ESA,Beirut-October 26, 2011 PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP

Transcript of PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec,...

Page 1: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

PPP contracts in water sectorJoubrane Ouechec, Suez Environnement

IPEMED-BADER, Seminar PPP

Page 2: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� SUMMARY

� Chapter 1 Introduction to Suez Environnement, 3’

� Chapter 2 Business Models (PPP), 8’

� Chapter 3 As Samra Case,14’

� Q/A

IPEMED-BADER, Seminar PPP

Page 3: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

�A GLOBAL LEADER IN WATER & WASTE

6%

AMERIQUE DU

SUD3%

AFRIQUE & Moyen

d‘Orient

EUROPE 79

%ASIE 3%

OCEANIE 3%

NORTH AMERICA6%

AMERICASOUTH

2% AFRICA &MIDDLE

-

EAST7%

EUROPE 78% ASIA

4%

OCEANIA 3%

WATER WASTE

POSITIONED ON THE FULL VALUE CHAINS OF WATER AND WASTEPOSITIONED ON THE FULL VALUE CHAINS OF WATER AND WASTE

- 91 million people supplied, 1,888 drinking water production facilities

- 61 million people served, 1,643 wastewater treatment sites

- 1 billion inhabitants served by 10,000 Degrémontfacilities

- 91 million people supplied, 1,888 drinking water production facilities

- 61 million people served, 1,643 wastewater treatment sites

- 1 billion inhabitants served by 10,000 Degrémontfacilities

- 51 million people benefiting from waste collection

- Over 464,985 industrial and commercial clients

- 41 million tonnes of waste treated

- 49 incinerators worldwide (46 of which provide energy recovery)

- 51 million people benefiting from waste collection

- Over 464,985 industrial and commercial clients

- 41 million tonnes of waste treated

- 49 incinerators worldwide (46 of which provide energy recovery)% of 2009

revenues

Page 4: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

�BALANCED POSITIONING(2010)

* Western part of Europe(1) Rest of the World (2) Including activities in France, Italy, Germany, Safège, OIS(3) Central Europe, Mediterranean and Middle East

27%

42%

31%FY 2010revenue:€13,9m

Waste Europe

WaterEurope

International

North AmericaDegrémont

41%17%

21%22%

Asia-Pacific

CEMME(3)

Lyonnaise des Eaux(2)AGBAR

56%

19%

25%

UK/Scandinavia

France

Benelux/Germany

Water Europe*: €4,248m

Waste Europe*: €5,863m

International: €3,743m

45% 55%45% 55%

Page 5: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� THE WATER VALUE CHAIN

Storage and distribution

Production of drinking water

Management of water resource

DRINKING WATER

WASTEWATER SERVICES

Consumption and customer

service

Wastewater collection and

treatment

Water treated return to

environment

Sludge treatment

Sludge recovery

Compost

Energy

Storage and distribution

Production of drinking water

Management of water resource

DRINKING WATER

WASTEWATER SERVICES

Consumption and customer

service

Wastewater collection and

treatment

Water treated return to

environment

Sludge treatment

Sludge recovery

Compost

Energy

Energy consumption may be overused

Losses throughout the network can be a financial burden

Consumption may be underestimated and collection ratio low

Treatment process is often not optimized

Sludge may be disposed of without reuse

Page 6: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� SUMMARY

� Chapter 1 Introduction to Suez Environnement, 3’

� Chapter 2 Business Models (PPP), 8’

� Chapter 3 As Samra Case,14’

� Q/A

Page 7: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

�PUBLIC PRIVATE PARTNERSHIPS

�A public-private partnership is an alliance that combines the business efficiency of a private operator and the government’s mission of public service.

�Tailor-made partnership: the scope of work is defined by the public authority with the support of the private operator.

�The partnership builds up through mutual trust between the public authority and a private operator to jointly offer solutions.

