ppquest

download ppquest

of 19

Transcript of ppquest

  • 8/3/2019 ppquest

    1/19

    Production Planning Questionnaire

    Production Planning Questionnaire

    InstructionsThis questionnaire is an online tool that you can use to collect information about your business that will

    then be used for tailoring the R/3 System to your business needs. You will need Microsoft Word for

    Windows to work with this document. Enter your answers in the fields after the questions, using the TAB

    key to move from field to field. You may save, and later change, your answers in this questionnaire just asyou can with any other Word document. This document can be password-protected to allow entrance of

    information only in the answer fields.

    1 Enterprise Structure

    1.1 Plants

    A plant is an organizational unit that representsa production facility, warehouse, sale office, or

    distribution center. In addition, MRP is

    executed separately for each plant.

    1.1.1List the different type of plants you will need,and briefly describe why each should be aseparate plant:

    2.1 Basic Data

    2.1.1Do you use engineering change managementfor your BOMs?

    Yes No

    2.1.2What application areas are your BOMs linkedto (for example, materials management, MRP,

    costing, etc.)?

    2.1.3Do you plan to use the default setting by SAPfor your BOMs validity or effectivity dates?

    Yes No

    If no, define your validity settings for your

    BOMs.

    2.1.4Do you maintain your BOMs using a CADsystem?

    Yes No

    If yes, explain.

    1997 SAP Technology, Inc. 1

  • 8/3/2019 ppquest

    2/19

    Production Planning Questionnaire

    2.1.5Select the BOM types you maintain in yourorganization with associated units of measure.(i.e., pieces, each, die, etc.)

    Material BOM

    Equipment BOM

    Functional location BOM

    Document structure

    Sales Order BOM

    2.1.6BOM usage

    Please select in what area(s) your BOMs willbe maintained.

    Production

    Engineering

    Universal

    Plant maintenance

    Sales and Distribution

    Costing

    2.1.7Define material provisionindicators

    Do your BOMs include material that is

    provided by the customer?

    Yes No

    2.1.8Define explosion types

    Select which BOM explosion type(s) your

    company uses.

    Phantom assembly off: you control how an

    assembly with the Phantom assembly is exploded.

    Phantom in planning: no dependent requirements

    are produced for materials, and the materials are not

    planned.

    Collective order off: used to control how assemblycollective orders are exploded. (A collective order is

    a structure of planned or production orders linked

    over several manufacturing levels.)

    Long term planning off: allows you to simulate

    materials planning, in parallel to operational

    materials planning, across all low-level codes. Thismeans that you can use the current bills of material to

    determine the effects of a planned production

    program on the material requirements and thecapacity load.

    Individual/collective requirements:planning for

    dependent requirements. This controls whetherindividual or collective customer requirements

    planning is allowed for dependent requirements.

    1997 SAP Technology, Inc. 2

  • 8/3/2019 ppquest

    3/19

    Production Planning Questionnaire

    2.1.9Will you be transforming BOM data from anexisting system into the SAP system?

    Yes No

    If yes, indicate the number of BOMs.

    2.1.10 Are there several alternative BOMs forone material (different production processes or

    proportions of quantities), or is this situationplanned for the future?

    2.1.11 Are there BOM items that are not keptin stock, but are externally produced for orders?

    Yes No

    2.1.12 What are your requirements foradministering BOMs (copy functions, mass

    changes, and so on)?

    2.2 Work Center

    2.2.1 If you are using Work Centers, select whatbusiness function(s) apply at your organization.

    Costing

    Scheduling

    Capacity Planning

    Printing Shop Floor Paper

    Shop Floor Control

    Confirmations

    2.2.2Will you integrate Work centers with theHuman Resources sytem?

    Yes No

    If yes, briefly describe the type of data that will

    be used (e.g., required skills).

    2.2.3 List the type(s) of data that are maintained atyour work centers (i.e., costing or scheduling)

    2.2.4Work centers can be categorized according totheir relevant use, for example, by maintenanceor inspection. Indicate how your work centers

    are categorized and give the number of work

    centers for each category.

