoring and Controllingprocess
Explanation:
The program transition plan enumerates all
necessary actions that are required totransfer the program from a development
state to an operational state pendingapproval that all requirements are complete.
It is an output of the Develop ProgramManagement Plan process.
The Standard for Program Management, p.
83
Question:
[QID: 6508] The contractor working on your
program is losing money on the contractand asks that you terminate the agreement.
She says that if you do not, she will simplystop working because she cannot afford to
continue. If she does stop work, she will
A) Terminate the contract for convenience
-
8/6/2019 Practice Test 1 Results
8/75
15/03/11 1:44 PMprint.html
Page 8 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
B) Default and be subject to legal action
C) Be held in contempt of court
D) Terminate the contract for cause
Explanation:
When a contractor refuses to performaccording to the terms and conditions of a
contract, he or she is in default and issubject to legal action. Although it is
unfortunate that the contractor is notmaking money on the program, that is not
grounds for refusing to live up to her end ofthe agreement. The organizations contractclosure procedure, a tool and technique in
the Close Program Procurements process,outlines the requirements for contract
termination, including verification criteria toprotect the organization from breach of
contract.
The Standard for Program Management, p.205
Question:
[QID: 6450] As the manager of a newprogram to develop the next-generation
heating, ventilation, and air-conditioning(HVAC) system, you establish a process to
monitor your program benefits. Following thestandard benefits management life cycle,
you develop this process during the
A) Benefits identification phase
B) Benefits analysis and planning phase
C) Benefits realization phase
D) Benefits monitoring phase
Explanation:
A process for benefits monitoring is
established in the benefits realization phase.At this time, the program manager and theteam establish the structure in which workwill occur as well as the technical
infrastructure to facilitate the work. Thisincludes establishing a framework to monitor
and control the projects and to measureprogram benefits.
The Standard for Program Management, pp.20 and 84
Question:
[QID: 6583] You are a program manager on
an international program that relies oncontractors for approximately 75 percent of
its work. Some of the contracts apply to a
specific project, but five contracts span sixof the projects. You have one basic orderingagreement, which enables you to obtain
temporary resources as required for thiscomplex program. In terms of the
Administer Program Procurements process,you should review the
A) Procurement register
B) Change requests
C) Program reports
D) Contract management plan
-
8/6/2019 Practice Test 1 Results
9/75
15/03/11 1:44 PMprint.html
Page 9 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html
Explanation:
The contract management plan is used toadminister contracts for significant purchasesand acquisitions. It covers contract
administration activities throughout the lifeof the contract and is used effectively to
manage a variety of suppliers. It is a tooland technique of the Administer Program
Procurements process.
The Standard for Program Management, p.201
Question:
[QID: 6566] You are an executive with amajor recording studio. Four new groups
have auditioned for a record contract, butyou can select only one. The program to
launch any group consists of Web sitedevelopment, music videos, a nationwide
tour, T-shirts, and a fan club. Your head ofMarketing has done a net present value
(NPV) for each group. Which do you choose?
You recommend that your company select
A) Group C
B) Group D
C) Group A
D) Group B
Explanation:
Using net present value (NPV) as a selectioncriterion, a dollar a year from now is worth
less than a dollar today. The more the futureis discounted (that is, the higher the
discount rate), then the lower the NPV ofthe program. If the NPV is higher, then the
program is rated higher than others. In this
example, Group C has the highest NPV andshould be selected.
Program Management Professional (PgMP)
Examination Specification, p. 17
Project Management ToolBox: Tools and
Techniques for the Practicing Project
Manager, pp. 4344
Question:
[QID: 6581] You are the program manager
for development of a next-generationpersonal digital assistant (PDA) that can be
used on computers, airplanes, trains, andphones. You determine the programs
financial framework as part of the
A) Develop Program Infrastructure process
B) Initiate Program process
C) Establish Program Financial Framework
-
8/6/2019 Practice Test 1 Results
10/75
15/03/11 1:44 PMprint.html
Page 10 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
process
D) Develop Program Financial Plan process
Explanation:
The purpose of this process is to assess theoverall financial environment for the
program and to identify funding sources forthe identified milestones. The key output is
the program financial framework chart.
The Standard for Program Management, pp.207 and 213
Question:
[QID: 6577] To identify risks that couldaffect your program, you and your core
program team clarify the definition of eachrisk and group them by cause. You are using
which of the following techniques?
A) Flowcharts
B) Root cause identification
C) SWOT analysis
D) Influence diagrams
Explanation:
Root causes are the fundamental conditions
or events that may give rise to a risk.Program-specific risk activities include
determining the primary causes of a
programs risks, which can be done bysharpening the definition of each risk andgrouping risks by cause. More effective risk
responses can be prepared after the rootcauses are identified.
The Standard for Program Management, p.
167
Question:
[QID: 6477] Your client has not paid its last
invoice of 500,000, and it is now more than90 days overdue. Your companys accounting
policy states that any invoice that is morethan 90 days late becomes bad debt. You
now need to
A) Update your cost management planB) Take corrective action
C) Rebaseline your budget
D) Issue a change request
Explanation:
Bad debt is money that is not collectible and
is therefore worthless. As a result, it isdeemed an expense to the business rather
than revenue, because the business incurredthe expense of providing a service or
product for which it was not paid. Inresponse to this problem, you need to take
corrective action, which is an output of theMonitoring and Controlling Program
Financials process.
The Standard for Program Management, p.226
Question:
-
8/6/2019 Practice Test 1 Results
11/75
15/03/11 1:44 PMprint.html
Page 11 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
[QID: 6504] To ensure that the programs
benefits are delivered as intended, specificmetrics and measurement approaches arerequired. These are stated in the
A) Program management plan
B) Program charter
C) Benefits realization plan
D) Programs business case
Explanation:
The benefits realization plan is part of the
Planning Process Group. It includes metrics
and measurement approaches for theintended benefits from the program and fortheir delivery.
The Standard for Program Management, p.
31
Question:
[QID: 6570] In a program performance
meeting, you asked the project manager ofProject A what the status was. She
responded by saying that the total projectbudget of $600,000 was evenly allocated
over the projects six-month life. She hasjust completed the second month of the
project and has finished 50 percent of thework. What earned value method
information is available thus far?
A) Earned value and planned value
B) Planned value
C) Earned value
D) Actual costs
Explanation:
For the earned value (EV) of the project,
note that half the work has been completed,for an EV of $300,000. The planned value
(PV) through month two is $200,000.Remember that the estimate was $600,000
spread evenly over six months (or$100,000/month).
The Standard for Program Management, p.
