Practice Test 1 Results

download Practice Test 1 Results

of 75

Transcript of Practice Test 1 Results

  • 8/6/2019 Practice Test 1 Results

    1/75

    15/03/11 1:44 PMprint.html

    Page 1 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    Exam Results for

    PgMP Practice Test#1

    You correctly answered 99 out of 170questions for a score of 58%.

    On the real PgMP exam, you'll face 170

    questions, 20 of which do not count towardyour PgMP, but are not identified as such.(The 20 unscored questions are "pretest"

    questions that PMI is trying out todetermine their validity.) You will receive a

    score that indicates whether you passed orfailed the exam. You will not know the

    number of questions you answered correctly.Instead, you will find out by Domain (Defining

    the Program, Initiating the Program, Planningthe Program, Executing the Program,

    Controlling the Program, and Closing theProgram) whether you are Proficient,

    Moderately Proficient, or Below Proficient.

    Your goal is to be Proficient in each domain.

    If you are not Below Proficient in any domain,statistically you have a very high likelihood of

    passing. If you receive a score of BelowProficient in any domain, you will need to

    earn enough extra points in another domainto make up for the deficiency.

    For your study purposes and for your goal tobe Proficient in all domains, we are

    interpreting Proficient as correctly answeringat least 90% of the questions in each domain,

    Moderately Proficient as 75% to 90%, andBelow Proficient as less than 75%. Note: This

    is ESI's interpretation and is not an official

    response from PMI.

    The table below shows how you performed onyour Practice Test in each of the domains

    described by the Program Management

    Professional (PgMP) Examination

    Specification.

    Domain

    Number Correct

    / Number ofQuestions

    Percentage

    Correct

    Defining

    theProgram

    13/24 54%

    Initiating

    theProgram

    12/20 60%

    PlanningtheProgram

    16/34 47%

    Executingthe

    Program

    32/42 76%

    Controllingthe

    Program

    16/36 44%

    Closingthe 10/14 71%

  • 8/6/2019 Practice Test 1 Results

    2/75

    15/03/11 1:44 PMprint.html

    Page 2 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    Program

    Questions

    Question:

    [QID: 6488] For seven years, you have

    managed a program that involvedbreakthrough scientific research. You are

    now in the closing stage. You have alreadymet with each scientist involved in the

    program at the time his or her work wasfinished. You have also met with a member

    of your enterprise program managementoffice (EPMO) who specializes in knowledge

    management to ensure that the intellectualproperty developed in the program is

    captured and documented for future reuse.You are

    A) Ensuring legal protection of thisvaluable asset

    B) Promoting collaboration in the scientificcommunity

    C) Recognizing individual efforts as well as

    the efforts of the entire project team

    D) Officially releasing each scientist to his

    or her functional organization

    Explanation:

    It is important not only to capture and

    document knowledge assets from eachproject and the intellectual property that hasbeen developed, but also to do so in a

    manner that ensures legal protection ofthese assets. This is necessary to ensure

    that data privacy and confidentially laws arenot violated.

    The Standard for Program Management, p.

    66

    Question:

    [QID: 6579] You are managing a business

    process management program for a largeinsurance company. After six months of

    effort, you have noticed that the keystakeholders seem to be losing interest in

    the effort and that friction has surfacedbetween your key staff members and key

    client contacts. You devise a plan to uncoverthe reasons for these apparent issues. Youadvise your deputy program manager to

    have lunch with her client counterpart atleast once a week; likewise, you will start

    taking the clients vice president out todinner every month. This activity can be

    viewed as

    A) Ineffective, because clients can seethrough such actions

    B) Positive, but bordering on beingunethical

    C) Positive, because you will be buildingstronger relationships with your client

    D) Negative, because it is a calculated

    attempt to gain information that could beobtained through more direct means

    Explanation:

  • 8/6/2019 Practice Test 1 Results

    3/75

    15/03/11 1:44 PMprint.html

    Page 3 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    Provided the clients code of ethics does not

    prohibit such entertainment activities,internal politicking is a skill and competencythat successful program managers practice.

    In this instance, such activity can be veryhelpful in uncovering underlying problems.

    Program Management Professional (PgMP)

    Examination Specification, p. 20

    Question:

    [QID: 6467] You are the program managerfor a sixth-generation cell phone product. Anumber of component projects are

    associated with this program. You were onthe core program team for the fifth-

    generation phone, so you can apply thelessons learned from that program. The

    schedule is the dominant constraint, andthere is a chance that you will miss the

    user-acceptance test milestone even thoughit is six months away. Your next step is to

    A) Ask your program steering committeefor additional resources to ensure that you

    can meet the milestone

    B) Inform the executive team that you willmiss this critical milestone unless preventive

    action is taken

    C) Revisit the program architecture

    baselineD) Implement your plan

    Explanation:

    The program architecture baseline is the

    output of the Develop Program Architectureprocess. It is useful in examining current

    risks and determining whether new risksexist.

    The Standard for Program Management, pp.

    114 and 161

    Question:

    [QID: 6582] You manage the development

    of an off-shore liquefied natural gas facility.Several contractors will be used in the

    component projects, and you are creatingspecific procurement strategies. After you

    determine which program work breakdownstructure (PWBS) elements will be handled

    internally and which will be contracted, yournext step is to

    A) Analyze the product description

    B) Use make-or-buy decision techniques

    C) Prepare a procurement managementplan

    D) Analyze the program scope statement

    Explanation:

    After you analyze the PWBS, scope

    statement, and product description, youapply make-or-buy decision techniques to

    determine which of the PWBS elements willbe produced using internal resources and

    which will be obtained from outsidesuppliers.

  • 8/6/2019 Practice Test 1 Results

    4/75

    15/03/11 1:44 PMprint.html

    Page 4 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    The Standard for Program Management, p.

    187

    Question:

    [QID: 6527] One of the issues on yourprogram is difficult to resolve because it

    concerns serious personality conflicts.Although it was raised by Project Manager A,

    it affects Projects B and C. Each of the threeproject managers has a different solution,

    and there is a stalemate. You cannot resolve

    this issue on your own and still maintain agood relationship with all three, so youescalate it to your executive sponsor for

    resolution at the next governance boardmeeting. This unresolved issue is

    A) An output of the Manage Program

    Issues process

    B) Best analyzed by a neutral party who

    will make a recommendation to theexecutive sponsor

    C) Sent to the enterprise programmanagement office (EPMO) to see whether it

    has been encountered and resolved onsimilar projects

    D) Put in a parking lot on the issuesregister until it is resolved

    Explanation:

    Ideally, issues should be resolved by theprogram manager or the component projectmanagers. If resolution is not possible, then

    an issue is escalated progressively higher onthe authority scale until resolution is

    achieved. Escalated issues are an output ofthe Issue Management and Control process.

    The Standard for Program Management, p.

    95

    Question:

    [QID: 6461] Communications planning and

    execution focus on

    A) Reacting to stakeholder concerns

    B) Proactively targeting development and

    delivery of key messagesC) Taking corrective actions in response to

    program issues

    D) Identifying suitable technologies fordistributing program information

    Explanation:

    The emphasis of communications planning

    and execution is on the proactive and

    targeted development of key messages.Program stakeholders should be engaged atthe right time and in the right way.

    The Standard for Program Management, p.227

    Question:

    [QID: 6521] Your organization is embarkingon a program to establish a culture of

    knowledge management. You established alessons-learned register on your last project.

  • 8/6/2019 Practice Test 1 Results

    5/75

    15/03/11 1:44 PMprint.html

    Page 5 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    The enterprise program management office

    (EPMO) was impressed and suggested to theCEO that a program focusing on knowledgemanagement is needed. The CEO concurred,

    and you were appointed program manager.Two people from the EPMO have been

    assigned to the core program team. Theymay be replaced by permanent staff during

    which one of the following processes?

    A) Human Resource Planning

    B) Manage Program Resources

    C) Acquire Program Team

    D) Initiate Team

    Explanation:

    Many organizations set up a program teamto participate in initiation or program start-

    up and then replace team members withpermanent staff during the Manage Program

    Resources process, which tracks and adaptsthe use of program resources throughout the

    life cycle.

    The Standard for Program Management, p.91

    Question:

    [QID: 6495] As each project manager beginsto identify the work to be done on their

    projects, you want to make sure that allwork will be integrated into a program plan.The best way to ensure this linkage is

    through a common

    A) Scheduling methodology

    B) Project management standard

    C) Work breakdown structure (WBS)

    methodology

    D) Organizational breakdown structure(OBS) methodology

    Explanation:

    Because the WBS defines all work in aproject and program, this is the best tool to

    use for integration. The program workbreakdown structure (PWBS) typically

    corresponds to the first one or two levels ofthe WBS of each component project. As the

    PWBS is developed, the managementplanning process is a key tool and technique

    to use.

