PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019...

27
mag. ERVIN PLANINC SINCRO.GRID project Ljubljana, 19. 9. 2019

Transcript of PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019...

Page 1: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

mag. ERVIN PLANINC

SINCRO.GRID project

Ljubljana, 19. 9. 2019

Page 2: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

1. ELES & Power System

2. Challanges

3. SINCRO.GRID

Page 3: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

ELES

Who we are?

What we do?

1

Page 4: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

ELES – National Transmission System Operater in Slovenia

o Safe and reliable power system operation and power supply

o Development, construction and maintenance of HV grid

o We connect all relevant grid users

Page 5: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

ELES – National Transmission System Operater in Slovenia

o We ensure safe, reliable and undisturbed transmission of

electric power in Slovenia and across its borders 24/7

Page 6: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Slovenian Power System

Page 7: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

950 MW

2860 MW

680 MW

1488 MW

950 MW

2860 MW

1500 MW

4716 MW

1500 MW

4716 MW

800 MW

1488 MW

NTC values in 2018

Thermal capacity of transmission

International connections

Page 8: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...
Page 9: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

frequency

Transmission

capacity

voltage

Power System operation

System services

Page 10: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Challanges2

Page 11: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Power System flexibility

Generation = Load (in every moment!)

Electricity cannot be stored (expensive)

RES = unstable, irregular source

Page 12: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Increase of RES in EU

Market impact

Vir: Eurostat

Page 13: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

UnstableRES generation

Electricity Price

[€/MWh]

[€/MWh]

Electricity [MW]

MC1

consumption

hydro

nuclear lignite

coal

gas

MC2

Unprofitable operation ofconventional units

Freq

. flu

ctu

atio

n

Larger Frequencydeviations

Lack of system services

Page 14: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Power system yesterday

Power system

tomorrow

Page 15: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

SINCRO.GRID

project3

Page 16: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...
Page 17: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Timeline and main steps of the SINCRO.GRID project

Submission of PCI application for projects with smart grid dimension

The project was successfully applied for the 2nd list of PCI projects in 2015

Submission of ConnectingEurope Facility (CEF) application

EU Member States agreed on the Commission's proposal to cofinance

€40,5 million

Signed a grant agreement

Feb, 2015

Nov, 2015

Nov, 2016

Feb, 2017

May, 2017

Implementation of the projects

2017-2020

System testing and optimization of all systems

2021

Page 18: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

DecentralizacijaDecentralizacijaGraf, ki prikazuje naraščanje deleža OVE na ravni EU – ?

Solved issues of voltage profiles

Provide more ancillary services -

frequency control

Increasing transmissionlines capacities

Benefits of SINCRO.GRID

Technological innovation with replication potential

Page 19: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Reactive power

flexibility

Increase of Transmission lines

capacitiesActive power

flexibility

II IIII

Elimination of limitation during transition phase in the energy sector

3 main issues

Page 20: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

SINCRO.GRID project scheme

Page 21: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Energy Storage System – new technologies

Large field of operation

Multifunctionality!

RES support

• Generation stability

• Increase of cost efficiency

Energy supply

• Energy time shift

• Peak shaving

• UPS

Power Systemoperation

• Voltage regulation

• Inertia

• Frequency control

• Black start

• Investment deferal

Page 22: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Demand shift Peak ShavingVoltage

regulationCongestion

management

RES Generation

support

Frequencyregulation

Power quality

Battery Energy Storage Systems (BESS)

There is no BEST TECHNOLOGY but BEST SOLUTION for the selected function

Page 23: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Battery cellBattery module

Battery rack

BESS

BESS

Page 24: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

BESS TSS Okroglo in Pekre

5 M

W

Page 25: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

BESS

o 2 x 5 MW/25 MWh @ 110 kV level

o Supplier TESLA MOTORS Netherlands

o Product MEGAPACK

o Start of installation in June 2020

o Start of operation in November 2020

Page 26: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Advancedsupervision

system

Power system

state

BESS output

BESS

state

Sincro.Grid BESS

Page 27: PPT PREDLOGA ELES 2018 · PPT PREDLOGA ELES 2018 Author: Tomaž Kužner Created Date: 10/16/2019 11:59:47 AM ...

Thank you for your

attention

[email protected]

www.eles.si

www.sincrogrid.eu