133
The Project Management Drill Book: A Self-
Study Guide, Chapter 1
Question:
[QID: 6445] To be successful, benefitsmanagement must begin when
A) The business case is approved
B) The program is initiated
C) The program is defined
D) Each project is selected
Explanation:
Although benefits management evolves asthe program continues through its phases, it
should begin when the program is initiated,in the Pre-Program Preparations and
Program Initiation phases of the program lifecycle.
-
8/6/2019 Practice Test 1 Results
12/75
15/03/11 1:44 PMprint.html
Page 12 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
The Standard for Program Management, p.
20
Question:
[QID: 6594] You are managing a program toestablish a new distribution center. The
facilitys location was selected because laborcosts were low, but it is in a remote area.
Now gasoline prices have increased 30percent and are forecasted to rise another
20 percent in the next six months. In
planning for the procurement oftransportation services, you need to
A) Prepare a contract management plan
B) Recommend to your sponsor that the
program be terminated and the distributioncenter be moved to a more urban area
C) Prepare a competitive analysis ofservice providers
D) Encourage bidders by providingsimplified legal requirements in the form ofstandard terms and conditions
Explanation:
In the Plan Program Procurement process, a
competitive analysis of service providers is atool and technique to identify those suppliers
that provide specific products and services.
The Standard for Program Management, p.189
Question:
[QID: 6481] You are a program manager for
a city transit authority. Your program has anumber of projects under way to upgrade
the infrastructure to current technologies
and to implement a process improvementprogram. The transit authoritys chieffinancial officer (CFO) has left to assume a
position in a different city, and a new personhas been appointed CFO. You should
A) Take no action at this time
B) Appoint one of your core teammembers to interact with the new CFO
C) Update your stakeholder inventoryD) Meet with the new CFO when it is
convenient, because the CFO is not a
primary stakeholder in your program
Explanation:
As program manager, you manage thestakeholder inventory throughout the
program and take appropriate action to
handle any changes that may occur.Although the CFO may not be a primarystakeholder, he or she is important to the
program and cannot be overlooked.
The Standard for Program Management, pp.
235 and 238
Question:[QID: 6546] Because of the strategic nature
of programs, it is easy to confuse thecharacteristics of benefits, objectives, and
-
8/6/2019 Practice Test 1 Results
13/75
15/03/11 1:44 PMprint.html
Page 13 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
success criteria. A benefit can best be
characterized as
A) An improvement in an organizations
operation
B) The voice of the customer (VOC)
C) The importance of the program
D) What the individual programs projectsare designed to achieve
Explanation:
A benefit is an improvement to the operation
of an organization. Benefits may include
increased profits, improved growth, orimproved employee morale.
The Standard for Program Management, p.309
Enterprise Program Management Delivering
Value, p. 178
Question:
[QID: 6580] You are assuming a position in
a company that has not had muchexperience with program management. You
will be leading the program team andperforming a business function for your
program. The business case has alreadybeen made, and the program is scheduled to
move into the Program Initiation phase. Asthe program manager, your most importantcompetency is
A) Communication
B) Strategic visioning
C) Political skills
D) Leadership
Explanation:A successful program manager must have a
special blend of knowledge, skills, andcompetencies. The most important is
communication skills to deal with all programstakeholders.
The Standard for Program Management, pp.
1213
Question:
[QID: 6439] One purpose of review by the
programs governance board is to
A) Manage the program resources
B) Identify how many project managers
have earned their PMPs
C) Direct program communications withthe public at large
D) Initiate another project into the
program
Explanation:
Reviews by the programs governance boardare an opportunity for senior management
to assess program performance before theprogram moves to the next phase or before
another project is initiated in the program.This process can occur during any program
phase except closing. The criteria for
-
8/6/2019 Practice Test 1 Results
14/75
15/03/11 1:44 PMprint.html
Page 14 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
approval are defined in the governance plan.
The Standard for Program Management, p.257
Question:
[QID: 6483] You are managing agovernment program that is responsible for
regulatory initiatives in food additives.Several people both inside and outside your
agency have questioned why the agency set
these initiatives up as a program rather thanas a series of individual projects, as hasbeen done in the past. They are complaining
that it is just more bureaucracy. You explainthat
A) Your focus as program manager is to
reduce resistance to change
B) You will be managing technicians and
specialists from scientific, regulatory, andlegal units in the agency
C) Because the projects support a diverseset of clients, integrated stakeholder
management is critical
D) The individual projects in the area of
food additive regulations have numerousinterdependencies and are best managed as
one initiative
Explanation:It is essential to determine why anorganization elects to use a program
structure rather than focus on projectmanagement. One of the criteria is whether
interdependencies on deliverables amongprojects will create a set of benefits. If so, a
program is recommended.
The Standard for Program Management, p. 6
Question:
[QID: 6597] Most programs involve cross-
disciplinary as well as cross-cultural teams.Program managers must be able to obtain
resources from various functional units andgeographies and must also direct and
coordinate the work of individual functionalteams across time and distance. This shows
the importance of which of the followingprogram management skills?
A) Leadership
B) Communication
C) Strategic visioning
D) People skills
Explanation:
The program manager leads interdisciplinary
teams as well as functional teams. Programsrequire resources, and the program managermust be able to obtain needed resources
from functional organizations. Strongleadership skills are critical to the successful
management of multiple program teamsthroughout the life cycle.
The Standard for Program Management, p.
13
-
8/6/2019 Practice Test 1 Results
15/75
15/03/11 1:44 PMprint.html
Page 15 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
Question:
[QID: 6507] As program manager for
development of a next-generation catalyticconverter, you decide to use an issue
register. After each issue is identified, yourcore program team records it in this register.
The next step is to
A) Subject the issue to analysis by a
reviewing authority
B) Appoint a member of the program team
to resolve the issueC) Refer the issue to the head of the
program management office (PMO) for
analysis and tracking
D) Ask the person who raised the issue to
propose a resolution
Explanation:
After an issue is identified, it should be
recorded in the issue register. The next stepis to subject it to analysis by a reviewingauthority or board. Issue reviews should be
conducted regularly.
The Standard for Program Management, p.96
Question:[QID: 6561] Because of their size,complexity, and duration, programs tend to
be more important than projects in mostorganizations, and program managers tend
to interact more with senior management,often through the governance board or
steering committee that oversees theprogram. Throughout the program, it is
especially important to monitor and controlprogram changes. A useful tool and
technique is
A) Impact analysis
B) Program metrics
C) Change request log
D) Change register
Explanation:
Impact analysis is a tool and technique in
the Monitor and Control Program Changesprocess, which explores the effect of the
proposed changes on the program. Itassesses the accuracy of any assumptions
and identifies the potential risks and benefitsthat possible changes may have on the
component projects.