    The Standard for Program Management, pp.115117

    Question:[QID: 6433] The person who is ultimatelyresponsible for ensuring program success is

    the

    A) Program manager

    B) Head of the program governance board

    C) Executive sponsor

    D) Program director

    Explanation:

    The executive sponsor is the group or

    person who is responsible for providing

  • 8/6/2019 Practice Test 1 Results

    6/75

    15/03/11 1:44 PMprint.html

    Page 6 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    project resources and ultimately for ensuring

    program success.

    The Standard for Program Management, p.

    245

    Question:

    [QID: 6562] You are a member of your

    insurance companys Program SelectionCommittee, which is considering a number of

    potential programs. Program A is estimated

    to cost $100,000 to implement and will haveannual net cash inflows (ANCI) of $25,000.Program B is estimated to cost $250,000 to

    implement and have ANCI of $75,000.Program C is estimated to cost $600,000 to

    implement and have ANCI of $125,000.Program D is estimated to cost $125,000 to

    implement and have ANCI of $50,000. Yourselection criteria are based on the shortest

    payback period. You recommend that yourcompany select

    A) Program C

    B) Program A

    C) Program B

    D) Program D

    Explanation:

    The payback period can be determined by

    dividing the initial fixed investment in theprogram by the estimated annual net cashinflows. In this example, the payback period

    for Program D is 2.5 years, so it should beselected.

    Program Management Professional (PgMP)

    Examination Specification, p. 17

    Question:

    [QID: 6458] A best practice in program

    management is to identify and documentlessons learned throughout the program as it

    moves through the various phases of its lifecycle. The next step in this process is to

    A) Have experts examine each one to

    determine whether it should be included inthe organizations process asset library

    B) Appoint one of the core program teammembers as a knowledge broker to pass on

    these lessons learned

    C) Analyze and archive them as part of

    the Closing Process Group

    D) Formally document these lessons

    learned in the knowledge management

    system

    Explanation:

    Lessons learned are an output of manyprogram management processes. Theyshould be identified during the life of the

    program and should be inputs to the CloseProgram process, where they are analyzed

    and archived.

    The Standard for Program Management, p.39

  • 8/6/2019 Practice Test 1 Results

    7/75

    15/03/11 1:44 PMprint.html

    Page 7 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    Question:

    [QID: 6584] You are managing a programthat lengthened existing icebreaker vessels

    so that they could be used in the waterssurrounding Antarctica. During extensive

    testing off the coast of Labrador, the vesselsperformed well, and the reliability and

    maintainability (R&M) data were well withinan acceptable variance range. Many of the

    vessels are now in use off the coast ofAntarctica, and the R&M data have a much

    wider range of variance; however, vessel

    performance remains acceptable. It is nowtime to close the program. You need to

    A) Support corrective actions as required

    B) Leave in place a legacy of operational

    benefits sustainment

    C) Continue to provide governance

    oversight

    D) Track all benefits even after the

    program closes

    Explanation:

    The Closing Process Group formalizesacceptance of the products, services, or

    results that define the programs successfulcompletion. It is intended to leave in place a

    legacy of operational benefits sustainment,thus deriving optimal value from the

    programs objectives.

    The Standard for Program Management, pp.6667

    Question:

    [QID: 6520] After the program benefits arerealized, it is important to ensure that they

    are sustained after they are transferred tothe organization. This is the purpose of the

    A) Transition Realization process

    B) Program road map update

    C) Program transition plan

    D) Transition Monitoring and Controllingprocess

    Explanation:

    The program transition plan enumerates all

    necessary actions that are required totransfer the program from a development

    state to an operational state pendingapproval that all requirements are complete.

    It is an output of the Develop ProgramManagement Plan process.

    The Standard for Program Management, p.

    83

    Question:

    [QID: 6508] The contractor working on your

    program is losing money on the contractand asks that you terminate the agreement.

    She says that if you do not, she will simplystop working because she cannot afford to

    continue. If she does stop work, she will

    A) Terminate the contract for convenience

  • 8/6/2019 Practice Test 1 Results

    8/75

    15/03/11 1:44 PMprint.html

    Page 8 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    B) Default and be subject to legal action

    C) Be held in contempt of court

    D) Terminate the contract for cause

    Explanation:

    When a contractor refuses to performaccording to the terms and conditions of a

    contract, he or she is in default and issubject to legal action. Although it is

    unfortunate that the contractor is notmaking money on the program, that is not

    grounds for refusing to live up to her end ofthe agreement. The organizations contractclosure procedure, a tool and technique in

    the Close Program Procurements process,outlines the requirements for contract

    termination, including verification criteria toprotect the organization from breach of

    contract.

    The Standard for Program Management, p.205

    Question:

    [QID: 6450] As the manager of a newprogram to develop the next-generation

    heating, ventilation, and air-conditioning(HVAC) system, you establish a process to

    monitor your program benefits. Following thestandard benefits management life cycle,

    you develop this process during the

    A) Benefits identification phase

    B) Benefits analysis and planning phase

    C) Benefits realization phase

    D) Benefits monitoring phase

    Explanation:

    A process for benefits monitoring is

    established in the benefits realization phase.At this time, the program manager and theteam establish the structure in which workwill occur as well as the technical

    infrastructure to facilitate the work. Thisincludes establishing a framework to monitor

    and control the projects and to measureprogram benefits.

    The Standard for Program Management, pp.20 and 84

    Question:

    [QID: 6583] You are a program manager on

    an international program that relies oncontractors for approximately 75 percent of

    its work. Some of the contracts apply to a

    specific project, but five contracts span sixof the projects. You have one basic orderingagreement, which enables you to obtain

    temporary resources as required for thiscomplex program. In terms of the

    Administer Program Procurements process,you should review the

    A) Procurement register

    B) Change requests

    C) Program reports

    D) Contract management plan

  • 8/6/2019 Practice Test 1 Results

    9/75

    15/03/11 1:44 PMprint.html

    Page 9 of 75file:///Users/kritichan/Librocal%20Store/2.0/print.html

    Explanation:

    The contract management plan is used toadminister contracts for significant purchasesand acquisitions. It covers contract

    administration activities throughout the lifeof the contract and is used effectively to

    manage a variety of suppliers. It is a tooland technique of the Administer Program

    Procurements process.

    The Standard for Program Management, p.201

    Question:

    [QID: 6566] You are an executive with amajor recording studio. Four new groups

    have auditioned for a record contract, butyou can select only one. The program to

    launch any group consists of Web sitedevelopment, music videos, a nationwide

    tour, T-shirts, and a fan club. Your head ofMarketing has done a net present value

    (NPV) for each group. Which do you choose?

    You recommend that your company select

    A) Group C

    B) Group D

    C) Group A

    D) Group B

    Explanation:

    Using net present value (NPV) as a selectioncriterion, a dollar a year from now is worth

    less than a dollar today. The more the futureis discounted (that is, the higher the

    discount rate), then the lower the NPV ofthe program. If the NPV is higher, then the

    program is rated higher than others. In this

    example, Group C has the highest NPV andshould be selected.

    Program Management Professional (PgMP)

    Examination Specification, p. 17

    Project Management ToolBox: Tools and

    Techniques for the Practicing Project

    Manager, pp. 4344

    Question:

    [QID: 6581] You are the program manager

    for development of a next-generationpersonal digital assistant (PDA) that can be

    used on computers, airplanes, trains, andphones. You determine the programs

    financial framework as part of the

    A) Develop Program Infrastructure process

    B) Initiate Program process

    C) Establish Program Financial Framework

  • 8/6/2019 Practice Test 1 Results

    10/75

    15/03/11 1:44 PMprint.html

    Page 10 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    process

    D) Develop Program Financial Plan process

    Explanation:

    The purpose of this process is to assess theoverall financial environment for the

    program and to identify funding sources forthe identified milestones. The key output is

    the program financial framework chart.

    The Standard for Program Management, pp.207 and 213

    Question:

    [QID: 6577] To identify risks that couldaffect your program, you and your core

    program team clarify the definition of eachrisk and group them by cause. You are using

    which of the following techniques?

    A) Flowcharts

    B) Root cause identification

    C) SWOT analysis

    D) Influence diagrams

    Explanation:

    Root causes are the fundamental conditions

    or events that may give rise to a risk.Program-specific risk activities include

    determining the primary causes of a

    programs risks, which can be done bysharpening the definition of each risk andgrouping risks by cause. More effective risk

    responses can be prepared after the rootcauses are identified.