    2.2.5List the type(s) of parameters you use for yourvarious work center(s). (e.g., WC1=setup,machine & labor, WC2=labor only)

    2.2.6What are the name(s) of the person or group ofpeople responsible for maintaining the data in

    your work center(s)?

    1997 SAP Technology, Inc. 3

  • 8/3/2019 ppquest

    4/19

    Production Planning Questionnaire

    2.2.7 If you are in a Kanban/JIT environment, list thenumber of supply areas you have, including a

    brief description. (A supply area is used for

    material replenishment and is situated on the

    shop floor.)

    2.2.8Select what default value(s) you plan tomaintain for your work center(s). (Defaultvalues help to simplify the maintenance of

    work centers.)

    Basic Data (General data)

    Default operation

    Scheduling

    Capacity data

    2.2.9Control keys allow you to determine thebusiness functions you want to carry out with

    an operation and how the operation is to be

    processed. Which business function(s) will be

    processed at your operations?

    Scheduling

    Capacity planning

    Costing

    External processing

    Completion confirmation (whether the

    operation is confirmed)

    Printing of time tickets

    2.2.10 If you are using the HR module inSAP or if you are not planning to maintain

    wages or salaries of your employees, skip this

    question.

    The wage and salaries of employees can be

    calculated based the wage type (e.g., hourly,salary and bonus) What wage type(s) do you

    maintain at your company?

    2.2.11 In the SAP system, performanceefficiency rates are used in costing and in

    capacity planning. What are the expected

    efficiency rates that typically occur at several

    work centers in your company? (e.g., 90, 100,

    or 110%)

    2.2.12 Define capacitycategories

    What capacity categories are maintained atyour work center(s)? (e.g., machine, labor,

    setup crew, emissions)

    2.2.13 Determine capacityplanner

    List the name(s) of people or groups of people

    responsible for planning capacity at your

    1997 SAP Technology, Inc. 4

  • 8/3/2019 ppquest

    5/19

    Production Planning Questionnaire

    company.

    1997 SAP Technology, Inc. 5

  • 8/3/2019 ppquest

    6/19

    Production Planning Questionnaire

    2.2.14 Define shift sequence

    Using the table below, indicate what shift

    definition(s) are common for several work

    centers at your company.

    Shift Description Start Finish Break Wrk. Hrs.(e.g.)Day1 Normal Day 08:00:00 16:00:00 Noon 8.00

    2.2.15 Indicate the work center formula(s)that you use in the following areas. (e.g.,

    Machine Requirements = Machine* Operation

    Qty. / Base Qty.)

    Setup time

    Machine time

    Labor time

    Setup Requirements

    Machine Requirements

    Labor Requirements

    2.3 Routing

    2.3.1 If you choose not to use the number rangeassignment in SAP, list your number range(s)

    for internal and/or external routings.

    2.3.2Skip this question if you are not using repetitivemanufacturing.

    If you choose not to use the number range

    assignment in SAP, list your number range(s)

    for internal and/or external routings. (Rate

    routings are used in repetitive manufacturing.)

    2.3.3Profiles with default values are proposed when

    you create a new routing. This data can eitherbe saved or overwritten. To assist when

    creating a routing profile, fill in the data.

    Unit of measure

    Status (select one) Created

    Released for Production

    1997 SAP Technology, Inc. 6

  • 8/3/2019 ppquest

    7/19

    Production Planning Questionnaire

    Operation increments (e.g., 10, 20, 30)

    Base quantity

    Currency

    2.3.4Select which material type(s) will be used inyour organization.Finished products: materials that are produced andsold to the customer

    Semi-finished products: materials that can be sold

    to the customer, or used in a higher assembly

    Trading goods: materials that you buy and

    sell without any manufacturing

    Configurable material: the selectable

    items form a BOM that are used to make a

    Finished product in various combinations.(i.e., a car)

    Non-stock material: material that you buy

    and track qty., but in value is not kept.

    Raw material: material you buy to producesomething with

    2.3.5What are the name(s) of people or group ofpeople that are responsible for maintaining your

    routings?

    2.3.6The control key for an operation is used tocarry out business functions and dictate how an

    operation is to be processed by the system.