The Standard for Program Management, p.269
Question:
[QID: 6515] The stakeholder analysis is akey tool and technique in program
management. To conduct such an analysis,the first step is to hold interviews, use focus
groups, and perhaps conduct a survey. Thisapproach enables you to
-
8/6/2019 Practice Test 1 Results
16/75
15/03/11 1:44 PMprint.html
Page 16 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
A) Identify stakeholders attitudes toward
the program
B) Prioritize stakeholders in terms of their
ability to influence the programC) Develop a stakeholder register
D) Develop a stakeholder communications
strategy
Explanation:
Stakeholder analysis is a tool and techniquein the Plan Program Stakeholder
Management process that is used to gain anunderstanding of the organizational culture
and the stakeholders needs andexpectations. Often this process is done
through interviews, focus groups, andquestionnaires and surveys.
The Standard for Program Management, p.
230
Question:
[QID: 6505] You have just completed the
program work breakdown structure (PWBS)for a program to develop a new line of scubaequipment. Your next step is to
A) Generate the program schedule
B) Develop the program scope definition
C) Negotiate for team members
D) Identify key milestones
Explanation:
Upon completion of the program work
breakdown structure (PWBS), realisticschedules can be built, cost estimates can be
developed, and the programs work can beorganized.
The Standard for Program Management, p.114
Question:
[QID: 6446] A key characteristic of the
program management life cycle is that it
A) Ends with the delivery process
B) Follows a repeatable processC) Focuses first on benefits realization
D) Is nonsequential
Explanation:
The program life cycle is nonsequential.Throughout the life cycle, components aremobilized as appropriate so that a stream of
deliverables focuses on facilitating new
operations and benefits.
The Standard for Program Management, p.
18
Question:
[QID: 6448] Your program to develop the
next-generation helium automobile has been
completed. In retrospect, you recognize thatyour companys standard programgovernance structure was not effective, as
-
8/6/2019 Practice Test 1 Results
17/75
15/03/11 1:44 PMprint.html
Page 17 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
more gate reviews were needed during the
Delivery of Program Benefits phase. Yourecommend that the enterprise programmanagement office (EPMO) reassess the
program life cycle and the role of thegovernance board. This is an example of a
A) Lesson learned
B) Mistake
C) Best practice
D) Good practice
Explanation:
In the closing phase, the program managerand team may provide feedback andrecommendations on areas that are outside
the scope of the program but could benefitthe organization in the future.
The Standard for Program Management, p.
30
Question:
[QID: 6517] One of the major purposes of
the Manage Program Issues process is toidentify, track, and close issues so that
stakeholder expectations are aligned withprogram activities and results. This
alignment can be accomplished by severalmethods, including
A) Performing program scope analysis
B) Leveraging opportunities
C) Adjusting enterprise environmental
factors
D) Adjusting program priorities
Explanation:
It is important that the program manager
ensure that stakeholder activities are alignedwith the programs activities and
deliverables. Issues may be sent to programrisk management, program governance, or
program scope management. When issuesare sent to program scope management,
then it is important to determine the effectthat such issues have on the programs
scope.
The Standard for Program Management, p.96
Question:
[QID: 6596] You are managing a programwhose budget at completion (BAC) is
420,000. The program is 10 percent
complete and has an earned value of42,000. The actual costs (AC) are 50,000.This means that
A) The program is over budget by
8,000, which is a major problem
B) Although the program is over budget,the overrun is insignificant at this time
C) The CV is 378,000, and immediate
action is necessary
D) You need to calculate a new estimate
to complete (ETC)
-
8/6/2019 Practice Test 1 Results
18/75
15/03/11 1:44 PMprint.html
Page 18 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
Explanation:
The cost variance (CV) is calculated bysubtracting the actual cost (AC) from theearned value (EV); that is, CV = EV AC, or
42,000 50,000 = 8,000, which isinsignificant compared to the budget at
completion (BAC).
The Standard for Program Management, p.133
PMBOK Guide, p. 182
Question:
[QID: 6599] You are Company As programmanager for the development of an online
banking system for your community bank,for which your company will receive $20
million. However, the bank is so interested inimplementing this system quickly that it also
contracts with Company B. You mustimplement your system completely in six
months to ensure that you beat CompanyBs schedule. At this point, you have an
expense estimate of $2.5 million. You willlose $10 million if you cannot deliver the
product in six months, but if you cancomplete it sooner, you will earn an
additional $25 million. Your risk managementofficer performs a risk analysis and tells you
that there is a 30 percent chance that thebank will change its requirements and a 70percent chance that the project will be
completed on time or ahead of schedule.Your company has completed similar projects
in the past, and on the basis of theseexperiences, you know that there is a 30
percent chance that your final expenses willincrease by $10 million. If no risks occur,
the value of your program will be
A) $29 million
B) $17.5 million
C) $2.5 million
D) $42.5 million
Explanation:
Decision-tree analysis is a technique of theAnalyze Program Risks process. It shows the
situation and the implications of each of theavailable choices. It also provides the
expected monetary value for the variousalternatives. If no risks occur, the value of
your program would be calculated as follows:$20m $2.5m = $17.5m.
-
8/6/2019 Practice Test 1 Results
19/75
15/03/11 1:44 PMprint.html
Page 19 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
The Standard for Program Management, pp.172174
Question:
[QID: 6600] You will need a number ofdifferent types of supplies and services to
support your program and its componentprojects. Many different techniques can be
used to evaluate proposals that aresubmitted. All use
A) Weighting systems
B) Expert judgment
C) Predefined weightings
D) Screening systems
Explanation:
Proposal evaluation systems are a tool and
technique in the Conduct Program
Procurements process. Although a number ofdifferent approaches can be used, all useexpert judgment and evaluation criteria.
The Standard for Program Management, p.195
Question:
[QID: 6572] You and several members ofyour team are developing your benefits
realization plan. Everyone is focused onemploying a set of benefits measurement
techniques that will provide substantiveinformation to all stakeholders. Of the
following, which is an example of a benefitsmeasurement technique?
A) Net present value (NPV)
B) Balanced scorecard
C) Value engineering
D) Internal rate of return (IRR)
Explanation:
The balanced scorecard is a benefits
measurement technique that includes a setof performance measures. These measures
cover a range of areas that reflect and show
a balanced view of organizationalperformance. Internal rate of return (IRR)and net present value (NPV) are financial
analysis techniques, and value engineering isa technique used to reduce costs in product
development.