    The Standard for Program Management, p.

    167

    Question:

    [QID: 6477] Your client has not paid its last

    invoice of 500,000, and it is now more than90 days overdue. Your companys accounting

    policy states that any invoice that is morethan 90 days late becomes bad debt. You

    now need to

    A) Update your cost management planB) Take corrective action

    C) Rebaseline your budget

    D) Issue a change request

    Explanation:

    Bad debt is money that is not collectible and

    is therefore worthless. As a result, it isdeemed an expense to the business rather

    than revenue, because the business incurredthe expense of providing a service or

    product for which it was not paid. Inresponse to this problem, you need to take

    corrective action, which is an output of theMonitoring and Controlling Program

    Financials process.

    The Standard for Program Management, p.226

    Question:

  • 8/6/2019 Practice Test 1 Results

    11/75

    15/03/11 1:44 PMprint.html

    Page 11 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    [QID: 6504] To ensure that the programs

    benefits are delivered as intended, specificmetrics and measurement approaches arerequired. These are stated in the

    A) Program management plan

    B) Program charter

    C) Benefits realization plan

    D) Programs business case

    Explanation:

    The benefits realization plan is part of the

    Planning Process Group. It includes metrics

    and measurement approaches for theintended benefits from the program and fortheir delivery.

    The Standard for Program Management, p.

    31

    Question:

    [QID: 6570] In a program performance

    meeting, you asked the project manager ofProject A what the status was. She

    responded by saying that the total projectbudget of $600,000 was evenly allocated

    over the projects six-month life. She hasjust completed the second month of the

    project and has finished 50 percent of thework. What earned value method

    information is available thus far?

    A) Earned value and planned value

    B) Planned value

    C) Earned value

    D) Actual costs

    Explanation:

    For the earned value (EV) of the project,

    note that half the work has been completed,for an EV of $300,000. The planned value

    (PV) through month two is $200,000.Remember that the estimate was $600,000

    spread evenly over six months (or$100,000/month).

    The Standard for Program Management, p.

    133

    The Project Management Drill Book: A Self-

    Study Guide, Chapter 1

    Question:

    [QID: 6445] To be successful, benefitsmanagement must begin when

    A) The business case is approved

    B) The program is initiated

    C) The program is defined

    D) Each project is selected

    Explanation:

    Although benefits management evolves asthe program continues through its phases, it

    should begin when the program is initiated,in the Pre-Program Preparations and

    Program Initiation phases of the program lifecycle.

  • 8/6/2019 Practice Test 1 Results

    12/75

    15/03/11 1:44 PMprint.html

    Page 12 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    The Standard for Program Management, p.

    20

    Question:

    [QID: 6594] You are managing a program toestablish a new distribution center. The

    facilitys location was selected because laborcosts were low, but it is in a remote area.

    Now gasoline prices have increased 30percent and are forecasted to rise another

    20 percent in the next six months. In

    planning for the procurement oftransportation services, you need to

    A) Prepare a contract management plan

    B) Recommend to your sponsor that the

    program be terminated and the distributioncenter be moved to a more urban area

    C) Prepare a competitive analysis ofservice providers

    D) Encourage bidders by providingsimplified legal requirements in the form ofstandard terms and conditions

    Explanation:

    In the Plan Program Procurement process, a

    competitive analysis of service providers is atool and technique to identify those suppliers

    that provide specific products and services.

    The Standard for Program Management, p.189

    Question:

    [QID: 6481] You are a program manager for

    a city transit authority. Your program has anumber of projects under way to upgrade

    the infrastructure to current technologies

    and to implement a process improvementprogram. The transit authoritys chieffinancial officer (CFO) has left to assume a

    position in a different city, and a new personhas been appointed CFO. You should

    A) Take no action at this time

    B) Appoint one of your core teammembers to interact with the new CFO

    C) Update your stakeholder inventoryD) Meet with the new CFO when it is

    convenient, because the CFO is not a

    primary stakeholder in your program

    Explanation:

    As program manager, you manage thestakeholder inventory throughout the

    program and take appropriate action to

    handle any changes that may occur.Although the CFO may not be a primarystakeholder, he or she is important to the

    program and cannot be overlooked.

    The Standard for Program Management, pp.

    235 and 238

    Question:[QID: 6546] Because of the strategic nature

    of programs, it is easy to confuse thecharacteristics of benefits, objectives, and

  • 8/6/2019 Practice Test 1 Results

    13/75

    15/03/11 1:44 PMprint.html

    Page 13 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    success criteria. A benefit can best be

    characterized as

    A) An improvement in an organizations

    operation

    B) The voice of the customer (VOC)

    C) The importance of the program

    D) What the individual programs projectsare designed to achieve

    Explanation:

    A benefit is an improvement to the operation

    of an organization. Benefits may include

    increased profits, improved growth, orimproved employee morale.

    The Standard for Program Management, p.309

    Enterprise Program Management Delivering

    Value, p. 178

    Question:

    [QID: 6580] You are assuming a position in

    a company that has not had muchexperience with program management. You

    will be leading the program team andperforming a business function for your

    program. The business case has alreadybeen made, and the program is scheduled to

    move into the Program Initiation phase. Asthe program manager, your most importantcompetency is

    A) Communication

    B) Strategic visioning

    C) Political skills

    D) Leadership

    Explanation:A successful program manager must have a

    special blend of knowledge, skills, andcompetencies. The most important is

    communication skills to deal with all programstakeholders.

    The Standard for Program Management, pp.

    1213

    Question:

    [QID: 6439] One purpose of review by the

    programs governance board is to

    A) Manage the program resources

    B) Identify how many project managers

    have earned their PMPs

    C) Direct program communications withthe public at large

    D) Initiate another project into the

    program

    Explanation:

    Reviews by the programs governance boardare an opportunity for senior management

    to assess program performance before theprogram moves to the next phase or before

    another project is initiated in the program.This process can occur during any program

    phase except closing. The criteria for

  • 8/6/2019 Practice Test 1 Results

    14/75

    15/03/11 1:44 PMprint.html

    Page 14 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    approval are defined in the governance plan.

    The Standard for Program Management, p.257

    Question:

    [QID: 6483] You are managing agovernment program that is responsible for

    regulatory initiatives in food additives.Several people both inside and outside your

    agency have questioned why the agency set

    these initiatives up as a program rather thanas a series of individual projects, as hasbeen done in the past. They are complaining

    that it is just more bureaucracy. You explainthat

    A) Your focus as program manager is to

    reduce resistance to change

    B) You will be managing technicians and

    specialists from scientific, regulatory, andlegal units in the agency

    C) Because the projects support a diverseset of clients, integrated stakeholder

    management is critical

    D) The individual projects in the area of

    food additive regulations have numerousinterdependencies and are best managed as

    one initiative

    Explanation:It is essential to determine why anorganization elects to use a program

    structure rather than focus on projectmanagement. One of the criteria is whether

    interdependencies on deliverables amongprojects will create a set of benefits. If so, a

    program is recommended.

    The Standard for Program Management, p. 6

    Question:

    [QID: 6597] Most programs involve cross-

    disciplinary as well as cross-cultural teams.Program managers must be able to obtain

    resources from various functional units andgeographies and must also direct and

    coordinate the work of individual functionalteams across time and distance. This shows

    the importance of which of the followingprogram management skills?

    A) Leadership

    B) Communication

    C) Strategic visioning

    D) People skills

    Explanation:

    The program manager leads interdisciplinary

    teams as well as functional teams. Programsrequire resources, and the program managermust be able to obtain needed resources

    from functional organizations. Strongleadership skills are critical to the successful

    management of multiple program teamsthroughout the life cycle.

    The Standard for Program Management, p.

    13

  • 8/6/2019 Practice Test 1 Results

    15/75

    15/03/11 1:44 PMprint.html

    Page 15 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    Question:

    [QID: 6507] As program manager for

    development of a next-generation catalyticconverter, you decide to use an issue

    register. After each issue is identified, yourcore program team records it in this register.

    The next step is to

    A) Subject the issue to analysis by a

    reviewing authority

    B) Appoint a member of the program team

    to resolve the issueC) Refer the issue to the head of the

    program management office (PMO) for

    analysis and tracking

    D) Ask the person who raised the issue to

    propose a resolution

    Explanation:

    After an issue is identified, it should be

    recorded in the issue register. The next stepis to subject it to analysis by a reviewingauthority or board. Issue reviews should be

    conducted regularly.