    What business functions are processed at the

    operation level in your organization? (Selectwhere applicable.)

    Scheduling

    Costing

    Inspection characteristics

    Print operation

    External Processing

    Automatic goods receipt

    Capacity Planning

    Time tickets

    Rework

    Confirmation

    Print Confirmation

    2.3.7Reduction strategies are used to determine howthe opeation lead time can be reduced step by

    step. Do you use reduction strategies in

    manufacturing at your company?

    Yes

    No

    1997 SAP Technology, Inc. 7

  • 8/3/2019 ppquest

    8/19

    Production Planning Questionnaire

    If yes, please explain.

    3 Sales and Operations Planning

    3.1 Master Data

    3.1.1 If currency conversion is required, which typeof exchange rate will be used?

    Average rate

    Buying rate

    Selling Rate

    3.1.2Should capacity information be displayed? Yes

    No

    3.1.2.1 If yes, which type of resources willrequire resource leveling?

    Work Centers

    Materials

    Production Resources and Tools

    Costs

    3.1.3Will SOP data be transferred from any non-SAP systems/sources?

    Yes

    No

    3.1.4Which plant should be used as the planningplant when no other plant is identified?

    3.2 Functions

    3.2.1Will sales quantities be transferred from the R/3Sales Information System (SIS)?

    Yes

    No

    3.2.2Which transfer strategy will be required whentransferring SAP data to Demand Management?

    Direct from the sales plan

    From the sales plan as a proportion of the

    product group of which it is a member

    Direct from the production plan

    From the production plan as a proportion of

    the product group of which it is a member

    From an Information Structure

    1997 SAP Technology, Inc. 8

  • 8/3/2019 ppquest

    9/19

    Production Planning Questionnaire

    3.2.3Application Link Enabling(ALE)

    Will Sales and Operations plans (information

    structures) be distributed to remote systems?

    Yes

    No

    3.2.4Maintain planning types

    Will more than one view of the planning table

    be required?

    Yes

    No

    If Yes, define the following for each user:

    Planning Start Date

    Number of time periods to plan

    3.2.5Where will planning quantities be copied from? Sales Information SystemProfitability Analysis (CO/PA)

    3.2.6Will non-SAP data be copied into the SAPplanning table?

    Yes

    No

    4 Master planning

    4.1 Planning Strategy4.1.1What type(s) of Planning Strategies are used

    your company? (e.g., make-to-stk., make-to-

    order, repetitive, etc.)

    4.1.2What planning time fence duration is requiredfor planned independent requirements?

    4.1.3Will planned independent requirements betransferred from the legacy system?

    Yes

    No

    4.2 MPS4.2.1What individuals or groups of individuals will

    be responsible for the monitoring of material

    availability (MPS)? Identify the materials that

    will be managed by each individual or group.

    4.2.2What is the desired planning time fence forMRP processing? Should out-of-date plannedorders and firm planned orders in future periods

    Yes

    No

    1997 SAP Technology, Inc. 9

  • 8/3/2019 ppquest

    10/19

    Production Planning Questionnaire

    be deleted before each material planning run?

    4.2.3What evaluations (on-line reports) need to beprovided for the analysis of MPS results? How

    should the report be structured?

    5 Material requirements planning

    5.1 Master Data

    5.1.1Define MRP controllers

    What individuals or groups of individuals will

    be responsible for the monitoring of material

    availability (MRP)?

    5.1.2What individuals or groups of individuals will

    be responsible for the processing of missingparts (MRP)?

    5.1.3Will any of the following conditions exist formaterials produced in-house?

    phantom assembly

    production in an alternative plant

    external reservation (withdrawal from an

    alternative plant)

    independent requirements

    5.1.4Will any of the following conditions exist formaterials procured externally?

    consignment

    subcontracting

    stock transport

    5.1.5 In what time bucket is your horizon? (i.e., days,weeks, months)

    5.1.6What is the required duration of the planningtime fence for each plant?

    5.1.7For each plant, what percentage of safety stockshould be available for material planning?