Program Management Professional (PgMP)
Examination Specification, p. 17
Question:
[QID: 6441] You are the program manager
on a highly controversial e-mail retentionprogram. More than 75 percent of the
organization is opposed to the programbecause it means that all their e-mail
messages will be archived and reviewed for
inappropriate, unethical, or illegalstatements. You know that there will bemany conflicts as you and your team
-
8/6/2019 Practice Test 1 Results
20/75
15/03/11 1:44 PMprint.html
Page 20 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
execute the component projects. You inform
your team that, in the case of any conflict,the first point of escalation is
A) The program sponsor
B) The program director
C) The program governance board
D) You, the program manager
Explanation:
Program managers are the escalation pointfor issues, changes, risks, interfaces, and
dependencies. As program manager, you
must manage relationships, resolve conflicts,and deal with the political aspects ofstakeholder management.
The Standard for Program Management, pp.
11 and 13
Question:
[QID: 6494] Your program is being audited
by the enterprise program managementoffice (EPMO). One of the audit team
members wants to know what documentdescribes the responsibility for delivery of
the intermediate and final program benefits.You tell him it is in the
A) Benefits realization plan
B) Business caseC) Benefits identification plan
D) Benefits analysis plan
Explanation:
The benefits realization plan includes theresponsibility for delivery of the intermediate
and final program benefits. Benefitsmanagement is a continuous process that
assesses the value of the programs benefitsas well as the interdependencies that exist
between benefits in the programs projects.It also assigns responsibility and
accountability for benefits realization.
The Standard for Program Management, pp.3031
Question:
[QID: 6487] You are the program managerfor a water-alleviation program that requires
extensive equipment. Some of thisequipment represents new technology. As
the program manager, you are preparingregular program performance reports, and
each one discusses this equipment. A useful
program performance analysis tool andtechnique to identify potential issues withthis untested technology is
A) Forecast data
B) Risk analysis
C) Program metrics information
D) Audit requirements
Explanation:
Program performance analysis, a tool andtechnique of the Monitor and Control
Program Performance process, includes gap
-
8/6/2019 Practice Test 1 Results
21/75
15/03/11 1:44 PMprint.html
Page 21 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
analysis, risk analysis, issues analysis, and
trend and probability analysis. Risk analysisemphasizes real-time monitoring of programrisk as critical for success.
The Standard for Program Management, p.
95
Question:
[QID: 6586] Your program is beginning to
miss key milestones because of delays by
your customer, with whom you have acontract. Your goal is to ensure thatcorrections are made as quickly as possible,
so you decide to conduct a contractperformance review earlier than planned.
During this review, you and the customerrealized that there was a deficiency in the
contract. Your next step is to
A) Document the delay and discuss it with
the steering committee
B) Document the causes for the delay andbring it to your attorneys attention
C) Prepare an assignment of claims form
D) Prepare a change request
Explanation:
A contract performance review is a tool andtechnique in the Administer Program
Procurements process. Change requests orrecommended corrective action requestsshould be raised when the performance
problems are the result of a deficiency in acontract.
The Standard for Program Management, p.
202
Question:
[QID: 6563] Because your program has the
highest priority in the organizationsportfolio, your governance board meets each
month and each member receives a weeklystatus report. The executive sponsor
requests these measures to enable him tostay current on program activities and assist
you with any issues that need resolution.Your customer also requests monthly
meetings and a weekly teleconference. Toensure that your list of these meetings and
communications is up-to-date, you shoulddevelop a(n)
A) Information reporting schedule
B) Communications log
C) Communications capability matrixD) Information distribution plan
Explanation:
The communications log is an output of thePlan Communications process. It identifies
the who, what, when, how, and why foreach form of communication. After the
communications framework has beendeveloped and agreed to, the next step is to
identify and put into place the components(that is, the processes and technical
elements) that will enable the
-
8/6/2019 Practice Test 1 Results
22/75
15/03/11 1:44 PMprint.html
Page 22 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
communications to be executed.
The Standard for Program Management, p.147
Question:
[QID: 6529] The development of conceptsfor products or services, initial requirements,
time lines, and cost guidelines are examplesof activities performed
A) During the Planning process
B) Before the Initiate Program process
C) During the Initiate Program process
D) Concurrently with the business case
Explanation:
A number of activities are typically
performed before the program is initiated.These activities result in the development of
concepts for products and services, scopeframeworks, initial requirements, timelines,
deliverables, and guidelines regardingacceptable costs. These activities are
required to determine the business case forthe program and to seek approval from the
governance board or comparable body.
The Standard for Program Management, p.42
Question:
[QID: 6571] You are a program manager foran aerospace company that is developingthe C888 aircraft. Each of the component
projects is scheduled to end at a differenttime. You establish a product support team
that you will manage as part of your
program responsibilities by providingupgrades during the product life cycle. Suchupgrades are often used in which one of the
following management approaches?
A) Earned value management
B) Program management
C) Operational management
D) Project management
Explanation:
Benefits sustainment may follow a structuredapproach, but it typically does not require
true program management principles tooperate the end product. However, upgrades
to a product often use project managementto design, develop, and implement such
changes.
The Standard for Program Management, p.31
Question:
[QID: 6485] Throughout your program, youmeet regularly with members of theprograms governance board at phase-gate
reviews. These meetings are necessarybecause they provide the board and other
interested stakeholders an opportunity to
-
8/6/2019 Practice Test 1 Results
23/75
15/03/11 1:44 PMprint.html
Page 23 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
A) Assess performance of the program
against expected outcomes
B) Review program performance
C) Focus on the phase that was justcompleted to determine whether the nextphase should begin
D) Assess performance against the needto realize and sustain program benefits for
the long term
Explanation:
Phase-gate reviews serve numerouspurposes and should be held throughout the
program. They focus on the phase that wasjust completed and result in go/no-go
decisions. However, these sessions are not asubstitute for periodic program performance
reviews.
The Standard for Program Management, p.22
Question:
[QID: 6435] You are preparing for a meetingof your governance board. You have learnedthat it is a best practice to meet in advance
with two board members to ensure that theyconcur with what you plan to present. Board
Member A says that your approach on somerecent issues was not in line with the
benefits realization plan, and she is upsetwith your performance. Board Member B
says that he is pleased with your work; hethinks that you are realizing the benefits
outlined in the benefits realization plan. Onthe basis of these two advance meetings,
you
A) Report the problem to the benefits
managerB) Continue with the governance board
meeting as scheduled, because you have
Board Member Bs support
C) Work with your program team to
address Board Member As concerns beforethe governance board meeting
D) Cancel the meeting to fully addressBoard Member As concerns
Explanation:
You should proceed with the scheduledgovernance board meeting but be preparedto address Board Member As concerns.