    The Standard for Program Management, p.96

    Question:[QID: 6561] Because of their size,complexity, and duration, programs tend to

    be more important than projects in mostorganizations, and program managers tend

    to interact more with senior management,often through the governance board or

    steering committee that oversees theprogram. Throughout the program, it is

    especially important to monitor and controlprogram changes. A useful tool and

    technique is

    A) Impact analysis

    B) Program metrics

    C) Change request log

    D) Change register

    Explanation:

    Impact analysis is a tool and technique in

    the Monitor and Control Program Changesprocess, which explores the effect of the

    proposed changes on the program. Itassesses the accuracy of any assumptions

    and identifies the potential risks and benefitsthat possible changes may have on the

    component projects.

    The Standard for Program Management, p.269

    Question:

    [QID: 6515] The stakeholder analysis is akey tool and technique in program

    management. To conduct such an analysis,the first step is to hold interviews, use focus

    groups, and perhaps conduct a survey. Thisapproach enables you to

  • 8/6/2019 Practice Test 1 Results

    16/75

    15/03/11 1:44 PMprint.html

    Page 16 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    A) Identify stakeholders attitudes toward

    the program

    B) Prioritize stakeholders in terms of their

    ability to influence the programC) Develop a stakeholder register

    D) Develop a stakeholder communications

    strategy

    Explanation:

    Stakeholder analysis is a tool and techniquein the Plan Program Stakeholder

    Management process that is used to gain anunderstanding of the organizational culture

    and the stakeholders needs andexpectations. Often this process is done

    through interviews, focus groups, andquestionnaires and surveys.

    The Standard for Program Management, p.

    230

    Question:

    [QID: 6505] You have just completed the

    program work breakdown structure (PWBS)for a program to develop a new line of scubaequipment. Your next step is to

    A) Generate the program schedule

    B) Develop the program scope definition

    C) Negotiate for team members

    D) Identify key milestones

    Explanation:

    Upon completion of the program work

    breakdown structure (PWBS), realisticschedules can be built, cost estimates can be

    developed, and the programs work can beorganized.

    The Standard for Program Management, p.114

    Question:

    [QID: 6446] A key characteristic of the

    program management life cycle is that it

    A) Ends with the delivery process

    B) Follows a repeatable processC) Focuses first on benefits realization

    D) Is nonsequential

    Explanation:

    The program life cycle is nonsequential.Throughout the life cycle, components aremobilized as appropriate so that a stream of

    deliverables focuses on facilitating new

    operations and benefits.

    The Standard for Program Management, p.

    18

    Question:

    [QID: 6448] Your program to develop the

    next-generation helium automobile has been

    completed. In retrospect, you recognize thatyour companys standard programgovernance structure was not effective, as

  • 8/6/2019 Practice Test 1 Results

    17/75

    15/03/11 1:44 PMprint.html

    Page 17 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    more gate reviews were needed during the

    Delivery of Program Benefits phase. Yourecommend that the enterprise programmanagement office (EPMO) reassess the

    program life cycle and the role of thegovernance board. This is an example of a

    A) Lesson learned

    B) Mistake

    C) Best practice

    D) Good practice

    Explanation:

    In the closing phase, the program managerand team may provide feedback andrecommendations on areas that are outside

    the scope of the program but could benefitthe organization in the future.

    The Standard for Program Management, p.

    30

    Question:

    [QID: 6517] One of the major purposes of

    the Manage Program Issues process is toidentify, track, and close issues so that

    stakeholder expectations are aligned withprogram activities and results. This

    alignment can be accomplished by severalmethods, including

    A) Performing program scope analysis

    B) Leveraging opportunities

    C) Adjusting enterprise environmental

    factors

    D) Adjusting program priorities

    Explanation:

    It is important that the program manager

    ensure that stakeholder activities are alignedwith the programs activities and

    deliverables. Issues may be sent to programrisk management, program governance, or

    program scope management. When issuesare sent to program scope management,

    then it is important to determine the effectthat such issues have on the programs

    scope.

    The Standard for Program Management, p.96

    Question:

    [QID: 6596] You are managing a programwhose budget at completion (BAC) is

    420,000. The program is 10 percent

    complete and has an earned value of42,000. The actual costs (AC) are 50,000.This means that

    A) The program is over budget by

    8,000, which is a major problem

    B) Although the program is over budget,the overrun is insignificant at this time

    C) The CV is 378,000, and immediate

    action is necessary

    D) You need to calculate a new estimate

    to complete (ETC)

  • 8/6/2019 Practice Test 1 Results

    18/75

    15/03/11 1:44 PMprint.html

    Page 18 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    Explanation:

    The cost variance (CV) is calculated bysubtracting the actual cost (AC) from theearned value (EV); that is, CV = EV AC, or

    42,000 50,000 = 8,000, which isinsignificant compared to the budget at

    completion (BAC).

    The Standard for Program Management, p.133

    PMBOK Guide, p. 182

    Question:

    [QID: 6599] You are Company As programmanager for the development of an online

    banking system for your community bank,for which your company will receive $20

    million. However, the bank is so interested inimplementing this system quickly that it also

    contracts with Company B. You mustimplement your system completely in six

    months to ensure that you beat CompanyBs schedule. At this point, you have an

    expense estimate of $2.5 million. You willlose $10 million if you cannot deliver the

    product in six months, but if you cancomplete it sooner, you will earn an

    additional $25 million. Your risk managementofficer performs a risk analysis and tells you

    that there is a 30 percent chance that thebank will change its requirements and a 70percent chance that the project will be

    completed on time or ahead of schedule.Your company has completed similar projects

    in the past, and on the basis of theseexperiences, you know that there is a 30

    percent chance that your final expenses willincrease by $10 million. If no risks occur,

    the value of your program will be

    A) $29 million

    B) $17.5 million

    C) $2.5 million

    D) $42.5 million

    Explanation:

    Decision-tree analysis is a technique of theAnalyze Program Risks process. It shows the

    situation and the implications of each of theavailable choices. It also provides the

    expected monetary value for the variousalternatives. If no risks occur, the value of

    your program would be calculated as follows:$20m $2.5m = $17.5m.

  • 8/6/2019 Practice Test 1 Results

    19/75

    15/03/11 1:44 PMprint.html

    Page 19 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    The Standard for Program Management, pp.172174

    Question:

    [QID: 6600] You will need a number ofdifferent types of supplies and services to

    support your program and its componentprojects. Many different techniques can be

    used to evaluate proposals that aresubmitted. All use

    A) Weighting systems

    B) Expert judgment

    C) Predefined weightings

    D) Screening systems

    Explanation:

    Proposal evaluation systems are a tool and

    technique in the Conduct Program

    Procurements process. Although a number ofdifferent approaches can be used, all useexpert judgment and evaluation criteria.

    The Standard for Program Management, p.195

    Question:

    [QID: 6572] You and several members ofyour team are developing your benefits

    realization plan. Everyone is focused onemploying a set of benefits measurement

    techniques that will provide substantiveinformation to all stakeholders. Of the

    following, which is an example of a benefitsmeasurement technique?

    A) Net present value (NPV)

    B) Balanced scorecard

    C) Value engineering

    D) Internal rate of return (IRR)

    Explanation:

    The balanced scorecard is a benefits

    measurement technique that includes a setof performance measures. These measures

    cover a range of areas that reflect and show

    a balanced view of organizationalperformance. Internal rate of return (IRR)and net present value (NPV) are financial

    analysis techniques, and value engineering isa technique used to reduce costs in product

    development.

    Program Management Professional (PgMP)

    Examination Specification, p. 17

    Question:

    [QID: 6441] You are the program manager

    on a highly controversial e-mail retentionprogram. More than 75 percent of the

    organization is opposed to the programbecause it means that all their e-mail

    messages will be archived and reviewed for

    inappropriate, unethical, or illegalstatements. You know that there will bemany conflicts as you and your team

  • 8/6/2019 Practice Test 1 Results

    20/75

    15/03/11 1:44 PMprint.html

    Page 20 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    execute the component projects. You inform

    your team that, in the case of any conflict,the first point of escalation is

    A) The program sponsor

    B) The program director

    C) The program governance board

    D) You, the program manager

    Explanation:

    Program managers are the escalation pointfor issues, changes, risks, interfaces, and

    dependencies. As program manager, you

    must manage relationships, resolve conflicts,and deal with the political aspects ofstakeholder management.

    The Standard for Program Management, pp.