    5.1.8Should stock in transfer and/or blocked stock(material that is not available) be included in

    the net requirements calculation as available

    stock?

    Yes

    No

    5.1.9For each plant, what is the desired maximumnumber of purchase order proposals that should

    be created during the material requirements

    planning run?

    1997 SAP Technology, Inc. 10

  • 8/3/2019 ppquest

    11/19

    Production Planning Questionnaire

    5.1.10 Which lot-sizing procedures will beutilized?

    static lot-sizing

    period lot-sizing

    optimizing lot-sizing

    5.1.11 Will the proposed lot-sizes for anymaterials need to be adjusted to match the

    deliverable/transportable units? For example, amaterial can only be delivered in crates of 10

    pieces.

    Yes

    No

    5.1.12 Should the system continue to utilizethe backward scheduling procedure even when

    a planned start date lies in the past?

    Yes

    No

    5.1.13 What is the maximum number of daysallowed between MRP runs?

    5.1.14 Will R/3 be interfaced to an externalassembly cord system?

    Yes

    No

    5.1.15 Will the hardware system environmentallow the splitting of the MRP planning run

    process among multiple R/3 application

    servers?

    Yes

    No

    6 Production Orders

    6.1 Master data

    6.1.1Define order types

    6.1.1.1 Do you use order settlement (planned vs.actual) for production orders?

    Yes

    No

    6.1.1.2 What type of number assignment do youuse for production orders?

    Internal (assignment automatically by the

    system)

    External (assigned by the user)

    6.1.1.3 Define the length and format of yourproduction order numbering scheme.

    6.1.1.4 If routing selection is required, will it beprocessed automatically or manually?

    1997 SAP Technology, Inc. 11

  • 8/3/2019 ppquest

    12/19

    Production Planning Questionnaire

    6.1.1.5 Will batch determination be required priorto releasing a production order to the shop

    floor?

    Yes

    No

    6.1.1.6 Do you use the same scheduling data fromyour planned orders for your production dates?

    Yes

    No

    6.1.1.7 Do you use external processing in youroperations? If so, would you prefer to use one

    purchase requisition per operation or one

    collective purchase requisition per order?

    6.1.1.8 Indicate below where you would want torecord change status to a document.

    The document records:

    which status changed

    who changed the status

    when the status was changed

    Order Status

    Operation Status

    Material Status

    Production Resources Tool (assigned to an

    operation, e.g., tools, jigs and fixtures,

    inspections, devices and drawings)

    6.1.1.9 Indicate at which point(s) you conductmaterial inspection.

    Goods receipts inspection

    Deliver to customer

    6.1.1.10 Do you document goods movements with

    reference to an order? If so, select whereapplicable.

    Good receipt for a purchase order

    Good receipt for a completed order

    Planned goods issue

    Unplanned goods issue

    6.1.2 If you choose not to use the predefined numberranges in SAP, list your order types and their

    number range(s).

    6.1.3Define number ranges forconfirmations

    If you choose not to use the predefined numberranges in SAP, list your number range(s) foroperation confirmations.

    6.1.4Define number ranges forreservations

    If you choose not to use the predefined number

    ranges in SAP, list your number range(s) for

    component reservations. (Only internal number

    1997 SAP Technology, Inc. 12

  • 8/3/2019 ppquest

    13/19

    Production Planning Questionnaire

    assignment is allowed for reservation number

    within production orders.)

    6.1.5Define number ranges foroperations

    If you choose not to use the predefined numberranges in SAP, list your number range(s) for

    operations.

    6.1.6Define number ranges forcapacity requirements

    If you choose not to use the predefined number

    ranges in SAP, list your number range(s) for

    tracking capacity requirements.

    6.1.7Define control key

    Indicate which business functions you will usein your routing.

    Scheduling

    External processing

    Capacity planning

    Printing shop papers

    Inspection characteristics

    Costing

    Automatic goods receipt

    Processing of confirmations

    6.1.7.1 Are setups used in capacity planning? Yes

    No

    6.1.7.2 Are formulas used for variable size items? Yes

    No

    6.1.8Define (standard) triggerpoint usage

    Trigger points are used to trigger certain

    functions, (i.e., operation release, insertion of

    reference operation sets) when the status of

    operation changes. A trigger point can be

    assigned to an order or routing.