Benefits are achieved in a cumulativemanner. At the meeting, you can discuss the
deliverables that have met requirements anddescribe the benefits that have been realized
to date. Noting Board Member As concerns,you can identify any risks that might affect
the program and describe how you plan tomitigate them.
The Standard for Program Management, pp.
58 and 236
Question:[QID: 6575] Every program is planned on
the basis of a set of hypotheses, scenarios,or assumptions. As a newly appointed
-
8/6/2019 Practice Test 1 Results
24/75
15/03/11 1:44 PMprint.html
Page 24 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
program manager, you ask one of your core
program team members to explore thevalidity of these assumptions and to do soperiodically as a way to identify risks. This is
important as part of the
A) Risk monitoring function
B) Issue management activities
C) Risk analysis options
D) Risk response analysis
Explanation:
Risk monitoring includes evaluation of
whether program assumptions remain valid.This function is ongoing throughout the lifeof the program as part of the Monitor and
Control Program Risks process.
The Standard for Program Management, p.180
Question:
[QID: 6462] At the program level, analysisof change requests involves identifying,
documenting, and estimating the work thatthe change would entail. In addition, as
program manager, you must
A) Convene a meeting of the projects
configuration control board
B) Meet with the program governanceboard for approval, rejection, or deferral ofthe request
C) Prepare a status report
D) Determine whether updates to theprogram document repository are needed
Explanation:
Changes affect the various program-level
processes. As part of the Monitor andControl Program Scope process, updates to
the document repository may be requiredbased on the nature of the change.
The Standard for Program Management, p.
124
Question:[QID: 6482] You are the program manager
for the development of a new slot machinefor the Sand Dunes casino in Macau. Your
organization operates with a balanced matrixorganizational structure, and you have
resources supporting your program from avariety of functional departments. Some of
these people report to you as well as to
their respective departmental managers. Youhave a cost accounting system in whicheveryone charges time to appropriate
account codes. Because your program isclose to completion, you need to
A) Close the program budget to avoidnon-allocable charges
B) Use the management reserve to payany additional charges
C) Integrate this cost accounting system
with the project management informationsystem (PMIS)
-
8/6/2019 Practice Test 1 Results
25/75
15/03/11 1:44 PMprint.html
Page 25 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
D) Issue a change request to close the
program management plan
Explanation:
As an output of the Monitor and ControlProgram Financials process, the program
budget is closed as the program comes to aclose, the final financial reports are
distributed in accordance with thestakeholder management plan, and any
unused funds are returned to the fundingorganization.
The Standard for Program Management, p.226
Question:
[QID: 6558] You are managing a program to
develop a new source of energy in theextreme northern latitudes when solar power
is not available. Working with your core
program team and your governance board,you have identified a number of component
projects. Your company has several keyprojects under way, and resources will be
difficult to acquire for this new program. Indetermining whether you will use internal or
external resources, you should consider
A) Your ability to negotiate with functional
managers for the needed staffB) The availability of off-shore employees
to drive down costs
C) The availability of key staff members
D) Previous work by the staff as asuccessful team
Explanation:
Resource availability indicates the availability
of the personnel, assets, materials, or capitalresources that are required to accomplish
the programs goals. It is an input to theManage Program Resources process.
The Standard for Program Management, p.
92
Question:[QID: 6454] You are managing a program
that includes 15 component projects. Thebenefits expected from each project shouldbe defined in the
A) Program benefits identification phase
B) Project business case during the Pre-Program Preparations phase
C) Program benefits realization phaseD) Project business case before the
project is initiated
Explanation:
Projects are typically initiated and executed
in the Delivery of Program Benefits phase.Projects should not be initiated without
having a business case that describes thebenefits the project will provide.
The Standard for Program Management, p.
257
-
8/6/2019 Practice Test 1 Results
26/75
15/03/11 1:44 PMprint.html
Page 26 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
Question:
[QID: 6587] You are a member of your
organizations Program Selection Committee,which is conducting an off-site meeting to
review the companys five major strategicgoals, all of which are weighted equally.
Goal 1 is to produce the highest possiblequality products; goal 2 is to provideoutstanding customer relationship
management; goal 3 is to reduce reliance onexternal supply sources and maximize
internal resources; goal 4 is to reducemanufacturing costs; and goal 5 is to
maximize productivity. You are consideringfour programs and will recommend one to
the CEO. Program A partially supports goal1, fully supports goals 2, 3, and 4, and does
not support goal 5. Program B fully supportsgoals 1, 3, 4, and 5, but does not support
goal 2. Program C fully supports goals 1 and
2, partially supports goals 3 and 4, but doesnot support goal 5. Program D partiallysupports goals 1, 2, and 5, and fully
supports goals 3 and 4. Considering thisinformation, your recommendation should be
to select
A) Program D
B) Program A
C) Program BD) Program C
Explanation:
Programs should have a strategic fit with theorganizations long-term goals. In selecting aprogram to pursue, this is one area to
consider. In this example, Program B fullysupports four of the five goals.
The Standard for Program Management, p.23
Program Management for Improved Business
Results, p. 286
Question:
[QID: 6564] You have staffed your program
team with a variety of in-house staffmembers, selected consultants, and severalnew full-time employees. It is now time to
A) Prepare your resource management
plan
B) Prepare your team development plan
C) Update your program resource plan
D) Update your staffing management plan
Explanation:
The output of the Manage ProgramResources process is the updates to the
program resource plan. Changes in theassignment of program staff are reflected in
this update.
The Standard for Program Management, p.
93
-
8/6/2019 Practice Test 1 Results
27/75
15/03/11 1:44 PMprint.html
Page 27 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
Question:
[QID: 6544] You are the legacy systemconversion program manager in yourcompany. You need to update the companys
business development/sales tracking system,which was developed in C++. Your
governance board recognizes the importanceof including this project in your program and
asks you to prepare a cost estimate for thisnew project. The board approves your
estimate. As part of the programs Monitorand Control Program Financials process,
you
A) Update the program budget baseline
B) Prepare a resource management plan
C) Identify staffing needs
D) Revise the cost management plan
Explanation:
As an output of the Monitor and ControlProgram Financials process, updates to the
program budget baseline are needed whenthere are significant cost impacts. These
updates are communicated to programstakeholders as appropriate.
The Standard for Program Management, p.
226
Question:[QID: 6532] Transition planning is the keyto benefits sustainment in program
management. As a program manager, yourecognize the importance of ensuring that
component transition requests are prepared.This preparation is done during the
A) Transition Planning process
B) Develop Program Management Planprocess
C) Direct and Manage Program Executionprocess
D) Transition Execution process
Explanation:
The Direct and Manage Program Execution
process is concerned with managing theexecution of the program management plan.