    11 and 13

    Question:

    [QID: 6494] Your program is being audited

    by the enterprise program managementoffice (EPMO). One of the audit team

    members wants to know what documentdescribes the responsibility for delivery of

    the intermediate and final program benefits.You tell him it is in the

    A) Benefits realization plan

    B) Business caseC) Benefits identification plan

    D) Benefits analysis plan

    Explanation:

    The benefits realization plan includes theresponsibility for delivery of the intermediate

    and final program benefits. Benefitsmanagement is a continuous process that

    assesses the value of the programs benefitsas well as the interdependencies that exist

    between benefits in the programs projects.It also assigns responsibility and

    accountability for benefits realization.

    The Standard for Program Management, pp.3031

    Question:

    [QID: 6487] You are the program managerfor a water-alleviation program that requires

    extensive equipment. Some of thisequipment represents new technology. As

    the program manager, you are preparingregular program performance reports, and

    each one discusses this equipment. A useful

    program performance analysis tool andtechnique to identify potential issues withthis untested technology is

    A) Forecast data

    B) Risk analysis

    C) Program metrics information

    D) Audit requirements

    Explanation:

    Program performance analysis, a tool andtechnique of the Monitor and Control

    Program Performance process, includes gap

  • 8/6/2019 Practice Test 1 Results

    21/75

    15/03/11 1:44 PMprint.html

    Page 21 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    analysis, risk analysis, issues analysis, and

    trend and probability analysis. Risk analysisemphasizes real-time monitoring of programrisk as critical for success.

    The Standard for Program Management, p.

    95

    Question:

    [QID: 6586] Your program is beginning to

    miss key milestones because of delays by

    your customer, with whom you have acontract. Your goal is to ensure thatcorrections are made as quickly as possible,

    so you decide to conduct a contractperformance review earlier than planned.

    During this review, you and the customerrealized that there was a deficiency in the

    contract. Your next step is to

    A) Document the delay and discuss it with

    the steering committee

    B) Document the causes for the delay andbring it to your attorneys attention

    C) Prepare an assignment of claims form

    D) Prepare a change request

    Explanation:

    A contract performance review is a tool andtechnique in the Administer Program

    Procurements process. Change requests orrecommended corrective action requestsshould be raised when the performance

    problems are the result of a deficiency in acontract.

    The Standard for Program Management, p.

    202

    Question:

    [QID: 6563] Because your program has the

    highest priority in the organizationsportfolio, your governance board meets each

    month and each member receives a weeklystatus report. The executive sponsor

    requests these measures to enable him tostay current on program activities and assist

    you with any issues that need resolution.Your customer also requests monthly

    meetings and a weekly teleconference. Toensure that your list of these meetings and

    communications is up-to-date, you shoulddevelop a(n)

    A) Information reporting schedule

    B) Communications log

    C) Communications capability matrixD) Information distribution plan

    Explanation:

    The communications log is an output of thePlan Communications process. It identifies

    the who, what, when, how, and why foreach form of communication. After the

    communications framework has beendeveloped and agreed to, the next step is to

    identify and put into place the components(that is, the processes and technical

    elements) that will enable the

  • 8/6/2019 Practice Test 1 Results

    22/75

    15/03/11 1:44 PMprint.html

    Page 22 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    communications to be executed.

    The Standard for Program Management, p.147

    Question:

    [QID: 6529] The development of conceptsfor products or services, initial requirements,

    time lines, and cost guidelines are examplesof activities performed

    A) During the Planning process

    B) Before the Initiate Program process

    C) During the Initiate Program process

    D) Concurrently with the business case

    Explanation:

    A number of activities are typically

    performed before the program is initiated.These activities result in the development of

    concepts for products and services, scopeframeworks, initial requirements, timelines,

    deliverables, and guidelines regardingacceptable costs. These activities are

    required to determine the business case forthe program and to seek approval from the

    governance board or comparable body.

    The Standard for Program Management, p.42

    Question:

    [QID: 6571] You are a program manager foran aerospace company that is developingthe C888 aircraft. Each of the component

    projects is scheduled to end at a differenttime. You establish a product support team

    that you will manage as part of your

    program responsibilities by providingupgrades during the product life cycle. Suchupgrades are often used in which one of the

    following management approaches?

    A) Earned value management

    B) Program management

    C) Operational management

    D) Project management

    Explanation:

    Benefits sustainment may follow a structuredapproach, but it typically does not require

    true program management principles tooperate the end product. However, upgrades

    to a product often use project managementto design, develop, and implement such

    changes.

    The Standard for Program Management, p.31

    Question:

    [QID: 6485] Throughout your program, youmeet regularly with members of theprograms governance board at phase-gate

    reviews. These meetings are necessarybecause they provide the board and other

    interested stakeholders an opportunity to

  • 8/6/2019 Practice Test 1 Results

    23/75

    15/03/11 1:44 PMprint.html

    Page 23 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    A) Assess performance of the program

    against expected outcomes

    B) Review program performance

    C) Focus on the phase that was justcompleted to determine whether the nextphase should begin

    D) Assess performance against the needto realize and sustain program benefits for

    the long term

    Explanation:

    Phase-gate reviews serve numerouspurposes and should be held throughout the

    program. They focus on the phase that wasjust completed and result in go/no-go

    decisions. However, these sessions are not asubstitute for periodic program performance

    reviews.

    The Standard for Program Management, p.22

    Question:

    [QID: 6435] You are preparing for a meetingof your governance board. You have learnedthat it is a best practice to meet in advance

    with two board members to ensure that theyconcur with what you plan to present. Board

    Member A says that your approach on somerecent issues was not in line with the

    benefits realization plan, and she is upsetwith your performance. Board Member B

    says that he is pleased with your work; hethinks that you are realizing the benefits

    outlined in the benefits realization plan. Onthe basis of these two advance meetings,

    you

    A) Report the problem to the benefits

    managerB) Continue with the governance board

    meeting as scheduled, because you have

    Board Member Bs support

    C) Work with your program team to

    address Board Member As concerns beforethe governance board meeting

    D) Cancel the meeting to fully addressBoard Member As concerns

    Explanation:

    You should proceed with the scheduledgovernance board meeting but be preparedto address Board Member As concerns.

    Benefits are achieved in a cumulativemanner. At the meeting, you can discuss the

    deliverables that have met requirements anddescribe the benefits that have been realized

    to date. Noting Board Member As concerns,you can identify any risks that might affect

    the program and describe how you plan tomitigate them.

    The Standard for Program Management, pp.

    58 and 236

    Question:[QID: 6575] Every program is planned on

    the basis of a set of hypotheses, scenarios,or assumptions. As a newly appointed

  • 8/6/2019 Practice Test 1 Results

    24/75

    15/03/11 1:44 PMprint.html

    Page 24 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    program manager, you ask one of your core

    program team members to explore thevalidity of these assumptions and to do soperiodically as a way to identify risks. This is

    important as part of the

    A) Risk monitoring function

    B) Issue management activities

    C) Risk analysis options

    D) Risk response analysis

    Explanation:

    Risk monitoring includes evaluation of

    whether program assumptions remain valid.This function is ongoing throughout the lifeof the program as part of the Monitor and

    Control Program Risks process.

    The Standard for Program Management, p.180

    Question:

    [QID: 6462] At the program level, analysisof change requests involves identifying,

    documenting, and estimating the work thatthe change would entail. In addition, as

    program manager, you must

    A) Convene a meeting of the projects

    configuration control board

    B) Meet with the program governanceboard for approval, rejection, or deferral ofthe request

    C) Prepare a status report

    D) Determine whether updates to theprogram document repository are needed

    Explanation:

    Changes affect the various program-level

    processes. As part of the Monitor andControl Program Scope process, updates to

    the document repository may be requiredbased on the nature of the change.

    The Standard for Program Management, p.

    124

    Question:[QID: 6482] You are the program manager

    for the development of a new slot machinefor the Sand Dunes casino in Macau. Your

    organization operates with a balanced matrixorganizational structure, and you have

    resources supporting your program from avariety of functional departments. Some of

    these people report to you as well as to

    their respective departmental managers. Youhave a cost accounting system in whicheveryone charges time to appropriate

    account codes. Because your program isclose to completion, you need to

    A) Close the program budget to avoidnon-allocable charges

    B) Use the management reserve to payany additional charges

    C) Integrate this cost accounting system

    with the project management informationsystem (PMIS)

  • 8/6/2019 Practice Test 1 Results

    25/75

    15/03/11 1:44 PMprint.html

    Page 25 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    D) Issue a change request to close the

    program management plan

    Explanation:

    As an output of the Monitor and ControlProgram Financials process, the program

    budget is closed as the program comes to aclose, the final financial reports are

    distributed in accordance with thestakeholder management plan, and any

    unused funds are returned to the fundingorganization.