    6.1.9Are you planning to use trigger points?

    Yes

    No

    If yes, please give some examples as to how

    1997 SAP Technology, Inc. 13

  • 8/3/2019 ppquest

    14/19

    Production Planning Questionnaire

    you will use trigger points.

    6.2 Operations

    6.2.1Select which criteria you use for routingselecting.

    When creating a routing using the copy

    function

    At the time of order creation (prior to

    release)

    During scheduling

    During costing

    6.2.2Select automatically

    Will you use automatic routing selection for

    alternative routing?

    Yes

    No

    6.2.3 If yes, what type of criteria will you use?

    6.2.4Availability check

    How do you process availability checks for

    material/components when creating production

    orders? Select where applicable.

    All material must be available prior to

    creating/releasing order

    Create/release with shortages (not all

    material available)

    User decides on whether to release

    Check material in groups (grouping materialbased on material and/or MRP type)

    Material quantities confirmed in the

    availability check are to be locked

    Check ATP quantities

    Check accumulated ATP quantities

    Take into account replenishment lead time

    Take into account stock categories

    Take into account purchase requisitions-

    MRP

    Take into account purchase orders-MRP

    Take into account planned orders-MRP

    6.2.5What process do you use for checkingbackorders?

    6.2.6Are capacity requirements (work orders, Yes

    1997 SAP Technology, Inc. 14

  • 8/3/2019 ppquest

    15/19

    Production Planning Questionnaire

    planned orders) taken into consideration when

    scheduling?

    No

    6.2.7Specify scheduling type

    When scheduling production orders, what

    criteria does your organization use? Selectwhere applicable.

    Forwards

    Backwards

    Only capacity requirements

    Current dates (The system schedules

    backwards from the basic date and then

    forward from the current date.)

    6.2.8Define time units

    Do you use time units for scheduling (i.e.,

    second, minute, decade, etc.)?

    Yes

    No

    If yes, list time units.

    6.2.9Define key for performanceefficiency rate

    Do you use performance efficiency rates (actual

    work done by an employee vs. average work

    done)?

    Yes

    No

    6.2.10 Define schedulingmargin key

    Select which type(s) of floats/buffers you use

    when scheduling order(s).

    Float before production: This is the time between

    the order start date and the schedule start date.

    Float after production: This is the time between the

    order finish date and the scheduled finish date.

    Release period: Number of working days in the

    release period of an order.

    6.2.11 Define move timematrix

    Does your organization use move time betweenwork orders?

    Yes

    No

    6.2.12 Define reductionstrategies

    Will you use reduction strategies reduces lead

    time if the basic dates given are not adhered to,or schedule dates lie outside of the basic dates?

    Yes

    No

    If you are currently using reduction strategies,

    what is your process?

    1997 SAP Technology, Inc. 15

  • 8/3/2019 ppquest

    16/19

    Production Planning Questionnaire

    6.2.13 Define confirmation

    parameters

    Confirmations are used for order monitoring.

    They can be performed at the operation and

    sub-operation level. Partial confirmation is the

    confirmation of an order that can still be

    processed.

    Select the area(s) in which your organizationuses confirmation control.

    Check dates

    Logs only warning messages or

    information messages

    Goods movement system to display all

    components assigned to the operation.

    Variances:

    Scrap on a quantity basis

    Excess consumption of activities

    Longer execution time

    6.2.14 What inventory valuation does yourorganization use?

    Price control (standard cost) delivered

    quantity is valuated with the standard cost.

    The difference between inventory valuation

    and credit posting to order is posted to the

    cost differences.

    Moving average cost.

    7 Kanban

    7.1 Will any stock points be situated directly at theproduction line or work center(s)?

    Yes

    No

    If yes, how many are there are how and they

    identified/named?

    7.2 ReplenishmentStrategies

    7.2.1Which of the following will be used to controlthe production of Kanban materials?