It receives transition requests and sendsthem to the governance board for gate
transition approval.
The Standard for Program Management, pp.8690
Question:[QID: 6466] As executive sponsor of a majorprogram to restore coral reefs off the coast
of the Maldives, you have observed conflictbetween the program manager and herproject managers, stakeholders, and peers.
Although the conflict is manageable, you areconcerned about her long-term future with
the organization. She is a very bright andtalented individual, and you want to keep
her in the organization. Therefore, you
A) Have her go through a 360-degree
-
8/6/2019 Practice Test 1 Results
28/75
15/03/11 1:44 PMprint.html
Page 28 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
feedback analysis
B) Assign her a personal coach to uncoverthe causes of conflict
C) Tell her to take a well-deservedvacation to reduce her stress level
D) Send her to a training class on conflictmanagement
Explanation:
A 360-degree feedback analysis is anexcellent mechanism to look broadly at a
persons management, leadership, andinterpersonal skills. It can provide anexcellent foundation for future development
as well as providing key insights by thepeople that work with her on a daily basis.
Program Management Professional (PgMP)
Examination Specification, p. 34
Question:
[QID: 6434] You have been appointed
program manager for Program XYZ. Youhave assembled your team and have begun
work on your benefits realization plan. Theperson who wrote the plan delivered it to
you. After you read it, you told the teammember that the plan was missing a key
component. It did not describe
A) An assessment of the value andorganizational impact of the program
B) A method to identify interdependenciesof benefits within program components
C) How the potential impact of anyplanned program change affects the benefits
outcome
D) A way to link the outputs to the
planned program outcomes
Explanation:
There are a number of key components inthe benefits realization plan, which is
prepared in the Define Program Goals andObjectives process and maintained
throughout the program. Two keycomponents are to ensure that the program
is managed in a way that satisfies the use of
the programs outputs and to link theoutputs to an outcome of the program. Eachbenefit should be specific, measurable,
actual, realistic, and time-based (SMART).
The Standard for Program Management, p.109
Question:[QID: 6518] You have been appointedclosing manager for a program that has been
under way for eight years. You have metwith the program manager to talk about
lessons learned. You have also met with thecore program team members and reviewed
the lessons learned that were documentedby each of the six projects in this program.
Your next step is to
A) Index each projects records
B) Assign metadata tags to the records so
-
8/6/2019 Practice Test 1 Results
29/75
15/03/11 1:44 PMprint.html
Page 29 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
they can be easily located using a content
management system
C) Select the key lessons learned and
archive themD) Archive all the lessons learned
Explanation:
Although only selected lessons learned may
be incorporated into the programs finalreport, all lessons learned and program-
related documents should be archived sothat they can be considered and used in
future programs.
The Standard for Program Management, pp.30 and 100
Question:
[QID: 6536] The Plan and Establish ProgramGovernance process is crucial to program
success. During this process, the programsgovernance goals are identified, and the
governance roles and responsibilities aredefined. A key input to this process is the
A) Benefits realization plan
B) Scope management plan
C) Stakeholder analysis chart
D) Program work breakdown structure(PWBS)
Explanation:
Each program is expected to deliver certain
benefits that may be tangible or intangible.Benefits realization planning is part of the
Initiate Program process. The benefitsrealization plan, which is an output of the
Define Program Goals and Objectivesprocess, defines each benefit and explains
how it is to be realized, maps the benefits tothe programs outcomes, provides a way to
measure benefits, describes roles andresponsibilities, includes a communications
plan, and notes transition to ongoingoperations and benefits sustainment. It is a
key input to the Plan and Establish ProgramGovernance and Plan Program Quality
processes.
The Standard for Program Management, pp.3031, 109, and 244
Question:
[QID: 6601] You are managing thedevelopment of a series of heating,
ventilation, and air-conditioning (HVAC)
products. Each product is being managed asa separate project. Because the products willbe completed at different times, you have a
product support group. Your team has alsoestablished a configuration managementsystem as a subsystem of the overall project
management information system (PMIS).Changes have been requested to the product
that was delivered in Project A. Thesechanges affect the product from Project B,
which is in production. You focus on
A) Ensuring that support is properly
-
8/6/2019 Practice Test 1 Results
30/75
15/03/11 1:44 PMprint.html
Page 30 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
scheduled for Project B
B) Conducting a thorough audit andextensive testing of future products before
they are deliveredC) Responding to customer complaints
regarding the product already delivered fromProject A
D) Ensuring that a policy of zero defects isimplemented as part of the quality
assurance and control activities
Explanation:
After a product is deployed, any supportmust be scheduled to avoid interruption to
the customers use of the item to thegreatest extent practicable.
The Standard for Program Management, p.
32
Question:
[QID: 6473] It is important to develop a
high-level plan to initiate a program. Such aplan is developed
A) In the Program Initiation phase
B) As part of the high-level business casefor the program
C) By the executive sponsor
D) In the Pre-Program Preparations phase
Explanation:
The high-level plan to initiate the program isdeveloped in the Pre-Program Preparations
phase. It shows how the program will mapto and deliver strategic objectives, and how
those objectives align with organizationalgoals.
The Standard for Program Management, p.23
Question:
[QID: 6551] Of the following key initiatives,which would benefit by being managed as a
program?
A) Expanding a ski areaB) Setting up a career path for people in
the project management profession
C) Upgrading the nations airspace system
D) Introducing a new project planning tool
in a large organization
Explanation:
An upgrade to the nations airspace system
would consist of numerous projects as wellas ongoing work. If these projects weremanaged in a coordinated way, then you
would have better control over them andwould obtain greater benefits.
The Standard for Program Management, p. 5
Question:[QID: 6543] As program manager, you areresponsible for facilitating and resolving
interproject risks, issues, and constraints.
-
8/6/2019 Practice Test 1 Results
31/75
15/03/11 1:44 PMprint.html
Page 31 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
You want to ensure that your components
remain aligned with strategic directives andthe business case. This is done as part ofyour work on which one of the following
program management processes?
A) Direct and Manage Program Execution
B) Plan Program Risk Management
C) Manage Component Interfaces
D) Identify Program Risk
Explanation:
The Direct and Manage Program Execution
process focuses on managing the executionof the program management plan. Theprimary goal is to deliver the program
benefits based on the component projects.Additionally, the program manager ensures
that each project aligns with the programsbusiness case and strategic directives.
The Standard for Program Management, p.
86
Question:
[QID: 6503] You have been appointed as a
program manager in your automotivecompany for the development of next-
generation vehicles for the model year 2020.You prepare a high-level program plan that
includes all of the following EXCEPT
A) Stimuli that triggered the program
B) Alignment of objectives with theorganization
C) Program objectives
D) The programs end state or vision
Explanation:
The vision is part of the charter preparedduring the Program Initiation phase. The
high-level plan shows the stimuli thattriggered the program, the program
objectives, and how the objectives align withthe organization.