Page 8: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� Key success factors for PPPs:Win-win situations

Consumers

Private operatorClient(public authority responsible for the

service)

Consumers

Private operatorClient(public authority responsible for the

service)

The Contractmust guarantee benefits for each stakeholders

Employees

KSF 1

Page 9: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� Key success factors for PPPs:Balance the constraints in order to set the contract’s objectives

6 key areas

Political and social constraints

Financial constraints

Technical constraints

(objective of the contract)

Political and social constraints

Financial constraints

Technical constraints

(objective of the contract)

The Contract aims to find a balance

between constraints

KSF 2

KSF2: Ensure the feasibility of each and the coherence between the three

Page 10: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� Key success factors for PPPs:Clearly allocate roles

Separates the roles of Public Authority from Private Operator

Public authority who:Generally owns the assets

Fix the rules

Set the tariffs

Controls the Operator performance

Private Operator who:Focuses on economic efficiency and performance of service

Owns state-of-the-art technologies

Manages Human Resources and skills

Optimises OPEX & CAPEX

Contributes to know-how

Public authority who:Generally owns the assets

Fix the rules

Set the tariffs

Controls the Operator performance

Public authority who:Generally owns the assets

Fix the rules

Set the tariffs

Controls the Operator performance

Private Operator who:Focuses on economic efficiency and performance of service

Owns state-of-the-art technologies

Manages Human Resources and skills

Optimises OPEX & CAPEX

Contributes to know-how

Private Operator who:Focuses on economic efficiency and performance of service

Owns state-of-the-art technologies

Manages Human Resources and skills

Optimises OPEX & CAPEX

Contributes to know-how

Page 11: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� Key success factors for PPPs:Comply with duties

� The public authority must have:

� A strategy

� A w illingness for permanent dialogue

� An interest in involving a specialised third party (transparency and arbitration)

� The private operator must accept to be:

� Measured objectively

� Controlled contractually

� Regulated transparently

Stakeholders dialogueStakeholders dialogueStakeholders dialogueStakeholders dialogue

Page 12: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� The contract is a tool that sustains the process

�The choice of contract depends on:

�The performance of the utility and the objectives t o be achieved

�The client’s expectations in terms of delegating pa rt of the public service

�The social and political constraints: regulation, i nstitutional framework, etc.

�The contract embeds:

-Role allocation

-Targets

-Control mechanisms

-Remuneration schemes

Page 13: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

�PPP schemes

Consulting Engineering

Management Contract

O & M Contract

Affermage / Lease Contract

Build Operate Transfer

ConcessionFully Privately

Owned

Consulting Public and Private Partnership Privatisation

Time in Years

Operating JV Public-Private

Design Build (Oparate)

Contractor’s risk / revenue&Private Sector Involvement

2 3 5 10 20 30 For ever

Infrastructure

Full Utility

Partial Utility =>

<= Public Utility

<= Support

Technical Assistance

Page 14: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

�Key Considerations

� Technical Assistance contracts are a cost-effective approach to meet specific technical needs, however their benefits are limited

� Management contracts are a first step of PPP where the main objective is to rapidly enhance a utility's technical capacity and its efficiency in performing specific tasks. A prepare for greater private involvement.

� Operation and Maintenance contracts are applicable for larger private involvement in utility services and when the revenues from the Bills are not covering the operating expenses.

� Affermage/Leases are recommended when a Utility is generating enough revenues thru the Bills of W and WW to pay for the Operations and the Operating CAPEX. Not for the Investments.

� Concessions are recommended when a Utility is generating enough revenues thru the Bills of W and WW to pay for the Operations and the Investments. They pass full responsibility for operations and investment to the private sector

� Build-operate-transfer (BOT) or variations resemble concessions for providing bulk services but are normally used for greenfield projects, such as a water or wastewater treatment plant

Page 15: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� SUMMARY

� Chapter 1 Introduction to Suez Environnement, 3’

� Chapter 2 Business Models (PPP), 08’

� Chapter 3 As Samra BOT Case,14’

� Q/A

Page 16: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Jordan’s First BOT Experience in Constructing the Biggest Wastewater Treatment Plant

Page 17: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Project Description

• 25 year Build, Operate and Transfer (BOT) contract for a Wastewater Treatment Plant to be built at As Samra

• Operate, Maintain and Transfer the Siphons from Ain GhazalPre-treatment Plant to the Samra Plant, and pumping stations at Hashimiyya and West Zarqa.