    Kanbans (cards) and a cost collector

    Planned orders and a cost collector

    Production orders

    7.2.2How will stock transfers need to be carried out? using a stock transfer reservation

    using a direct transfer posting

    1997 SAP Technology, Inc. 16

  • 8/3/2019 ppquest

    17/19

    Production Planning Questionnaire

    7.2.3For each status change, which of the followingshould occur?

    Automatic goods receipt

    Print Kanban card

    8 RepetitiveManufacturing

    8.1 Basic Settings

    8.1.1Define number ranges forrun schedule headers

    If you choose not to use the predefined number

    ranges in SAP, list your number range(s) for

    run schedule headers.

    8.1.2Define number of thenumber ranges for backlogs

    If you choose not to use the predefined number

    ranges in SAP, list your number range(s) forbacklogs.

    8.1.3Define number of numberrange for document log

    If you choose not to use the predefined number

    ranges in SAP, list your number range(s) for

    document logs.

    8.1.4What repetitive manufacturing profile(s) doesyour organization use or will use?

    The data and costs incurred in productionare assigned to the run schedule header andare settled.

    All the costs incurred in production are

    assigned to the cost collector where they are

    settled. (Production orders are not required.)

    8.1.5Select how cost collectors are created at yourcompany.

    Automatically, when creating the run

    schedule header

    Manually, in the CO system.

    1997 SAP Technology, Inc. 17

  • 8/3/2019 ppquest

    18/19

    Production Planning Questionnaire

    8.1.6Specify control data forrepetitive manufacturingprofiles.

    Select the repetitive manufacturing profiles

    your organization plans to use.

    Activities are automatically backflushed to

    the cost collector

    Discrepancies in backflushing are corrected

    manually

    The withdrawal of an item with a

    discrepancy is refused

    Master plan is reduced after a goods receipt

    Planned orders are recreated when reversinga backflush

    Reporting points for backflushes

    Goods receipt is automatically posted at the

    last reporting point backflush

    Goods receipt and a goods issue is posted

    when backflushing

    Only post goods receipt

    8.2 Planning

    8.2.1Define planning periodicity

    Select which planning period or buckets your

    organization uses when creating a run schedule

    header. (A run schedule header is an order in

    repetitive manufacturing for the production of

    finished products or semi-finished products that

    are produced on a repetitive basis over a longerperiod).

    Day

    Week

    Month

    Posting period

    8.2.2 If you do not use capacity planning in repetitivemanufacturing, skip this section.

    You have two options for executing capacity

    leveling. Select which option(s) you plan to use

    in your organization.

    via the planning table (spreadsheet format)

    via the graphic table that you access via the

    planning table

    8.2.3How will requirements be distributed?Select one only.

    Continuously (lineraly)

    Discretely to defined points

    1997 SAP Technology, Inc. 18

  • 8/3/2019 ppquest

    19/19

    Production Planning Questionnaire

    8.2.4Define distributionaccording to usage time

    The distribution of orders is based on operating

    time that takes available capacity into account

    and shifts. Do you use operation time todistribute orders?

    Yes

    No

    If yes, what is your process?

    8.2.5When backflushing, what sequence for materialwithdrawal do you or will you use in your

    organization? Indicate using 1 3

    withdrawal of unrestricted stock-use stock

    withdrawal of consignment stock

    withdrawal of pipeline material

    8.2.6Select which movements type you plan to use

    in repetitive manufacturing. (Movements typesare automatically used for backflushing.)

    goods receipts

    goods issue

    scrap

    by-products

    movements referring to individual customer

    orders

    8.3 Cost Object Controlling

    8.3.1Define generation of costlog

    Does your organization log costs in repetitive

    manufacturing when backflushing activities?

    Yes

    No

    8.3.2Select which distribution rule for settlementyou will use.

    full settlement

    settlement by period specifies variancecalculation is done out by period

    8.3.3Select which cost collector your organizationwill use for backflushing in repetitive

    manufacturing.

    cost collector is created automatically by the

    system, no search is required

    use search strategy to define which cost

    collector is used. If selected, choose one

    option below:

    on material is settled to one cost

    collector

    one material and one production version

    are settled using several cost collectors

    1997 SAP T h l I 19