    The Standard for Program Management, p.226

    Question:

    [QID: 6558] You are managing a program to

    develop a new source of energy in theextreme northern latitudes when solar power

    is not available. Working with your core

    program team and your governance board,you have identified a number of component

    projects. Your company has several keyprojects under way, and resources will be

    difficult to acquire for this new program. Indetermining whether you will use internal or

    external resources, you should consider

    A) Your ability to negotiate with functional

    managers for the needed staffB) The availability of off-shore employees

    to drive down costs

    C) The availability of key staff members

    D) Previous work by the staff as asuccessful team

    Explanation:

    Resource availability indicates the availability

    of the personnel, assets, materials, or capitalresources that are required to accomplish

    the programs goals. It is an input to theManage Program Resources process.

    The Standard for Program Management, p.

    92

    Question:[QID: 6454] You are managing a program

    that includes 15 component projects. Thebenefits expected from each project shouldbe defined in the

    A) Program benefits identification phase

    B) Project business case during the Pre-Program Preparations phase

    C) Program benefits realization phaseD) Project business case before the

    project is initiated

    Explanation:

    Projects are typically initiated and executed

    in the Delivery of Program Benefits phase.Projects should not be initiated without

    having a business case that describes thebenefits the project will provide.

    The Standard for Program Management, p.

    257

  • 8/6/2019 Practice Test 1 Results

    26/75

    15/03/11 1:44 PMprint.html

    Page 26 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    Question:

    [QID: 6587] You are a member of your

    organizations Program Selection Committee,which is conducting an off-site meeting to

    review the companys five major strategicgoals, all of which are weighted equally.

    Goal 1 is to produce the highest possiblequality products; goal 2 is to provideoutstanding customer relationship

    management; goal 3 is to reduce reliance onexternal supply sources and maximize

    internal resources; goal 4 is to reducemanufacturing costs; and goal 5 is to

    maximize productivity. You are consideringfour programs and will recommend one to

    the CEO. Program A partially supports goal1, fully supports goals 2, 3, and 4, and does

    not support goal 5. Program B fully supportsgoals 1, 3, 4, and 5, but does not support

    goal 2. Program C fully supports goals 1 and

    2, partially supports goals 3 and 4, but doesnot support goal 5. Program D partiallysupports goals 1, 2, and 5, and fully

    supports goals 3 and 4. Considering thisinformation, your recommendation should be

    to select

    A) Program D

    B) Program A

    C) Program BD) Program C

    Explanation:

    Programs should have a strategic fit with theorganizations long-term goals. In selecting aprogram to pursue, this is one area to

    consider. In this example, Program B fullysupports four of the five goals.

    The Standard for Program Management, p.23

    Program Management for Improved Business

    Results, p. 286

    Question:

    [QID: 6564] You have staffed your program

    team with a variety of in-house staffmembers, selected consultants, and severalnew full-time employees. It is now time to

    A) Prepare your resource management

    plan

    B) Prepare your team development plan

    C) Update your program resource plan

    D) Update your staffing management plan

    Explanation:

    The output of the Manage ProgramResources process is the updates to the

    program resource plan. Changes in theassignment of program staff are reflected in

    this update.

    The Standard for Program Management, p.

    93

  • 8/6/2019 Practice Test 1 Results

    27/75

    15/03/11 1:44 PMprint.html

    Page 27 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    Question:

    [QID: 6544] You are the legacy systemconversion program manager in yourcompany. You need to update the companys

    business development/sales tracking system,which was developed in C++. Your

    governance board recognizes the importanceof including this project in your program and

    asks you to prepare a cost estimate for thisnew project. The board approves your

    estimate. As part of the programs Monitorand Control Program Financials process,

    you

    A) Update the program budget baseline

    B) Prepare a resource management plan

    C) Identify staffing needs

    D) Revise the cost management plan

    Explanation:

    As an output of the Monitor and ControlProgram Financials process, updates to the

    program budget baseline are needed whenthere are significant cost impacts. These

    updates are communicated to programstakeholders as appropriate.

    The Standard for Program Management, p.

    226

    Question:[QID: 6532] Transition planning is the keyto benefits sustainment in program

    management. As a program manager, yourecognize the importance of ensuring that

    component transition requests are prepared.This preparation is done during the

    A) Transition Planning process

    B) Develop Program Management Planprocess

    C) Direct and Manage Program Executionprocess

    D) Transition Execution process

    Explanation:

    The Direct and Manage Program Execution

    process is concerned with managing theexecution of the program management plan.

    It receives transition requests and sendsthem to the governance board for gate

    transition approval.

    The Standard for Program Management, pp.8690

    Question:[QID: 6466] As executive sponsor of a majorprogram to restore coral reefs off the coast

    of the Maldives, you have observed conflictbetween the program manager and herproject managers, stakeholders, and peers.

    Although the conflict is manageable, you areconcerned about her long-term future with

    the organization. She is a very bright andtalented individual, and you want to keep

    her in the organization. Therefore, you

    A) Have her go through a 360-degree

  • 8/6/2019 Practice Test 1 Results

    28/75

    15/03/11 1:44 PMprint.html

    Page 28 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    feedback analysis

    B) Assign her a personal coach to uncoverthe causes of conflict

    C) Tell her to take a well-deservedvacation to reduce her stress level

    D) Send her to a training class on conflictmanagement

    Explanation:

    A 360-degree feedback analysis is anexcellent mechanism to look broadly at a

    persons management, leadership, andinterpersonal skills. It can provide anexcellent foundation for future development

    as well as providing key insights by thepeople that work with her on a daily basis.

    Program Management Professional (PgMP)

    Examination Specification, p. 34

    Question:

    [QID: 6434] You have been appointed

    program manager for Program XYZ. Youhave assembled your team and have begun

    work on your benefits realization plan. Theperson who wrote the plan delivered it to

    you. After you read it, you told the teammember that the plan was missing a key

    component. It did not describe

    A) An assessment of the value andorganizational impact of the program

    B) A method to identify interdependenciesof benefits within program components

    C) How the potential impact of anyplanned program change affects the benefits

    outcome

    D) A way to link the outputs to the

    planned program outcomes

    Explanation:

    There are a number of key components inthe benefits realization plan, which is

    prepared in the Define Program Goals andObjectives process and maintained

    throughout the program. Two keycomponents are to ensure that the program

    is managed in a way that satisfies the use of

    the programs outputs and to link theoutputs to an outcome of the program. Eachbenefit should be specific, measurable,

    actual, realistic, and time-based (SMART).

    The Standard for Program Management, p.109

    Question:[QID: 6518] You have been appointedclosing manager for a program that has been

    under way for eight years. You have metwith the program manager to talk about

    lessons learned. You have also met with thecore program team members and reviewed

    the lessons learned that were documentedby each of the six projects in this program.

    Your next step is to

    A) Index each projects records

    B) Assign metadata tags to the records so

  • 8/6/2019 Practice Test 1 Results

    29/75

    15/03/11 1:44 PMprint.html

    Page 29 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    they can be easily located using a content

    management system

    C) Select the key lessons learned and

    archive themD) Archive all the lessons learned

    Explanation:

    Although only selected lessons learned may

    be incorporated into the programs finalreport, all lessons learned and program-

    related documents should be archived sothat they can be considered and used in

    future programs.

    The Standard for Program Management, pp.30 and 100

    Question:

    [QID: 6536] The Plan and Establish ProgramGovernance process is crucial to program

    success. During this process, the programsgovernance goals are identified, and the

    governance roles and responsibilities aredefined. A key input to this process is the

    A) Benefits realization plan

    B) Scope management plan

    C) Stakeholder analysis chart

    D) Program work breakdown structure(PWBS)

    Explanation:

    Each program is expected to deliver certain

    benefits that may be tangible or intangible.Benefits realization planning is part of the

    Initiate Program process. The benefitsrealization plan, which is an output of the

    Define Program Goals and Objectivesprocess, defines each benefit and explains

    how it is to be realized, maps the benefits tothe programs outcomes, provides a way to

    measure benefits, describes roles andresponsibilities, includes a communications

    plan, and notes transition to ongoingoperations and benefits sustainment. It is a

    key input to the Plan and Establish ProgramGovernance and Plan Program Quality

    processes.