• Treat Wastewater generated in Greater Amman area including Russeifa, Zarqa and Hashimiyya: population 2.3 million

Page 18: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Page 19: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Key Terms of the Project Agreement• Executed with the Government of Jordan represented by the Ministry of

Water & Irrigation

• MWI Contribution (USAID grant) payable on Completio n of Sections

• Treatment Charges payable when first (of four) Treatment Lines brought into

Operation after 30 months

• Treatment Charges (Fixed and Variable) structured to match Project

Company’s Liabilities

• Payment Assurance Scheme to address any revenue shortfall

Page 20: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Financing Plan & Sponsors’ UndertakingsFinancing Plan:

• MWI contribution 50% $ 92 M (GOJ $ 14 M + USAID $ 78 M)

• SPC : Minimum 20% of project costs in equity & 30% of project costs in commercial financing.

Sponsors’ Undertaking

• Equity Investment ~11%

• Equity Guarantee ~ 9%

• Commercial Loan (11 Jordanian Banks & Financial Institutions)

• Performance Guarantee $ 15 Million

• Post completion the Commercial loan guaranteed by the Gov.

• Mother Companies Repayment Guarantee to USAID

Page 21: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� Fixed Treatment ChargePayable monthly, made up of five parts to reflect:

– Repayment of Principal of Project Loan– Interest on Project Term Loan – Principal and Interest on Shareholder Loans, Dividends (linked to

USD/JD exchange rate) – Fixed Renewal cost (indexed)– Fixed Operating Costs (indexed on local inflation)

� Variable Treatment ChargePayable monthly, and made up of two parts to reflect:

– Additional Volume of Influent (above 160,000 m3/day)– Additional Pollution of Influent (for BOD 5 above 0.55kg/m3)

Project Company Revenues

Page 22: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Treatment Charges: Structure

Fixed Portion:= Fix (Cap) +II. Fix I (Cap)+ IC. Fix F (Cap)+ IL. Fix (Op) +IR. ICFixR(Op)� Fix (Cap) : Repayment of Senior Debt� I I. Fix I (Cap) : Payment of Senior Debt Interests� IC. Fix F (Cap) : Remuneration of Sponsors Investment � IR. Fix R (Op) : Payment of Fixed Renewal Expenditures� IL. Fix (Op) : Payment of Fixed Operation Expenditures

Variable Portion:=IL .{(A.(Vp-160))+B[( Xp.(Vp-160))+160.( Xp-0.55)]}� IL.A.(Vp-160) : Payment of Variable OPEX (Flow)� IL.B.( Xp.(Vp-160)+160.( Xp-0.55)) : Payment of Variable OPEX (Load)I I= Interest rate indexIC=Currency Exchange rate index JD/USDIR=Renewal Index – Construction & Machinery indexIL=(50% X ALm/A0) + (40% X BLm/B0) + (10% X CLm / C0) A- Labour Index B- Producer price index C- Electricity Index

Page 23: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Base Case Operating Cash-flow

0

2

4

6

8

10

12

14

16

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Periods: Annual from January 2006

Flo

w -

JO

D m

illio

ns -

No

min

al

O&M fee Project Management Costs Principal Tranche Debt Service Project Sponsor Loan

Tax Dividends Revenues

Page 24: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Simplified Contractual Framework

Fixed Price EPC Contract

Payment Assurance Scheme

EPC Contractor

50% Infilco Degrémont Inc50% Morganti, CCC

GOJ/MOF

Project Company20% Suez Environment

30% Infilco Degremont Inc50% Morganti Group

Sponsors GOJ/MWI Lenders

USAID

Project Sponsors Agreement

Project Agreement

Loan Agreement

Direct Agreement

MWI Contribution (USAID)

O&M Contractor51% Degremont Inc

49% CCCGroup

Supervision Agreement Sida grant + Swed. Bank Loan

Sweco In./Engicon

Page 25: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Payment Assurance Scheme-Reserve Account Agreement