The Standard for Program Management, pp.
2324
Question:
[QID: 6589] The list of deliverables and the
success criteria for the program and itsproducts, services, and results must be
included in the procurement documentationthat is provided to potential suppliers. This
list is derived from an analysis of the
A) Program scope statement
B) Program work breakdown structure
(PWBS)
C) Contract WBS
D) Project work breakdown structure(WBS)
Explanation:
The program scope statement is the basis
for future program decisions, and it definesand articulates the scope of the program. It
also contains a list of the programs
-
8/6/2019 Practice Test 1 Results
32/75
15/03/11 1:44 PMprint.html
Page 32 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
deliverables and success criteria; these
factors require consideration, because theymay need to be included in procurementdocumentation.
The Standard for Program Management, pp.
108 and 187
Question:
[QID: 6573] Each of the projects in your
program prepares a project risk
management plan to describe how riskmanagement is structured. Each projectmanager also prepares risk response plans
for each of the key identified risks. Asprogram manager, you review the risk
response plans to
A) Identify intraproject risks
B) Determine actions that could affect
other components
C) Establish a contingency reserve
D) Establish triggers for the project risks
Explanation:
Program management should support the
risk activities of the program components.The program components risk response
plans should be reviewed to assess proposedactions that could affect the program risk
responses for better or for worse. Thesecomponent plans are an input to the PlanProgram Responses process. This enables
response mechanisms that could benefitmore than one component to be suggested
and implemented.
The Standard for Program Management, p.177
Question:
[QID: 6591] You are preparing for a meetingof your programs governance board. On
your program, you are using earned valuefor monitoring, control, and forecasting. The
planned value is $30,587, and the earnedvalue is $26,365. You are working on a
customer-imposed schedule for thecompletion of the program. Looking at the
schedule variance (SV), you conclude that
A) The budget at completion is $46,475,
but the delays are insignificant
B) The program is behind schedule, andthe tasks on the critical path are affected
C) The SV is 1.16, and it appears that the
schedule will be metD) The SV is $4,222, and the program is
behind schedule
Explanation:
Schedule variance (SV) is calculated by
subtracting the planned value (PV) from theearned value (EV); that is, SV = EV PV. At
this point, the SV is $4,222. The programis behind schedule; however, without
additional information, the effect on thecritical path is not known.
-
8/6/2019 Practice Test 1 Results
33/75
15/03/11 1:44 PMprint.html
Page 33 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
The Standard for Program Management, p.
133
PMBOK Guide, p. 182
Question:
[QID: 6512] You manage a legacy systemconversion program and have identified a
number of issues. Many of them involveCOBOL programming, so you have assigned
them to a COBOL subject matter expert on
your core team. This person owns all theCOBOL issues, which means that he or she
A) Has the authority and means to resolveCOBOL issues
B) Is responsible for all COBOL-relatedproject work
C) Can modify program scope if needed toresolve issues
D) Has been appointed so that no COBOLissues will require resolution at a higher level
Explanation:
The issue owner should have the authorityand means to resolve and close COBOL
issues. If an issue cannot be resolved, thenit should be escalated progressively higher
until resolution is achieved.
The Standard for Program Management, p.96
Question:
[QID: 6554] You are working on a
manufacturing program and need to takeaction in response to a quality control
metric. This metric indicated that the
manufacturing process exceeded establishedparameters. You meet with your programsteering committee and describe the
situation. Your next step should be to
A) Issue a change request
B) Update the Quality Management Plan
C) Allocate to the program a resource whois a certified Six Sigma Black Belt
D) Use the governance decision register
Explanation:
Decisions of the governance board or
steering committee must be formallydocumented because these decisions are
critical feedback used to improve the resultof the components and the program. A
governance decision register is an output of
the Provide Governance Oversight process.
The Standard for Program Management, p.
262
Question:
[QID: 6501] Component projects of theprogram are initiated during the
A) Initiation phase
B) Program Setup phase
C) Planning phase
-
8/6/2019 Practice Test 1 Results
34/75
15/03/11 1:44 PMprint.html
Page 34 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
D) Delivery of Program Benefits phase
Explanation:
Phase four in the program life cycle is the
Delivery of Program Benefits phase. Itspurpose is to initiate the various component
projects in the program and coordinatedeliverables to create the incremental
benefits.
The Standard for Program Management, p.28
Question:
[QID: 6437] As a program is closed, benefitsmanagement focuses on a number of key
initiatives, including
A) Ensuring stakeholder agreement on the
factors contributing to the benefits
B) Prioritizing the value of each of the
program components
C) Ensuring that the benefits delivered arein line with the business case
D) Forecasting the ongoing value of thebenefits
Explanation:
Upon program completion, the benefits
delivered should always be compared against
those identified in the business case toensure that all expected benefits weredelivered.
The Standard for Program Management, p.
31
Question:
[QID: 6541] Commitment of organizationalresources for the initial phases of theprogram is provided
A) After the program charter is approvedby the stakeholders
B) When the benefits realization plan is
issued
C) When the program manager is
appointedD) Before the Initiate Program process
begins
Explanation:
The program mandate, which is preparedduring the Pre-Program Preparations phase,
confirms the commitment of organizationalresources. It also triggers the Program
Initiation phase.
The Standard for Program Management, p.23
Question:
[QID: 6444] When a program is initiated, agovernance board, program board, or
steering committee is typically established.Such program governance falls within the
overall corporate governance of theorganization. The recommended governance
-
8/6/2019 Practice Test 1 Results
35/75
15/03/11 1:44 PMprint.html
Page 35 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
structure is stated in the
A) Benefits realization plan
B) Program charter
C) Business case
D) Program management plan
Explanation:
The primary output of program initiation isthe program charter. Among other things, it
includes the recommended governancestructure to manage, control, and support
the program as well as the governance
structure for the programs components.
The Standard for Program Management, p.
25
Question:
[QID: 6590] As program manager, you keep
all of your stakeholders informed in a timelymanner and you distribute a variety of
different types of information. One type thatis often overlooked is
A) Notification of change requests
B) List of preventive actions
C) Record of training
D) Receipt of proposals
Explanation:During the Distribute Information process,information that is distributed includes
notification of change requests to theprogram and project teams, and eventually,
notification of the responses to the changerequests through use of the change request
log, which contains data on approved,rejected, or modified change requests.
The Standard for Program Management, p.