    The Standard for Program Management, pp.3031, 109, and 244

    Question:

    [QID: 6601] You are managing thedevelopment of a series of heating,

    ventilation, and air-conditioning (HVAC)

    products. Each product is being managed asa separate project. Because the products willbe completed at different times, you have a

    product support group. Your team has alsoestablished a configuration managementsystem as a subsystem of the overall project

    management information system (PMIS).Changes have been requested to the product

    that was delivered in Project A. Thesechanges affect the product from Project B,

    which is in production. You focus on

    A) Ensuring that support is properly

  • 8/6/2019 Practice Test 1 Results

    30/75

    15/03/11 1:44 PMprint.html

    Page 30 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    scheduled for Project B

    B) Conducting a thorough audit andextensive testing of future products before

    they are deliveredC) Responding to customer complaints

    regarding the product already delivered fromProject A

    D) Ensuring that a policy of zero defects isimplemented as part of the quality

    assurance and control activities

    Explanation:

    After a product is deployed, any supportmust be scheduled to avoid interruption to

    the customers use of the item to thegreatest extent practicable.

    The Standard for Program Management, p.

    32

    Question:

    [QID: 6473] It is important to develop a

    high-level plan to initiate a program. Such aplan is developed

    A) In the Program Initiation phase

    B) As part of the high-level business casefor the program

    C) By the executive sponsor

    D) In the Pre-Program Preparations phase

    Explanation:

    The high-level plan to initiate the program isdeveloped in the Pre-Program Preparations

    phase. It shows how the program will mapto and deliver strategic objectives, and how

    those objectives align with organizationalgoals.

    The Standard for Program Management, p.23

    Question:

    [QID: 6551] Of the following key initiatives,which would benefit by being managed as a

    program?

    A) Expanding a ski areaB) Setting up a career path for people in

    the project management profession

    C) Upgrading the nations airspace system

    D) Introducing a new project planning tool

    in a large organization

    Explanation:

    An upgrade to the nations airspace system

    would consist of numerous projects as wellas ongoing work. If these projects weremanaged in a coordinated way, then you

    would have better control over them andwould obtain greater benefits.

    The Standard for Program Management, p. 5

    Question:[QID: 6543] As program manager, you areresponsible for facilitating and resolving

    interproject risks, issues, and constraints.

  • 8/6/2019 Practice Test 1 Results

    31/75

    15/03/11 1:44 PMprint.html

    Page 31 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    You want to ensure that your components

    remain aligned with strategic directives andthe business case. This is done as part ofyour work on which one of the following

    program management processes?

    A) Direct and Manage Program Execution

    B) Plan Program Risk Management

    C) Manage Component Interfaces

    D) Identify Program Risk

    Explanation:

    The Direct and Manage Program Execution

    process focuses on managing the executionof the program management plan. Theprimary goal is to deliver the program

    benefits based on the component projects.Additionally, the program manager ensures

    that each project aligns with the programsbusiness case and strategic directives.

    The Standard for Program Management, p.

    86

    Question:

    [QID: 6503] You have been appointed as a

    program manager in your automotivecompany for the development of next-

    generation vehicles for the model year 2020.You prepare a high-level program plan that

    includes all of the following EXCEPT

    A) Stimuli that triggered the program

    B) Alignment of objectives with theorganization

    C) Program objectives

    D) The programs end state or vision

    Explanation:

    The vision is part of the charter preparedduring the Program Initiation phase. The

    high-level plan shows the stimuli thattriggered the program, the program

    objectives, and how the objectives align withthe organization.

    The Standard for Program Management, pp.

    2324

    Question:

    [QID: 6589] The list of deliverables and the

    success criteria for the program and itsproducts, services, and results must be

    included in the procurement documentationthat is provided to potential suppliers. This

    list is derived from an analysis of the

    A) Program scope statement

    B) Program work breakdown structure

    (PWBS)

    C) Contract WBS

    D) Project work breakdown structure(WBS)

    Explanation:

    The program scope statement is the basis

    for future program decisions, and it definesand articulates the scope of the program. It

    also contains a list of the programs

  • 8/6/2019 Practice Test 1 Results

    32/75

    15/03/11 1:44 PMprint.html

    Page 32 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    deliverables and success criteria; these

    factors require consideration, because theymay need to be included in procurementdocumentation.

    The Standard for Program Management, pp.

    108 and 187

    Question:

    [QID: 6573] Each of the projects in your

    program prepares a project risk

    management plan to describe how riskmanagement is structured. Each projectmanager also prepares risk response plans

    for each of the key identified risks. Asprogram manager, you review the risk

    response plans to

    A) Identify intraproject risks

    B) Determine actions that could affect

    other components

    C) Establish a contingency reserve

    D) Establish triggers for the project risks

    Explanation:

    Program management should support the

    risk activities of the program components.The program components risk response

    plans should be reviewed to assess proposedactions that could affect the program risk

    responses for better or for worse. Thesecomponent plans are an input to the PlanProgram Responses process. This enables

    response mechanisms that could benefitmore than one component to be suggested

    and implemented.

    The Standard for Program Management, p.177

    Question:

    [QID: 6591] You are preparing for a meetingof your programs governance board. On

    your program, you are using earned valuefor monitoring, control, and forecasting. The

    planned value is $30,587, and the earnedvalue is $26,365. You are working on a

    customer-imposed schedule for thecompletion of the program. Looking at the

    schedule variance (SV), you conclude that

    A) The budget at completion is $46,475,

    but the delays are insignificant

    B) The program is behind schedule, andthe tasks on the critical path are affected

    C) The SV is 1.16, and it appears that the

    schedule will be metD) The SV is $4,222, and the program is

    behind schedule

    Explanation:

    Schedule variance (SV) is calculated by

    subtracting the planned value (PV) from theearned value (EV); that is, SV = EV PV. At

    this point, the SV is $4,222. The programis behind schedule; however, without

    additional information, the effect on thecritical path is not known.

  • 8/6/2019 Practice Test 1 Results

    33/75

    15/03/11 1:44 PMprint.html

    Page 33 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    The Standard for Program Management, p.

    133

    PMBOK Guide, p. 182

    Question:

    [QID: 6512] You manage a legacy systemconversion program and have identified a

    number of issues. Many of them involveCOBOL programming, so you have assigned

    them to a COBOL subject matter expert on

    your core team. This person owns all theCOBOL issues, which means that he or she

    A) Has the authority and means to resolveCOBOL issues

    B) Is responsible for all COBOL-relatedproject work

    C) Can modify program scope if needed toresolve issues

    D) Has been appointed so that no COBOLissues will require resolution at a higher level

    Explanation:

    The issue owner should have the authorityand means to resolve and close COBOL

    issues. If an issue cannot be resolved, thenit should be escalated progressively higher

    until resolution is achieved.

    The Standard for Program Management, p.96

    Question:

    [QID: 6554] You are working on a

    manufacturing program and need to takeaction in response to a quality control

    metric. This metric indicated that the

    manufacturing process exceeded establishedparameters. You meet with your programsteering committee and describe the

    situation. Your next step should be to

    A) Issue a change request

    B) Update the Quality Management Plan

    C) Allocate to the program a resource whois a certified Six Sigma Black Belt

    D) Use the governance decision register

    Explanation:

    Decisions of the governance board or

    steering committee must be formallydocumented because these decisions are

    critical feedback used to improve the resultof the components and the program. A

    governance decision register is an output of

    the Provide Governance Oversight process.

    The Standard for Program Management, p.

    262

    Question:

    [QID: 6501] Component projects of theprogram are initiated during the

    A) Initiation phase

    B) Program Setup phase

    C) Planning phase

  • 8/6/2019 Practice Test 1 Results

    34/75

    15/03/11 1:44 PMprint.html

    Page 34 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    D) Delivery of Program Benefits phase

    Explanation:

    Phase four in the program life cycle is the

    Delivery of Program Benefits phase. Itspurpose is to initiate the various component

    projects in the program and coordinatedeliverables to create the incremental

    benefits.

    The Standard for Program Management, p.28

    Question:

    [QID: 6437] As a program is closed, benefitsmanagement focuses on a number of key

    initiatives, including

    A) Ensuring stakeholder agreement on the

    factors contributing to the benefits

    B) Prioritizing the value of each of the

    program components

    C) Ensuring that the benefits delivered arein line with the business case

    D) Forecasting the ongoing value of thebenefits

    Explanation:

    Upon program completion, the benefits

    delivered should always be compared against

    those identified in the business case toensure that all expected benefits weredelivered.

    The Standard for Program Management, p.

    31

    Question:

    [QID: 6541] Commitment of organizationalresources for the initial phases of theprogram is provided

    A) After the program charter is approvedby the stakeholders

    B) When the benefits realization plan is

    issued

    C) When the program manager is

    appointedD) Before the Initiate Program process

    begins

    Explanation:

    The program mandate, which is preparedduring the Pre-Program Preparations phase,

    confirms the commitment of organizationalresources. It also triggers the Program

    Initiation phase.