Reserve Account JD 4 million(Real Value)

(Jordan Kuwait Bank)Reserve account agreement

Project Company

MWI

1) Default in paying TC

2) Notification

3) Instruction to pay ( 5BD after Notification to MWI )

4) Payment of Treatment Charge within 2BD

5) Notification of payment

Page 26: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Payment Assurance Scheme-MoF Guarantee Agreement

Project Company

MWI

1) Failure to pay TC or TP

2) Notification

Ministry of Finance(Guarantee Agreement )

Reserve Account

4) Credit or cause CBJ to credit Payable Treatment Charge (at least the Fixed Charge within 5BD)

3) Written Demand (5BD after

notification to MWI)

5) Pay or cause CBJ to pay Payable TerminationPayment ( at least the Outstanding Debt within 5BD )

In case of termination

Page 27: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Risk Sharing/SPC’s Exposure

1. During Construction.

• Equity Investments up to JD 22Millions

• No profit for acceleration of Works

• Liquidated damages for completion delay

• Mother Companies guarantee for MWI contribution

• Performance guarantee

• Insurance ~ value of MWI Properties

2. During Operation

• Insurance ~ value of MWI Properties

• Performance Guarantee

• Liquidated damages for violating standards & no payment for treatment

Page 28: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Make sure that:• Government/Owner is fully committed to project. • Enabling Legislation is in place (WAJ Law, Investment Promotion Law)• Well prepared documentation : Feasibility Study and EIA, Pre-qualification,

Invitation to Tender, Draft Agreements• Transparent and comprehensible evaluation procedure• Limited number of strong consortia be pre-qualified (5 max.)• Timetable is realistic and deadlines are achieved • Support at high levels, quick decision making and flexibility• Government is perceived to be able to meet its long term commitments by

providing securities• For maximum leverage Government should contribute as little as necessary say

30-50% of total Project Costs • To make the project affordable to both Government and other stakeholders• To set enough reasonable tariffs to attract bidders,

Valuable Rules/Lessons Learnt

Page 29: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Project that Makes Many Firsts

• The first BOT Project in Jordan

• The first electricity Self-sufficient WWTP

• The first mix financed project (Government, Donors

“USAID”, Sponsors and Lenders)

• First Project financed by Jordanian Banks (under PPP)

• First Comprehensive environmental project (full cycle)

conveyance, treatment and reuse of by-products (water,

sludge, hydropower and gas)

Page 30: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Illustration of treatment stages, electricity generation, fodder and fertilizers production at the plant

Page 31: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Effluent qualityParameter Quality

BOD5 6mg/lTotal Suspended Solids 10mg/lTotal Nitrogen 15mg/lNematode Eggs <1 egg/lFaecal Coliforms < 40 MPN/100mlDO > 1 mg/lpH 7-9Fat, Oil ,Grease <8mg/lOdours: (H2S, NH3, Mercaptans e.tc) - < standard

Page 32: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Plant Expansion

40 % increase of water line

80% increase of sludge line

New sludge line

New water line

Tertiarytreatment

AdditionalFrancis turbin on

effluent discharge

Page 33: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

Main Specifications

• Treatment Capacity increase by 100 000 m3/d (+40%)(from 267 to 367.000 m3/d)

• Sludge treatment of Phase 1 increased by 80%

• A negociated Contract (clause 10 « New Investment »)���� on the basis of existing BOT Agreements

• Duration : 25 years from 2012 onwards���� 2035

• MWI Budget :���� EPC: 50% subsidised by MCC���� Acceptable Tariff (80% subsidised by MWI)

Page 34: PPP contracts in water sector - ipemed.coop€¦ · PPP contracts in water sector Joubrane Ouechec, Suez Environnement IPEMED-BADER, Seminar PPP. ESA,Beirut-October 26, 2011 SUMMARY

ESA,Beirut-October 26, 2011

� SUMMARY

� Chapter 1 Introduction to Suez Environnement, 3’

� Chapter 2 Business Models (PPP), 08’

� Chapter 3 As Samra BOT Case,14’

� Q/A