149
Question:
[QID: 6457] A key member of your program
staff has been complaining lately of thecompanys vacation policies. He would like to
take more time off but has not yet accruedenough time to do so. You are concerned
that he is going to leave the company, soyou monitor his e-mail, in accordance with
company policy, to see whether he issending his resume to other companies. The
act of sending out his resume would becalled a
A) Risk event
B) Misuse of the companys e-mail policy
C) Risk trigger
D) Violation of the companys code ofethics
Explanation:
A risk trigger is a sign that a particular risk
may occur.
The Standard for Program Management, p.180
-
8/6/2019 Practice Test 1 Results
36/75
15/03/11 1:44 PMprint.html
Page 36 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
Dictionary of Project Management Terms, p.
389
Question:
[QID: 6528] You are the program managerfor a six-year program that is in its second
year. To ensure that the benefits realizationplan is on target, you perform a benefits
review of the four projects that are underway. Project B is not achieving the desired
benefits and its deliverables are not being
completed as planned. When you report thisconcern to the governance board, theexecutive sponsor recommends that Project
B be terminated. At the program level, you
A) Conduct a final program review
B) Prepare a report of lessons learned
C) Reassign the project manager forProject B
D) Prepare a transition requestExplanation:
A termination request is an input to the
Approve Component Transition process, andit is required if a project is terminated before
its scheduled completion. A terminationdecision may be the result of a program
benefits review or a change in the externalenvironment. The transition request is also
required for normal project completion.
The Standard for Program Management, p.
270
Question:
[QID: 6567] The Initiate Program process
produces numerous outputs; the two
primary outputs are
A) High-level program plan and benefits
realization plan
B) Program manager identification and
program sponsor identification
C) Benefits identification analysis and
benefits realization plan
D) Program charter and program road
map
Explanation:
The program charter authorizes the program,
whereas the program road map is achronological representation of the programs
stated direction. These two outputs are keyinputs to other program processes.
The Standard for Program Management, p.78
Question:
[QID: 6472] You are the program manager
for a new version of an MP3 player. Theplayers are manufactured by third-partycompanies operating plants in five different
countries. You have been receiving statisticalprocess control (SPC) charts from each
company, and there is indication that theprocess is out of control at one of the
-
8/6/2019 Practice Test 1 Results
37/75
15/03/11 1:44 PMprint.html
Page 37 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
plants. This means that
A) There are supply chain problemscoming from a lack of raw materials
B) There are union problems causingdisruption in the manufacturing line
C) The manufacturer has little control over
how human resources are being deployed
D) The process is not in conformance with
overall quality requirements
Explanation:
A statistical process control (SPC) chart
shows how a process is being executed overtime. A process is deemed out of controlwhen certain measurements exceed
tolerance levels thus affecting quality. ThePlan Program Quality process includes
preparation of the program qualitymanagement plan, which sets, among other
things, quality standards for components.
The Standard for Program Management, pp.256 and 263
Question:
[QID: 6598] As the program managerworking on the development of an advanced
polymer chemical for raincoats, you are inthe process of assessing the feasibility of
your program. In reading the latest industryjournal, you discovered that a competitor isalso entering the marketplace. To assess
your position against that of yourcompetitor, you conduct a
A) Delphi technique exercise
B) Brainstorming session
C) Nominal group technique
D) SWOT analysis
Explanation:
A SWOT (strengths-weaknesses-
opportunities-threats) analysis providesinformation that is helpful when matching an
organizations resources and capabilities tothe competitive environment in which it
operates. It is used in feasibility studies as atool and technique in the Initiate Program
process.
Program Management Professional (PgMP)
Examination Specification, p. 21
The Standard for Program Management, p.
77
Question:
[QID: 6475] An expert in your company will
be needed by two of the projects in yourprogram at approximately the same time.Both project managers have included this
person in their project management plans,resource assignment matrices, and project
schedules. This is an example of
A) An issue to be resolved by thegovernance board
B) An assumption
-
8/6/2019 Practice Test 1 Results
38/75
15/03/11 1:44 PMprint.html
Page 38 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
C) Critical chain analysis
D) A constraint
Explanation:
An assumption is a common input to mostprogram management processes.
Assumptions are considered to be true, real,or certain. In this situation, both project
managers have assumed that this criticalresource will be available as required. The
program manager must work to resolve thissituation, and the resolution should be noted
in the program management plan.
The Standard for Program Management, pp.26 and 38
Question:
[QID: 6478] Your program to develop a 4Gphone is being terminated early because
your competition already has a 4G phonemodel on the market. Your company has
initiated a program to develop a 6GXi phone,and you hope to be assigned to manage this
program. At this point, you
A) Document the current state
B) Appoint a closeout manager
C) Immediately disband your team
D) Archive your records
Explanation:
During the Closing processes, it is important
to demonstrate that the benefits have beendelivered and the scope of work has been
fulfilled. If the program is terminated early,then the current state should be
documented.
The Standard for Program Management, p.66
Question:
[QID: 6500] The program management planincludes a number of subsidiary plans, such
as the
A) Contracts administration planB) Quality assurance plan
C) Benefits management plan
D) Benefits realization plan
Explanation:
This set of plans includes the benefitsrealization plan, which is an output of the
Define Program Goals and Objectives
process. Benefits realization planning is partof the Planning Process Group.
The Standard for Program Management, p.79
Question:
[QID: 6490] You manage a program to
develop a new e-commerce program forautomotive parts distributors. Your
organization has established this program tokeep up with competitors and to increase
-
8/6/2019 Practice Test 1 Results
39/75
15/03/11 1:44 PMprint.html
Page 39 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html
market share, but it has recently acquired a
competitor that already has a highlyregarded e-commerce program in place. Yournext step is to
A) Revisit and update your program plans
B) Meet with each of your projectmanagers to discuss an orderly transition to
redeploy resources
C) Meet with your executive sponsor torequest a new assignment
D) Convene a meeting of your governanceboard to terminate your program
Explanation:
Acquisitions and mergers are unplanned
events. When they occur, they should triggera review of existing program plans to see
whether updates are required to ensureongoing usefulness.
The Standard for Program Management, p.
46
Question:
[QID: 6556] A definition and description of
program funding flows are contained in the
A) Program financial framework
B) Program charter
C) Program financial planD) Program business case
Explanation:
The program financial framework is a plan to
coordinate available funding, including thespecific constraints under which it is
available and how the money is paid out. Itdefines and describes program funding flows
in a way that ensures that program fundsare spent as efficiently as possible.
The Standard for Program Management, p.
213
Question:
[QID: 6451] As a program manager, you
recognize the importance of stakeholdermanagement. To support your efforts,
especially with key stakeholders whosedispleasure might hinder the programs
success, you p