    The Standard for Program Management, p.23

    Question:

    [QID: 6444] When a program is initiated, agovernance board, program board, or

    steering committee is typically established.Such program governance falls within the

    overall corporate governance of theorganization. The recommended governance

  • 8/6/2019 Practice Test 1 Results

    35/75

    15/03/11 1:44 PMprint.html

    Page 35 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    structure is stated in the

    A) Benefits realization plan

    B) Program charter

    C) Business case

    D) Program management plan

    Explanation:

    The primary output of program initiation isthe program charter. Among other things, it

    includes the recommended governancestructure to manage, control, and support

    the program as well as the governance

    structure for the programs components.

    The Standard for Program Management, p.

    25

    Question:

    [QID: 6590] As program manager, you keep

    all of your stakeholders informed in a timelymanner and you distribute a variety of

    different types of information. One type thatis often overlooked is

    A) Notification of change requests

    B) List of preventive actions

    C) Record of training

    D) Receipt of proposals

    Explanation:During the Distribute Information process,information that is distributed includes

    notification of change requests to theprogram and project teams, and eventually,

    notification of the responses to the changerequests through use of the change request

    log, which contains data on approved,rejected, or modified change requests.

    The Standard for Program Management, p.

    149

    Question:

    [QID: 6457] A key member of your program

    staff has been complaining lately of thecompanys vacation policies. He would like to

    take more time off but has not yet accruedenough time to do so. You are concerned

    that he is going to leave the company, soyou monitor his e-mail, in accordance with

    company policy, to see whether he issending his resume to other companies. The

    act of sending out his resume would becalled a

    A) Risk event

    B) Misuse of the companys e-mail policy

    C) Risk trigger

    D) Violation of the companys code ofethics

    Explanation:

    A risk trigger is a sign that a particular risk

    may occur.

    The Standard for Program Management, p.180

  • 8/6/2019 Practice Test 1 Results

    36/75

    15/03/11 1:44 PMprint.html

    Page 36 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    Dictionary of Project Management Terms, p.

    389

    Question:

    [QID: 6528] You are the program managerfor a six-year program that is in its second

    year. To ensure that the benefits realizationplan is on target, you perform a benefits

    review of the four projects that are underway. Project B is not achieving the desired

    benefits and its deliverables are not being

    completed as planned. When you report thisconcern to the governance board, theexecutive sponsor recommends that Project

    B be terminated. At the program level, you

    A) Conduct a final program review

    B) Prepare a report of lessons learned

    C) Reassign the project manager forProject B

    D) Prepare a transition requestExplanation:

    A termination request is an input to the

    Approve Component Transition process, andit is required if a project is terminated before

    its scheduled completion. A terminationdecision may be the result of a program

    benefits review or a change in the externalenvironment. The transition request is also

    required for normal project completion.

    The Standard for Program Management, p.

    270

    Question:

    [QID: 6567] The Initiate Program process

    produces numerous outputs; the two

    primary outputs are

    A) High-level program plan and benefits

    realization plan

    B) Program manager identification and

    program sponsor identification

    C) Benefits identification analysis and

    benefits realization plan

    D) Program charter and program road

    map

    Explanation:

    The program charter authorizes the program,

    whereas the program road map is achronological representation of the programs

    stated direction. These two outputs are keyinputs to other program processes.

    The Standard for Program Management, p.78

    Question:

    [QID: 6472] You are the program manager

    for a new version of an MP3 player. Theplayers are manufactured by third-partycompanies operating plants in five different

    countries. You have been receiving statisticalprocess control (SPC) charts from each

    company, and there is indication that theprocess is out of control at one of the

  • 8/6/2019 Practice Test 1 Results

    37/75

    15/03/11 1:44 PMprint.html

    Page 37 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    plants. This means that

    A) There are supply chain problemscoming from a lack of raw materials

    B) There are union problems causingdisruption in the manufacturing line

    C) The manufacturer has little control over

    how human resources are being deployed

    D) The process is not in conformance with

    overall quality requirements

    Explanation:

    A statistical process control (SPC) chart

    shows how a process is being executed overtime. A process is deemed out of controlwhen certain measurements exceed

    tolerance levels thus affecting quality. ThePlan Program Quality process includes

    preparation of the program qualitymanagement plan, which sets, among other

    things, quality standards for components.

    The Standard for Program Management, pp.256 and 263

    Question:

    [QID: 6598] As the program managerworking on the development of an advanced

    polymer chemical for raincoats, you are inthe process of assessing the feasibility of

    your program. In reading the latest industryjournal, you discovered that a competitor isalso entering the marketplace. To assess

    your position against that of yourcompetitor, you conduct a

    A) Delphi technique exercise

    B) Brainstorming session

    C) Nominal group technique

    D) SWOT analysis

    Explanation:

    A SWOT (strengths-weaknesses-

    opportunities-threats) analysis providesinformation that is helpful when matching an

    organizations resources and capabilities tothe competitive environment in which it

    operates. It is used in feasibility studies as atool and technique in the Initiate Program

    process.

    Program Management Professional (PgMP)

    Examination Specification, p. 21

    The Standard for Program Management, p.

    77

    Question:

    [QID: 6475] An expert in your company will

    be needed by two of the projects in yourprogram at approximately the same time.Both project managers have included this

    person in their project management plans,resource assignment matrices, and project

    schedules. This is an example of

    A) An issue to be resolved by thegovernance board

    B) An assumption

  • 8/6/2019 Practice Test 1 Results

    38/75

    15/03/11 1:44 PMprint.html

    Page 38 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    C) Critical chain analysis

    D) A constraint

    Explanation:

    An assumption is a common input to mostprogram management processes.

    Assumptions are considered to be true, real,or certain. In this situation, both project

    managers have assumed that this criticalresource will be available as required. The

    program manager must work to resolve thissituation, and the resolution should be noted

    in the program management plan.

    The Standard for Program Management, pp.26 and 38

    Question:

    [QID: 6478] Your program to develop a 4Gphone is being terminated early because

    your competition already has a 4G phonemodel on the market. Your company has

    initiated a program to develop a 6GXi phone,and you hope to be assigned to manage this

    program. At this point, you

    A) Document the current state

    B) Appoint a closeout manager

    C) Immediately disband your team

    D) Archive your records

    Explanation:

    During the Closing processes, it is important

    to demonstrate that the benefits have beendelivered and the scope of work has been

    fulfilled. If the program is terminated early,then the current state should be

    documented.

    The Standard for Program Management, p.66

    Question:

    [QID: 6500] The program management planincludes a number of subsidiary plans, such

    as the

    A) Contracts administration planB) Quality assurance plan

    C) Benefits management plan

    D) Benefits realization plan

    Explanation:

    This set of plans includes the benefitsrealization plan, which is an output of the

    Define Program Goals and Objectives

    process. Benefits realization planning is partof the Planning Process Group.

    The Standard for Program Management, p.79

    Question:

    [QID: 6490] You manage a program to

    develop a new e-commerce program forautomotive parts distributors. Your

    organization has established this program tokeep up with competitors and to increase

  • 8/6/2019 Practice Test 1 Results

    39/75

    15/03/11 1:44 PMprint.html

    Page 39 of 75file:///Users/kritichan/Libcal%20Store/2.0/print.html

    market share, but it has recently acquired a

    competitor that already has a highlyregarded e-commerce program in place. Yournext step is to

    A) Revisit and update your program plans

    B) Meet with each of your projectmanagers to discuss an orderly transition to

    redeploy resources

    C) Meet with your executive sponsor torequest a new assignment

    D) Convene a meeting of your governanceboard to terminate your program

    Explanation:

    Acquisitions and mergers are unplanned

    events. When they occur, they should triggera review of existing program plans to see

    whether updates are required to ensureongoing usefulness.

    The Standard for Program Management, p.

    46

    Question:

    [QID: 6556] A definition and description of

    program funding flows are contained in the

    A) Program financial framework

    B) Program charter

    C) Program financial planD) Program business case

    Explanation:

    The program financial framework is a plan to

    coordinate available funding, including thespecific constraints under which it is

    available and how the money is paid out. Itdefines and describes program funding flows

    in a way that ensures that program fundsare spent as efficiently as possible.

    The Standard for Program Management, p.

    213

    Question:

    [QID: 6451] As a program manager, you

    recognize the importance of stakeholdermanagement. To support your efforts,

    especially with key stakeholders whosedispleasure might hinder the programs

    success, you p